Date post: | 18-Jan-2016 |
Category: |
Documents |
Upload: | lea-mercier |
View: | 141 times |
Download: | 8 times |
Appendix J
Modified ISR System Design
Imagine the result
Raytheon Company
REMEDIAL ACTION PLAN ADDENDUM
FDEP Site # 65215/FDEP Project #66061
St. Petersburg, Florida
Appendix J – Modified ISR System Design
February 25, 2010
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx i
Table of Contents
1. Introduction 1
2. Modified ISR System 1
2.1 Modified ISR System Design Requirements 2
2.1.1 Modified ISR System Design Basis 2
2.1.1.1 Expected Flow Rate 2
2.1.1.2 Influent Calculations 3
2.1.1.3 Discharge Requirements 3
2.1.1.4 Process Flow Diagram and Mass Balance 4
2.1.1.5 Piping and Instrumentation Diagram 4
2.2 AOP Pre-Treatment System Design 4
2.2.1 Design Basis 4
2.2.1.1 Heat Exchanger Feed Tank (T-100) 5
2.2.1.2 Heat Exchanger Feed Pumps (P-100A/B) 6
2.2.1.3 Heat Exchangers (HX-100A/B) 7
2.2.1.4 Influent Equalization Tanks (T-200A/B/C) 8
2.2.1.5 Aeration Tank Feed Pumps (P-200A/B) 9
2.2.1.6 Recirculation Pump (P-200C) 10
2.2.1.7 Aeration Tank (T-300) 11
2.2.1.8 Aeration Blower (B-100) 12
2.2.1.9 Coarse Bubble Diffusers 13
2.2.1.10 Sodium Hydroxide Injection System (T-1000 and P-700) 14
2.2.1.11 Filter Feed Tank (T-400) 15
2.2.1.12 Filter Feed Pumps (P-300A/B) 16
2.2.1.13 Backwash Pump (P-300C) 17
2.2.1.14 Multi-Media Filters (T-500A/B/C) 17
2.2.1.15 Backwash Tank (T-800) 19
2.2.1.16 Decant Pump (P-600) 20
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx ii
Table of Contents
2.2.1.17 Polymer Injection System (T-900, P-500 and SM-200) 20
2.2.1.18 Air Stripper System (T-600A/B) 21
2.2.1.19 Air Stripper Discharge Tank (T-700) 23
2.2.1.20 Air Stripper Discharge Pumps (P-400A/B) 24
2.2.1.21 Tank Vent Blower (B-300) 24
2.2.1.22 Scrubber Blow-Down Water Treatment 25
2.2.1.23 AOP Pre-Treatment System Discharge Line 28
2.3 AOP Treatment System Design 28
2.3.1 Design Basis 28
2.3.1.1 Potential Sodium Sulfite Addition during ISCO Implementation 29
2.3.1.2 Influent Equalization Tank (T-1300) 31
2.3.1.3 Vapor-Phase Granular Activated Carbon (T-2300) 31
2.3.1.4 Advanced Oxidation Process – HiPOxTM System (AOP-100) 32
2.3.1.5 Existing Advanced Oxidation Process – HiPOxTM System (AOP-200) 33
2.3.1.6 Filter Feed Tanks (T-1400 and T-1600) 34
2.3.1.7 Filter Feed Pumps (P-1100A/B) 34
2.3.1.8 Backwash Pump (P-1200) 35
2.3.1.9 Catalytic Media Filters - LayneOxTM (T-1700A/B/C) 36
2.3.1.10 Multi-Media Filters (T-1800A/B) 37
2.3.1.11 Backwash Tank (T-2000) 38
2.3.1.12 Decant Pump (P-1300) 39
2.3.1.13 Polymer Injection System (T-2100, P-1400 and SM-300) 40
2.3.1.14 Liquid-Phase Granular Activated Carbon Adsorption (T-1900A/B/C) 41
2.3.2 Discharge of Treated Water 42
2.4 Modified ISR System General Arrangement 43
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx iii
Table of Contents
2.4.1 Containment Curb 43
2.4.2 Floor Sumps and Pumps 43
2.5 Modified ISR System Support Equipment 43
2.5.1 Air Compressors (A-100 and A-200) 44
2.5.2 Safety Showers 45
2.5.3 Treatment System Control and Interconnections 45
2.5.3.1 Process Piping Interconnections 45
2.5.3.2 Programmable Logic Controllers and Control Interconnections 46
2.5.4 Modified ISR System Piping and Instrumentation 47
2.5.4.1 Treatment System Piping 47
2.5.4.2 Process and Instrumentation 48
2.5.4.3 Modified ISR System Sampling Ports 49
2.5.5 Chemical Handling and Storage 49
2.5.6 Air Emissions 50
2.5.7 Utility Requirements 50
2.5.7.1 Electricity 50
2.5.7.2 Water 50
2.6 Operation and Maintenance Plan 50
2.6.1 Pre-Start-Up Inspection 51
2.6.2 System Start-Up 51
2.6.2.1 Start-Up Operation 51
2.6.2.2 Level of Monitoring 52
2.6.3 System Proof of Performance Testing 53
2.6.3.1 Performance Testing 53
2.6.3.2 Level of Monitoring 53
2.6.4 System Continuous Operation 53
2.6.4.1 Level of Monitoring 54
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx iv
Table of Contents
2.6.4.2 Operational Optimization 54
2.6.5 Maintenance Activities 54
2.6.5.1 Routine Operation and Maintenance 55
2.6.5.2 Monthly Operation and Maintenance 57
2.6.5.3 Scheduled Operation and Maintenance 57
2.7 Best Management Practice Plan 58
2.8 Monitoring Plan 58
2.8.1 Treatment System Process Monitoring 59
2.8.2 Treated Water Discharge Monitoring 60
2.8.3 Air Monitoring 61
2.9 Reporting 61
2.10 Cessation Criteria 63
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx v
Table of Contents
Tab
#1 Modified ISR System – Design Basis
• Figure J-1: Schematic of the Modified ISR System
• Table J-1: AOP Pre-Treatment System Design Basis Summary
• Table J-2: Modified ISR System Design Basis Summary
• Figure J-2: AOP Pre-Treatment System Process Flow Diagram
• Figure J-3: AOP Treatment System Process Flow Diagram
• Table J-3: AOP Pre-Treatment System Mass Balance
• Table J-4: AOP Treatment System Mass Balance
#2 Modified ISR System – Piping & Instrumentation
• Figures J-4 – J-7: AOP Pre-Treatment System Piping and Instrumentation Diagrams (Sheets #1 through #4)
• Figures J-8 – J-10: AOP Treatment System Piping and Instrumentation Diagrams (Sheets #1 through #3)
• Figure J-11: Piping and Instrumentation Diagram Legend Sheet
#3 Modified ISR System – AOP Pre-Treatment System Heat Exchanger
• Heat Exchanger Feed Tank (T-100) Tank Sizing Calculations
• Gould’s Pump Model 3196 STi Product Bulletin
• Heat Exchanger Feed Pumps (P-100A/B) TDH Calculations and Performance Curve
• Heat Exchanger (HX-100A/B) Sizing Calculations and Specification Sheets
#4 Modified ISR System – AOP Pre-Treatment System Influent Equalization and Iron Oxidation
• Influent Equalization Tanks (T-200A/B/C) Specification Sheets and Tank Sizing Calculations
• Aeration Tank Feed Pumps (P-200A/B) TDH Calculations and Performance Curve
• Recirculation Pump (P-200C) TDH Calculations and Performance Curve
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx vi
Table of Contents
• Aeration Tank (T-300) Specification Sheets and Tank Sizing Calculations
• Air Flow Requirements for Iron Oxidation Calculation Sheet
• Aeration Blower (B-100) Sizing Calculations, Specification Sheets and Performance Curve
• Coarse Bubble Diffuser Specification Sheets and Performance Curves
• Sodium Hydroxide Tank (T-1000) Specification Sheet
• Sodium Hydroxide Metering Pump (P-700) Specification Sheets and Performance Curve
• Static Mixer (SM-100) Specification Sheet
#5 Modified ISR System – AOP Pre-Treatment System Filtration and Solids Settling
• Filter Feed Tank (T-400) Specification Sheets and Tank Sizing Calculations
• Filter Feed Pumps (P-300A/B) TDH Calculations and Performance Curve
• Backwash Pump (P-300C) TDH Calculations and Performance Curve
• Multi-Media Filters (T-500A/B/C) Specification Sheets and Sizing Calculation
• Backwash Tank (T-800) Specification Sheets and Tank Sizing Calculations
• Decant Pump (P-600) TDH Calculations, Specification Sheets and Performance Curve
• Polymer Usage Rate Calculation Sheet and MSDS
• Polymer Metering Pump (P-500) Specification Sheets and Performance Data
• Static Mixer (SM-200) Specification Sheets
#6 Modified ISR System – AOP Pre-Treatment System Air Stripping
• Air Stripper VOC Removal Efficiency Model
• Air Stripper (T-600A/B) Specification Sheets
• Air Stripper Blower (B-200A/B) Sizing Calculations, Specification Sheets and Performance Curve
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx vii
Table of Contents
• Air Stripper Discharge Tank (T-700) Specification Sheets and Tank Sizing Calculations
• Air Stripper Discharge Pumps (P-400A/B) TDH Calculations and Performance Curve
#7 Modified ISR System – AOP Pre-Treatment System Tank Venting
• Tank Vent Blower (B-300) Sizing Calculations, Specification Sheets and Performance Curve
#8 Modified ISR System – AOP Pre-Treatment System Scrubber Blow-Down System
• Scrubber Blow-Down Tank (T-1100) Tank Sizing Calculations
• Transfer Pump (P-900) TDH Calculations, Specification Sheets and Performance Curve
• LPGAC Unit Specification Sheet and Vendor Model
#9 Modified ISR System – AOP Treatment System Sodium Sulfite Contactor System
• Sodium Sulfite Contactor Specification Sheets
• Sodium Sulfite Materials Safety Data Sheet (MSDS)
• ARCADIS Permanganate – Sulfite Bench Test Report
#10 Modified ISR System – AOP Treatment System Influent Equalization and Advanced Oxidation Process
• Influent Equalization Tank (T-1300) Specification Sheets and Tank Sizing Calculations
• VPGAC Unit Specification Sheet and Usage Calculations
• AOP-100 HiPOxTM System Specification Sheets
#11 Modified ISR System – AOP Treatment System Filtration and Solids Settling
• Filter Feed Pumps (P-1100A/B) TDH Calculations and Performance Curve
• Backwash Pump (P-1200) TDH Calculations and Performance Curve
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx viii
Table of Contents
• Catalytic Media Filters (T-1700A/B/C) Specification Sheets and Sizing Calculation
• LayneOxTM Media MSDS
• Multi-Media Filters (T-1800A/B) Specification Sheets and Sizing Calculation
• Backwash Tank (T-2000) Specification Sheets and Tank Sizing Calculations
• Decant Pump (P-1300) TDH Calculations, Specification Sheets and Performance Curve
• Polymer Usage Rate Calculation Sheet and MSDS
• Polymer Metering Pump (P-1400) Specification Sheets and Performance Curve
• Static Mixer (SM-300) Specification Sheet
#12 Modified ISR System – AOP Treatment System Granular Activated Carbon
• LPGAC Unit Specification Sheet and Usage Calculations
#13 Modified ISR System – General Arrangement Plans
• Figure J-12: AOP Pre-Treatment System Layout
• Figure J-13: AOP Treatment System Layout
#14 Modified ISR System – Building Containment Curb
• AOP Pre-Treatment System Required Containment Volume Calculations
• AOP Treatment System Required Containment Volume Calculations
#15 Modified ISR System – Support Equipment
• Air Compressor (A-100 and A-200) Specification Sheets and Performance Curve
#16 Modified ISR System – Process and Instrumentation
• Table J-5: AOP Pre-Treatment System Control Logic
• Table J-6: AOP Treatment System Control Logic
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx ix
Table of Contents
#17 Modified ISR System – Sampling Port locations
• Table J-7: Modified ISR System Sample Port Locations
#18 Modified ISR System – Air Emission Calculations
• AOP Pre-Treatment System – Air Stripper Off-Gas Emissions
• AOP Pre-Treatment System – Aeration Tank Off-Gas Emissions
#19 Modified ISR System – Electrical Load Calculation
• Electrical Load Calculation
#20 Modified ISR System – Operation and Maintenance Plan
• Table J-8: Modified ISR System Start-up and Proof of Performance Monitoring Plan
• Table J-9: Modified ISR System Process Monitoring Plan and Reporting Schedule
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx x
Acronym List
AOP Advanced Oxidation Process
APT Applied Process Technology, Inc.
BMPP Best Management Practices Plan
MEK 2-Butanone
City City of St. Petersburg
CO2 Carbon Dioxide
COC Constituent of Concern
CVOCs Chlorinated Volatile Organic Compounds
DNAPL Dense Non-Aqueous Phase Liquids F Degrees Fahrenheit
EQ tank Equalization Tank
Fe+2 Ferrous Iron
Fe+3 Ferric Iron
F.A.C. Florida Administrative Code
ft Feet
ft/sec Feet per Second
ft3 Cubic Feet
GCTLs Groundwater Cleanup Target Levels
gpd Gallons per Day
gpm Gallons per Minute
H2O2 Hydrogen Peroxide
HAP Hazardous Air Pollutant
HX Heat Exchanger
HDPE High Density Polyethylene
ISCO In-Situ Chemical Oxidation
ISR Interim Source Removal
IWD Industrial Wastewater Discharge
KVA Kilovolt-ampere
LPGAC Liquid -Phase Granular Activated Carbon
MIBK 4-Methyl-2-pentanone
mg/L Milligrams per Liter
mL/min Milliliters per Minute
MSDS Material Safety Data Sheet
O3 Ozone
O&M Operation and Maintenance
PCRs Periodic Compliance Reports
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx xi
Acronym List
PFD Process Flow Diagram
PID Piping and Instrumentation Diagram
PLC Programmable Logic Controller
POTW Publicly Owned Treatment Works
ppm Parts per Million
psi Pounds per Square Inch
PVC Polyvinyl Chloride
SCFM Standard Cubic Feet per Minute
Site Raytheon Site
SU Standard Units
ton/yr Tons per Year
TDH Total Dynamic Head
VFD Variable Frequency Drive
VPGAC Vapor Phase Granular Activated Carbon
VOCs Volatile Organic Compounds
VSA Vacuum Swing Absorption
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 1
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
1. Introduction
This document provides design information for the modified interim source removal
(ISR) system and treatment units which includes water treatment for the ISR system
and Building M source area treatment by in-situ thermal remediation technology. It has
been prepared to support the Remedial Action Plan Addendum (RAPA) for the
Raytheon Site located at 1501 72nd Street, St. Petersburg, Pinellas County, Florida
(Site). The in-situ thermal system and modified ISR systems are projected to operate
for 7 to 8 months. After operation of the in-situ thermal system is discontinued, the
modified ISR system operation will be discontinued and some of the process
equipment will be re-used and incorporated into the groundwater recovery and
treatment system. The design objectives of the modified ISR treatment system are to
remove Site-related constituents of concern (COCs) in groundwater near the source
areas within an accelerated time frame and reduce concentrations of COCs in
recovered groundwater to acceptable discharge limits specified by the City of St.
Petersburg (City).
2. Modified ISR System
The modified ISR system will include two separate treatment systems, the advanced
oxidation process (AOP) pre-treatment system and the AOP treatment system, which
are further discussed in Sections 2.2 and 2.3, respectively. The treatment systems will
be installed to treat groundwater from different areas of the Site. In addition, an in-situ
thermal system will be installed for source reduction beneath Building M. This system
has been designed and will be operated by TerraTherm Inc. (refer to Appendix I).
Groundwater recovered from the in-situ thermal system will be treated in both the AOP
pre-treatment and AOP treatment systems, prior to discharge to the City’s publicly
owned treatment works (POTW). The AOP pre-treatment system will be installed
inside of Building M near the in-situ thermal system. Effluent from the AOP pre-
treatment system will be routed to the AOP treatment system, which will be located on
the south side of Building E.
Some of the existing treatment components of the ISR system will be incorporated into
the treatment components of the modified ISR system and some additional
components will be added. In addition to treating water from the AOP pre-treatment
system, the AOP treatment system will continue to treat groundwater from the four
existing recovery wells (RW-2 through RW-5). Figure J-1, Tab #1 illustrates a
schematic of the modified ISR system process flow.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 2
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Treated process water from the AOP treatment system will be discharged to the City’s
POTW in accordance with an Industrial Wastewater Discharge Permit (IWDP). The
discharge permit will identify maximum allowable flow rates and establish chemical
discharge limitations.
2.1 Modified ISR System Design Requirements
The following sections include discussions of the modified ISR system design basis,
the treatment process and associated details related to each process unit, and
disposition of treated effluent. In addition, the process flow diagram (PFD), plant
layout, and treatment system piping and instrumentation diagram (PID) are presented.
2.1.1 Modified ISR System Design Basis
The design of the AOP pre-treatment system needs to be flexible to accommodate the
changing flow rates and water quality conditions that are anticipated during the in-situ
thermal system operation. High concentrations of COCs are expected in recovered
groundwater (discussed further in subsequent sections) at temperatures ranging from
70 degrees Fahrenheit (oF) to 180oF. To address these variable conditions, the
modified ISR system will be highly automated to:
• Reduce the need for 24-hour manned operation;
• Reduce the level of operator attention required; and
• Minimize the potential for untreated water to be released to the environment.
The following sections present the evaluation of expected flow rates and influent
concentrations that the design must take into account.
2.1.1.1 Expected Flow Rate
The process flow rate for the modified ISR system was established through
groundwater modeling. The design of the system is based on the following criteria:
• Expected term of operation – 7 to 8 months;
• Flow rates – ranging from 32 to 92 gallons per minute (gpm);
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 3
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
– 40 gpm average flow from the in-situ thermal system with design maximum flows of 60 gpm
Treated by the AOP pre-treatment system
AOP pre-treatment system effluent will be routed to the AOP treatment system for further treatment
– 32 gpm from existing ISR recovery wells
On-Site recovery wells – 4 wells @ 8 gpm = 32 gpm
Treated by the AOP treatment system
– 92 gpm total process flow
Combination of AOP pre-treatment system effluent and recovered groundwater from the existing ISR recovery wells
2.1.1.2 Influent Calculations
Influent calculations were prepared to estimate the concentrations of volatile organic compounds (VOCs) and other compounds of interest that would need to be treated by either the AOP pre-treatment system or the AOP treatment system. The estimated concentrations for the AOP pre-treatment system influent were estimated by averaging the groundwater concentrations detected during the vertical profile investigation performed at Building M in November 2009, then applying peaking and safety factors based on professional judgment. This calculation is summarized in the AOP pre-treatment system design basis summary table (Table J-1, Tab #1).
The AOP treatment system has been designed to accept water from two influent streams as discussed above. An estimate of influent concentrations to the AOP treatment system was prepared by evaluating influent concentrations to the existing ISR system and estimated effluent concentrations from the AOP pre-treatment system. Concentrations in the effluent of the AOP pre-treatment system were estimated based on assumed removal efficiencies during the pre-treatment process. This calculation is summarized in the modified ISR system design basis summary table (Table J-2, Tab #1).
2.1.1.3 Discharge Requirements
The required effluent concentrations for each compound of interest are summarized in the design basis summary table (Table J-2, Tab #1), in accordance with the discharge requirements for the City’s POTW. Following treatment by the modified ISR system, the final water quality will meet the applicable POTW discharge permit limits for all COCs. Currently, the treated water from the existing ISR system is discharged to the
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 4
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
City’s POTW through an on-Site connection under IWDP # SPFL-562910-SIU-08-112. A modification to this permit has been requested for discharging the processed water through the modified ISR system. The City has tentatively approved this modification which is discussed in a letter included in Appendix A.
2.1.1.4 Process Flow Diagram and Mass Balance
The PFD for the AOP pre-treatment and AOP treatment systems are presented in
Figures J-2 and J-3, Tab #1, respectively. The PFD identifies the treatment process
units and illustrates general orientation of flow through the system. A mass balance is
presented for the operating conditions of each system and is summarized in Tables J-
3 and J-4, Tab #1. The mass balances present the influent flow rate and
concentrations that are discussed above, and illustrates where compounds of interest
are removed within each treatment process.
2.1.1.5 Piping and Instrumentation Diagram
The design for the modified ISR system is fully detailed in the PID (Figures J-4
through J-11, Tab #2). The PIDs identify pipe material, pipe size, instrumentation,
process units, process unit interconnection, and some control features for both the
AOP pre-treatment and AOP treatment systems.
2.2 AOP Pre-Treatment System Design
The AOP pre-treatment system will only receive water from the in-situ thermal system.
The system is designed to treat an average flow rate of 40 gpm; however, the total
design flow rate for the AOP pre-treatment system is 60 gpm. The selected influent
concentrations for each COC were generally the highest of the evaluated data sets,
and are summarized in Tables J-1 and J-3, Tab #1.
The following sections include discussions of the AOP pre-treatment system design
basis, the treatment process and associated details related to each process unit.
2.2.1 Design Basis
In general, the in-situ thermal system will address the area with the highest
concentrations of VOCs and 1,4-dioxane; and the area with highest likelihood of dense
non-aqueous phase liquids (DNAPL). Any DNAPL recovered will be stored in the AOP
pre-treatment system influent equalization tanks and disposed off-site at an approved
facility.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 5
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Heated groundwater recovered by the in-situ thermal system will be cooled to
approximately 120oF using a multi-pass shell and tube heat exchanger system. The
heat exchanger is a non-contact system where heated process water and cooling
water do not come into contact. The cooling water will be provided by a chilled water
system, utilizing potable water provided by the City, which is operated within the in-situ
thermal system.
The VOCs in the AOP pre-treatment system process water will be primarily removed
(volatilized) by the air stripper. Additional treatment (oxidation and adsorption) for
organic compounds will be by the HiPOxTM system developed by Applied Process
Technology, Inc. (APT), and liquid-phase granular activated carbon (LPGAC) units in
the downstream AOP treatment system. Based on performance of the existing ISR
system and bench-scale testing results, it was determined that the HiPOxTM system
was able to achieve the objectives of the project and treat recovered groundwater to
the established criteria.
Dissolved iron will be removed by oxidation (through pH adjustment and aeration) and
multi-media filtration. Iron and other suspended solids that are removed by the filters
will be settled in the backwash tank. Settled solids will be removed from the backwash
tank via vacuum truck and will be taken off-site for disposal as needed. The air stripper
vapor effluent and vapors extracted from tank vents will be routed to the in-situ thermal
system prior to discharge, which is discussed further in Appendix I. Each process unit
in the AOP pre-treatment system is further discussed in subsequent sections.
2.2.1.1 Heat Exchanger Feed Tank (T-100)
The heat exchanger (HX) feed tank (T-100) will provide storage capacity for
equalization of groundwater from the in-situ thermal system recovery wells prior to
processing through the heat exchanger. The HX feed tank will provide a minimum of
20 minutes residence time at the design flow rate of 60 gpm. The HX feed tank will
have a design operation capacity of 1,150 gallons. Process water from the HX feed
tank will be transferred to the heat exchangers (HX-100A/B) by heat exchanger feed
pumps (P-100A/B).
The HX feed tank will be equipped with a pressure transducer to sense water level in
the tank. Data will be transferred to the plant programmable logic controller (PLC).
Water level set points will be programmed into the control logic for the system so the
PLC will automatically control the speed of the heat exchanger feed pumps (P-100A/B)
to maintain water level in the heat exchanger feed tank. In addition, a redundant
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 6
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
high/high float switch will shut down the AOP pre-treatment system when activated and
disable the transfer of groundwater and condensate from the in-situ thermal system. It
may be possible that solids accumulate in the tank; if solids need to be removed from
the tank, the system will be shutdown and solids will be removed and taken off-site for
disposal.
Venting of this tank will occur as the tank is filled and drained. The vapor venting from
the HX feed tank will be routed to the in-situ thermal system using a blower (B-300).
The blower will be used to convey vapors into a pressurized line in the in-situ thermal
system.
The HX feed tank will be a custom built carbon steel tank with an epoxy liner that can
withstand temperatures to 180oF. Tank sizing calculations are presented in Tab #3.
The specifications for the HX feed tank are summarized below.
Item: Heat Exchanger Feed Tank T-100
Quantity: 1
Manufacturer: Custom, to be determined
Type: Vertical bulk storage tank, closed top
Material: Carbon steel with interior epoxy coating rated for 180o F
Volume: 2,000 gallons
2.2.1.2 Heat Exchanger Feed Pumps (P-100A/B)
The water from the HX feed tank will be pumped by the HX feed pumps (P-100 A/B)
through the heat exchanger system. Two pumps will be provided with one pump
operating continuously and the other pump in standby. The pumps have been
designed to each operate at the design rate of 60 gpm and provide sufficient pressure
to pump process water through the heat exchangers to the influent equalization tank
(T-200A). The pump motors will be operated using a variable frequency drive (VFD)
controlled by the plant PLC that will receive water level data from the HX feed tank (T-
100). The speed of the pump will be controlled to maintain a constant water level in
the heat exchanger feed tank (T-100).
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 7
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
The pump head loss calculations, vendor cut sheets, and performance curves are
presented in Tab #3. The specifications for the HX feed pumps are provided below.
Item: Heat Exchanger Feed Pumps P-100A/B
Manufacturer: Gould’s, or equal Quantity: 2 Model: 3196 STi Type: End Suction Centrifugal Size: 2x3-8; 7.125-inch impeller Seal: Single mechanical seal Horsepower and Power Requirement:
3 HP, 1750 RPM, 230/460/3/60 TEFC
Design Flow Rate and TDH:
60 gpm @ 53 feet (ft) total dynamic head (TDH)
2.2.1.3 Heat Exchangers (HX-100A/B)
The heat exchangers (HX-100A/B) will cool the process water from the in-situ thermal
system recovery wells. Two heat exchangers will be provided with one exchanger
operating continuously and the other operating in standby. The heat exchanger will
cool the process water temperature from approximately 180oF to 120oF using a multi-
pass shell and tube heat exchanger system. The HX will operate at the design flow
rate of 60 gpm and will require approximately 80 gpm of 40oF cooling water to achieve
the desired cooling. The process water will be processed in four passes through the
system, while the cooling water will be processed in a single pass. The cooling water
will be provided by a chilled water system operated within the in-situ thermal system,
as discussed in detail in Appendix I.
The sizing of the heat exchanger is presented in a calculation included in Tab #3. The
heat exchanger specifications are presented below.
Item Heat Exchanger HX-100A/B
Quantity: 2
Manufacturer: API Basco, or equal
Type: Basco Type 500, Series 08114
No. Process Water Passes:
4
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 8
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Item Heat Exchanger HX-100A/B
Materials: 316L stainless steel shell and tubes
Hot Water Capacity: 60 gpm @ 180oF
Cooling Water Capacity:
80 gpm @ 40oF
2.2.1.4 Influent Equalization Tanks (T-200A/B/C)
The influent equalization tanks (EQ tanks) T-200A/B/C will provide storage capacity for
equalization of process water flows from the heat exchanger system. EQ tank (T-
200A) will provide approximately 18,000 gallons of useable volume and will use a
normal operating level of 50 percent (9,000 gallons). Therefore, approximately 150
minutes of residence time will be provided at the maximum design flow rate of 60 gpm.
Process water from EQ tank (T-200A) will be transferred to the aeration tank (T-300)
by aeration tank feed pumps (P-200A/B).
Equalization tanks (T-200B/C) will be used for additional storage capacity in the event
the AOP pre-treatment system is shut down for maintenance or unscheduled shut-
down events, and the in-situ thermal system is still operating. EQ tanks (T-200B/C) will
provide 18,000 gallons of usable storage capacity each, for a total additional storage
capacity of 36,000 gallons. This additional capacity will allow the in-situ thermal
system to continue to operate for an additional 10 hours (at 60 gpm) to 16 hours (at 40
gpm) without the downstream treatment systems operating. The stored water will be
processed once the treatment system is placed back on-line. Recirculation pump (P-
200C) will transfer the process water to EQ tank (T-200A) to be processed through the
system.
The EQ tanks will be equipped with a pressure transducer to sense water level in the
tank and data will be transferred to the plant PLC. Water level set points will be
programmed into the control logic for the system so the PLC will automatically control
the speed of the aeration tank feed pumps. In addition, a redundant high/high float
switch will be installed in each equalization tank that will shut down the AOP pre-
treatment system and disable the transfer of groundwater and condensate from the in-
situ thermal system when activated. It may be possible that solids and DNAPL
accumulate in the tank; if solids and/or DNAPL need to be removed from the tank, the
system will be shutdown and the solids/DNAPL will be removed and taken off-site for
disposal.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 9
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
The EQ tanks will be steel tanks with two sealed top access hatches and smooth
interior walls for easy cleaning. The sizing of the EQ tanks is presented in a calculation
included in Tab #4. The specifications are summarized below.
Item: Influent Equalization Tanks T-200A/B/C
Quantity: 3
Manufacturer: Baker Corp., or equal
Type: EZ Clean Fixed Axle Safety Vapor Frac Tank
Material: Carbon Steel with no interior coating
Working Volume: 18,000 gallons
Dimensions: 37-ft, 6-inches long by 8-ft, 6-inches wide by 11-ft, 2-inches high
2.2.1.5 Aeration Tank Feed Pumps (P-200A/B)
The water from the influent equalization tank (T-200A) will be pumped by aeration tank
feed pumps (P-200A/B) to the aeration tank (T-300). Two pumps will be provided with
one pump operating continuously and the other pump in standby. The pumps have
been designed to each operate at the design rate of 60 gpm and provide sufficient
pressure to pump process water to the aeration tank. The pump motors will be
operated using a VFD controlled by the plant PLC that will receive water level data
from the EQ tank (T-200A). The pump speed will be controlled to maintain a constant
water level in the influent equalization tank (T-200A).
The pump head loss calculations and performance curves are presented in Tab #4.
The pump specification sheets are presented in Tab #3. The specifications for the
aeration tank feed pumps are provided below.
Item: Aeration Tank Feed Pumps P-200A/B
Manufacturer: Gould’s, or equal
Quantity: 2
Model: 3196 STi
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 10
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Item: Aeration Tank Feed Pumps P-200A/B
Type: End Suction Centrifugal
Size: 2x3-8; 5.875-inch impeller
Seal: Single mechanical seal
Horsepower and Power Requirement:
1.5 HP, 1750 RPM, 230/460/3/60 TEFC
Design Flow Rate and TDH:
60 gpm @ 35 ft TDH
2.2.1.6 Recirculation Pump (P-200C)
The overflow water from the influent EQ tanks (T-200B/C) will be pumped by the
recirculation pump (P-200C) back to the influent EQ tank (T-200A) to be processed
through the AOP pre-treatment system. One pump will be provided and will operate on
as-needed basis. The pump has been designed to operate at a design rate of 40 gpm
and will provide sufficient pressure to pump process water to the influent EQ tank. The
pump motor will be operated using a VFD controlled by the plant PLC that will receive
water level from the influent EQ tanks (T-200A/B/C).
The pump head loss calculations and performance curves are presented in Tab #4.
The pump specification sheets are presented in Tab #3. The specifications for the
recirculation pump are provided below.
Item: Recirculation Pump P-200C
Manufacturer: Gould’s, or equal
Quantity: 1
Model: 3196 STi
Type: End Suction Centrifugal
Size: 2x3-8; 6.5-inch impeller
Seal: Single mechanical seal
Horsepower and Power Requirement:
2 HP, 1750 RPM, 230/460/3/60 TEFC
Design Flow Rate and TDH:
40 gpm @ 46 ft TDH
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 11
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.2.1.7 Aeration Tank (T-300)
The aeration tank (T-300) will provide aeration of water and sufficient residence time to
allow for oxidation of iron and complete mixing of the tank. Sodium hydroxide will be
added to the process stream to increase the pH of the water from approximately 6.0
standard units (SU) to 7.4 SU to enhance the oxidation of iron. Sodium hydroxide will
be metered into an injection port in an in-line static mixer (SM-100) that will provide
rapid mixing of the injected sodium hydroxide. The static mixer will be a 3-inch
diameter, schedule 40 carbon steel unit containing six mixing elements.
In addition, the aeration tank influent line will include an approximately 5-ft section of
12-inch diameter piping to provide additional residence time for the pH control loop to
respond. A pH analyzer will be installed downstream of this pipe section and will
provide data to the PLC to control operation of the sodium hydroxide metering pump.
Air flow requirement calculations have been performed to determine the air flow rate
required to oxidize iron. Based on influent concentrations and flow rate, 8 standard
cubic feet per minute (scfm) of air is required to complete the iron oxidation process as
shown in the design calculation in Tab #4. Oxygen transfer requirements to achieve
complete mixing are approximately 30 scfm per 1,000 cubic ft (ft3) of tank volume. The
aeration tank is approximately 870 ft3 (6,500 gallons); therefore, 26 scfm is required to
achieve complete mixing. The aeration tank blower was sized to operate at a design
flow rate of 30 scfm to provide sufficient air flow for both mixing and iron oxidation.
The aeration tank will be equipped with a coarse bubble diffuser system to promote
distribution of air within the tank. The air will provide mixing that will prevent the
settling of iron particulates and suspended solids. The aeration tank will provide a
minimum 90 minutes of residence time at the design flow rate of 60 gpm. The
operating capacity will be 5,400 gallons, with 6,500 gallons of total storage capacity.
Process water from aeration tank (T-300) will be transferred to the filter feed tank (T-
400) by gravity.
The aeration tank will be equipped with a pressure transducer to sense water level in
the tank and data will be transferred to the plant PLC. In addition, a redundant
high/high float switch will shut down the AOP pre-treatment system components
downstream of the influent EQ tanks when activated.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 12
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
The aeration tank will be a vertical high density polyethylene tank with one sealed top
access hatch. The sizing of the aeration tank and air flow requirement calculations are
presented in Tab #4. The specifications are summarized below.
Item: Aeration Tank T-300
Quantity: 1
Manufacturer: Baker Corp., or equal
Type: 6,500 Gallon Poly Tank (vertical, cylindrical, closed-top tank)
Material: High density polyethylene
Volume: 6,500 gallons
Dimensions: 10-ft diameter by 12-ft, 4-inch total height (10-ft, 6-inch sidewall)
Item: Static Mixer SM-100
Manufacturer: Koflo, or equal
Model: Series 275
Type: Low pressure loss, flange mounted mixer with FNPT injection port
Size: 3-inch
2.2.1.8 Aeration Blower (B-100)
The aeration blower (B-100) will provide air to the coarse bubble diffusers installed
inside of aeration tank (T-300) to provide complete mixing of the tank. Oxygen transfer
requirements to achieve complete mixing of the aeration tank are approximately 26
scfm, as discussed above. Blower (B-100) was sized to operate at a design flow rate
of 30 scfm to provide sufficient air flow to the aeration tank.
The blower has been designed to operate at the design air flow rate and provide
sufficient pressure to push air through the coarse bubble diffusers and the water
column within the aeration tank. The blower discharge line will be equipped with a
pressure indicator to sense pressure in the piping and data will be transferred to the
plant PLC. Pressure set points will be programmed into the control logic for the system
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 13
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
so the PLC will automatically operate the aeration blower (B-100), as part of blower
cycle operations.
The blower sizing calculations, vendor cut sheets, and performance curves are
presented in Tab #4. The specifications for the aeration blower are provided below.
Item: Aeration Blower B-100
Manufacturer: Becker Pumps Corp., or equal
Quantity: 1
Model: KDT 3.60
Type: Oil-less, rotary vane, low pressure compressor
Horsepower and Power Requirement:
3 HP, 1740 RPM, 230/460/3/60
Max Flow Rate and Pressure:
39 scfm @ 22 psig
Design Flow Rate and Pressure:
36 scfm @ 5 psig
2.2.1.9 Coarse Bubble Diffusers
The coarse bubble diffusers will be provided to aid in complete mixing of the aeration
tank. Cap diffusers will be installed in the main air feed line in the tank using a pipe tap
and threaded grommet connection. The cap diffusers have been designed to operate
at the design air flow rate.
The coarse bubble diffuser vendor cut sheets and performance curves are presented
in Tab #4. The specifications for the coarse bubble diffusers are provided below.
Item: Coarse Bubble Diffusers
Manufacturer: Stamford Scientific International, or equal
Quantity: 6
Model: CAP AFC75
Type: Cap Diffuser with (10) 5 millimeter diameter holes
Design Flow Rate: 4 – 6 scfm per diffuser
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 14
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.2.1.10 Sodium Hydroxide Injection System (T-1000 and P-700)
Given the expected pH of the recovered groundwater (approximately 6.0 SU), the
treatment system will include a sodium hydroxide injection system to increase the pH
required for efficient treatment. Sodium hydroxide (50 percent) will be added to the
influent line of the aeration tank, as discussed above, to increase pH to 7.4 SU. The
total amount of sodium hydroxide required for the 60 gpm design flow rate is estimated
to be approximately 8.3 gallons per day (gpd). This estimated volume was based on
sodium hydroxide usage observed during operation of the existing ISR system.
The sodium hydroxide injection system will include a sodium hydroxide tank (T-1000)
and one chemical metering pump (P-700). The sodium hydroxide tank has been sized
to contain a 30-day supply of sodium hydroxide (275 gallons) and will be equipped with
individual secondary containment. The metering pump will be controlled by the plant
PLC that will receive pH data from a pH probe installed in the aeration tank influent
line. Anticipated flow rate for sodium hydroxide injection is approximately 8.3 gpd, and
the pump has the capability of pumping 0.1 to 18 gpd.
The vendor cut sheets for the sodium hydroxide tank and metering pump are provided
in Tab #4. The specifications are summarized below.
Item: Sodium Hydroxide Tank T-1000
Quantity: 1
Manufacturer: Snyder Tank, or equal
Type: Double Wall Containment Tank (vertical, cylindrical, closed top tank)
Material: High density polyethylene
Volume: 250 gallons
Dimensions: 47-inch diameter by 64-inch total height
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 15
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Item Sodium Hydroxide Metering Pump, P-700
Quantity: 1
Manufacturer: LMI, or equal
Model: AA-962-362HI
Max Pumping Rate and Pressure:
18 gpd @ 80 pounds per square inch (psi)
Design Flow Rate: 8.3 gpd
2.2.1.11 Filter Feed Tank (T-400)
The filter feed tank (T-400) will receive discharge water from the aeration tank (T-300)
and decant water generated from the backwash tank (T-800). The filter feed tank will
be the source of main process water and clean backwash water to the multi-media
filters. Total backwash volume is 2,545 gallons per cycle which will be decanted to the
filter feed tank once per day, just prior to the beginning of the backwash cycle.
The filter feed tank will provide a minimum of 30 minutes of residence time, with an
average operating capacity of 3,250 gallons. The total storage capacity of the tank is
6,500 gallons. This tank will operate at 50 percent capacity to leave sufficient capacity
to accept the backwash decant water. Process water from filter feed tank (T-400) will
be pumped through the multi-media filters (T-500A/B/C) by filter feed pumps (P-
300A/B).
The filter feed tank will be equipped with a pressure transducer to sense water level in
the tank and data will be transferred to the plant PLC. Water level set points will be
programmed into the control logic for the system so the PLC will control the speed of
filter feed pumps (P-300A/B) to maintain a constant water level in the filter feed tank.
In addition, a redundant high/high float switch will shut down the AOP pre-treatment
system components downstream of the influent EQ tanks when activated.
The filter feed tank will be a vertical high density polyethylene tank with one sealed top
access hatch. The sizing of the filter feed tank is presented in a calculation included in
Tab #5. The specifications are summarized below.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 16
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Item: Filter Feed Tank T-400
Quantity: 1
Manufacturer: Baker Corp., or equal
Type: 6,500 Gallon Poly Tank (vertical, cylindrical, closed top tank)
Material: High density polyethylene
Volume: 6,500 gallons
Dimensions: 10-ft diameter by 12-ft, 4-inch total height (10-ft, 6-inch sidewall)
2.2.1.12 Filter Feed Pumps (P-300A/B)
The water from the filter feed tank will be pumped by filter feed pumps (P-300 A/B)
through the multi-media filters to the air strippers (T-600A/B). Two pumps will be
provided with one pump operating continuously and the other pump in standby. Each
pump has been designed to operate at the design rate of 60 gpm and provide sufficient
pressure to pump process water through the multi-media filters to the air strippers. The
pump motors will be operated using a VFD controlled by the plant PLC that will receive
water level data from the filter feed tank (T-400).
The pump head loss calculations and performance curves are presented in Tab #5.
The pump specification sheets are presented in Tab #3. The specifications for the filter
feed pumps are provided below.
Item: Filter Feed Pumps P-300A/B
Manufacturer: Gould’s, or equal
Quantity: 2
Model: 3196 STi
Type: End Suction Centrifugal
Size: 1.5x3-6; 5.125-inch impeller
Seal: Single mechanical seal
Horsepower and Power Requirement
7.5 HP, 3520 RPM, 230/460/3/60 TEFC
Design Flow Rate and TDH:
60 gpm @ 112 ft TDH
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 17
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.2.1.13 Backwash Pump (P-300C)
Backwash pump (P-300C) will pump water from the filter feed tank through the multi-
media filters to the backwash tank (T-800). The filter feed tank (T-400) will be the
source of backwash water for the multi-media filter backwash cycle. Filter feed pumps
(P-300A/B) will be shut-down during the backwash cycle. The backwash cycle will be
106 gpm for 8 minutes (for three multi-media filter vessels), resulting in a total
backwash volume of 2,545 gallons.
The backwash pump has been designed to operate at the design backwash rate of
106 gpm and provide sufficient pressure to pump process water through the multi-
media filters to the backwash tank. The pump motor will be operated using a VFD
controlled by the plant PLC that will receive water level data from the filter feed tank (T-
400). The VFD will allow for maximum flow and pressure control, and will allow
adjustments to be made during each application.
The pump head loss calculations and performance curves are presented in Tab #5.
The pump specification sheets are presented in Tab #3. The backwash pump
specifications are provided below.
Item: Backwash Pump P-300C
Manufacturer: Gould’s, or equal
Quantity: 1
Model: 3196 STi
Type: End Suction Centrifugal
Size: 1.5x3-6; 5.125-inch impeller
Seal: Single mechanical seal
Horsepower and Power Requirement:
7.5 HP, 3520 RPM, 230/460/3/60 TEFC
Design Flow Rate and TDH:
110 gpm @ 103 ft TDH
2.2.1.14 Multi-Media Filters (T-500A/B/C)
A multi-media filtration system (T-500A/B/C) will be installed for primary filtration of iron
particulates and suspended solids produced in the upstream aeration process. The
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 18
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
multi-media filters are designed to protect the air strippers from significant iron fouling.
Multi-media filters were selected for their good filtration performance (consistent
removal of particles 5 microns in size or greater) and ability to handle the design flow
rate 60 gpm. Filtration performance will not be affected by lower flow rates in the event
of reduced flow rates from the in-situ thermal system.
The multi-media filter package will include three 3-foot diameter vessels in a pre-
packaged skid with an internal control system. During normal operation, all three
vessels will operate continuously in parallel. During a backwash cycle, water will be
processed through two vessels while the third is backwashed. The filtered water from
the two operating vessels will be used as clean backwash water for the third vessel.
Each vessel contains four layers of filtration media including gravel, coarse garnet, fine
garnet, and anthracite. To prevent clogging, the filters will be backwashed when the
differential pressure across the filters is approximately 15 to 20 psi. Backwash
frequency is anticipated to be once per day, and process water from the filter feed tank
will be used as the source of water for backwashing.
Calculations for multi-media filter sizing, backwash requirements, and vendor cut
sheets are presented in Tab #5. Specifications are provided below.
Item: Multi-Media Filters T-500A/B/C
Manufacturer: Yardney, or equal
Model: MM-3660-3AS
Type: 3-vessel filtration system with manifolded influent, effluent and backwash piping; and automated valves
Service Flow Rate: Nominal flow range 105-320 gpm; max flow rate 426 gpm
Backwash Flow Rate: 106 gpm
Max Pressure: 80 psi
Material: Epoxy-coated steel
Vessel Dimensions: 36-inch diameter by 60-inch side shell height
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 19
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.2.1.15 Backwash Tank (T-800)
The backwash tank (T-800) will receive backwash water from the multi-media filters (T-
500A/B/C). The backwash tank will provide a total storage capacity of 6,500 gallons.
The tank was designed for sufficient volume to handle a single backwash event plus
21-days of solids storage capacity. Backwash solids from the multi-media filters will be
allowed to settle between backwash cycles, which are estimated to be approximately
once per day. Prior to the backwash sequence, the supernatant within the tank will be
decanted to the filter feed tank (T-400). One backwash cycle storage volume (2,545
gallons) will be decanted to provide room to accept water from the new backwash
cycle. This cycle of backwashing, settling and decanting will continue until solids build
up in the bottom of the tank. At this time, the system will be shutdown and the solids
will be removed via vacuum truck and taken off-site for disposal.
The backwash tank will be equipped with a pressure transducer to sense water level in
the tank and data will be transferred to the plant PLC. Water level set points will be
programmed into the control logic for the system so the PLC will control the speed of
the decant pump (P-600) to maintain a set water level in the tank. In addition, a
redundant high/high float switch will shut down the AOP pre-treatment system
components downstream of the influent EQ tanks when activated.
The backwash tank will be a vertical high density polyethylene tank with one sealed top
access hatch. The sizing of the backwash tank is presented in a calculation included in
Tab #5. Specifications are summarized below.
Item: Backwash Tank T-800
Quantity: 1
Manufacturer: Baker Corp., or equal
Type: 6,500 Gallon Poly Tank (vertical, cylindrical, closed top tank)
Material: High density polyethylene
Volume: 6,500 gallons nominal
Dimensions: 10-ft diameter by 12-ft, 4-inch total height (10-ft, 6-inch sidewall)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 20
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.2.1.16 Decant Pump (P-600)
The decant pump (P-600) will pump water from the backwash tank to the filter feed
tank (T-400). One backwash cycle storage volume (2,545 gallons) will be decanted
prior to each new backwash cycle. The decant pump has been designed to decant the
required volume of supernatant in approximately 2 hours. The pump motor will be
operated using a VFD controlled by the plant PLC that will receive water level data
from the filter feed tank (T-400) and the backwash tank (T-800). The VFD will allow for
maximum flow and pressure control, and will allow adjustments to be made during
each application.
The pump head loss calculations, vendor cut sheet, and performance curves are
presented in Tab #5. The decant pump specifications are provided below.
Item: Decant Pump P-600
Manufacturer: Gould’s, or equal
Quantity: 1
Model: 1SC51C-F
Type: Submersible
Size: 1.25-inch discharge; 3 stage
Horsepower and Power Requirement:
1/2 HP, 3450 RPM, 115/1/60 TEFC
Design Flow Rate and TDH:
30 gpm @ 41 ft TDH
2.2.1.17 Polymer Injection System (T-900, P-500 and SM-200)
During the multi-media filter backwash sequence polymer will be added to the water
stream to promote the formation of larger and heavier particles that will aid in settling
the suspended solids. The polymer injection system will include a storage tank (T-
900), chemical metering pump (P-500) and an in-line static mixer (SM-200). Based on
jar testing completed during operation of the existing ISR system, the selected polymer
is PolyFloc AS1002 which will be metered at a dosage rate of 15 parts per million
(ppm). The Material Safety Data Sheet (MSDS) and fact sheet for the PolyFloc are
included in Tab #5.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 21
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
A summary of polymer usage rates and volumes, and vendor cut sheets are presented
in Tab #5. The polymer will be supplied from the vendor in a 5-gallon bucket that is
expected to last approximately 6 months based on the estimated polymer usage rate of
0.27 gallons per week. The polymer metering pump (P-500) will inject polymer into an
injection port in the in-line static mixer (SM-200) which will provide rapid mixing of the
injected polymer. The static mixer will be a 3-inch diameter, schedule 40 carbon steel
unit containing six mixing elements.
Polymer metering pump and static mixer specifications are provided below.
Item: Polymer Metering Pump P-500
Manufacturer: LMI, or equal
Model: AA-971-352HI
Max Pumping Rate and Pressure:
10 gpd @ 140 psi
(27 mL/min)
Design Flow Rate: 2.3 gpd (6 milliliters per minute [mL/min])
Item: Static Mixer SM-200
Manufacturer: Koflo, or equal
Model: Series 275
Type: Low pressure loss, flange mounted mixer with FNPT injection port
Size: 3-inch
2.2.1.18 Air Stripper System (T-600A/B)
The air strippers (T-600A/B) will be used to remove the majority of VOCs from the
water stream. The air strippers were designed for greater than 99.9 percent removal
rates of all COCs except 1,4-dioxane, acetone, 2-butanone [i.e., methyl ethyl ketone
(MEK)], and 4-methyl 2-pentanone [i.e., methyl isobutyl ketone (MIBK)]. 1,4-Dioxane
will be treated in downstream AOP unit. Two air strippers will be provided with one air
stripper operating continuously and the other in standby. The air stripper is a tray type
stripper equipped with 4 trays, a plexiglass front hatch, polypropylene de-mister, liquid
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 22
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
level sight gauge, sump pressure gauge and other appurtenances. Process water will
drain via gravity from the air stripper sump to the air stripper discharge tank (T-700).
Each air stripper will be equipped with a high-pressure blower that will be positioned to
allow an induced draft configuration. The air stripper blowers (B-200A/B) have been
designed to operate at the design air flow rate of 900 scfm and provide sufficient
pressure to pull air through the air stripper to the in-situ thermal system (Appendix I).
The blower inlet line will be equipped with a pressure indicator to sense pressure in the
piping and data will be transferred to the plant PLC. Pressure set points will be
programmed into the control logic for system monitoring.
The air stripper COC removal model, blower sizing calculations, vendor cut sheets,
and performance curves are presented in a calculation included in Tab #6. The air
stripper and air stripper blower specifications are presented below.
Item: Air Stripper T-600A/B
Quantity: 2
Manufacturer: QED, or equal
Type: E-Z Tray Model 16.6 SS
No. Trays: 4
Max Flow Range: 1 – 150 gpm
Design Flow Rate: 60 gpm
Shell Dimensions: 49-inch by 52-inch by 104-inch height
Materials: 304 SS
Item: Air Stripper Blowers B-200A/B
Manufacturer: New York Blower Co., or equal
Quantity: 2
Model: 28506, Arrangement 4
Type: HP Pressure Blower
Horsepower and Power Requirement:
7.5 HP, 3500 RPM, 230/460/3/60
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 23
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Item: Air Stripper Blowers B-200A/B
Design Flow Rate and Pressure:
900 scfm @ 60 inches water
2.2.1.19 Air Stripper Discharge Tank (T-700)
Process water from the air stripper sump will drain via gravity to the air stripper
discharge tank (T-700). The tank was designed to supplement the volume of the air
stripper sump capacity. The tank was sized for approximately 10 minutes of residence
time at the design flow rate of 60 gpm, providing 1,100 gallons of total storage
capacity. Process water from the air stripper discharge tank (T-700) will be transferred
to the influent EQ Tank (T-1300) in the AOP treatment system via air stripper discharge
pumps (P-400A/B).
The air stripper tank will be equipped with a pressure transducer to sense water level in
the tank and data will be transferred to the plant PLC. Water level set points will be
programmed into the control logic for the system so the PLC will control the speed of
the air stripper discharge pumps (P-400A/B) to maintain a constant water level in the
air stripper discharge tank (T-700). In addition, a redundant high/high float switch will
shut down the AOP pre-treatment system components downstream of the influent EQ
tanks when activated.
The air stripper discharge tank will be a vertical high density polyethylene tank with one
sealed top access hatch. The sizing of the air stripper discharge tank is presented in a
calculation included in Tab #6. The specifications are summarized below.
Item: Air Stripper Discharge Tank T-700
Quantity: 1
Manufacturer: Snyder Industries Inc., or equal
Type: 1,100 Gallon Dome Bottom Tank
Material: High density polyethylene
Volume: 1,100 gallons
Dimensions: 86-inch diameter by 55-inch total height (36-inch sidewall)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 24
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.2.1.20 Air Stripper Discharge Pumps (P-400A/B)
The water from the air stripper discharge tank will be pumped by air stripper discharge
pumps (P-400A/B) to influent EQ tank (T-1300) in the downstream AOP treatment
system. Two pumps will be provided with one pump operating continuously and the
other pump in standby. The pumps have been designed to operate at the design rate
of 60 gpm and provide sufficient pressure to pump process water the approximate
1,400 ft distance to influent EQ tank (T-1300). The pump motors will be operated
using a VFD controlled by the plant PLC that will receive water level data from the air
stripper discharge tank (T-700).
The pump head loss calculations and performance curves are presented in Tab #6.
The pump specification sheets are presented in Tab #3. The specifications for the air
stripper discharge pumps are provided below.
Item: Air Stripper Discharge Pumps P-400A/B
Manufacturer: Gould’s, or equal
Quantity: 2
Model: 3196 STi
Type: End Suction Centrifugal
Size: 2x3-8; 7.75-inch impeller
Seal: Single mechanical seal
Horsepower and Power Requirement:
3 HP, 1750 RPM, 230/460/3/60 TEFC
Design Flow Rate and TDH:
60 gpm @ 64 ft TDH
2.2.1.21 Tank Vent Blower (B-300)
The tank vent blower (B-300) will be used to convey vapors from tanks upstream of the
air strippers (T-600A/B) to the in-situ thermal system. The blower was sized to provide
sufficient air flow and pressure to convey tank vapors into a pressurized line.
The blower suction line will be equipped with a pressure indicator to sense pressure in
the piping. This data will be transferred to the plant PLC to verify continuous operation
of the vent blower.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 25
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
The blower sizing calculations, vendor cut sheets, and performance curves are
presented in Tab #7. The specifications for the tank vent blower are provided below.
Item: Tank Vent Blower B-300
Manufacturer: Rotron, or equal
Quantity: 1
Model: DR303AE72M
Type: Regenerative Blower
Horsepower and Power Requirement:
0.5 HP, 230/460/3/60
Max Flow Rate and Pressure:
55 scfm @ 45 inches of water
Design Flow Rate and Pressure:
30 scfm @ 24 inches of water
2.2.1.22 Scrubber Blow-Down Water Treatment
Several sources of water generated within the in-situ thermal system will be
segregated and not processed by the AOP pre-treatment system. This water stream
includes the scrubber sump discharge water, the boiler water softener discharge, and
various blow-down ports throughout the in-situ thermal system. Most of this water is
non-contact water, meaning that the water does not contact any COCs. However, the
scrubber discharge water has the potential to include low concentrations of COCs
since the water comes into contact with scrubber gases that may potentially contain
COCs. Any COCs in the scrubber blow-down water would likely be VOCs; 1,4-dioxane
is not expected to be in this water stream. The majority of this segregated stream will
be scrubber blow-down water at an expected flow rate ranging from 3 to 8 gpm.
The scrubber blow-down water will contain sodium chloride (NaCl) that is generated in
the scrubber unit. The concentrations of NaCl will vary during operations and will
depend on the amount of chlorinated VOCs (CVOCs) being oxidized in the thermal
oxidizer. The estimated NaCl concentrations within the scrubber discharge may range
from 1,700 – 12,000 milligrams per liter (mg/L). Chlorides can have a detrimental
effect on AOP treatment reactions, in addition to being corrosive to plant components.
Therefore, to prevent damage to downstream operations, the blow-down water will be
segregated and handled separately.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 26
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
The blow-down water will be treated by LPGAC to remove potential VOCs. Following
treatment, the water will be pumped to the AOP treatment system and combined with
AOP treatment system effluent prior to discharging to the City’s POTW. The AOP
treatment system effluent is expected to have low NaCl concentrations; therefore, the
NaCl concentration of the combined flow stream will be reduced. The maximum
chloride concentrations of the combined effluent flow streams discharged to the City
are expected to be less than 1,150 mg/L, with typical chloride concentrations in the
range of 100 to 500 mg/L; well below the discharge limit of 1,350 mg/L. Components
of the scrubber blow-down system include a blow-down collection tank, process
pumps, and two LPGAC vessels; which are further described below.
2.2.1.22.1 Scrubber Blow-Down Tank (T-1100)
The scrubber blow-down tank (T-1100) will collect water from several sources including
the scrubber sump discharge water, the boiler water softener, and various blow-down
ports throughout the in-situ thermal system. The average flow rate is expected to vary
and will range from 3 to 8 gpm. The system will be designed for a maximum flow rate
of 15 gpm. The scrubber blow-down tank will provide a minimum of 60 minute
residence time at the maximum design flow rate of 15 gpm, and will have a minimum
storage capacity of 1,200 gallons. The tank will be a vertical, domed top custom
reinforced fiberglass epoxy tank with approximate dimensions of 6-ft diameter and 6-ft
sidewall height. Tank sizing calculations are included in Tab #8.
The scrubber blow-down tank will be equipped with a pressure transducer to sense
water level in the tank and data will be transferred to the plant PLC. Water level set
points will be programmed into the control logic for the system so the PLC will
automatically control the speed of the transfer pump (P-900). In addition, a redundant
high/high level float switch will shut down the AOP pre-treatment system and disable
transfer of scrubber blow-down water from the in-situ thermal system when activated.
2.2.1.22.2 Transfer Pump (P-900)
The water from the scrubber blow-down tank will be pumped by transfer pump (P-900).
The pump has been designed to operate at the design flow rate of 15 gpm and provide
sufficient pressure to pump water through the LPGAC vessels to the modified ISR
system discharge point to the City’s POTW. The pump motor will be operated using a
VFD controlled by the plant PLC that will receive water level data from the scrubber
blow-down tank (T-1100).
The pump head loss calculations, vendor cut sheets and performance curves are
presented in Tab #8. The specifications for transfer pump (P-900) are provided below.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 27
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Item: Transfer Pump P-900
Manufacturer: Gould’s, or equal
Quantity: 1
Model: 1SVD1FSD1H
Type: Vertical Multi-Stage Pump (SSV Series)
No. Stages: 6
Horsepower and Power Requirement:
0.75 HP, 3500 RPM, 230/460/1/60 TEFC
Design Flow Rate and TDH:
15 gpm @ 126 ft TDH
2.2.1.22.3 Liquid-Phase Granular Activated Carbon (T-1200A/B)
Water from the scrubber blow-down tank will be pumped through two LPGAC vessels
that will be operated in series for VOC removal. The potential of having VOCs in the
scrubber blow-down is low, but LPGAC is provided to remove any VOCs that may be
present in the water stream. Each vessel will contain 250 pounds of acid-washed
coconut carbon. The vessels will be constructed of fiberglass in order to prevent
corrosion due to the high salt content. The LPGAC COC removal model and vendor
cut sheets are provided in Tab #8. Specifications are provided below.
Item: LPGAC Vessels T-1200A/B
Manufacturer: Carbonair, or equal
Model: PC3, complete skid mounted
Max Pressure: 150 psi
Material: Reinforced fiberglass
The estimated time for breakthrough through the first vessel is 30 days and the second
vessel is 120 days (Tab #8); however, other factors besides VOC loading that may
contribute to the carbon life include bio-fouling and solids build-up. These factors will
result in pressure increases across the LPGAC vessel. Water from between the
LPGAC vessels will be sampled and analyzed monthly to determine if VOCs are
breaking through the first LPGAC vessel. If break-through above City discharge limits
is occurring after the first vessel or the vessels become clogged with solids, the first
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 28
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
vessel will be taken off-line and the second vessel will be moved to the first position. A
new LPGAC unit will be placed as the second vessel. The spent LPGAC will be taken
off-site for proper disposal.
2.2.1.23 AOP Pre-Treatment System Discharge Line
The effluent from the AOP pre-treatment system will be routed approximately 1,400 ft
to the AOP treatment system influent EQ tank (T-1300) to be processed through the
AOP treatment system. The pre-treated process water pipeline will be 3-inch high
density polyethylene (HDPE) piping. The HDPE piping will transition to 3-inch carbon
steel at the influent EQ tank (T-1300) to connect to the influent nozzle on the tank.
2.3 AOP Treatment System Design
The AOP treatment system is designed to treat groundwater extracted from the
existing ISR recovery wells and process water from the AOP pre-treatment system. It
is anticipated that the AOP treatment system will operate for approximately 7 to 8
months, which is the expected time of operation of the in-situ thermal system. Based
on data obtained during operation of the existing ISR system, the AOP treatment
system is expected to be effective in containing affected on-Site groundwater and
removing COCs from the groundwater prior to discharge to the City’s POTW.
The total design flow rate for the AOP treatment system is 92 gpm and includes 32
gpm from the existing ISR wells and 60 gpm from the AOP pre-treatment system. The
selected influent concentration for each COC was generally the highest of the
evaluated data sets, as shown in Tables J-2 and J-4, Tab #1.
The following sections include discussions of the AOP treatment system design basis,
the treatment process and associated details related to each process unit, and
disposition of treated effluent. Since the groundwater recovery system of the modified
ISR system remains the same as the existing ISR system, the details provided below
focus on the treatment system components.
2.3.1 Design Basis
In general, the organic compounds in the AOP treatment system will be primarily
destroyed (oxidized) by the HiPOxTM AOP treatment system developed by APT.
Additional polishing treatment for organic compounds will be provided by LPGAC units.
The recovered groundwater and AOP pre-treatment system effluent will be treated to
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 29
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
meet the required effluent concentrations for each compound of interest, and will be
discharged to the City’s POTW in accordance with the discharge limits requirements.
Dissolved iron in the process water and in the AOP pre-treatment system effluent will
be removed by oxidation through AOP treatment and by catalytic media (LayneOxTM)
and multi-media filtration units. Iron and other suspended solids that are removed by
the filters will be settled in the backwash tank (T-2000). Settled solids will be removed
from the backwash tank via vacuum truck and will be taken off-site for disposal as
needed.
Some of the process units in the existing ISR system will continue to be used in the
AOP treatment system and include the groundwater recovery wells (RW-2 through
RW-5), EQ tank (T-1500), AOP feed pump (P-1000), HiPOxTM system (AOP-200), filter
feed tanks (T-1400 and T-1600), vapor-phase granular activated carbon (VPGAC)
vessel (T-2200) and associated piping, valves and instrumentation. In addition, the
media filter vessels that are currently being used with LayneOxTM catalytic media, will
be used, but the media will be replaced with a multi-media consisting of gravel, coarse
garnet, fine garnet, and anthracite. This equipment has been discussed in previously
submitted reports; therefore, will only be briefly discussed in the following sections.
2.3.1.1 Potential Sodium Sulfite Addition during ISCO Implementation
It is anticipated that during the in-situ chemical oxidation (ISCO) injections performed in
the area south of Building E, sodium permanganate may be recovered by recovery well
RW-4. Sodium permanganate may adversely affect the oxidation process within the
HiPOxTM system by causing an increase in the hydrogen peroxide (H2O2) and ozone
(O3) demand. Also, additional manganese (from permanganate reactions) may cause
fouling within the treatment system.
Two contingency mechanisms will be used to evaluate and control the permanganate
in RW-4 so that the treatment system is not adversely affected. First, groundwater in
the vicinity of RW-4 and recovered by RW-4, will be monitored to evaluate the
permanganate concentrations. Second, if permanganate does get recovered from
RW-4, a sodium sulfite contactor will be installed on the RW-4 recovery piping to react
the permanganate.
Monitoring for permanganate will include periodic groundwater sampling at RW-4 and
an upgradient monitoring well during and following the permanganate injections.
