+ All Categories
Home > Documents > Introduction About National Power Transmission … About National Power Transmission Corporation ......

Introduction About National Power Transmission … About National Power Transmission Corporation ......

Date post: 12-Mar-2018
Category:
Upload: vodiep
View: 218 times
Download: 2 times
Share this document with a friend
25
Presented by: Mr. Duong Viet Duc Expert of Investment Management Department National Power T ransmission Corporation (EVNNPT) May, 2013 Introduction About National Power Transmission Corporation And Overview of Investment Processes in Electricity Transmission in Vietnam
Transcript
Page 1: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

Presented by:

Mr. Duong Viet Duc

Expert of Investment Management Department

National Power Transmission Corporation (EVNNPT)

May, 2013

Introduction About National Power Transmission Corporation

And Overview of Investment Processes

in Electricity Transmission in Vietnam

Page 2: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

2

CONTENTS

1. Introduction about EVNNPT and Vietnam Power Transmission Network

2. Overview of Investment Processes in EVNNPT

3. Issues, Challenges

Page 3: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

3

1. Introduction about EVNNPT and Vietnam Power Transmission Network

Page 4: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

4

G

DC

C

IPP G-e

MOIT – Ministry of Industry and Trade

ERAV – Electricity Regulatory Authority of Vietnam

EVN – Electricity of Vietnam

EVNNPT – National Power Transmission Corporation

NLDC – National Load Dispatch Centre (SO/MO)

G – EVN Owned Generation Companies

G-e – Equitized Generation Companies

IPP – Independent Power Producer

DC – Distribution Companies

C – Consumers

State Management Interface

Electrical Interface

Power System Operation Interface

1. Introduction about EVNNPT and Vietnam Power Transmission Network

Page 6: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

1. Introduction about EVNNPT and Vietnam Power Transmission Network

Note:

PTC1(/2/3/4) – Power Transmission Company No. 1 (/2/3/4)

N(/C/S)PPMB - The Northern (/Central/Southern) Power Project Management Board

PTC1 PTC2 PTC3 PTC4 NPPMB CPPMB SPPMB

EVN

Operation & Maintenance (O&M) Construction and Investment (C&I)

6

Page 7: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

1. Introduction about EVNNPT and Vietnam Power Transmission Network

Power Transmission Company No. 2

Power Transmission Company No. 3

Power Transmission Company No. 4

Power Transmission Company No. 1

EVNNPT’s Headquarter

Northern Power Project Management Board

Central Power Project Management Board

Southern Power Project Management Board

7

Ha Noi

Da Nang

Nha Trang

HCM city

Page 8: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

(MVA) 2008 2009 2010 2011 2012

500 kV 7050 8400 11550 13950 15150

220 kV 15477 17977 21039 24476 25351

1. Introduction about EVNNPT and Vietnam Power Transmission Network

8

0

5000

10000

15000

20000

25000

30000

2008 2009 2010 2011 2012

MV

A

Capacity of transformer 500-220kV

in period 2008-2012

500 kV

220 kV

Page 9: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

(Km) 2008 2009 2010 2011 2012

500 kV 3455 3758 4243 4328 4847

220 kV 7987 9400 9870 10645 10858

1. Introduction about EVNNPT and Vietnam Power Transmission Network

9

0

2000

4000

6000

8000

10000

12000

2008 2009 2010 2011 2012

Km

Length of transmission lines 500-220kV

in period 2008-2012

500 kV

220 kV

Page 10: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

(%) 2008 2009 2010 2011 2012

500-220kV 3.14 2.86 3.13 2.56 2.33

1. Introduction about EVNNPT and Vietnam Power Transmission Network

10

0

0.5

1

1.5

2

2.5

3

3.5

2008 2009 2010 2011 2012

%

Losses of 500 - 220kV transmission grid

in period 2008-2012

(not include losses of grid under 220kV)

Page 11: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

1. Introduction about EVNNPT and Vietnam Power Transmission Network

11

(million kWh) 2008 2009 2010 2011 2012

Electrical energy production

(Vietnam power system) 75,955 87,019 100,071 108,729 117,590

Electrical energy transmission

(500-220kV transmission grid) 67,292 76,998 89,573 97,005 104,300

0

20000

40000

60000

80000

100000

120000

140000

2008 2009 2010 2011 2012

mil

lion

kW

h

Electrical energy production &

Electrical energy transmission

in period 2008-2012

Electrical energyproduction

Electrical energytransmission

Page 12: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

12

2. Overview of Investment Processes in EVNNPT

Page 13: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

13

2. Overview of Investment Processes in EVNNPT

Transmission Network Investment Responsibility

Line Substation

Article 21 (MOIT's Circular No.12/2010/TT-BCT of April 15, 2010, detailing the Grid Code): NPT bear the

responsibility to prepare 5 years Investment Plan of Transmission Network

Page 14: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

14

MASTER PLAN

• Master Plan VII prepared by Intitute of Energy – MOIT;

• Master Plan VII issued by Prime Minister (decision No. 1208/QĐ-TTg dated 21th July 2011);

• Master Plan VII included list of investments for power plant and transmission network in the 2011-2020 period with perspective reference to 2030;

5 years Network

development Plan

• 5 Years Network development Plan prepared annual by NPT and issued by MOIT (according to the MOIT's Circular No.12/2010/TT-BCT of April 15, 2010, detailing the Grid Code - Article 21);

• 5 Years Network development Plan included list of investments for transmission network in the 2013-2017 period;

Annual Investment

Plan

• Annual Investment Plan issued by NPT based on 5 Years Network development Plan

2. Overview of Investment Processes in EVNNPT

Investment Processes

(… Next Slide)

