May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program Introduction to Electricity PART 1
Transcript
Page 1: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Introduction to Electricity PART 1

Page 2: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Part 1: Introduction to Electricity

Basic Electricity How Central Power Grids WorkElectricity Generation

STOP FOR TRANSLATIONASK QUESTIONS ANY TIME

Page 3: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Part 1: Electricity Concepts

What is Electricity? Electrons, atoms, negative charge Conductors (example?) Insulators (example?) Electrical energyMagnet

Page 4: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

How does a generator work?

A generator is simply a device that moves a magnet to create a steady flow of electrons.What moves the magnet? Water, or high pressure steam or gas drive turbine blades.

Page 5: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Process of Generation

Page 6: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Electrical Units

Three basic units of measurement:

Voltage (volts)Current (amps)Resistance (ohms)

Page 7: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Water Analogy

Voltage ~ water pressure Current ~ flow rate Resistance ~ pipe size

Page 8: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Key Concept

Let’s say you have a tank of pressurized water connected to a hose that you use to water your vegetable garden. If you increase the pressure in the tank, more water comes out of the hose. Same for electrical systems: increase the voltage: you get a higher current of electrons.OR if you increase the size of the hose more water can flow out. This is like reducing resistance in an electrical system, so you get more current.

Page 9: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Basic Electrical Circuit

All circuits have basic components: a source of electricity (such as a battery), a load (a light or motor) and two wires to carry electricity between the two. Electrons move from the source, through the load, and back to the source. These moving electrons have what we call energy. As they move they can do work.

Page 10: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Key Concept

In an electrical system, increasing either the current (i) or the voltage (V) will increase power output (P).Increase resistance in the wires, voltage drops, current drops > power output drops.

Page 11: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Electrical Circuits

Battery is a simple electrical circuit and source

When you load a battery into an electronic device, the negatively charged electrons will travel to the portion of the battery with a positive charge - much like water flowing down a stream and being forced to turn a water wheel.

Page 12: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

How to calculate electricity consumption

In a lightbulb, electrical energy creates heat in the bulb, and the heat then creates light. How much power in kilowatt-hours does a 100-watt lightbulb use in a year?0.1 kW x 8,760 hours in a year (24 x 365) or 876 kilowatt-hours (kWh)

Page 13: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Household Electricity Consumption

In Thailand, the power outlets in the wall deliver 220 volts each. The frequency or the current is 50 cycles per second. If you know the amps and volts, you can determine the amount of electricity consumed, which is measured in watts. Most appliances are rated in watts. Say your appliance consumes 1,200 watts or 1.2 kilowatts. If you leave the appliance on for one hour the amount of electrical energy consumed is 1.2 kilowatts per hour.

Page 14: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Your Electricity Bill

Power is measured in watts (voltage x current) Consumption is measured in kilowatt-hoursHow much does the power company charge you for electricity?

Page 15: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Electrical Current

Direct Current (DC) Batteries (and solar cells) produce DC. The

positive and negative terminals of a battery are always positive and negative. Current always flows in the same direction between the two terminals.

Page 16: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Electrical Current

Alternating Current (AC)Power from a power plant is AC. The direction of the current reverses or alternates.In Thailand, AC moves at 50 cycles per second. Power from a wall socket is 220 volts, 50-cycle single-phase AC power.

Page 17: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Key Concept

There is an advantage in using less current to make the same amount of power. The resistance in electrical wires consumes power; as current increases, more power consumed. Using a higher voltage to reduce the current makes electrical system more efficient.

Page 18: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Part 2: How Central Power Systems Work

Page 19: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

The Power Plant

This is where electrical power begins. In most cases, the plant consists of a spinning electrical generator. Something – some kind of force or pressure - has to make the generator spin. It might be a turbine in a hydroelectric dam, a large diesel engine, or a gas turbine. Often a steam turbine is used to spin the generator. The steam is created by burning coal, oil or natural gas. Or the steam may be generated in a nuclear station.

Page 20: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Power Plants Generate 3-phase AC Power

Commercial generators of any size generate what is called 3-phase AC power.

There are 4 wires coming out of every power plant – the three phases plus a ground.

Page 21: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Transmission Substation

3-phase power leaves the generator and enters a transmission substation at the power plant. This substation uses large transformers to convert the generator’s voltage (thousands of volts) up to extremely high voltages for long distance transmission on the grid.

Page 22: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Transmission Lines

Typical voltages for long distance transmission range from 155 to 765 kilovolts (1 kilo is 1000)A typical long distance transmission is under 500 kilometres.