Permanganate concentrations at the upgradient well will provide an early indication of
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 30
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
approaching permanganate levels to RW-4. If permanganate concentrations in
groundwater recovered at RW-4 exceeds 1 mg/L, then the sodium sulfite contactor will
be placed on the RW-4 recovery piping. Detailed information on groundwater
monitoring during ISCO injections can be found in the Groundwater Monitoring Plan
included in Appendix L.
Sodium sulfite is commonly used to neutralize chlorine in water treatment processes.
Chlorine is an oxidizer, like permanganate, and reacts in a similar manner. Sodium
sulfite will neutralize the permanganate according to the following theoretical chemical
reaction:
2MnO4- + 3SO3
-2 2MnO2 + 3SO4-2 + 2OH-
ARCADIS performed bench testing to verify the reaction and to confirm theoretical
molar and mass reaction ratios. This study was needed to evaluate the dosages of
sodium sulfite required at varying concentrations of permanganate. The bench test
results are provided in Tab #9. The results of the bench test confirmed that the sodium
sulfite neutralized the permanganate and reaction ratios were similar to the theoretical
values. As shown by this reaction, the molar relationship between permanganate and
sulfite is 2:3 and the mass ratio is 1.33 mg of sulfite per 1.0 mg of permanganate.
The sodium sulfite contactor installed on the RW-4 recovery piping will be filled with
sodium sulfite tablets. A slip stream from the groundwater recovery piping will direct
water into the contactor which will dissolve the sodium sulfite tablets. Sodium sulfite
solution will then be routed into the process flow stream. The concentration of sodium
sulfite will be controlled by adjusting the flow rate of process water through the
contactor. As the sodium sulfite tablets are dissolved, new tablets will be added.
Sodium sulfite usage will be based on the concentration of permanganate in the
recovered groundwater and the mass relationship noted above. Vendor specifications
and the sodium sulfite MSDS are included in Tab #9.
Based on the bench test results and professional judgment, the sodium sulfite
neutralization will be effective from 1 to greater than 1,000 mg/L of permanganate.
However, it is not desirable to exceed permanganate concentrations of 100 mg/L due
of the significant amounts of manganese that will be produced. Therefore, from
concentrations of 1 to 100 mg/L, the sodium sulfite contactors will be used to react the
permanganate. For permanganate concentrations exceeding 100 mg/L, extraction
from RW-4 will be discontinued until permanganate concentrations within the
groundwater surrounding RW-4 are naturally reduced.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 31
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.3.1.2 Influent Equalization Tank (T-1300)
The influent EQ tank (T-1300) will provide 18,000 gallons of useable storage capacity
for pre-treated process water flows from the AOP pre-treatment system. EQ tank (T-
1300) will provide approximately 150 minutes of residence time at the design flow rate
of 60 gpm (from the AOP pre-treatment system) and will have a minimum operating
capacity of 9,000 gallons. Process water from influent EQ tank (T-1300) will be treated
by AOP-100. A pump within the AOP-100 unit will transfer process water from the EQ
tank through the AOP process to the existing filter feed tank (T-1400).
EQ tank (T-1300) will be equipped with a pressure transducer to sense water level in
the tank and data will be transferred to the plant PLC. Water level set points will be
programmed into the control logic for the system so the PLC will control the speed of
the air stripper discharge pumps (P-400A/B) in the AOP pre-treatment system to
maintain a constant water level in the EQ tank. In addition, a redundant high/high float
switch will shut down the AOP treatment system and will disable transfer of pre-treated
process water from the AOP pre-treatment system when activated.
EQ tank (T-1300) will be a steel tank with two sealed top access hatches and smooth
interior walls for easy cleaning. The sizing of the EQ tank (T-1300) is presented in a
calculation included in Tab #10. The specifications are summarized below.
Item: Equalization Tank T-1300
Quantity: 1
Manufacturer: Baker Corp., or equal
Type: EZ Clean Fixed Axle Safety Vapor Frac Tank
Material: Carbon Steel with no interior coating
Working Volume: 18,000 gallons
Dimensions: 37-ft, 6-inches long by 8-ft, 6-inches wide by 11-ft, 2-inches high
2.3.1.3 Vapor-Phase Granular Activated Carbon (T-2300)
A passive vapor treatment system including VPGAC vessels will be used to absorb
constituents that may volatilize inside influent EQ tank (T-1300). Passive venting of
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 32
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
this tank will occur as the tank is filled and drained. A calculation was prepared to
estimate the amount of vapors and associated COC concentrations in the vapor
stream from the EQ tank (Tab #10). These will be the only air emissions associated
with the AOP treatment system. Based on the calculations, the air emissions from the
EQ tank is not anticipated to exceed vapor-phase treatment requirements. However,
VPGAC units (T-2300) will be used to prevent potential VOCs in the influent EQ tank
vapor stream from being released to the environment.
The vapor venting from the EQ tank will be treated using a single G-1S Carbtrol®
VPGAC vessel, or equal, containing 200 pounds of carbon and rated for a maximum
flow of 100 cubic feet per minute. The spent VPGAC will be replaced as required
according to air monitoring results; the estimated time for breakthrough is 285 days for
T-1300. A summary of calculations, vendor cut sheets and performance curves for the
VPGAC treatment unit are included in Tab #10.
2.3.1.4 Advanced Oxidation Process – HiPOxTM System (AOP-100)
Pre-treated process water accumulated in influent EQ tank (T-1300) will be transferred
to proposed HiPOxTM unit (AOP-100) by a transfer pump included in the HiPOxTM
system. The HiPOxTM system uses O3 and H2O2 chemistry within an oxidation reactor.
The reactants are injected directly into the water stream in precisely controlled ratios
and locations, generating hydroxyl radicals that attack the bonds in the organic
molecules, progressively oxidizing these compounds and any resulting intermediate
by-products until the basic atoms ultimately recombine into benign end-products of
carbon dioxide (CO2), water, and salts.
The HiPOxTM system is a proprietary system developed by APT, with fully constructed
modules. The process components include feed pumps, an H2O2 storage and delivery
system, oxygen generation and delivery system, an O3 generation and delivery
system, and a process cooling system for the O3 generators. Oxygen will be
generated on-site using vacuum swing absorption (VSA) process and fed into the O3
generator, which is subsequently injected into the reactor along with H2O2. The
treatment module will include plug-flow reactors, O3 and H2O2 injectors, and gas/liquid
separation system. The treatment system will include a caustic solution addition
system to improve the buffering capacity required for efficient treatment. Sodium
hydroxide (50 percent) will be added on the influent and effluent sides of the HiPOxTM
unit to provide pH control capabilities, if needed.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 33
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
The unit is configured with an integral PLC system which includes controls and sensors
to monitor performance. The control system will operate independently, but there will
be communication links between the HiPOxTM PLC and the main plant PLC to provide
a seamless control system for the AOP treatment system.
The vendor design basis summary, laboratory bench testing results and specifications
for the HiPOxTM unit are included in Tab #10, and are summarized below.
Item: Advanced Oxidation Process Unit AOP-100
Quantity: 1
Manufacturer: Applied Process Technology, Inc.
Type: HiPOxTM SRS Remediation System
Model: SRS-4.0-SS-100
No. Reactors: 4
Reactor Size and Materials:
Nominal 4-inch diameter, stainless steel
Max Flow Range: 1 – 150 gpm
Design Flow Rate: 60 gpm
Ozone Generation Capacity:
100 pounds per day
2.3.1.5 Existing Advanced Oxidation Process – HiPOxTM System (AOP-200)
The AOP-200 HiPOxTM system supplied by APT is currently in operation at the ISR
system treating a process flow rate of 32 gpm. This HiPOxTM unit (AOP-100) has been
treating recovered groundwater at the Site for more than 12 months, and has
consistently met discharge requirements. The operational experience with the ISR unit
has provided information for the development of destruction curves and models for
influent concentrations reported at the Site. These models have been taken into
consideration for the design of the HiPOxTM unit (AOP-200) discussed above.
The oxidation process components of the AOP-200 unit include an H2O2 storage and
delivery system, liquid oxygen storage and delivery system, O3 generation and delivery
system, integrated control system, and process cooling system for the ozone
generators. As the water enters the process, pH and alkalinity are adjusted to the
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 34
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
desired range prior to entering the oxidation reactor. Liquid oxygen is vaporized and
fed into the O3 generator, which is subsequently injected into the reactor along with
H2O2 in precisely controlled ratios and locations in the reactor. The system is
configured with controls and sensors to monitor system performance.
2.3.1.6 Filter Feed Tanks (T-1400 and T-1600)
The existing filter feed tanks (T-1400 and T-1600) receive discharge water from the
AOP-200 HiPOxTM unit. During AOP treatment system operation, system piping will be
reconfigured so that filter feed tank (T-1600) will receive flow from the AOP-200
HiPOxTM unit and filter feed tank (T-1400) will receive flow from the AOP-100 HiPOxTM
unit. Process water from the filter feed tanks will be pumped through the catalytic
media filters, multi-media filters and LPGAC vessels by filter feed pumps (P-1100A/B).
The filter feed tanks will be equipped with pressure transducers to sense water level in
the tanks and data is transferred to the plant PLC. Water level set points were
programmed into the control logic for the system so the PLC will control the speed of
the filter feed pumps (P-200A/B) to maintain a constant water level in the filter feed
tanks. In addition, a redundant high/high float switch will shut down the AOP treatment
system when activated.
2.3.1.7 Filter Feed Pumps (P-1100A/B)
The water from the existing filter feed tanks (T-1400 and T-1600) will be pumped by
filter feed pumps (P-1100A/B) through the catalytic media filters, multi-media filters,
LPGAC vessels and the approximately 2,400 ft distance to the City’s POTW
connection. Two pumps will be provided with one pump operating continuously and the
other pump in standby. The filter feed pumps will be used in the full-scale treatment
system, following discontinuation of modified ISR system operation; therefore, they
have been designed to operate at the maximum full-scale system design flow rate of
146 gpm, but will be operated using VFDs to provide sufficient turn-down capacity to
operate at 92 gpm when used in the modified ISR system. The pump motors and
VFDs will be controlled by the plant PLC that will receive water level data from the filter
feed tanks (T-1400 and T-1600).
The pump head loss calculations and performance curves are presented in Tab #11.
The pump specification sheets are presented in Tab #3. The specifications for the filter
feed pumps are provided below.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 35
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Item: Filter Feed Pumps P-1100A/B
Manufacturer: Gould’s, or equal
Quantity: 2
Model: 3196 STi
Type: End Suction Centrifugal
Size: 2x3-8; 6.375-inch impeller
Seal: Single mechanical seal
Horsepower and Power Requirement:
15 HP, 3560 RPM, 230/460/3/60 TEFC
Design Flow Rate and TDH:
92 gpm @ 180 ft TDH
2.3.1.8 Backwash Pump (P-1200)
Backwash pump (P-1200) will pump water from the filter feed tanks (T-1400 and T-
1600) through the catalytic media filters (T-1700A/B/C) or the multi-media filters (T-
1800A/B) to the backwash tank (T-2000). Only one set of filters will be backwashed at
a time. The filter feed tanks will be the source of backwash water for the both filter
backwash cycles. The filter feed pumps (P-1100A/B) will be shut-down during the
backwash cycle. The backwash sequence for the catalytic media filters will include a
phase of combined air at 38 SCFM and water at 63 gpm, followed by a water only
backwash at 188 gpm. The required backwash flow rate for the multi-media filter is
106 gpm. Total backwash volume will be 4,710 gallons for the catalytic media filter
backwash cycle and 1,480 gallons for the multi-media filter backwash cycle. Each
backwash will be completed using treated process water; therefore, the solids removed
by filters should generally be free of VOCs.
The backwash pump will be used in the full-scale system following discontinuation of
AOP treatment system operation; therefore, has been designed to operate at the
design backwash rate of 188 gpm. The pump motor will be operated using a VFD
controlled by the plant PLC that will receive water level data from the filter feed tanks
(T-1400 and T-1600). The VFD will allow for maximum flow and pressure control, and
will allow adjustments to be made during each application.
The pump head loss calculations and performance curves are presented in Tab #11.
The pump specification sheets are presented in Tab #3. The backwash pump
specifications are provided below.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 36
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Item: Backwash Pump P-1200
Manufacturer: Gould’s, or equal
Quantity: 1
Model: 3196 STi
Type: End Suction Centrifugal
Size: 2x3-8; 6.5-inch impeller
Seal: Single mechanical seal
Horsepower and Power Requirement:
15 HP, 3000 RPM, 230/460/3/60 TEFC
Design Flow Rate and TDH:
190 gpm @ 160 ft TDH
2.3.1.9 Catalytic Media Filters - LayneOxTM (T-1700A/B/C)
Following AOP treatment through the HiPOxTM systems, water will be pumped through
a catalytic media filter package that will include three vessels filled with LayneOxTM
granular filter media. LayneOxTM operates both as a classic filter and as a catalytic
media, converting ferrous iron (Fe+2) to ferric iron (Fe+3), and accelerating the
precipitation and adsorption of the particles. Although the retention time in the
HiPOxTM reactor will be sufficient to complete oxidation of iron through AOP treatment,
iron that is not oxidized will become catalytically precipitated and then adsorbed
directly onto the LayneOxTM media. The H2O2 residual from the HiPOxTM unit will work
as the oxidant needed to continuously regenerate and replenish the media. The
specifications and MSDS for the LayneOxTM media are included in Tab #11.
The filters are designed for the full-scale treatment design flow of 146 gpm and the
filtration performance will not be affected by lower flow rates that will occur during
operation of the AOP treatment system. The catalytic media filter unit will include three
4-foot diameter carbon steel vessels (T-1700A/B/C) in a pre-packaged skid with an
internal control system. The selected vessels will provide a minimum bed depth of 36
inches, and a media contact time of approximately 5.8 minutes. The removed particles
and adsorbed iron will be expelled during backwash. The backwash frequency of the
LayneOxTM media is anticipated to be once per day when the differential pressure
across the filters is approximately 10 psi. The backwash procedures will include a
combined air scour and water phase, followed by a water only phase. Backwashing
with combined air and water will allow the use of lower backwash rates, reducing the
generated backwash volumes. Treated process water will be used as the source of
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 37
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
water for backwashing. The calculation for the catalytic media filter sizing, backwash
requirements, and vendor cut sheets are presented in Tab #11. Specifications are
provided below.
Item: Catalytic Media Filters T-400A/B/C
Manufacturer: Yardney, or equal
Model: MM-4860-3AS, complete skid mounted
Type: 3-vessel filtration system with manifolded influent, effluent and backwash piping; and automated valves
Service Flow Rates: Nominal flow range 189-567 gpm; max flow rate 756 gpm
Design Flow Rate: 146 gpm
Backwash Flow Rate: 63 gpm and 188 gpm water;
38 scfm air scour
Max Pressure: 80 psi
Material: Epoxy-coated steel
Vessel Dimensions: 48-inch diameter by 60-inch side shell height
2.3.1.10 Multi-Media Filters (T-1800A/B)
A multi-media filtration system (T-1800A/B) is currently being used in the existing ISR
system operation. The vessels currently contain LayneOxTM media, which will be
switched out for a multi-media consisting of gravel, coarse garnet, fine garnet, and
anthracite. The filters will be used for back-up filtration of iron particulates and
suspended solids that may break-through the upstream catalytic media filters. The
multi-media filters are going to be used to protect the LPGAC vessels from fouling.
Multi-media filters were selected for their good filtration performance (consistent
removal of particles 5 microns in size or greater) and ability to handle the design flow
rate 92 gpm.
The multi-media filter package includes two 30-inch diameter vessels in a pre-
packaged skid with an internal control system supplied by Yardney. During normal
AOP treatment system operation, both vessels will operate continuously in parallel. To
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 38
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
prevent clogging, the filters will be backwashed when the differential pressure across
the filters is approximately 15 to 20 psi. Backwash frequency is anticipated to be once
every three days, and treated process water will be used as the source of water for
backwashing. Calculations for multi-media filter sizing, backwash requirements, and
vendor cut sheets are presented in Tab #11. Specifications are provided below.
Item: Multi-Media Filters T-1800A/B
Manufacturer: Yardney, or equal
Model: MM-3060-2AS
Type: 2-vessel filtration system with manifolded influent, effluent and backwash piping; and automated valves
Service Flow Rate: Nominal flow range 50-147 gpm; max flow rate 196 gpm
Backwash Flow Rate: 74 gpm
Max Pressure: 100 psi
Material: Epoxy-coated steel
Vessel Dimensions: 30-inch diameter by 60-inch side shell height
2.3.1.11 Backwash Tank (T-2000)
The backwash tank (T-2000) will receive backwash water from the catalytic media
filters (T-1700A/B/C) and multi-media filters (T-1800A/B/C). The backwash tank will
provide 18,000 gallons of usable storage capacity. This will be a sufficient volume to
handle daily backwash events plus 21-days of solids storage capacity. Backwash
solids from the catalytic media and multi-media filters will be allowed to settle between
backwash cycles. The catalytic media filters will be backwashed daily, while the multi-
media filter backwash cycle is estimated to be approximately once every 3 days. Prior
to the backwash sequence, the supernatant within the tank will be decanted to the
influent EQ tank (T-1300). Sufficient volume will be decanted to provide room to
accept water from the new backwash cycle. Each backwash cycle for the catalytic
media and multi-media filters results in 4,170 and 1,480 gallons of backwash solids to
the backwash tank, respectively. This cycle of backwashing, settling and decanting will
continue until solids build up in the bottom of the tank. At this time, the system will be
shutdown and the solids will be removed and taken off-site for disposal.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 39
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
The backwash tank will be equipped with a pressure transducer to sense water level in
the tank and data will be transferred to the plant PLC. In addition, a redundant
high/high float switch will shut down the AOP treatment system when activated.
The backwash tank will be a steel tank with two sealed top access hatches and smooth
interior walls for easy cleaning. The sizing of the backwash tank is presented in a
calculation included in Tab #11. The specifications are summarized below.
Item: Backwash tank T-2000
Quantity: 1
Manufacturer: Baker Corp., or equal
Type: EZ Clean Fixed Axle Safety Vapor Frac Tank
Material: Carbon Steel with no interior coating
Volume: 18,000 gallons
Dimensions: 37-ft, 6-inches long by 8-ft, 6-inches wide by 11-ft, 2-inches high
2.3.1.12 Decant Pump (P-1300)
The decant pump (P-1300) will pump water from the backwash tank (T-2000) to the
influent EQ tank (T-1300). One backwash cycle storage volume (4,170 gallons or
1,480 gallons for catalytic media and multi-media filter backwash cycles, respectively)
will be decanted prior to each new backwash cycle. The decant pump has been
designed to decant the required volume of supernatant in approximately 4 hours. The
pump motor will be operated using a VFD controlled by the plant PLC that will receive
water level data from the existing filter feed tanks (T-1400 and T-1600) and the
backwash tank (T-2000). The VFD will allow for maximum flow and pressure control,
and will allow adjustments to be made during each application.
The pump head loss calculations, vendor cut sheet, and performance curves are
presented in Tab #11. The decant pump specifications are provided below.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 40
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Item: Decant Pump P-1300
Manufacturer: Gould’s, or equal
Quantity: 1
Model: 1SC51C-F
Type: Submersible
Size: 1.25-inch discharge; 3 stage
Horsepower and Power Requirement:
1/2 HP, 3450 RPM, 115/1/60 TEFC
Design Flow Rate and TDH:
30 gpm @ 43 ft TDH
2.3.1.13 Polymer Injection System (T-2100, P-1400 and SM-300)
During the catalytic media and multi-media filter backwash sequences polymer will be
added to the water stream to promote the formation of larger and heavier particles that
will aid in settling. The polymer injection system will include a storage tank (T-2100),
chemical metering pump (P-1400) and an in-line static mixer (SM-300). Based on jar
testing completed during operation of the existing ISR system, the selected polymer is
PolyFloc AS1002 which will be metered at a dosage rate of 15 ppm. The MSDS and
fact sheet for the PolyFloc are included in Tab #11.
The polymer will be supplied by the vendor in a 5-gallon bucket that is expected to last
approximately 6 months based on the calculated usage rate of 0.56 gallons per week.
The polymer metering pump (P-1400) will inject polymer into an injection port in the in-
line static mixer (SM-300) which will provide rapid mixing of the injected polymer. The
static mixer will be a 4-inch diameter, schedule 40 carbon steel unit containing six
mixing elements.
A summary of polymer usage rates and volumes, and vendor cut sheets are presented
in Tab #11. Polymer metering pump and static mixer specifications are provided
below.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 41
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Item: Polymer Metering Pump P-400
Manufacturer: LMI, or equal
Model: AA-971-352HI
Max Pumping Rate and Pressure:
10 gpd (27 mL/min) @ 140 psi
Design Flow Range: 3.6 – 10.7 mL/min
Item: Static Mixer SM-300
Manufacturer: Koflo, or equal
Model: Series 275
Type: Low pressure loss, flange mounted mixer with FNPT injection port
Size: 4-inch
2.3.1.14 Liquid-Phase Granular Activated Carbon Adsorption (T-1900A/B/C)
Following catalytic media and multi-media filtration, water will be pumped through a
series of two LPGAC vessels for polishing treatment. The HiPOxTM systems (AOP-100
and AOP-200) are designed to reduce COC concentrations to meet the required
effluent concentrations in accordance with discharge limit requirements. Therefore, the
contaminant loading on the LPGAC vessels will be minimal. The LPGAC vessels will
provide an additional polishing treatment step to provide a factor of safety against
unintended discharges of VOCs.
The LPGAC module will include three 72-inch diameter vessels, containing 2,500
pounds of acid-washed coconut carbon each. During normal operation, two vessels
will be on-line (lead and lag configuration) with one vessel on stand-by. The selected
LPGAC module is a skid-mounted, fully piped unit that allows the flow to be switched
between the vessels.
As the useful life of the carbon is reached, it will be scheduled for change-out. In the
event that process monitoring results indicate that compounds are breaking through
the lead vessel, the vessel will be taken out of service and replaced with a new unit
(stand-by vessel). The estimated time for breakthrough is 85 days (Tab #12);
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 42
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
however, other factors besides VOC loading may contribute to the carbon adsorber life
including bio-fouling and scaling. These factors will result in pressure build up across
the LPGAC vessel. When the flow rate through the LPGAC vessel drops below the
required level due to pressure build up, the vessel will be changed out with a new unit.
The spent LPGAC will be taken off-site for proper regeneration or disposal.
The calculation for the sizing of the LPGAC module and vendor cut sheets are
provided in Tab #12. Specifications are provided below.
Item: LPGAC Vessels T-1900A/B/C
Manufacturer: Yardney, or equal
Model: LPGAC 7272-3MS, complete skid mounted
Type: 3-vessel system with manifolded influent, effluent and backwash piping; and manual valves
Max Pressure: 80 psi
Material: Epoxy-coated steel
2.3.2 Discharge of Treated Water
Recovered groundwater from the existing ISR recovery wells and the AOP pre-
treatment system will be treated via air stripping, AOP technology, subsequent catalytic
and multi-media filtration, and final carbon polishing. Following treatment through the
LPGAC system, the water will be discharged to the City’s POTW under an IWDP.
Currently, the treated process water from the existing ISR system is discharged to the
City’s POTW through an on-Site connection under IWDP # SPFL-562910-SIU-08-112.
The existing sewer discharge location does not have sufficient hydraulic capacity for
the modified ISR system; therefore, a new discharge location will be established. A
new 6-inch diameter underground pipeline will be routed north along 72nd Street from
the AOP treatment system and will tie-in to an existing gravity pipeline located on 22nd
Avenue. In addition, the permit is expected to be increased to 100 gpm to
accommodate the increased flow rate from the modified ISR system. The City has
tentatively approved this modification which is discussed in a letter included in
Appendix A.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 43
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.4 Modified ISR System General Arrangement
The general arrangement layout for both the AOP pre-treatment and AOP treatment
systems will be located as shown on Figures J-12 and J-13, Tab #13. Each layout
illustrates the general arrangement of process equipment and control panels for the
treatment systems. The AOP pre-treatment system will be housed inside Building M
and will be situated near the in-situ thermal system. The AOP treatment system will be
placed outdoors, on the parking lot on the south end of Building E. Equipment for the
AOP treatment system will be specified consistent with outdoor use and will be
properly grounded.
2.4.1 Containment Curb
A 9-inch high containment curb will be provided around the perimeter of the AOP pre-
treatment system. The containment berm walls and bottom of containment area will be
sealed with a concrete floor sealer. A 9-inch high containment curb will be provided
around the perimeter of the AOP treatment system. The containment berm walls and
bottom of containment area will be sealed with an asphalt sealant. The purpose of the
containment curbs is to contain any water that leaks from process piping or tank
rupture. A calculation is provided in Tab #14 that determines the required and actual
containment volume for each system.
2.4.2 Floor Sumps and Pumps
One floor sump equipped with a sump pump will be provided for each treatment
system and will be installed within the containment area. The sumps will be
approximately 2.5 ft wide by 2.5 ft long by 2 ft deep. Each floor sump will be sealed to
prevent infiltration of spills through the asphalt or concrete slab. Water collected in the
AOP pre-treatment system floor sump will be pumped using sump pump (P-800) to
influent EQ tank (P-200A) to be processed through the system. In addition, water
collected in the AOP treatment system floor sump will be pumped using sump pump
(P-1500) to the influent EQ tank (T-1500) for processing.
2.5 Modified ISR System Support Equipment
The support equipment needed for operation of the treatment system includes air
compressors and eyewash/safety showers. The following sections present the details
for these treatment components.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 44
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.5.1 Air Compressors (A-100 and A-200)
Air compressor (A-100) will be installed in the AOP pre-treatment system to provide
compressed air for instrument air and pneumatic valve operation. The air compressor
has been designed to operate to provide sufficient pressure to operate the
instrumentation and valves as necessary.
Air compressor (A-200) will be installed in the AOP treatment system to provide
compressed air to the catalytic media filters as part of the backwash sequence. The air
compressor was sized to provide 38 scfm of air flow to the catalytic media filters to
promote scouring of the media and optimize the backwash cycle. The air compressor
has been designed to operate at the design air flow rate and provide sufficient pressure
to push air through the catalytic media.
The air compressor inlet and discharge lines will be equipped with pressure indicators
to sense pressure in the piping and data will be transferred to the plant PLC. Pressure
set points will be programmed into the control logic for the system so the PLC will
automatically operate the air compressors (A-100 and A-200), as part of compressor
cycle operations.
The air compressor vendor cut sheets and performance curves are presented in Tab
#15. The specifications for the compressor are provided below.
Item: Air Compressor A-100
Manufacturer: Atlas-Copco, or equal
Quantity: 1
Model: SF 1
Type: Oil free, scroll compressor
Horsepower and Power Requirement:
2 HP, 230/460/3/60
Design Flow Rate and Pressure:
5.7 scfm @ 116 psi
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 45
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Item: Air Compressor A-200
Manufacturer: Atlas-Copco, or equal
Quantity: 1
Model: SF 11
Type: Oil free, scroll compressor
Horsepower and Power Requirement:
15 HP, 230/460/3/60
Design Flow Rate and Pressure:
42.8 scfm @ 116 psi
2.5.2 Safety Showers
Two eyewash/safety shower units will be installed in the modified ISR system; one
within the AOP pre-treatment system area and the other in the AOP treatment system
area. Potable water will be provided to each safety shower.
2.5.3 Treatment System Control and Interconnections
Operation of the modified ISR system includes the operation and process control of
three interconnected treatment systems including the in-situ thermal system, the AOP
pre-treatment system, and the AOP treatment system. These three systems are
interconnected by water and vapor piping, in addition to process control
communications. The treatment system piping and process control interconnections
are discussed below.
2.5.3.1 Process Piping Interconnections
The process piping interconnections between the in-situ thermal, AOP pre-treatment,
and AOP treatment systems are described below.
1. Piping routed from the in-situ thermal system to the AOP pre-treatment system
includes:
Process water (maximum flow of 60 gpm from multi-phase extraction wells
and condensate);
Chilled water feed to the heat exchangers (80 gpm at 40 oF); and
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 46
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
Blow-down water (a total of 3-8 gpm from the air scrubber, water softener, and other miscellaneous blow-down ports in the in-situ thermal system).
2. Piping routed from the AOP pre-treatment system to the in-situ thermal system:
Air strippers vapors (approximately 900 SCFM);
Tank vent vapors (approximately 70 SCFM); and
Chilled water return from heat exchangers (80 gpm at 85oF).
3. Piping routed from the AOP pre-treatment system to the AOP treatment system:
Process water (maximum flow of 60 gpm from multi-phase extraction wells
and condensate pre-treated through AOP pre-treatment system); and
Blow-down water (a total of 3-8 gpm from the air scrubber, water softener, and other miscellaneous blow-down ports in the in-situ thermal system treated through LPGAC).
2.5.3.2 Programmable Logic Controllers and Control Interconnections
The in-situ thermal, AOP pre-treatment, and AOP treatment systems are operated
using independent control systems. Each system is controlled using individual PLCs.
The PLC includes a program or set of detailed instructions for operation of the
treatment system. The function of the PLC is to automate the operation and
monitoring of the treatment process. Some examples of the PLC functions include:
• Receiving and recording process data including
– Tank water levels;
– Motor speeds;
– Alarm conditions;
– System operating time; and
– Temperature and pressure within the various process units and piping.
• Controlling the speed of pumps or blowers in the system
• Shut down portions or all of the treatment system during alarm conditions
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 47
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
• Phone (or text message) the plant operators for maintenance reminders and/or
notification of an alarm indication or plant shutdown
• Provide the ability to remotely monitor the plant and/or trouble shoot problems
when they arise
Each PLC will control and monitor the operation of the treatment system. Since the
three treatment systems are interconnected, it is necessary for the three individual
PLCs to be able to communicate. For example, if one system is automatically shut
down by the PLC, notifications to the other treatment system PLCs and/or operators
are necessary so that the other systems adjust operations for changing conditions.
Each system will have the ability to send and receive status signals (status – plant is
on, plant is off) between the other system PLCs. Specific details on the type of signals
and the response to the signals are discussed in the control logic table presented in
Tables J-5 and J-6, Tab #16.
The PLC for each treatment system will be located within the control panels associated
with each system. Control wiring between the three PLCs will be installed to allow
these communications mechanisms.
2.5.4 Modified ISR System Piping and Instrumentation
As discussed in previous sections, the PID for the modified ISR system is provided on
Figures J-4 through J-11, Tab #2. Piping details are presented in the PID, which
includes the general orientation of piping, pipe sizes, pipe materials, and pipe fittings.
Further discussions on treatment system piping and process and instrumentation
details are presented below.
2.5.4.1 Treatment System Piping
Most process and vent piping used in the modified ISR will be painted schedule 40
carbon steel, appropriately sized for specific design flow rates of individual process
lines. In general, pipes will be sized to maintain flow velocities in the range of 2 – 5 feet
per second (ft/sec). Velocities within this range will prevent solids deposition in the
pipe lines and avoid water hammer that may be caused at higher velocities. The
piping within the plant will be well supported and fastened according to manufacturer
recommendations. Other pipe materials may be used (including polyvinyl chloride
[PVC], chlorinated PVC, tubing, stainless steel, and/or hose) for secondary process
streams and chemical metering. In areas that are prone to vibration and/or heat, such
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 48
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
as at the inlet and outlet connections of pumps, braided steel flexible connections will
be used to reduce wear on pumps and prevent damage to piping joints. The piping
materials will be compatible with the conditions present in the modified ISR system.
2.5.4.2 Process and Instrumentation
The modified ISR system has been designed to run continuously. The instrumentation
and control logic for the treatment system is summarized in Tables J-5 and J-6, Tab
#16. The location of various instrumentation components is shown on the PIDs
included in Tab #2. The PLC system will monitor key treatment system parameters
that will include pressure of the influent groundwater recovery piping (for pipeline
break); influent and post-process tank water levels; containment levels; multiple system
alarms for treatment equipment including the air strippers, AOP treatment systems,
catalytic media filters, multi-media filters and LPGAC; pump operation; effluent flow
rates and pH levels. The control scheme for the modified ISR system includes
redundant control devices in critical control features such as tank water level alarms to
prevent tank overflows.
The system parameters and alarms will be able to be remotely monitored via
computer-to-computer software such as PCAnywhere. This will allow treatment
system operation to be monitored off-site, remote diagnosis of alarm conditions, and
remote system shut down, as necessary. When operating parameters are out of the
operation range, the modified ISR system will automatically shut down and the
monitoring system will notify on-call personnel by text message and email. The system
will not be re-started from a remote location; plant startup will only be conducted by an
operator located at the facility.
Flow meters and/or totalizers will be placed throughout the AOP pre-treatment and
AOP treatment systems to monitor and record process flow rates. Flow meters in the
AOP pre-treatment system will be placed on the scrubber blow-down LPGAC effluent
line, multi-media filter influent line, multi-media filter backwash line and system effluent
line. Flow meters in the AOP treatment system will be placed on each recovery well,
the catalytic media filter influent line, filter backwash line, and at the discharge line to
the POTW. This will enable quantification of water processed through the AOP unit,
and treated water discharged to the POTW.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 49
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.5.4.3 Modified ISR System Sampling Ports
Sampling ports will be located in the system process lines so that the performance of
the AOP pre-treatment and AOP treatment systems can be monitored. Sample port
locations within the modified ISR system are detailed in Table J-7, Tab #17. The
Operation and Maintenance Plan (O&M), which is discussed in subsequent sections,
will provide additional details regarding AOP pre-treatment and AOP treatment system
sampling and analysis.
2.5.5 Chemical Handling and Storage
The chemicals used throughout the modified ISR system include 50 percent sodium
hydroxide, 25 percent H2O2, ozone gas (generated on-Site), liquid/gaseous oxygen
and PolyFloc flocculent polymer. The 50 percent sodium hydroxide will be utilized for
pH adjustment will be stored in a 275-gallon tank (T-1000) in the AOP pre-treatment
system. An 800-gallon tank will be used for storage of 25 percent H2O2, which will be
included with the HiPOxTM system equipment in the AOP treatment system. These
chemical storage tanks will have individual secondary containment to prevent the
spread of potentially leaked chemicals. The secondary containment vessels will be
inspected daily for signs of damage, weakening, or leakage. Appropriate physical
separation will be provided to prevent reactivity between chemicals or their containers
should a leak in any container occur.
The HiPOxTM system uses oxygen to generate ozone. Oxygen will be generated on-
Site using VSA process for the AOP-100 unit, and liquid oxygen will continue to be
used for the AOP-200 unit as discussed in previous sections. Secondary containment
for this equipment is not required for gases. Similarly, the PolyFloc AS1002 does not
require secondary containment; however, spilled polymer may be slippery resulting in a
health and safety concern. Small amounts of spilled polymer will be wiped up and
washed down with copious amounts of water. A large spill will be contained and
absorbed on inert material, then disposed as solid waste, prior to flushing with water.
Chemicals will be delivered to the Site as needed. As chemicals are delivered, they
will be transferred to the on-line process tanks. A Best Management Practices Plan
(BMPP) has been developed for the RAPA and is included in Appendix M. The
document provides further information on handling and storage of the chemicals
needed for the treatment process.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 50
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.5.6 Air Emissions
In the AOP pre-treatment system, air emissions are associated with the influent EQ
tanks (T-200A/B/C), the aeration tank (T-300), the filter feed tank (T-400), the
backwash tank (T-800) and the air strippers (T-600A/B). These emissions will be
treated by the in-situ thermal system to destroy any COCs in the vapor prior to
discharge to the atmosphere. An estimate of air emissions from the AOP pre-
treatment system is summarized in Tab #18.
Air emissions from the AOP treatment system are primarily associated with the EQ
tanks (T-1300 and T-1500). These emissions will be treated by VPGAC to capture any
COCs in the vapor prior to discharge to the atmosphere. An estimate of air emissions
from the AOP treatment system is summarized in the VPGAC calculations provided in
Tab #10.
2.5.7 Utility Requirements
Utility requirements for the modified ISR system will be potable water, electricity,
telephone and POTW discharge.
2.5.7.1 Electricity
Electric power for the modified ISR system will be used to operate all motors, controls,
lighting and other electrical devices required at the treatment facility. Power
requirements will be three-phase 460 volt power is anticipated to be used. An
electrical load calculation is presented in Tab #19; the anticipated electrical load for the
AOP pre-treatment and AOP treatment systems is approximately 65 kilovolt-ampere
(KVA) and 95 KVA, respectively.
2.5.7.2 Water
Water will be required for general system maintenance, initial treatment plant filling and
hydraulic testing, and some process make-up water. Adequate potable water service
to the Site exists.
2.6 Operation and Maintenance Plan
The proposed PFDs for the Modified ISR system are shown on Figures J-2 and J-3,
Tab #1. The PID is presented on Figures J-4 through J-11, Tab #2. The AOP pre-
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 51
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
treatment and AOP treatment systems have been designed to run on a continuous
basis; however, prior to continuous operation the modified ISR system will be started-
up and tested for performance optimization. To promote proper operation of the
system, O&M activities described in this section will be conducted.
2.6.1 Pre-Start-Up Inspection
Pre-start-up activities will be conducted to test mechanical and electrical functionality of
unit processes, system controls, and fail-safe mechanisms. These activities will
include inspection of the system installation when it is mechanically and electrically
complete to verify that it meets installation specifications. A clean water test will be
completed to verify that the tanks and piping system are leak-free.
The modified ISR system equipment, control panels, level switches, fail-safe
mechanisms, and alarms will be tested and verified to confirm appropriate operation
and correct response of the PLC. The sensors will be manually triggered to confirm
the correct response and activities will be recorded in pre-start-up inspection and alarm
checklists developed prior to start-up.
2.6.2 System Start-Up
Following the installation inspection and equipment check, the start-up procedure will
be initiated. System start-up activities will be conducted to test and optimize system
performance. Start-up procedures are described in the subsequent sections.
2.6.2.1 Start-Up Operation
Based on the performance of the existing ISR system, it has been determined that the
current operating settings for the HiPOxTM unit are consistently effective in treating
groundwater extracted from the existing ISR recovery wells (RW-2 through RW-5) to
the discharge standards established by the City, and to levels below the applicable
groundwater cleanup target levels (GCTLs) specified in Chapter 62-777 Florida
Administrative Code (F.A.C.). Therefore, start-up operation of the current AOP unit
(AOP-200) is not warranted. The ISR recovery wells and associated HiPOxTM unit will
be operated in continuous mode while the remaining modified ISR system equipment
is under-going start-up testing.
Start-up procedures will be implemented for the AOP pre-treatment system and the
HiPOxTM unit (AOP-100). During the start-up operation, the influent for the AOP pre-
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 52
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
treatment system will consist of groundwater recovered during the start-up period of
the in-situ thermal system (refer to Appendix I). The recovered groundwater will be
discharged into the heat exchanger feed tank (T-100) and treated through the AOP
pre-treatment process prior to being routed to the AOP treatment system. An initial
range of O3 and H2O2 dosage conditions for the AOP-100 unit will be pre-determined
based on ISR operational experience and bench testing results. The chemical
dosages within the pre-determined range will be evaluated to optimize AOP-100
operating parameters, with analytical samples collected for each condition.
The treated effluent of the AOP-100 unit will be containerized in the filter feed tank (T-
1400) pending laboratory analysis. Effluent COC concentrations will be verified to be
below permitted discharge levels prior to combining the treated effluent of both AOP
units for POTW discharge. In the event that laboratory analytical results indicate that
IWDP requirements are not met for the AOP-100 treated effluent; the water will be
pumped back to the influent equalization tank (T-1300) for re-processing. Adjustments
will be made to the AOP-100 settings as necessary. This procedure will be repeated
until effluent analytical results are below discharge permit criteria.
The start-up period is expected to last approximately two weeks; however, the
schedule may be adjusted based on field experience and system performance. The
start-up period will provide information to define the AOP pre-treatment system and
AOP-100 unit operating settings for continuous operation.
2.6.2.2 Level of Monitoring
The start-up monitoring program for the AOP pre-treatment system and AOP-100 unit
is summarized in Table J-8, Tab #20. Samples will be collected throughout the
treatment process to obtain data required to evaluate system performance. The
samples will be placed in iced coolers and delivered to a certified laboratory to be
analyzed on an expedited turnaround-time (24 to 48 hours).
Laboratory analytical results for the different operating settings will be evaluated to
optimize system performance. When laboratory analytical results for the effluent
samples indicate that concentrations of target constituents are in compliance, the
treated water will be discharged to the POTW and samples will be collected during
discharge in accordance with the IWDP.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 53
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.6.3 System Proof of Performance Testing
The results of the start-up operation will provide information to define the operating
parameters for continuous operation of the AOP pre-treatment system and the
operating settings for the AOP-100 unit. During the system proof of performance
testing, the capability of the treatment process to consistently treat recovered
groundwater from the in-situ thermal system will be verified. Based on the results of
the performance testing, reaction rates will be estimated for the AOP process. System
proof of performance procedures are described in the following sections.
2.6.3.1 Performance Testing
Based on start-up results, operating parameters will be selected and tested in batch
mode to confirm output conditions. Three consecutive batches will be completed using
the selected operating settings to confirm compliance with the discharge permit
requirements. During the confirmatory batches, AOP pre-treatment system operation
will be consistent with the start-up period.
In compliance with discharge protocols, treated water will be discharged after
laboratory analysis confirms that the water has been successfully treated to the
discharge standards established by the IWDP. This testing period is expected to last
approximately two weeks, although the schedule may be adjusted based on field
experience and system performance.
2.6.3.2 Level of Monitoring
The same level of monitoring and effluent disposal protocol associated with the start-up
operation will be maintained during the proof of performance period.
2.6.4 System Continuous Operation
At the completion of the proof of performance testing, the modified ISR system will be
considered ready for continuous operation and discharge to the POTW. When
compliance is verified, the AOP pre-treatment system and AOP-100 unit will be
operated in continuous mode using the confirmed operating parameters, in conjunction
with the previously established continuous operation of the AOP-200 unit and ISR
recovery well network.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 54
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.6.4.1 Level of Monitoring
The modified ISR system treated water discharge samples will be collected in
accordance with Rule 62-780.700(3)(g), F.A.C. and the IWDP requirements. In
addition, operational samples will also be collected to evaluate the performance of the
AOP pre-treatment system and the AOP units. Sampling location, analysis, and
frequencies are further discussed in Section 2.8.1 – Treatment System Process
Monitoring.
The alarms and system operation will be accessible by remote telemetry using the
treatment system computer and PCAnywhere software. System shutdown will result in
activation of the system auto dialer, which will be used to alert pre-designated
personnel by text message and/or email. The PLC, treatment system computer, and
PCAnywhere software will be used to remotely investigate, identify necessary action,
and document alarm conditions that occur.
2.6.4.2 Operational Optimization
The modified ISR system has been designed to handle variations in influent
concentrations and flow rates. Based on data obtained during operation of the existing
ISR system, the modified ISR system is expected to be effective in containing affected
groundwater and removing COCs from the water prior to discharge to the City POTW.
The process monitoring program discussed in Section 2.8.1. includes collection of
samples from the influent to AOP-100 to monitor the incoming conditions for the
treatment unit. Adjustments to the operating conditions will be performed based on the
monitoring results and the established reaction rates for the HiPOxTM unit.
2.6.5 Maintenance Activities
Two full-time operators and support staff, as needed, will operate the modified ISR
treatment system. The operators will be responsible for maintaining records
throughout the operation of the treatment systems to verify performance and document
proper O&M. The O&M activities performed on the AOP pre-treatment and AOP
treatment system components will be documented on appropriate O&M Field Logs.
The operator will be responsible for performing and documenting preventative
maintenance tasks on treatment system components and safety controls. A managing
engineer will oversee operation of the system. Copies of the O&M Manuals provided
by the equipment manufacturers will be stored at the treatment system, and a separate
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 55
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
treatment system O&M Manual will be developed as part of the design documents. A
supply of expendables and tools will be maintained on-Site for O&M purposes.
2.6.5.1 Routine Operation and Maintenance
Operating personnel will perform routine O&M activities on a daily basis during the
start-up operation and proof of performance period. During continuous operation, the
routine O&M activities will be conducted daily for the first five days and then reduced to
at least two times a week. The following practices will be considered routine O&M
activities:
AOP Pre-Treatment System
• Visually inspect tanks and piping for leaks and integrity.
• Inspect heat exchangers and record operating temperatures.
• Observe treatment system blowers and process pumps during normal operation
and check for unusual noises or general indications of poor performance.
• Record treatment system blower and process pump operating data (flow rates and
pressures).
• Record tank operating water levels.
• Record sodium hydroxide levels and usage rates.
• Record pH levels through treatment units.
• Observe chemical metering pump during normal operation and check for leaks and
general indications of poor performance.
• Record multi-media filter pressures and backwash data.
• Inspect backwash tank.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 56
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
• Observe operation of polymer injection system (storage tank, metering pump, and
tank water levels) during operation and check for general indications of poor
performance.
• Record instantaneous and totalized system flow rates.
• Inspect and test air compressor.
AOP Treatment System
• Observe recovery well vaults for indications of flooding or damage.
• Observe recovery well pumps during normal operation and check for leaks or
general indications of poor performance.
• Observe piping and tanks for leaks and spills.
• Observe treatment system process pumps during normal operation and check for
leaks, unusual noises or general indications of poor performance.
• Record instantaneous and totalized system flow rates.
• Record tank operating water levels.
• Record HiPOxTM unit operating data.
• Record chemical tank levels.
• Record catalytic media filter pressures and backwash data.
• Record multi-media filter pressures and backwash data.
• Inspect backwash tank.
• Observe operation of polymer injection system (storage tank, metering pump, and
tank water levels) during operation and check for general indications of poor
performance.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 57
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
• Record pH levels through treatment units and effluent discharge.
• Record LPGAC vessel pressures.
• Inspect and test air compressor.
2.6.5.2 Monthly Operation and Maintenance
In addition to the specific routine O&M activities, operating personnel will perform the
following O&M activities at least once per month in both the AOP pre-treatment and
AOP treatment systems:
• Visually inspect tanks, equipment, associated piping, and containment areas for
leaks, cracks, chips, exterior corrosion, or other damage;
• Check tanks for sediment buildup;
• As is practical, visually verify proper operation of instrumentation (operational and
free of obstruction). Compare local transmitter/gauge displays to the data
displayed at the PLC units;
• Calibrate pH meters;
• Inspect and test the eye wash/safety shower unit; and
• Test high-level tank and spill containment berm alarms.
2.6.5.3 Scheduled Operation and Maintenance
Specific maintenance tasks associated with the treatment units will be scheduled as
required by the equipment manufacturer specifications. For detailed instruction on
performing preventative maintenance on system components, Site personnel will refer
to the manufacturer’s O&M Manual and vendor literature, and the treatment system
O&M Manual that will be stored at the treatment system. The frequency of the
following specific maintenance tasks will be further optimized by operational
experience:
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 58
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
• Clean air stripper trays;
• Clean recovery wells;
• Clean recovery well pumps;
• Clean treatment system tanks;
• Change out VPGAC units;
• Grease motor bearings in treatment system pumps;
• Clean HiPOxTM reactors;
• Replenish treatment chemicals (H2O2, sodium hydroxide, and polymer);
• Backwash for catalytic media filter;
• Backwash for multi-media filter; and
• Change out LPGAC units.
2.7 Best Management Practice Plan
A BMPP has been developed for the RAPA and is included in Appendix M. The
objective of the BMPP is to identify those features and actions that will prevent or
minimize the potential for a release or spill at the recovery and transmission system,
and at the treatment facility. The document provides information on handling and
proper disposal of wastes generated, in addition to the handling and storage of
chemicals needed for the operation of the modified ISR treatment system.
2.8 Monitoring Plan
Three types of performance monitoring are discussed in this section: (1) treatment
system process monitoring, (2) treated water discharge monitoring, and (3) air
monitoring. The performance monitoring activities associated with groundwater
recovery, capture zones, and groundwater quality are discussed in further detail in the
Groundwater Monitoring Plan included in Appendix L.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 59
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.8.1 Treatment System Process Monitoring
Treatment system process sampling and analysis are summarized in Table J-9, Tab
#20. To evaluate the operational performance of the modified ISR treatment system,
the following operational samples will be collected:
AOP Pre-Treatment System
• Aeration tank influent – sample will be used to estimate source recovery rates from
the in-situ thermal system and monitor iron concentration/state in the process
water.
• Filter feed – sample will be used to evaluate performance of the iron oxidation
system and determine the solids loading to the multi-media filter.
• Multi-media filter effluent – sample will be used to determine filter efficiency to
remove oxidized iron particles and optimize backwash frequency. Results will be
used to monitor influent concentrations to the air stripper.
• Air stripper discharge – sample will be used to verify treatment efficiency. Results
will be used to determine influent concentrations to the AOP-100 unit.
• Backwash solids – sample will be used to develop waste profile for proper
disposal.
AOP Treatment System
• Recovery wells – sample will be used to monitor source recovery for individual
recovery wells.
• Equalization tank (T-1300) effluent – sample will be used to monitor influent
conditions for the AOP-100 unit.
• AOP-100 unit discharge – sample will be used to verify treatment efficiency to
remove COCs and update destruction curve/model generated for the HiPOxTM unit.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 60
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
• AOP-200 feed pump (P-1000) – sample will be used to estimate source recovery
rates for the recovery well network and monitor influent conditions for the AOP-200
unit.
• AOP-200 unit discharge – sample will be used to verify treatment efficiency to
remove COCs and update destruction curve/model generated for the HiPOxTM unit.
• Filter feed – Results will be used to determine the influent solids loading to the
catalytic media filter.
• Catalytic media filter effluent – sample will be used to determine filter efficiency to
remove oxidized iron and other particles. Results will be used to optimize
backwash frequency, and determine the influent solids loading to the multi-media
filter.
• Multi-media filter effluent – sample will be used to determine filter efficiency to
remove particles that may break through the catalytic media filter, and optimize
backwash frequency.
• Intermediate LPGAC – sample will be used to determine the time and volume of
water required for COC break through, and optimize the LPGAC change out
frequency.
Additional samples may be collected from supplemental locations as necessary to
monitor system performance and evaluate operational protocols.
2.8.2 Treated Water Discharge Monitoring
Treatment system effluent sampling and analysis are summarized in Table J-9, Tab
#20. The treated water discharge sample will be collected from the secondary (lag)
LPGAC vessel effluent. In accordance with requirements specified in the IWDP and
Rule 62-780-700(3)(g), F.A.C., treated water discharge samples will be collected on
the following frequency:
• Daily – for the first five days of operation;
• Weekly – for the next three weeks; and
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 61
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
• Monthly – for the duration of the remedial action and/or IWDP.
2.8.3 Air Monitoring
Air emissions from the modified ISR system are associated with aeration tank venting,
air stripper discharge and passive venting of process tanks. Vapors from the aeration
tank, process tank venting and air stripper discharge in the AOP pre-treatment system
will be treated by the in-situ thermal system. Passive venting from the influent EQ
tanks in the AOP treatment system will be treated by VPGAC units (T-2200 and T-
2300). Pursuant to Rules 62-780.700(3)(f)(3) and 62-210.300 F.A.C., total air
emissions from the modified ISR system will be maintained below the thresholds for
any single hazardous air pollutant (HAP) or total HAPs; thus no air permits will be
required. As a precautionary measure, the exhaust side of the VPGAC unit will be
monitored using a PID.
Air monitoring activities will be conducted weekly during the first month of operation
and monthly thereafter. The PID monitoring results will be used as an indication of
VPGAC status. In the event that PID results are above 10 ppm, the VPGAC will be
replaced with a new unit. The spent VPGAC will be taken off-site for proper
regeneration or disposal.
2.9 Reporting
Within 120 days of completion of the start-up of the modified ISR treatment system,
Raytheon will provide the FDEP with two signed and sealed sets of As-Built
engineering drawings (Record Drawings). The engineering drawing will include
construction and equipment design specifications of the installed modified ISR system,
and any operational parameters different from those in the approved RAPA. A
summary of the system start-up activities will be included in the engineering drawings.
In accordance with Rule 62-780.700(13), two copies of a Remedial Action Status
Report will be submitted to the FDEP on a quarterly basis during operation of the
modified ISR treatment system (Table J-9, Tab #20). The Remedial Action Status
Reports will document the recovery progress and will summarize recovery activities for
the specified period. The Reports will be submitted within 60 days of the end of the
reporting period and will include the following information:
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 62
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
• Operational summary
– O&M data and activities; and
– BMPP compliance.
• Summary of flow data including
– Flow totalizer readings for the AOP pre-treatment system effluent;
– Summation of recovery well totalizer readings to indicate total recovered groundwater;
– HiPOxTM unit process flow data; and
– Totalizer data for treated water discharged to the sewer.
• Summary of groundwater data
– Groundwater level data;
– Groundwater elevation contour maps;
– Capture zones of the groundwater recovery system based upon groundwater elevation data;
– Groundwater quality summary tables included data from monitoring wells and recovery wells;
– Maps posting groundwater Site COC analytical results in the groundwater stratigraphic units; and
– Analytical reports.
• Summary of treatment efficiency
– Process water analytical data summary;
– Graphs of groundwater COC concentrations versus time for select monitoring locations;
– Site COC source removal rates; and
– Analytical reports.
• Conclusions and recommendations based on the effectiveness of the active
remediation effort
Periodic Compliance Reports (PCRs) will be submitted to the City in accordance with
the requirements specified in the IWDP.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Appendix J_Design Text_MS_REV2.docx 63
Modified ISR System Design
Raytheon Remedial Action Plan Addendum
2.10 Cessation Criteria
After in-situ thermal remediation is discontinued, components of the modified ISR
system will be incorporated into the groundwater recovery and treatment system
described in Appendix K. It is expected that active thermal remediation will be
conducted at the Site for up to one year during which time COC source removal will be
optimized. After six to eight months of in-situ thermal system operation, the benefits of
continued remediation will be evaluated in the context of the expected diminished
concentrations of COCs in the extraction system effluent stream.
The cessation criterion for the modified ISR system is contingent upon completion of
the in-situ thermal system operations. Once in-situ thermal system operation is
complete, the modified ISR system operation will also be completed. The cessation
criterion for the in-situ thermal system is discussed in Section 8.6 of the RAPA text.
After shutdown of the modified ISR system, select process equipment will be relocated
and used for the groundwater RTS system described in Appendix K.
Tab 1
Modified ISR System – Design Basis
Table J-1AOP Pre-Treatment System Design Basis Summary
Raytheon CompanySt. Petersburg, Florida
Page 1 of 1
Estimated Flow Estimated Flow Calculated Applied Factor for Calculated Additional DesignUpper Sand Interbedded Upper sand Interbedded Contribution From Contribution From Average Concentration Increased Solubility Maximum Concentration Design Safety Maximum Concentration
Concentration Concentration Concentration Concentration Upper Sand Zone (4) Interbedded Unit (4) From Heating System (5) Due to Heating (6) From Heating System (7) Factor From Heating System (8)
Chemicals of Concern1,1,1-Trichloroethane 111 5,644 50 2,565 60% 40% 1,056 3.4 3,592 20% 4,3101,1-Dichloroethene 871 17,282 396 7,855 60% 40% 3,380 3.4 11,491 20% 13,789cis-1,2-Dichloroethene 701 15,359 319 6,981 60% 40% 2,984 3.4 10,145 20% 12,174Vinyl chloride 729 5,643 331 2,565 60% 40% 1,225 3.4 4,164 20% 4,997Trichloroethene 1,305 57,596 593 26,180 60% 40% 10,828 3.4 36,815 20% 44,1781,1-Dichloroethane 242 8,154 110 3,706 60% 40% 1,549 3.4 5,265 20% 6,3181,4-Dioxane 1,135 19,552 516 8,887 60% 40% 3,864 3.4 13,139 20% 15,767
Other Compounds1,1,2-Trichloroethane 130 470 59 214 60% 40% 121 3.4 411 20% 4931,2,4-Trimethylbenzene 31 775 (1) 14 352 60% 40% 149 3.4 508 20% 6091,2-Dichloroethane 50 (1) 1,261 (1) 23 573 60% 40% 243 3.4 826 20% 9921,3,5-Trimethylbenzene 56 1,400 (1) 25 636 60% 40% 270 3.4 917 20% 1,1012-Butanone (MEK) 475 (1) 11,878 216 5,399 60% 40% 2,289 3.4 7,783 20% 9,3404-Methyl-2-pentanone (MIBK) 58 8,145 26 3,702 60% 40% 1,497 3.4 5,089 20% 6,107Acetone 890 19,121 405 8,691 60% 40% 3,719 3.4 12,646 20% 15,175Benzene 29 (1) 723 13 329 60% 40% 139 3.4 474 20% 569Carbon Disulfide 127 755 58 343 60% 40% 172 3.4 584 20% 701Chloroethane 3 664 1 302 60% 40% 122 3.4 413 20% 496Chloroform 49 17,414 22 7,915 60% 40% 3,180 3.4 10,810 20% 12,973Ethylbenzene 150 180 68 82 60% 40% 74 3.4 250 20% 300Isopropylbenzene 24 600 (1) 11 273 60% 40% 116 3.4 393 20% 472m,p-Xylene 269 171 122 78 60% 40% 104 3.4 355 20% 426Methylene chloride 22 17,550 10 7,977 60% 40% 3,197 3.4 10,869 20% 13,043Naphthalene 8 195 (1) 4 89 60% 40% 38 3.4 128 20% 153o-Xylene 115 170 52 77 60% 40% 62 3.4 212 20% 254Tetrachloroethene 77 1,925 (1) 35 875 60% 40% 371 3.4 1,261 20% 1,514Toluene 1,180 5,789 536 2,631 60% 40% 1,374 3.4 4,673 20% 5,607trans-1,2-Dichloroethene 6 140 3 64 60% 40% 27 3.4 92 20% 111Trichlorofluoromethane 30 750 (1) 14 341 60% 40% 145 3.4 491 20% 590
Bromide -- -- -- -- -- -- 2.0 -- -- -- 2.0Bromate -- -- -- -- -- -- 0 -- -- -- 0Iron (total) -- -- -- -- -- -- 20 -- -- -- 20
Footnotes:
Concentrations in micrograms per liter (g/L). (1) Data was not available. Estimated values were based on a typical ratio of concentrations detected in interbedded unit and upper sand zone. Concentrations are typically 25 times higher in the intebedded unit.(2) Represents the average groundwater concentration detected during the vertical profile investigation performed at Building M in November 2009(3) A factor of 2.2 was estimated to adjust the vertical profile data to reflect expected data from a monitoring well. This factor is based on an analysis of two monitoring wells within the thermal treatment zone using the compounds Trichloroethene and 1,4-Dioxane. VAP results were generally 2.2 times higher than monitoring well data.(4) Based on professional judgment.(5) Flow weighted average calculation (Upper sand zone concentration x flow contribution %) + (Interbedded unit concentration x flow contribution %).(6) The peaking factor of 3.4 was based on other application thermal treatment system data that compares baseline data versus concentrations throughout the thermal treatment operation. (7) Peaking factor x calculated average concentration.(8) Maximum concentration x safety factor.VAP Vertical Aquifer Profilinggpm Gallons per minute-- Not applicable
VAP Analysis (2) Estimated Well Analysis (3)
Compounds
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #1\(2) Table J-1 (Tab 1)_PreAOP Design Summary.xls ARCADIS
Table J-2Modified ISR System Design Basis Summary
Raytheon CompanySt. Petersburg, Florida
Page 1 of 1
60 gpm32 gpm
CompoundsDesign Influent
Concentration to AOP Pre-
Treatment System (1)
Estimated Effluent Concentration from AOP
Pre-Treatment System (2)
Detected Concentration from Existing ISR System
Influent (3)
Estimated Effluent Concentration from Modified
ISR System (Standard
Operation) (4)
Estimated Effluent Concentration from Modified ISR System
(Contingency Operation) (5)
St. Petersburg POTW Discharge
Limits
Chemicals of Concern1,1,1-Trichloroethane 4,310 0 0 <200 <200 2001,1-Dichloroethene 13,789 1 61 <7 <7 7cis-1,2-Dichloroethene 12,174 1 480 <70 <70 70Vinyl chloride 4,997 0 0 <1 <1 1Trichloroethene 44,178 4 2,300 <3 <3 31,1-Dichloroethane 6,318 1 38 <70 <70 701,4-Dioxane 15,767 15,767 425 <3.2 <3.2 3.2
Other Compounds1,1,2-Trichloroethane 493 2 0 <5 <5 51,2,4-Trimethylbenzene 609 0 0 <10 <10 101,2-Dichloroethane 992 2 0 <3 <3 31,3,5-Trimethylbenzene 1,101 0 0 <10 <10 102-Butanone (MEK) 9,340 7,076 0 4,615 7,021 7,750 (6)
4-Methyl-2-pentanone (MIBK) 6,107 555 0 362 550 1,640 (6)
Acetone 15,175 12,540 0 8,178 12,442 13,700 (6)
Benzene 569 0 0 <1 <1 1Carbon Disulfide 701 0 0 <700 <700 700Chloroethane 496 0 0 <12 <12 12Chloroform 12,973 1 0 <70 <70 70Ethylbenzene 300 0 0 <30 <30 30Isopropylbenzene 472 0 0 <0.8 <0.8 0.8m,p-Xylene 426 0 0 <20 <20 20Methylene chloride 13,043 4 0 <5 <5 5Naphthalene 153 6 0 <14 <14 14o-Xylene 254 0 0 <20 <20 20Tetrachloroethene 1,514 0 0 <3 <3 3Toluene 5,607 1 0 <40 <40 40trans-1,2-Dichloroethene 111 0 0 <100 <100 100Trichlorofluoromethane 590 0 0 <2,100 <2,100 2,100
Bromide 2.0 2.0 0.7 0.8 1.0 NABromate 0 0 0 0.3 0.3 0.5Iron (total) 20 2.0 10 0.3 0.3 1
Footnotes:
Concentrations are in micrograms per liter (g/L).(1) Calculated values based on estimates provided in Table J-1.(2) Estimated concentrations following AOP pre-treatment system. Refer to Table J-3 for calculation.(3) Concentrations are the maximum influent concentrations detected in the existing ISR system influent during system operation between 3/20/09 and 11/17/09.(4) Standard operation includes treating water from the AOP pre-treatment system and the existing ISR recovery wells. Estimated values are based on operation of both systems.(5) Contingency operation assumes the existing ISR recovery wells will be shut down; therefore, estimated values are based on treatment of the AOP pre-treatment system effluent only.(6) The City of St. Petersburg has provided a letter of intent to approve revisions to the current permit to include increases in flow rate to 100 gpm and increased discharge limits for the indicated compounds.