Page 15: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

15

2. Overview of Investment Processes in EVNNPT

Investment Processes

(… Previous Slide)

Project Management

Upgrade & Retrofit Projects

(Power Transmission Company

No. 1/2/3/4)

New Projects

(Regionals Power Project

Management Board)

Feasibility Study, Technical Design

(prepare by Consultants and approve by MOIT/EVN/NPT)

Fund Arrangement (from WB, ADB, JICA…)

Procurement (Bidding document prepare by Consultants and approve by NPT)

Contract, Construction, Commissioning,

Energizing and Operation

Page 16: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

16

2. Overview of Current Management of Investment Processes in EVNNPT

Transmission Lines Investment Plan

Lines 2012 2015 2020 2025 2030

500 kV (km) 4847 8152 12691 14925 17649

220 kV (km) 10828 21465 26770 32322 37342

Source: Master Plan VII

0

5000

10000

15000

20000

25000

30000

35000

40000

2011 2015 2020 2025 2030

(km

) Length of transmission lines 500-220kV in period 2012 - 2030

500 kV

220 kV

Page 17: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

17

2. Overview of Current Management of Investment Processes in EVNNPT

Substations Investment Plan

Transformers 2012 2015 2020 2025 2030

500 kV (MVA) 15150 31050 57800 82200 102600

220 kV (MVA) 25351 60339 99402 142177 195427

Source: Master Plan VII

0

50000

100000

150000

200000

250000

2011 2015 2020 2025 2030

(MV

A)

Capacity of transformer 500/220kV in period 2012-2030

500 kV

220 kV

Page 18: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

18

2. Overview of Current Management of Investment Processes in EVNNPT

Substations Investment Plan

2011-2015 2016-2020 2021-2025 Total

New substation 86 82 68 236

Addition Transformer 43 65 75 183

Replacement Transformer 38 48 41 127

Total 167 195 184 546

Source: Master Plan VII

0

10

20

30

40

50

60

70

80

90

100

2011-2015 2016-2020 2021-2025

New substation

Addition Transformer

Replacement Transformer

Page 19: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

19

2. Overview of Investment Processes in EVNNPT

Investment Capital for Transmission Network

Period 2011 – 2020 2021 - 2030

Investment Capital for Transmission Network (billion VND) 210.400 494.000

Investment Capital for Transmission Network (billion USD) 10,02 23,52

Comparison with Total Investment Capital for Power System (%) 33,4% 34,5%

Source: Master Plan VII

Page 20: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

20

3. Issues, Challenges

Page 21: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

21

3. Issues, Challenges

Issues, Challenges

The rising electricity consumption in Vietnam (~13,13% per year of period 1996 - 2011).

0

20000

40000

60000

80000

100000

120000

mil

lio

n k

Wh

"Vietnam power system"

Year 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011

million kWh 16945 19153 21642 23737 27040 31137 36410 41275 46790 53647 60623 69071 76593 86667 99106 107587

(%) 13.03% 13.00% 9.68% 13.91% 15.15% 16.93% 13.36% 13.36% 14.65% 13.00% 13.94% 10.89% 13.15% 14.35% 8.56%

Source: National Load Dispatch Centre

Page 22: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

22

3. Issues, Challenges

Issues, Challenges (continue…)

Transmission pricing is low in comparition with other Transmission Network Owner in the world (~6.58%

in the 2008-2012 period).

(VND/kWh) 2008 2009 2010 2011 2012

Transmission pricing 59,67 67,47 67,83 76,10 83,30

Electricity pricing 870,8 948,5 1058 1242 1304

Transmission/Electricity pricing (%) 6.85% 7.11% 6.41% 6.13% 6.39%

Source: Electricity Regulatory Authority of Vietnam (ERAV)

Current Transmission pricing does not allow to cover future investment.

Page 23: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

23

3. Issues, Challenges

Issues, Challenges (continue…)

Investment of transmission network of period 2006 - 2011 is low in comparison with Master Plan VI

causing overload, rising losses.

Transmission Lines

Projects Length (km)

Finished in

2006-2011

period

In comparison

with Master

Plan VI

Finished in

2006-2011

period

In comparison

with Master

Plan VI

500kV transmission lines 7 72% 1041 79%

220kV transmission lines 76 61% 3067 76%

Substations

Projects Capacity (MVA)

Finished in

2006-2011

period

In comparison

with Master

PlanVI

Finished in

2006-2011

period

In comparison

with Master

Plan VI

500kV substations 11 82% 6750 88%

220kV substations 58 70% 12688 74%

Page 24: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

24

3. Issues, Challenges

Issues, Challenges (continue…)

Shortage of investment capital:

• Total Investment (up to 2020): ~10.000 mil. USD

• Projects to be arranged from ODA and commercial loans: ~5000 mil. USD (as below table)

• Projects without identified source of financing: ~6.000 mil. USD

Donor Ongoing projects

Future proposed projects

(up to 2020)

World Bank 500 mil. USD 500 mil. USD

ADB 590 mil. USD 500 mil. USD

AFD 100 mil. USD

Japanese funds (JICA …) 70 mil. USD 1.850 mil. USD

Others 210 mil. USD

Commercial banks 720 mil. USD 2.000 mil. USD

Total 1.980 mil. USD 5060 mil. USD

NPT meet with difficulties to Land Acquisition and Resettlement for transmission

network projects.

Page 25: Introduction About National Power Transmission … About National Power Transmission Corporation ... (Regionals Power Project Management Board) ...  . Title: Slide 1

NATIONAL POWER TRANSMISSION CORPORATION

Address: #4 Nguyen Khac Nhu Str., Hanoi

Tel.: (84-4) 2220 4444

Fax: (84-4) 2220 4455

Email: [email protected]

Website: www.npt.evn.vn


Recommended