Page 23: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Power Substation

The power substation does 2 or 3 things:transformers bring down the voltage to distribution voltages. a busbar splits the distribution power off in multiple directions.circuit breakers and switches to allow the substation to be disconnected from the transmission grid or separate distribution lines.

Page 24: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Electricity Distribution

To use power in homes and temples, power from the transmission grid must be stepped down to the distribution grid. Conversion from transmission voltage to standard line voltage 7.2 kV (kilovolts)

Page 25: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Distribution Line to End Users

The transformer drum steps down electricity from 7.2 kilovolts to 240 volts for normal household electrical service.The 240 volts enters your house through a typical watt-hour meter. The meter allows the power company to charge you (the end user) the cost of putting up all these wires and consuming electricity delivered to your house, office, factory, etc.

Page 26: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Key Concept

AC power has one big advantage: voltage can be changed (up or down) using a device called a transformer. Power companies save money using very high voltages to transmit power over long distances.

Page 27: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Part 3: Electricity Generation

Generation Technologies Steam turbines Gas turbines Wind turbinesHydro/hydraulic turbinesCombined cycle plantsCogenerationMicroturbinesSolar photovoltaics (DC power)

Page 28: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Coal Plants Use Steam Turbines

Page 29: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Nuclear Reactors use steam turbines

Page 30: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Biomass Generation

Page 31: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Biomass Gasifier Power Plant

Page 32: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Combined Cycle Power Plants use gas & steam turbines

Page 33: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Combined Cycle Plants use gas turbine and steam turbine

Page 34: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Solar Photovoltaics

Page 35: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Solar: On-Grid/Off-Grid Technology

Page 36: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Characteristics of Generating Plants

Size, generating capacityEnergy/fuel source Efficiency – conversion to electrical energy Type of use Availability

Page 37: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Generation: Capacity

Depends on size of the hydraulic turbine, the electric generator and the height of the water (head). The volume of water behind the dam affects the maximum amount of energy that may be generated in a given period of time.

Page 38: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Power Plant – Size (Capacity)

Range from a few kilowatts to >1,000 MWMicroturbines are the smallest (see Capstone video for a tour of a microturbine cogeneration facility)

Page 39: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Generation: Efficiency

The efficiency of a generating unit is a measure of the amount of electrical energy produced per unit of energy input. For thermal plants (plants burning fuel), the energy input is fuel and the way efficiency is measured is called the heat rate. The more fuel that has to be burned to produce electricity, the lower the thermal efficiency.

Page 40: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Comparing Plant Efficiency

Newer combined cycle plants have near 50 percent thermal efficiency compared to coal or nuclear plants which can only convert 30 percent of their fuel into electrical energy (the rest is released into the atmosphere as waste heat).

Page 41: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Type of Use: Base, Intermediate, Peak Load

In a central power system, power plants are designed and operated for: base load, intermediate load, and peak load. Base load – usually large units with low operating costs. Usually operated at full capacity during most of the hours they are available. Designed to operate for long periods of time at or near maximum dependable capacity. Low operating costs refer to low cost of the fuel they use.

Page 42: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Intermediate Load

Power plants used to respond to variations in customer demand which occur during the day. Plants designed for change in output levels.

Page 43: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Type of Use: Peak Load

Peak load – power plant is called upon to supply customer demand during peak (= highest) load hours of a given day, month, season or year. Combustion turbines and small hydro units – usually less than 150 MW, capable of achieving full load operation within 10 minutes. They may also be used to replace capacity of other units that have suddenly been taken off the system due to forced outages.

Page 44: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Plant Availability & Dispatch

System operators are concerned about availability of each power plant to supply the grid.System operators dispatch power plants according to their availability (and operating cost).On a day to day and hour to hour basis there must sufficient generation synchronized to the grid to meet all load requirements and respond to short-term variations in customer load, as well as cover for the loss of another generator.

Page 45: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Availability vs Outages

Unavailability of a generating unit due to component failure is called a forced outage.Various components of generating units must be removed from service on a regular basis for preventive maintenance or to replace components before a forced outage results – this is called a planned outage.

Page 46: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Power System Reliability

80 to 90 percent of power disruption in power systems today are caused by transmission grid, not generation.Voltage dips in major transmission line > other transmission lines within the system pick up additional load and may require central utility to redispatch generation >instability, overloading, blackouts.

Page 47: Introduction to Electricity

May 11 – 30, 2009 Mekong Energy & Ecology Network Training Program

Reserve Capacity

Central power systems designed to meet demand plus a reserve capacity, over and above the expected peak load obligation of the power plant (15 to 45 %). Today big questions within the industry: should the amount of installed generating capacity should be a design requirement (set by government) or should be determined by the market; who should pay for transmission? [MORE TOMORROW].

Page 48: Introduction to Electricity