ISR - Interim Source RemovalPOTW - Publicly Owned Treatment Worksgpm - Gallons per minute
Expected Flow Rate From AOP Pre-Treatment System =Flow Rate From Existing ISR Recovery Wells =
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #1\(3) Table J-2 (Tab 1)_Mod ISR Design Summary.xls ARCADIS
Table J-2Modified ISR System Design Basis Summary
Raytheon CompanySt. Petersburg, Florida
Page 1 of 1
60 gpm32 gpm
CompoundsDesign Influent
Concentration to AOP Pre-
Treatment System (1)
Estimated Effluent Concentration from AOP
Pre-Treatment System (2)
Detected Concentration from Existing ISR System
Influent (3)
Estimated Effluent Concentration from Modified
ISR System (Standard
Operation) (4)
Estimated Effluent Concentration from Modified ISR System
(Contingency Operation) (5)
St. Petersburg POTW Discharge
Limits
Chemicals of Concern1,1,1-Trichloroethane 4,310 0 0 <200 <200 2001,1-Dichloroethene 13,789 1 61 <7 <7 7cis-1,2-Dichloroethene 12,174 1 480 <70 <70 70Vinyl chloride 4,997 0 0 <1 <1 1Trichloroethene 44,178 4 2,300 <3 <3 31,1-Dichloroethane 6,318 1 38 <70 <70 701,4-Dioxane 15,767 15,767 425 <3.2 <3.2 3.2
Other Compounds1,1,2-Trichloroethane 493 2 0 <5 <5 51,2,4-Trimethylbenzene 609 0 0 <10 <10 101,2-Dichloroethane 992 2 0 <3 <3 31,3,5-Trimethylbenzene 1,101 0 0 <10 <10 102-Butanone (MEK) 9,340 7,076 0 4,615 7,021 7,750 (6)
4-Methyl-2-pentanone (MIBK) 6,107 555 0 362 550 1,640 (6)
Acetone 15,175 12,540 0 8,178 12,442 13,700 (6)
Benzene 569 0 0 <1 <1 1Carbon Disulfide 701 0 0 <700 <700 700Chloroethane 496 0 0 <12 <12 12Chloroform 12,973 1 0 <70 <70 70Ethylbenzene 300 0 0 <30 <30 30Isopropylbenzene 472 0 0 <0.8 <0.8 0.8m,p-Xylene 426 0 0 <20 <20 20Methylene chloride 13,043 4 0 <5 <5 5Naphthalene 153 6 0 <14 <14 14o-Xylene 254 0 0 <20 <20 20Tetrachloroethene 1,514 0 0 <3 <3 3Toluene 5,607 1 0 <40 <40 40trans-1,2-Dichloroethene 111 0 0 <100 <100 100Trichlorofluoromethane 590 0 0 <2,100 <2,100 2,100
Bromide 2.0 2.0 0.7 0.8 1.0 NABromate 0 0 0 0.3 0.3 0.5Iron (total) 20 2.0 10 0.3 0.3 1
Footnotes:
Concentrations are in micrograms per liter (g/L).(1) Calculated values based on estimates provided in Table J-1.(2) Estimated concentrations following AOP pre-treatment system. Refer to Table J-3 for calculation.(3) Concentrations are the maximum influent concentrations detected in the existing ISR system influent during system operation between 3/20/09 and 11/17/09.(4) Standard operation includes treating water from the AOP pre-treatment system and the existing ISR recovery wells. Estimated values are based on operation of both systems.(5) Contingency operation assumes the existing ISR recovery wells will be shut down; therefore, estimated values are based on treatment of the AOP pre-treatment system effluent only.(6) The City of St. Petersburg has provided a letter of intent to approve revisions to the current permit to include increases in flow rate to 100 gpm and increased discharge limits for the indicated compounds.
ISR - Interim Source RemovalPOTW - Publicly Owned Treatment Worksgpm - Gallons per minute
Expected Flow Rate From AOP Pre-Treatment System =Flow Rate From Existing ISR Recovery Wells =
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #1\(3) Table J-2 (Tab 1)_Mod ISR Design Summary.xls ARCADIS
Table J-2Modified ISR System Design Basis Summary
Raytheon CompanySt. Petersburg, Florida
Page 1 of 1
60 gpm32 gpm
CompoundsDesign Influent
Concentration to AOP Pre-
Treatment System (1)
Estimated Effluent Concentration from AOP
Pre-Treatment System (2)
Detected Concentration from Existing ISR System
Influent (3)
Estimated Effluent Concentration from Modified
ISR System (Standard
Operation) (4)
Estimated Effluent Concentration from Modified ISR System
(Contingency Operation) (5)
St. Petersburg POTW Discharge
Limits
Chemicals of Concern1,1,1-Trichloroethane 4,310 0 0 <200 <200 2001,1-Dichloroethene 13,789 1 61 <7 <7 7cis-1,2-Dichloroethene 12,174 1 480 <70 <70 70Vinyl chloride 4,997 0 0 <1 <1 1Trichloroethene 44,178 4 2,300 <3 <3 31,1-Dichloroethane 6,318 1 38 <70 <70 701,4-Dioxane 15,767 15,767 425 <3.2 <3.2 3.2
Other Compounds1,1,2-Trichloroethane 493 2 0 <5 <5 51,2,4-Trimethylbenzene 609 0 0 <10 <10 101,2-Dichloroethane 992 2 0 <3 <3 31,3,5-Trimethylbenzene 1,101 0 0 <10 <10 102-Butanone (MEK) 9,340 7,076 0 4,615 7,021 7,750 (6)
4-Methyl-2-pentanone (MIBK) 6,107 555 0 362 550 1,640 (6)
Acetone 15,175 12,540 0 8,178 12,442 13,700 (6)
Benzene 569 0 0 <1 <1 1Carbon Disulfide 701 0 0 <700 <700 700Chloroethane 496 0 0 <12 <12 12Chloroform 12,973 1 0 <70 <70 70Ethylbenzene 300 0 0 <30 <30 30Isopropylbenzene 472 0 0 <0.8 <0.8 0.8m,p-Xylene 426 0 0 <20 <20 20Methylene chloride 13,043 4 0 <5 <5 5Naphthalene 153 6 0 <14 <14 14o-Xylene 254 0 0 <20 <20 20Tetrachloroethene 1,514 0 0 <3 <3 3Toluene 5,607 1 0 <40 <40 40trans-1,2-Dichloroethene 111 0 0 <100 <100 100Trichlorofluoromethane 590 0 0 <2,100 <2,100 2,100
Bromide 2.0 2.0 0.7 0.8 1.0 NABromate 0 0 0 0.3 0.3 0.5Iron (total) 20 2.0 10 0.3 0.3 1
Footnotes:
Concentrations are in micrograms per liter (g/L).(1) Calculated values based on estimates provided in Table J-1.(2) Estimated concentrations following AOP pre-treatment system. Refer to Table J-3 for calculation.(3) Concentrations are the maximum influent concentrations detected in the existing ISR system influent during system operation between 3/20/09 and 11/17/09.(4) Standard operation includes treating water from the AOP pre-treatment system and the existing ISR recovery wells. Estimated values are based on operation of both systems.(5) Contingency operation assumes the existing ISR recovery wells will be shut down; therefore, estimated values are based on treatment of the AOP pre-treatment system effluent only.(6) The City of St. Petersburg has provided a letter of intent to approve revisions to the current permit to include increases in flow rate to 100 gpm and increased discharge limits for the indicated compounds.
ISR - Interim Source RemovalPOTW - Publicly Owned Treatment Worksgpm - Gallons per minute
Expected Flow Rate From AOP Pre-Treatment System =Flow Rate From Existing ISR Recovery Wells =
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #1\(3) Table J-2 (Tab 1)_Mod ISR Design Summary.xls ARCADIS
Table J-3Modified ISR System
AOP Pre-Treatment System Mass BalanceRaytheon Company
St. Petersburg, Florida
Page 1 of 1
Flow ID:
Parameters Units
Flow Rate (water, average) gpm 60 60 -- -- 60 60 60 60 1.8 (5) 1.8 (5) 0.09 1.7 -- -- --Flow Rate (water, instantaneous) gpm -- -- -- -- -- -- -- -- 106 (5) 106 20 20 -- -- --Flow Rate gpd -- -- -- 8.3 (2) -- -- -- -- -- -- 125 -- -- -- --Air Flow Rate SCFM -- -- 30 (1) -- -- -- -- -- -- -- -- -- 900 40 60Temperature ºF 72 - 180 72 - 120 -- -- 72 - 115 72 - 114 72 - 113 72 - 100 72 - 114 72 - 114 72 - 114 72 - 114 72 - 100 72 - 100 72 - 100Solids Generation cu.ft./day -- -- -- -- -- -- -- -- -- -- -- -- -- -- --
pH SU 6.0 6.0 -- 14.0 7.4 7.4 7.4 7.4 7.4 7.4 7.4 7.4 -- -- --Total suspended solids mg/L 30 30 -- -- 50 (3) 50 5 5 50 1,527 30,000 50 -- -- --Iron (total) mg/L 20.0 20 -- -- 20.0 20.0 2.0 2.0 20.0 611 12,000 20.0 -- -- --Iron (dissolved) mg/L 20.0 20 -- -- 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 -- -- --Bromide mg/L 2.0 2 -- -- 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 -- -- --Bromate mg/L 0.0 0 -- -- 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 -- -- --
1,1,1-Trichloroethane µg/L 4,310 4,310 -- -- 3,879 (4) 3,879 3,879 0 3,879 3,879 3,879 3,879 7.0 (6) 15.7 (6) 10.4 (6)1,1-Dichloroethene µg/L 13,789 13,789 -- -- 12,410 (4) 12,410 12,410 1 12,410 12,410 12,410 12,410 30.6 (6) 69.0 (6) 46.0 (6)cis-1,2-Dichloroethene µg/L 12,174 12,174 -- -- 10,957 (4) 10,957 10,957 1 10,957 10,957 10,957 10,957 27.1 (6) 60.9 (6) 40.6 (6)Vinyl chloride µg/L 4,997 4,997 -- -- 4,497 (4) 4,497 4,497 0 4,497 4,497 4,497 4,497 17.2 (6) 38.8 (6) 25.8 (6)Trichloroethene µg/L 44,178 44,178 -- -- 39,760 (4) 39,760 39,760 4 39,760 39,760 39,760 39,760 72.4 (6) 163.0 (6) 108.7 (6)1,1-Dichloroethane µg/L 6,318 6,318 -- -- 5,686 (4) 5,686 5,686 1 5,686 5,686 5,686 5,686 13.8 (6) 31.0 (6) 20.6 (6)1,4-Dioxane µg/L 15,767 15,767 -- -- 15,767 (4) 15,767 15,767 15,767 15,767 15,767 15,767 15,767 0.0 (6) 0.0 (6) 0.0 (6)
1,1,2-Trichloroethane µg/L 493 493 -- -- 444 (4) 444 444 2 444 444 444 444 0.8 (6) 1.8 (6) 1.2 (6)1,2,4-Trimethylbenzene µg/L 609 609 -- -- 548 (4) 548 548 0 548 548 548 548 1.1 (6) 2.5 (6) 1.6 (6)1,2-Dichloroethane µg/L 992 992 -- -- 893 (4) 893 893 2 893 893 893 893 2.2 (6) 4.9 (6) 3.2 (6)1,3,5-Trimethylbenzene µg/L 1,101 1,101 -- -- 991 (4) 991 991 0 991 991 991 991 2.0 (6) 4.4 (6) 3.0 (6)2-Butanone (MEK) µg/L 9,340 9,340 -- -- 8,873 (4) 8,873 8,873 7,076 8,873 8,873 8,873 8,873 5.7 (6) 31.4 (6) 20.9 (6)4-Methyl-2-pentanone (MIBK) µg/L 6,107 6,107 -- -- 5,802 (4) 5,802 5,802 555 5,802 5,802 5,802 5,802 11.9 (6) 14.8 (6) 9.9 (6)Acetone µg/L 15,175 15,175 -- -- 14,872 (4) 14,872 14,872 12,540 14,872 14,872 14,872 14,872 8.8 (6) 25.3 (6) 16.9 (6)Benzene µg/L 569 569 -- -- 512 (4) 512 512 0 512 512 512 512 1.6 (6) 3.5 (6) 2.4 (6)Carbon Disulfide µg/L 701 701 -- -- 631 (4) 631 631 0 631 631 631 631 2.0 (6) 4.5 (6) 3.0 (6)Chloroethane µg/L 496 496 -- -- 446 (4) 446 446 0 446 446 446 446 1.7 (6) 3.7 (6) 2.5 (6)Chloroform µg/L 12,973 12,973 -- -- 11,676 (4) 11,676 11,676 1 11,676 11,676 11,676 11,676 23.4 (6) 52.7 (6) 35.1 (6)Ethylbenzene µg/L 300 300 -- -- 270 (4) 270 270 0 270 270 270 270 0.6 (6) 1.4 (6) 0.9 (6)Isopropylbenzene µg/L 472 472 -- -- 425 (4) 425 425 0 425 425 425 425 0.8 (6) 1.9 (6) 1.3 (6)m,p-Xylene µg/L 426 426 -- -- 383 (4) 383 383 0 383 383 383 383 0.9 (6) 1.9 (6) 1.3 (6)Methylene chloride µg/L 13,043 13,043 -- -- 11,739 (4) 11,739 11,739 4 11,739 11,739 11,739 11,739 33.1 (6) 74.5 (6) 49.6 (6)Naphthalene µg/L 153 153 -- -- 138 (4) 138 138 6 138 138 138 138 0.2 (6) 0.6 (6) 0.4 (6)o-Xylene µg/L 254 254 -- -- 229 (4) 229 229 0 229 229 229 229 0.5 (6) 1.2 (6) 0.8 (6)Tetrachloroethene µg/L 1,514 1,514 -- -- 1,363 (4) 1,363 1,363 0 1,363 1,363 1,363 1,363 2.0 (6) 4.4 (6) 3.0 (6)Toluene µg/L 5,607 5,607 -- -- 5,046 (4) 5,046 5,046 1 5,046 5,046 5,046 5,046 13.1 (6) 29.5 (6) 19.7 (6)trans-1,2-Dichloroethene µg/L 111 111 -- -- 100 (4) 100 100 0 100 100 100 100 0.2 (6) 0.6 (6) 0.4 (6)Trichlorofluoromethane µg/L 590 590 -- -- 531 (4) 531 531 0 531 531 531 531 0.9 (6) 2.1 (6) 1.4 (6)
Footnotes:gpm - Gallons per Minutegpd - Gallons per DaySCFM - Standard Cubic Feet per MinuteºF - Fahrenheitcu.ft./day - Cubic Feet per Day
SU - Standard Unitmg/L - Milligrams per Literµg/L - Micrograms per LiterNE - Not Estimated at this TimeTSS - Total Suspended Solids
(1) 30 SCFM was the calculated volume to mix the tank using coarse bubble diffusers, volume required to oxidize iron was estimate to be approximately 5 SCFM(2) Sodium hydroxide usage is estimated based on usage in the ISR system which is 12 ml/minute at a flow rate of 33 gpm, the conversion was made to adjust for 60 gpm flow rate and units of gallons per day(3) TSS = TSS (from heating stream) - total iron + (2 X Dissolved Iron)(4) Assume that 10% of volatile compounds will be stripped in the aeration tank which is operated at an approximate air to water ratio of 4:1, removal rates for select compounds were decreased (1,4-dioxane, acetone, MEK, and MIBK)(5) Based on 3 filters beds, each backwashed once per day, 36-inch diameter bed, 106 gpm backwash rate x 8 minute (each bed) x 3 beds
2,545 gpd backwash water required, daily average = 1.8 gpm(6) calculated on separate sheet, units are ppmv
Other Compounds
Multi-Media Filter Effluent
Clean Backwash Water
From In-situ Thermal System
Air to Aeration Tank
Sodium Hydroxide
Aeration Tank Overflow
Multi-Media Filter Influent
Post Heat Exchanger
7 11Water to AOP
Treatment System
Backwash Solids
Chemicals of Concern
General Water Quality Parameters
1 3 4 5 62
Aeration Tank Vapors
8
Tank Vapors
14 1513Decant From
Backwash Tank
Air Stripper Vapors
12
Dirty Backwash Water
9 10
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #1\(6)Table J-3 (Tab 1)_Pre-AOP Mass Balance.xlsx ARCADIS
Table J-4Modified ISR System
AOP Treatment System Mass BalanceRaytheon Company
St. Petersburg, Florida
Page 1 of 1
Flow ID:
Parameters Units
Flow Rate (water, average) gpm 60 61 61 32 32 32 93 93 93 93 3.27 (4) 0.34 (5) 3.3 (4) 0.34 1.38 0 1.38 0.06 -- --Flow Rate (water, instantaneous) gpm -- -- -- -- -- -- -- -- -- -- 63, 188 74 -- 74 20 NA 20 -- -- --Flow Rate gpd -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- NA -- 84 -- --Air Flow Rate (instantaneous) SCFM -- -- -- -- -- -- -- -- -- -- 38 (4) -- -- -- -- NA -- -- 4 max 8 maxTemperature ºF 72 - 100 72 - 100 72 - 100 75 75 75 73 - 94 73 - 94 73 - 94 73 - 94 73 - 94 73 - 94 73 - 94 73 - 94 73 - 94 NA 73 - 94 73 - 94 -- --Solids Generation cu.ft./day -- -- -- -- -- -- -- -- -- -- -- -- NA 0 -- -- --
pH SU 7.4 7.4 7.4 6.0 6.0 7.4 7.4 7.4 7.4 7.4 7.4 7.4 7.4 7.4 7.4 NA 7.4 7.4 -- --Total suspended solids mg/L 5 5 5 30 30 50 20 5 1 1 20 20 438 1,099 20 NA 20 30,000 -- --Iron (total) mg/L 2.0 2.0 2.0 10 10 10 5 0.3 0.3 0.3 5 5 101 254 5 NA 5 6,947 -- --Iron (dissolved) mg/L 0.0 0.0 0.0 10 10 0 0 0 0 0 0 0 0 0 0 NA 0 0 -- --Bromide mg/L 2.0 2.0 1.0 (2) 0.7 0.7 0.4 (2) 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 NA 0.8 0.8 -- --Bromate mg/L 0.0 0.0 0.3 (3) 0.0 0.0 0.3 (3) 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 NA 0.3 0.3 -- --
1,1,1-Trichloroethane µg/L 0 0 0 0 0 0 0 0 0 <200 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)1,1-Dichloroethene µg/L 1 1 0 61 61 0 0 0 0 <7 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)cis-1,2-Dichloroethene µg/L 1 1 0 480 480 0 0 0 0 <70 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)Vinyl chloride µg/L 0 0 0 0 0 0 0 0 0 <1 0 0 0 0 0 NA 0 0 <2 (6) <2 (6)Trichloroethene µg/L 4 4 0 2,300 2,300 0 0 0 0 <3 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)1,1-Dichloroethane µg/L 1 1 0 38 38 30 0 0 0 <70 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)1,4-Dioxane µg/L 15,767 15,413 0 425 425 0 0 0 0 <3.2 0 0 0 0 0 NA 0 0 NA (6) NA (6)
1,1,2-Trichloroethane µg/L 2 2 0 0 0 0 0 0 0 <5 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)1,2,4-Trimethylbenzene µg/L 0 0 0 0 0 0 0 0 0 <10 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)1,2-Dichloroethane µg/L 2 2 0 0 0 0 0 0 0 <3 0 0 0 0 0 NA 0 0 <10 (6) <10 (6)1,3,5-Trimethylbenzene µg/L 0 0 0 0 0 0 0 0 0 <10 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)2-Butanone (MEK) µg/L 7,076 7,021 7,021 0 0 0 4,615 4,615 4,615 <7,750 4,615 4,615 4,615 4,615 4,615 NA 4,615 4,615 <10 (6) <10 (6)4-Methyl-2-pentanone (MIBK) µg/L 555 550 550 0 0 0 362 362 362 <1,640 362 362 362 362 362 NA 362 362 NA (6) NA (6)Acetone µg/L 12,540 12,442 12,442 0 0 0 8,178 8,178 8,178 <13,700 8,178 8,178 8,178 8,178 8,178 NA 8,178 8,178 <10 (6) <10 (6)Benzene µg/L 0 0 0 0 0 0 0 0 0 <1 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)Carbon Disulfide µg/L 0 0 0 0 0 0 0 0 0 <700 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)Chloroethane µg/L 0 0 0 0 0 0 0 0 0 <12 0 0 0 0 0 NA 0 0 <2 (6) <2 (6)Chloroform µg/L 1 1 0 0 0 0 0 0 0 <70 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)Ethylbenzene µg/L 0 0 0 0 0 0 0 0 0 <30 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)Isopropylbenzene µg/L 0 0 0 0 0 0 0 0 0 <0.8 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)m,p-Xylene µg/L 0 0 0 0 0 0 0 0 0 <20 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)Methylene chloride µg/L 4 3 0 0 0 0 0 0 0 <5 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)Naphthalene µg/L 6 6 0 0 0 0 0 0 0 <14 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)o-Xylene µg/L 0 0 0 0 0 0 0 0 0 <20 0 0 0 0 0 NA 0 0 <2 (6) <2 (6)Tetrachloroethene µg/L 0 0 0 0 0 0 0 0 0 <3 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)Toluene µg/L 1 0 0 0 0 0 0 0 0 <40 0 0 0 0 0 NA 0 0 <2 (6) <2 (6)trans-1,2-Dichloroethene µg/L 0 0 0 0 0 0 0 0 0 <100 0 0 0 0 0 NA 0 0 <1 (6) <1 (6)Trichlorofluoromethane µg/L 0 0 0 0 0 0 0 0 0 <2100 0 0 0 0 0 NA 0 0 <2 (6) <2 (6)
Footnotes:gpm - Gallons per Minutegpd - Gallons per DaySCFM - Standard Cubic Feet per MinuteºF - Fahrenheitcu.ft./day - Cubic Feet per DaySU - Standard Unitmg/L - Milligrams per Literµg/L - Micrograms per LiterNE - Not Estimated at this TimeTSS - Total Suspended Solids
(1) TSS = TSS (HiPOxTM Influent) + (2 X Dissolved Iron)(2) Based on bromide/bromate conversion (30-40%) observed in Interim Source Remediation System
(3) Based on bromate/bromide reduction observed in HiPOxTM technology laboratory testing completed by Applied Process Technology Inc.(4) Based on 3 filters beds, each backwashed once per day with a combination of air and water, followed by water only backwash sequence.
Air & Water Backwash: 48-inch diameter bed, 63 gpm backwash rate x 10 minute (each bed) x 3 beds = 1,890 gpd backwash water (630 gpd) required, on average = 1.31 gpm.38 scfm air scour rate x 10 minutes (each bed) x 3 beds = 1,140 scf per backwash or 380 scfd air sour required, on average = 0.79 scfm.Water Backwash: 48-inch diameter bed, 188 gpm backwash rate x 5 minutes (each bed) x 3 beds = 2,820 gp backwash water or 940 per day required, on average = 1.96 gpm.Total backwash water = 1.1 gpm daily average
(5) Based on 2 filters beds, each backwashed once every three days, 30-inch diameter bed, 74 gpm backwash rate x 10 minute (each bed) x 2 beds1,480 gallons of water required every third day, on average = 0.34 gpm
(6) Vapor concentration units are milligrams per cubic meter (mg/m3)
General Water Quality Parameters
Chemicals of Concern
Other Compounds
MMF Backwash
Solids
2824 25 262313 14 1510 11
T-1500 Influent from
Recovery Wells
AOP-200 Influent
Water From AOP Pre-Treatment
System
AOP-100 Influent
MMF Effluent LGAC Effluent
29
T-2300 Treated Vapor
Effluent
T-2200 Treated Vapor
Effluent
T-2000 Decant
Decant to T-1500
Decant to T-1300
27
Backwash Solids To Disposal
Catalytic Media Filter Backwash
Water
2212 18 19 20
Catalytic Media Filter Backwash
Solids
AOP-100 Effluent
MMF Backwash
Water
2116 17
Catalytic Media Filter Influent
Catalytic Media Filter Effluent
AOP-200 Effluent
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #1\(7) Table J-4 (Tab 1)_MISR Mass Balance.xlsx ARCADIS
Tab 2
Modified ISR System – Piping & Instrumentation
Tab 3
Modified ISR System – AOP Pre-Treatment System Heat Exchanger
Page 1 of 1
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate: 01/28/2010
Considerations:
Tank volume = 2,000 gal
Solids Storage = 188 gal 6-inch Depth
Freeboard = 376 gal 12-inch Depth
Usable tank volume = Total tank volume - Solids storage - Freeboard
Usable tank volume = 1,436 gal
Process flow rate = 60 gpm In-Situ Thermal System Effluent
Total retention time = 24 min
Operation = 80 % Full
Design retention time = 19 min
Additional requirements = 0 gal
Calculate Required Tank Volume:
Retention time volume = Flow rate x Design retention time
1,149 gal
Minimum volume = Retention time volume + Additional requirements
1,149 gal
Tank Selection:
Cylindrical Tank:
Diameter = 8 feet
Sidewall Height = 10.5 feet
Usable Tank Volume = 1,436 gal
Available Tank Volume = 1,436 gal
Required Tank Volume = 1,149 gal
Volume Available > Volume Required therefore design is acceptable
HEAT EXCHANGER FEED TANK (T-100) SIZINGModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #3\(1) Tab #3_T-100 Sizing.xlsx ARCADIS
Page 1 of 3
Total dynamic head calculation = Calc prepared by: M. Seppanenhead loss due to elevation change Calc checked by: J. Perellahead loss due to pipe friction Date: 1/28/2010head loss across misc. process componentsrequired discharge head
Calculate pipe size:
Where: v = Velocity (ft/sec)Q = Flow rate (gpm)r = Pipe radius (in)
Flow Rate Pipe Size Pipe ODWall
Thickness Pipe ID Area velocity(gpm) (in) (in) (in) (in) (ft2) (ft/sec)
60 2 2.375 0.154 2.067 0.023 5.5860 3 3.500 0.216 3.068 0.051 2.5360 4 4.500 0.237 4.026 0.088 1.47
*Pipe dimensions noted for Schedule 40 galvanized steel piping.Note: Design for velocity between 3 and 5 feet/sec to maintain sufficient scour velocity.
Calculate head loss (he) due to elevation change:
assume: Height from pump to discharge point = 15 feetHead loss, he = 15 feet
Calculate head loss due to pipe friction losses:
Step 1. There are multiple pipe sections with flow and pipe diameters shown below
Pipe Section 1 Nominal pipe diameter 1 = 3 inch
Flow (v1) = 60 gpm
Step 2. Calculate the friction factor for each pipe section using the Hazen-Williams formula
Hazen-Williams f = .2083 * (100/C)1.852 * (q1.852) / (D4.8655)Formula
f = Friction in head in feet of water per 100 ft of pipeC = Constant for inside roughness
(140 for new galvanized steel pipe, 150 for hdpe pipe)q = Flow rate (gal/min)D = Inside diameter of pipe (inches)
Nominal Diam (in)
ID (in)
ID w/ deposition (in)
1 1.049 0.9241.5 1.610 1.4852 2.067 1.9423 3.068 2.9434 4.026 3.9016 6.065 5.94
NOTE: a 0.0625 inch (1/16 inch) deposition on interior pipe wall is included in diameter for calculation - 1.003 - (2 x 0.0625) = 0.878 inch diameter
HEAT EXCHANGER FEED PUMP (P-100A/B) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
sec60
min1*
)*( 2r
Qv
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #3\(3) Tab #3_P-100A&B TDH.xlsx ARCADIS
Page 2 of 3
HEAT EXCHANGER FEED PUMP (P-100A/B) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Friction factor for Pipe Section 1C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 60 gal/minD1 = Inner pipe diameter (inches) 2.943 inches (see NOTE)
Pipe Section friction factor 1.1 ft water / 100 feet of pipe
Step 3. Calculate the equivalent length of pipe for each section
Nominal Fitting size 1 in 1.5 in 2 in 3 in 4 in 6 in
90˚ Elbows 2.7 3.4 3.6 4.0 4.6 10.4Standard Tee (thru flow) 3.2 5.6 7.7 12.0 17.0 38.3Standard Tee (branch flow) 6.6 9.9 12.0 17.0 21.0 47.3Ball valve (full open) 1.6 2.3 2.9 4.3 5.5 12.3Check Valve 11.0 15.0 19.0 27.0 38.0 85.5Union 0.3 0.4 0.5 0.5 0.7 1.5Reducer (2/1) 1.0 1.5 1.5 3.0 4.0 9.0Expansion (1/2) 1.5 2.5 3.0 4.0 6.0 13.5
Equivalent lengths from reference: Civil Engineering Reference Manual, 9th Ed, Professional Publications, Inc., 2003; and "Flow of Fluids", Crane Technical Paper No. 410, 1988.
Pipe Section 1 - 3"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 50 50Standard Tee (thru flow) 2 12 24Standard Tee (branch flow) 2 17 3490˚ Elbows 8 4 32Union 4 0.5 2Check Valve - Swing 1 27 27Ball valve (full open) 4 4.3 17
Equivalent Length: 186
Step 4. Determine pipe friction for each pipe section.
total pipe friction = total equivalent length x friction factor
Total Pipe Friction - Pipe Section 1total equivalent length = 186 feet
friction factor = 1.1 feet water / 100 feet of pipe
Total Pipe Friction = 2.1 feet
Step 5. Determine total pipe friction (all sections)
Total Pipe Friction - Pipe Section 1 = 2.1
Equivalent Length
Equivalent Length per Fitting (ft)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #3\(3) Tab #3_P-100A&B TDH.xlsx ARCADIS
Page 3 of 3
HEAT EXCHANGER FEED PUMP (P-100A/B) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Calculate Total Dynamic Head:
Head Loss Due to Change in Elevation 15 ft
Headless due to pipe friction 2.1 ft
Headless Across Misc. Process Components Heat Exchanger 25 ft
Required Discharge Pressure (0 psi) 0 ft
Total Dynamic Head Required - Calculated 42 ft
Design Safety Factor 25%
Total Dynamic Head Required - Design 53 feet
Pump Design Requirements:Flow 60 gpm
Total Dynamic Head 53 feet
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #3\(3) Tab #3_P-100A&B TDH.xlsx ARCADIS
Model: 3196 Size: 2X3-8 Group: MTi 60Hz RPM: 1750 Stages: 1
Job/Inq.No. : RAYTHEONPurchaser : ARCADISEnd User : ARCADIS Issued by : Rev. : 0Item/Equip.No. : P-100AB Quotation No. : RAPA PRETREATMENT Date : 02/03/2010Service :Order No. :
Operating Conditions Pump PerformanceLiquid: Water Published Efficiency: 46.0 % Suction Specific Speed: 8,693 gpm(US) ftTemp.: 180.0 deg F Rated Pump Efficiency: 46.0 % Min. Hydraulic Flow: 7.7 gpmS.G./Visc.: 1.000/1.000 cp Rated Total Power: 1.8 hp Min. Thermal Flow: N/AFlow: 60.0 gpm Non-Overloading Power: 2.6 hpTDH: 53.0 ft Imp. Dia. First 1 Stg(s): 7.1250 inNPSHa: NPSHr: 2.0 ftSolid size: Shut off Head: 56.7 ft% Susp. Solids(by wtg):
Vapor Press:
Max. Solids Size: 0.5000 inNotes: 1. The Mechanical seal increased drag effect on power and efficiency is not included, unless the correction is shown in the
appropriate field above. 2. Magnetic drive eddy current on power and efficiency is not included. 3. Elevated temperatureeffects on performance are not included. 4. Non Overloading power does not reflect v-belt/gear losses.
Page 1 of 2
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate: 1/28/2010
I. Conditions:
Process Fluid: 60GPM of effluent from heating system to be cooled from 180º to 120ºF.Cooling Medium: Water at 40ºF. Assume a 45º maximum temperature rise.Cooler Design: 4-Pass design is selected to conserve water and energy usage.
II. Rate Flow Determination
Qp = M x C x Δt
Temperature of the inlet process water (T1) 180.0 ºF
Temperature of the outlet process water (T2) 120.0 ºF
Flow rate of process water 60.0 gpmMass flow rate of water in the heat exchanger (M) 30024 lb/hrSpecific heat of water ( C ) 1.0 Btu/lbºFTemperature difference of the process fluid ( Δ t) 60.0 ºFHeat Transfer (Qp) 1,801,440 Btu/hr
III. Determining cooling water flow rate
Temperature of the inlet cooling water (t1) 40.0 ºF
Temperature of the inlet outlet cooling water (t2) 85.0 ºF
Temperature difference of the cooling fluid (Δt) 45.00 ºFSpecific heat of water ( C ) 1.0 Btu/lbºFHeat Transfer (Qp) 1801440 Btu/hrCooling water mass flow rate (M) 40032 lb/hrCooling water flow rate (Qc) 80 gpm
IV. Determine Exchanger Surface area
Area = Qp/(U x (Cf x LMTD))
Where,
U = Overall Heat transmission Coefficient 275.0 (Btu/ft2 hr ºF)LMTD = Log Mean Temperature DifferenceCf = LMTD Correction Factor (4-Pass Hx) 0.67
Typical Overall heat Transmission Coefficient
Hot Fluid Cooling Fluid U
(Btu/ft2 hr ºF)Water Water 275-325Steam Water 300-500Steam Air 30-40
Heat Exchanger Design CalculationsModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
Calculation to select the right type of Heat exchanger.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #3\(5) Tab #3_HX Calc.xls ARCADIS
Page 2 of 2
Heat Exchanger Design CalculationsModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
LMTD = Log Mean Temperature Difference = (T1 -t2) - (T2 - t1)/ ln [(T1 -t2) / (T2 - t1)]
(T1 -t2) 95.0
(T2 - t1) 80.0
LMTD = Log Mean Temperature Difference = 87.3 ºF
Cf =
Required Surface area of the heat exchanger = 112 ft2
Required Surface area of the heat exchanger = 112 ft2
Based on the required surface area of the heat exchanger Model 08120 per foot from BASCO TYPE 500 Heat exchangers is selected.
Surface area of the selected heat exchanger 124.0 ft2
V. Check tube side velocity
Velocity should fall between 2 and 6 feet per second and should not exceed 8 feet per second.
Velocity factor for standard Tubing1/4" tubing = 9.663/8" tubing = 4.025/8" tubing = 1.47
Velocity factor of the selected model (Vf) with 3/8" tubing 1.47Flow rate of the cooling liquid 60.0 gpmNo of passes 4.0 noNo of tubes in the selected model 76 no
Velocity in the tube 4.6 ft/sec ok
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #3\(5) Tab #3_HX Calc.xls ARCADIS
Basco/Whitlock Shell and Tube Heat Exchanger
1 JOB NO.
2 CUSTOMER ARCADIS REFERENCE NO.
3 ADDRESS TAMPA, FL PROPOSAL NO.
4 PLANT LOCATION AOP PRE-TREATMENT SYSTEM DATE 2/ 2/2010
5 SERVICE OF UNIT ITEM NO.
6 SIZE 08114 TYPE 500 (HORIZ.) (VERT.) CONNECTED IN
7 SQ.FT. SURFACE (GROSS) (EFF.) 118.1 SHELLS/UNIT ONE SQ.FT.SURF/SHELL (GROSS)
(EFF.) 118.1
8 PERFORMANCE OF ONE UNIT 9 SHELL SIDE TUBE SIDE
10 FLUID CIRCULATED WATER WATER
11 TOTAL FLUID ENTERING LB/HR 78.7 GPM 60.0 GPM
12 VAPOR LB/HR
13 LIQUID LB/HR 39391.9 29498.1
14 STEAM LB/HR
15 NON-CONDENSIBLES LB/HR
16 FLUID VAPORIZED OR CONDENSED LB/HR
17 STEAM CONDENSED LB/HR
18 SPECIFIC GRAVITY 1.00 0.98
19 VISCOSITY @ TEMP cP @ ºF 1.08 @ 62 0.43 @ 150
20 MOLECULAR WEIGHT
21 SPECIFIC HEAT BTU/LB-ºF 0.999 1.000
22 THERMAL CONDUCTIVITY BTU/HR-FT-ºF 0.352 0.376
23 LATENT HEAT – VAPORS BTU/LB
24 TEMPERATURE IN ºF 40.0 180.0
25 TEMPERATURE OUT ºF 85.0 120.0
26 OPERATING PRESSURE PSIA
27 NO. PASSES PER SHELL ONE FOUR
28 VELOCITY FT/SEC 5.82 4.65
29 PRESSURE DROP PSI 13.26 4.13
30 FOULING RESISTANCE (Min) ºF-FT²-HR/BTU 0.0010 0.0020
31 HEAT EXCHANGED 1769989. BTU/HR MTD CORRECTED 81.85 ºF
32 TRANSFER RATE – SERVICE 183.04 CLEAN BTU/HR-FT²-ºF
33 CONSTRUCTION 34 DESIGN PRESSURE PSIG 300 150
35 TEST PRESSURE PSIG 100 100
36 DESIGN TEMPERATURE (Max/Min) ºF 300 / +20 300 / +20
37 TUBES Stainless Steel NO. 76 OD 0.625" BWG 18 LENGTH 114 PITCH 0.75" Tri
38 SHELL Carbon Steel ID 8.071 OD 8.625" SHELL COVER (INTEG)(REMOV)
39 BONNET/CHANNEL Cast 304 Stainless CHANNEL COVER
40 TUBESHEET-STATIONARY Stainless Steel TUBESHEET-FLOATING
41 BAFFLES - CROSS Carbon Steel TYPE Seg. FLOATING HEAD COVER
42 BAFFLES - LONG TYPE IMPINGEMENT PROTECTION
43 TUBE SUPPORTS
44 TUBE TO TUBESHEET JOINT Mechanically Rolled
45 GASKETS Compressed Fiber PACKING
46 CONNECTIONS-SHELL SIDE IN 3 OUT 3 RATING NPT
47 BONNET/CHANNEL SIDE IN 2 OUT 2 RATING NPT
48 CORROSION ALLOWANCE – SHELL SIDE TUBE SIDE
49 CODE REQUIREMENTS Commercial Standard TEMA CLASS
50 OTHER
51 REMARKS
52
53
54
• API Basco • 2777 Walden Avenue, Buffalo, NY 14225 • (716) 684-6700 Fax: (716) 684-2129 (mai22104.doc)
• www.apiheattransfer.com
Member Of:
LU
BUT
AR
AC
XE
MANTU
AS
SO
CIA
TO
N
G
NH
ERUFAC
ER
SR
������
������ ��
�� �����
...world leaders in heat transfer technology
�������������� �������������������������������� ������
���� ����� ��� ����� �� � ��
��� �����������������
��� ���������� ���� ����
���������������������
�� ��� �� ��� ��� ���
�������� ���������
���!����� ��� �""
��� ��� ���� ������
������� �� ��� ���� ����
��� ����� ����� ��� # � ��
�������������� ���������������
��������������� ���������������������������������
�������������� ���������������������������������������������������������������������������������������������� ���������������������������������������������������������������!���������"��#���������������������$����������������� ��%�&���%�&�'��&%($"����������� ������������������������������������������������������������������"
��������������������������� �������������������������
)�������������������������!�������������������������(����������������������������������������*������������������������������������������*�������������"���������������� ���������+
� ��������������$������������������������������������
� ,�����������������������������-���������(�����������������������
�������������"
� �� �����������$���������� ���������������� ���. '/ �$�0�����������������
����������� ������������������������������������������������"
� �� ������$���� �%������� �. '/ �$�0� ���������������� �����$����������
���������������������������������������� �������������������������
���������������������������������������������"
� �����������$����1�����$�������������������������������������� �������
���(������������"��2��������������������-������������������������������
�������������������������������"
� ������������������������������������������������������� ������������
���������������������!���*������������"��1�������������������������-����
�������������*����������������������������*������������"
���������������������� ���������������������������������� �������������������������������������������������������+
����������������� ���������������������������������������������������������������������������������������������������������������� ����������!����"���������
�������������������������������������������������������������� �������� ����
������������� ����������������������������������������� ������� ���� ��� ����� ������ ����������������������������
�������� ������!������������� ��"#$%#���&���� ���������������� � � ��������
�� �������� ������ ����!�"#$%#��&�!�������������!�'������� ������������ ������� �������������������������� ������� ����� ��������
(��� ��������� �������)��������*� �!�+� ���� ������������������%!�,� �-����� � �������� ���� . ���������������� �������������� ���(�'���� ����
/������ ���������� ����� ��������������� ������� �� ���� ���������������������� ������� ���� �� ����� �� ��� ����+������������������� ����������������� � ������������� ���� ���������
0���������������� ���������������������� ��� ���������������� � ��� ������� ��� ������������������� ������������ � ���� ����
������� ���������� ����� � ������� ��������������� ��������� ��������� ��� ������������ ��������������� ������� ��� ��� �� �������� ������������ ���� � ������������ �������
� !"�� ����������������������� ��������� � ��������� � ���������#����� ��� ���$���� ��%����������&� ��� ���� �%�����$��� ����������� ������������� ��$������������� �������� ���� �����������%������� �����
�������������� ��!������������"� ���������#�$�������
%,1���������������������������������������������!����� �����������*(������������������������������3������4�����������534�6��������������",����������������7�(������8��������������������(����������������������������"��9����34� ���(������������������������������ ������������������������ �����!�����������������������������������������������������������"�%,1���������1�:�. /���������������������������(�������������������������������������������������������������"
34������1�:�. /����������������������������� ��������������������� ������������������� �����������������!����� �����;��"�����!#��$"��"#��#�"����
'������()(�*�������(������ ��� ������������������ � ��������&�#������� ���� ��������
������������
������������ ���� �������� ������������������������ ������������ ���� ���� ����������������������� ��������������������������� ��������� ����������� ����������������������������������� ������������������ ����� �����!!��� ��������������������� ������� �����"��#��� ������������������� ���������� $���
������������� �������� �������������������������������������� %������&�'��������� ���� ������������������������������������� &�'��������������� ��������� ������������������������� &�'���������������������� �������������������������������� �����&�'�����������!!��� ����������������������������������� &�'���������������"��#��� ��������������������������������� ���������� $���
����������������� �������� ��������������������������� ������� ����� ���� ������������������������� ����������������������������� ��������� �������������� ������������������������������ �������������������� �������������������(�)���� �����!!��� ����������������������� �������������� ��"��#��� ��������������������� ���������� $���
������������ ������� ����� ���������������� ��������������������
���������������������������� ����������������� ��������������������
����������������� ����������� ���������������� ��������������������
� ��������������� ������� ������� ��� ����� ������ �������� ������� ����������� ������� ��������� �� ���� ��� ������ ����������������
� ����� ��������� � ���� �������1��� ������������2#-���������������� ����.����� ������ ����� ��� ��
'��(�� ���� ��������� ���� ��344�������� ��� ���� �(�'���� ���� ���� �� ��������������1��� ������������ ����%,44���������
������� �� ������ ��� +,-� ���������� ����� ����*.� ������������� ������� ���� ����������� ��� ���������
���� �(������ &� ������� ������� ����� �������� ��� /0-11&� +0211� ��� 30211� 4��� �����%�������� �����������&� +,-&� +/5� ��������������� ��� 6,0/,�( )��
����������7 �����������������*.���������������� ��������������� ���� ����������������� ���������� ������ ��� 6,0/,� ( )������ �%�������� ��� ���� ��8���
� ������9���������� ���������� �������������������������������������.������������������ ���� ��� �� �� � ���#������������������� %������� �� ��������� �%�������� ��:����� ��� +,-� ���������� ������
�� �� �(���� ��� ��������� ����� ������%�����������/&�;&����-����������������������*.� ���������������������� ������%����������� ���$��� ���������4������� ��� ���������� ����� ����� �����&� +,-� ����������&� ��� 6,0/,� ( )��� (���� ����� ����%�����������!���&�����+,-����������&�������:���8��� <��� ������ ��� ��� � ������ ������ ����������
����������� � � ������ ��� ������������������ ������� ��� ��8��� +11&� -11&� 311&� 511���211�������������������������������%��� ��� ������� ��� ����������
��������*.&���*.0�.*��(������%��������� ��� ������� ���������� (���=�������� /� ���� ����� ����� �������� ��� � ������ ���� ������� (��� =������� ;� ���� ���������� ����� ��� ����� ���� ������
�������.��������� ������������������������� #���� �� ����� � ������ ��� �����������
��������%��������������
����� ����� ����� ������� ������������������������������������������ ����������������� � !�� " #�� $ #�� ����� ��%� &�%� !�%�
'"'�! 2�%$-44 ������������ -�5 ,�6 � % %�%$, % %'"'&! 6�7 -�7 � 8-69 8,29 8%,9
'!'�! 6�" 3�# �'!'&! -�%$,44 ������������� %2�5 7�5 � %�%$, , %�%$- 2$-'!'"( ,#�- %,�, � 8759 8-29 8,,9
'$'�! %2�6 "�% 3�2'$'&! 3�%$-44 ���������� ,2�5 %3�6 "�% %�%$, ,�%$, %�%$, %'$'"( 23�- ,- %2�5 8%5#9 87#9 8-#9
'('&! 2-�3 ,,�7 %2�#'('"( 5�%$-44 ������������� 3%�7 2-�, %"�3 , 2 , ,'('!# 5"�% -3�5 ,5 8,2#9 8%%39 8369'('(' 75�- 36 2,�3
'#'&! � -3�5 ,-�"'#'"( � 57�2 26�2'#'!# 7�3$744 ���������� � "%�% -"�6 2 2 ,�%$, ,'#'(' � %%- 5,�% 8-5%9 8,2%9 8%%39'#')& � %25�6 6-�3
��� �������
������������������� ������������������������������� ����������������� &���� �*��� ������ ����������������� �*��� �*���
������� �� ������������&��+$����������������
����� ��������������������������������)����������������)����� �������
� ������������� �� ���8��>�����?
��������������������������
���� ���
�������������%�&����������'((� �����)�%�����
�������� �� ����� ������ ����� �� ���� ����� ��� � ��� �� �� ����� ������� �� �� � ��� �������� ������ �� ��� �������� �� ���� ������ ���� �� ���������� �����
����� ����� ����� ������� ������������������������������������������ ������ � ����� � !�� " #�� $ #�� ����� ��%� &�%� !�%�
'$'&! 3�%$-44 7#�����,7 � %3�6 ,7 %�%$, ,�%$, %�%$, %���� ���� 6�7 -�3 8%5#9 87#9 8-#9
'('&! 5�%$-44 %%5����-# � ,,�7 %2 , 2 , %�%$,���� ���� %%�- 5�3 8,2#9 8%%39 8369
'#'&! 7�3$744 ,2,����65 � -3�5 ,-�" 2 2 ,�%$, ,���� ���� ,,�7 %,�- 8-5%9 8,2%9 8%%39
��������������%�&����������'((� �����)�%�����
����� ����� ����� ������� ���������������������������������������� ������ ����� � !�� " #�� $ #�� ����� ��%� �&�%� !�%�
'$'&! 3�%$-44 ��������� � %- 5�3 %�%$, ,�%$, %�%$, %���� ���� 6�7 -�3 8%5#9 87#9 8-#9
'('&! 5�%$-44 �������� � ,#�- %% , 2 , %�%$,���� ���� %#�, 3�" 8,2#9 8%%39 8369
'#'&! 7�3$744 ������� � -#�" ,,�, 2 2 ,�%$, ,���� ���� ,#�- %%�% 8-5%9 8,2%9 8%%39
�'�&' %#�2$-44 �������� � 227 %"# -�.: 5�.: -�.: ,�%$,���� ���� 2- %" ����� ����� �����
�&�&' %,�2$-44 ��������� � 3#6 ,7% 5�.: 5�.: -�.: 2���� ���� 3% ,7 ���� ���� ����
���*����&�������%�&����� ���� �)�%�����
; ����� �������<�2$744�=>���%,�����?��3$744�=>���,#����������� �� ���� ��7������ �� �� �� ����<�%$%544� ��������� ���(�'���� �����.��������%3#@�'&�*������.��
����� ����� ����� ������� ���������������������������������������� ������ ����� � !�� " #�� $ #�� ����� ��%� &�%� !�%�
'$'!# 3�%$-44 ������� � ,6 %% %�%$, � %�%$, %���� ���� 5�7 ,�6 � ���� ����
'('!# 5�%$-44 ��������� � 3% %7�3 , � , %�%$,���� ���� %#�, -�5 � ���� ����
'#'!# 7�3$744 �������� � 7, --�3 2 � ,�%$, ,���� ���� ,#�3 %%�, � ���� ���
�������������'((�#&����� �����)�%�����
����� ����� ����� ������� ���������������������������������������� ������ ����� � !�� " #�� $ #�� ����� ��%� &�%� !�%�
�'�&' %#�2$-44 �������� � 23# %"3 -�.: � -�.: ,�%$,���� ���� 2- %" � ����� ����
�&�&' %,�2$-44 ������ � 3,6 ,"6 5�.: � -�.: 2���� ���� 3% ," � ����� �����
���*����&��#&����� �����)�%�����+
������������� �������������������������
����� � � � � � � ����� ����� � � � ����� ����� �
����� ����� ����� �� ����� ���� ����� ����� ���� ��� ��� � ����� ������ ��� �� ����� ������� �� ���� �����
����� � ���� ���������� ����� �� ���� ����� ����� ����� ����� ��� ��� ����� ����� ����� �� �� � ������ �� ���� �����
����� � ����� ������� ����� ���� �� ����� ����� � ����� � ��� � ��� ��� ����� �� � ���� �� ����� ������ �� ����� ��
����� ����� ����� ���������� ���� ����� ������ ����� ����� ����� ���� ����� ��� � ��� �� � ����� ����� � ��� � ������ ������ ����� ���������� ������ ���� ����
����� �� ������ ���������� �� ������ ���������� ��� ������ �� ����� ������ ����� ���� ����� �� � �� �� � ����� ����� ������ ��� � ������ �� ����� ��������� � ������ �����
�,"&�����-���
������������� �� ������� ������� ��������
�,"&������.-/!�&�����������&�
����� � � � � � � ����� ����� � � � ����� ����� �
����� ����� ���� �� ���� ����� � ����� � ��� � ��� ��� ����� ������ ����� ���� �� ����� ������ ���� ����� ������ ����� ������ ����� ���� ����� ��� � ��� �� � ������ ��� � ��� � ������ ��� ������ �� ���� ����� ����� ���� ����� �� � �� �� � � ������ ��� � �
���������������� �������� ������� ��������
����������� ���� ���������� � � ������ �� ������������ ���� ������������ ���� ��� � ��� ���� ��� ���� �� ������������ ��� ��� �� ���� �� ����� ����� ���� ����� ���� ���� !"#$$� ��� �� ��� %&� �������� ���� ���� �� ���� ���� '"#$$� ��� �� ��� &(� ������ � )�� � ���������*�+�%'(� ����,)� ��� ����-��������� ������������.������/��������������� �� ��� � � ���� ������ ������0� ��� �� ������� ������ ������� ����� ��.�������� ��� �.������/���� 1� �� � �����
����� � � � � � � ����� ����� � � � ����� ����� �
����� ������ ������ ������� ����� ����� ����� �� ������ � ����� ������ � ���� � ��� �� ������ ������ ������� ������� ������ ������ ����� �� ������ �� ����� ������ � ���� ���� �� �� �
������������������������ ������� ��������
��������"�� $"#�&�����-����������"��
$"#�&�����������&�������&�
����� � � � ����� ����� � � � � ����� ����� � �!"#$ � �����
����� ����� ����� �� �� � � ����� ����� �� �� ��� � � ����� ���������� ����� ����� �� ����� �����
����� ����� ����� �� ����� ���������� ����� ����� �� �� ����� ����� ����� ����� �� �� ��� ����� �� ����� ���������� ����� ����� �� ����� �����
����� �� ������ �� ����� ���������� �� � ���� �� ����� ����� ������ ������ ��� �� � ������ �� ����� ���������� �� ������� �� ����� �����
����� ����� ����� �� ������ ���������� ����� ����� � ��� � ����� ����� ����� � ��� ����� � ��� ������ ���������� ����� ��� ����� ��� ��� ������ ���������� ���� ���� ���� ���� ��� ������ �����
����� ����� ����� �� ����� ���������� ����� ����� ��� ����� ���������� ����� ����� ������ ��� ����� ����� ����� ����� ������ ��� � ����� �� ����� ���������� ��� ��� ��� ��� ��� ����� ���������� ���� ���� ���� ���� ��� ����� �����
������ �������
����������� ���� ���������� � � ������ �� ������������ ���� ������������ ���� ��� � ��� ���� ��� ���� �� ������������ ��� ��� �� ���� �� ����� ����� ���� ����� ���� ���� !"#$$� ��� �� ��� %&� �������� ���� ���� �� ���� ���� '"#$$� ��� �� ��� &(� ������ � )�� � ���������*�+�%'(� ����,)� ��� ����-��������� ������������.������/��������������� �� ��� � � ���� ������ ������0� ��� �� ������� ������ ������� ����� ��.�������� ��� �.������/���� 1� �� � �����
����� � � � ����� ����� � � � � ����� ����� � �!"#$ � �����
����� ������ ����� ���� �� ����� ����� ������ ����� ��� �� � ������ ����� ���������� ������ ��� � ��� � ����� ������ ��� � ��� ����� � ���� ���������� � ������ ��� ����� ����� ������ ������ ��� � ����� ����� �����
������ �������
����� � � � ����� ����� � � � � ����� ����� � �!"#$ � �����
����� � ���� � ��� ��� � � ���� � ��� ����� � � ���������� � ���� ���� �� ��� � � ���� ���� �� � � � �����
������ �������
��������������������������������
�,"&���#&�#0���"��!
����������� ���� ���������� � � ������ �� ������ ������ ���� ������������ ���� ��� � ��� ���� ��� ���� �� ������������ ��� ��� �� ���� �� ����� ���� ���� ���� �� ���� ���� !"#$$� ��� �� ��� %&� �������� ���� ���� �� ���� ���� '"#$$� ��� �� ��� &(� ������ � )�� � ���������*�+� %'(� ���� ,)� ��� ���
�,"&���#&�#0�����&������
������������� �� ������������� �������
����� � � � � � � ����� �����
����� ����� ���� ����� ����� ������ � ����� � ��� � ��� ��� �����
����� ���� ����� �� ����� ���� ����� ���� ����� ��� � ��� �� �
����� ��� ������ ������ ����� ������ ����� ���� ����� �� � �� �� �
��������������� ��� ��
����� � � � � � � ����� �����
����� ����� ���� ����� ���� ������ � ����� � ��� � ��� ��� �����
����� ���� ����� �� ����� ���� ����� ���� ����� ��� � ��� �� �
����� ��� ������ ������ ���� ������ ����� ���� ����� �� � �� �� �
��������������������� ��
����� � � � � � � � �
����� ������ ������ ��� ����� �� ����� �� ������ ��� ����� ������
����� ������ ������� ������� ������ ������ ����� �� ������ ��� ����� ������
������ �������
������ �������
������ �������
$"#�&���#&�#0���"��!
$"#�&���#&�#0�����&������
����������� ���� ���������� � � ������ �� ������ ������ ���� ������������ ���� ��� � ��� ���� ��� ���� �� ������������ ��� ��� �� ���� �� ����� ���� ���� ���� �� ���� ���� !"#$$� ��� �� ��� %&� �������� ���� ���� �� ���� ���� '"#$$� ��� �� ��� &(� ������ � )�� � ���������*�+� %'(� ���� ,)� ��� ���
� � � ����� ����� � � � � ����� ����� � �!"#$ � �����
������ ����� ���� �� ����� ����� ������ ����� ��� � � ������ � ������ �����
���� ��� � ��� � ����� ���� ��� � � ����� � ��� ������ �����
����� ������ ��� ����� ����� ����� ������ ��� � ����� ��� ����� �����
� � � ����� ����� � � � � ����� ����� � �!"#$ � �����
������ ����� ���� �� ����� ����� ������ ����� ��� � � ������ �� ������ �����
���� ��� � ��� � ����� ���� ��� � � ����� � ��� ������ �����
����� ������ ��� ����� ����� ����� ������ ��� � ����� ��� ������� �����
� � � % � � � � � % � � �!"#$ � �����
� ���� � �� ��� ��� � ���� � ��� ��� ����� ��� � �����
� ���� ���� ��� �� ��� � ���� ���� ��� �� � ��� � �����
����������������������� �
����������������������������������� �
���������������������������������� �
������������������ �������������� ��������������������� �������������� ��
��������������������� ����
����� �
�������������� �����������������������������������
������������������������������� ����!��"�����#�$������� "�� �������������� "� %&�%��������������������" ��������������� �'
� �� �������������&�(������)�����$����� *�����#"� (������* $��������*)������ ������ ��"��� �� *������#�"� (������� ������ �������'��"���������#��$������ ���������� ����#�� ���������&� � ������ ���"��� �)�� �#�������) ��������"������������ �'
�������������������+ ������#���������(�&�,�
�������������������+ ������#�-��������(�&�,�
��������������������� �#�����#���������(�&�,�
��������������������� �#�����#�-��������(�&�,�
����������������� ���������� ���� !��"##��������������
����������
����������� ��������������� ����������������������������������
������������ ����������������� �����������!�� ����"���� ��������
������������ �#���������$%������������������%���&�'������%���%��$(� ��$��
��� ������������� ����
)�*�+�,�+-������. �(�/�� ��01-���2�,�����0�������1��2
)�*�0���#���2�,�����,���)�*���34���5� -�05� 6��"���-� �2
���������������� ��������������
)�*���0����'��������"�����2��,�����'�1�%���%���,������
*��������*���3���)
�+�,����'�1�%���%� ���,����
���������� �������� ��������
������*
) ������*�������34���5� -
78#/�� �9���������%���������-���-�����������$-�������-����%$���������:�#������� ��%$��-�������������("��������-�%��� �����%�'��-������������ ��%$��-��������������'��'���� �������������%#���&���&��8#/�� ��
� ���� �������������� ����� ����� �
���� ; ���� 0 ����+2#�<�� ; #���� 0�������+2��� ; =��
+- ���� $����������"���� ����������%���*��������������"���� ����������%����*�=��
� �������������� !������"�#$%�
����* �*
�"���&'('���(���(
����� ��� �'$$�) ����� ���
>���������-��1����%�"����������%��-�����%�"�$����&���?�#������-������������=4�-�������@ ������������� �������%�������������������-���""�������%�
�������4�=4�-�����4�� �����%����%���%��=���@���������� ��� �������?�'���� ��� �-����!� ���'� ����� ���%����!�������+-��"��&�� ������ ���������'����������4�=�������+-���4�=4-�������!�� �����'����������:������+-����������"������
A%��-���&�%���-����-����@ ��������'�������!�������-����!�� ����'�����������-��-�����!�-�%$��3������$��������������@ �����
)
8�,�B�$����%�+��"�.������%��
)8�,�B�+.
��34���5� -���,���
� ���� �����*��� ��) ����� ��������
C� � ��%� ���� ����� �-�� ��� ��� ��%$�-� ��� �-�� -���� �!�-�%$����@ ��������������(���$�&�%����������%�����%���+-���("������ ��� ��������%���%���"�����%������������� ��%$���D
�E�FF�+ ��%$ ���������� ���4����@�����"����������� ��%$
=E�FF�+ ��%$ ���������� ���<����@�����"����������� ��%$
�E�FF�+ ��%$ ���������� ���4=4��@�����"����������� ��%$
B�%������������� ��%$���@ ������*
8��%$��-��"��&�� ���!��"�����
����B�%����������* ����"�&(&+���
� ���� �������,�����-������
C� ���%����� ������-��&������(�����-���� ������'�%$��-�� $-��-�� �����/������(��-� �����������'��%����%��4������"�������%��%��%����!������������"�������%���/������(�����������������%#������ ��%$����D
�E�FF�+ ��%$ ����������������� <�44�&������(�������3�0/�2
=E�FF�+ ��%$ ����������������� �����&������(�������3�0/�2
�E�FF�+ ��%$ ����������������� ���:�&������(�������3�0/�2
8��%$��-��"��&�� ���!��"�����
/������(� 0���E����2 *
"��&(&.���� ���������������,�
�������) ���� ����������� �
5� - * 5� E��%���,��4�5� - * G����"�'����,���3���5� - * H'��,��=3��=5� -� �� * ����0 ��2�,�����,��+5� -������ * ����0�����2�,�����,��+B�+.��� * B�+.��1��,�����
�/01�*���)���*���2�/�-*�2�������� ����� � ��� � ��� �� ���� � ����� ������ ��� �������� ����������
����� ��� � � � � � � � �� ��������������������� ��� � �� � � � �� �� ��������������� ��� � �� � �� � ! �� ���"�� ��� � # � �� � ���$%&
�/01�*��3-��*���24-*�2��
)�������� ������������� 24- ��� 5�� �� �6����� ����� ������� � ����� �� ������� ������� ������� � ������� � � ������� ������ ������ ��� �� ��������� ������ ������ ��� ��������� ������ ������ !��"�#��$%� ����� ���������� ����� � ������� ������ ��� ������� ���� ���������� ������� ���� ������ � ������� ������� ���������� ������ ��� �������� ������� ��� ���� ����� ��� ����� �� ���� ��������
����>�@ ����?��
���+ ������
��������7
�4��@�������4�� �����,�����<��
�4�=�0���2�,������0/�2�,���0������2
��4�0?�������+ ���2
"�8.(9�:0�
������������ ���������� �������������������� �� ����� ����� ��� ��������� ������������ ���� �� ������ ������������������� ���������� ��� ���������� �� ����� ������� �� ������ ������ ������������� ��� � !�"# ��$ �� #"�� � %���& ��$�
� ���� ������� �� '()� ����� ��� ������������ �������������� �� ����� ������� �������� ��*�� ��� ���������� �������������� ���� ��� � !�"# ��$ �� �%�� � !"�#��$� ��)(� '()�� �+,� �-�� './� ,�+(�0��� ����� ���� ������������ ���������
��������� ���� ����
����������� ��������
�������� �� .���� ��1�� �� ��������������� ������� ������ �1�������� ��������� �� ���� ���� ������ ���������� ��� �������� ��������� ������ � ������� �� ���� �������������� ��� ��������� ��� ��������� ���������� ���� 2�� �3��" ��$ �� "�� �2%�#& ��$�
������������� �����������������������
4������������� �������� ���� ������� ��� �������� ����� ���� �1������� ���������� �����1��� ����������� ��� ��� ����� ,������� 4() �� ��������5�� ������������� )��������� ����5�� ��� ����� �� ����� )�������� ������� �� ������������� �������������
��������������������������
.��6�� �������� ��������� ������ ������������� �� �1��� ���������� �������������� ����������� ������������ ��� �������������� ����� ������ ���������� �������������)( ���� ������ �� ��������� ������������� "%�� �!%�& ��$ �� "%�� �2%#�& ��$�
�������� ������
7��� ����������� ��*�� ������ ���������� ������� � ���� ������� �� ��6��� �������� ���� ������ ���� 0����������� ��������� 8����� �� ������� ������� ������� ������ ���� )����� ��� � ������� ����������� ��� ��� � ������� �� �������
����� �������� ����������
8������ ���� ������� �1������� ���� ��������� ��� ����� ��*�� +����� ��� ������� ������������� ������ '������ ��� ����� �������9��5��� �� :������� (+�)� /��������������������� ��� '������ ��� ���� 9��5������������� ��� ��*�� ������� ���������
�������������������
������������ �������� ���� �1��������� ���� ���� �������� �����������;������� ������� ��� ���� ���5 ������������ ���� ������������ ��������� ���� 2���3��" ��$ �� #"�� � %���& ��$� ��)(� �+,�'()�� �-� ��� ����� ����� ���������
��� ������
����� ����� ���� ������� ��� ����� ���� � �� ����� ���������� ����
������������� �������������� ����������������
����������
����� ��� ISO-9001 Certified
Air Cooled Aluminum Heat Exchangers
91 North Street • P.O. Box 68
Arcade, New York 14009-0068
(716) 496-5755 • Fax: (716) 496-5776
������� ISO-9001 Certified
Basco®/Whitlock® Shell & Tube Heat Exchangers
2777 Walden Avenue
Buffalo, New York 14225
(716) 684-6700 • Fax: (716) 684-2129
���� ���Acme® Refrigeration Equipment
2300 West Marshall Drive
Grand Prairie, Texas 75051
(972) 647-2626 • Fax: (972) 641-1518
�������� ���� ��Plate Heat Exchangers and
Thermal Process Systems
2777 Walden Avenue
Buffalo, New York 14225
(716) 684-6700 • Fax: (716) 684-2129
�������� ���� �������.
ISO-9001 Certified
Plate Heat Exchangers and
Thermal Process Systems
P.O. Box 1580 D-75005 Bretten
Pforzheimer Strasse 46
D-75015 Bretten, Germany
49-7252-53101 • Fax: 49-7252-53201
� ��������� ����� ������������ ����������������� ��������� ��� !!�����"��#
$������ �%%%# ���� ��� �����#��&����& ���� � � ���' ���� ��� �����#��&
������������ ��������������������������� ���������������� !� "�# �$$
Tab 4
Modified ISR System – AOP Pre-Treatment System Influent Equalization and Iron Oxidation
Page 1 of 1
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate: 01/28/2010
Considerations:
Useable tank volume = 18,000 gal
Process flow rate = 60 gpm Heat Exchanger Effluent
Total retention time = 300 min
Operation = 50 % Full
Design retention time = 150 min
Additional requirements = 0 gal
Calculate Required Tank Volume:
Retention time volume = Flow rate x Design retention time
9,000 gal
Minimum volume = Retention time volume + Additional requirements
9,000 gal
Tank Selection:
Rectangular Tank:
Length = 37.5 feet
Width = 8.5 feet
Height = 11 feet
Volume = 18,000 gal
Available Tank Volume = 18,000 gal
Required Tank Volume = 9,000 gal
Volume Available > Volume Required therefore design is acceptable
INFLUENT EQUALIZATION TANK (T-200A) SIZINGModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #4\(1) Tab #4_T-200A Sizing.xlsxEQ T-200A ARCADIS
Page 1 of 1
Calc prepared by: M. SeppanenCalc checked by: J. DarbyDate: 01/28/2010
Considerations:
Useable tank volume = 18,000 gal
Process flow rate = 60 gpm EQ Tank (T-200A) Overflow
Total retention time = 300 min
Operation = 90 % Full
Design retention time = 270 min
Additional requirements = 0 gal
Calculate Required Tank Volume:
Retention time volume = Flow rate x Design retention time
16,200 gal
Minimum volume = Retention time volume + Additional requirements
16,200 gal
Tank Selection:
Rectangular Tank:
Length = 37.5 feet
Width = 8.5 feet
Height = 11 feet
Volume = 18,000 gal
Available Tank Volume = 18,000 gal
Required Tank Volume = 16,200 gal
Volume Available > Volume Required therefore design is acceptable
INFLUENT EQUALIZATION TANKS (T-200B/C) SIZINGModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #4\(2) Tab #4_T-200B&C Sizing.xlsxEQ T-200B&C ARCADIS
To the best of our knowledge the technical data contained herein are true and accurate at the date of issuance and are subject to change without prior notice. No guarantee of accuracy is given or implied because variations can and do exist. NO WARRANTY OR GUARANTEE OF ANY KIND IS MADE BY BAKERCORP, EITHER EXPRESSED OR IMPLIED.
3020 OLD RANCH PARKWAY • SUITE 220 • SEAL BEACH, CA • 562-430-6262
Technical Information Manual
2.2.15
PRODUCT DATA SHEET February, 2008
EZ CLEAN FIXED AXLE SAFETY VAPOR TANK
GENERAL INFORMATION Vapor tight steel tank with two sealed top access hatches and pressure/vacuum relief valve. Smooth interior walls for easy cleaning. WEIGHTS AND MEASURES
» Capacity: ....... 480 BBL (20,160 gal.)
» Height: ....... 11’-2” (grade to roof deck) 14’-8” (grade to top of upright guardrails)
» Width : ....... 8’-6” (between side runners) » Length: ....... 39’-9” (front nose to outside of rear stairway) 37’-6” (tank only)
» Weight:
....... 24,480 lbs.
STRUCTURAL DESIGN
» Floor: ....... ¼”thick ASTM A36 carbon steel (V-bottom)
» Sides/Ends: ....... ¼” thick ASTM A36 carbon steel
» Roof Deck: ....... ¼” thick ASTM A36 carbon steel
» Wall Frame: ....... 3/16”x3”x5” ASTM A36 formed channel
» Roof Frame: ....... 3/16”x3”x5” ASTM A36 formed channel
» Skid Rails: ....... C8x11.5 structural channel
FEATURES
» Valves: ....... 1-Front &1-Rear: 6”- wafer butterfly valve. Cast iron body, Buna-N seat & seals, 316 SS stem, Nylon 11 coated ductile iron disk w/ plug and chain.
» Relief Valve: ....... 16 oz./in2 pressure setting, 0.4 oz./in2 vacuum setting; Buna-N seal
» Roof Deck Connections:
....... Vapor Recovery: 4”-150# flange (blinded) Gauging Port: 4” flange (blinded) with 2” threaded plugged port in blind flange.
» Side Manways: ....... One or two (depending on make of tank) on curb side of tank.
FEATURES – cont.
» Front Piping Connections:
....... Bottom Drain: 6”-150# flanged nozzle and butterfly valve Inlet/Outlet: 2 - 4”-150# raised face flange with blind flange (chained)
» Rear Piping Connections:
....... Bottom Drain: 6”-150# flanged nozzle and butterfly valve Inlet/Outlet: 2 - 4”-150# raised face flange with blind flange (chained)
» Interior Access: ....... 2-50” long x 32” wide hinged vapor-proof marine-style hatches with neoprene gaskets and removable fall protection grid.
» Hatch and Manway Seals:
....... Neoprene gasket
» Roof Access Stairway:
....... Rear mounted – lower section folds up for transport and down for use. Stairway includes handrails.
» Guardrails: ....... Top deck, fold-down, 1¼” x 1¼” square tubing.
» Internal Ladder: ....... One; mounted below front-end interior access hatch on roof deck.
» Level Indication: ....... Ball style with 2-8” 304 SS floats with pointer-indicator on front endwall. Floor supports hold floats ½” off floor. [One 2” plugged connection for optional electronic gauge on top deck.]
» Axle: ....... 77½ track straight, non steer, 22,500# capacity.
» Suspension: ....... Silent Drive, 3 air-bags with manual release.
SURFACE DETAILS
» Exterior Coating: ....... High Gloss Polyurethane
» Interior Coating: ....... None
TESTS/CERTIFICATIONS
» Tests Performed: .......
Major repairs – hydrotest Scheduled- Level I, II and III inspections, including NESHAP testing
Page 1 of 3
Total dynamic head calculation = Calc prepared by: M. Seppanenhead loss due to elevation change Calc checked by: J. Perellahead loss due to pipe friction Date: 1/28/2010head loss across misc. process componentsrequired discharge head
Calculate pipe size:
Where: v = Velocity (ft/sec)Q = Flow rate (gpm)r = Pipe radius (in)
Flow Rate Pipe Size Pipe ODWall
Thickness Pipe ID Area velocity(gpm) (in) (in) (in) (in) (ft2) (ft/sec)
60 2 2.375 0.154 2.067 0.023 5.5860 3 3.500 0.216 3.068 0.051 2.5360 4 4.500 0.237 4.026 0.088 1.47
*Pipe dimensions noted for Schedule 40 galvanized steel piping.Note: Design for velocity between 3 and 5 feet/sec to maintain sufficient scour velocity
Calculate head loss (he) due to elevation change:
assume: Height from pump to discharge point = 15 feetHead loss, he = 15 feet
Calculate head loss due to pipe friction losses:
Step 1. There are multiple pipe sections with flow and pipe diameters shown below
Pipe Section 1 Nominal pipe diameter 1 = 3 inch
Flow (v1) = 60 gpm
Step 2. Calculate the friction factor for each pipe section using the Hazen-Williams formula
Hazen-Williams f = .2083 * (100/C)1.852 * (q1.852) / (D4.8655)Formula
f = Friction in head in feet of water per 100 ft of pipeC = Constant for inside roughness
(140 for new galvanized steel pipe, 150 for hdpe pipe)q = Flow rate (gal/min)D = Inside diameter of pipe (inches)
Nominal Diam (in)
ID (in)
ID w/ deposition (in)
1 1.049 0.9241.5 1.610 1.4852 2.067 1.9423 3.068 2.9434 4.026 3.9016 6.065 5.94
NOTE: a 0.0625 inch (1/16 inch) deposition on interior pipe wall is included in diameter for calculation - 1.003 - (2 x 0.0625) = 0.878 inch diameter
Modified ISR System - AOP Pre-Treatment SystemAERATION TANK FEED PUMP (P-200A/B) DESIGN CALCULATIONS
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
sec60
min1*
)*( 2r
Qv
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #4\(4) Tab #4_P-200A&B TDH.xlsx ARCADIS
Page 2 of 3
Modified ISR System - AOP Pre-Treatment SystemAERATION TANK FEED PUMP (P-200A/B) DESIGN CALCULATIONS
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Friction factor for Pipe Section 1C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 60 gal/minD1 = Inner pipe diameter (inches) 2.943 inches (see NOTE)
Pipe Section friction factor 1.1 ft water / 100 feet of pipe
Step 3. Calculate the equivalent length of pipe for each section
Nominal Fitting size 1 in 1.5 in 2 in 3 in 4 in 6 in
90˚ Elbows 2.7 3.4 3.6 4.0 4.6 10.4Standard Tee (thru flow) 3.2 5.6 7.7 12.0 17.0 38.3Standard Tee (branch flow) 6.6 9.9 12.0 17.0 21.0 47.3Ball valve (full open) 1.6 2.3 2.9 4.3 5.5 12.3Check Valve 11.0 15.0 19.0 27.0 38.0 85.5Union 0.3 0.4 0.5 0.5 0.7 1.5Reducer (2/1) 1.0 1.5 1.5 3.0 4.0 9.0Expansion (1/2) 1.5 2.5 3.0 4.0 6.0 13.5
Equivalent lengths from reference: Civil Engineering Reference Manual, 9th Ed, Professional Publications, Inc., 2003;and "Flow of Fluids", Crane Technical Paper No. 410, 1988.
Pipe Section 1 - 3"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 60 60Standard Tee (thru flow) 4 12 48Standard Tee (branch flow) 2 17 3490˚ Elbows 8 4 32Union 4 0.5 2Check Valve - Swing 1 27 27Ball valve (full open) 4 4.3 17
Equivalent Length: 220
Step 4. Determine pipe friction for each pipe section.
total pipe friction = total equivalent length x friction factor
Total Pipe Friction - Pipe Section 1total equivalent length = 220 feet
friction factor = 1.1 feet water / 100 feet of pipe
Total Pipe Friction = 2.5 feet
Step 5. Determine total pipe friction (all sections)
Total Pipe Friction - Pipe Section 1 = 2.5
Equivalent Length
Equivalent Length per Fitting (ft)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #4\(4) Tab #4_P-200A&B TDH.xlsx ARCADIS
Page 3 of 3
Modified ISR System - AOP Pre-Treatment SystemAERATION TANK FEED PUMP (P-200A/B) DESIGN CALCULATIONS
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Calculate Total Dynamic Head:
Head Loss Due to Change in Elevation 15 ft
Head Loss due to pipe friction 2.5 ft
Head Loss Across Misc. Process Components 0 ft
Required Discharge Pressure (0 psi) 0 ft
Total Dynamic Head Required - Calculated 18 ft
Design Safety Factor 100%
Total Dynamic Head Required - Design 35 feet
Pump Design Requirements:Flow 60 gpm
Total Dynamic Head 35 feet
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #4\(4) Tab #4_P-200A&B TDH.xlsx ARCADIS
Model: 3196 Size: 2X3-8 Group: MTi 60Hz RPM: 1750 Stages: 1
Job/Inq.No. : RAYTHEONPurchaser : ARCADISEnd User : ARCADIS Issued by : Rev. : 0Item/Equip.No. : P-200AB Quotation No. : RAPA PRETREATMENT Date : 02/03/2010Service :Order No. :
Operating Conditions Pump PerformanceLiquid: Water Published Efficiency: 45.0 % Suction Specific Speed: 8,693 gpm(US) ftTemp.: 120.0 deg F Rated Pump Efficiency: 45.0 % Min. Hydraulic Flow: 6.3 gpmS.G./Visc.: 1.000/1.000 cp Rated Total Power: 1.2 hp Min. Thermal Flow: N/AFlow: 60.0 gpm Non-Overloading Power: 1.5 hpTDH: 35.0 ft Imp. Dia. First 1 Stg(s): 5.8750 inNPSHa: NPSHr: 2.5 ftSolid size: Shut off Head: 37.5 ft% Susp. Solids(by wtg):
Vapor Press:
Max. Solids Size: 0.5000 inNotes: 1. The Mechanical seal increased drag effect on power and efficiency is not included, unless the correction is shown in the
appropriate field above. 2. Magnetic drive eddy current on power and efficiency is not included. 3. Elevated temperatureeffects on performance are not included. 4. Non Overloading power does not reflect v-belt/gear losses.
Page 1 of 3
RECIRCULATION PUMP (P-200C) DESIGN CALCULATIONS
Total dynamic head calculation = Calc prepared by: M. Seppanenhead loss due to elevation change Calc checked by: J. Perellahead loss due to pipe friction Date: 1/28/2010head loss across misc. process componentsrequired discharge head
Calculate pipe size:
Where: v = Velocity (ft/sec)Q = Flow rate (gpm)r = Pipe radius (in)
Flow Rate Pipe Size Pipe ODWall
Thickness Pipe ID Area velocity(gpm) (in) (in) (in) (in) (ft2) (ft/sec)
40 1.5 1.900 0.145 1.610 0.014 6.1340 2 2.375 0.154 2.067 0.023 3.7240 3 3.500 0.216 3.068 0.051 1.69
*Pipe dimensions noted for Schedule 40 galvanized steel pipingNote: Design for velocity between 3 and 5 feet/sec to maintain sufficient scour velocity
Calculate head loss (he) due to elevation change:
assume: Height from pump to discharge point = 15 feetHead loss, he = 15 feet
Calculate head loss due to pipe friction losses:
Step 1. There are multiple pipe sections with flow and pipe diameters shown below
Pipe Section 1 Nominal pipe diameter 1 = 2 inch
Flow (v1) = 40 gpm
Step 2. Calculate the friction factor for each pipe section using the Hazen-Williams formula
Hazen-Williams f = .2083 * (100/C)1.852 * (q1.852) / (D4.8655)Formula
f = Friction in head in feet of water per 100 ft of pipeC = Constant for inside roughness
(140 for new galvanized steel pipe, 150 for hdpe pipe)q = Flow rate (gal/min)D = Inside diameter of pipe (inches)
Nominal Diam (in)
ID (in)
ID w/ deposition (in)
1 1.049 0.9241.5 1.610 1.4852 2.067 1.9423 3.068 2.9434 4.026 3.9016 6.065 5.94
NOTE: a 0.0625 inch (1/16 inch) deposition on interior pipe wall is included indiameter for calculation - 1.003 - (2 x 0.0625) = 0.878 inch diameter
Modified ISR System - AOP Pre-Treatment SystemTotal Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
sec60
min1*
)*( 2r
Qv
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #4\(6) Tab #4_P-200C TDH.xlsx ARCADIS
Page 2 of 3
RECIRCULATION PUMP (P-200C) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Friction factor for Pipe Section 1C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 40 gal/minD1 = Inner pipe diameter (inches) 1.942 inches (see NOTE)
Pipe Section friction factor 4.1 ft water / 100 feet of pipe
Step 3. Calculate the equivalent length of pipe for each section
Nominal Fitting size 1 in 1.5 in 2 in 3 in 4 in 6 in
90˚ Elbows 2.7 3.4 3.6 4.0 4.6 10.4Standard Tee (thru flow) 3.2 5.6 7.7 12.0 17.0 38.3Standard Tee (branch flow) 6.6 9.9 12.0 17.0 21.0 47.3Ball valve (full open) 1.6 2.3 2.9 4.3 5.5 12.3Check Valve 11.0 15.0 19.0 27.0 38.0 85.5Union 0.3 0.4 0.5 0.5 0.7 1.5Reducer (2/1) 1.0 1.5 1.5 3.0 4.0 9.0Expansion (1/2) 1.5 2.5 3.0 4.0 6.0 13.5
Equivalent lengths from reference: Civil Engineering Reference Manual, 9th Ed, Professional Publications, Inc., 2003;and "Flow of Fluids", Crane Technical Paper No. 410, 1988
Pipe Section 1 - 1-1/2"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 100 100Standard Tee (thru flow) 4 7.7 31Standard Tee (branch flow) 1 12 1290˚ Elbows 6 3.6 22Union 2 0.45 1Check Valve 1 19 19Ball valve (full open) 2 2.9 6
Equivalent Length: 190
Step 4. Determine pipe friction for each pipe section.
total pipe friction = total equivalent length x friction factor
Total Pipe Friction - Pipe Section 1total equivalent length = 190 feet
friction factor = 4.1 feet water / 100 feet of pipe
Total Pipe Friction = 7.8 feet
Step 5. Determine total pipe friction (all sections)
Total Pipe Friction - Pipe Section 1 = 7.8
Equivalent Length
Equivalent Length per Fitting (ft)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #4\(6) Tab #4_P-200C TDH.xlsx ARCADIS
Page 3 of 3
RECIRCULATION PUMP (P-200C) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Calculate Total Dynamic Head:
Head Loss Due to Change in Elevation 15 ft
Head loss due to pipe friction 7.8 ft
Head loss Across Misc. Process Components 0 ft
Required Discharge Pressure (0 psi) 0 ft
Total Dynamic Head Required - Calculated 23 ft
Design Safety Factor 100%
Total Dynamic Head Required - Design 46 feet
Pump Design Requirements:Flow 40 gpm
Total Dynamic Head 46 feet
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #4\(6) Tab #4_P-200C TDH.xlsx ARCADIS
Model: 3196 Size: 2X3-8 Group: MTi 60Hz RPM: 1750 Stages: 1
Job/Inq.No. : RAYTHEONPurchaser : ARCADISEnd User : ARCADIS Issued by : Rev. : 0Item/Equip.No. : P-200C Quotation No. : RAPA PRETREATMENT Date : 02/03/2010Service :Order No. :
Operating Conditions Pump PerformanceLiquid: Water Published Efficiency: 36.0 % Suction Specific Speed: 8,693 gpm(US) ftTemp.: 120.0 deg F Rated Pump Efficiency: 36.0 % Min. Hydraulic Flow: 7.0 gpmS.G./Visc.: 1.000/1.000 cp Rated Total Power: 1.3 hp Min. Thermal Flow: N/AFlow: 40.0 gpm Non-Overloading Power: 1.9 hpTDH: 46.0 ft Imp. Dia. First 1 Stg(s): 6.5000 inNPSHa: NPSHr: 2.0 ftSolid size: Shut off Head: 47.1 ft% Susp. Solids(by wtg):
Vapor Press:
Max. Solids Size: 0.5000 inNotes: 1. The Mechanical seal increased drag effect on power and efficiency is not included, unless the correction is shown in the
appropriate field above. 2. Magnetic drive eddy current on power and efficiency is not included. 3. Elevated temperatureeffects on performance are not included. 4. Non Overloading power does not reflect v-belt/gear losses.
Page 1 of 1
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate: 01/28/2010
Considerations:
Tank volume = 6,500 gal
Solids Storage = 310 gal 6-inch Depth
Freeboard = 619 gal 12-inch Depth
Usable tank volume = Total tank volume - Solids storage - Freeboard
Usable tank volume = 5,571 gal
Process flow rate = 60 gpm EQ Tank (T-300A) Effluent
Total retention time = 93 min
Operation = 83 % Full
Design retention time = 77 min
Additional requirements = 0 gal
Calculate Required Tank Volume:
Retention time volume = Flow rate x Design retention time
4,628 gal
Minimum volume = Retention time volume + Additional requirements
4,628 gal
Tank Selection:
Cylindrical Tank:
Diameter = 10.0 feet
Sidewall Height = 10.5 feet
Usable Tank Volume = 5,571 gal
Available Tank Volume = 5,571 gal
Required Tank Volume = 4,628 gal
Volume Available > Volume Required therefore design is acceptable
AERATION TANK (T-300) SIZINGModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #4\(8) Tab #4_T-300 Sizing.xlsx ARCADIS
Technical Information Manual
2.4.4
PRODUCT DATA SHEET January, 2007
6500 GALLON POLY TANK (Original Style and Total Drain)
GENERAL INFORMATION This type of tank is not to be used for food applications. Potable water applications are generally not acceptable and must be reviewed by the Corporate office first for approval. WEIGHTS AND MEASURES
» Capacity: _ 6500 gallons (nominal)
» Height‡: _ 10’-6” (to top tangent line) 11’-11” (to top of dome) 12’-4” (to highest point on top lid)
» Diameter: :
_ 10’-0” (nominal)
To the best of our knowledge the technical data contained herein are true and accurate at the date of issuance and are subject to change without prior notice. No guarantee of accuracy is given or implied because variations can and do exist. NO WARRANTY OR GUARANTEE OF ANY KIND IS MADE BY BAKERCORP, EITHER EXPRESSED OR IMPLIED.
3020 Old Ranch Parkway • Suite 220 • Seal Beach, CA • 562-430-6262
» Weight*:
_ Tank: 1700 lbs. – 1975 lbs. Pad: 400 lbs. - 450 lbs.
*Varies with origin of manufacture ‡ Does not include height of pad. Add four inches for pad thickness to determine heights from grade when pad is used. DESIGN PARAMETERS
» Tank Material:
_ High Density Polyethylene
» Design Pressure:
_ 0 psi – vented to atmosphere
» Design Vacuum:
_ 0 psi – vented to atmosphere
» Spec. Gravity Limit:
_ Original Style – 1.65 Total Drain – 1.9
» Temp. Limit: _ 150° F » Certification: _ ASTM D1998 (not UL listed)
RESTRICTIONS
» Sulfuric Acid Storage:
_ • 80% concentration maximum • Use only tanks with equipment
numbers ≥ 7376 • Previously repaired tank cannot be
used (equipment number should have “W” at end)
• 100° F maximum temperature • Top fill only • Top manway must be open during
pneumatic filling of tank • Use flexible plumbing fixtures resistant
to sulfuric acid FEATURES
» Top Vent: _ 2” PVC U-vent (two threaded street elbows)
» Manway: _ Top mounted with 24” opening (34 inch diameter screw-on cover)
» Valves: _ 3” butterfly valve with PVC body and disc, Viton O-Ring seal and 316 SS stem.
» Ladder: _ Top mounted bracket for ladder hook-up. Ladder is not permanently mounted to tank.
» Piping Connections:
_ Inlet – 3” with butterfly valve Outlet – 3” with butterfly valve Top – 4” PVC adapter and PVC cap
MISCELLANEOUS
» Options: _ Secondary containment berm
Page 1 of 1
Calc prepared by: M. SeppanenCalc checked by: J. DarbyDate: 1/28/2010
Determine amount of oxygen required to oxidize dissolved iron:
Input Water flow rate 60 gpmInput Ferrous iron concentration 20 mg/L Fe+3
Calc Amount of ferrous iron (1) 14.41 lbs/day Fe+3
Known mg O2 required to oxidize mg Fe+2 (2) 0.143 mg O2/mg Fe+3
Calc Amount of oxygen required to oxidize ferrous iron 2.06 lbs/day O2
Determine airflow rate required to oxidize ferrous iron:
Calc from above Amount of oxygen required to oxidize ferrous iron 2.06 lbs/day O2
Input Transfer efficiency (3) 2%Calc Pounds of oxygen injected 103.04 lbs/day O2
Known Density of oxygen 0.08 lbs/ft3 O2
Calc Free oxygen flow rate 1224.02 ft3/day O2
Calc Free oxygen flow rate 0.850 ft3/min O2
Calc Free air flow rate 4.05 ft3/min airCalc Free air flow rate 114.55 liters/min
Input Safety factor (4) 2
Calc Injected free air flow rate 8.095 ft3/min airCalc Injected free air flow rate 229.099 liters/min
NOTES:
(1) lbs/day = 8.34 x mg/L x MGD(2) 4 Fe+2 + 2H+ + O2 ---> 4Fe+3 + 2OH-, stochiometric = 1 O2 : 4 Fe+2, mass basis 1 O2 : 7 Fe+2
(Source: Montgomery, Water Treatment Principles and Design, page 340, 1985) (3) Professional judgment - contact tubing system similar to efficiency of 10-foot deep tank .(4) Selected to match design conditions of a similar system.
IRON OXIDATION DESIGN CALCULATIONModified ISR System - AOP Pre-Treatment System
Total Air Requirement Calculation
Raytheon CompanySt. Petersburg, Florida
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #4\(10) Tab #4_Air Rqmts - Fe Ox.xls ARCADIS
Page 1 of 2
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate: 1/28/2010
I. Define System Parameters
a. Conveyance PipingInternal Diameter of Conveyance Piping 2.067 in (2-in. Nominal Dia., galv. steel)
0.17 ftMin. Flow Rate per Conveyance Line 36.0 ft3 / minFlow velocity 25.7 ft / sec
II. Define Flow Characteristics
a. Conveyance Piping
where:NRe = Reynolds Number
Internal Diameter of Conveyance Piping, D 2.067 in0.17 ft
AERATION BLOWER (B-100A/B) DESIGN CALCULATIONSModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
Calculate friction loss due to air flow through piping.
eeR
DN
mean velocity of flow, v 25.7 ft / secweight density of fluid (assume air), ρ 0.0752 lb / ft3
1.89E-05 kg / (m*sec)dynamic viscosity, e 1.27E-05 lb / (sec*ft)
Reynolds Number, N Re 26,260 (dimensionless)
(NRe < 2000 = Laminar, NRe > 4000 = Turbulent)
Flow is Turbulent
III. Determine Friction Factors
In the turbulent regime, the friction factor can be approximated by;Note: This equation applies for smooth piping onlyOther materials require friction factor obtained from Friction Factor chart
a. Conveyance Piping
Friction Factor, f 6.22E-03 (dimensionless)
eeR
DN
32.0Re
125.00014.0
Nf
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #4\(11) Tab #4_B-100 Calc.xls ARCADIS
Page 2 of 2
AERATION BLOWER (B-100A/B) DESIGN CALCULATIONSModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
IV. Determine Other Resistance Losses
a. Conveyance Piping
Ball Valve 2 0.06 1 0.06Diaphragm Valve 2 6.5 1 6.590 Degree Elbow 2 0.57 6 3.42
Total K 9.98
V. Determine Pressure Loss/Drop
a. Conveyance Piping
i. Conveyance Pipe Length, L 140 ftii. No vertical height change, therefore, Za-Zb = 0 20 ft [assumed]
iii. Gravity, g 32.2 ft / sec2
iv. gc 32.2 lb-ft / sec2-lbf
Pressure Drop, ∆Pa 25.61 lb / ft2
0.18 psi
4.9 in. water
csba
c gK
D
LfZZ
g
gP
2)4()(
2
Re
VI. Other Items
Coarse Bubble Diffuser 2.75 in. water [2.75 in wc / diffuser]
Water Depth above Diffusers 108 in. water
VII. Total Pressure Blower will be required to Generate
ΔPa 4.9 in. waterOther Items 110.8 in. waterSafety Factor 20%
Total Pressure Required 138.81 in. water
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #4\(11) Tab #4_B-100 Calc.xls ARCADIS
Becker Pumps Corp. • 100 East Ascot Lane • Cuyahoga Falls, Ohio 44223-3768 Ph. (330) 928-9966 • (888) 633-1083 • FAX: (330) 928-7065 • [email protected] • www.beckerpumps.com
KDT Series100% OIL-LESS COMPRESSORS
ISO 9001 Certified Compliant
The Becker KDT series is a line of 100% Oil-less, rotary vane, low pressure compressors. They are designed to operate on a continuous basis throughout a pressure range from atmospheric pressure to 22 PSIG.
Each KDT unit is a direct drive com-pressor and is supplied with a TEFC flange mounted electric motor. Each unit is equipped with inlet and discharge filters, a pressure regulating valve, and vibration isolators as
standard equipment, all of which are an integral part of the compressor.
The Becker KDT compressor is ideal for applications where air is the gas and where operation is in the low pressure range where high pressure compressors are less efficient. Applications for the KDT compressor include graphic arts,
soil remediation, pneumatic convey-ing, robotics and material handling,
packaging, and paper converting.
* @ 29.92" Hg Bar. Pr.; 68oF; 36% R.H.; 0.075#/ft3
1
4
6
8
12
50
20
30
40
60
70
120
90
80
KDT 3.140
0 2 4 6 8 10 12 14 16 2018 2210
9
7
5
3
2
SCFM*
SCFM*
SCFM*
SCFM*
BHP
BHP
BHP
BHP
KDT 3.100
KDT 3.80
KDT 3.60
FLO
W (
SCFM
*)
PO
WER
REQ
UIR
EMEN
TS (
HP
)
PRESSURE (PSIG)
100
110
10
11
Becker Pumps Corp. • 100 East Ascot Lane • Cuyahoga Falls, Ohio 44223-3768 Ph. (330) 928-9966 • (888) 633-1083 • FAX: (330) 928-7065 • [email protected] • www.beckerpumps.com
3LIT0006 • 2/00
TECHNICAL DATA
KD
T 3.6
0K
DT
3.8
0K
DT
3.1
00
All data based on 60 Hz operation
KD
T 3.1
40
Top View
Side View
End View (Opposite Motor End)
Flow (SCFM @ 0 PSIG)
Horsepower
Speed (RPM)
Maximum Pressure (PSIG)
Weight (lbs.)—w/o motor
Weight (lbs.)—w/ motor**
Noise Level (Max. dBA)
Outlet size (BSP, inches)
Dimensional Dataa
b
b1
e
e1
g
g1
g2
h
h1
h3
h4
i
k2
kL
o
48
71/2*
1740
22
108
265*
76
1
12.83
7.5
3.75
5.43
2.56
13.9
7.68
5.55
6.38
11.38
12.28
12.9
3.78
17.64
30
1.81
95
12*
1740
22
172
368*
84
11/2
15.67
9.65
4.82
7.5
3.75
18.5
8.78
9.06
6.38
11.7
13.0
13.25
5.5
22.17
36.6
2.36
69
10*
1740
22
156
323*
78
11/2
15.67
9.65
4.82
7.5
3.75
18.5
8.78
9.06
6.38
11.7
13.0
13.25
5.5
22.17
34.15
2.36
Manufacturer reserves right to alter data without notice.* Operation at lower pressure may use smaller motor.** May vary with motor type and manufacturer
39
5*
1740
22
104
191*
74
1
12.83
7.5
3.75
5.43
2.56
13.9
7.68
5.55
6.38
11.38
12.28
12.9
3.78
17.64
28.2
1.81
1 - Inlet Port2 - Discharge Port3 - Pressure Relief Valve4 - Vibration Isolators
g
g1 g2
h3 h1
h4
b1
b4
a i
K2
3
1
12mm dia.
h
oe
2
8mm thds.
(Inches)
e1 e1
KL**
TAN
KS
&TA
NK
AC
C.
531For A Quote Call 1-800-877-4472
50th Anniversary Product Catalog
DOUBLE WALL CONTAINMENT - MINI-BULK TANKS
Diameter(in.)
Optional Elevation StandsPart
Number
Double Wall Containment Mini-BulkSmaller dual-containment tanks provide added safety and environment protection in moreconfined or remote storage locations. The advanced double wall tank design is enclosed toprohibit foreign matter from entering the secondary containment tank, and a unique octagonalshape provides optimal spacing and sealing surface for the industry’s most reliable transition fitting.
Features:• Available in HDLPE and XLPE resin packages.• Primary tank is available in both closed and open-top designs.• Secondary tank provides 115-120% of inner tank’s capacity,complies with CRF-264.193.
• Transition fitting allows side safe installation and long-term sealingpower through both walls of the tank.
• Large flat surface area provides ample space for a variety offitting sizes and styles.
• Rib reinforced flat-top design provides ample surface space for chemical feedpump mounting.
• Narrow diameter provides location versatility to fit through most any doorway.• Forklift and pallet jack accessible design on 275, 360 and 500 gallon models.• Optional top draw tube assembly.• Optional 2” vent provides vacuum relief for interior tank.• Optional all-poly elevation stands create more room for plumbing and othersystem requirements without using additional floor space.
Snyder
BottomClearance
(in.)137023 22 12 376.00
137001023 22 18 434.00169023 30 12 568.00
169001023 30 18 651.00173023 36 12 682.00
173001023 36 18 785.00175023 42 12 796.00
175001023 42 18 914.00176023 48 12 948.00
176001023 48 18 1,089.00
PartNumber
TankSize(Gals.)
Dimensions (In.)Diameter Height
List PriceEa. ($)
Double Wall Containment Tanks Mini-BulkPart
Number
XLPE HDPEPrimaryTank Specific
Gravity
ManwayFill(in.)
35 19 36 1.9 6 100020042 537.00 100020045 423.0060 253⁄4 403⁄4 1.9 14 100030042 636.00 100030045 500.00120 33 49 1.9 14 598000042 1,076.00 598000045 888.00150 333⁄4 60 1.9 14 100040042 1,220.00 100040045 1,024.00275 47 631⁄4 1.9 14 100050042 1,800.00 100050045 1,502.00360 53 601⁄4 1.9 14 100060042 2,130.00 100060045 1,864.00500 48 65 1.9 14 100080042 2,884.00 100080045 2,239.00
Shownwith Tank
Shown with OptionalEquipment
List PriceEa. ($)
List PriceEa. ($)• All plastic corrosion resistant.
• Plastic stands elevate tanks off the floor12 to 18 inches forfitting and piping clearance.
• Heavy-duty plastic stand is corrosionproof and available for both flat and conebottom tanks.
Tank Stand Features:
Industri
al
Industri
al
ASTM
ASTM
Grade
Grade
Tanks.qxd:Tanks 1/26/09 3:00 PM Page 531
Koflo Corporation309 CARY POINT DR.CARY, IL 60013
CUSTOMER:
DATE:
SCALE:
MODEL NO:
APPROVED BY DRAWN BY
REVISED
REVISED
REVISED
DRAWING NUMBER:
NONE
7/10/06
NJF
KD-985TYPICAL LOW PRESSURE LOSS DESIGN FLANGE MOUNTED MIXER WITH FNPT INJECTION PORT
5/30/08
"B" HOLES "C" DIAMETER ON A "D" D.B.C.
150 LB. RAISED FACE FLANGED ENDS
KOFLO STATIC MIXER CONSTRUCTED OFSCHEDULE 40 OR 10 PIPE WITH *____ FIXED LOW PRESSURE LOSS DESIGN MIXING ELEMENTS
"A"(Inches)
NOTE: SCH 40 IS USED FOR CARBON STEEL MIXERS SCH 10 IS USED FOR SS/ALLOY MIXERS 3" AND LARGER
"E"
FNPT INJECTION PORT "F" SIZE OR AS SPECIFIED
DIRECTIONOF FLOW
Tab 5
Modified ISR System – AOP Pre-Treatment System Filtration and Solids Settling
Page 1 of 1
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate: 01/28/2010
Considerations:
Tank volume = 6,500 gal
Solids Storage = 310 gal 6-inch Depth
Freeboard = 619 gal 12-inch Depth
Usable tank volume = Total tank volume - Solids storage - Freeboard
Usable tank volume = 5,571 gal
Process flow rate = 60 gpm Aeration Tank Effluent
Total retention time = 93 min
Operation = 50 % Full
Design retention time = 30 min
Additional requirements = 2,600 gal Backwash Decant
Calculate Required Tank Volume:
Retention time volume = Flow rate x Design retention time
1,800 gal
Minimum volume = Retention time volume + Additional requirements
4,400 gal
Tank Selection:
Cylindrical Tank:
Diameter = 10.0 feet
Sidewall Height = 10.5 feet
Usable Tank Volume = 5,571 gal
Available Tank Volume = 5,571 gal
Required Tank Volume = 4,400 gal
Volume Available > Volume Required therefore design is acceptable
FILTER FEED TANK (T-400) SIZINGModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(1) Tab #5_T-400 Sizing.xlsx ARCADIS
Technical Information Manual
2.4.4
PRODUCT DATA SHEET January, 2007
6500 GALLON POLY TANK (Original Style and Total Drain)
GENERAL INFORMATION This type of tank is not to be used for food applications. Potable water applications are generally not acceptable and must be reviewed by the Corporate office first for approval. WEIGHTS AND MEASURES
» Capacity: _ 6500 gallons (nominal)
» Height‡: _ 10’-6” (to top tangent line) 11’-11” (to top of dome) 12’-4” (to highest point on top lid)
» Diameter: :
_ 10’-0” (nominal)
To the best of our knowledge the technical data contained herein are true and accurate at the date of issuance and are subject to change without prior notice. No guarantee of accuracy is given or implied because variations can and do exist. NO WARRANTY OR GUARANTEE OF ANY KIND IS MADE BY BAKERCORP, EITHER EXPRESSED OR IMPLIED.
3020 Old Ranch Parkway • Suite 220 • Seal Beach, CA • 562-430-6262
» Weight*:
_ Tank: 1700 lbs. – 1975 lbs. Pad: 400 lbs. - 450 lbs.
*Varies with origin of manufacture ‡ Does not include height of pad. Add four inches for pad thickness to determine heights from grade when pad is used. DESIGN PARAMETERS
» Tank Material:
_ High Density Polyethylene
» Design Pressure:
_ 0 psi – vented to atmosphere
» Design Vacuum:
_ 0 psi – vented to atmosphere
» Spec. Gravity Limit:
_ Original Style – 1.65 Total Drain – 1.9
» Temp. Limit: _ 150° F » Certification: _ ASTM D1998 (not UL listed)
RESTRICTIONS
» Sulfuric Acid Storage:
_ • 80% concentration maximum • Use only tanks with equipment
numbers ≥ 7376 • Previously repaired tank cannot be
used (equipment number should have “W” at end)
• 100° F maximum temperature • Top fill only • Top manway must be open during
pneumatic filling of tank • Use flexible plumbing fixtures resistant
to sulfuric acid FEATURES
» Top Vent: _ 2” PVC U-vent (two threaded street elbows)
» Manway: _ Top mounted with 24” opening (34 inch diameter screw-on cover)
» Valves: _ 3” butterfly valve with PVC body and disc, Viton O-Ring seal and 316 SS stem.
» Ladder: _ Top mounted bracket for ladder hook-up. Ladder is not permanently mounted to tank.
» Piping Connections:
_ Inlet – 3” with butterfly valve Outlet – 3” with butterfly valve Top – 4” PVC adapter and PVC cap
MISCELLANEOUS
» Options: _ Secondary containment berm
Page 1 of 3
FILTER FEED PUMPS (P-300A/B) DESIGN CALCULATIONS
Total dynamic head calculation = Calc prepared by: M. Seppanenhead loss due to elevation change Calc checked by: J. Perellahead loss due to pipe friction Date: 1/28/2010head loss across misc. process componentsrequired discharge head
Calculate pipe size:
Where: v = Velocity (ft/sec)Q = Flow rate (gpm)r = Pipe radius (in)
Flow Rate Pipe Size Pipe ODWall
Thickness Pipe ID Area velocity(gpm) (in) (in) (in) (in) (ft2) (ft/sec)
60 2 2.375 0.154 2.067 0.023 5.5860 3 3.500 0.216 3.068 0.051 2.5360 4 4.500 0.237 4.026 0.088 1.47
*Pipe dimensions noted for Schedule 40 galvanized steel piping.Note: Design for velocity between 3 and 5 feet/sec to maintain sufficient scour velocity.
Calculate head loss (he) due to elevation change:
assume: Height from pump to discharge point = 15 feetHead loss, he = 15 feet
Calculate head loss due to pipe friction losses:
Step 1. There are multiple pipe sections with flow and pipe diameters shown below
Pipe Section 1-3" Nominal pipe diameter 1 = 3 inch
Flow (v1) = 60 gpm
Step 2. Calculate the friction factor for each pipe section using the Hazen-Williams formula
Hazen-Williams f = .2083 * (100/C)1.852 * (q1.852) / (D4.8655)Formula
f = Friction in head in feet of water per 100 ft of pipeC = Constant for inside roughness
(140 for new galvanized steel pipe, 150 for hdpe pipe)q = Flow rate (gal/min)D = Inside diameter of pipe (inches)
Nominal Diam (in)
ID (in)
ID w/ deposition (in)
1 1.049 0.9241.5 1.610 1.4852 2.067 1.9423 3.068 2.9434 4.026 3.9016 6.065 5.94
NOTE: a 0.0625 inch (1/16 inch) deposition on interior pipe wall is included in diameter for calculation - 1.003 - (2 x 0.0625) = 0.878 inch diameter
Modified ISR System - AOP Pre-Treatment SystemTotal Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
sec60
min1*
)*( 2r
Qv
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(3) Tab #5_P-300A&B TDH.xlsx ARCADIS
Page 2 of 3
FILTER FEED PUMPS (P-300A/B) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Friction factor for Pipe Section 1C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 60 gal/minD1 = Inner pipe diameter (inches) 2.943 inches (see NOTE)
Pipe Section 1 friction factor 1.1 ft water / 100 feet of pipe
Step 3. Calculate the equivalent length of pipe for each section
Nominal Fitting size 1 in 1.5 in 2 in 3 in 4 in 6 in
90˚ Elbows 2.7 3.4 3.6 4.0 4.6 10.4Standard Tee (thru flow) 3.2 5.6 7.7 12.0 17.0 38.3Standard Tee (branch flow) 6.6 9.9 12.0 17.0 21.0 47.3Ball valve (full open) 1.6 2.3 2.9 4.3 5.5 12.3Check Valve 11.0 15.0 19.0 27.0 38.0 85.5Union 0.3 0.4 0.5 0.5 0.65 1.5Reducer (2/1) 1.0 1.5 1.5 3.0 4.0 9.0Expansion (1/2) 1.5 2.5 3.0 4.0 6.0 13.5
Equivalent lengths from reference: Civil Engineering Reference Manual, 9th Ed, Professional Publications, Inc., 2003; and "Flow of Fluids", Crane Technical Paper No. 410, 1988.
Pipe Section 1 - 3"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 100 100Standard Tee (thru flow) 4 12 48Standard Tee (branch flow) 2 17 3490˚ Elbows 16 4 64Union 8 0.5 4Check Valve 2 27 54Ball valve (full open) 8 4.3 34
Equivalent Length: 338
Step 4. Determine pipe friction for each pipe section.
total pipe friction = total equivalent length x friction factor
Total Pipe Friction - Pipe Section 1total equivalent length = 338 feet
friction factor = 1.1 feet water / 100 feet of pipe
Total Pipe Friction = 3.9 feet
Equivalent Length
Equivalent Length per Fitting (ft)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(3) Tab #5_P-300A&B TDH.xlsx ARCADIS
Page 3 of 3
FILTER FEED PUMPS (P-300A/B) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Step 5. Determine total pipe friction (all sections)
Total Pipe Friction - Pipe Section 1 = 3.9
Calculate Total Dynamic Head:
Head Loss Due to Change in Elevation 15 ft
Head loss due to pipe friction 4 ft
Head loss Across Misc. Process Components Multi-Media Filter 35 ft
Air Stripper 24 ftFlow meter 12 ft
Required Discharge Pressure (0 psi) 0 ft
Total Dynamic Head Required - Calculated 90 ft
Design Safety Factor 25%
Total Dynamic Head Required - Design 112 feet
Pump Design Requirements:Flow 60 gpm
Total Dynamic Head 112 feet
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(3) Tab #5_P-300A&B TDH.xlsx ARCADIS
Model: 3196 Size: 1.5X3-6 Group: STi 60Hz RPM: 3520 Stages: 1
Job/Inq.No. : RAYTHEONPurchaser : ARCADISEnd User : ARCADIS Issued by : Rev. : 0Item/Equip.No. : P-300AB Quotation No. : RAPA PRETREATMENT Date : 02/03/2010Service :Order No. :
Operating Conditions Pump PerformanceLiquid: Water Published Efficiency: 45.0 % Suction Specific Speed: 7,945 gpm(US) ftTemp.: 114.0 deg F Rated Pump Efficiency: 45.0 % Min. Hydraulic Flow: 16.9 gpmS.G./Visc.: 1.000/1.000 cp Rated Total Power: 3.9 hp Min. Thermal Flow: N/AFlow: 60.0 gpm Non-Overloading Power: 6.4 hpTDH: 112.0 ft Imp. Dia. First 1 Stg(s): 5.1250 inNPSHa: NPSHr: 6.0 ftSolid size: Shut off Head: 118.3 ft% Susp. Solids(by wtg):
Vapor Press:
Max. Solids Size: 0.4380 inNotes: 1. The Mechanical seal increased drag effect on power and efficiency is not included, unless the correction is shown in the
appropriate field above. 2. Magnetic drive eddy current on power and efficiency is not included. 3. Elevated temperatureeffects on performance are not included. 4. Non Overloading power does not reflect v-belt/gear losses.
Page 1 of 3
BACKWASH PUMP (P-300C) DESIGN CALCULATIONS
Total dynamic head calculation = Calc prepared by: M. Seppanenhead loss due to elevation change Calc checked by: J. Perellahead loss due to pipe friction Date: 1/28/2010head loss across misc. process componentsrequired discharge head
Calculate pipe size:
Where: v = Velocity (ft/sec)Q = Flow rate (gpm)r = Pipe radius (in)
Flow Rate Pipe Size Pipe ODWall
Thickness Pipe ID Area velocity(gpm) (in) (in) (in) (in) (ft2) (ft/sec)
110 3 3.500 0.216 3.068 0.051 4.64110 4 4.500 0.237 4.026 0.088 2.70110 6.00 6.625 0.280 6.065 0.201 1.19
*Pipe dimensions noted for Schedule 40 galvanized steel piping.Note: Design for velocity between 3 and 5 feet/sec to maintain sufficient scour velocity.
Calculate head loss (he) due to elevation change:
assume: Height from pump to discharge point = 15 feetHead loss, he = 15 feet
Calculate head loss due to pipe friction losses:
Step 1. There are multiple pipe sections with flow and pipe diameters shown below
Pipe Section 1 Nominal pipe diameter 1 = 3 inch
Flow (v1) = 110 gpm
Step 2. Calculate the friction factor for each pipe section using the Hazen-Williams formula
Hazen-Williams f = .2083 * (100/C)1.852 * (q1.852) / (D4.8655)Formula
f = Friction in head in feet of water per 100 ft of pipeC = Constant for inside roughness
(140 for new galvanized steel pipe, 150 for hdpe pipe)q = Flow rate (gal/min)D = Inside diameter of pipe (inches)
Nominal Diam (in)
ID (in)
ID w/ deposition (in)
1 1.049 0.9241.5 1.610 1.4852 2.067 1.9423 3.068 2.9434 4.026 3.9016 6.065 5.94
NOTE: a 0.0625 inch (1/16 inch) deposition on interior pipe wall is included in diameter for calculation - 1.003 - (2 x 0.0625) = 0.878 inch diameter
Modified ISR System - AOP Pre-Treatment SystemTotal Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
sec60
min1*
)*( 2r
Qv
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(5) Tab #5_P-300C TDH.xlsx ARCADIS
Page 2 of 3
BACKWASH PUMP (P-300C) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Friction factor for Pipe Section 1C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 110 gal/minD1 = Inner pipe diameter (inches) 2.943 inches (see NOTE)
Pipe Section 1 friction factor 3.5 ft water / 100 feet of pipe
Step 3. Calculate the equivalent length of pipe for each section
Nominal Fitting size 1 in 1.5 in 2 in 3 in 4 in 6 in
90˚ Elbows 2.7 3.4 3.6 4.0 4.6 10.4Standard Tee (thru flow) 3.2 5.6 7.7 12.0 17.0 38.3Standard Tee (branch flow) 6.6 9.9 12.0 17.0 21.0 47.3Ball valve (full open) 1.6 2.3 2.9 4.3 5.5 12.3Check Valve 11.0 15.0 19.0 27.0 38.0 85.5Union 0.3 0.4 0.5 0.5 0.7 1.5Reducer (2/1) 1.0 1.5 1.5 3.0 4.0 9.0Expansion (1/2) 1.5 2.5 3.0 4.0 6.0 13.5
Equivalent lengths from reference: Civil Engineering Reference Manual, 9th Ed, Professional Publications, Inc., 2003; and "Flow of Fluids", Crane Technical Paper No. 410, 1988.
Pipe Section 1 - 3"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 100 100Standard Tee (thru flow) 6 12 72Standard Tee (branch flow) 2 17 3490˚ Elbows 4 4 16Check Valve 1 27 27Ball valve (full open) 6 4.3 26
Equivalent Length: 275
Step 4. Determine pipe friction for each pipe section.
total pipe friction = total equivalent length x friction factor
Total Pipe Friction - Pipe Section 1total equivalent length = 275 feet
friction factor = 3.5 feet water / 100 feet of pipe
Total Pipe Friction = 9.7 feet
Step 5. Determine total pipe friction (all sections)
Total Pipe Friction - Pipe Section 1 = 9.7
Equivalent Length
Equivalent Length per Fitting (ft)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(5) Tab #5_P-300C TDH.xlsx ARCADIS
Page 3 of 3
BACKWASH PUMP (P-300C) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Calculate Total Dynamic Head:
Head Loss Due to Change in Elevation 15 ft
Head loss due to pipe friction 9.7 ft
Head loss Across Misc. Process Components Static Mixer 10 ft
Multi-Media Filter 35 ftFlow meter 12 ft
Required Discharge Pressure (0 psi) 0 ft
Total Dynamic Head Required - Calculated 82 ft
Design Safety Factor 25%
Total Dynamic Head Required - Design 102 feet
Pump Design Requirements:Flow 110 gpm
Total Dynamic Head 102 feet
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(5) Tab #5_P-300C TDH.xlsx ARCADIS
Model: 3196 Size: 1.5X3-6 Group: STi 60Hz RPM: 3520 Stages: 1
Job/Inq.No. : RAYTHEONPurchaser : ARCADISEnd User : ARCADIS Issued by : Rev. : 0Item/Equip.No. : P-300C Quotation No. : RAPA PRETREATMENT Date : 02/03/2010Service :Order No. :
Operating Conditions Pump PerformanceLiquid: Water Published Efficiency: 61.0 % Suction Specific Speed: 7,945 gpm(US) ftTemp.: 114.0 deg F Rated Pump Efficiency: 61.0 % Min. Hydraulic Flow: 16.9 gpmS.G./Visc.: 1.000/1.000 cp Rated Total Power: 4.9 hp Min. Thermal Flow: N/AFlow: 110.0 gpm Non-Overloading Power: 6.4 hpTDH: 103.0 ft Imp. Dia. First 1 Stg(s): 5.1250 inNPSHa: NPSHr: 7.5 ftSolid size: Shut off Head: 118.3 ft% Susp. Solids(by wtg):
Vapor Press:
Max. Solids Size: 0.4380 inNotes: 1. The Mechanical seal increased drag effect on power and efficiency is not included, unless the correction is shown in the
appropriate field above. 2. Magnetic drive eddy current on power and efficiency is not included. 3. Elevated temperatureeffects on performance are not included. 4. Non Overloading power does not reflect v-belt/gear losses.
Multi-Media Filter Design CalculationsModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
Page 1 of 1
Calc prepared by: M. Seppanen
Calc checked by: J. Perella
Date: 1/28/2010
Assume:
Filter sizing is based on hydraulic loading
8 - 15 gpm/ft2
Process Flow Rate = 60 gpm
Design Loading Rate 5.0 gpm/ft2
Filtration Area Required = 12.0 ft2
Number of online vessels = 3
Filtration area per vessel = 4.0 ft2
Calculated diameter of vessel = 2.3 ft
Selected vessel diameter = 3.0 ft
Filtration Area per vessel = 7.1 ft2
Actual Loading Rate = 2.8 gpm/ft2
Water Loading Rate = 15 gpm/ft2
Time per vessel = 8 min
Backwash Flow Rates:
Water = 106 gpm
Backwash Volumes:
Volume of Backwash Required per Vessel= 848 gpm
Total Volume of Backwash Required = 2,544 gpm
Calculate size of Multi-Media Filter units:
Recommended hydraulic loading for media
Calculate diameter of Multi-Media Filter:
Selected design requirement specifications:
Backwash Requirements
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(7) Tab #5_Pre AOP MMF Calcs.xlsx ARCADIS
Page 1 of 1
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate: 01/28/2010
Considerations:
Tank volume = 6,500 gal
21-Days Solids Storage = 2,625 gal 125 gallons per day
Freeboard = 619 gal 12-inch Depth
Input Volume = 2545 gal Daily Backwash Volume
Additional Requirements = 0 gal
Calculate Required Tank Volume:
Total input volume = Daily Backwash Volume + Additional Requirements
2,545 gal
Minimum required volume = Total input volume + Solids storage + Freeboard
5,789 gal
Tank Selection:
Cylindrical Tank:
Diameter = 10.0 feet
Sidewall Height = 10.5 feet
Volume = 6,500 gal
Available Tank Volume = 6,500 gal
Required Tank Volume = 5,789 gal
Volume Available > Volume Required therefore design is acceptable
BACKWASH TANK (T-800) SIZINGModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(10) Tab #5_T-800 Sizing.xlsx ARCADIS
Technical Information Manual
2.4.4
PRODUCT DATA SHEET January, 2007
6500 GALLON POLY TANK (Original Style and Total Drain)
GENERAL INFORMATION This type of tank is not to be used for food applications. Potable water applications are generally not acceptable and must be reviewed by the Corporate office first for approval. WEIGHTS AND MEASURES
» Capacity: _ 6500 gallons (nominal)
» Height‡: _ 10’-6” (to top tangent line) 11’-11” (to top of dome) 12’-4” (to highest point on top lid)
» Diameter: :
_ 10’-0” (nominal)
To the best of our knowledge the technical data contained herein are true and accurate at the date of issuance and are subject to change without prior notice. No guarantee of accuracy is given or implied because variations can and do exist. NO WARRANTY OR GUARANTEE OF ANY KIND IS MADE BY BAKERCORP, EITHER EXPRESSED OR IMPLIED.
3020 Old Ranch Parkway • Suite 220 • Seal Beach, CA • 562-430-6262
» Weight*:
_ Tank: 1700 lbs. – 1975 lbs. Pad: 400 lbs. - 450 lbs.
*Varies with origin of manufacture ‡ Does not include height of pad. Add four inches for pad thickness to determine heights from grade when pad is used. DESIGN PARAMETERS
» Tank Material:
_ High Density Polyethylene
» Design Pressure:
_ 0 psi – vented to atmosphere
» Design Vacuum:
_ 0 psi – vented to atmosphere
» Spec. Gravity Limit:
_ Original Style – 1.65 Total Drain – 1.9
» Temp. Limit: _ 150° F » Certification: _ ASTM D1998 (not UL listed)
RESTRICTIONS
» Sulfuric Acid Storage:
_ • 80% concentration maximum • Use only tanks with equipment
numbers ≥ 7376 • Previously repaired tank cannot be
used (equipment number should have “W” at end)
• 100° F maximum temperature • Top fill only • Top manway must be open during
pneumatic filling of tank • Use flexible plumbing fixtures resistant
to sulfuric acid FEATURES
» Top Vent: _ 2” PVC U-vent (two threaded street elbows)
» Manway: _ Top mounted with 24” opening (34 inch diameter screw-on cover)
» Valves: _ 3” butterfly valve with PVC body and disc, Viton O-Ring seal and 316 SS stem.
» Ladder: _ Top mounted bracket for ladder hook-up. Ladder is not permanently mounted to tank.
» Piping Connections:
_ Inlet – 3” with butterfly valve Outlet – 3” with butterfly valve Top – 4” PVC adapter and PVC cap
MISCELLANEOUS
» Options: _ Secondary containment berm
Page 1 of 3
DECANT PUMP (P-600) DESIGN CALCULATIONS
Total dynamic head calculation = Calc prepared by: M. Seppanenhead loss due to elevation change Calc checked by: J. Perellahead loss due to pipe friction Date: 1/28/2010head loss across misc. process componentsrequired discharge head
Calculate pipe size:
Where: v = Velocity (ft/sec)Q = Flow rate (gpm)r = Pipe radius (in)
Flow Rate Pipe Size Pipe ODWall
Thickness Pipe ID Area velocity(gpm) (in) (in) (in) (in) (ft2) (ft/sec)
30 1.5 1.900 0.145 1.610 0.014 4.6030 2 2.375 0.154 2.067 0.023 2.7930 3 3.500 0.216 3.068 0.051 1.27
*Pipe dimensions noted for Schedule 40 galvanized steel piping.Note: Design for velocity between 3 and 5 feet/sec to maintain sufficient scour velocity.
Calculate head loss (he) due to elevation change:
assume: Height from pump to discharge point = 15 feetHead loss, he = 15 feet
Calculate head loss due to pipe friction losses:
Step 1. There are multiple pipe sections with flow and pipe diameters shown below
Pipe Section 1 Nominal pipe diameter 1 = 1.5 inch
Flow (v1) = 30 gpm
Step 2. Calculate the friction factor for each pipe section using the Hazen-Williams formula
Hazen-Williams f = .2083 * (100/C)1.852 * (q1.852) / (D4.8655)Formula
f = Friction in head in feet of water per 100 ft of pipeC = Constant for inside roughness
(140 for new galvanized steel pipe, 150 for hdpe pipe)q = Flow rate (gal/min)D = Inside diameter of pipe (inches)
Nominal Diam (in)
ID (in)
ID w/ deposition (in)
1 1.049 0.9241.5 1.610 1.4852 2.067 1.9423 3.068 2.9434 4.026 3.9016 6.065 5.94
NOTE: a 0.0625 inch (1/16 inch) deposition on interior pipe wall is included in diameter for calculation - 1.003 - (2 x 0.0625) = 0.878 inch diameter
Modified ISR System - AOP Pre-Treatment SystemTotal Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
sec60
min1*
)*( 2r
Qv
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(12) Tab #5_P-600 TDH.xlsx ARCADIS
Page 2 of 3
DECANT PUMP (P-600) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Friction factor for Pipe Section 1C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 30 gal/minD1 = Inner pipe diameter (inches) 1.485 inches (see NOTE)
Pipe Section 1 friction factor 8.9 ft water / 100 feet of pipe
Step 3. Calculate the equivalent length of pipe for each section
Nominal Fitting size 1 in 1.5 in 2 in 3 in 4 in 6 in
90˚ Elbows 2.7 3.4 3.6 4.0 4.6 10.4Standard Tee (thru flow) 3.2 5.6 7.7 12.0 17.0 38.3Standard Tee (branch flow) 6.6 9.9 12.0 17.0 21.0 47.3Ball valve (full open) 1.6 2.3 2.9 4.3 5.5 12.3Check Valve 11.0 15.0 19.0 27.0 38.0 85.5Union 0.3 0.4 0.5 0.5 0.65 1.5Reducer (2/1) 1.0 1.5 1.5 3.0 4.0 9.0Expansion (1/2) 1.5 2.5 3.0 4.0 6.0 13.5
Equivalent lengths from reference: Civil Engineering Reference Manual, 9th Ed, Professional Publications, Inc., 2003; and "Flow of Fluids", Crane Technical Paper No. 410, 1988.
Pipe Section 1 - 1-1/2"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 150 150Standard Tee (thru flow) 2 5.6 11Standard Tee (branch flow) 0 9.9 090˚ Elbows 6 3.4 20Union 2 0.39 1Check Valve 1 15 15Ball valve (full open) 2 2.3 5
Equivalent Length: 202
Step 4. Determine pipe friction for each pipe section.
total pipe friction = total equivalent length x friction factor
Total Pipe Friction - Pipe Section 1total equivalent length = 202 feet
friction factor = 8.9 feet water / 100 feet of pipe
Total Pipe Friction = 17.9 feet
Step 5. Determine total pipe friction (all sections)
Total Pipe Friction - Pipe Section 1 = 17.9
Equivalent Length
Equivalent Length per Fitting (ft)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(12) Tab #5_P-600 TDH.xlsx ARCADIS
Page 3 of 3
DECANT PUMP (P-600) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Calculate Total Dynamic Head:
Head Loss Due to Change in Elevation 15 ft
Head loss due to pipe friction 18 ft
Head loss Across Misc. Process Components ft
Required Discharge Pressure (0 psi) 0 ft
Total Dynamic Head Required - Calculated 33 ft
Design Safety Factor 25%
Total Dynamic Head Required - Design 41 feet
Pump Design Requirements:Flow 30 gpm
Total Dynamic Head 41 feet
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(12) Tab #5_P-600 TDH.xlsx ARCADIS
ITTGoulds Pumps1SC Submersible
Water Pump
GouldsPumpsisabrandofITTCorporation.
www.goulds.com
Engineered for life
Residential Water Systems
Features
■ Casing: AISI 304 SS. Corrosion resistant, non-toxic, non-leaching.
■ Impeller: FDA compliant, glass filled Noryl®. Corrosion and abrasion resistant.
■ Mechanical Seal: Silicon/carbide sealing faces; all metal components of AISI type 300 stainless steel running in protected oil chamber.
■ Elastomers: BUNA-N.
■ Motor Shell and Lifting Handle: Constructed of AISI type 304 series stainless steel.
■ Shaft: AISI type 304 stainless steel high strength keyed pump shaft with impeller locking cap screw.
■ Discharge: 11⁄4" NPT vertical discharge connection.
■ Suction Strainer: Detachable for easy clean out.
�
ITT GOuLDs PuMPsResidential Water Systems
0 �50
CAPACITY
TOTA
L D
YNA
MIC
HEA
D
FEET
U.S. GPM
100
50
150
�010 �00
�0
40
METERS
0 � 4� 6 m3/hr
60
5 15
51
�00
�5
7 8
1SC51E-H
1SC51C-F
1SC51D-G
1SC51C-A
1SC51D-B
1SC51E-C
1 HP3/4 HP1/2 HP
1 HP
3/4 HP
1/2 HP
aPPLICatIONs
Submersible water pumps designed for pumping out of reservoirs and storage tanks:• Homes and farms• Mobile home parks and motels• Schools and hospitals• Municipal applications• Industrial applications• Commercial applications
sPeCIFICatIONs
Pump:
• 11⁄4" NPT discharge and open suction.
• Maximum suspended solids 1⁄8".
• Capacities: to 35 U.S. GPM (7.9 m3/h).
• Total heads: to 240 feet TDH (70 m).
• Temperature: 104ºF (40ºC) continuous 140ºF (60ºC) intermittent.
• Maximum submergence: to 65 feet (20 m).
• Continuous duty rated, non-overloading motor.Motor:
• Single phase: 3450 RPM, 115 and 230 V, 60 Hz.
• Three phase: 3450 RPM, 230 V, 60 Hz.
• Non-overloading.
• Class F insulation.
• Thermal overload protection: built-in with automatic reset on single phase.
• Three phase models require external overloads in panel.
• Power cord: All 30' long.Single phase – 16/3, with 115 V or 230 V plugThree phase – 16/4 STO, bare leads
NOTE: See accessory section for separate control panels.
�
ITT GOuLDs PuMPsResidential Water Systems
DIMeNsIONs
MeCHaNICaL Data
NPT 11⁄4
L
5"
“L” Dimensions Discharge Series HP Phase in inches Size
1⁄2 1,3 191⁄8
1SC 3⁄4 1,3 201⁄8 11⁄4
1 1,3 213⁄4
Series Number of HP Volts Phase Maximum RPM Weight Stages Amps (lbs.) 1SC51C0AA 115 1 10.6
1SC51C1AA 1⁄2 230 4.5
1SC51C3AA 3 3 3.0 31 1SC51C0FA 115 1 10.7
1SC51C1FA 1⁄2 230 4.5
1SC51C3FA 3 3.0
1SC51D1BA 1 5.4 3450
1SC51D3BA 4 3⁄4 230 3 3.5 33 1SC51D1GA 1 5.3
1SC51D3GA 3 3.5
1SC51E1CA 1 6.4
1SC51E3CA 5 1 230 3 4.1 38 1SC51E1HA 1 6.8
1SC51E3HA 3 4.3
ITT
GouldsPumpsandtheITTEngineeredBlocksSymbolareregisteredtrademarksandtradenamesofITTCorporation.
NorylisaregisteredtrademarkofGEPlastic.
SPECIFICATIONS ARE SUBJECT TO CHANGE WITHOUT NOTICE.
B1SC August, 2007©2007ITTCorporation
Engineered for life
Residential Water Systems
Component Material Outer Casing and Upper Support Stainless Steel (AISI 304)
Motor Casing Stainless Steel (AISI 304)
Suction Strainer Stainless Steel (AISI 304)
Motor Shaft Stainless Steel (AISI 304)
Impeller Noryl
Diffuser Stainless Steel (AISI 304)
Upper Cover Technopolymer
Mechanical Seal Housing Technopolymer
Lower Bearing Support Aluminum Die Cast
Lower Bearing Urethane Resin
Elastomers Buna-N
Lower Mechanical Seal Silicon Carbide/Silicon Carbide
Upper Lip Seal Nitrile Rubber
Polymer CalculationsModified ISR System
AOP Pre-Treatment System
Raytheon Company St. Petersburg, Florida
Page 1 of 1
M. Seppanen
J. Darby
1/28/2010
Flow rate = 106 gpm
Polymer dosage = 15 ppmv Jar Test Results
Specific gravity of polymer = 1.015
Polymer weight = 8.465 lbs/gal
Polymer flow rate = 6.0 mL/min
Backwash flow rate = 106 gpm
Polymer flow rate = 6.0 mL/min
Duration of backwash = 8 min
Volume of polymer per vessel = 0.05 L
Number of vessels = 3
Total Volume of polymer = 0.14 L
Backwash Frequency = 7 Backwash cycles/week
Total Volume of polymer per week = 1.01 L/week
0.27 gal/week
Total Volume of polymer per week 0.27 gal/week
Calculate Volume of Polymer Required per Week:
Calculate Polymer Flow Rates for the Multi-Media Filter Backwash Cycle:
Calculate Volume of Polymer Required:
Calc prepared by:
Calc checked by:
Date:
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #5\(14) Tab #5_PreAOP Polymer Calc.xlsx ARCADIS
©2006, General Electric Company. All rights reserved. *Trademark of General Electric Company; may be registered in one or more countries.
Fact Sheet
PFW957EN 0606
Europe/Middle East/Africa Heverlee, Belgium +32-16-40-20-00
Asia/Pacific Shanghai, China +86-21-5298-4573
Find a contact near you by visiting gewater.com or e-mailing [email protected].
Americas Watertown, MA +1-617-926-2500
Global Headquarters Trevose, PA +1-215-355-3300
PolyFloc* AS1002 High Molecular Weight Flocculant• Easy-to-feed polymeric flocculant
• Convenient, true liquid
• Reduces floc carryover
• Approved for potable use
Description and Use
PolyFloc AS1002 is a liquid, weakly anionic, high molecular weight, polymeric flocculant, which is designed to function in industrial treatment programs as a coagulant aid, or flocculant, in clarification, thickening, and softening processes. The product is chlorine resistant. NSF certification for potable applications is pending.
PolyFloc AS1002 is true liquid, high molecular weight flocculant. This polymer is ideal for remote plant operations or small volume usage because it does not require extensive feed and makedown equipment.
A fast-settling floc is formed when PolyFloc AS1002 is applied to warm or hot lime/soda softeners, cold lime softeners, and influent clarification systems. Floc carryover is reduced, resulting in a cleaner effluent.
PolyFloc AS1002 is also an excellent sludge dewatering aid producing clean filtrate, high solids capture, and a drier cake. Applications to many types of industrial sludges have been successful, including blast furnace sludge dewatering applications.
Treatment and Feeding Requirements
PolyFloc AS1002 is an easy-to-feed liquid that does not require any special makedown procedures. Poly-Floc AS1002 can be fed neat with any suitable high viscosity gear pump or diluted with water to any con-venient concentration. Diluted product may be fed by a pump, eductor, or by gravity flow to a point where good mixing, but not violent agitation, of the treated water occurs. High speed mixing decreases the activ-
ity of the polymer. Pumps used to transfer the solution to the point of application should be positive dis-placement gear or piston pumps.
To minimize corrosion and contamination by corro-sion products, liquid-side components of tanks, pumps, and piping should be constructed of stainless steel, polyethylene, or polyvinyl chloride. Mild steel is acceptable only in systems where contamination by corrosion products is not a critical problem.
General Properties
Physical properties of PolyFloc AS1002 are shown on the Material Safety Data Sheet, a copy of which is available on request.
Packaging Information
PolyFloc AS1002 is a liquid product, available in a vari-ety of containers. Consult your GE representative for delivery and packaging alternatives.
Storage and Handling
Store PolyFloc AS1002 at moderate temperatures of 40 to 90°F (4 to 32°C), and protect from freezing. The recommended shelf life of the product is six months.
Spilled polymer is very slippery. Small amounts of spilled polymer can be washed down with copious amounts of water. Large spills should be contained and absorbed on inert material, then disposed as solid waste, prior to flushing with water.
Safety Precautions
A Material Safety Data Sheet containing detailed in-formation about this product is available upon re-quest.
Material Safety Data Sheet Issue Date: 28-JAN-2008 Supercedes: 28-JAN-2008
POLYFLOC AS1002
1 IdentificationIdentification of substance or preparationPOLYFLOC AS1002
Product Application AreaFlocculant.
Company/Undertaking IdentificationGE Betz, Inc.4636 Somerton RoadTrevose, PA 19053T 215 355-3300, F 215 953 5524
Emergency Telephone(800) 877-1940
Prepared by Product Stewardship Group: T 215-355-3300 Prepared on: 28-JAN-2008
2 Hazard(s) identification
******************************************************************************** EMERGENCY OVERVIEW CAUTION May cause slight irritation to the skin. May cause slight irritation to the eyes. Mists/aerosols may cause irritation to upper respiratory tract. DOT hazard is not applicable Odor: Slight; Appearance: Colorless To Light Yellow, Liquid Fire fighters should wear positive pressure self-contained breathing apparatus(full face-piece type). Proper fire-extinguishing media: dry chemical, carbon dioxide, foam or water ******************************************************************************** POTENTIAL HEALTH EFFECTS ACUTE SKIN EFFECTS: Primary route of exposure; May cause slight irritation to the skin. ACUTE EYE EFFECTS: May cause slight irritation to the eyes. ACUTE RESPIRATORY EFFECTS: Mists/aerosols may cause irritation to upper respiratory tract.
Page 1Substance or Preparation: POLYFLOC AS1002
INGESTION EFFECTS: May cause slight gastrointestinal irritation. TARGET ORGANS: No evidence of potential chronic effects. MEDICAL CONDITIONS AGGRAVATED: Not known. SYMPTOMS OF EXPOSURE: May cause redness or itching of skin.
3 Composition / information on ingredients
Information for specific product ingredients as required by the U.S. OSHA HAZARD COMMUNICATION STANDARD is listed. Refer to additional sections of this MSDS for our assessment of the potential hazards of this formulation. HAZARDOUS INGREDIENTS: This product is not hazardous as defined by OSHA regulations. No component is considered to be a carcinogen by the National Toxicology Program, the International Agency for Research on Cancer, or the Occupational Safety and Health Administration at OSHA thresholds for carcinogens.
4 First-aid measures
SKIN CONTACT: Wash thoroughly with soap and water. Remove contaminated clothing. Get medical attention if irritation develops or persists. EYE CONTACT: Remove contact lenses. Hold eyelids apart. Immediately flush eyes with plenty of low-pressure water for at least 15 minutes. Get medical attention if irritation persists after flushing. INHALATION: If nasal, throat or lung irritation develops - remove to fresh air and get medical attention. INGESTION: Do not feed anything by mouth to an unconscious or convulsive victim. Do not induce vomiting. Immediately contact physician. Dilute contents of stomach using 2-8 fluid ounces (60-240 mL) of milk or water. NOTES TO PHYSICIANS: No special instructions
5 Fire-fighting measures
Page 2Substance or Preparation: POLYFLOC AS1002
FIRE FIGHTING INSTRUCTIONS: Fire fighters should wear positive pressure self-contained breathing apparatus (full face-piece type). EXTINGUISHING MEDIA: dry chemical, carbon dioxide, foam or water HAZARDOUS DECOMPOSITION PRODUCTS: oxides of carbon and sulfur FLASH POINT: > 200F > 93C P-M(CC)
6 Accidental release measures
PROTECTION AND SPILL CONTAINMENT: Ventilate area. Use specified protective equipment. Contain and absorb on absorbent material. Place in waste disposal container. Flush area with water. Wet area may be slippery. Spread sand/grit. DISPOSAL INSTRUCTIONS: Water contaminated with this product may be sent to a sanitary sewer treatment facility,in accordance with any local agreement,a permitted waste treatment facility or discharged under a permit. Product as is - Incinerate or land dispose in an approved landfill.
7 Handling and storage
HANDLING: Normal chemical handling. STORAGE: Keep containers closed when not in use. Protect from freezing. Shelf life 135 days.
8 Exposure controls / personal protection
EXPOSURE LIMITS This product is not hazardous as defined by OSHA regulations. ENGINEERING CONTROLS: adequate ventilation PERSONAL PROTECTIVE EQUIPMENT: Use protective equipment in accordance with 29CFR 1910 Subpart I RESPIRATORY PROTECTION: A RESPIRATORY PROTECTION PROGRAM THAT MEETS OSHA’S 29 CFR 1910.134 AND ANSI Z88.2 REQUIREMENTS MUST BE FOLLOWED WHENEVER WORKPLACE CONDITIONS WARRANT A RESPIRATOR’S USE. USE AIR PURIFYING RESPIRATORS WITHIN USE LIMITATIONS ASSOCIATED WITH THE EQUIPMENT OR ELSE USE SUPPLIED AIR-RESPIRATORS. If air-purifying respirator use is appropriate, use any of the following particulate respirators: N95, N99, N100, R95, R99, R100, P95, P99 or P100. SKIN PROTECTION: rubber, butyl, viton or neoprene gloves -- Wash off after each use. Replace as necessary. EYE PROTECTION: splash proof chemical goggles
Page 3Substance or Preparation: POLYFLOC AS1002
9 Physical and chemical properties
Specific Grav.(70F,21C) 1.015 Vapor Pressure (mmHG) ~ 18.0 Freeze Point (F) 32 Vapor Density (air=1) < 1.00 Freeze Point (C) 0 Viscosity(cps 70F,21C) 2000 % Solubility (water) 100.0 Odor Slight Appearance Colorless To Light Yellow Physical State Liquid Flash Point P-M(CC) > 200F > 93C pH As Is (approx.) 4.1 Evaporation Rate (Ether=1) < 1.00 Percent VOC: 0.0 NA = not applicable ND = not determined
10 Stability and reactivity
STABILITY: Stable under normal storage conditions. HAZARDOUS POLYMERIZATION: Will not occur. INCOMPATIBILITIES: May react with strong oxidizers. DECOMPOSITION PRODUCTS: oxides of carbon and sulfur INTERNAL PUMPOUT/CLEANOUT CATEGORIES: "A"
11 Toxicological information
Oral LD50 RAT: >2,000 mg/kg NOTE - Estimated value Dermal LD50 RABBIT: >2,000 mg/kg NOTE - Estimated value
12 Ecological information
AQUATIC TOXICOLOGY Daphnia magna 48 Hour Static Acute Bioassay (pH adjusted) LC50= 25466; No Effect Level= 8700 mg/L Fathead Minnow 96 Hour Static Acute Bioassay (pH adjusted) LC50= 30944; No Effect Level= 15500 mg/L BIODEGRADATION No Data Available.
13 Disposal considerations
Page 4Substance or Preparation: POLYFLOC AS1002
If this undiluted product is discarded as a waste, the US RCRA hazardous waste identification number is : Not applicable. Please be advised; however, that state and local requirements for waste disposal may be more restrictive or otherwise different from federal regulations. Consult state and local regulations regarding the proper disposal of this material.
14 Transport information
DOT HAZARD: Not Applicable PROPER SHIPPING NAME: DOT EMERGENCY RESPONSE GUIDE #: Not applicable Note: Some containers may be DOT exempt, please check BOL for exact container classification
15 Regulatory information
TSCA: All components of this product are included on or are in compliance with the U.S. TSCA regulations. CERCLA AND/OR SARA REPORTABLE QUANTITY (RQ): No regulated constituent present at OSHA thresholds FOOD AND DRUG ADMINISTRATION: 21 CFR 176.110 (acrylamide - acrylic acid resins) All ingredients comprising this product are authorized by FDA for the manufacture of paper and paperboard that may contact aqueous and fatty foods as per 21 CFR 176.170(a) (4). USDA FOOD PLANT APPROVALS: G1 SARA SECTION 312 HAZARD CLASS: Product is non-hazardous under Section 311/312 SARA SECTION 302 CHEMICALS: No regulated constituent present at OSHA thresholds SARA SECTION 313 CHEMICALS: No regulated constituent present at OSHA thresholds CALIFORNIA REGULATORY INFORMATION CALIFORNIA SAFE DRINKING WATER AND TOXIC ENFORCEMENT ACT (PROPOSITION 65): No regulated constituents present MICHIGAN REGULATORY INFORMATION No regulated constituent present at OSHA thresholds
16 Other information
NFPA/HMIS CODE TRANSLATION Health 1 Slight Hazard Fire 0 Minimal Hazard Reactivity 0 Minimal Hazard Special NONE No special Hazard
Page 5Substance or Preparation: POLYFLOC AS1002
(1) Protective Equipment B Goggles,Gloves (1) refer to section 8 of MSDS for additional protective equipment recommendations. CHANGE LOG EFFECTIVE DATE REVISIONS TO SECTION: SUPERCEDES --------- --------------------- ---------- MSDS status: 30-JAN-1997 ** NEW ** 12-MAY-1997 15 30-JAN-1997 06-MAY-1998 ;EDIT:9 12-MAY-1997 27-MAY-1999 15 06-MAY-1998 21-SEP-1999 15 27-MAY-1999 11-FEB-2002 4,16 21-SEP-1999 28-JAN-2008 4,5,7,8,10 11-FEB-2002
Page 6Substance or Preparation: POLYFLOC AS1002
Koflo Corporation309 CARY POINT DR.CARY, IL 60013
CUSTOMER:
DATE:
SCALE:
MODEL NO:
APPROVED BY DRAWN BY
REVISED
REVISED
REVISED
DRAWING NUMBER:
NONE
7/10/06
NJF
KD-985TYPICAL LOW PRESSURE LOSS DESIGN FLANGE MOUNTED MIXER WITH FNPT INJECTION PORT
5/30/08
"B" HOLES "C" DIAMETER ON A "D" D.B.C.
150 LB. RAISED FACE FLANGED ENDS
KOFLO STATIC MIXER CONSTRUCTED OFSCHEDULE 40 OR 10 PIPE WITH *____ FIXED LOW PRESSURE LOSS DESIGN MIXING ELEMENTS
"A"(Inches)
NOTE: SCH 40 IS USED FOR CARBON STEEL MIXERS SCH 10 IS USED FOR SS/ALLOY MIXERS 3" AND LARGER
"E"
FNPT INJECTION PORT "F" SIZE OR AS SPECIFIED
DIRECTIONOF FLOW
Tab 6
Modified ISR System – AOP Pre-Treatment System Air Stripping
QED Air Stripper Model ver. 2.01 2/15/2010
Site DataName: Maija Seppanen e-mail: maija.seppanen@arcadis-
us.comProject: Raytheon RAPAUnits: English Altitude: 0 ftAir Temp: 90 F Flow: 60 gpmWater Temp: 72 FStripper: EZ-Tray 16.x - Click for details Stripper Air Flow: 850 cfmStripper Max Flow: 150 gpm
Water ResultsContaminant Influent
(ppb)Target (ppb)
4-Tray Results (ppb)
4-Tray %Removal
6-Tray Results (ppb)
6-Tray %Removal
1,1,1-trichloroethane 4310 0 < 1 100.000 < 1 100.0001,1,2-trichloroethane 493 0 12.8 97.404 2.4 99.5131,1-dichloroethane 6318 0 2.7 99.957 < 1 100.0001,1-dichloroethylene 13789 0 < 1 100.000 < 1 100.0001,2,4-trimethylbenzene 609 0 < 1 100.000 < 1 100.0001,2-dichloroethane 992 0 15.2 98.468 2.1 99.7881,3,5-trimethylbenzene 1101 0 < 1 100.000 < 1 100.0001,4-dioxane 15767 0 15363.8 2.557 15363.8 2.5572-butanone (MEK) 9340 0 7462.1 20.106 7448.6 20.2512-hexanone (MBK) 6107 0 42.2 99.309 3.8 99.938acetone 15175 0 12805.1 15.617 12796.2 15.676benzene 569 0 < 1 100.000 < 1 100.000c-1,2-dichloroethylene 12174 0 3.0 99.975 < 1 100.000carbon disulfide 701 0 < 1 100.000 < 1 100.000chloroethane 496 0 < 1 100.000 < 1 100.000chloroform (trichloromethane) 12973 0 13.8 99.894 < 1 100.000ethylbenzene 300 0 < 1 100.000 < 1 100.000isopropylbenzene 472 0 < 1 100.000 < 1 100.000m-xylene 426 0 < 1 100.000 < 1 100.000methylene chloride 13043 0 51.7 99.604 3.5 99.973naphthalene 153 0 15.6 89.804 6.6 95.686o-xylene 254 0 < 1 100.000 < 1 100.000t-1,2-dichloroethylene 111 0 < 1 100.000 < 1 100.000tetrachloroethylene (PERC,PCE) 1514 0 < 1 100.000 < 1 100.000toluene 5607 0 2.1 99.963 < 1 100.000trichloroethylene (TCE) 44178 0 3.5 99.992 < 1 100.000trichlorofluoromethane 590 0 < 1 100.000 < 1 100.000vinyl chloride (chloroethylene) 4997 0 < 1 100.000 < 1 100.000
Air ResultsContaminant 4-Tray
(ppmV)4-Tray (lb/hr)
6-Tray (ppmV)
6-Tray (lb/hr)
Page 1 of 3QED Stripper Model
2/15/2010http://64.9.214.199/cgi-bin/cmod_run.pl
1,1,1-trichloroethane 7.6390 0.12948 7.6393 0.129491,1,2-trichloroethane 0.8511 0.01443 0.8695 0.014741,1-dichloroethane 15.0893 0.18973 15.0955 0.189811,1-dichloroethylene 33.6308 0.41426 33.6313 0.414271,2,4-trimethylbenzene 1.1974 0.01829 1.1980 0.018301,2-dichloroethane 2.3339 0.02935 2.3651 0.029741,3,5-trimethylbenzene 2.1652 0.03307 2.1660 0.033081,4-dioxane 1.0820 0.01211 1.0820 0.012112-butanone (MEK) 6.1585 0.05642 6.2027 0.056822-hexanone (MBK) 14.3171 0.18221 14.4076 0.18336acetone 9.6481 0.07120 9.6840 0.07147benzene 1.7215 0.01709 1.7223 0.01709c-1,2-dichloroethylene 29.6851 0.36566 29.6922 0.36575carbon disulfide 2.1771 0.02106 2.1772 0.02106chloroethane 1.8175 0.01490 1.8178 0.01490chloroform (trichloromethane) 25.6675 0.38934 25.6940 0.38974ethylbenzene 0.6680 0.00901 0.6681 0.00901isopropylbenzene 0.9285 0.01418 0.9285 0.01418m-xylene 0.9484 0.01279 0.9487 0.01280methylene chloride 36.1666 0.39030 36.3009 0.39175naphthalene 0.2536 0.00413 0.2701 0.00440o-xylene 0.5651 0.00762 0.5657 0.00763t-1,2-dichloroethylene 0.2707 0.00333 0.2707 0.00333tetrachloroethylene (PERC,PCE) 2.1586 0.04549 2.1587 0.04549toluene 14.3831 0.16839 14.3884 0.16845trichloroethylene (TCE) 79.4960 1.32715 79.5021 1.32725trichlorofluoromethane 1.0155 0.01773 1.0155 0.01773vinyl chloride (chloroethylene) 18.9044 0.15012 18.9046 0.15013
NotesCopyright -- QED Treatment Equipment, PO Box 3726, Ann Arbor, MI 48106.
PH-> 1-800-624-2026 or 1-734-995-2547, FX-> 1-734-995-1170. E-mail->[email protected]. WEB->www.qedenv.com.
The QED modeler estimates unit performance for the listed contaminants. Results assume -
1. dissolved-phase contaminant within a water matrix 2. clean stripper air 3. no surfactants, oil, grease or other immiscible phase(s) in the influent 4. unit operated within the given parameters and as instructed in the O&M
manual
Stripper performance shall meet or exceed either the required effluent concentration(s) or effluent estimates, whichever is greater, for the conditions supplied and assumes the influent concentrations of each contaminant are less than 25% solubility in water. QED makes no claim of the model's accuracy beyond the 25% solubility in water limit.
Page 2 of 3QED Stripper Model
2/15/2010http://64.9.214.199/cgi-bin/cmod_run.pl
Contact UsFill out your contact and project information and click Send to have a QED Treatment application specialist contact you.
Name - Maija Seppanen
Company - Company
Phone - Phone Fax - Fax
e-mail - [email protected] - Raytheon RAPA
Application Notes
Send Reset
Save Data
Use the following URL to reconstruct your data form for future remodeling with changes. This URL can be saved in any text file for record keeping and later retrieval. This run's URL:
http://64.9.214.199/cgi-bin/remodel.pl?u=e&tw=72&ta=90&f=60&a=0&s=16.x&n=Maija&[email protected]&p=Rayth&c=9,4310;13,493;15,6318;16,13789;23,609;27,992;29,1101;33,15767;36,9340;40,6107;55,15175;63,569;81,12174;84,701;89,496;91,1
Page 3 of 3QED Stripper Model
2/15/2010http://64.9.214.199/cgi-bin/cmod_run.pl
Sliding Tray, High-EfficiencyAir Strippers for VOC Removal
800-624-2026www.qedenv.com
Air flows up through perforatedtrays creating a turbulent froth zonewith a high air-to-liquid surface areafor mass transfer of volatile organiccompounds (VOCs)
Additional space required by conventionalstacking tray air strippers.
E-Z Tray®
Conventional air strippers needmore than twice the accessand tray removal space than E-Z Tray® air strippers.
Hinged door optionallows for easy accesswithout door removal.
Flow rates available from1 to 1,000 gpm.
Front access hatches sealtight and are removedquickly with hand-knobs.
Split-tray option reduces maximumtray weight to only 28 lbs., even on the 1,000 gpm unit!
Front access slide-out trays allowunit maintenance by one person.
E-Z Trayaccessarea
Flow Rates from 1 to 1,000 gpm and Options to Fit Every Treatment Project
The E-Z Tray® Air Stripper (U.S. Patent Number5,518,668) is a sliding tray, stainless steel air stripperused to remove volatile organic compounds (VOC)from contaminated groundwater and waste streams.The exclusive design of the E-Z Tray stripper results invery high removal efficiencies in an easier to maintainprocess unit.
Any air stripping process subject to fouling conditionshas to contend with periodic cleaning in order toretain treatment efficiencies and capacity. Tower airstrip pers can become maintenance headaches whenthe tower packing becomes clogged and cementedtogether with bio-fouling or precipitants. When theperforated trays in stacking tray air strippers becomefouled they require major disassembly, cranes orhoists, and lots of room.
Unlike these traditional types of air strippers, QED’s E-Z Tray air strippers use removable, lightweight, front slide-out trays. This unique feature providesmany advantages, including one person cleaning andless building space.
E-Z Tray air strippers are available in configurationswith 4 or 6 trays, with maximum flow rates from 1-25 gpm (4-100 Lpm) all the way up to 1,000 gpm(3,784 Lpm).
NEW – High Capacity Process Air StrippersThese air strippers are engineered to serve in larger,process-type projects involving multiple treatmentstages, where they are an effective component oflarge-scale water or wastewater processes in
E-Z Tray
• Single personcleaning
• Easy processmonitoring andinspection, even while inoperation
• Reducedfootprint forinstallation andmaintenance
• High removalefficiencieseasier tomaintain
• Easily modeledonline bycustomer tohelp processevaluation
E-Z Tray AdvantagesTower AirStrippers
• Condition ofpacking andliquid and airflow distribu-tion are verydifficult toobserve
• Small footprintbut very tallstructurerequired
• More difficultto keep atdesignperformance
• More complexprocessassistancerequired
Stacking Tray AirStrippers
• Major disassemblysteps and crewneeded
• Difficult toimpossible toobserve air andliquid flowdistribution duringoperation
• Lots of spaceneeded fordisassembly, toaccess all sidesand to lift andstore tray stages
• More difficult tokeep at designperformance
• Online modelernot offered
Easier tray cleaning andsuperior technical supportmake E-Z Tray® air strippersa smart choice!
manufacturing, refining, chemical processing andother industries. They can act as a pre-treatment stagefor other process elements, such as large aerobicbiotreatment units, removing VOCs at much lowerairflow rates to reduce the costs of off-gas treatment.
All of this combined with the easier maintenance andsmaller footprint of QED's sliding tray air strippers,has led E-Z Tray to become the preferred choice formajor remediation and process stream projects in theU.S. and abroad.
The QED VOC Removal AdvantageProven equipment, expert help with its selection and installation, and support you can count on when you need it
Air Stripper SpecificationsModel Maximum Dry Operating Shell Dimension TraysNo. Flow Range Weight Weight (LxWxH) Per Tier
4.4 1-50 gpm (4-189 Lpm) 630 lbs. (286 kg) 985 lbs. (447 kg) 29 x 27 x 82 in. (74 x 69 x 208 cm) 4 x 29 lbs. (4 x 13 kg)
4.6 1-50 gpm (4-189 Lpm) 780 lbs. (354 kg) 1,219 lbs. (553 kg) 29 x 27 x 102 in. (74 x 69 x 259 cm) 6 x 29 lbs. (6 x 13 kg)
6.4 1-65 gpm (4-246 Lpm) 790 lbs. (358 kg) 1,285 lbs. (583 kg) 37 x 27 x 82 in. (94 x 69 x 208 cm) 4 x 40 lbs. (4 x 18 kg)
6.6 1-65 gpm (4-246 Lpm) 978 lbs. (443 kg) 1,591 lbs. (722 kg) 37 x 27 x 102 in. (94 x 69 x 259 cm) 6 x 40 lbs. (6 x 18 kg)
8.4 1-75 gpm (4-284 Lpm) 955 lbs. (433 kg) 1,580 lbs. (717 kg) 49 x 27 x 82 in. (124 x 69 x 208 cm) 4 x 50 lbs. (4 x 23 kg)
8.6 1-75 gpm (4-284 Lpm) 1,182 lbs. (536 kg) 1,956 lbs. (887 kg) 49 x 27 x 102 in. (124 x 69 x 259 cm) 6 x 50 lbs. (6 x 23 kg)
12.4 1-120 gpm (4-454 Lpm) 1,165 lbs. (528 kg) 2,105 lbs. (955 kg) 73 x 27 x 82 in. (185 x 69 x 208 cm) 4 x 60 lbs. (4 x 447 kg)
12.6 1-120 gpm (4-454 Lpm) 1,442 lbs. (654 kg) 2,606 lbs. (1,182 kg) 73 x 27 x 102 in. (185 x 69 x 259 cm) 6 x 60 lbs. (6 x 447 kg)
16.4 1-150 gpm (4-566 Lpm) 1,625 lbs. (737 kg) 2,870 lbs. (1,302 kg) 49 x 52 x 84 in. (124 x 132 x 213 cm) 8 x 50 lbs. (8 x 23 kg)
16.6 1-150 gpm (4-566 Lpm) 2,011 lbs. (912 kg) 3,553 lbs. (1,612 kg) 49 x 52 x 104 in. (124 x 132 x 264 cm) 12 x 50 lbs. (12 x 23 kg)
24.4 1-250 gpm (4-946 Lpm) 2,100 lbs. (953 kg) 3,980 lbs. (1,805 kg) 73 x 52 x 84 in. (185 x 132 x 213 cm) 8 x 60 lbs. (8 x 27 kg)
24.6 1-250 gpm (4-946 Lpm) 2,599 lbs. (1,179 kg) 4,926 lbs. (2,234 kg) 73 x 52 x 104 in. (185 x 132 x 264 cm) 12 x 60 lbs. (12 x 27 kg)
48.4 1-500 gpm (1,893 Lpm) 5,000 lbs. (2,268 kg) 12,500 lbs. (5,670 kg) 98 x 71 x 84 in. (249 x 180 x 213 cm) 16 x 60 lbs. (16 x 27 kg)
48.6 1-500 gpm (1,893 Lpm) 5,500 lbs. (2,495 kg) 13,000 lbs. (5,897 kg) 98 x 71 x 104 in. (249 x 180 x 264 cm) 24 x 60 lbs. (24 x 27 kg)
96.4 1-1,000 gpm (3,785 Lpm) 11,000 lbs. (4,990 kg) 25,000 lbs. (11,340 kg) 142 x 98 x 84 in. (361 x 249 x 213 cm) 32 x 60 lbs. (32 x 27 kg)
96.6 1-1,000 gpm (3,785 Lpm) 11,500 lbs. (5,216 kg) 30,000 lbs. (13,608 kg) 142 x 98 x 104 in. (361 x 249 x 264 cm) 48 x 60 lbs. (48 x 27 kg)Standard construction is 304 SS, other alloys upon request. *Allow additional space for accessory components. (blower, piping, etc.)
Exclusive Online PerformanceModeler has been developedto assist you in selecting themost effective air strippingpackage for your groundwatercleanup project
E-Z Tray®
Model 24.4E-Z Tray®
Model 16.4E-Z Tray®
Model 6.4
count on when you need it
Active Nominal Additional SpaceArea Air Flow for Tray Removal*2.8 ft.2 (0.26 m2) 210 cfm (5.95 m3/min) 27 in. (69 cm)
2.8 ft.2 (0.26 m2) 210 cfm (5.95 m3/min) 27 in. (69 cm)
3.8 ft.2 (0.35 m2) 320 cfm (9.06 m3/min) 35 in. (89 cm)
3.8 ft.2 (0.35 m2) 320 cfm (9.06 m3/min) 35 in. (89 cm)
5.6 ft.2 (0.52 m2) 420 cfm (11.89 m3/min) 47 in. (119 cm)
5.6 ft.2 (0.52 m2) 420 cfm (11.89 m3/min) 47 in. (119 cm)
8.8 ft.2 (0.82 m2) 600 cfm (16.99 m3/min) 71 in. (180 cm)
8.8 ft.2 (0.82 m2) 600 cfm (16.99 m3/min) 71 in. (180 cm)
11.1 ft.2 (1.03 m2) 850 cfm (24.07 m3/min) 47 in. (119 cm)
11.1 ft.2 (1.03 m2) 850 cfm (24.07 m3/min) 47 in. (119 cm)
17.5 ft.2 (1.63 m2) 1,300 cfm (36.81 m3/min) 72 in. (183 cm)
17.5 ft.2 (1.63 m2) 1,300 cfm (36.81 m3/min) 72 in. (183 cm)
27 ft.2 (2.51 m2) 2,600 cfm (73.62 m3/min) 72 in. (183 cm)
27 ft.2 (2.51 m2) 2,600 cfm (73.62 m3/min) 72 in. (183 cm)
54 ft.2 (5.02 m2) 5,200 cfm (147.25 m3/min) 2 x 72 in. (2 x 183 cm)*
54 ft.2 (5.02 m2) 5,200 cfm (147.25 m3/min) 2 x 72 in. (2 x 183 cm)*
Try it for yourself today! Use our exclusiveonline stripper modeler atwww.qedenv.com/model/model.htmlto spec the exact size and configuration foryour project. Then talk to a QED applicationsspecialist toll-free at (800) 624-2026for fast, free system design assistance and a price quote.
E-Z Tray®
Model 96.6
How it WorksAs contaminated groundwater enters throughthe top of the air stripper, millions of airbubbles are forced by blower pressure upthrough the perforated trays. This creates aturbulent froth zone with an extremely highair-to-liquid surface area for mass transfer ofvolatile organic compounds (VOCs) from liquidto air. Using the froth instead of a conventionaltower packing delivers high VOC removalefficiencies even under fouling conditions, andis easier to inspect and maintain.
6095 Jackson RoadAnn Arbor, MI 48106-3726USA
800-624-2026T: 734-995-2547F: [email protected]
The World Leader in Air-Powered RemediationFor Remediation, Landfills and Groundwater Sampling
CODE 2336 4/09
Visit qedenv.com/air-strippers to view and use the exclusive OnlinePerformance Modeler, which allows you to model your process conditions andselect the most efficient air stripping package for your VOC removal project.You can also view case studies where E-Z Tray air strippers were the topchoice in successful projects.
QED Quality Control,Manufacturing Standardsand Customer ServiceExperienced site owners, including major oilcompanies, are increasingly choosing E-Z Tray®
air strippers from QED due to their uniquefeatures and solid technical support, including:
• Lower long-term O&M costs due to easiertray maintenance than tower-type orstacking tray air strippers.
• Lightweight, slide-out trays don’trequire hoists, regardless of the size ofthe air stripper.
• E-Z Tray air strippers need less buildingspace, which can lower building costs.
• QED’s staff and resources are #1 in airstripper technical and service support,including for unusual applications.
• Online Performance Modeler tool available 24/7 to help you select theproper air stripper.
• QED quote & delivery times are quickand dependable.
1565 Alvarado StreetSan Leandro, CA 94577USA
800-624-2026T: 510-346-0400F: [email protected]
QED EZ-Tray Model 16.4 - Front View
BLOWER
46
51.5
93
89
GRAVITYDRAIN4" PIPE
PUMP
CONTROL PANEL
Copyright QED Environmental Systems, Inc., 2001
QED EZ-Tray Model 16.4 - Top View
GRAVITYDRAIN
AREA OF TRAYEXTRACTION
AREA OF TRAYEXTRACTION
BLOWER
INLETPUMP
DISCHPUMP
CONTROL PANEL
47.25
93
51.5
AIR EXHAUST8" PIPE
WATER INLET4" FNPT
Copyright QED Environmental Systems, Inc., 2001
Page 1 of 3
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate: 1/28/2010
I. Define System Parameters
a. Conveyance PipingInternal Diameter of Conveyance Piping 7.981 in (8-in. Nominal Dia., galv. steel)
0.67 ftMin. Flow Rate per Conveyance Line 900.0 ft3 / minFlow velocity 43.2 ft / sec
II. Define Flow Characteristics
a. Conveyance Piping
where:NRe = Reynolds Number
Internal Diameter of Conveyance Piping, D 7.981 in0.67 ft
St. Petersburg, FloridaRaytheon Company
Calculate friction loss due to air flow through piping.
AIR STRIPPER BLOWERS (B-200A/B) DESIGN CALCULATIONSModified ISR System
AOP Pre-Treatment System
eeR
DN
mean velocity of flow, v 43.2 ft / secweight density of fluid (assume air), ρ 0.0752 lb / ft3
1.89E-05 kg / (m*sec)1.27E-05 lb / (sec*ft)
Reynolds Number, N Re 170,025 (dimensionless)
(NRe < 2000 = Laminar, NRe > 4000 = Turbulent)
Flow is Turbulent
III. Determine Friction Factors
In the turbulent regime, the friction factor can be approximated by;Note: This equation applies for smooth piping onlyOther materials require friction factor obtained from Friction Factor chart
a. Conveyance Piping
Friction Factor, f 4.05E-03 (dimensionless)
eeR
DN
32.0Re
125.00014.0
Nf
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #6\(4) Tab #6_B-200A&B Calc.xls ARCADIS
Page 2 of 3
St. Petersburg, FloridaRaytheon Company
AIR STRIPPER BLOWERS (B-200A/B) DESIGN CALCULATIONSModified ISR System
AOP Pre-Treatment System
IV. Determine Other Resistance Losses
a. Conveyance Piping
i. Flow Resistance due to Sudden Expansion6" Blower outlet expands to 8" conveyance line
Internal Diameter of Conveyance Piping, d1 6.065 inInternal Diameter of Conveyance Piping, d2 7.981 in
Resistance, K1 0.21 (dimensionless)
ii. Fittings Size (in) K-Value Quantity Total K-Value
Butterfly Valve 8 0.63 3 1.89Diaphragm Valve 8 5.1 1 5.190 Degree Elbow 8 0.42 10 4.2
Total K 11.40
V. Determine Pressure Loss/Drop
KL
fZZgP
)4()(2
22
2115.0
d
dK
a. Conveyance Piping
i. Conveyance Pipe Length, L 100 ftii. No vertical height change, therefore, Za-Zb = 0 15 ft [assumed]
iii. Gravity, g 32.2 ft / sec2
iv. gc 32.2 lb-ft / sec2-lbf
Pressure Drop, ∆Pa 30.92 lb / ft2
0.21 psi
5.9 in. water
VI. Other Items
Air Stripper 4 in. water [loss per tray]24 in. water [total loss - 6 trays]
Actuated Flow Control Valve (Electric) 10 in. water [assumed]
Discharge into a Pressurized Line 10 in. water [assumed]
Air Stripper Inlet Screen 2 in. water [assumed]
csba
c gK
D
LfZZ
g
gP
2)4()( Re
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #6\(4) Tab #6_B-200A&B Calc.xls ARCADIS
Page 3 of 3
St. Petersburg, FloridaRaytheon Company
AIR STRIPPER BLOWERS (B-200A/B) DESIGN CALCULATIONSModified ISR System
AOP Pre-Treatment System
VII. Total Pressure Blower will be required to Generate
ΔPa 5.9 in. waterOther Items 46.0 in. waterSafety Factor 15%
Total Pressure Required 59.73 in. water
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #6\(4) Tab #6_B-200A&B Calc.xls ARCADIS
PRESSURE BLOWERS
BULLETIN 451JANUARY, 2001
• Static pressures to 58”WG• Capacities to 5200 CFM• Temperatures to 600̊ F.
ARRANGEMENT 4
ARRANGEMENT 10
ARRANGEMENT 8
For greater pressures and capacities: see Type HP Pressure Blowers
7660 QUINCY STREET–WILLOWBROOK,ILLINOIS 60521-5596TEL: [630] 794-5700•FAX: [630] 794-5776•WEB: http://www.nyb.com •E-MAIL: [email protected]
PAGE 2
DESIGN FEATURES
• Pressures to 58”WG.
• Capacities to 5200 CFM.
• Stable performance . . . the pressure curveremains stable from wide-open to closed-off . . .fan instability, or pulsation, is eliminated evenwhen “turn-down” approaches zero flow.
• Efficiency . . . advanced wheel and aerodynamichousing design combine for air-handling efficiencysuperior to conventional radial-wheel designs.
• Wide performance range . . . choice of 13 wheeldiameters and five outlet sizes enable efficientfan selection across a broad range of volumes andpressures.
• Choice of arrangements . . . direct-drive and belt-drive.
• Wide application range . . . designed for continuousoperation in combustion, cooling, conveying, drying,and various process systems.
CONSTRUCTION FEATURES
• All-welded steel housings . . . heavy-gauge hous-ings are rigidly braced to prevent “flexing” at highpressures.
• Flanges . . . continuously welded flanges matchANSI Class 125/150 hole pattern.
• Balance . . . all wheels are precision-balancedprior to assembly . . . fans with motors and drivesmounted by nyb are final-balanced at the speci-fied running speed.
• Shafting . . . straightened to close tolerance to min-imize “run-out” and ensure smooth operation.
• Inlet configuration . . . a choice of three inlet typesallows units to be tailored to specific applicationrequirements.
• Lifting eyes . . . standard on all units for ease ofhandling and installation.
• Finish . . . medium-green industrial coating.
... for process systems
© Copyright 2001 by The New York Blower Company.® Registered trademark of The New York Blower Company.
BLOWERS
PRESSURE
Arrangement 1 Pressure Blower with plain pipe inlet.
Arrangement 4 Pressure Blower with Venturi inlet.
Arrangement 8 Pressure Blower
with motor, coupling guard,and shaft and bearing guard.
The New York Blower Company certifies thatthe Pressure Blowers shown herein arelicensed to bear the AMCA Seal. The ratingsshown are based on tests and procedures per-formed in accordance with AMCA Publication211 and comply with the requirements of theAMCA Certified Ratings Program.
PRESSURE BLOWERS
WHEEL
PAGE 3
ALUMINUM
STANDARD
The unique Pressure Blower wheel is designedto provide efficient performance and reducedsound levels . . . the dual-taper design conceptyields typical efficiencies up to 10 percentagepoints greater than conventional straight radialwheels. Riveted high-strength aluminum alloyblades and side plates minimize overhungwheel weight and starting inertia. Ductile-iron,taper-lock hubs make wheels easily removable.Welded steel and stainless steel wheels are alsoavailable . . . see page 5.
Recommended for belt-driven applications only.Wheel is mounted onshaft mounted in heavy-duty bearings.
Max. airstream temperature:200˚F.–aluminum wheel.300˚F.–steel wheel.600˚F.–heat fan.
ARRANGEMENT 1
A compact direct-driveunit with a minimumnumber of moving partsfor ease of maintenance.Wheel is mounted directlyon motor shaft.
Max. airstream temperature:180˚F.
ARRANGEMENT 4
Direct-drive arrangementsimilar to Arrangement 1,but with integral motorpedestal . . . fan shaft isconnected to the motorshaft with a flexible cou-pling.
Max. airstream temperature:200˚F.–aluminum wheel.300˚F.–steel wheel.600˚F.–heat fan.
ARRANGEMENT 8
Enclosed belt-drive ar-rangement. Ideal for out-door applications. Wheelmounted on shaftmounted in heavy-dutybearings.
Max. airstream temperature:200˚F.–aluminum wheel.300˚F.–steel wheel.600˚F.–heat fan.
ARRANGEMENT 10
ARRANGEMENTSStandard aluminum wheel.
MATERIAL SPECIFICATIONSU. S. STANDARD SHEET GAUGE TO 7 GAUGE
FLANGEDIMENSIONS
[INCHES]† Holes straddle centerline.
ANSI Class 125/150 hole pattern.Flange thickness 3/8”
WHEEL WEIGHTSAND INERTIA [WR2=LBS.–FT.2]
PAGE 10
DIMENSIONS [INCHES] Dimensions not to be used for construction unless certified.
Wheeldia.
Wheeldia.
Wheeldia.
Scrollandsides
Outletsize
Inletflange
AArr.4
B JJ L MNNArr.8
Motorframe
Arr. 4, 8
A
H
C D F GArr. 8
Arrangement
Arr. 8
8
Arr. 8Arr. 4
4
Arr. 4Arr. 10
10
RArr.
4, 8 10
Housing Shaft dia. Bearings Drive keySide platesSide plates Arrangement Arr. 1 Arrangement Arrangement
Drive Inlet Driveend
In-board1, 10 888 1010
Fan weight*Arrangement
84 10
SArr.
84
Arr. 10 Arr. 10 Arr. 10 Arr. 10 Arr. 10 Arr. 10K N S T U V W
14-1819-2223-26
14-18
12
10
8
8
6
8
6
143-145182-184
182-184
182-184
182-184
182-184
182-184
213-215
213-215
213-215
213-215
213-215
213-215
213-215
254-256
254-256
254-256
254-256
254-256
284-286
284-286
284-286
284-286324-326
324-326 291⁄4281⁄4291⁄4263⁄426
26
26
26
26
263⁄4
263⁄4243⁄4
243⁄4
243⁄4
243⁄4
243⁄4
24
24
24
24
23
23
193⁄419
19 181⁄4
181⁄4
181⁄4
173⁄4
173⁄4
173⁄4
213⁄4
23
23 39
39
38
375⁄8
38
331⁄2
375⁄8
361⁄8
331⁄2
361⁄8
311⁄8 55⁄8
61⁄8
61⁄8
7
7
71⁄4 71⁄4
71⁄4 71⁄4103⁄4
103⁄4
85⁄8
85⁄8
85⁄8
85⁄8
85⁄8
85⁄8
65⁄8
65⁄8 37⁄8
41⁄2
5
5
41⁄2
41⁄2
41⁄2
37⁄8
37⁄8
33⁄8
33⁄843⁄8
51⁄2
51⁄2
61⁄4
61⁄4
63⁄4
63⁄4 231⁄2
231⁄2
191⁄2
191⁄2
191⁄2
191⁄2
191⁄2
141⁄8
141⁄8
141⁄8
141⁄8
141⁄8
141⁄8
141⁄8
141⁄8
141⁄8
85⁄8
85⁄8 15 145165
230
165185190235
240
290
315
190
260
290
320
300
350
375
390 550
540
535
450
430
515
495440425420320315510
490
400
395
320
315
395
295 205
305
210
310
390
215
315
400
325
405
410
15
15
15
17191⁄4
191⁄4
245⁄8
245⁄8
245⁄8
253⁄8
253⁄8
253⁄8
161⁄2
161⁄2
161⁄2
161⁄2
161⁄2
161⁄2
183⁄4
183⁄4
183⁄4
183⁄4
183⁄4241⁄4247⁄8
241⁄8
51⁄8
51⁄8
55⁄8
55⁄8
61⁄4
61⁄4
61⁄4
61⁄4
37⁄8
5
5
63⁄4
63⁄4
63⁄4
63⁄4
371⁄4
371⁄4
331⁄4
321⁄4
321⁄4
267⁄8
267⁄8
267⁄8
267⁄8
213⁄8
317⁄8
317⁄8
261⁄2
261⁄2
25
25
241⁄219 391⁄2
417⁄8
417⁄8443⁄8
443⁄8
443⁄8
471⁄2
471⁄2
471⁄2
471⁄2513⁄4543⁄8
543⁄8
543⁄8567⁄8
567⁄8 463⁄8 277⁄8
277⁄8463⁄8437⁄8
437⁄8431⁄8427⁄8421⁄8
421⁄8
363⁄4
363⁄4
363⁄4
363⁄4
341⁄2
341⁄233
341⁄2
423⁄442
42
365⁄8
365⁄8343⁄8355⁄8333⁄8
333⁄8
333⁄8
317⁄8
317⁄8
317⁄8
531⁄4
513⁄4
397⁄8
397⁄8
421⁄2
421⁄2455⁄8441⁄2475⁄8
475⁄8
517⁄8
517⁄853
19
19
173⁄4
173⁄4
19193⁄4
143-145182-184143-145
143-145
04
06
08
10
12
19-22
14-18
19-22
23-26
15-18
19-22
23-26
19-22
23-26
14-18 10 10 10 17⁄16 17⁄16 A A A A 3⁄8 3⁄819-22 10 10 10 17⁄16 17⁄16 B B A B 3⁄8 3⁄823-26 10 10 7 111⁄16 17⁄16 B C A B 3⁄8 3⁄8
23-26
191⁄2235⁄8265⁄8
21275⁄8275⁄8
135⁄8161⁄2191⁄2
113⁄4147⁄8175⁄8
143⁄8171⁄2205⁄8
123⁄4151⁄2181⁄4
31⁄241⁄241⁄2
222626
173⁄8197⁄8197⁄8
87⁄8107⁄8107⁄8
91⁄8107⁄8107⁄8
93⁄8121⁄4121⁄4
93⁄4113⁄4113⁄4
10113⁄4113⁄4
81⁄41111
101⁄41313
KArr.8
31⁄4
31⁄4
27⁄8
27⁄8
27⁄8
27⁄8
33⁄8
33⁄8
33⁄8
31⁄4
31⁄4
37⁄827⁄8
33⁄8
33⁄8
* Bare fan weight, pounds, is approximate for units with aluminum wheels, less motors. For units with steel wheels,add the difference in wheel weights from the table at left.
Tolerance: ± 1⁄8”
Tolerance: ± 1⁄8”
14041406
Size AluminumWt.[lbs.] WR2
SteelWt.[lbs.] WR2
19.25 11.222.3 11.2
52.0 30.2461.0 35.48
50.0 26.8958.5 31.46
48.0 23.7956.0 27.75
46.0 20.9353.5 24.35
34.0 14.1640.0 16.66
32.5 12.3338.0 14.42
31.0 10.6736.5 12.56
29.5 9.1634.5 10.72
22.0 6.1326.0 7.25
21.0 5.2224.5 6.09
20.0 4.4123.0 5.07
19.0 3.6821.5 4.16
18.0 3.0420.5 3.46
19.0 10.2221.9 11.0
18.75 9.2921.9 10.8
18.5 8.4221.7 10.6
12.75 5.3115.6 5.4
12.5 4.7415.5 5.3
12.25 4.2215.3 5.2
12.0 3.7315.1 5.1
9.5 2.6512.4 2.6
9.25 2.312.2 2.6
9.0 1.9812.1 2.5
8.75 1.6911.8 2.4
8.5 1.4311.7 2.4
15041506, 1508
16041606, 1608
17041706, 1708
18041806, 18081904, 19061908, 19102004, 20062008, 20102104, 21062108, 21102204, 22062208, 22102306, 23082310, 23122406, 24082410, 24122506, 25082510, 25122606, 26082610, 2612
Flange I. D. O. D. Bolt Holes†size circle No. - Size
04 4 9 71⁄2 8 - 3⁄4”06 6 11 91⁄2 8 - 7⁄8”08 8 131⁄2 113⁄4 8 - 7⁄8”10 10 16 141⁄4 12 - 1”12 12 19 17 12 - 1”
A–200 Series Ball B–22400 Series Roller C–300 Series Ballnyb reserves the right to substitute bearings of equal rating.
Arr. 10 motor lim.ODP TEFC C-NW215T256T256T
215T254T254T
165⁄8185⁄8185⁄8
PAGE 11
DRAWINGS Dimensions not to be used for construction unless certified.
L
A
B
FD
G
CJJM
H
UT
UT
R S
9/16" DIA. HOLES
INLETVENTURI
INLETPLAIN PIPE
JJ-3/8"
LCHOUSING
JJ-3/8"
Arrangement
4PRESSUREBLOWERS
1 1/4"
UT
SR
H
JJ
MJJ-5/16" JJ-3/8"
F
UT
D
9/16" DIA. HOLES
B
A
L
NN
G
C
K
12 1/4"
LCHOUSING
INLETVENTURI
INLETPLAIN PIPE
Arrangement
8PRESSUREBLOWERS
NH
MJJ-3/8" JJ-3/8"
WTV
B
WTV
D F
R
A
S
SIZES 19–26: 3/4" DIA. HOLESSIZES 14–18: 9/16" DIA. HOLES
L
C
G
KJJ
LCHOUSING
INLETVENTURI
INLETPLAIN PIPE
Arrangement
10PRESSUREBLOWERS
The New York Blower Company has a policy of continuous product developmentand reserves the right to change designs and specifications without notice.
Housings are reversible and rotatable in 221⁄2˚ increments except Down Blast and Bottom Angular Down which require special construction.Arrangement 10 fans Sizes 19–22 are not rotatable in the field.
The New York Blower CompanyFan-to-SizeFan Selection Data
Project:Location:Contact:
Fan Tagging: 012810-02C2
Fan DesignProduct: Type HP Pressure Blower Arrangement: 4Size/Model: 28506 Drive type: DirectWheel Type: AluminumWheel Material: AluminumWheel Width: 100.0 % Wheel Diameter: 100.0 %
Operating ConditionsVolume Flow Rate: 850 CFM Fan Speed: 3500 rpmFan Static Pressure: 61.2 in wg Fan Input Power: 17.1 bhpOutlet Velocity: 4337 ft/min VP/SP ratio: 0.0192Altitude (above mean sea level): 0 ft Operating Temperature: 70 Deg FOperating Inlet Airstream Density: 0.0750 lb/ft3Static Efficiency: 47.70% Mechanical Efficiency: 48.62%Maximum Operating Temperature: 70 Deg F Maximum Safe Operating Speed: 3600 rpm
Sound Power Level Ratings Levels expressed in dB (power levels reference 10^(-12) watts)Center Frequency (Hz): 63 125 250 500 1000 2000 4000 8000Octave Bands: 1 2 3 4 5 6 7 8 OverallTotal Fan Power Levels*: 102.9 104.9 102.8 105.7 105.8 102.7 96.7 92.7 112.3Inlet Power Levels**: 99.9 101.9 99.8 102.7 102.8 99.7 93.7 89.7 109.3Outlet Power Levels**: 99.9 101.9 99.8 102.7 102.8 99.7 93.7 89.7 109.3
*As corrected for point of operation (location on fan curve)**Unsilenced Inlet and Outlet power ratings are 3 dB lower than total fan power levels under the assumption that "half" of the sound power can be attributed to each opening. Silenced power ratings include this 3 dB reduction as well as the silencer attenuation. Estimated Sound Pressure Levels Expressed in dB (pressure levels reference 2x10-7 microbar) Directivity/Reflection Factor (Q) is 2, hemispherical radiation; Distance is 3 ft.; A-weighting is in use.
The estimated sound pressure level outside the fan due to an open inlet OR outlet is 99.6 dBA at 3.0 feet. The estimated sound pressure level outside the fan when BOTH inlet and outlet are ducted is 91.2 dBA at 3.0 feet (Housing Radiated Noise). Your Representative:Baltus Incorporated6020 W Maple Road Suite 504West Bloomfield, MI 48322Phone: (248) 851-6420Fax: (248) 851-6694E-Mail: [email protected]
Version: 1.77.30-R (October 2007) Printed: 02/03/2010 PDF. Calc Mode: 3
Static PressurePower
0
10
20
30
40
50
60
0
5
10
15
20
25
30
35
0 500 1000 1500 2000 2500 3000
The New York Blower CompanyFan-to-Size
Type HP Pressure Blower Volume Flow Rate: 850 CFM Temp.: 70 Deg F28506 Aluminum Fan Static Press.: 61.2 in wg Altitude: 0 ftArr.: 4 Speed: 3500 rpm Density: 0.0750 lb/ft3
Power: 17.1 bhp Outlet Velocity: 4337 ft/minTag: 012810-02C2
Copyright ©1999 The New York Blower Company. Phone: (248) 851-6420Baltus, Inc. [v1.77.30-R -- October 2007] Date Printed: 2/3/2010 Baltus IncorporatedCustomer: Your Sales Representative:
Fan
Sta
tic P
ress
ure
(in w
g)Fan Input P
ower (bhp)
Volume Flow Rate (CFM)
Version: 1.77.30-R (October 2007) Printed: 02/03/2010 PDF. Calc Mode: 3
Page 1 of 1
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate: 01/28/2010
Considerations:
Tank volume = 1,100 gal
Freeboard = 244 gal 8-inch Depth
Usable tank volume = Total tank volume - Solids storage - Freeboard
Usable tank volume = 856 gal
Process flow rate = 60 gpm Air Stripper Effluent
Total retention time = 14 min
Operation = 80 % Full
Design retention time = 11 min
Additional requirements = 0 gal
Calculate Required Tank Volume:
Retention time volume = Flow rate x Design retention time
684 gal
Minimum volume = Retention time volume + Additional requirements
684 gal
Tank Selection:
Cylindrical Tank:
Diameter = 7.2 feet
Total Tank Height = 4.3 feet
Usable Tank Volume = 856 gal
Available Tank Volume = 856 gal
Required Tank Volume = 684 gal
Volume Available > Volume Required therefore design is acceptable
AIR STRIPPER DISCHARGE TANK (T-700) SIZINGModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #6\(7) Tab #6_T-700 Sizing.xlsx ARCADIS
Page 1 of 3
AIR STRIPPER DISCHARGE PUMPS (P-400A/B) DESIGN CALCULATIONS
Total dynamic head calculation = Calc prepared by: M. Seppanenhead loss due to elevation change Calc checked by: J. Perellahead loss due to pipe friction Date: 1/28/2010head loss across misc. process componentsrequired discharge head
Calculate pipe size:
Where: v = Velocity (ft/sec)Q = Flow rate (gpm)r = Pipe radius (in)
Flow Rate Pipe Size Pipe ODWall
Thickness Pipe ID Area velocity(gpm) (in) (in) (in) (in) (ft2) (ft/sec)
60 2 2.375 0.154 2.067 0.023 5.5860 3 3.500 0.216 3.068 0.051 2.5360 4 4.500 0.237 4.026 0.088 1.47
*Pipe dimensions noted for Schedule 40 galvanized steel piping.Note: Design for velocity between 3 and 5 feet/sec to maintain sufficient scour velocity.
Calculate head loss (he) due to elevation change:
assume: Height from pump to discharge point = 20 feetHead loss, he = 15 feet
Calculate head loss due to pipe friction losses:
Step 1. There are multiple pipe sections with flow and pipe diameters shown below
Pipe Section 1 Nominal pipe diameter 1 = 3 inch
Flow (v1) = 60 gpm
Step 2. Calculate the friction factor for each pipe section using the Hazen-Williams formula
Hazen-Williams f = .2083 * (100/C)1.852 * (q1.852) / (D4.8655)Formula
f = Friction in head in feet of water per 100 ft of pipeC = Constant for inside roughness
(140 for new galvanized steel pipe, 150 for hdpe pipe)q = Flow rate (gal/min)D = Inside diameter of pipe (inches)
Nominal Diam (in)
ID (in)
ID w/ deposition (in)
1 1.049 0.9241.5 1.610 1.4852 2.067 1.9423 3.068 2.9434 4.026 3.9016 6.065 5.94
NOTE: a 0.0625 inch (1/16 inch) deposition on interior pipe wall is included in diameter for calculation - 1.003 - (2 x 0.0625) = 0.878 inch diameter
Modified ISR System - AOP Pre-Treatment SystemTotal Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
sec60
min1*
)*( 2r
Qv
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #6\(9) Tab #6_P-400A&B TDH.xlsx ARCADIS
Page 2 of 3
AIR STRIPPER DISCHARGE PUMPS (P-400A/B) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Friction factor for Pipe Section 1C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 60 gal/minD1 = Inner pipe diameter (inches) 2.943 inches (see NOTE)
Pipe Section 1 friction factor 1.1 ft water / 100 feet of pipe
Step 3. Calculate the equivalent length of pipe for each section
Nominal Fitting size 1 in 1.5 in 2 in 3 in 4 in 6 in
90˚ Elbows 2.7 3.4 3.6 4.0 4.6 10.4Standard Tee (thru flow) 3.2 5.6 7.7 12.0 17.0 38.3Standard Tee (branch flow) 6.6 9.9 12.0 17.0 21.0 47.3Ball valve (full open) 1.6 2.3 2.9 4.3 5.5 12.3Check Valve 11.0 15.0 19.0 27.0 38.0 85.5Union 0.3 0.4 0.5 0.5 0.65 1.5Reducer (2/1) 1.0 1.5 1.5 3.0 4.0 9.0Expansion (1/2) 1.5 2.5 3.0 4.0 6.0 13.5
Equivalent lengths from reference: Civil Engineering Reference Manual, 9th Ed, Professional Publications, Inc., 2003; and "Flow of Fluids", Crane Technical Paper No. 410, 1988.
Pipe Section 1 - 3"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 1,400 1,400Standard Tee (thru flow) 6 12 72Standard Tee (branch flow) 2 17 3490˚ Elbows 12 4 48Union 6 0.5 3Check Valve 2 27 54Ball valve (full open) 6 4.3 26
Equivalent Length: 1,637
Step 4. Determine pipe friction for each pipe section.
total pipe friction = total equivalent length x friction factor
Total Pipe Friction - Pipe Section 1total equivalent length = 1,637 feet
friction factor = 1.1 feet water / 100 feet of pipe
Total Pipe Friction = 18.8 feet
Step 5. Determine total pipe friction (all sections)
Total Pipe Friction - Pipe Section 1 = 18.8
Equivalent Length
Equivalent Length per Fitting (ft)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #6\(9) Tab #6_P-400A&B TDH.xlsx ARCADIS
Page 3 of 3
AIR STRIPPER DISCHARGE PUMPS (P-400A/B) DESIGN CALCULATIONSModified ISR System - AOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Calculate Total Dynamic Head:
Head Loss Due to Change in Elevation 20 ft
Head loss due to pipe friction 19 ft
Head loss Across Misc. Process Components Flow meter 12 ft
Required Discharge Pressure (0 psi) 0 ft
Total Dynamic Head Required - Calculated 51 ft
Design Safety Factor 25%
Total Dynamic Head Required - Design 64 feet
Pump Design Requirements:Flow 60 gpm
Total Dynamic Head 64 feet
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #6\(9) Tab #6_P-400A&B TDH.xlsx ARCADIS
Model: 3196 Size: 2X3-8 Group: MTi 60Hz RPM: 1750 Stages: 1
Job/Inq.No. : RAYTHEONPurchaser : ARCADISEnd User : ARCADIS Issued by : Rev. : 0Item/Equip.No. : P-400AB Quotation No. : RAPA PRETREATMENT Date : 02/03/2010Service :Order No. :
Operating Conditions Pump PerformanceLiquid: Water Published Efficiency: 46.0 % Suction Specific Speed: 8,693 gpm(US) ftTemp.: 100.0 deg F Rated Pump Efficiency: 46.0 % Min. Hydraulic Flow: 8.3 gpmS.G./Visc.: 1.000/1.000 cp Rated Total Power: 2.2 hp Min. Thermal Flow: N/AFlow: 60.0 gpm Non-Overloading Power: 3.4 hpTDH: 64.0 ft Imp. Dia. First 1 Stg(s): 7.7500 inNPSHa: NPSHr: 2.0 ftSolid size: Shut off Head: 67.2 ft% Susp. Solids(by wtg):
Vapor Press:
Max. Solids Size: 0.5000 inNotes: 1. The Mechanical seal increased drag effect on power and efficiency is not included, unless the correction is shown in the
appropriate field above. 2. Magnetic drive eddy current on power and efficiency is not included. 3. Elevated temperatureeffects on performance are not included. 4. Non Overloading power does not reflect v-belt/gear losses.
Tab 7
Modified ISR System – AOP Pre-Treatment System Tank Venting
Page 1 of 2
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate: 1/28/2010
I. Define System Parameters
a. Conveyance PipingInternal Diameter of Conveyance Piping 3.068 in (3-in. Nominal Dia., galv. steel)
0.26 ftMin. Flow Rate per Conveyance Line 30.0 ft3 / minFlow velocity 9.7 ft / sec
II. Define Flow Characteristics
a. Conveyance Piping
where:NRe = Reynolds Number
Internal Diameter of Conveyance Piping, D 3.068 in0.26 ft
mean velocity of flow, v 9.7 ft / secweight density of fluid (assume air), ρ 0.0752 lb / ft3
TANK VENT BLOWER (B-300) DESIGN CALCULATIONSModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
Calculate friction loss due to air flow through piping.
eeR
DN
1.89E-05 kg / (m*sec)1.27E-05 lb / (sec*ft)
Reynolds Number, N Re 14,743 (dimensionless)
(NRe < 2000 = Laminar, NRe > 4000 = Turbulent)
Flow is Turbulent
III. Determine Friction Factors
In the turbulent regime, the friction factor can be approximated by;Note: This equation applies for smooth piping onlyOther materials require friction factor obtained from Friction Factor chart
a. Conveyance Piping
Friction Factor, f 7.19E-03 (dimensionless)
eeR
DN
32.0Re
125.00014.0
Nf
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #7\(1) Tab #7_B-300 Calc.xls ARCADIS
Page 2 of 2
TANK VENT BLOWER (B-300) DESIGN CALCULATIONSModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
IV. Determine Other Resistance Losses
a. Conveyance Piping
i. Flow Resistance due to Sudden ExpansionNot applicable
Internal Diameter of Conveyance Piping, d1 3.068 inInternal Diameter of Conveyance Piping, d2 3.068 in
Resistance, K1 0.00 (dimensionless)
ii. Fittings Size (in) K-Value Quantity Total K-Value
Butterfly Valve 3 0.81 2 1.62Diaphragm Valve 3 6.1 1 6.190 Degree Elbow 3 0.54 8 4.32
Total K 12.04
V. Determine Pressure Loss/Drop
csba
c gK
D
LfZZ
g
gP
2)4()(
2
Re
22
2115.0
d
dK
a. Conveyance Piping
i. Conveyance Pipe Length, L 140 ftii. No vertical height change, therefore, Za-Zb = 0 20 ft [assumed]
iii. Gravity, g 32.2 ft / sec2
iv. gc 32.2 lb-ft / sec2-lbf
Pressure Drop, ∆Pa 3.33 lb / ft2
0.02 psi
0.6 in. water
VI. Other Items
Actuated Flow Control Valve (Electric) 10 in. water [assumed]
Discharge into a Pressurized Line 10 in. water [assumed]
VII. Total Vacuum Blower will be required to Generate
ΔPa 0.6 in. water
Other Items 20.0 in. waterSafety Factor 15%
Total Vacuum Required 23.74 in. water
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #7\(1) Tab #7_B-300 Calc.xls ARCADIS
B-9
DR 303M & CP 303MRegenerative BlowerFEATURES• Manufactured in the USA – ISO 9001 compliant• CE compliant – Declaration of Conformity on file• Maximum flow: 55 SCFM• Maximum pressure: 45 IWG• Maximum vacuum: 3.4" Hg (42 IWG)• Standard motor: 0.5 HP, TEFC• Cast aluminum blower housing, impeller
& cover; cast iron flanges (threaded)• UL & CSA approved motor with permanently
sealed ball bearings• Inlet & outlet internal muffling• Quiet operation within OSHA standardsMOTOR OPTIONS• International voltage & frequency (Hz)• Chemical duty, high efficiency, inverter duty
or industry-specific designs• Various horsepowers for application-specific needsBLOWER OPTIONS• Corrosion resistant surface treatments & sealing options• Remote drive (motorless) models• Slip-on or face flanges for application-specific needsACCESSORIES (See Catalog Accessory Section)• Flowmeters reading in SCFM• Filters & moisture separators• Pressure gauges, vacuum gauges & relief valves• Switches – air flow, pressure, vacuum or temperature• External mufflers for additional silencing• Air knives (used on blow-off applications)• Variable frequency drive package
BLOWER PERFORMANCE AT STANDARD CONDITIONSAIR FLOW RATE (M3/MIN)
INC
HE
S O
F W
ATE
R
PS
IG
PRESSURE
AIR FLOW RATE (SCFM)
600500400300200
80604020
MO
TOR
WIN
DIN
GTE
MP
RIS
E °
C
PO
WE
RIN
PU
TW
ATT
S
BLO
WE
RA
IR T
EM
PR
ISE
°C
AIR FLOW RATE (M3/MIN)
3
INC
HE
S O
F W
ATE
R
INC
HE
S O
F M
ER
CU
RY
SUCTION
AIR FLOW RATE (SCFM)
MO
TOR
WIN
DIN
GTE
MP
RIS
E °
C
PO
WE
RIN
PU
TW
ATT
S
BLO
WE
RA
IR T
EM
PR
ISE
°C
MM
OF
WA
TER
0 10 20 30 40 50
0.5 1.0 1.5 2.0
60 70
750
500
250
1000
2
1
1.5
MM
OF
WA
TER
0 10 20 30 40 50
0.5 1.0 1.5 2.0
60 70
750
500
250
1000
1.0
0.5
6050403020
600500400300200
80604020
6050403020
60 Hz
50 Hz
60 Hz
50 Hz
55
45
35
25
15
5
-55
-45
-35
-25
-15
-5
2.0 41250 1250
Rev. 2/04
SUCTION
60 Hz
50 Hz
0
10
20
30
40
50
0 10 20 30 40 50 60 70
AIR FLOW RATE (SCFM)
INC
HE
S O
F W
AT
ER
0
200
400
600
800
1000
1200
0 0.5 1 1.5 2
AIR FLOW RATE (m3/MIN)
mm
H2O
AMETEK Technical and Industrial Products, Kent, OH 44240 • e mail: [email protected] • internet: www.ametektmd.com
ROTRON Regenerative Blowers
SectionB 2004.qxd 6/26/04 10:37 AM Page B-9
Scale CAD drawing available upon request.
Specifications subject to change without notice. Please consult your Local Field Sales Engineer for specification updates.
B-10
DR 303M & CP 303MRegenerative Blower
1 Rotron motors are designed to handle a broad range of world voltages and power supply variations. Our dual voltage 3 phase motors arefactory tested and certified to operate on both: 208-230 /415-460 VAC-3 ph-60 Hz and 190-208/380-415 VAC-3 ph-50 Hz. Our dualvoltage 1 phase motors are factory tested and certified to operate on both: 104-115/208-230 VAC-1 ph-60 Hz and 100-110 /200-220VAC-1 ph-50 Hz. All voltages above can handle a ±10% voltage fluctuation. Special wound motors can be ordered for voltages outside ourcertified range.
2 Maximum operating temperature: Motor winding temperature (winding rise plus ambient) should not exceed 140°C for Class F rated motorsor 120°C for Class B rated motors. Blower outlet air temperature should not exceed 140°C (air temperature rise plus inlet temperature).Performance curve maximum pressure and suction points are based on a 40°C inlet and ambient temperature. Consult factory for inlet orambient temperatures above 40°C.
3 Maximum blower amps corresponds to the performance point at which the motor or blower temperature rise with a 40°C inlet and/orambient temperature reaches the maximum operating temperature.
SPECIFICATIONS
A .68 INCH DIAMETER CONNECTOR HOLE
B CAPACITOR LOCATION ON SINGLE PHASE MOTORS
DIMENSIONS: INMM
TOLERANCES: .XX ± .082
(UNLESS OTHERWISE NOTED)
Same as DR303AE72M –
038842except addChemical
Processing (CP)
features from catalog
inside front cover
MODEL DR303AE9M DR303AE72M DR303AE86M CP303FA91MLRPart No. 038841 038842 038843 080148Motor Enclosure – Shaft Material TEFC – CS TEFC – CS TEFC – CS ChemTEFC – SSHorsepower 0.5 0.5 0.5Voltage 1 115/230 208-230/460 575Phase – Frequency 1 Single - 60 Hz Three - 60 Hz Three - 60 HzInsulation Class 2 F F FNEMA Rated Motor Amps 6.2/3.1 1.3-1.2/0.6 0.6Service Factor 1.25 1.25 1.25Locked Rotor Amps 21/10.5 10-9.2/4.6 4.2Max. Blower Amps 3 6/3 1.63/0.83 0.7Recommended NEMA Starter Size 0/00 00/00 00Shipping Weight 40 lb (18.2 kg) 36 lb (16.3 kg) 35 lb (15.9 kg)
Rev. 2/04
AMETEK Technical and Industrial Products, Kent, OH 44240 • e mail: [email protected] • internet: www.ametektmd.com
ROTRON Regenerative Blowers
SectionB 2004.qxd 6/26/04 10:37 AM Page B-10
Tab 8
Modified ISR System – AOP Pre-Treatment System Scrubber Blow-Down System
Page 1 of 1
Calc prepared by: J. DarbyCalc checked by: J. PerellaDate: 2/5/2010
Considerations:
Process flow rate = 15 gpm
Minimum retention time = 60 min
Free board requirement = 1 foot
Height of discharge fitting = 0.75 foot
Calculate Tank Volume:
Retention time volume = Flow rate x Retention time
900 gal
Tank Dimensions:
Selected diameter = 6 feet
Usable volume = 900 gal
Calculated height = 4.3 feet
Freeboard requirement = 1 feet
Height of discharge fitting = 0.75 feet
Required height = 6.0 feet
Selected height = 6.0 feet
Tank Selection:
Vertical Cylindrical Tank Diameter = 6 feet
Height = 6 feet
Volume = 170 ft3
Volume = 1,268 gal
Nominal Volume = 1,200 gal
Scrubber Blow-Down Tank (T-1100) SizingModified ISR System
Raytheon CompanySt. Petersburg, Florida
AOP Pre-Treatment System
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #8\(1) Scrubber T-1100 Sizing.xlsx ARCADIS
Page 1 of 3
TRANSFER PUMP (P-900) DESIGN CALCULATIONSAOP Pre-Treatment System
Calc prepared by: J. DarbyCalc checked by: J. PerellaDate: 2/5/10
Total dynamic head calculation = head loss due to elevation changehead loss due to pipe frictionhead loss across misc. process componentsrequired discharge head
Calculate pipe size:
Where: v = Velocity (ft/sec)Q = Flow rate (gpm)r = Pipe radius (in)
Flow Rate Pipe Size Pipe OD Wall Thickness Pipe ID Area velocity(gpm) (in) (in) (in) (in) (ft2) (ft/sec)
15 1 1.315 0.133 1.049 0.006 5.4215 1.5 1.900 0.145 1.610 0.014 2.3015 2 2.375 0.154 2.067 0.023 1.39
*Pipe dimensions noted for Schedule 40 galvanized steel piping.Note: Design for velocity between 3 and 5 feet/sec to maintain sufficient scour velocity.
Calculate head loss (he) due to elevation change:
assume: Height from pump to discharge point = 6 feetHead loss, he = 6 feet
Calculate head loss due to pipe friction losses:
Step 1. There are multiple pipe sections with flow and pipe diameters shown below
Pipe Section 1 Nominal pipe diameter 1 = 1.5 inch
Flow (v1) = 15 gpm
Pipe Section 2 Nominal pipe diameter 2 = 2 inch
Flow (v2) = 15 gpm
Step 2. Calculate the friction factor for each pipe section using the Hazen-Williams formula
Hazen-Williams Formula f = .2083 * (100/C)1.852 * (q1.852) / (D4.8655)
f = Friction in head in feet of water per 100 ft of pipeC = Constant for inside roughness
(140 for new carbon steel pipe)q = Flow rate (gal/min)D = Inside diameter of pipe (inches)
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
sec60
min1*
)*( 2r
Qv
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #8\(2) P-900 TDH.xlsx ARCADIS
Page 2 of 3
TRANSFER PUMP (P-900) DESIGN CALCULATIONSAOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Nominal Diam (in) ID (in)ID w/ deposition
(in)
1 1.003 0.8781.5 1.452 1.3272 1.826 1.7013 2.691 2.5664 3.460 3.3356 5.460 5.335
NOTE: a 0.0625 inch (1/16 inch) deposition on interior pipe wall is included in diameter for calculation - 1.003 - (2 x 0.0625) = 0.878 inch diameter
Friction factor for Pipe Section 1C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 15 gal/minD1 = Inner pipe diameter (inches) 1.327 inches (see NOTE)
Pipe Section 1 friction factor 4.2 ft water / 100 feet of pipe
Friction factor for Pipe Section 2C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 15 gal/minD2 = Inner pipe diameter (inches) 1.701 inches (see NOTE)
Pipe Section 2 friction factor 1.3 ft water / 100 feet of pipe
Step 3. Calculate the equivalent length of pipe for each section
Nominal Fitting size 1 in 1.5 in 2 in 3 in 4 in 6 in
90˚ Elbows 2.7 3.4 3.6 4.0 4.6 10.4Standard Tee (thru flow) 3.2 5.6 7.7 12.0 17.0 38.3Standard Tee (branch flow) 6.6 9.9 12.0 17.0 21.0 47.3Ball valve (full open) 1.6 2.3 2.9 4.3 5.5 12.3Check Valve - Spring and Swing 11.0 15.0 19.0 27.0 38.0 85.5Union 0.3 0.4 0.5 0.5 0.7 1.5Reducer (2/1) 1.0 1.5 1.5 3.0 4.0 9.0Expansion (1/2) 1.5 2.5 3.0 4.0 6.0 13.5
Equivalent lengths from reference: Civil Engineering Reference Manual, 9th Ed, Professional Publications, Inc., 2003; and"Flow of Fluids", Crane Technical Paper No. 410, 1988.
Pipe Section 1 - 1.5" - pump discharge to LPGAC
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 20 20
Standard Tee (thru flow) 2 3.2 6Standard Tee (branch flow) 0 6.6 0Union 4 0.3 1.290˚ Elbows 8 2.7 21.6Check Valve - Swing 1 11 11Expansion (1.5 x 1) 2 1.5 3.0Ball valve (full open) 4 1.6 6
Equivalent Length: 70
Equivalent Length per Fitting (ft)
Equivalent Length
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #8\(2) P-900 TDH.xlsx ARCADIS
Page 3 of 3
TRANSFER PUMP (P-900) DESIGN CALCULATIONSAOP Pre-Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Pipe Section 2 - 2" - LPGAC, pump discharge to south end of Building E, tie-in to Mod. ISR discharge
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 2,500 2,000
Union 4 0.5 2.090˚ Elbows 8 3.6 28.8Check Valve - Swing 0 19 0
Equivalent Length: 2,031
Step 4. Determine pipe friction for each pipe section.
Total pipe friction = Total equivalent length x Friction factor
Total Pipe Friction - Pipe Section 1Total equivalent length = 70 feet
Friction factor = 4.2 feet water / 100 feet of pipe
Total Pipe Friction = 3.0 feet
Total Pipe Friction - Pipe Section 2Total equivalent length = 2,031 feet
Friction factor = 1.3 feet water / 100 feet of pipe
Total Pipe Friction = 25.8 feet
Step 5. Determine total pipe friction (all sections)
Total Pipe Friction - Pipe Section 1+2 = 28.7
Calculate Total Dynamic Head:
Head Loss Due to Change in Elevation 6 ft
Head loss due to pipe friction 29 ft
Head loss Across Misc. Process Components LPGAC-1 35 ft 1 psi = 2.31 ftLPGAC-2 23 ft
Flow Meter 12 ft
Required Discharge Pressure (0 psi) 0 ft
Total Dynamic Head Required - Calculated 105 ft
Design Safety Factor 20%
Total Dynamic Head Required - Design 126 feet
Pump Design Requirements:Flow 15 gpm
Total Dynamic Head 126 feet
Equivalent Length
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #8\(2) P-900 TDH.xlsx ARCADIS
1 NPT
D1
D2
L3
L1
L2
2
65⁄16
3⁄8 DRAIN
3⁄8FILL VENT
3⁄82 HOLES
3⁄4
M1
71⁄16 85⁄16
315⁄16
57⁄8
M2
1⁄24 HOLES
CAPACITORCOVER ONSINGLE PHASEONLY
7⁄8
TECHNICAL MANUAL
SSV Series VerticalMulti-StagePumps
G&LSeriesSSV
300 LB. FLANGE
4
General Characteristics2-pole
SSV Product Range 1SV 2SV 3SV 4SV 33SV 46SV 66SV 92SV Nominal Flow (GPM) 15 30 60 85 150 220 350 450 Flow Range (GPM) 2 – 22 6 – 40 11 – 75 17 – 110 30 – 195 45 – 285 70 – 420 90 – 580 Max. Head (Ft) 1100 945 1005 930 1125 1210 850 715 Max. Working Pressure (PSI) 2 360 PSIG 1 360 / 580 PSIG Temperature Range -20ºF to 250ºF (-30ºC to -121ºC) Motor Power (HP) ½ – 5 HP ¾ – 5 HP 2 – 15 HP 5 – 20 HP 3 – 60 HP 7½ – 75 HP 10 – 75 HP 15 – 75 HP Max. Pump Efficiency 44% 58% 64% 67% 76% 78% 78% 80% Material of Construction SVA AISI 304SS – – – – SVB AISI 304SS Cast Iron / AISI 316L SVC AISI 304SS – – – – SVD AISI 316LSS Cast Stainless Steel / AISI 316L Connection Sizes
SVA – Oval NPT 1" NPT 1¼" NPT 1½" NPT
–
– – – –
(female) (female) (female) SVB – Round ANSI 1¼" 1¼" 2" 2" 2½" 3" 4" 4" Size/Class 300# 300# 300# 300# 125/250# 1325/250# 125/250# 125/250# SVC – Top/Bottom Round 1¼" 1¼" 2" 2"
– – – –
ANSI – Size/Class 300# 300# 300# 300# SVD – Round ANSI 1¼" 1¼" 2" 2" 2½" 3" 4" 4" Size/Class 300# 300# 300# 300# 150/300# 150/300# 150/200# 150/300# Optional Connections (on request)
Victaulic (PJE) 1¼" 1¼" 2" 2"
– – – –
(Victaulic) (Victaulic) (Victaulic) (Victaulic)
1 Some staging may have MAWP of 580 psi (40 bar). 2 See pages 53-60 for specific details.
SVA1SV, 2SV, 3SV
SVB, SVD1SV, 2SV, 3SV, 4SV
SVC1SV, 2SV, 3SV, 4SV
VICTAULIC1SV, 2SV, 3SV, 4SV
SVB, SVD33SV, 46SV, 66SV, 92SV
6
SSV Product Line Numbering System for 1 – 4SV
The various versions of the SSV line are identified by a product code number on the pump label. This number is also the catalog number for the pump. The meaning of each digit in the product code number is shown below.Note: Not all combinations are possible. Consult your G&L distributor.
Example Product Code2 SV A 1 D 2 B 1 H
Options: H = Horizontal mount, refer to back cover VIC = Victaulic connections (1SVB/D – 4SVB/D only)
Mechanical Seal Options:
Number of Stages: B = 2 D = 4 F = 6 H = 8 K = 10 M = 12 P = 14 R = 16 V = 20 Z = 24 C = 3 E = 5 G = 7 J = 9 L = 11 N = 13 Q = 15 T = 18 X = 22
Driver: (50 Hz, no single phase number 0, 1, 4) 1 = 1 PH, ODP 3 = 575V, ODP 5 = 3 PH, TEFC 7 = 3 PH, XP 9 = 3 PH, TEFC with premium efficiency 2 = 3 PH, ODP 4 = 1 PH, TEFC 6 = 575V, TEFC 8 = 575V, XP 0 = 1 PH, XP
HP Rating: C = 1⁄2 E = 1 G = 2 J = 5 L = 10 N = 20 D = 3⁄4 F = 11⁄2 H = 3 K = 71⁄2 M = 15 P = 25
Hertz/RPM: 1 = 60 Hz, 3500 RPM 3 = 60 Hz, 3500 RPM, 380 V 5 = 60 Hz, 3500 RPM, 220-380 V, D.O.L. 2 = 50 Hz, 2900 RPM, 190-380 V, (50 Hz motor) 4 = 50 Hz, 2900 RPM, 460 V 6 = 60 Hz, 3500 RPM, 380 V, Y-DELTA 7 = 60 Hz, 1750 RPM, 208-230, 460 V
Material and Suction/Discharge: A = 304 stainless steel, in-line NPT threaded oval flange connections (1, 2, 3 only) B = 304 stainless steel, in-line ANSI flange (1, 2, 3, 4SV) C = 304 stainless steel, top/bottom ANSI flange connections D = 316 stainless steel, in-line ANSI flange
Product Line: Stainless Vertical
Nominal Flow: 1 = 15 GPM 2 = 28 GPM 3 = 55 GPM 4 = 86 GPM
Code No. Rotary Stationary Elastomer Reference Application 0 High Temp. General Carbon Silicon Viton Service 4 Silicon Carbide Carbide Graphite Filled Graphite 6 High Temp. Filled EPR Boiler Feed Carbon
Abrasive
Rating Plate 1, 2, 3 and 4SV
G&L PumpsSSV™
CATALOG NUMBER
GPM FEET RPM
DO NOT OPERATE AT CLOSED DISCHARGE
Goulds Pumps, ITT Industries, Inc. 8
2
5
3
7
4
1
6
1 Goulds Catalog Number 2 Capacity Range 3 TDH Range 4 Rated Speed 5 Rated Horsepower 6 Maximum Operating Pressure 7 Maximum Operating Temperature 8 Pump Serial Number
19
1SV Curve 3500 RPM
0
100
200
300
400
500
600
700
0 10 15 25 US GPM
FEET
TOTA
L D
YNA
MIC
HEA
D
CAPACITY
30
40
50
EFF
%
1100
1SV 60 Hz3500 RPM
0
0.5
HP/
STA
GE
0 5 m3/h
0
50
100
150
200
250
300
350
METERS
1000
800
900
0
8
12
20
4321
10
6
kW/S
TAG
E
0
.30
.20
.10
5
4
2
0.25
NPS
Hr
0
2
3
1
(m) (ft)
2 – 16 STAGES
18 – 22 STAGES*
* For vertical shaft installation only.
22 STAGE
20 STAGE
18 STAGE
16 STAGE
13 STAGE
11 STAGE
9 STAGE
8 STAGE
7 STAGE
6 STAGE
5 STAGE
4 STAGE
3 STAGE
2 STAGE
Eff.
BHP
15 STAGE
Your Mobile Water Treatment Specialists
7500 Boone Ave N, Suite 101, Brooklyn Park, MN 55428 Ph: 800-526-4999 Fax: 763-315-4614 www.carbonair.com Customer: ARCADIS, Tampa, FL Site: Unknown Date: 2/5/10 Design Basis: Water flow rate: 15 gpm Water temperature: 120 oF (from wet scrubber) Critical contaminant: TCE Influent concentration: 50 ppb Effluent criteria: < 1 ppb (assumed for ND) Water Quality: Chloride 1,700-12,000 ppm Recommendations: Liquid Phase Carbon Adsorbers Two FRP PC3 vessels in series, each with 250 lbs of carbon
The FRP vessels are recommended in order to avoid corrosion due to the high chloride. The lead and lag vessels are predicted to last 30 and 120 days, respectively. Recommend
changing out the lead vessel every 90 days. Note:
Chloride will not be effectively adsorbed by carbon and will have no adverse effect on the adsorption of non-polar organic compounds such as TCE. The high water temperature of 120 oF will increase the solubility of TCE in water and consequently will reduce the adsorbability of TCE onto carbon.
CONFIDENTIALITY NOTICE: Reproduction, disclosure, or distribution of any parts of this document is strictly prohibited without a written approval from Carbonair.
LIQUID-PHASE CARBON ADSORPTION MODEL CALCULATIONS
CARBONAIR ENVIRONMENTAL SYSTEMS
7500 BOONE AVENUE NORTH, SUITE 101
BROOKLYN PARK, MN 55428
PHONE: 800-526-4999
FAX: 763-315-4614
CARBON ADSORBERS: PC3
NO OF ADSORBERS IN SERIES: 1
TOTAL MASS OF CARBON (LBS): 250.00
FLOW RATE (GPM): 15.000
HYDRAULIC LOADING (GPM/SQ.FT): 6.3159
EMPTY BED CONTACT TIME (MIN.): 4.5435
DESIGN COMPOUND: TCE (120 F)
EXPECTED INFLUENT CONCENTRATION (PPB): 50.000
MODEL INFLUENT CONCENTRATION (PPB): 50.000
EFFLUENT CRITERIA (PPB): 1.0000
EFFECTIVE K-VALUE (%): 50.000
TIME(DAYS) VOLUME TREATED(GAL) EFF. CONC.(PPB)
5.0 108000. 0.0000
10.0 216000. 0.0000
15.0 324000. 0.0225
20.0 432000. 0.0759
25.0 540000. 0.2277
30.0 648000. 0.6064 BREAKTHROUGH
35.0 756000. 1.4180
40.0 864000. 2.8386
45.0 972000. 4.8516
50.0 1080000. 7.2420
55.0 1188000. 9.7850
60.0 1296000. 12.3006
65.0 1404000. 14.7117
70.0 1512000. 16.9811
75.0 1620000. 19.0984
80.0 1728000. 21.0658
85.0 1836000. 22.8937
90.0 1944000. 24.5925
95.0 2052000. 26.1721
100.0 2160000. 27.6421
105.0 2268000. 29.0125
110.0 2376000. 30.2933
115.0 2484000. 31.4906
120.0 2592000. 32.6117
Note: The model influent concentration results from the
impact of the other background compounds, which is
determined by using a competitive adsorption model
DISCLAIMER: ACTUAL RESULTS MAY VARY SIGNIFICANTLY FROM
THE MODEL. THE MODEL IS BASED ON THE ASSUMPTIONS THAT
THE FLOW RATE AND INFLUENT CONCENTRATION ARE CONSTANT,
AND ONLY THE CONTAMINANTS PROVIDED TO CARBONAIR ARE
PRESENT IN THE WATER. VARYING OPERATING CONDITIONS CAN
HAVE ADVERSE EFFECTS ON CARBON ADSORPTIVE CAPACITY.
THE PREDICTED BED LIFE IS NOT GUARANTEED.
LIQUID-PHASE CARBON ADSORPTION MODEL CALCULATIONS
CARBONAIR ENVIRONMENTAL SYSTEMS
7500 BOONE AVENUE NORTH, SUITE 101
BROOKLYN PARK, MN 55428
PHONE: 800-526-4999
FAX: 763-315-4614
CARBON ADSORBERS: PC3
NO OF ADSORBERS IN SERIES: 2
TOTAL MASS OF CARBON (LBS): 500.00
FLOW RATE (GPM): 15.000
HYDRAULIC LOADING (GPM/SQ.FT): 6.3159
EMPTY BED CONTACT TIME (MIN.): 9.0869
DESIGN COMPOUND: TCE (120 F)
EXPECTED INFLUENT CONCENTRATION (PPB): 50.000
MODEL INFLUENT CONCENTRATION (PPB): 50.000
EFFLUENT CRITERIA (PPB): 1.0000
EFFECTIVE K-VALUE (%): 50.000
TIME(DAYS) VOLUME TREATED(GAL) EFF. CONC.(PPB)
10.0 216000. 0.0000
20.0 432000. 0.0000
30.0 648000. 0.0000
40.0 864000. 0.0000
50.0 1080000. 0.0000
60.0 1296000. 0.0000
70.0 1512000. 0.0000
80.0 1728000. 0.0000
90.0 1944000. 0.0140
100.0 2160000. 0.0656
110.0 2376000. 0.2458
120.0 2592000. 0.8576 BREAKTHROUGH
130.0 2808000. 2.3719
140.0 3024000. 4.9095
150.0 3240000. 8.0677
160.0 3456000. 11.4139
170.0 3672000. 14.7078
180.0 3888000. 17.8383
190.0 4104000. 20.7704
200.0 4320000. 23.4838
210.0 4536000. 25.9837
220.0 4752000. 28.2780
230.0 4968000. 30.3755
240.0 5184000. 32.2903
Note: The model influent concentration results from the
impact of the other background compounds, which is
determined by using a competitive adsorption model
DISCLAIMER: ACTUAL RESULTS MAY VARY SIGNIFICANTLY FROM
THE MODEL. THE MODEL IS BASED ON THE ASSUMPTIONS THAT
THE FLOW RATE AND INFLUENT CONCENTRATION ARE CONSTANT,
AND ONLY THE CONTAMINANTS PROVIDED TO CARBONAIR ARE
PRESENT IN THE WATER. VARYING OPERATING CONDITIONS CAN
HAVE ADVERSE EFFECTS ON CARBON ADSORPTIVE CAPACITY.
THE PREDICTED BED LIFE IS NOT GUARANTEED.
Pressure Drop for PC 3F
0.00.51.01.52.02.53.03.54.04.5
0 2 4 6 8 10 12 14 16 18 20
Flow Rate (gpm)
Pres
sure
Dro
p (p
si)
Tab 9
Modified ISR System – AOP Treatment System Sodium Sulfite Contactor System
©MMVI NORWECO, INC.
220 REPUBLIC STREETNORWALK, OHIO, USA 44857-1156TELEPHONE (419) 668-4471FAX (419) 663-5440www.norweco.com
PROGRESS THROUGH SERVICE SINCE 1906
BIO-MAX® DECHLORINATION TABLETS
SPECIFICATIONSTablet Size 2 5/8" diameter,
1" thickApprox. Tablet Weight 5 oz. (140 grams)Active Ingredient Sodium Sulfite
( Na2SO3 )Active Ingredient 92%Inert Ingredients 8%Appearance and odor Blue-green tablet with
herbal odorD.O.T. Designation Non-Hazardous
GENERAL INFORMATIONBio-Max dechlorination tablets provide a convenient to usesource of concentrated sodium sulfite to instantly removechlorine from wastewater, potable water and process water.Containing 92% sodium sulfite and 8% inert ingredients,Bio-Max dechlorination tablets assist plant operators inmeeting stringent chlorine discharge limitations in a low cost,low maintenance, environmentally safe manner. Formulatedfor use in all major gravity or pressure rated tablet feeders,several patent pending inert compounds are blended intoBio-Max tablets during production. These compounds havea synergistic effect with the sulfite, resulting in a tablet withexceptional integrity and a precisely regulated dissolve rate.
A single chemical feed tube filled with 21 Bio-Max tabletswill remove 1 ppm chlorine from over 400,000 gallons of wateror wastewater without affecting dissolved oxygen levels orreleasing irritating and potentially dangerous treatmentchemicals into the environment. For a 15,000 GPD water orwastewater facility, this means up to 26 days of treatmentbefore new tablets must be loaded into the feed tubes. Alsoideal for periodic flows typical of USEPA storm watercompliance related activities, Bio-Max dechlorination tabletsare not affected by long periods of no flow conditions andcan be repeatedly immersed in water and dried down withno loss of integrity or performance.
Pound for pound, Bio-Max dechlorination tablets are 30%more effective in removing chlorine than ascorbic acid tabletsor slurries. This means less chemical consumption, lessmaintenance and of course, reduced operating costs for aslong as you operate your system. Available in 48 lb.resealable pails, Norweco’s Bio-Max tablets offer plantowners and operators the best way to meet stringent chlorinedischarge requirements.
ADVANTAGES92% concentrated sodium sulfiteCompletely eliminates both free and combined chlorineFor use in all types of tablet feedersCost effective treatment for high flow systemsNo effect on dissolved oxygen or pHVery low maintenance requiredNo mixing of chemicals or solutions
Bio-Max dechlorination tablets are available from your localNorweco dealer or distributor in conveniently packaged, childresistant 48 lb. resealable polyethylene pails with a whitebase and a blue-green lid.
CAUTIONBio-Max dechlorination tablets are a strongreducing agent containing sodium sulfite. Directcontact with most oxidizing agents such asBio-Sanitizer disinfecting tablets, swimmingpool tablets or any other chlorine containingcompound is extremely dangerous. Water orwastewater being treated with Bio-Maxdechlorination tablets should be at or near aneutral pH. If water or wastewater has anavailable chlorine level greater than 20 ppm ora water temperature greater than 100° F, donot use any mixture containing sodium sulfiteor other reducing agents. A reaction may occurwhich could generate heat and chlorine gas.Care must be taken in the handling and storageof Bio-Max tablets. Store only in sealed originalcontainer and in a well-ventilated area. Readthe product container label carefully prior to use.Keep out of the reach of children. This productshould not be used to treat water intended forhuman consumption.
DISTRIBUTED LOCALLY BY:
DECHLORINATION TABLETS
GENERAL SPECIFICATIONSBio-Max dechlorination tablets shall be formulated to serve as a source of concentrated sodium sulfite for the removal of chlorinein water, wastewater and process water. The slow and consistent release of concentrated sodium sulfite from Bio-Max tabletsshall allow their use in a variety of applications such as meeting National Pollution Discharge Elimination System (NPDES)criteria, and phase two storm water discharge requirements. The tablets shall be 2 5/8" diameter, 1" in thickness with anapproximate weight of 140 grams. Proprietary beveled edges incorporated into the tablets will stabilize the slow release ofsodium sulfite. Bio-Max dechlorination tablets shall contain a minimum of 92% sodium sulfite as an active ingredient and 8%patent pending inert ingredients. Ascorbic acid tablets or liquid sodium metabisulfite systems require the mixing of irritatingchemicals into a pumpable slurry which exposes operators to potentially hazardous conditions and shall not be considered forthis application.
TABLET PROPERTIES AND USAGEBio-Max dechlorination tablets shall release sodium sulfite in direct correlation to the velocity of the incoming flow. This shallallow design engineers and system operators to precisely regulate the sulfite dose, and in turn, the dechlorination process formaximum effectiveness and minimum operating cost. Patent pending inert ingredients added to Bio-Max tablets shall maintainthis predictable chemical dose at intermittent peak flow factors as high as four, and shall provide reliable elimination of chlorineeven when the significant runoff period is six hours. Bio-Max tablets shall be an ideal product for municipal storm watertreatment which requires treatment capacity for high or pressurized flow and then an extended time of no flow conditions. Byincorporating commercial feeders such as Norweco’s Bio-Dynamic tablet feeders, or constructing custom units, the consistentdosage of Bio-Max tablets will allow effective and controlled dechlorination for a wide variety of applications.
PRODUCT APPLICATIONBio-Max dechlorination tablets shall be incorporated into the treatment process following the chlorine contact tank or finaltankage. As Bio-Max tablets stop the disinfection process by eliminating chlorine, no bacterial sampling shall be performed onthe effluent or water stream following the addition of Bio-Max tablets. The dechlorination system can be designed so the entireflow needing dechlorination contacts the Bio-Max tablets or in a bypass arrangement where a percentage of flow is directed atthe tablets, is saturated with the sulfite, and then blended into the remainder of the flow. While the cost effective performanceof Bio-Max tablets is optimized with Norweco’s Bio-Dynamic tablet feeders in gravity flow applications, the tablets can provideexceptional dechlorination with field constructed feed systems or in conjunction with the various brands of pressure typefeeders. Check your feeder’s operating manual for further details.
DESIGN DATATablet Size 25/8" diameter, 1" thick Inert Ingredient Content 8%Approximate Tablet Weight 5 oz. (140 grams) U.S. DOT Hazard Class Non-hazardousActive Ingredient Sodium Sulfite – Na
2SO
3Appearance Characteristics Blue-Green Tablet with Herbal Odor
Active Ingredient Content 92% Special Design Features Beveled Edges
PRODUCT DOSAGEUnder gravity flow conditions, the sulfite dose from Bio-Max tablets shall be 6.75 mg/L at 70° F. Significant variations intemperature or flow velocity may have an impact on tablet dose. Adjustment of dosing equipment will be required upon start-up.Chlorine residuals prior to dechlorination fluctuate based on upstream treatment processes and conditions. Monitoring ofchlorine residual levels prior to dechlorination is recommended to insure consistent performance of the dechlorination system.Once steady performance of the upstream treatment process and dechlorination system is established only minor adjustmentsof the feeder shall be required. A single feed tube of Bio-Max dechlorination tablets shall remove up to 3.8 mg/L availablechlorine, with no excess sodium sulfite. To estimate average tablet usage, multiply plant flow in liters (l) per day by 6.75 mg/L,then divide this product by 1,000 and again by 140. The final result will be the number of Bio-Max dechlorination tablets used perday of operation. Consult your tablet feeder’s operational manual for further information.
PRODUCT STORAGEBio-Max dechlorination tablets are a strong reducing agent. Tablets should be stored in a cool, dry, well-ventilated area, awayfrom heat or flame. Avoid storage in areas subject to direct sunlight or temperatures in excess of 140° F. Stock should berotated on a first-in, first-out basis. Bio-Max dechlorination tablets must be stored in their original container with the lid tightlyclosed. Do not allow moisture to enter the pail during storage or while removing tablets for use. Moisture contamination mayaffect tablet integrity and performance. Do not reuse the empty container.
SAFETY INSTRUCTIONSBefore handling Bio-Max tablets, carefully read the container label and the Product Storage, Tablet Handling, Caution and FirstAid sections of these instructions. Do not add Bio-Max tablets to a feed tube containing any other product, particularly oil andpetroleum products or swimming pool chlorine. Such action may cause a violent reaction leading to fire or explosion. Do notcontaminate food or feed during the use, storage or disposal of Bio-Max tablets or the cleaning of chemical feed equipment.Always wear rubber gloves and either safety goggles or a face shield when handling Bio-Max tablets or working with any tabletfeeder or feed tube. Avoid contact with skin, eyes, mouth, respiratory system or clothing. Keep this product only in its tightlyclosed original container. Store only in a cool, dry, well-ventilated area.
TABLET HANDLINGUse only clean, dry utensils. Do not add Bio-Max dechlorination tablets to any device containing remnants of any other product– contact with oxidizers, such as Bio-Sanitizer disinfecting tablets or any other tablets used for chlorination can cause fire andthe release of toxic gas. Read the entire Bio-Max tablet container label and these instructions carefully before handling thisproduct. Use only in well-ventilated areas. Bio-Max tablets are not rated a hazardous substance by the U.S. DOT or USEPA,but necessary care should be taken in the use and handling of the tablets. Collected material can be dissolved in water,exercising caution as the solution can get hot. Dispose of dissolved material in any appropriate industrial waste collectionsystem. Consult local, state and federal regulatory agencies before disposing of any material.
FEED TUBE LOADING INSTRUCTIONS1. Remove feed tube from dispenser housing.2. Remove protective cap from feed tube; place cap in a clean, dry area.3. Remove any tablet residue by gently tapping feed tube on concrete or stone
surface. If tablets other than Bio-Max have been used, rinse tube and capwith fresh water until clean and allow to dry before proceeding.
4. Hold tube, slotted end up, at a 45° angle and slide Bio-Max dechlorinationtablets into the tube, one tablet at a time.
5. Ensure that all tablets lie flat, on top of one another, in the feed tube.6. Use your gloved hand to retain tablets inside the open end of the inverted
tube while filling.7. Carefully return tube to upright position.8. Replace the cap securely.9. Place tube back into housing, slotted end down.10. Be sure feed tube is fully engaged and rests evenly on the floor of the housing.11. If the tablet feeder incorporates multiple feed tubes, consult the manufacturer’s instructions to determine the correct
number of tubes to be filled and their placement.
CAUTIONDo not mix Bio-Max dechlorination tablets with acids or oxidizing agents such as Bio-Sanitizer disinfecting tablets or othertablets used for chlorination – fire or explosion could result. Keep out of the reach of children. Avoid contact with skin, eyes,mouth, respiratory system or clothing – failure to do so may cause irritation on contact. Wear rubber gloves and either safetygoggles or a face shield when handling this product. Product will form Sodium Sulfide at 600° C. At 900° C Sulfur Dioxide isformed. Inert ingredients could support combustion. Use self-contained breathing apparatus for fire fighting.
FIRST AID INSTRUCTIONSIf contact with skin occurs, wash with water for 15 minutes. If irritation persists, seek medical attention.If eye contact occurs, flush with water for at least 15 minutes. Get immediate medical treatment.If swallowed, promptly drink large quantities of water or milk. Induce vomiting. Avoid alcohol. Call physician immediately.If inhaled, move victim to fresh air. If difficulty in breathing persists, get immediate medical attention.In case of fire, immediately evacuate the area and notify the fire department.
MATERIAL SAFETY DATA SHEET EMERGENCY TELEPHONE: (800) 424-9300
BIO-MAX® DECHLORINATION TABLETS DATE PREPARED: JANUARY 2009
NOTE: THIS PRODUCT IS NOT RATED A HAZARDOUS MATERIAL BY THE U.S. DEPARTMENT OF TRANSPORTATION OR THE U.S.ENVIRONMENTAL PROTECTION AGENCY. THE FOLLOWING DATA IS FOR INFORMATIONAL PURPOSES ONLY.
I. PRODUCT IDENTIFICATION
TRADE NAME Bio-Max®CHEMICAL Sodium SulfiteCHEMICAL ABSTRACT SYSTEM NO. CAS #7757-83-7CHEMICAL DESCRIPTION ReducerFORMULA Na
2SO
3
U.S. DOT SHIPPING NAME Non-Hazardous Tablets, Item NM503401U.S. DOT HAZARD CLASS Non-Hazardous
II. INGREDIENTS
HAZARDOUS INGREDIENTS NoneNON-HAZARDOUS INGREDIENTS Sodium Sulfite 92%
Inert Ingredients 8% (Includes sustained release agents)
III. PHYSICAL DATA
BOILING POINT AT 760 mm Hg Decomposes at 900° CFREEZING/MELTING POINT Not ApplicableSOLUBILITY IN H
2O; % BY WEIGHT 25% at 80° C
SPECIFIC GRAVITY OF TABLET 2.63 (H2O = 1)
APPROXIMATE TABLET DENSITY 125 lbs./ft3
pH OF SOLUTION AlkalineVOLUME % VOLATILE Not ApplicableAPPEARANCE AND ODOR Blue-Green Tablet with Mild Odor
IV. FIRE AND EXPLOSION DATA
FLASH POINT Not ApplicableFLAMMABLE LIMITS IN AIR Not ApplicableEXTINGUISHING MEDIA Use extinguishing media appropriate for burning material. Compatible with water fog, spray foam or CO
2.
SPECIAL FIRE FIGHTING PROCEDURES NIOSH/MSHA-Approved, positive pressure, self-contained breathing apparatus with full face piece.UNUSUAL FIRE & EXPLOSION HAZARD At 600° C, Sodium Sulfide is formed. At 900° C, Sulfur Dioxide is formed. Inert ingredients could support combustion by burning,
yielding carbon dioxide and water. Use self-contained breathing apparatus for fire fighting.
V. HEALTH HAZARD DATA
ACUTE TOXICITY DATA (ANIMAL)LC 50 INHALATION See effects of overexposure.LD 50 ORAL 2825 MG/KG (Rabbit)LD 50 DERMAL See effects of overexposure.LC 50 AQUATIC Very high concentrations will chemically deplete dissolved oxygen necessary for aquatic life.
CHRONIC TOXICITY Sodium Sulfite may cause allergic reactions in sensitive individuals. Contact with strong acids or high temperatures maygenerate Sulfur Dioxide, which is toxic, corrosive, and hazardous.
VI. EFFECTS OF OVEREXPOSURE
PERMISSIBLE No permissible exposure limits have been established by OSHA.ACUTE
INHALATION Inhalation of product dust or solution may cause respiratory tract irritation.EYE Dust or solution may burn eyes on contact.SKIN Product dust or solution may result in skin irritation upon prolonged contact.INGESTION Ingestion may irritate gastrointestinal tract. Toxic if taken in large doses.
VII. EMERGENCY AND FIRST AID PROCEDURES
INHALATION Remove to fresh air. If not breathing, resuscitate and administer oxygen if readily available. Seek medical attention immediately.EYE CONTACT Immediately flush with large amounts of water for fifteen (15) minutes, rinsing eye thoroughly. Get medical attention.SKIN CONTACT Wash with plenty of soap and water for fifteen (15) minutes. Remove contaminated clothing. If skin irritation occurs, get medical attention. Wash
clothing before reuse.INGESTION If conscious, drink large quantities of water or milk and induce vomiting. Call a physician immediately. Avoid alcohol.
If unconscious, or in convulsions, seek medical attention immediately. Do not give anything by mouth to an unconscious person.
VIII. STEPS FOR MATERIAL SPILL
Spills exceeding 100 pounds should be reported to the local authorities.1. Contain all spilled material, wearing appropriate protective equipment.2. Place spilled material in clean, dry containers for disposal. Do not flush to surface water.
WASTE DISPOSAL METHODNot rated a hazardous substance by USEPA. Collected material can be dissolved in water, exercising caution. Dissolved material may be discharged into an appropriateindustrial waste collection system but consult local, state, and federal regulating agencies before disposing of any material.
IX. SPECIAL PROTECTION INFORMATION
RESPIRATORY PROTECTION If dusty conditions are encountered, use NIOSH/MSHA respirator with acid gas cartridge and dust pre-filter.VENTILATION Store and use in a well-ventilated area.EYE PROTECTION Chemical safety goggles.GLOVES Natural or synthetic rubber.OTHER PROTECTIVE EQUIPMENT Boots, aprons, or chemical suits as required to prevent skin contact.
THIS MATERIAL SAFETY DATA SHEET IS OFFERED SOLELY FOR YOUR INFORMATION, CONSIDERATION AND INVESTIGATION. NORWALK WASTEWATER EQUIPMENT COMPANY PROVIDES NOREPRESENTATIONS OR WARRANTIES, EITHER EXPRESSED OR IMPLIED, AND ASSUMES NO RESPONSIBILITY FOR THE ACCURACY OR COMPLETENESS OF THE DATA CONTAINED HEREIN.
220 REPUBLIC STREETNORWALK, OHIO, USA 44857-1156TELEPHONE (419) 668-4471FAX (419) 663-5440www.norweco.com
DISTRIBUTED LOCALLY BY:
Norweco®, Norweco.com®, Singulair®, Modulair®, Travalair®, Lift-Rail®, Microsonic®, Bio-Dynamic®, Bio-Sanitizer®, Bio-Neutralizer®, Bio-Kinetic®,Bio-Static®, Bio-Gem®, Bio-Regeneration®, Bio-Perc®, Blue Crystal®, ClearCheck®, ChemCheck®, Service Pro®, Grease Buster® and “BUSTER”logo® are registered trademarks of Norwalk Wastewater Equipment Company, Inc.
©MMVI NORWECO, INC.
ADDITIONAL CHEMICAL PRODUCTS FROM NORWECO
BIO-DYNAMIC® TABLET FEEDERSBio-Dynamic tablet feeders are a technological advancement in self-contained dry chemical dosing systems for the treatment ofwater or wastewater. A low cost, low maintenance and extremely effective method of chemical treatment, Bio-Dynamic feeders
have no mechanical components and require no electricity. The safety, accuracyand reliability provided by Bio-Dynamic feeders outperform gas, liquid and ultravioletsystems. With fourteen different models, Bio-Dynamic feeders have multipleinstallation options that provide maximum flexibility, including direct burial, in-lineand contact chamber mounting. Riser assemblies are available to eliminate theneed for a manhole or separate enclosure during direct burial installations. Fullyserviceable from finished grade, riser assemblies eliminate the need for confinedspace entry equipment required by OSHA regulations. Direct burial models includetrim lines that allow height adjustment on site for each installation. Molded inletand outlet hubs allow the Bio-Dynamic feeder to be directly connected to treatmentsystem piping without the need for a separate drop box. The tiered flow deck ofthe Bio-Dynamic feeder accommodates variable, intermittent and surge hydraulicflows into the system. The flow deck directs liquid to the feed tubes during lowflows and disperses liquid velocity throughout the feeder during peak flows, resultingin consistent chemical application. Chemical dosage is further controlled byinterchangeable weir plates or an optional sluice that can be completely adjustedfrom a 1" to 3" outlet width. The sluice can be adjusted during tablet feederoperation using only a standard socket wrench with extension. All models are
backed by a ten year limited warranty. Standard components include one-piece feed tubes with twist lock caps, adjustable inletbaffle, molded inlet and outlet hubs, molded mounting feet and interchangeable outlet weir plates.
BIO-LOGICAL® DISINFECTING TABLETSBio-Logical disinfecting tablets are a new type of biocide formulated exclusively for low flow water and wastewater disinfection.This patent pending blend of isocyanurates and buffering agents quickly eliminate bacteria without the use of concentratedoxidizing chemicals. Safe and effective to use in all dry tablet feeders, Bio-Logical tablets are not considered an oxidizer underUnited States Department of Transportation or International Marine Standards. This allows for quick and economical shipmentof product direct to your customers anywhere in the world. Bio-Logical disinfecting tablets are ideal for use with potable watersystems, cisterns, individual home aerobic treatment systems, commercial wastewater treatment systems, sand filters andMarine Sanitation Devices. Bio-Logical tablets are available in 6-tablet bags and 5 lb., 35 lb. and 90 lb. resealable pails.
BIO-GEM® ORGANIC DIGESTERA blend of bacteria, enzymes and natural growth accelerators, Bio-Gem organic digester effectively digests grease, fats andoils in wastewater treatment systems, lift stations, septic tanks, sand filters, drain lines and commercial grease traps. Whenused as directed, Bio-Gem liquid will quickly and effectively convert common grease, fats and oils into carbon dioxide andwater. This organic digestion process is much more effective and reliable than compounds that merely emulsify the grease,fats and oils, sending the problem to downstream treatment processes. Regular use of Bio-Gem liquid will reduce odors,stabilize effluent quality, reduce system maintenance and minimize tank pump-out frequency. Packaged in one or five galloncontainers and 55 gallon drums, Bio-Gem organic digester is environmentally safe and works in aerobic or anaerobic conditions.
Page:
1/5
MEMO
To:
Joe DarbyCopies:
David Liles
From:
Todd Thornton
Date: ARCADIS Project No.:
February 15, 2010 TF000922.0048.00001
Subject:
Raytheon Permanganate-Sulfite Lab Study Results
Background
This lab project was intended to test the theoretical molar relationship in the oxidation-reduction (redox) reaction between permanganate and sulfite. The theoretical redox reaction is shown below.
2MnO4- + 3SO3
2- → 2MnO2 + 3SO42- + 2OH-
The spectator cations are not shown in the equation since they have no influence on the redox reaction. From the balanced redox reaction above, the molar relationship between permanganate and sulfite is 2:3.
In addition to validating the molar relationship between sulfite and permanganate, a series of non-quantitative additions of sulfite was tested to examine the residual permanganate concentrations. Theoretically, the purple color imparted by the permanganate in solution will lighten and eventually turn clear upon sufficient addition of sulfite to reduce the Mn(VII). Insufficient additions of sulfite should reduce the permanganate concentration and thereby only lighten the color of the solution. The change in concentration can be measured using visible spectroscopy and Beer’s law which related absorbance of visible light to the concentration of the analyte (A = εBC, where A = absorbance, ε = molar absorbtivity, B = cell path length, C = concentration).
ARCADIS G&M of North Carolina, Inc.
4915 Prospectus Drive
Suite F
Durham
North Carolina 27713
Tel 919.544.4535
Fax 919.544.5690
ARCADIS, Inc.
Page:
2/5
Experimental
A stock 1000 mg/L sodium permanganate solution was prepared by diluting 2.5 g 40% sodium permanganate solution to 1000 mL using deionized water. The concentration of the stock solution was verified using the NaMnO4 standardization in method 4500-KMnO4 from Standard Methods for the Examination of Water and Wastewater. Using the stock solution, five solutions of varying concentration were created by dilution with deionized water. These solutions were then analyzed by visible spectroscopy to create a calibration curve for future permanganate measurements.
A 100 mL sample of the stock permanganate solution was taken and to it 104 mg of received sodium metabisulfite was added directly. After mixing, there was no visible change in the color of the permanganate solution even though sufficient sulfite (SO3
2-) ions had been added to completely react with the permanganate ions in solution. A second attempt was made, this time adding the 104 mg of sodium metabisulfite to 50 mL deionized water to ensure that the sodium metabisulfite completely dissolved. After swirling, no visible crystals were observed in the water. The solution was added to a fresh 100 mL sample of the stock permanganate solution and swirled. Again, there was no visible change in color.
At this point the experiment was repeated once more, this time using reagent grade sodium sulfite (Na2SO3) that was available in the lab. A 50 mL sample of the stock permanganate solution was combined with 76 mg of sodium sulfite which had been dissolved in 20 mL of deionized water. Immediately the solution changed color from purple to brown. Due to the brown color, the solution could not be analyzed by spectroscopy for residual permanganate. Approximately 1 mL of 20% sulfuric acid was added to the solution to precipitate the Mn. This resulted in a “soft” brown solid falling out of solution leaving a clear supernatant.
The original experiment was then conducted using the reagent grade sodium sulfite. 50 mL aliquots of the stock permanganate solution were taken and varying amounts of sodium sulfite were added to each one by dissolving the sulfite salt into 1-2 mL of deionized water. Once mixed, 3 drops of concentrated sulfuric acid was added to the solution and mixed. A 5-10 mL sample of the supernatant was collected and analyzed in the spectrophotometer for permanganate.
Data and Results
The prepared stock permanganate solution was titrated with sodium oxalate per standard water and wastewater method 4500. The titration was performed three times with a resulting average concentration of 1029 mg/L.
Page:
3/5
A series of five dilutions were prepared to generate a calibration curve for the spectrophotometer. This data is shown in Table 1.
Table 1 Calibration Data
Calibration Point
MnO4used(mL)
MnO4Concentration
(mg/mL)
%T A
C1 0.1 0.0021 93 0.03C2 0.5 0.010 67 0.17C3 1.0 0.021 46 0.34C4 1.5 0.031 32 0.49C5 2.0 0.041 23 0.64
Absorbance is calculated from the %T reading through the formula A = -log10(%T/100). The plot of the absorbance vs. concentration curve is shown in Figure 1.
Figure 1 Calibration Curve
Page:
4/5
Once permanganate samples were reacted with selected molar quantities of sodium sulfite and acidified to precipitate the Mn, samples of supernatant were collected and analyzed in the spectrophotometer. The concentration of the residual permanganate was calculated from the calibration curve. This data is presented in Table 2.
Table 2 Permanganate-Sulfite Reaction Data
Molar % required
SO3
Moles SO3
added
Na2SO3needed
(mg)
Na2SO3added(mg)
%T D.F APermanganate Concentration
(mg/mL)% MnO4 reacted
100 3 68.5 69 100 1 0.00 -0.001 1.0066 2 45.7 47 3 1 1.52 0.098 0.9050 1.5 34.3 35 18 10 0.74 0.474 0.5325 0.75 17.1 16 9.5 10 1.02 0.653 0.360 0 0 0 68 100 0.17 1.018 0.00
D.F. = dilution factorA = absorbance
As a control, the stock permanganate solution was analyzed (shown as the 0 required SO3). The measured concentration (1018 mg/L) is consistent with the calculated concentration from titration (1029 mg/L). This solution was acidified with sulfuric acid just as the samples had been and re-analyzed to ensure there were no effects on the permanganate concentration by the acid. The acidified permanganate solution resulted in the same measured %T, so the acid was verified to have no effect.
Conclusion
The percent permanganate reacted correlates very well with the molar percent sulfite added. The exception noted in the 66 molar percent sulfite addition is most likely due to approaching the end of the calibration curve. From the data it is clear that the molar relationship of permanganate and sulfite in this redox reaction is 2:3, which corresponds to a mass relationship of 1.33 Na2SO3/NaMnO4. Additionally, when less than the molar requirement for sulfite is added, residual permanganate will remain in solution.
As this redox reaction occurs and permanganate is removed from the solution, manganese dioxide (MnO2) is generated. From the balanced redox equation it is apparent that for each mole of NaMnO4 that reacts with Na2SO3 there will be one mole of MnO2 produced. On a mass basis, 0.6 units MnO2 is created for every 1 unit NaMnO4 reacted. Examples of expected MnO2 concentrations at various permanganate levels are shown in Table 3.
Page:
5/5
Table 3 Expected MnO2 Concentrations at Various Initial MnO4 Levels
Flow rate (GPM)
NaMnO4concentration
(mg/L)NaMnO4(lbs/day)
Na2SO3 demand (lbs/day)
MnO2produced (lbs/day)
MnO2concentration
(mg/L)
8 1 0.096 0.128 0.0576 0.68 10 0.961 1.28 0.576 68 100 9.61 12.8 5.76 608 500 48.0 63.9 28.8 3008 1000 96.1 127.8 57.6 600
Tab 10
Modified ISR System – AOP Treatment System Influent Equalization and Advanced Oxidation Process
Page 1 of 1
Calc prepared by: M. SeppanenCalc checked by: J. DarbyDate: 01/28/2010
Considerations:
Useable tank volume = 18,000 gal
Process flow rate = 60 gpm AOP Pre-Treatment System Effluent
Total retention time = 300 min
Operation = 50 % Full
Design retention time = 150 min
Additional requirements = 6,190 gal Backwash Tank
Calculate Required Tank Volume:
Retention time volume = Flow rate x Design retention time
9,000 gal
Minimum volume = Retention time volume + Additional requirements
15,190 gal
Tank Selection:
Rectangular Tank:
Length = 37.5 feet
Width = 8.5 feet
Height = 11 feet
Volume = 18,000 gal
Available Tank Volume = 18,000 gal
Required Tank Volume = 15,190 gal
Volume Available > Volume Required therefore design is acceptable
INFLUENT EQUALIZATION TANK (T-1300) SIZINGModified ISR System
Raytheon CompanySt. Petersburg, Florida
AOP Treatment System
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #10\(1) Tab #10_T-1300 Sizing.xlsx ARCADIS
To the best of our knowledge the technical data contained herein are true and accurate at the date of issuance and are subject to change without prior notice. No guarantee of accuracy is given or implied because variations can and do exist. NO WARRANTY OR GUARANTEE OF ANY KIND IS MADE BY BAKERCORP, EITHER EXPRESSED OR IMPLIED.
3020 OLD RANCH PARKWAY • SUITE 220 • SEAL BEACH, CA • 562-430-6262
Technical Information Manual
2.2.15
PRODUCT DATA SHEET February, 2008
EZ CLEAN FIXED AXLE SAFETY VAPOR TANK
GENERAL INFORMATION Vapor tight steel tank with two sealed top access hatches and pressure/vacuum relief valve. Smooth interior walls for easy cleaning. WEIGHTS AND MEASURES
» Capacity: ....... 480 BBL (20,160 gal.)
» Height: ....... 11’-2” (grade to roof deck) 14’-8” (grade to top of upright guardrails)
» Width : ....... 8’-6” (between side runners) » Length: ....... 39’-9” (front nose to outside of rear stairway) 37’-6” (tank only)
» Weight:
....... 24,480 lbs.
STRUCTURAL DESIGN
» Floor: ....... ¼”thick ASTM A36 carbon steel (V-bottom)
» Sides/Ends: ....... ¼” thick ASTM A36 carbon steel
» Roof Deck: ....... ¼” thick ASTM A36 carbon steel
» Wall Frame: ....... 3/16”x3”x5” ASTM A36 formed channel
» Roof Frame: ....... 3/16”x3”x5” ASTM A36 formed channel
» Skid Rails: ....... C8x11.5 structural channel
FEATURES
» Valves: ....... 1-Front &1-Rear: 6”- wafer butterfly valve. Cast iron body, Buna-N seat & seals, 316 SS stem, Nylon 11 coated ductile iron disk w/ plug and chain.
» Relief Valve: ....... 16 oz./in2 pressure setting, 0.4 oz./in2 vacuum setting; Buna-N seal
» Roof Deck Connections:
....... Vapor Recovery: 4”-150# flange (blinded) Gauging Port: 4” flange (blinded) with 2” threaded plugged port in blind flange.
» Side Manways: ....... One or two (depending on make of tank) on curb side of tank.
FEATURES – cont.
» Front Piping Connections:
....... Bottom Drain: 6”-150# flanged nozzle and butterfly valve Inlet/Outlet: 2 - 4”-150# raised face flange with blind flange (chained)
» Rear Piping Connections:
....... Bottom Drain: 6”-150# flanged nozzle and butterfly valve Inlet/Outlet: 2 - 4”-150# raised face flange with blind flange (chained)
» Interior Access: ....... 2-50” long x 32” wide hinged vapor-proof marine-style hatches with neoprene gaskets and removable fall protection grid.
» Hatch and Manway Seals:
....... Neoprene gasket
» Roof Access Stairway:
....... Rear mounted – lower section folds up for transport and down for use. Stairway includes handrails.
» Guardrails: ....... Top deck, fold-down, 1¼” x 1¼” square tubing.
» Internal Ladder: ....... One; mounted below front-end interior access hatch on roof deck.
» Level Indication: ....... Ball style with 2-8” 304 SS floats with pointer-indicator on front endwall. Floor supports hold floats ½” off floor. [One 2” plugged connection for optional electronic gauge on top deck.]
» Axle: ....... 77½ track straight, non steer, 22,500# capacity.
» Suspension: ....... Silent Drive, 3 air-bags with manual release.
SURFACE DETAILS
» Exterior Coating: ....... High Gloss Polyurethane
» Interior Coating: ....... None
TESTS/CERTIFICATIONS
» Tests Performed: .......
Major repairs – hydrotest Scheduled- Level I, II and III inspections, including NESHAP testing
VAPOR PHASE GAC VESSEL DESIGN CALCULATIONSModified ISR System
AOP Treatment System
Raytheon CompanySt. Petersburg, Florida
Page 1 of 2
M. Seppanen
J. Darby
1/28/2010
Assume:
No active aeration within tank T-1300
The only airflow is from tank venting during filling periods
Filling period is the difference between the high and low set points in the EQ tank
During filling period the system flow rate will be equal to the AOP pre-treatment system effluent rate
The air discharge rate has been estimated to be 60 gpm on a daily basis
The air in the tank will be in equilibrium with the influent groundwater concentrations
System Flow Rate = 60 gpm8.0 CFM
0.227 m3/min
ModelMaximum
Flow (CFM)
Amount of Carbon
(lbs)
Design Pressure
(psi)
G-1S 100 200 10G-2S 300 170 10G-3S 500 140 10
Source: Carbtrol Corporation
VPGAC Selection:G-1S 55 gallon drum
Maximum flow = 100 CFMRequired flow = 8.0 CFMAmount of Carbon 200 lbs
Convert air concentrations from ppmv to µg/m3:
Convert air concentrations from ppmv to µg/m3:
Conc 2 =
Where: Conc 1 = Air concentration in parts per million by volume (ppmv)
Conc 2 = Air concentration in (µg/m3)
MW = Molecular weight of compound (g/mol)
Temp = Air temperature in degrees Kelvin (298.15)
R = Universal gas constant (0.08205 atm*L/mol*K)
Calc prepared by:
Calc checked by:
Date:
Calculate size of VPGAC unit to treat off-gasses from Influent Tank T-1300:
VPGAC vessel design requirements:
VPGAC Vessel Specifications:
Estimate VPGAC Usage
RTemp
MWConc
*
*1000*1
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #10\(3) Tab #10_VPGAC Calcs.xlsx ARCADIS
VAPOR PHASE GAC VESSEL DESIGN CALCULATIONSModified ISR System
AOP Treatment System
Raytheon CompanySt. Petersburg, Florida
Page 2 of 2
Calculate VOC Flow Rate:
Mass flow rate (lb/day) =
Conversions: 2.2 kg = 1 lb
1,440 min = 1 day
1 kg = 1,000,000 µg
VOC Flow Rate (lbs/day)
0.00
0.00
0.01
0.00
0.00
0.00
0.01
0.00
0.00
0.04
Total potential lbs of VOCs = 0.1 lbs/day
Average VPGAC Loading Rate = 0.1 lb/lb
Potential VPGAC Use Rate = 1 lbs/day
Assume:
Amount of VPGAC in G-1S = 200 lbs
Potential Vapor-Phase GAC Use = 1 lbs/day
Estimated Time for Carbon Breakthrough = 285 days
Trichloethene
Xylenes 0.000
1,1-Dichloroethane 0.000 0.000 0
1,1-Dicholoethene 0.001 0.003 12
Equilibrium Air Concentration
(ppmv)
Equilibrium Air Concentration
(µg/m3)
Chloroethane 0.000 0.000 0
Vinyl Chloride 0.000 0.002 5
CompoundInfluent Concentration
(mg/L)
2
1,1,1-Trichloroethane 0.000 0.001 3
0.004 0.003 17
cis-1,2-Dichloroethene 0.001 0.001 2
Toluene 0.001 0.000
Calculate Estimated Time for Carbon Breakthrough:
0.000 0
1,4-Dioxane 15.8 0.016 58
440,1**)000,000,1
1(*2.2*2 airQConc
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #10\(3) Tab #10_VPGAC Calcs.xlsx ARCADIS
VAPOR PHASE GAC VESSEL DESIGN CALCULATIONSModified ISR System
AOP Treatment System
Raytheon CompanySt. Petersburg, Florida
Page 1 of 2
M. Seppanen
J. Darby
1/28/2010
Assume:
No active aeration within tank T-1500
The only airflow is from tank venting during filling periods
Filling period is the difference between the high and low set points in the EQ tank
During filling period the recovery well network will pump approx 2 gpm more than the HiPOx unit
The air discharge rate has been estimated to be 2 gpm on a daily basis
The air in the tank will be in equilibrium with the influent groundwater concentrations
System Flow Rate = 2 gpm0.3 CFM
0.008 m3/min
ModelMaximum
Flow (CFM)
Amount of Carbon
(lbs)
Design Pressure
(psi)
G-1S 100 200 10G-2S 300 170 10G-3S 500 140 10
Source: Carbtrol Corporation
VPGAC Selection:G-1S 55 gallon drum
Maximum flow = 100 CFMRequired flow = 0.3 CFMAmount of Carbon 200 lbs
Convert air concentrations from ppmv to µg/m3:
Convert air concentrations from ppmv to µg/m3:
Conc 2 =
Where: Conc 1 = Air concentration in parts per million by volume (ppmv)
Conc 2 = Air concentration in (µg/m3)
MW = Molecular weight of compound (g/mol)
Temp = Air temperature in degrees Kelvin (298.15)
R = Universal gas constant (0.08205 atm*L/mol*K)
VPGAC Vessel Specifications:
Estimate VPGAC Usage
VPGAC vessel design requirements:
Calc prepared by:
Calc checked by:
Date:
Calculate size of VPGAC unit to treat off-gasses from Influent Tank T-1500:
RTemp
MWConc
*
*1000*1
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #10\(4) Tab #10_VPGAC Calcs.xlsx ARCADIS
VAPOR PHASE GAC VESSEL DESIGN CALCULATIONSModified ISR System
AOP Treatment System
Raytheon CompanySt. Petersburg, Florida
Page 2 of 2
Calculate VOC Flow Rate:
Mass flow rate (lb/day) =
Conversions: 2.2 kg = 1 lb
1,440 min = 1 day
1 kg = 1,000,000 µg
VOC Flow Rate (lbs/day)
0.00
0.00
0.00
0.02
0.00
0.00
0.23
0.00
0.00
0.00
Total potential lbs of VOCs = 0.3 lbs/day
Average VPGAC Loading Rate = 0.1 lb/lb
Potential VPGAC Use Rate = 3 lbs/day
Assume:
Amount of VPGAC in G-1S = 200 lbs
Potential Vapor-Phase GAC Use = 3 lbs/day
Estimated Time for Carbon Breakthrough = 78 days
Calculate Estimated Time for Carbon Breakthrough:
Xylenes 0.000 0.00 0
1,4-Dioxane 0.425 0.00 1
Trichloethene 2.300 2 9,614
Vinyl Chloride 0.000 0.00 0
Toluene 0.001 0.00 3
1,1,1-Trichloroethane 0.001 0.00 6
1,1-Dicholoethene 0.061 0.02 63
cis-1,2-Dichloroethene 0.480 0.22 884
Chloroethane 0.000 0.00 0
1,1-Dichloroethane 0.038 0.02 97
CompoundInfluent Concentration
(mg/L)
Equilibrium Air Concentration
(ppmv)
Equilibrium Air Concentration
(µg/m3)
440,1**)000,000,1
1(*2.2*2 airQConc
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #10\(4) Tab #10_VPGAC Calcs.xlsx ARCADIS
Tab 11
Modified ISR System – AOP Treatment System Filtration and Solids Settling
Page 1 of 3
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate: 1/28/2010
Total dynamic head calculation = head loss due to elevation changehead loss due to pipe frictionhead loss across misc. process componentsrequired discharge head
Calculate pipe size:
Where: v = Velocity (ft/sec)Q = Flow rate (gpm)r = Pipe radius (in)
Flow Rate Pipe Size Pipe ODWall
Thickness Pipe ID Area velocity(gpm) (in) (in) (in) (in) (ft2) (ft/sec)
92 3 3.500 0.216 3.068 0.051 3.8892 4 4.500 0.237 4.026 0.088 2.2592 6 6.625 0.280 6.065 0.201 0.99
*Pipe dimensions noted for Schedule 40 galvanized steel piping.Note: Design for velocity between 3 and 5 feet/sec to maintain sufficient scour velocity.
Calculate head loss (he) due to elevation change:
assume: Height from pump to discharge point = 15 feetHead loss, he = 15 feet
Calculate head loss due to pipe friction losses:
Step 1. There are multiple pipe sections with flow and pipe diameters shown below
Pipe Section 1 Nominal pipe diameter 1 = 3 inch
Flow (v1) = 92 gpm
Pipe Section 2 Nominal pipe diameter 2 = 4 inch
Flow (v2) = 92 gpm
Pipe Section 3 Nominal pipe diameter 3 = 6 inch
Flow (v3) = 92 gpm
Step 2. Calculate the friction factor for each pipe section using the Hazen-Williams formula
Hazen-Williams Formula f = .2083 * (100/C)1.852 * (q1.852) / (D4.8655)
f = Friction in head in feet of water per 100 ft of pipeC = Constant for inside roughness
(140 for new carbon steel pipe)q = Flow rate (gal/min)D = Inside diameter of pipe (inches)
Nominal Diam (in)
ID (in)
ID w/ deposition (in)
1 1.003 0.8781.5 1.452 1.3272 1.826 1.7013 2.691 2.5664 3.460 3.3356 5.460 5.335
NOTE: a 0.0625 inch (1/16 inch) deposition on interior pipe wall is included in diameter for calculation - 1.003 - (2 x 0.0625) = 0.878 inch diameter
Friction factor for Pipe Section 1C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 92 gal/minD1 = Inner pipe diameter (inches) 2.566 inches (see NOTE)
Pipe Section 1 friction factor 4.9 ft water / 100 feet of pipe
FILTER FEED PUMP (P-1100A/B) DESIGN CALCULATIONSModified ISR System - AOP Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
sec60
min1*
)*( 2r
Qv
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\(1) Tab #11_P-1100A&B TDH.xlsx ARCADIS
Page 2 of 3
FILTER FEED PUMP (P-1100A/B) DESIGN CALCULATIONSModified ISR System - AOP Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Friction factor for Pipe Section 2C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 92 gal/minD2 = Inner pipe diameter (inches) 3.335 inches (see NOTE)
Pipe Section 2 friction factor 1.4 ft water / 100 feet of pipe
Friction factor for Pipe Section 3C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 92 gal/minD3 = Inner pipe diameter (inches) 5.335 inches (see NOTE)
Pipe Section 3 friction factor 0.1 ft water / 100 feet of pipe
Step 3. Calculate the equivalent length of pipe for each section
Nominal Fitting size 1 in 1.5 in 2 in 3 in 4 in 6 in
90˚ Elbows 2.7 3.4 3.6 4.0 4.6 10.4Standard Tee (thru flow) 3.2 5.6 7.7 12.0 17.0 38.3Standard Tee (branch flow) 6.6 9.9 12.0 17.0 21.0 47.3Ball valve (full open) 1.6 2.3 2.9 4.3 5.5 12.3Check Valve - Spring and Swing 11.0 15.0 19.0 27.0 38.0 85.5Union 0.3 0.4 0.5 0.5 0.7 1.5Reducer (2/1) 1.0 1.5 1.5 3.0 4.0 9.0Expansion (1/2) 1.5 2.5 3.0 4.0 6.0 13.5
Equivalent lengths from reference: Civil Engineering Reference Manual, 9th Ed, Professional Publications, Inc., 2003; and"Flow of Fluids", Crane Technical Paper No. 410, 1988.
Pipe Section 1 - 3"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 10 10Standard Tee (thru flow) 1 12 12.0Check Valve - Swing 1 27 27Ball valve (full open) 1 4.3 4.390˚ Elbows 3 4.0 12.0Expansion (3"x4") 1 4.0 4.0
Equivalent Length: 70
Pipe Section 2 - 4"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 350 350Standard Tee (thru flow) 6 17 102Standard Tee (branch flow) 4 21 84Union 8 0.7 5.290˚ Elbows 20 4.6 92Check Valve - Swing 4 38 152Ball valve (full open) 10 5.5 55
Equivalent Length: 840
Pipe Section 3 - 6"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 2,500 2,500Union 8 1.5 11.790˚ Elbows 4 10.35 41.4Check Valve - Swing 1 85.5 85.5
Equivalent Length: 2,639
Step 4. Determine pipe friction for each pipe section.
Total pipe friction = Total equivalent length x Friction factor
Total Pipe Friction - Pipe Section 1Total equivalent length = 70 feet
Friction factor = 4.9 feet water / 100 feet of pipe
Total Pipe Friction = 3.5 feet
Total Pipe Friction - Pipe Section 2Total equivalent length = 840 feet
Friction factor = 1.4 feet water / 100 feet of pipe
Total Pipe Friction = 11.6 feet
Equivalent Length
Equivalent Length per Fitting (ft)
Equivalent Length
Equivalent Length
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\(1) Tab #11_P-1100A&B TDH.xlsx ARCADIS
Page 3 of 3
FILTER FEED PUMP (P-1100A/B) DESIGN CALCULATIONSModified ISR System - AOP Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Total Pipe Friction - Pipe Section 3Total equivalent length = 2,639 feet
Friction factor = 0.1 feet water / 100 feet of pipe
Total Pipe Friction = 3.7 feet
Step 5. Determine total pipe friction (all sections)
Total Pipe Friction - Pipe Section 1+2+3 = 18.8
Calculate Total Dynamic Head:
Head Loss Due to Change in Elevation 15 ft
Head loss due to pipe friction 19 ft
Head loss Across Misc. Process Components Catalytic Media Filter 35 ft 1 psi = 2.31 ft
Multi-Media Filter 20 ftLPGAC-1 23 ftLPGAC-2 12 ft
Flow Meter (plant) 10 ftFlow Meter (discharge) 10 ft
Required Discharge Pressure (0 psi) 0 ft
Total Dynamic Head Required - Calculated 144 ft
Design Safety Factor 25%
Total Dynamic Head Required - Design 180 feet
Pump Design Requirements:Flow 92 gpm
Total Dynamic Head 180 feet
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\(1) Tab #11_P-1100A&B TDH.xlsx ARCADIS
Model: 3196 Size: 2X3-8 Group: MTi 60Hz RPM: 3560 Stages: 1
Job/Inq.No. : RAYTHEONPurchaser : ARCADISEnd User : ARCADIS Issued by : Rev. : 0Item/Equip.No. : P-1100AB Quotation No. : RAPA AOP Date : 02/04/2010Service :Order No. :
Operating Conditions Pump PerformanceLiquid: Water Published Efficiency: 45.0 % Suction Specific Speed: 8,693 gpm(US) ftTemp.: 82.0 deg F Rated Pump Efficiency: 45.0 % Min. Hydraulic Flow: 45.7 gpmS.G./Visc.: 1.000/1.000 cp Rated Total Power: 9.4 hp Min. Thermal Flow: N/AFlow: 92.0 gpm Non-Overloading Power: 13.8 hpTDH: 180.0 ft Imp. Dia. First 1 Stg(s): 6.3750 inNPSHa: NPSHr: 5.0 ftSolid size: Shut off Head: 186.6 ft% Susp. Solids(by wtg):
Vapor Press:
Max. Solids Size: 0.5000 inNotes: 1. The Mechanical seal increased drag effect on power and efficiency is not included, unless the correction is shown in the
appropriate field above. 2. Magnetic drive eddy current on power and efficiency is not included. 3. Elevated temperatureeffects on performance are not included. 4. Non Overloading power does not reflect v-belt/gear losses.
Page 1 of 3
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate:
Total dynamic head calculation = head loss due to elevation changehead loss due to pipe frictionhead loss across misc. process componentsrequired discharge head
Calculate pipe size:
Where: v = Velocity (ft/sec)Q = Flow rate (gpm)r = Pipe radius (in)
Flow Rate Pipe Size Pipe ODWall
Thickness Pipe ID Area velocity(gpm) (in) (in) (in) (in) (ft2) (ft/sec)
106 3 3.500 0.216 3.068 0.051 4.47106 4 4.500 0.237 4.026 0.088 2.60106 6 6.625 0.280 6.065 0.201 1.14
*Pipe dimensions noted for Schedule 40 galvanized steel pipingNote: Design for velocity between 3 and 5 feet/sec to maintain sufficient scour velocity
Calculate head loss (he) due to elevation change:
assume: Height from pump to discharge point = 15 feetHead loss, he = 15 feet
Calculate head loss due to pipe friction losses:
Step 1. There are multiple pipe sections with flow and pipe diameters shown below
Pipe Section 1 Nominal pipe diameter 1 = 3 inch
Flow (v1) = 106 gpm
Pipe Section 2 Nominal pipe diameter 2 = 4 inch
Flow (v2) = 106 gpm
Step 2. Calculate the friction factor for each pipe section using the Hazen-Williams formula
Hazen-Williams Formula f = .2083 * (100/C)1.852 * (q1.852) / (D4.8655)
f = Friction in head in feet of water per 100 ft of pipeC = Constant for inside roughness
(140 for new carbon steel pipe)q = Flow rate (gal/min)D = Inside diameter of pipe (inches)
Nominal Diam (in)
ID (in)
ID w/ deposition (in)
1 1.003 0.8781.5 1.452 1.3272 1.826 1.7013 2.691 2.5664 3.460 3.3356 5.460 5.335
NOTE: a 0.0625 inch (1/16 inch) deposition on interior pipe wall is included indiameter for calculation - 1.003 - (2 x 0.0625) = 0.878 inch diameter
Friction factor for Pipe Section 1C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 106 gal/minD1 = Inner pipe diameter (inches) 2.566 inches (see NOTE)
Pipe Section 1 friction factor 6.4 ft water / 100 feet of pipe
BACKWASH PUMP (P-1200) DESIGN CALCULATIONSModified ISR System - AOP Treatment System
St. Petersburg, Florida
Total Dynamic Head Calculation
Raytheon Company
sec60
min1*
)*( 2r
Qv
G:\ENV\TF\901‐1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\
(3) Tab #11_P‐1200 TDH.xlsx ARCADIS
Page 2 of 3
BACKWASH PUMP (P-1200) DESIGN CALCULATIONSModified ISR System - AOP Treatment System
St. Petersburg, Florida
Total Dynamic Head Calculation
Raytheon Company
Friction factor for Pipe Section 2C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 106 gal/minD2 = Inner pipe diameter (inches) 3.335 inches (see NOTE)
Pipe Section 2 friction factor 1.8 ft water / 100 feet of pipe
Step 3. Calculate the equivalent length of pipe for each section
Nominal Fitting size 1 in 1.5 in 2 in 3 in 4 in 6 in
90˚ Elbows 2.7 3.4 3.6 4.0 4.6 10.4Standard Tee (thru flow) 3.2 5.6 7.7 12.0 17.0 38.3Standard Tee (branch flow) 6.6 9.9 12.0 17.0 21.0 47.3Ball valve (full open) 1.6 2.3 2.9 4.3 5.5 12.3Check Valve - Spring and Swing 11.0 15.0 19.0 27.0 38.0 85.5Union 0.3 0.4 0.5 0.5 0.7 1.5Reducer (2/1) 1.0 1.5 1.5 3.0 4.0 9.0Expansion (1/2) 1.5 2.5 3.0 4.0 6.0 13.5
Equivalent lengths from reference: Civil Engineering Reference Manual, 9th Ed, Professional Publications, Inc., 2003; an"Flow of Fluids", Crane Technical Paper No. 410, 1988
Pipe Section 1 - 3"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 10 10Standard Tee (thru flow) 1 12 12Check Valve - Swing 1 27 27Ball valve (full open) 1 4.3 4.390˚ Elbows 1 4.0 4.0Expansion (3"x4") 1 4.0 4.0
Equivalent Length: 62
Pipe Section 2 - 4"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 150 150Standard Tee (thru flow) 6 17 102Standard Tee (branch flow) 3 21 63Union 3 0.7 2.090˚ Elbows 6 4.6 27.6Check Valve - Swing 1 38 38Ball valve (full open) 6 5.5 33
Equivalent Length: 416
Step 4. Determine pipe friction for each pipe section.
Total pipe friction = Total equivalent length x Friction facto
Total Pipe Friction - Pipe Section 1Total equivalent length = 62 feet
Friction factor = 6.4 feet water / 100 feet of pipe
Total Pipe Friction = 4.0 feet
Total Pipe Friction - Pipe Section 2Total equivalent length = 416 feet
Friction factor = 1.8 feet water / 100 feet of pipe
Total Pipe Friction = 7.5 feet
Step 5. Determine total pipe friction (all sections)
Total Pipe Friction - Pipe Section 1+2 = 11.4
Calculate Total Dynamic Head:
Head Loss Due to Change in Elevation 15 ft
Head loss due to pipe friction 11 ft
Equivalent Length per Fitting (ft)
Equivalent Length
Equivalent Length
G:\ENV\TF\901‐1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\
(3) Tab #11_P‐1200 TDH.xlsx ARCADIS
Page 3 of 3
BACKWASH PUMP (P-1200) DESIGN CALCULATIONSModified ISR System - AOP Treatment System
St. Petersburg, Florida
Total Dynamic Head Calculation
Raytheon Company
Head loss Across Misc. Process Components Catalytic Media Filter 45 ft 1 psi = 2.31 ft
Static Mixer 20 ftFlow Meter 12 ft
Required Discharge Pressure (0 psi) 0 ft
Total Dynamic Head Required - Calculated 103 ft
Design Safety Factor 25%
Total Dynamic Head Required - Design 129 feet
Pump Design Requirements:Flow 106 gpm
Total Dynamic Head 129 feet
G:\ENV\TF\901‐1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\
(3) Tab #11_P‐1200 TDH.xlsx ARCADIS
Model: 3196 Size: 2X3-8 Group: 3196MTI 60Hz RPM: 3000 Stages: 1
Job/Inq.No. : RAYTHEONPurchaser : ARCADISEnd User : ARCADIS Issued by : Rev. : 0Item/Equip.No. : P-1200 Quotation No. : RAPA AOP Date : 02/04/2010Service :Order No. :
Operating Conditions Pump PerformanceLiquid: Water Published Efficiency: 48.0 % Suction Specific Speed: 8,693 gpm(US) ftTemp.: 82.0 deg F Rated Pump Efficiency: 53.0 % Min. Hydraulic Flow: 39.2 gpmS.G./Visc.: 1.000/1.000 cp Rated Total Power: 6.6 hp Min. Thermal Flow: N/AFlow: 106.0 gpm Non-Overloading Power: 8.8 hpTDH: 129.0 ft Imp. Dia. First 1 Stg(s): 6.5000 inNPSHa: NPSHr: 5.4 ftSolid size: Shut off Head: 138.5 ft% Susp. Solids(by wtg):
Vapor Press:
Max. Solids Size: 0.5000 inNotes: 1. The Mechanical seal increased drag effect on power and efficiency is not included, unless the correction is shown in the
appropriate field above. 2. Magnetic drive eddy current on power and efficiency is not included. 3. Elevated temperatureeffects on performance are not included. 4. Non Overloading power does not reflect v-belt/gear losses.
CATALYTIC MEDIA FILTER DESIGN CALCULATIONSModified ISR System
AOP Treatment System
Raytheon CompanySt. Petersburg, Florida
Page 1 of 1
Calc prepared by: M. Seppanen
Calc checked by: J. Perella
Date: 1/28/2010
Assume:
Filter sizing is based on hydraulic loading
3 - 5 gpm/ft2
Process Flow Rate = 92 gpm
Design Loading Rate 4.0 gpm/ft2
Filtration Area Required = 23.0 ft2
Number of online vessels = 3
Filtration area per vessel = 7.7 ft2
Calculated diameter of vessel = 3.1 ft
Selected vessel diameter = 4.0 ft
Filtration Area per vessel = 12.6 ft2
Actual Loading Rate = 2.4 gpm/ft2
Bed Depth and Media Contact Time:
Minimum bed depth = 36 inches
Filtration area per vessel = 12.6 ft2
Flow rate per vessel = 30.7 gpm
4.11 ft3/min
Media contact time = 9.2 min
With Air Scour:
Step 1: Air Loading Rate = 3 SCFM/ft2
Water Loading Rate = 5 gpm/ft2
Time per vessel = 10 min
Step 2: Water Loading Rate = 15 gpm/ft2
Time per vessel = 5 min
Backwash Flow Rates:
Step 1: Air = 38 SCFM
Water = 63 gpm
Step 2: Water = 188 gpm
Backwash Volumes:
Volume of Backwash Required per Vessel= 1,570 gpm
Total Volume of Backwash Required = 4,710 gpm
Calculate size of Catalytic Media Filter units:
Recommended hydraulic loading for media
Calculate diameter of Catalytic Media Filter:
Selected design requirement specifications:
Backwash Requirements
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\(5) Tab #11_LayneOx Calcs.xlsx ARCADIS
Multi-Media Filter Design CalculationsModified ISR System
AOP Treatment System
Raytheon CompanySt. Petersburg, Florida
Page 1 of 1
Calc prepared by: M. Seppanen
Calc checked by: J. Perella
Date: 1/28/2010
Assume:
Filter sizing is based on hydraulic loading
8 - 15 gpm/ft2
Process Flow Rate = 92 gpm
Design Loading Rate 10.0 gpm/ft2
Filtration Area Required = 9.2 ft2
Number of online vessels = 2
Filtration area per vessel = 4.6 ft2
Calculated diameter of vessel = 2.4 ft
Selected vessel diameter = 2.5 ft
Filtration Area per vessel = 4.9 ft2
Actual Loading Rate = 9.4 gpm/ft2
Water Loading Rate = 15 gpm/ft2
Time per vessel = 10 min
Backwash Flow Rates:
Water = 74 gpm
Backwash Volumes:
Volume of Backwash Required per Vessel= 740 gpm
Total Volume of Backwash Required = 1,480 gpm
Backwash Requirements
Selected design requirement specifications:
Recommended hydraulic loading for media
Calculate diameter of Multi-Media Filter:
Calculate size of Multi-Media Filter units:
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\(9) Tab #11_Media Filter Calcs.xlsx ARCADIS
INDUSTRIALPRESSURIZED
WATER MANAGEMENT SYSTEMS, INC. IN-LINE
Yardney high rate automatic backwashing Multi-Media filters are designed for enhanced capacity water filtration. These permanent media automatic backwashing filters will remove organic and/or inorganic suspended solids down to 5-10 microns in size and will entrap greater amounts of suspended solid contaminants than sand media filters. Through the use of automatically controlled backwashing, the filter will operate “on line” for extended periods of time prior to the short backwashing cycle. Automatic filter operation is monitored on both elapsed time as well as pressure differential. When the
controller “calls” for a backwash as a result of pressure differential or elapsed time, the backwashing function utilizes a portion of the clean filtered water produced by the system to clean the media. Single tank systems utilize unfiltered water for backwashing. Optional external backwash water sourcing systems are available for both single and multiple tank systems.
EXCELLENT FOR SUSPENDED SOLIDS REMOVAL DOWN TO 5-10 MICRONSUNITS SHIPPED COMPLETELY ASSEMBLED ON STRUCTURAL SKIDS 3M SCOTCHKOTE 134 FUSION BONDED EPOXY LININGS 60” DEEP SAND MEDIA TANK SHELLS ARE STANDARD AUTOMATIC BACKWASH VALVES IN CAST IRON, STAINLESS TRIM- (AIR OR WATER POWERED) SOLID STATE CONTROLS WITH INTEGRAL ADJUSTABLE PRESSURE DIFFERENTIAL SWITCH. FLANGED OR GROOVED OPTIONS AVAILABLE FOR INLET AND OUTLET CONNECTIONS REMOVEABLE TYPE 304 STAINLESS UNDER-DRAINS IDEAL FOR RAW WATER FILTRATION OR PRE-TREATMENT OF R.O. OR D.I. SYSTEMS AND IN-LINE DISPOSABLE CARTRIDGE OR BAG FILTERS EASY INSTALLATION AND START-UP ASME CODE STAMP AVAILABLE (OPTIONAL) NEMA 4X CONTROLS HOUSING AVAILABLE (OPTIONAL) FILTERED WATER BACKWASH ON MULTIPLE TANK SYSTEMS
Yardney Water Management Systems, Inc. 6666 Box Springs Blvd., Riverside, CA U.S.A.
Phone: (951) 656-67l6 or (800) 854-4788 Fax (951) 656-3867 Website: www.yardneyfilters.com Email: [email protected]
LIT-MM UNITS BROCHURE-002-1206
INDUSTRIAL IN-LINE PRESSURIZED MULTI-MEDIA FILTRATION SYSTEMS
WATER MANAGEMENT SYSTEMS, INC.
ENGINEERING & SIZING DATA FOR SINGLE & MULTIPLE TANK SYSTEMS MULTI-MEDIA FILTRATION SYSTEMS – 60” SIDE SHELL TANKS DESIGNED FOR HIGH QUALITY FILTRATION APPLICATIONS
FOR REMOVAL OF SUSPENDED SOLIDS DOWN TO 5-10 MICRONS IN SIZE
Service Flow rates
Approximate Shipping
Weight Lbs. Approximate Space
Requirement
Model Number
Normal Flow
Range GPM
Peak Flow Rate GPM
Total Filtration
Area (Sq. Ft.)
Dia. X Side Shell
(Inches)
Multi- Media Cu. Ft.
Back-Wash GPM
Inlet/Outlet Size
Back-wash Line Size
StandardMaximum Working Pressure Equip. Media
Approximate Operating
Weight Lbs. Length Width HeightMM-2460-1A 16-47 63 3.15 24 X 60 12.0 47 2" 2" 100 PSI 465 1210 2200 3' 1" 2' 4" 8' 0" MM-2460-2A 32-95 126 6.30 24 X 60 24.0 47 3" 2" 100 PSI 875 2468 4500 4' 5" 2' 4" 8' 6" MM-2460-3A 48-142 189 9.45 24 X 60 36.0 47 3" 2" 100 PSI 1330 3578 6750 6' 9" 2' 4" 8' 6" MM-3060-1A 25-74 98 4.91 30 X 60 20.0 74 3" 3" 100 PSI 680 2116 3650 4' 8" 2' 9" 8' 6" MM-3060-2A 50-147 196 9.82 30 X 60 40.0 74 4" 2" 100 PSI 1140 4205 7050 5' 5" 2' 9" 8' 8" MM-3060-3A 75-221 294 14.73 30 X 60 60.0 74 4" 2" 100 PSI 1740 5846 10,600 8' 3" 2' 9" 8' 8" MM-3660-1A 35-107 142 7.10 36 X 60 28.5 107 3" 3" 100 PSI 840 3022 5150 4' 8" 3' 3" 8? 10"MM-3660-2A 70-213 284 14.20 36 X 60 57.0 107 4" 4" 100 PSI 1485 5617 10,100 6' 5" 3' 3" 9' 3" MM-3660-3A 105-320 426 21.30 36 X 60 85.5 107 4" 4" 100 PSI 2420 8364 15,350 9' 9" 3' 3" 9' 3" MM-4860-1A 63-189 252 12.60 48 X 60 51.5 189 4" 4" 80 PSI 1160 5138 9150 5' 7" 4' 3" 9? 10"MM-4860-2A 126-378 504 25.20 48 X 60 103.0 189 6" 4" 80 PSI 2360 10,101 18,300 8' 5" 4' 3" 10' 2"MM-4860-3A 189-567 756 37.80 48 X 60 154.5 189 6" 4" 80 PSI 3450 15,064 27,300 12' 9" 4' 3" 10' 2"MM-4860-4A 252-756 1008 50.40 48 X 60 206.0 189 8" 4" 80 PSI 5070 20,002 36,850 17' 1" 4' 3" 10' 4"MM-4860-5A 315-945 1260 63.00 48 X 60 257.5 189 10" 4" 80 PSI 6060 25,065 45,850 22? 2” 4' 3" 10' 2"MM-4860-6A 378-1134 1512 75.60 48 X 60 309.0 189 10" 4" 80 PSI 7150 30,028 54,850 26? 6” 4' 3" 10' 2"MM-5460-1A 80-239 318 15.91 54 X 60 65.5 239 4" 4" 80 PSI 1350 6423 11,400 5? 10” 4? 9” 10? 4”MM-5460-2A 160-477 636 31.82 54 X 60 131.0 239 6" 4" 80 PSI 2710 12,746 22,850 9? 4” 4? 9” 10? 8”MM-5460-3A 240-716 954 47.73 54 X 60 196.5 239 6" 4" 80 PSI 4080 17,366 34,250 14? 2” 4? 9” 10? 8”MM-5460-4A 320-955 1272 63.64 54 X 60 262.0 239 8" 4" 80 PSI 5540 25,417 45,750 19? 9” 4? 9” 10? 10”MM-5460-5A 400-1193 1590 79.55 54 X 60 327.5 239 10" 4" 80 PSI 6940 31,740 57,200 24? 7” 4? 9” 10? 8”
MM-5460-6A 480-1432 1908 95.46 54 X 60 393.0 239 10" 4" 80 PSI 8320 38,088 68,650 29? 5” 4? 9” 10? 8”
Single Tank Models I.D. – 1A Multiple Tank Models I.D. – 2A, 3A, 4A, 5A, 6A STANDARD MEDIA SPECIFICATIONS:Gravel Pack: ½” X ¾” crushed rock Garnet: INTERFACE MEDIA Garnet: WORKING MEDIA Anthracite: PRE-FILTER MEDIA
NOTE: For optional media grades, consult factory. NOTE: Media shipping weight includes gravel pack. NOTE: For higher working pressure operation
requirements, consult factory.
Standard Systems Include: Filtered water backwash on multi-tank systemsAll interior surfaces fusion epoxy coated with 3M Scotchkote 134Advanced solid-state automation with elapsed timer and pressure differential controlSkid mounted on structural steel skidLiquid-filled stainless steel pressure gaugesGrooved coupling in/out standard (flanged available – consult factoryAutomatic diaphragm operated non-corrosive brass or cast iron valvesSystems provided with interconnecting pipingRemovable type 304 stainless steel cross-flow underdrain standardASME code stamped available – consult factoryFiltration media is included in the system definition and pricing.
?Excellence In Filtration For A Better World”
Yardney Water Management Systems, Inc. 6666 Box Springs Blvd., Riverside, CA U.S.A.
Phone: (951) 656-67l6 or (800) 854-4788 Fax (951) 656-3867 Website: www.yardneyfilters.com Email: [email protected]
LIT-MM UNITS BROCHURE-002-1206
Page 1 of 1
Calc prepared by: M. SeppanenCalc checked by: J. PerellaDate: 01/28/2010
Considerations:
Useable tank volume = 18,000 gal
21-Days Solids Storage = 1,764 gal 84 gallons per day
Daily Input Volume = 4,710 gal Catalytic Media Backwash
Daily Input Volume = 493 gal Multi-Media Backwash
Additional Requirements = 0 gal
Calculate Required Tank Volume:
Total input volume = Daily Backwash Volume + Additional Requirements
5,203 gal
Minimum required volume = Total input volume + Solids storage
10,407 gal
Tank Selection:
Rectangular Tank:
Length = 37.5 feet
Width = 8.5 feet
Height = 11 feet
Volume = 18,000 gal
Available Tank Volume = 18,000 gal
Required Tank Volume = 10,407 gal
Volume Available > Volume Required therefore design is acceptable
BACKWASH TANK (T-2000) SIZINGModified ISR System
AOP Treatment System
Raytheon CompanySt. Petersburg, Florida
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\(12) Tab #11_T-2000 Sizing.xlsx ARCADIS
To the best of our knowledge the technical data contained herein are true and accurate at the date of issuance and are subject to change without prior notice. No guarantee of accuracy is given or implied because variations can and do exist. NO WARRANTY OR GUARANTEE OF ANY KIND IS MADE BY BAKERCORP, EITHER EXPRESSED OR IMPLIED.
3020 OLD RANCH PARKWAY • SUITE 220 • SEAL BEACH, CA • 562-430-6262
Technical Information Manual
2.2.15
PRODUCT DATA SHEET February, 2008
EZ CLEAN FIXED AXLE SAFETY VAPOR TANK
GENERAL INFORMATION Vapor tight steel tank with two sealed top access hatches and pressure/vacuum relief valve. Smooth interior walls for easy cleaning. WEIGHTS AND MEASURES
» Capacity: ....... 480 BBL (20,160 gal.)
» Height: ....... 11’-2” (grade to roof deck) 14’-8” (grade to top of upright guardrails)
» Width : ....... 8’-6” (between side runners) » Length: ....... 39’-9” (front nose to outside of rear stairway) 37’-6” (tank only)
» Weight:
....... 24,480 lbs.
STRUCTURAL DESIGN
» Floor: ....... ¼”thick ASTM A36 carbon steel (V-bottom)
» Sides/Ends: ....... ¼” thick ASTM A36 carbon steel
» Roof Deck: ....... ¼” thick ASTM A36 carbon steel
» Wall Frame: ....... 3/16”x3”x5” ASTM A36 formed channel
» Roof Frame: ....... 3/16”x3”x5” ASTM A36 formed channel
» Skid Rails: ....... C8x11.5 structural channel
FEATURES
» Valves: ....... 1-Front &1-Rear: 6”- wafer butterfly valve. Cast iron body, Buna-N seat & seals, 316 SS stem, Nylon 11 coated ductile iron disk w/ plug and chain.
» Relief Valve: ....... 16 oz./in2 pressure setting, 0.4 oz./in2 vacuum setting; Buna-N seal
» Roof Deck Connections:
....... Vapor Recovery: 4”-150# flange (blinded) Gauging Port: 4” flange (blinded) with 2” threaded plugged port in blind flange.
» Side Manways: ....... One or two (depending on make of tank) on curb side of tank.
FEATURES – cont.
» Front Piping Connections:
....... Bottom Drain: 6”-150# flanged nozzle and butterfly valve Inlet/Outlet: 2 - 4”-150# raised face flange with blind flange (chained)
» Rear Piping Connections:
....... Bottom Drain: 6”-150# flanged nozzle and butterfly valve Inlet/Outlet: 2 - 4”-150# raised face flange with blind flange (chained)
» Interior Access: ....... 2-50” long x 32” wide hinged vapor-proof marine-style hatches with neoprene gaskets and removable fall protection grid.
» Hatch and Manway Seals:
....... Neoprene gasket
» Roof Access Stairway:
....... Rear mounted – lower section folds up for transport and down for use. Stairway includes handrails.
» Guardrails: ....... Top deck, fold-down, 1¼” x 1¼” square tubing.
» Internal Ladder: ....... One; mounted below front-end interior access hatch on roof deck.
» Level Indication: ....... Ball style with 2-8” 304 SS floats with pointer-indicator on front endwall. Floor supports hold floats ½” off floor. [One 2” plugged connection for optional electronic gauge on top deck.]
» Axle: ....... 77½ track straight, non steer, 22,500# capacity.
» Suspension: ....... Silent Drive, 3 air-bags with manual release.
SURFACE DETAILS
» Exterior Coating: ....... High Gloss Polyurethane
» Interior Coating: ....... None
TESTS/CERTIFICATIONS
» Tests Performed: .......
Major repairs – hydrotest Scheduled- Level I, II and III inspections, including NESHAP testing
Page 1 of 3
DECANT PUMP (P-1300) DESIGN CALCULATIONS
Total dynamic head calculation = Calc prepared by: M. Seppanenhead loss due to elevation change Calc checked by: J. Perellahead loss due to pipe friction Date: 1/28/2010head loss across misc. process componentsrequired discharge head
Calculate pipe size:
Where: v = Velocity (ft/sec)Q = Flow rate (gpm)r = Pipe radius (in)
Flow Rate Pipe Size Pipe ODWall
Thickness Pipe ID Area velocity(gpm) (in) (in) (in) (in) (ft2) (ft/sec)
30 1.5 1.900 0.145 1.610 0.014 4.6030 2 2.375 0.154 2.067 0.023 2.7930 3 3.500 0.216 3.068 0.051 1.27
*Pipe dimensions noted for Schedule 40 galvanized steel piping.Note: Design for velocity between 3 and 5 feet/sec to maintain sufficient scour velocity.
Calculate head loss (he) due to elevation change:
assume: Height from pump to discharge point = 15 feetHead loss, he = 15 feet
Calculate head loss due to pipe friction losses:
Step 1. There are multiple pipe sections with flow and pipe diameters shown below
Pipe Section 1 Nominal pipe diameter 1 = 1.5 inch
Flow (v1) = 30 gpm
Step 2. Calculate the friction factor for each pipe section using the Hazen-Williams formula
Hazen-Williams f = .2083 * (100/C)1.852 * (q1.852) / (D4.8655)Formula
f = Friction in head in feet of water per 100 ft of pipeC = Constant for inside roughness
(140 for new galvanized steel pipe, 150 for hdpe pipe)q = Flow rate (gal/min)D = Inside diameter of pipe (inches)
Nominal Diam (in)
ID (in)
ID w/ deposition (in)
1 1.049 0.9241.5 1.610 1.4852 2.067 1.9423 3.068 2.9434 4.026 3.9016 6.065 5.94
NOTE: a 0.0625 inch (1/16 inch) deposition on interior pipe wall is included in diameter for calculation - 1.003 - (2 x 0.0625) = 0.878 inch diameter
Modified ISR System - AOP Treatment SystemTotal Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
sec60
min1*
)*( 2r
Qv
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\(14) Tab #11_P-1300 TDH.xlsx ARCADIS
Page 2 of 3
DECANT PUMP (P-1300) DESIGN CALCULATIONSModified ISR System - AOP Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Friction factor for Pipe Section 1C = Pipe roughness factor 140 unitlessq = flow rate (gal/min) 30 gal/minD1 = Inner pipe diameter (inches) 1.485 inches (see NOTE)
Pipe Section 1 friction factor 8.9 ft water / 100 feet of pipe
Step 3. Calculate the equivalent length of pipe for each section
Nominal Fitting size 1 in 1.5 in 2 in 3 in 4 in 6 in
90˚ Elbows 2.7 3.4 3.6 4.0 4.6 10.4Standard Tee (thru flow) 3.2 5.6 7.7 12.0 17.0 38.3Standard Tee (branch flow) 6.6 9.9 12.0 17.0 21.0 47.3Ball valve (full open) 1.6 2.3 2.9 4.3 5.5 12.3Check Valve 11.0 15.0 19.0 27.0 38.0 85.5Union 0.3 0.4 0.5 0.5 0.65 1.5Reducer (2/1) 1.0 1.5 1.5 3.0 4.0 9.0Expansion (1/2) 1.5 2.5 3.0 4.0 6.0 13.5
Equivalent lengths from reference: Civil Engineering Reference Manual, 9th Ed, Professional Publications, Inc., 2003; and "Flow of Fluids", Crane Technical Paper No. 410, 1988.
Pipe Section 1 - 2"
Item Qty. L (ft) Qty * LLinear Pipe (L1) 1 150 150Standard Tee (thru flow) 2 5.6 11Standard Tee (branch flow) 1 9.9 1090˚ Elbows 8 3.4 27Union 2 0.39 1Check Valve 1 15 15Ball valve (full open) 3 2.3 7
Equivalent Length: 221
Step 4. Determine pipe friction for each pipe section.
total pipe friction = total equivalent length x friction factor
Total Pipe Friction - Pipe Section 1total equivalent length = 221 feet
friction factor = 8.9 feet water / 100 feet of pipe
Total Pipe Friction = 19.6 feet
Step 5. Determine total pipe friction (all sections)
Total Pipe Friction - Pipe Section 1 = 19.6
Equivalent Length
Equivalent Length per Fitting (ft)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\(14) Tab #11_P-1300 TDH.xlsx ARCADIS
Page 3 of 3
DECANT PUMP (P-1300) DESIGN CALCULATIONSModified ISR System - AOP Treatment System
Total Dynamic Head Calculation
Raytheon CompanySt. Petersburg, Florida
Calculate Total Dynamic Head:
Head Loss Due to Change in Elevation 15 ft
Head loss due to pipe friction 20 ft
Head loss Across Misc. Process Components 0 ft
Required Discharge Pressure (0 psi) 0 ft
Total Dynamic Head Required - Calculated 35 ft
Design Safety Factor 25%
Total Dynamic Head Required - Design 43 feet
Pump Design Requirements:Flow 30 gpm
Total Dynamic Head 43 feet
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\(14) Tab #11_P-1300 TDH.xlsx ARCADIS
ITTGoulds Pumps1SC Submersible
Water Pump
GouldsPumpsisabrandofITTCorporation.
www.goulds.com
Engineered for life
Residential Water Systems
Features
■ Casing: AISI 304 SS. Corrosion resistant, non-toxic, non-leaching.
■ Impeller: FDA compliant, glass filled Noryl®. Corrosion and abrasion resistant.
■ Mechanical Seal: Silicon/carbide sealing faces; all metal components of AISI type 300 stainless steel running in protected oil chamber.
■ Elastomers: BUNA-N.
■ Motor Shell and Lifting Handle: Constructed of AISI type 304 series stainless steel.
■ Shaft: AISI type 304 stainless steel high strength keyed pump shaft with impeller locking cap screw.
■ Discharge: 11⁄4" NPT vertical discharge connection.
■ Suction Strainer: Detachable for easy clean out.
�
ITT GOuLDs PuMPsResidential Water Systems
0 �50
CAPACITY
TOTA
L D
YNA
MIC
HEA
D
FEET
U.S. GPM
100
50
150
�010 �00
�0
40
METERS
0 � 4� 6 m3/hr
60
5 15
51
�00
�5
7 8
1SC51E-H
1SC51C-F
1SC51D-G
1SC51C-A
1SC51D-B
1SC51E-C
1 HP3/4 HP1/2 HP
1 HP
3/4 HP
1/2 HP
aPPLICatIONs
Submersible water pumps designed for pumping out of reservoirs and storage tanks:• Homes and farms• Mobile home parks and motels• Schools and hospitals• Municipal applications• Industrial applications• Commercial applications
sPeCIFICatIONs
Pump:
• 11⁄4" NPT discharge and open suction.
• Maximum suspended solids 1⁄8".
• Capacities: to 35 U.S. GPM (7.9 m3/h).
• Total heads: to 240 feet TDH (70 m).
• Temperature: 104ºF (40ºC) continuous 140ºF (60ºC) intermittent.
• Maximum submergence: to 65 feet (20 m).
• Continuous duty rated, non-overloading motor.Motor:
• Single phase: 3450 RPM, 115 and 230 V, 60 Hz.
• Three phase: 3450 RPM, 230 V, 60 Hz.
• Non-overloading.
• Class F insulation.
• Thermal overload protection: built-in with automatic reset on single phase.
• Three phase models require external overloads in panel.
• Power cord: All 30' long.Single phase – 16/3, with 115 V or 230 V plugThree phase – 16/4 STO, bare leads
NOTE: See accessory section for separate control panels.
�
ITT GOuLDs PuMPsResidential Water Systems
DIMeNsIONs
MeCHaNICaL Data
NPT 11⁄4
L
5"
“L” Dimensions Discharge Series HP Phase in inches Size
1⁄2 1,3 191⁄8
1SC 3⁄4 1,3 201⁄8 11⁄4
1 1,3 213⁄4
Series Number of HP Volts Phase Maximum RPM Weight Stages Amps (lbs.) 1SC51C0AA 115 1 10.6
1SC51C1AA 1⁄2 230 4.5
1SC51C3AA 3 3 3.0 31 1SC51C0FA 115 1 10.7
1SC51C1FA 1⁄2 230 4.5
1SC51C3FA 3 3.0
1SC51D1BA 1 5.4 3450
1SC51D3BA 4 3⁄4 230 3 3.5 33 1SC51D1GA 1 5.3
1SC51D3GA 3 3.5
1SC51E1CA 1 6.4
1SC51E3CA 5 1 230 3 4.1 38 1SC51E1HA 1 6.8
1SC51E3HA 3 4.3
ITT
GouldsPumpsandtheITTEngineeredBlocksSymbolareregisteredtrademarksandtradenamesofITTCorporation.
NorylisaregisteredtrademarkofGEPlastic.
SPECIFICATIONS ARE SUBJECT TO CHANGE WITHOUT NOTICE.
B1SC August, 2007©2007ITTCorporation
Engineered for life
Residential Water Systems
Component Material Outer Casing and Upper Support Stainless Steel (AISI 304)
Motor Casing Stainless Steel (AISI 304)
Suction Strainer Stainless Steel (AISI 304)
Motor Shaft Stainless Steel (AISI 304)
Impeller Noryl
Diffuser Stainless Steel (AISI 304)
Upper Cover Technopolymer
Mechanical Seal Housing Technopolymer
Lower Bearing Support Aluminum Die Cast
Lower Bearing Urethane Resin
Elastomers Buna-N
Lower Mechanical Seal Silicon Carbide/Silicon Carbide
Upper Lip Seal Nitrile Rubber
Polymer CalculationsModified ISR System
AOP Treatment System
Raytheon Company St. Petersburg, Florida
Page 1 of 2
M. Seppanen
J. Darby
1/28/2010
Air/Water Scour: Flow rate = 63 gpm
Polymer dosage = 15 ppmv Jar Test Results
Specific gravity of polymer = 1.015
Polymer weight = 8.465 lbs/gal
Polymer flow rate = 3.6 mL/min
Water Only: Flow rate = 188 gpm
Polymer dosage = 15 ppmv Jar Test Results
Polymer flow rate = 10.7 mL/min
Flow rate = 74 gpm
Polymer dosage = 15 ppmv Jar Test Results
Polymer flow rate = 4.2 mL/min
Air Scour: Backwash flow rate = 63 gpm
Polymer flow rate = 3.6 mL/min
Duration of backwash = 10 min
Volume of polymer = 0.04 L
Water Only: Backwash flow rate = 188 gpm
Polymer flow rate = 10.7 mL/min
Duration of backwash = 5 min
Volume of polymer = 0.05 L
Calc prepared by:
Calc checked by:
Date:
Calculate Polymer Flow Rates for the Catalytic Media Backwash Cycle:
Calculate Volume of Polymer Required for the Catalytic Media Filters:
Calculate Polymer Flow Rates for the Multi-Media Backwash Cycle:
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\(16) Tab #11_AOP Polymer Calc.xlsx ARCADIS
Polymer CalculationsModified ISR System
AOP Treatment System
Raytheon Company St. Petersburg, Florida
Page 2 of 2
Combined: Total Volume of polymer per vessel = 0.09 L
Number of vessels = 3
Total Volume of polymer = 0.27 L
Backwash flow rate = 74 gpm
Polymer flow rate = 4.2 mL/min
Duration of backwash = 10 min
Volume of polymer per vessel = 0.04 L
Number of vessels = 2
Total Volume of polymer = 0.08 L
Cataltyic Media Filters:
Total Volume of polymer = 0.27 L
Backwash Frequency = 7 Backwash cycles/week
Total Volume of polymer per week = 1.87 L/week
0.49 gal/week
Multi-Media Filters:
Total Volume of polymer = 0.08 L
Backwash Frequency = 3 Backwash cycles/week
Total Volume of polymer per week = 0.25 L/week
0.07 gal/week
Total Volume of polymer per week = 0.56 gal/week
Calculate Total Volume of Polymer Required per Week:
Calculate Volume of Polymer Required for the Mulit-Media Filters:
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #11\(16) Tab #11_AOP Polymer Calc.xlsx ARCADIS
©2006, General Electric Company. All rights reserved. *Trademark of General Electric Company; may be registered in one or more countries.
Fact Sheet
PFW957EN 0606
Europe/Middle East/Africa Heverlee, Belgium +32-16-40-20-00
Asia/Pacific Shanghai, China +86-21-5298-4573
Find a contact near you by visiting gewater.com or e-mailing [email protected].
Americas Watertown, MA +1-617-926-2500
Global Headquarters Trevose, PA +1-215-355-3300
PolyFloc* AS1002 High Molecular Weight Flocculant• Easy-to-feed polymeric flocculant
• Convenient, true liquid
• Reduces floc carryover
• Approved for potable use
Description and Use
PolyFloc AS1002 is a liquid, weakly anionic, high molecular weight, polymeric flocculant, which is designed to function in industrial treatment programs as a coagulant aid, or flocculant, in clarification, thickening, and softening processes. The product is chlorine resistant. NSF certification for potable applications is pending.
PolyFloc AS1002 is true liquid, high molecular weight flocculant. This polymer is ideal for remote plant operations or small volume usage because it does not require extensive feed and makedown equipment.
A fast-settling floc is formed when PolyFloc AS1002 is applied to warm or hot lime/soda softeners, cold lime softeners, and influent clarification systems. Floc carryover is reduced, resulting in a cleaner effluent.
PolyFloc AS1002 is also an excellent sludge dewatering aid producing clean filtrate, high solids capture, and a drier cake. Applications to many types of industrial sludges have been successful, including blast furnace sludge dewatering applications.
Treatment and Feeding Requirements
PolyFloc AS1002 is an easy-to-feed liquid that does not require any special makedown procedures. Poly-Floc AS1002 can be fed neat with any suitable high viscosity gear pump or diluted with water to any con-venient concentration. Diluted product may be fed by a pump, eductor, or by gravity flow to a point where good mixing, but not violent agitation, of the treated water occurs. High speed mixing decreases the activ-
ity of the polymer. Pumps used to transfer the solution to the point of application should be positive dis-placement gear or piston pumps.
To minimize corrosion and contamination by corro-sion products, liquid-side components of tanks, pumps, and piping should be constructed of stainless steel, polyethylene, or polyvinyl chloride. Mild steel is acceptable only in systems where contamination by corrosion products is not a critical problem.
General Properties
Physical properties of PolyFloc AS1002 are shown on the Material Safety Data Sheet, a copy of which is available on request.
Packaging Information
PolyFloc AS1002 is a liquid product, available in a vari-ety of containers. Consult your GE representative for delivery and packaging alternatives.
Storage and Handling
Store PolyFloc AS1002 at moderate temperatures of 40 to 90°F (4 to 32°C), and protect from freezing. The recommended shelf life of the product is six months.
Spilled polymer is very slippery. Small amounts of spilled polymer can be washed down with copious amounts of water. Large spills should be contained and absorbed on inert material, then disposed as solid waste, prior to flushing with water.
Safety Precautions
A Material Safety Data Sheet containing detailed in-formation about this product is available upon re-quest.
Material Safety Data Sheet Issue Date: 28-JAN-2008 Supercedes: 28-JAN-2008
POLYFLOC AS1002
1 IdentificationIdentification of substance or preparationPOLYFLOC AS1002
Product Application AreaFlocculant.
Company/Undertaking IdentificationGE Betz, Inc.4636 Somerton RoadTrevose, PA 19053T 215 355-3300, F 215 953 5524
Emergency Telephone(800) 877-1940
Prepared by Product Stewardship Group: T 215-355-3300 Prepared on: 28-JAN-2008
2 Hazard(s) identification
******************************************************************************** EMERGENCY OVERVIEW CAUTION May cause slight irritation to the skin. May cause slight irritation to the eyes. Mists/aerosols may cause irritation to upper respiratory tract. DOT hazard is not applicable Odor: Slight; Appearance: Colorless To Light Yellow, Liquid Fire fighters should wear positive pressure self-contained breathing apparatus(full face-piece type). Proper fire-extinguishing media: dry chemical, carbon dioxide, foam or water ******************************************************************************** POTENTIAL HEALTH EFFECTS ACUTE SKIN EFFECTS: Primary route of exposure; May cause slight irritation to the skin. ACUTE EYE EFFECTS: May cause slight irritation to the eyes. ACUTE RESPIRATORY EFFECTS: Mists/aerosols may cause irritation to upper respiratory tract.
Page 1Substance or Preparation: POLYFLOC AS1002
INGESTION EFFECTS: May cause slight gastrointestinal irritation. TARGET ORGANS: No evidence of potential chronic effects. MEDICAL CONDITIONS AGGRAVATED: Not known. SYMPTOMS OF EXPOSURE: May cause redness or itching of skin.
3 Composition / information on ingredients
Information for specific product ingredients as required by the U.S. OSHA HAZARD COMMUNICATION STANDARD is listed. Refer to additional sections of this MSDS for our assessment of the potential hazards of this formulation. HAZARDOUS INGREDIENTS: This product is not hazardous as defined by OSHA regulations. No component is considered to be a carcinogen by the National Toxicology Program, the International Agency for Research on Cancer, or the Occupational Safety and Health Administration at OSHA thresholds for carcinogens.
4 First-aid measures
SKIN CONTACT: Wash thoroughly with soap and water. Remove contaminated clothing. Get medical attention if irritation develops or persists. EYE CONTACT: Remove contact lenses. Hold eyelids apart. Immediately flush eyes with plenty of low-pressure water for at least 15 minutes. Get medical attention if irritation persists after flushing. INHALATION: If nasal, throat or lung irritation develops - remove to fresh air and get medical attention. INGESTION: Do not feed anything by mouth to an unconscious or convulsive victim. Do not induce vomiting. Immediately contact physician. Dilute contents of stomach using 2-8 fluid ounces (60-240 mL) of milk or water. NOTES TO PHYSICIANS: No special instructions
5 Fire-fighting measures
Page 2Substance or Preparation: POLYFLOC AS1002
FIRE FIGHTING INSTRUCTIONS: Fire fighters should wear positive pressure self-contained breathing apparatus (full face-piece type). EXTINGUISHING MEDIA: dry chemical, carbon dioxide, foam or water HAZARDOUS DECOMPOSITION PRODUCTS: oxides of carbon and sulfur FLASH POINT: > 200F > 93C P-M(CC)
6 Accidental release measures
PROTECTION AND SPILL CONTAINMENT: Ventilate area. Use specified protective equipment. Contain and absorb on absorbent material. Place in waste disposal container. Flush area with water. Wet area may be slippery. Spread sand/grit. DISPOSAL INSTRUCTIONS: Water contaminated with this product may be sent to a sanitary sewer treatment facility,in accordance with any local agreement,a permitted waste treatment facility or discharged under a permit. Product as is - Incinerate or land dispose in an approved landfill.
7 Handling and storage
HANDLING: Normal chemical handling. STORAGE: Keep containers closed when not in use. Protect from freezing. Shelf life 135 days.
8 Exposure controls / personal protection
EXPOSURE LIMITS This product is not hazardous as defined by OSHA regulations. ENGINEERING CONTROLS: adequate ventilation PERSONAL PROTECTIVE EQUIPMENT: Use protective equipment in accordance with 29CFR 1910 Subpart I RESPIRATORY PROTECTION: A RESPIRATORY PROTECTION PROGRAM THAT MEETS OSHA’S 29 CFR 1910.134 AND ANSI Z88.2 REQUIREMENTS MUST BE FOLLOWED WHENEVER WORKPLACE CONDITIONS WARRANT A RESPIRATOR’S USE. USE AIR PURIFYING RESPIRATORS WITHIN USE LIMITATIONS ASSOCIATED WITH THE EQUIPMENT OR ELSE USE SUPPLIED AIR-RESPIRATORS. If air-purifying respirator use is appropriate, use any of the following particulate respirators: N95, N99, N100, R95, R99, R100, P95, P99 or P100. SKIN PROTECTION: rubber, butyl, viton or neoprene gloves -- Wash off after each use. Replace as necessary. EYE PROTECTION: splash proof chemical goggles
Page 3Substance or Preparation: POLYFLOC AS1002
9 Physical and chemical properties
Specific Grav.(70F,21C) 1.015 Vapor Pressure (mmHG) ~ 18.0 Freeze Point (F) 32 Vapor Density (air=1) < 1.00 Freeze Point (C) 0 Viscosity(cps 70F,21C) 2000 % Solubility (water) 100.0 Odor Slight Appearance Colorless To Light Yellow Physical State Liquid Flash Point P-M(CC) > 200F > 93C pH As Is (approx.) 4.1 Evaporation Rate (Ether=1) < 1.00 Percent VOC: 0.0 NA = not applicable ND = not determined
10 Stability and reactivity
STABILITY: Stable under normal storage conditions. HAZARDOUS POLYMERIZATION: Will not occur. INCOMPATIBILITIES: May react with strong oxidizers. DECOMPOSITION PRODUCTS: oxides of carbon and sulfur INTERNAL PUMPOUT/CLEANOUT CATEGORIES: "A"
11 Toxicological information
Oral LD50 RAT: >2,000 mg/kg NOTE - Estimated value Dermal LD50 RABBIT: >2,000 mg/kg NOTE - Estimated value
12 Ecological information
AQUATIC TOXICOLOGY Daphnia magna 48 Hour Static Acute Bioassay (pH adjusted) LC50= 25466; No Effect Level= 8700 mg/L Fathead Minnow 96 Hour Static Acute Bioassay (pH adjusted) LC50= 30944; No Effect Level= 15500 mg/L BIODEGRADATION No Data Available.
13 Disposal considerations
Page 4Substance or Preparation: POLYFLOC AS1002
If this undiluted product is discarded as a waste, the US RCRA hazardous waste identification number is : Not applicable. Please be advised; however, that state and local requirements for waste disposal may be more restrictive or otherwise different from federal regulations. Consult state and local regulations regarding the proper disposal of this material.
14 Transport information
DOT HAZARD: Not Applicable PROPER SHIPPING NAME: DOT EMERGENCY RESPONSE GUIDE #: Not applicable Note: Some containers may be DOT exempt, please check BOL for exact container classification
15 Regulatory information
TSCA: All components of this product are included on or are in compliance with the U.S. TSCA regulations. CERCLA AND/OR SARA REPORTABLE QUANTITY (RQ): No regulated constituent present at OSHA thresholds FOOD AND DRUG ADMINISTRATION: 21 CFR 176.110 (acrylamide - acrylic acid resins) All ingredients comprising this product are authorized by FDA for the manufacture of paper and paperboard that may contact aqueous and fatty foods as per 21 CFR 176.170(a) (4). USDA FOOD PLANT APPROVALS: G1 SARA SECTION 312 HAZARD CLASS: Product is non-hazardous under Section 311/312 SARA SECTION 302 CHEMICALS: No regulated constituent present at OSHA thresholds SARA SECTION 313 CHEMICALS: No regulated constituent present at OSHA thresholds CALIFORNIA REGULATORY INFORMATION CALIFORNIA SAFE DRINKING WATER AND TOXIC ENFORCEMENT ACT (PROPOSITION 65): No regulated constituents present MICHIGAN REGULATORY INFORMATION No regulated constituent present at OSHA thresholds
16 Other information
NFPA/HMIS CODE TRANSLATION Health 1 Slight Hazard Fire 0 Minimal Hazard Reactivity 0 Minimal Hazard Special NONE No special Hazard
Page 5Substance or Preparation: POLYFLOC AS1002
(1) Protective Equipment B Goggles,Gloves (1) refer to section 8 of MSDS for additional protective equipment recommendations. CHANGE LOG EFFECTIVE DATE REVISIONS TO SECTION: SUPERCEDES --------- --------------------- ---------- MSDS status: 30-JAN-1997 ** NEW ** 12-MAY-1997 15 30-JAN-1997 06-MAY-1998 ;EDIT:9 12-MAY-1997 27-MAY-1999 15 06-MAY-1998 21-SEP-1999 15 27-MAY-1999 11-FEB-2002 4,16 21-SEP-1999 28-JAN-2008 4,5,7,8,10 11-FEB-2002
Page 6Substance or Preparation: POLYFLOC AS1002
Koflo Corporation309 CARY POINT DR.CARY, IL 60013
CUSTOMER:
DATE:
SCALE:
MODEL NO:
APPROVED BY DRAWN BY
REVISED
REVISED
REVISED
DRAWING NUMBER:
NONE
7/10/06
NJF
KD-985TYPICAL LOW PRESSURE LOSS DESIGN FLANGE MOUNTED MIXER WITH FNPT INJECTION PORT
5/30/08
"B" HOLES "C" DIAMETER ON A "D" D.B.C.
150 LB. RAISED FACE FLANGED ENDS
KOFLO STATIC MIXER CONSTRUCTED OFSCHEDULE 40 OR 10 PIPE WITH *____ FIXED LOW PRESSURE LOSS DESIGN MIXING ELEMENTS
"A"(Inches)
NOTE: SCH 40 IS USED FOR CARBON STEEL MIXERS SCH 10 IS USED FOR SS/ALLOY MIXERS 3" AND LARGER
"E"
FNPT INJECTION PORT "F" SIZE OR AS SPECIFIED
DIRECTIONOF FLOW
Tab 12
Modified ISR System – AOP Treatment System Granular Activated Carbon
LIQUID-PHASE GAC VESSEL DESIGN CALCULATIONSModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
Page 1 of 2
M. Seppanen
J. Darby
1/28/2010
Assume: LPGAC vessel sizing is based on chemical adsorption and hydraulic loading.
The amount of volatile organic compounds to the LPGAC vessel in the influent stream is
expected to be minimal. The orientation of the LPGAC vessels are two vessels in series
3 - 8 gpm/ft2
Process Flow Rate = 92 gpm
Design Loading Rate 5.0 gpm/ft2
Filtration Area Required = 18.4 ft2
Number of online vessels = 1
Filtration area per vessel = 18.4 ft2
Calculated diameter of vessel = 4.8 ft
Selected vessel diameter = 6.0 ft
Filtration Area per vessel = 28.3 ft2
Actual Loading Rate = 3.3 gpm/ft2
COCs: 1,1 - Dichloroethane (1,1-DCA) = 10 μg/L
Total VOCs in Influent = 0.010 mg/L
0.011 lbs/day
Carbon usage =
Where,
Co = Contaminant concentration (mg/L)
Q = Process flow rate (Lpm)
t = Time (day)
k = Adsorption Capacity @ 1ppm (mg/g carbon)
η = Efficiency (%)
Calc prepared by:
Calc checked by:
Date:
Calculate Carbon Usage Rate:
Calculate size of aqueous phase granular activated carbon (GAC) units:
Incoming VOCs (Based on Mass Balance and ISR Operation):
Calculate diameter of LPGAC vessel:
Selected design requirement specifications:
Design is based on hydraulic loading
Recommended hydraulic loading for carbon
)1
(*)**
( 0
k
tQC
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #12\(1) Tab #12_LGAC Calc.xlsx ARCADIS
LIQUID-PHASE GAC VESSEL DESIGN CALCULATIONSModified ISR System
AOP Pre-Treatment System
Raytheon CompanySt. Petersburg, Florida
Page 2 of 2
1,1 - DCA Concentration at Mid Process point 1 = (C0) = 0.010 mg/L
Process Flow Rate = (Q) = 348 L/min
Adsorption capacity 2 = (k) = 7.5 mg/g carbon
Efficiency = (η) = 5 %
Time = (t) = 1,440 min
Carbon usage rate for 1,1-DCA: 13,372 g carbon/day
29.5 lb carbon/day
Mass of carbon in vessel = 2,500 lb
Estimated Time for Carbon Breakthrough = 85 days
Calculate Estimated Time for Carbon Breakthrough:
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #12\(1) Tab #12_LGAC Calc.xlsx ARCADIS
Tab 13
Modified ISR System – General Arrangement Plans
Tab 14
Modified ISR System – Building Containment Curb
Page 1 of 2
Calc prepared by: M. SeppanenCalc checked by: J. DarbyDate: 01/28/2010
Calculate Volume of Tanks and Process Equipment within Containment:
Equipment Name Volume (gal) No. Units Total Volume (gal)
Heat Exchanger Feed Tank (T-100) 2,145 1 2,145Heat Exchanger (HX-100A/B) 10 2 20Influent Equalization Tank (T-200A/B/C) 20,160 3 60,480Aeration Tank (T-300) 6,500 1 6,500Filter Feed Tank (T-400) 6,500 1 6,500Multi-Media Filters (T-500A/B/C) 370 3 1,110Air Stripper (T-600A/B) 250 2 500Air Stripper Discharge Tank (T-700) 1,100 1 1,100Backwash Holding Tank (T-800) 6,500 1 6,500Polymer Tank (T-900) 5 1 5Sodium Hydroxide Tank (T-1000) 275 1 275Scrubber Blow-Down Tank (T-1000) 1,000 1 1,000Scrubber Blow-Down LPGAC (T-1100A/B) 160 1 160
Subtotal = 86,295 gallons
Calculate Volume of Required Containment:
The total containment volume required shall be the larger volume from either Method 1 or 2 below:
Method 1:
Total Volume = 10% of Total Volume of Tanks and Process Equipment
Volume of Tanks and Process Equipment 86,295 gallons10% 8,630 gallons
Total Method 1 = 8,630 gallons
Method 2:
Raytheon CompanySt. Petersburg, Florida
CONTAINMENT VOLUME CALCULATIONModified ISR System
AOP Pre-Treatment System
Total Volume = 110% Volume of the Largest Tank
Volume of Largest Tank 20,160 gallons110% 22,176 gallons
Total Method 2 = 22,176 gallons
Calculate Volume of Containment Available:
Containment Volume = (Containment Area - Equipment Area) x Containment Curb Depth
Length (feet) Width (feet) Total Area (ft2)Containment Area 85 80 6,800
Subtotal = 6,800 ft2
Equipment Name Area (ft2) * % under curb Displacement Area (ft2)Heat Exchanger Feed Tank (T-100) 44 100% 44Heat Exchanger (HX-100A/B) 36 50% 18Influent Equalization Tank (T-200A/B/C) 960 100% 960Aeration Tank (T-300) 79 100% 79Filter Feed Tank (T-400) 79 100% 79Multi-Media Filters (T-500A/B/C) 30 30% 9Air Stripper (T-600A/B) 70 20% 14Air Stripper Discharge Tank (T-700) 41 100% 41Backwash Tank (T-800) 79 100% 79Polymer Tank and Pump (T-900) 16 100% 16Sodium Hydroxide Tank (T-1000) 12 100% 12Scrubber Blow-Down Tank (T-1000) 25 50% 13Scrubber Blow-Down LPGAC (T-1100A/B) 20 50% 10Pump Skids (7) 63 50% 32Blower Skids (3) 27 50% 14
Subtotal = 1,418
* measurements from Modified ISR System AOP Pre-treatment System Layout: Figure J-5, Tab #11
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #14\(1) Pre-AOP Containment Volume.xlsx ARCADIS
Page 2 of 2
Raytheon CompanySt. Petersburg, Florida
CONTAINMENT VOLUME CALCULATIONModified ISR System
AOP Pre-Treatment System
Containment Area 6,800 square feetEquipment Area 1,418 square feet
Subtotal = 5,382 square feetDepth 0.75 feet (Curb 9" high)Estimated Floor Slope 0.17 feetCorrected Depth 0.67 feet
Total = 3,588 cubic feetConversion 7.48 gallons/cubic foot
Containment Volume Available 26,839 gallons
Containment Volume Available 26,839 gallonsContainment Volume Required 22,176 gallons
Volume Available > Volume Required therefore design is acceptable
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #14\(1) Pre-AOP Containment Volume.xlsx ARCADIS
Page 1 of 2
Calc prepared by: M. SeppanenCalc checked by: J. DarbyDate: 01/28/2010
Calculate Volume of Tanks and Process Equipment within Containment:
Equipment Name Volume (gal) No. Units Total Volume (gal)
Influent Equalization Tank (T-1300) 20,160 1 20,160Influent Equalization Tank (T-1500) 20,160 1 20,160Filter Feed Tank (T-1400) 6,500 1 6,500Filter Feed Tank (T-1600) 6,500 1 6,500Catalytic Media Filters (T-1700A/B/C) 750 3 2,250Multi-Media Filters (T-1800A/B) 370 2 740LPGAC (T-1900A/B/C) 2,200 3 6,600Backwash Tank (T-2000) 20,160 1 20,160Polymer Storage Tank (T-2100) 5 1 5AOP Unit (AOP-100) 150 1 150AOP Unit (AOP-200) 250 1 250AOP-100 Unit pH Control Unit 500 1 500Hydrogen Peroxide Tank 1,500 1 1,500Sodium Permanganate Solution Tanks 530 1 530
Subtotal = 86,005 gallons
Calculate Volume of Required Containment:
The total containment volume required shall be the larger volume from either Method 1 or 2 below:
Method 1:
Total Volume = 10% of Total Volume of Tanks and Process Equipment
Volume of Tanks and Process Equipment 86,005 gallons10% 8,601 gallons
Total Method 1 = 8,601 gallons
Method 2:
Total Volume = 110% Volume of the Largest Tank
Volume of Largest Tank 20,160 gallons110% 22,176 gallons
Total Method 2 = 22,176 gallons
Calculate Volume of Containment Available:
Containment Volume = (Containment Area - Equipment Area) x Containment Curb Depth
Length (feet) Width (feet) Total Area (ft2)Containment Area 118 68 8,024
Subtotal = 8,024 ft2
Equipment Name Area (ft2) * % under curb Displacement Area (ft2)Influent Equalization Tank (T-1300) 344 100% 344Influent Equalization Tank (T-1500) 344 100% 344Filter Feed Tank (T-1400) 79 100% 79Filter Feed Tank (T-1600) 79 100% 79Catalytic Media Filters (T-1700A/B/C) 63 30% 19Multi-Media Filters (T-1800A/B) 19 30% 6LPGAC (T-1900A/B/C) 147 30% 44Backwash Tank (T-2000) 344 100% 344AOP Unit (AOP-100) 320 100% 320AOP Unit (AOP-200) 204 100% 204Control Panels 70 30% 21Vapor Phase Carbon Vessels (3) 25 30% 8VSA Oxygen Skid 36 100% 36AOP-100 Unit Chiller 10 100% 10AOP-200 Unit Chiller 7 100% 7Hydrogen Peroxide Tank 76 100% 76AOP-100 Unit pH Control Unit 35 100% 35AOP-100 Unit Feed Pump Skid 11 100% 11Polymer Skid 9 100% 9Pump Skids (4 pumps) 16 50% 8Sodium Permanganate System Building 204 100% 204
Subtotal = 2,206
St. Petersburg, Florida
Modified ISR SystemAOP Treatment System
CONTAINMENT VOLUME CALCULATION
Raytheon Company
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #14\(2) AOP System Containment Volume.xlsx ARCADIS
Page 2 of 2
Modified ISR SystemAOP Treatment System
CONTAINMENT VOLUME CALCULATION
Raytheon Company
* measurements from Modified ISR System AOP System Layout: Figure J-6, Tab #9
Containment Area 8,024 square feetEquipment Area 2,206 square feet
Subtotal = 5,818 square feetDepth 0.75 feet (Curb 9" high)Estimated Floor Slope 0.17 feetCorrected Depth 0.67 feet
Total = 3,879 cubic feetConversion 7.48 gallons/cubic foot
Containment Volume Available 29,014 gallons
Containment Volume Available 29,014 gallonsContainment Volume Required 22,176 gallons
Volume Available > Volume Required therefore design is acceptable
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #14\(2) AOP System Containment Volume.xlsx ARCADIS
Tab 15
Modified ISR System – Support Equipment
Tab 16
Modified ISR System – Process and Instrumentation
Table J-5Modified ISR System
AOP Pre-Treatment SystemControl Logic TableRaytheon Company
St. Petersburg, Florida
PROCESS UNIT DEVICE ID DEVICE TYPE SET POINT RESPONSE (1) COMMENT
LS-100 Level Switch 1. 56 inches - high / high level Alarm - Notify Operator.
AOP pre-treatment system shut down (2). Critical alarm to Thermal System PLC - disable transfer of groundwater and condensate.
LE/LT-100 Level Transmitter 1. 12 inches - low level 2. 40 inches - operating level3. 48 inches - high level4. 52 inches - high / high level
1. Alarm - Notify Operator; Disable operation of heat exchanger feed pumps (P-100A/B).2. PLC controls P-100A/B pump speed to maintain specified water level in tank.3. Alarm - Notify Operator.4. Critical alarm to Thermal System PLC - disable transfer of groundwater and condensate.
HS-100A/B HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
VFD-100A/B Variable Frequency Drive PLC adjustable set point The purpose is to maintain a constant water level in the heat exchanger feed tank (T-100). Tank level data will be monitored and transmitted to PLC by LE/LT-100.
YI-100A/B Status Indicator On/Off 1. Indicates status of P-100A/B. A discord alarm will occur if P-100A or P-100B is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
TE/TT-100A Temperature transmitter Indication only 4-20mA signal sent to PLC, PLC to track temperature reading. The purpose is to monitor influent temperature to heat exchanger (HX-100A/B). Data to be used to determine heat exchanger performance.
TE/TT-100B Temperature transmitter PLC adjustable set point to detect temperature in the heat exchanger effluent line.
High temperature response:1. >140 F - Shut down power to Pumps P-100A/B, Critical alarm to Thermal System PLC, Notify Operator.2. 130 - 140F - Slow speed of Pump P-100A/B 10%, delay 15 minutes and then re-assess, Notify operator, Notification alarm to Thermal System PLC3. 120 - 130 F - Notify Operator.
TE/TT-100C Temperature transmitter PLC adjustable set point to detect temperature in the chilled water feed line.
1. 4-20mA signal sent to PLC, PLC to track temperature reading.2. Temperatures >50 F, Notify Operator.
TE/TT-100D Temperature transmitter Indication only 1. 4-20mA signal sent to PLC, PLC to track temperature reading.2. Temperatures >95 F, Notify Operator.
The purpose is to monitor water temperature returned to TerraTherm's system. Data to be used to determine heat exchanger performance.
LS-1100 Level Switch 1. 64 inches - high / high level 1. Alarm - Notify Operator.2. Critical alarm to Thermal System PLC - disable transfer of scrubber blow-down water.
LE/LT-1100 Level Transmitter 1. 12 inches - low level 2. 16 inches 3. 48 inches - operating level4. 54 inches - high level5. 60 inches - high / high level
1. Alarm - Notify Operator. 2. Disable operation of transfer pump (P-900).3. PLC controls P-900 pump speed to maintain specified water level in tank.4. Alarm - Notify Operator.5. Critical alarm to Thermal System PLC - disable transfer of scrubber blow-down water.
HS-900 HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
VFD-900 Variable Frequency Drive PLC adjustable set point The purpose is to maintain a constant water level in the scrubber blow-down tank (T-1100). Tank level data will be monitored and transmitted to PLC by LE/LT-1100.
YI-900 Status Indicator On/Off 1. Indicates status of P-900. A discord alarm will occur if P-900 is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
LPGAC Vessels (T-1200A/B)
PIT-1200A/B;DPI-1200
Pressure Transmitter, Differential Pressure Indicator
PLC adjustable set point to detect pressure at the inlet and outlet of the LPGAC vessels.
Low pressure at PIT-1200A:1. Shut down power to Pump P-900.2. Notify Operator.3. Flashing strobe light.High pressure at PT-1200A:1. Shut down power to Pump P-900.2. Notify Operator.3. Flashing strobe light.High differential pressure response:1. Notify Operator.
The purpose is to optimize operation of the GAC filters. Low pressure may indicate leakage and high pressure indicates membranes and/or piping may be plugged. High differential pressure indicates changeout of carbon is required.
Treatment System - Figure J-4Heat Exchanger Feed Tank (T-100)
Heat Exchanger(HX-100A/B)Chilled Water Feed and Return Lines
Heat Exchanger Feed Pumps (P-100A/B)
Heat Exchanger (HX-100A/B) Process Water Line
Scrubber Blow-Down Tank (T-1100)
Transfer Pump (P-900)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #16\Tables J-5 and J-6_Control Logic.xlsx Page 1 of 6 ARCADIS
Table J-5Modified ISR System
AOP Pre-Treatment SystemControl Logic TableRaytheon Company
St. Petersburg, Florida
PROCESS UNIT DEVICE ID DEVICE TYPE SET POINT RESPONSE (1) COMMENT
Scrubber Blow-Down Effluent Piping
FE/FIT-100 Totalizing flow meter with indicating transmitter
NA 4-20mA signal sent to PLC, PLC to calculate flow rate and track totalizer reading.
LS-200A Level Switch 1. 122 inches - high / high level Alarm - Notify Operator.
AOP pre-treatment system shut down (2). Critical alarm to Thermal System PLC - disable transfer of groundwater and condensate.
LE/LT-200A Level Transmitter 1. 24 inches - low level 2. 20 inches 3. 80 inches - operating level4. 100 inches - high level5. 112 inches - high / high level
1. Alarm - Notify Operator; Disable operation of aeration tank feed pumps (P-200A/B). 2. Notify Operator.3. PLC controls P-200A/B pump speed to maintain specified water level in tank.4. Alarm - Notify Operator. Begin overflow to influent EQ tanks (T-200B/C).5. Disable operation of heat exchanger feed pumps (P-100A/B). Critical alarm to Thermal System PLC - disable transfer of groundwater and condensate.
FV-200A Flow Valve On/Off Flow Valve FV-200A opens or closes depending on the control device and alarms it is subject to. FV-200A shall fail closed in the event of AOP pre-treatment system shut down.
The purpose is to control the flow of compressed air to the pneumatic actuated valves associated with EQ tank operation.
LS-200B/C Level Switch 1. 122 inches - high / high level Alarm - Notify Operator.
AOP pre-treatment system shut down (2). Critical alarm to Thermal System PLC - disable transfer of groundwater and condensate.
LE/LT-200B/C Level Transmitter 1. 24 inches - low level 2. 96 inches - operating level3. 108 inches - high level4. 116 inches - high / high level
1. Alarm - Notify Operator; Disable operation of recirculation pump (P-200C).2. Enable operation of recirculation pump (P-200C). PLC controls P-200C pump speed to maintain a constant flow of recycled water to influent EQ tank (T-200A).3. Alarm - Notify Operator. 4. Disable operation of heat exchanger feed pumps (P-100A/B). Critical alarm to Thermal System PLC - disable transfer of groundwater and condensate.
FV-200B/C Flow Valve On/Off Flow Valve FV-200B/C opens or closes depending on the control device and alarms it is subject to. FV-200B/C shall fail closed in the event of AOP pre-treatment system shut down.
The purpose is to control the flow of compressed air to the pneumatic actuated valves associated with EQ tank operation.
HS-200A/B HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
VFD-200A/B Variable Frequency Drive PLC adjustable set point The purpose is to maintain a constant water level in the influent EQ tank (T-200A). Tank level data will be monitored and transmitted to PLC by LE/LT-200A.
YI-200A/B Status Indicator On/Off 1. Indicates status of P-200A/B. A discord alarm will occur if P-200A or P-200B is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
HS-200C HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
VFD-200C Variable Frequency Drive PLC adjustable set point The purpose is to maintain a constant recycled water flow rate to influent EQ tank (T-200A). Tank level data will be monitored and transmitted to PLC by LE/LT-200A/B/C.
YI-200C Status Indicator On/Off 1. Indicates status of P-200C. A discord alarm will occur if P-200C is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
Aeration Tank (T-300) Influent Line
AE/AIT-300 pH Sensor 1. pH = 6.0 - low level2. pH = 7.6 - high level
Data will be used to control the speed of the sodium hydroxide metering pump (P-700) and ensure the correct pH is maintained in the aeration tank (T-300).
LS-300 Level Switch 1. 114 inches - high / high level Alarm - Notify Operator.
Shut down AOP pre-treatment system components downstream of EQ tanks T-200A/B/C (3). LE/LT-300 Level Transmitter 1. display/record tank water level
2. 108 inches - high / high level 1. 4-20 mA signal sent to PLC to display/record tank water level2. Critical alarm - Notify operator, disable aeration feed tank pumps (P-200A/B).
Influent EQ Tanks(T-200B/C)
Treatment System - Figure J-5Influent Equalization (EQ) Tank (T-200A)
Aeration Tank(T-300)
Aeration Tank Feed Pumps (P-200A/B)
Recirculation Pump (P-200C)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #16\Tables J-5 and J-6_Control Logic.xlsx Page 2 of 6 ARCADIS
Table J-5Modified ISR System
AOP Pre-Treatment SystemControl Logic TableRaytheon Company
St. Petersburg, Florida
PROCESS UNIT DEVICE ID DEVICE TYPE SET POINT RESPONSE (1) COMMENT
Aeration Tank Blower (B-100A/B)
VFD-B-100A/B Variable Frequency Drive PLC adjustable set point The purpose is to maintain a constant air flow rate to the aeration tank (T-300).
HS-B-00A/B HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
YI-B-100A/B Status Indicator On/Off 1. Indicates status of blower B-100A/B. A discord alarm will occur if B-100A/B is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
PI/PIT-B-100A/B Pressure transmitter PLC adjustable set point to detect pressure in the aeration tank blower discharge lines
Low pressure response:1. Shut down power to blower B-100A/B.2. Notify Operator.3. Flashing strobe light.High pressure response:1. Shut down power to blower B-100A/B.2. Notify Operator.3. Flashing strobe light.
Low pressure may indicate leakage and high pressure indicates piping may be plugged.
HS-700 HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
P-700 operation will be dependant upon pH in the aeration tank (T-300) influent line.
YI-700 Status Indicator On/Off 1. Indicates status of P-700. A discord alarm will occur if P-700 is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
LS-400 Level Switch 1. 114 inches - high / high level Alarm - Notify Operator.
Shut down AOP pre-treatment system components downstream of EQ tanks T-200A/B/C (3). LE/LT-400 Level Transmitter 1. 12 inches - low level
2. 20 inches - low level3. 64 inches - operating level4. 100 inches - high level5. 108 inches - high / high level
1. Alarm - Notify Operator; Disable operation of filter feed pumps (P-300A/B). 2. Notify Operator of low level. 3. PLC controls P-300A/B pump speed to maintain specified water level in tank.4. Alarm - Notify Operator.5. Critical alarm - Notify Operator; Disable operation of aeration tank feed pumps (P-200A/B).
HS-300A/B HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
YI-300A/B Status Indicator On/Off 1. Indicates status of P-300A/B. A discord alarm will occur if P-300A/B is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
PI/PIT-300A/B Pressure transmitter PLC adjustable set point to detect pressure in the filter feed pump discharge line.
Low pressure response (<10 psi): (1) shut down power to Pumps P-300A/B, Notify Operator, flashing strobeMid-Pressure response (40-50 psi): (1) Notify OperatorHigh pressure response (>50 psi): (1) Shut down power to pumps P-300A/B, (2) Notify operator, (3) flashing strobe light
Low pressure may indicate leakage and high pressure indicates piping may be plugged.
VFD-300C Variable Frequency Drive PLC adjustable set point. The purpose is to maintain a constant backwash flow rate through the multi-media filters (T-500A/B/C).
HS-300C HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
Pump operation shall be tied to differential pressure switches (DPI-500). Run permissive based on level in filter feed tank (T-300) and backwash tank (T-800). Do not operate if P-300A/B is engaged.
YI-300C Status Indicator On/Off 1. Indicates status of P-300C. A discord alarm will occur if P-300C is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
Backwash Pump (P-300C)
Sodium Hydroxide Metering Pump (P-700)
Filter Feed Pumps (P-300A/B)
Treatment System - Figure J-6Filter Feed Tank (T-400)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #16\Tables J-5 and J-6_Control Logic.xlsx Page 3 of 6 ARCADIS
Table J-5Modified ISR System
AOP Pre-Treatment SystemControl Logic TableRaytheon Company
St. Petersburg, Florida
PROCESS UNIT DEVICE ID DEVICE TYPE SET POINT RESPONSE (1) COMMENT
PI/PIT-500A/B/C;DPI-500
Pressure Transmitter, Differential Pressure Indicator
PLC adjustable set point to detect pressure in the multi-media filter piping.
High pressure response (>20 psi): Notify Operator, warning.High-High Pressure response (>50 psi): (1) Notify Operator, backwash required.
The purpose is to notify the operator when backwash may be required.
LS-800 Level Switch 1. 114 inches - high / high level Alarm - Notify Operator.Shut down backwash pump (P-300C)
LE/LT-800 Level Transmitter 1. display/record tank water level 2. 102 inches - high level3. 108 inches - high / high level
1. 4-20 mA signal sent to PLC to display/record tank water level. 2. Alarm - Notify Operator.3. Critical alarm - Notify Operator; Disable operation of backwash pump (P-300C) and polymer metering pump (P-500).
HS-600 HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
P-600 shall operate based on water level in the backwash tank (T-800) and filter feed tank (T-400).
YI-600 Status Indicator On/Off 1. Indicates status of P-600. A discord alarm will occur if P-600 is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
HS-500 HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
Pump operation will be dependant upon backwash cycle operation. Pump will only operate when backwash pump (P-300C) operates.
YI-500 Status Indicator On/Off 1. Indicates status of P-500. A discord alarm will occur if P-500 is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
HS-100 HOA selector switch 1. Hand2. Auto3. Off
1. The compressor shall operate regardless of the status of alarms and interlocks.2. The compressor shall be subject to control devices, interlocks and alarms.3. The compressor shall not operate.
YI-100 Status Indicator On/Off 1. Indicates status of A-100. A discord alarm will occur if A-100 is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
KV-100 Timer Valve Manual set point Drain valve on air receiver tank will open or close depending on a set timer.PI/PIT-A100 Pressure transmitter 70 psi Low pressure response (<10 psi): (1) Notify Operator. Low pressure may indicate leakage and high pressure indicates
piping may be plugged.
Air Stripper(T-600A/B)
PI/PIT-600A/B Pressure transmitter PLC adjustable set point. Low pressure response:1. Shut down power to pumps P-300A/B and blowers B-200A/B.2. Notify Operator.3. Flashing strobe light.High pressure response:1. Shut down power to pumps P-300A/B and blowers B-200A/B.2. Notify Operator.3. Flashing strobe light.
The purpose is to optimize operation of the air stripper. Low pressure may indicate leakage and high pressure indicates piping may be plugged.
VFD-B-200A/B Variable Frequency Drive PLC adjustable set point. The purpose is to maintain a constant air flow rate to the air strippers (T-600A/B).
HS-B-200A/B HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
YI-B-200A/B Status Indicator On/Off 1. Indicates status of B-200A/B. A discord alarm will occur if B-200A/B is engaged to run and the return input from the auxiliary contact is not made.2. Notify operator
NOTE: not all valving for the Multi-media filter is shown on the PID. Valving will be controlled by a PLC that is part of the MMF system. Full control logic and valve sequencing for backwashing is not
presented within this control logic table.
Decant Pump (P-600)
Backwash Tank (T-800)
Multi-Media Filters (T-500A/B/C)
Treatment System - Figure J-7
Polymer Metering Pump (P-500)
Air Compressor (AC-100)
Air Stripper Blower (B-200A/B)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #16\Tables J-5 and J-6_Control Logic.xlsx Page 4 of 6 ARCADIS
Table J-5Modified ISR System
AOP Pre-Treatment SystemControl Logic TableRaytheon Company
St. Petersburg, Florida
PROCESS UNIT DEVICE ID DEVICE TYPE SET POINT RESPONSE (1) COMMENT
VFD-B-300 Variable Frequency Drive PLC adjustable set point. The purpose is to maintain a constant air flow rate to the air strippers (T-600A/B).
HS-B-300 HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
YI-B-300 Status Indicator On/Off 1. Indicates status of B-200A/B. A discord alarm will occur if B-200A/B is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
PI/PIT-B-300 Pressure transmitter PLC adjustable set point. Low pressure response:1. Shut down power to blower B-300.2. Notify Operator.3. Flashing strobe light.High pressure response:1. Shut down power to blower B-300.2. Notify Operator.3. Flashing strobe light.
Low pressure may indicate leakage and high pressure indicates piping may be plugged.
PI/PCV-100 On/Off Manual set point. PCV-100 opens or closes depending on the pressure in the line. The PLC will modulate valve PCV-100 to maintain a consistent pressure at PIT-600C. The purpose is to control the pressure in the vapor discharge line to achieve a consistent flow rate from the airstripper blower (B-200A/B) and the vent blower (B-300).
PI/PIT-600C Pressure transmitter PLC adjustable set point Pressure data will be transferred to PLC, and the PLC will modulate valve PCV-100 to maintain a constant pressure at PIT-600C Low pressure response:1. Notify Operator.High pressure response:1. Shut down power to Pumps P-300A/B/C and Blower B-200A/B 2. Notify Operator. 3. Flashing strobe light.
Low pressure may indicate leakage and high pressure indicates piping may be plugged.
PI/PIT-600D Pressure transmitter PLC adjustable set point. Record/transmit pressure data to PLC
LS-700 Level Switch 1. 38 inches - high / high level Alarm - Notify Operator.
Shut down AOP pre-treatment system components downstream of EQ tanks T-200A/B/C (3). LE/LT-700 Level Transmitter 1. 10 inches - low level
2. 14 inches3. 24 inches - operating level4. 28 inches - high level5. 32 inches - high / high level
1. Alarm - Notify Operator; Disable operation of air stripper discharge pumps (P-400A/B).2. Alarm - low level: Notify Operator. 3. PLC controls P-400A/B pump speed to maintain specified water level in tank.4. Alarm - high level - Notify Operator.5. Critical alarm - Notify Operator; Disable operation of filter feed pumps (P-300A/B).
VFD-400A/B Variable Frequency Drive PLC adjustable set point. The purpose is to maintain a constant water level in the air stripper discharge tank (T-700). Tank level data will be monitored and transmitted to PLC by LE/LT-700.
HS-400A/B HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
YI-400A/B Status Indicator On/Off 1. Indicates status of P-400A/B. A discord alarm will occur if P-400A/B is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
FE/FIT-400 Totalizing flow meter with indicating transmitter
NA 4-20mA signal sent to PLC, PLC to calculate flow rate and track totalizer reading.
PI/PIT-400 Pressure transmitter PLC adjustable set point to monitor pressure in pipeline between AOP pre-treatment system and AOP treatment system.
Low pressure response:1. Shut down power to Pumps P-400A/B.2. Notify Operator.3. Flashing strobe light.High pressure response:1. Shut down power to Pumps P-400A/B.2. Notify Operator.3. Flashing strobe light.
Low pressure may indicate leakage and high pressure indicates piping may be plugged.
Air Stripper Discharge Tank(T-700)
Vapor Discharge Line
AOP Pre-Treatment System Effluent Line
Air Stripper Discharge Pumps (P-400A/B)
Tank Vent Blower (B-300)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #16\Tables J-5 and J-6_Control Logic.xlsx Page 5 of 6 ARCADIS
Table J-5Modified ISR System
AOP Pre-Treatment SystemControl Logic TableRaytheon Company
St. Petersburg, Florida
PROCESS UNIT DEVICE ID DEVICE TYPE SET POINT RESPONSE (1) COMMENT
LS-800A Level switch 1. 6 inches - low level 2. 18 inches - high level
1. Low level response - Sump Pump (P-800) will turn off.2. High level response - Sump Pump (P-800) will turn on.
HS-800A HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
YI-800A Status Indicator On/Off 1. Indicates status of P-800. A discord alarm will occur if P-800 is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
Containment Area Leak Sensor
LS-800B Level switch 1. 2 inches - high level 1. Indicates leak in treatment area. AOP pre-treatment system shut down (2). Critical Alarm - Notify Operator.
Footnotes: (1) All analog values (level, flow, pressure, etc.) shall be recorded for the purpose of historical trending and data analysis. (2) AOP pre-treatment system shut down - if AOP pre-treatment system shutdown is identified as response, the following will occur: a. All motors will be de-energized b. Flow valves FV-200A/B/C will fail closed c. Audible alarm will sound in the plant area and in the plant office d. A red stack light in the plant will illuminate e. The operator will be notified via cell phone text message (3) AOP pre-treatment system components will be shut down downstream of the EQ Tanks T-200A/B/C. Response is the same as (2) above. AOP - Advanced Oxidation Process EQ - Equalization NA - Not Applicable PLC - Programmable Logic Controller VFD - Variable Frequency Drive
Sump Pump (P-800)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #16\Tables J-5 and J-6_Control Logic.xlsx Page 6 of 6 ARCADIS
Table J-6Modified ISR System
AOP Treatment SystemControl Logic TableRaytheon Company
St. Petersburg, Florida
PROCESS UNIT DEVICE ID DEVICE TYPE SET POINT RESPONSE (2) COMMENT
FE/FIT-XXX Totalizing flow meter with indicating transmitter
NA 4-20mA signal sent to PLC, PLC to calculate flow rate and track totalizer reading.
PIT-XXXA Pressure Transmitter (water level in well)
PLC adjustable set point Display and track water level within the recovery well:1. Recovery pump speed may be controlled by PLC to maintain select water level within the well.
The purpose is to optimize operation of the recovery well pumps.
PIT-XXX Pressure Transmitter (recovery piping line pressure)
PLC adjustable set point Low pressure response:1. Shut down power to Pumps P-XXX.2. Notify Operator.High pressure response:1. Shut down power to Pumps P-XXX.2. Notify Operator.
The purpose is to optimize operation of the recovery well pumps. Low pressure may indicate leakage and high pressure indicates the pump and/or piping may be plugged.
LS-XXX Level Switch (water level in the recovery well vault
1. 2 inches - high level High level response:1. Stop Extraction Well Pumps P-XXXX.2. Notify Operator.
VFD-XXX Variable Frequency Drive PLC adjustable set point The pump VFD may be controlled to maintain a select water level within the well.
HS-XXX HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
YI-XXX Status Indicator On/Off 1. Indicates status of P-XXX. A discord alarm will occur if P-XXX is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
LS-1300 Level Switch 1. 122 inches - high / high level Alarm - Notify Operator.
AOP treatment system shut down (2). Critical alarm - disable transfer of pre-treated groundwater from the AOP pre-treatment system.
LE/LT-1300 Level Transmitter 1. 24 inches - low / low level 2. 30 inches - low level3. 80 inches - operating level4. 100 inches - high level5. 112 inches - high / high level
1. Alarm - Notify Operator; Disable operation of AOP feed pump (P-1000). 2. Alarm - Notify Operator - low level warning.3. PLC controls AOP feed pump (P-1000) speed to maintain specified water level in tank.4. Alarm - Notify Operator - high level warning.5. Critical alarm - disable operation of recovery well pumps.
FV-1300 Flow Valve On/Off Flow Valve FV-1300 opens or closes depending on the control device and alarms it is subject to. FV-1300 shall fail closed in the event of AOP treatment system shut down.
The purpose is to control the flow of compressed air to the pneumatic actuated valves associated with EQ tank operation.
LS-1500 Level Switch 1. 122 inches - high / high level Alarm - Notify Operator.
Treatment system shut down (2). Critical alarm - disable operation of recovery well extraction pumps.
LE/LT-1500 Level Transmitter 1. 24 inches - low / low level 2. 30 inches - low level3. 80 inches - operating level4. 100 inches - high level5. 112 inches - high / high level
1. Alarm - Notify Operator; Disable operation of AOP feed pump (P-1000). 2. Alarm - Notify operator - low level warning.3. PLC controls AOP feed pump (P-1000) speed to maintain specified water level in tank.4. Alarm - Notify Operator - high level warning.5. Critical alarm - disable operation of recovery well pumps.
FV-1500 Flow Valve On/Off Flow Valve FV-1500 opens or closes depending on the control device and alarms it is subject to. FV-1500 shall fail closed in the event of AOP treatment system shut down.
The purpose is to control the flow of compressed air to the pneumatic actuated valves associated with EQ tank operation.
HS-1000 HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
VFD-1000 Variable Frequency Drive PLC adjustable set point The purpose is to maintain a constant water level in the heat exchanger feed tank (T-100). Tank level data will be monitored and transmitted to PLC by LE/LT-100.
PLC programmable timer.
YI-1000 Status Indicator On/Off 1. Indicates status of P-110A/B. A discord alarm will occur if P-110A or P-110B is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
PI/PIT-1000 Pressure transmitter PLC adjustable set point to detect pressure in the AOP feed pump discharge line.
Low pressure response:1. Shut down power to Pumps P-1000.2. Notify Operator.3. Flashing strobe light.High pressure response:1. Shut down power to Pumps P-1000.2. Notify Operator.3. Flashing strobe light.
Low pressure may indicate leakage and high pressure indicates piping may be plugged.
Treatment System - Figure J-8
AOP Feed Pump(P-1000)
Recovery Wells(Each Well)
Recovery Well Pumps (P-XXX)
Influent EQ Tank (T-1500)
Influent Equalization (EQ) Tank (T-1300)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #16\Tables J-5 and J-6_Control Logic.xlsx Page 1 of 3 ARCADIS
Table J-6Modified ISR System
AOP Treatment SystemControl Logic TableRaytheon Company
St. Petersburg, Florida
PROCESS UNIT DEVICE ID DEVICE TYPE SET POINT RESPONSE (2) COMMENT
LS-1500A Level switch 1. 6 inches - low level 2. 18 inches - high level
1. Low level response - Sump Pump (P-1500) will turn off.2. High level response - Sump Pump (P-1500) will turn on.
HS-1500A HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
YI-1500A Status Indicator On/Off 1. Indicates status of P-1500. A discord alarm will occur if P-1500 is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
LS-1500B Level switch 1. 2 inches - low level 1. Indicates potential leak within treatment system or build-up of rainwater in the containment area. Notify Operator.
LS-1500C Level switch 1. 6 inches - high level 1. Indicates potential leak within treatment system or build-up of rainwater in the containment area. AOP treatment system shut down (2). Critical Alarm - Notify Operator.
LS-1400 Level Switch 1. 114 inches - high / high level Alarm - Notify Operator.
AOP treatment system shut down (2). LE/LT-1400 Level Transmitter 1. 12 inches - low level
2. 18 inches - low level3. 64 inches - operating level4. 100 inches - high level5. 108 inches - high / high level
1. Alarm - Notify Operator; Disable operation of filter feed pumps (P-1100A/B). 2. Alarm - Notify Operator - low level warning.3. PLC controls filter feed pumps (P-1100A/B) speed to maintain specified water level in tank.4. Alarm - Notify Operator - high level warning.5. Critical alarm - disable operation of AOP-100.
LS-1600 Level Switch 1. 122 inches - high / high level Alarm - Notify Operator.
AOP treatment system shut down (2). LE/LT-1600 Level Transmitter 1. 12 inches - low level
2. 18 inches - low level3. 64 inches - operating level4. 100 inches - high level5. 108 inches - high / high level
1. Alarm - Notify Operator; Disable operation of filter feed pumps (P-1100A/B). 2. Alarm - Notify Operator - low level warning.3. PLC controls filter feed pumps (P-1100A/B) speed to maintain specified water level in tank.4. Alarm - Notify Operator - high level warning.5. Critical alarm - disable operation of AOP-100.
HS-1100A/B HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
VFD-1100A/B Variable Frequency Drive PLC adjustable set point The purpose is to maintain a constant water level in the filter feed tanks (T-1400 and T-1600). Tank level data will be monitored and transmitted to PLC by LE/LT-1400 and LE/LT-1600.
YI-1100A/B Status Indicator On/Off 1. Indicates status of P-110A/B. A discord alarm will occur if P-110A or P-110B is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
PI/PIT-1100A/B Pressure transmitter PLC adjustable set point to detect pressure in the aeration tank feed pump discharge line.
Low pressure response (<10 psi): (1) shut down power to Pumps P-1100A/B, Notify Operator, flashing strobe.Mid-Pressure response (40-50 psi): (1) Notify Operator.High pressure response (>50 psi): (1) Shut down power to pumps P-1100A/B, (2) Notify operator, (3) flashing strobe light.
Low pressure may indicate leakage and high pressure indicates piping may be plugged.
VFD-1200 Variable Frequency Drive PLC adjustable set point The purpose is to maintain a constant backwash flow rate through the catalytic and multi-media filters.
HS-1200 HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
Pump operation shall be tied to differential pressure switches (DPI-1700 and DPI-1800). Run permissive based on level in filter feed tanks (T-1400 and T-1600) and backwash tank (T-2000). Do not operate if P-1100A/B is engaged.
YI-1200 Status Indicator On/Off 1. Indicates status of P-1200. A discord alarm will occur if P-1200 is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
PI/PIT-1700A/B/C;DPI-1700
Pressure Transmitter, Differential Pressure Indicator
PLC adjustable set point to detect pressure in the catalytic media filter piping.
High pressure response (>20 psi): Notify Operator, warning.High-High Pressure response (>50 psi): (1) Notify Operator, backwash required.
The purpose is to notify the operator when backwash may be required.
HS-200 HOA selector switch 1. Hand2. Auto3. Off
1. The compressor shall operate regardless of the status of alarms and interlocks.2. The compressor shall be subject to control devices, interlocks and alarms.3. The compressor shall not operate.
YI-200 Status Indicator On/Off 1. Indicates status of A-200. A discord alarm will occur if A-200 is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
KV-200 Timer Valve Manual set point Drain valve on air receiver tank will open or close depending on a set timer.PI/PIT-A100 Pressure transmitter 70 psi Low pressure response (<10 psi): (1) Notify operator. Low pressure may indicate leakage and high pressure indicates
piping may be plugged.
Air Compressor (A-200)
Treatment System - Figure J-9Filter Feed Tank (T-1400)
Catalytic Media Filters (T-1700A/B/C)
Filter Feed Pumps (P-1100A/B)
Filter Feed Tank (T-1600)
Backwash Pump (P-1200)
NOTE: not all valving for the Multi-media filter is shown on the PID. Valving will be controlled by a PLC that is part of the MMF system. Full control logic and valve sequencing for backwashing is not
presented within this control logic table.
Containment Area Leak Sensors
Sump Pump (P-1500)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #16\Tables J-5 and J-6_Control Logic.xlsx Page 2 of 3 ARCADIS
Table J-6Modified ISR System
AOP Treatment SystemControl Logic TableRaytheon Company
St. Petersburg, Florida
PROCESS UNIT DEVICE ID DEVICE TYPE SET POINT RESPONSE (2) COMMENT
PI/PIT-1800A/B;DPI-1800
Pressure Transmitter, Differential Pressure Indicator
PLC adjustable set point to detect pressure in the multi-media filter piping.
High pressure response (>20 psi): Notify Operator, warning.High-High Pressure response (>50 psi): (1) Notify Operator, backwash required.
The purpose is to notify the operator when backwash may be required.
GAC Vessels (F-1900A/B/C)
PIT-1900A/B/C;DPI-1900
Pressure Transmitter, Differential Pressure Indicator
PLC adjustable set point to detect pressure at the inlet and outlet of the GAC vessels
High pressure response (>20 psi): Notify Operator, warning.High-High Pressure response (>50 psi): (1) Notify Operator, backwash required.
The purpose is to notify the operator when backwash may be required.
FE/FIT-700 Totalizing flow meter with indicating transmitter
1. Flow monitoring data as required by City POTW permit. 2. Flow = 95 - 100 gpm (high flow alarm) 3. Flow > 100gpm (high flow alarm)
1. Data transmitted and recorded by PLC as required by City POTW permit. 2. Notify Operator - high flow warning.
3. Shutdown of AOP Treatment System (2) .
AE/AIT-700 pH Sensor 1. pH monitoring data as required by City POTW permit. 2. pH < 5.5 (low pH alarm) 3. pH = 5.5 - 6.0 (low pH warning) 4. pH = 9 - 11 (high pH warning) 5. pH >11.0 (high pH alarm)
1. Data transmitted and recorded by PLC as required by City POTW permit.
2. Shutdown of AOP Treatment System (2) . 3. Notify Operator. 4. Notify Operator.
5. Shutdown AOP Treatment System (2) .
LS-2000 Level Switch 1. 122 inches - high / high level Alarm - Notify Operator.
AOP treatment system shut down (2). LE/LT-200- Level Transmitter 1. display/record tank water level
2. 102 inches - high level3. 108 inches - high / high level
1. 4-20 mA signal sent to PLC to display/record tank water level. 2. Alarm - Notify Operator.3. Critical alarm - Notify Operator; Disable operation of backwash pump (P-300C) and polymer metering pump (P-500).
HS-1300 HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
P-13 shall operate based on water level in the backwash tank (T-2000) and influent EQ tank (T-1300).
YI-1300 Status Indicator On/Off 1. Indicates status of P-1300. A discord alarm will occur if P-1300 is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
HS-1400 HOA selector switch 1. Hand2. Auto3. Off
1. The pump shall operate regardless of the status of alarms and interlocks.2. The pump shall be subject to control devices, interlocks and alarms.3. The pump shall not operate.
Pump operation will be dependant upon backwash cycle operation. Pump will only operate when backwash pump (P-1200) operates.
YI-1400 Status Indicator On/Off 1. Indicates status of P-1400. A discord alarm will occur if P-1400 is engaged to run and the return input from the auxiliary contact is not made.2. Notify Operator.
Footnotes: (1) All analog values (level, flow, pressure, etc.) shall be recorded for the purpose of historical trending and data analysis. (2) AOP treatment system shut down - if AOP treatment system shutdown is identified as response, the following will occur: a. All motors will be de-energized b. Flow valves FV-1300 and FV-1500 will fail closed c. Audible alarm will sound in the plant area and in the plant office d. A red stack light in the plant will illuminate e. The operator will be notified via cell phone text message
AOP - Advanced Oxidation Process EQ - Equalization NA - Not Applicable PLC - Programmable Logic Controller VFD - Variable Frequency Drive
Polymer Metering Pump (P-1400)
Treatment System - Figure J-10Multi-Media Filters (T-1800A/B)
Backwash Tank (T-2000)
Decant Pump (P-1300)
AOP Treatment System Effluent Piping
NOTE: not all valving for the Multi-media filter is shown on the PID. Valving will be controlled by a PLC that is part of the MMF system. Full control logic and valve sequencing for backwashing is not
presented within this control logic table.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #16\Tables J-5 and J-6_Control Logic.xlsx Page 3 of 3 ARCADIS
Tab 17
Modified ISR System – Sampling Port Locations
Table J-7Sample Port LocationsModified ISR System
Raytheon CompanySt. Petersburg, Florida
Page 1 of 2
Sample Location Purpose of SampleCompliance Sample
(Yes/No)
AOP Pre-Treatment System Influent
Composite of in-situ thermal system recovery well network - collected from the heat exchanger discharge line. Sample will be used to evaluate source recovery rates and determine concentrations of COCs in the AOP pre-treatment system influent.
Yes
Aeration Tank EffluentSample will be used to evaluate performance of the aeration tank and verify oxidation of dissolved iron in the groundwater.
No
Multi-Media Filter EffluentMulti-media effluent - sample will be used to determine filter efficiency to remove particles and optimize backwash frequency.
No
Air Stripper EffluentAir stripper effluent - sample will be used to assess the performance of the air stripper unit and determine concentrations of COCs in the AOP treatment system influent.
No
VPGAC Effluent
Passive venting from the AOP treatment system influent equalization tanks will be monitored with an organic vapor analyzer. Samples will be used to demonstrate air emissions compliance and estimate the time required for COC break-through of the carbon unit.
Yes
AOP-100 IntermediateSample will be used to evaluate performance of the AOP unit, and
verify and update destruction curve/ model for the HiPOxTM system.No
AOP-100 Effluent
AOP effluent - sample will be used to assess the performance of the AOP unit and update destruction curve/model generated for the
HiPOxTM system. Results will be used to determine influent solids loading to the catalytic media filters.
No
AOP Pre-Treatment System
AOP Treatment System
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #17\Tab J-7 - Sample Port Locations.xlsx ARCADIS
Table J-7Sample Port LocationsModified ISR System
Raytheon CompanySt. Petersburg, Florida
Page 2 of 2
Catalytic Media Filter Effluent
Catalytic media effluent - sample will be used to determine filter efficiency to remove/oxidized iron and other particles. Results will be used to optimize backwash frequency, and determine the influent solids loading for the multi-media filter.
No
Multi-Media Filter EffluentMulti-media effluent - sample will be used to determine filter efficiency to remove particles that may break through the catalytic media filter, and optimize backwash frequency.
No
Primary LPGAC Vessel Effluent
Effluent of the lead carbon vessel - sample will be used to determine the time and volume of water required for COC break-through, and optimize the LPGAC change out frequency.
No
Secondary LPGAC Vessel Effluent(Treated Water Discharge - POTW)
Effluent of the lag carbon vessel - sample will be used to show compliance with the City IWD Permit.
Yes
Settled SolidsSolids sample will be collected from the backwash tank prior to off-site disposal. Sample will be representative of settled solids and will be used to develop a waste profile for off-site disposal of generated solids.
Yes
Footnotes:VPGAC - Vapor-Phase Granular Activated CarbonAOP - Advanced Oxidation ProcessLPGAC - Liquid Phase Granular Activated Carbon
POTW - Publicly Owned Treatment WorksCOC - Constituents of Concern
IWD - Industrial Wastewater Discharge
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #17\Tab J-7 - Sample Port Locations.xlsx ARCADIS
Tab 18
Modified ISR System – Air Emission Calculations
Page 1 of 2
Calc prepared by: M. SeppanenChecked by: J. Darby
Date: 1/17/10
Determine emissions from air stripper exhaust using the following equations:
Emissions = Cremoved * QW gpm * 3.79 L/gal * 1 g/106 g * 1 lb/454.5 g * 1440 min/day
Cout = Cin * Air Stripper Removal Efficiency
Cremoved = Cin - Cout
Where: Cin = Concentration of contaminant in the liquid (mg/L)
Cout = Concentration of contaminant in the liquid effluent of the air stripper (mg/L)
Cremoved = Concentration of contaminant removed from the liquid and transferred to the
vapor phase (mg/L)QW = Liquid flow rate = 60 gpm
QA = Air flow rate = 900 SCFM
Conversions:lbs/day to mg/m3 = mg/m3 = lbs/day * (453,600 mg/lbs) * (1/Q minutes/ft3) * (1 day/1440 minutes) * (35.3 ft3/m3)
ppmv = (mg/m3)*(273.15 + °C) / (12.187)(MW)
ppmv = ppm by volume mg/m3 = milligrams of gaseous pollutant per cubic meter of ambient air
MW = molecular weight of the gaseous pollutant°C = ambient air temperature in degrees Centigrade
Notes:1 The design maximum groundwater concentrations from the In-situ Thermal System were used to estimate off-gas emissions.2 Concentrations determined using QED air stripper model EZ-Tray 16.6, modeled at an air:water ratio of 110:1, water temperature of 72 F, assume 4 trays.
Raytheon CompanySt. Petersburg, Florida
Calculation of Off-Gas Emissions from Air StripperModified ISR System
AOP Pre-treatment System
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #18\(1) Air Stripper Emissions.xlsx ARCADIS
Page 2 of 2
Volatile Organic Compounds
Design Maximum Concentration from
Heating System 1 (g/L)
Air Stripper Removal
Efficiency 2
(%)
Cremoved
(g/L)
Cout
(g/L)
Unabated Emissions
(lb/day)
Vapor Concentration
(mg/m3) MW
Vapor Concentration
(ppmv)Chemicals of Concern1,1,1-Trichloroethane 4,310 99.99% 4,310 0.43 3.11E+00 38.4 133.4 7.01,1-Dichloroethene 13,789 99.99% 13,788 1.38 9.93E+00 122.7 96.9 30.6cis-1,2-Dichloroethene 12,174 99.99% 12,172 1.22 8.77E+00 108.4 96.9 27.1Vinyl chloride 4,997 99.99% 4,997 0.50 3.60E+00 44.5 62.5 17.2Trichloroethene 44,178 99.99% 44,173 4.42 3.18E+01 393.2 131.4 72.41,1-Dichloroethane 6,318 99.99% 6,317 0.63 4.55E+00 56.2 99.0 13.81,4-Dioxane 15,767 0.00% 0.0 15,767 0.00E+00 0.0 88.1 0.0
Other Compounds1,1,2-Trichloroethane 493 99.51% 491 2.4 3.54E-01 4.4 133.4 0.81,2,4-Trimethylbenzene 609 99.99% 609 0.06 4.39E-01 5.4 120.2 1.11,2-Dichloroethane 992 99.79% 989 2.08 7.13E-01 8.8 99.0 2.21,3,5-Trimethylbenzene 1,101 99.99% 1,101 0.11 7.93E-01 9.8 120.2 2.02-Butanone (MEK) 9,340 20.25% 1,891 7,449 1.36E+00 16.8 72.1 5.74-Methyl-2-pentanone (MIBK) 6,107 90.44% 5,523 584 3.98E+00 49.2 100.2 11.9Acetone 15,175 15.68% 2,379 12,795 1.71E+00 21.2 58.1 8.8Benzene 569 99.99% 568 0.06 4.10E-01 5.1 78.1 1.6Carbon Disulfide 701 99.99% 701 0.1 5.05E-01 6.2 76.1 2.0Chloroethane 496 99.99% 496 0.05 3.57E-01 4.4 64.5 1.7Chloroform 12,973 99.99% 12,971 1.30 9.35E+00 115.5 119.4 23.4Ethylbenzene 300 99.99% 300 0.03 2.16E-01 2.7 106.2 0.6Isopropylbenzene 472 99.99% 472 0.05 3.40E-01 4.2 120.2 0.8m,p-Xylene 426 99.99% 426 0.04 3.07E-01 3.8 106.2 0.9Methylene chloride 13,043 99.97% 13,039 3.91 9.39E+00 116.1 84.9 33.1Naphthalene 153 95.69% 147 6.61 1.06E-01 1.3 128.2 0.2o-Xylene 254 99.99% 254 0.03 1.83E-01 2.3 106.2 0.5Tetrachloroethene 1,514 99.99% 1,514 0.15 1.09E+00 13.5 165.8 2.0Toluene 5,607 99.99% 5,607 0.56 4.04E+00 49.9 92.1 13.1trans-1,2-Dichloroethene 111 99.99% 111 0.01 7.96E-02 1.0 96.9 0.2Trichlorofluoromethane 590 99.99% 590 0.06 4.25E-01 5.2 137.4 0.9
Total Air Emissions 9.79E+01 281
Total Emissions = 97.94 lbs/day
Allowable Emissions = 13.7
Allowable Emissions Exceeded = Yes
lbs/day
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #18\(1) Air Stripper Emissions.xlsx ARCADIS
Page 1 of 2
Calc prepared by: M. SeppanenChecked by: J. Darby
Date: 1/17/10
Determine emissions from aeration tank using the following equations:
Emissions = Cremoved * QW gpm * 3.79 L/gal * 1 g/106 g * 1 lb/454.5 g * 1440 min/day
Cout = Cin * Aeration Tank Removal Efficiency
Cremoved = Cin - Cout
Where: Cin = Concentration of contaminant in the liquid (mg/L)
Cout = Concentration of contaminant in the liquid effluent of the aeration tank (mg/L)
Cremoved = Concentration of contaminant removed from the liquid and transferred to the
vapor phase (mg/L)QW = Liquid flow rate = 60 gpm
QA = Air flow rate = 40 SCFM
Conversions:lbs/day to mg/m3 = mg/m3 = lbs/day * (453,600 mg/lbs) * (1/Q minutes/ft3) * (1 day/1440 minutes) * (35.3 ft3/m3)
ppmv = (mg/m3)*(273.15 + °C) / (12.187)(MW)
ppmv = ppm by volume mg/m3 = milligrams of gaseous pollutant per cubic meter of ambient air
MW = molecular weight of the gaseous pollutant°C = ambient air temperature in degrees Centigrade
Notes:1 The design maximum groundwater concentrations from the In-situ Thermal System were used to estimate off-gas emissions.2 Concentrations determined using QED air stripper model EZ-Tray 16.6, modeled at an air:water ratio of 110:1, water temperature of 72 F, assume 4 trays.
Raytheon CompanySt. Petersburg, Florida
Calculation of Off-Gas Emissions from Aeration Tank (T-300)Modified ISR System
AOP Pre-treatment System
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #18\(2) Aeration Tank Emissions.xlsx ARCADIS
Page 2 of 2
Volatile Organic Compounds
Design Maximum Concentration from
Heating System 1 (g/L)
Aeration Tank
Removal
Efficiency 2
(%)
Cremoved
(g/L) Cout (g/L)
Unabated Emissions
(lb/day)
Vapor Concentration
(mg/m3) MW
Vapor Concentration
(ppmv)
Chemicals of Concern1,1,1-Trichloroethane 4,310 10.00% 431 3,879.30 3.11E-01 86.3 133.4 15.71,1-Dichloroethene 13,789 10.00% 1,379 12,410.36 9.93E-01 276.2 96.9 69.0cis-1,2-Dichloroethene 12,174 10.00% 1,217 10,956.25 8.77E-01 243.8 96.9 60.9Vinyl chloride 4,997 10.00% 500 4,497.53 3.60E-01 100.1 62.5 38.8Trichloroethene 44,178 10.00% 4,418 39,760.08 3.18E+00 884.8 131.4 163.01,1-Dichloroethane 6,318 10.00% 632 5,686.26 4.55E-01 126.5 99.0 31.01,4-Dioxane 15,767 0.00% 0.0 15,767 0.00E+00 0.0 88.1 0.0
Other Compounds1,1,2-Trichloroethane 493 10.00% 49 444.0 3.55E-02 9.9 133.4 1.81,2,4-Trimethylbenzene 609 10.00% 61 548.46 4.39E-02 12.2 120.2 2.51,2-Dichloroethane 992 10.00% 99 892.40 7.14E-02 19.9 99.0 4.91,3,5-Trimethylbenzene 1,101 10.00% 110 990.77 7.93E-02 22.0 120.2 4.42-Butanone (MEK) 9,340 5.00% 467 8,873 3.36E-01 93.5 72.1 31.44-Methyl-2-pentanone (MIBK) 6,107 5.00% 305 5,801 2.20E-01 61.2 100.2 14.8Acetone 15,175 2.00% 303 14,871 2.19E-01 60.8 58.1 25.3Benzene 569 10.00% 57 511.66 4.10E-02 11.4 78.1 3.5Carbon Disulfide 701 10.00% 70 631.3 5.05E-02 14.0 76.1 4.5Chloroethane 496 10.00% 50 446.52 3.57E-02 9.9 64.5 3.7Chloroform 12,973 10.00% 1,297 11,675.29 9.35E-01 259.8 119.4 52.7Ethylbenzene 300 10.00% 30 270.39 2.16E-02 6.0 106.2 1.4Isopropylbenzene 472 10.00% 47 424.62 3.40E-02 9.4 120.2 1.9m,p-Xylene 426 10.00% 43 383.56 3.07E-02 8.5 106.2 1.9Methylene chloride 13,043 10.00% 1,304 11,739.05 9.40E-01 261.2 84.9 74.5Naphthalene 153 10.00% 15 138.00 1.10E-02 3.1 128.2 0.6o-Xylene 254 10.00% 25 228.67 1.83E-02 5.1 106.2 1.2Tetrachloroethene 1,514 10.00% 151 1,362.31 1.09E-01 30.3 165.8 4.4Toluene 5,607 10.00% 561 5,046.66 4.04E-01 112.3 92.1 29.5trans-1,2-Dichloroethene 111 10.00% 11 99.48 7.96E-03 2.2 96.9 0.6Trichlorofluoromethane 590 10.00% 59 530.77 4.25E-02 11.8 137.4 2.1
Total Air Emissions 9.87E+00 646
Total Emissions = 9.87 lbs/day
Allowable Emissions = 13.7 lbs/day
Allowable Emissions Exceeded = No
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #18\(2) Aeration Tank Emissions.xlsx ARCADIS
Tab 19
Modified ISR System – Electrical Load Calculation
Page 1 of 1
Calc prepared by: J. DarbyCalc checked by: A. CardosoDate: 2/24/10
AOP Pre-Treatment SystemEquipment Name Tag HP Voltage AMP KVA kW1
Heat Exchanger Feed Pump 1 P-100A 3 460 4.8 2.21 3.06Heat Exchanger Feed Pump 2 P-100B 3 460 4.8 2.21 3.06Aeration Tank Feed Pump 1 P-200A 1.5 460 2.6 1.20 1.66Aeration Tank Feed Pump 2 P-200B 1.5 460 2.6 1.20 1.66Recirculation Pump P-200C 2 460 3.4 1.56 2.16Filter Feed Pump 1 P-300A 7.5 460 11.0 5.06 7.00Filter Feed Pump 2 P-300B 7.5 460 11.0 5.06 7.00Backwash Feed Pump P-300C 7.5 460 11.0 5.06 7.00Air Stripper Feed Pump 1 P-400A 3 460 4.8 2.21 3.06Air Stripper Feed Pump 2 P-400B 3 460 4.8 2.21 3.06Polymer Feed Pump P-500 0.25 115 5.8 0.67 0.67Decant Pump P-600 0.5 115 9.8 1.13 1.13Sodium Hydroxide Feed Pump P-700 0.25 115 5.8 0.67 0.67Aeration Blower 1 B-100 3 460 4.8 2.21 3.06Aeration Blower 2 B-100 3 460 4.8 2.21 3.06Air Stripper Blower 1 B-200A 10 460 14.0 6.44 8.91Air Stripper Blower 2 B-200B 10 460 14.0 6.44 8.91Tank Vent Blower B-300 0.5 460 1.0 0.46 0.64Air Compressor A-100 2 460 3.4 1.56 2.16Misc Load MISC NA 115 130.4 15.00 12.00
Total KVA = 64.75AMP at 460V Service = 140.76
Amp. Service (125% Round UP) = 180.0Maximum kW = 79.9
Average kW2 = 41.7AOP Treatment SystemEquipment Name Tag HP Voltage AMP KVA kW1
AOP Feed Pump (Existing) P-1000 2 230 6.8 1.56 2.16Filter Feed Pump 1 P-1100A 15 460 21.0 9.66 13.37Filter Feed Pump 2 P-1100B 15 460 21.0 9.66 13.37Backwash Feed Pump P-1200 15 460 21.0 9.66 13.37Polymer Feed Pump P-1400 0.25 115 5.8 0.67 0.92Decant Pump P-1300 0.5 115 9.8 1.13 1.56Sump Pump (Existing) P-1500 1 115 16.0 1.84 2.55Extraction Pump RW-2 RW-2 1 230 3.6 0.83 1.15Extraction Pump RW-3 RW-3 1 230 3.6 0.83 1.15Extraction Pump RW-4 RW-4 1 230 3.6 0.83 1.15Extraction Pump RW-5 RW-5 1 230 3.6 0.83 1.15Air Compressor 1 A-100 15 460 21.0 9.66 13.37Misc Load MISC NA 115 130.4 15.00 12.00AOP-100 System 3 AOP-100 NA 230 28.3 6.50 5.20AOP-200 System AOP-200 NA 460 56.5 26.00 20.80
Total KVA = 94.65AMP at 460V Service = 205.76
Amp. Service (125% Round UP) = 260.0Maximum kW = 103.3
Average kW 4 = 66.6Notes:1 three phase = kW = KVA x power-factor x 1.73 (power factor = 0.8) single phase = kW = KVA
and Misc loads. 50% of A-100, 20% of P-700, and 10% of P-200C, P-300C, P-500, and P-600.
oxygen generator, ozone generator, and chiller. AOP-100 System is assumed to have 4 times the power usage as AOP-200 System (increased size plus oxygen generator)4 Average power usage includes, 100% operation of P-1000, P-1100A, RW-2, RW-3, RW-4, RW-5, Misc Loads,
AOP-100, and AOP-200. 50% operation of A-100, 10% operation of P-1200, P-1400, P-1300, and P-1500.
2 Average power usage includes, 100% operation of P-100A, P-200A, P-300A, P-400A, B-100, B-200A, B-300,
Electrical Load CalculationModified ISR SystemRaytheon Company
St. Petersburg, Florida
3 AOP System is assumed to operate feed pump, chemical pumps (sodium hydroxide and hydrogen peroxide),
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #19\Raytheon Load Calc_MISR.xls ARCADIS
Tab 20
Modified ISR System – Operation and Maintenance Plan
Table J-8Start-up and Proof of Performance Monitoring Program
Modified ISR System Raytheon Company
St. Petersburg, Florida
Page 1 of 1
Analyte VOC 1,4-dioxane Bromide Bromate Iron TSS COD Alkalinity pH
USEPA Method 8260B 8260 SIM 300.0 300.0 200.7 SM 2540D SM 5220D SM 2320B Field
X X X X X X X X XMultiples samples throughout testing period.
Aeration Tank Effluent X X XMultiples samples throughout testing period.
Multi-Media Filter Effluent (T-500A/B/C) X X X X XMultiples samples throughout testing period. Sample will be used to monitor influent conditions to the air stripper.
X X XMultiples samples throughout testing period. Sample will be used to monitor influent conditions to AOP-100.
X X X X X Complete set for each tested condition.
X X X X X Complete set for each tested condition.
X X X X X XOne set for combined effluent. Results will be used to obtain approval for POTW discharge.
X X X During POTW discharge.
X X X During POTW discharge.
X X During POTW discharge.
Footnotes:USEPA - United States Environmental Protection AgencyVOC - Volatile Organic CompoundsCOD - Chemical Oxygen DemandIWD - Industrial Wastewater DischargeSIM - Selective Ion MonitoringPOTW - Publicly Owned Treatment WorksAOP - Advanced Oxidation ProcessLPGAC - Liquid-Phase Granular Activated CarbonMMF - Multi-Media Filters
(1) - IWD Permit Suite includes parameters specified by the City POTW discharge permit.
AOP-100 Intermediate
AOP-100 Effluent
Filter Feed Tank(2) (T-1400)
Catalytic Media Filter Effluent (T-1700A/B/C)
Multi-Media Filter Effluent (T-1800A/B/C)
(2) - Combined effluent from operating conditions evaluated during testing period will be stored in the Filter Feed Tank until analytical results indicate treated water is acceptable for discharge.For continuous operation, any time there is a significant change of greater than 30 percent of the present flow, and for AOP operating settings of greater than 25 percent of current process flow rate or chemical dose/feed rate, a new proof of performance testing will be conducted.
Secondary LPGAC Effluent(Treated Water Discharge)
Start-Up and Proof of Performance Testing
Air Stripper Effluent
Sample Location CommentsIWD Permit
Suite(1)
Influent to heat exchanger feed tank (T100)
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #20\(1) Table J-8 (Tab #20)_Startup and proof monitoring.xlsx ARCADIS
Table J-9Process Monitoring Plan and Reporting Schedule
Modified ISR SystemRaytheon Company
St. Petersburg, Florida
Page 1 of 1
Year>
Month > 2 3 4 5 6 7 8 9 10 11 12
Week > 2 3 4 - - - - - - - - - - -
Days > 1 2 3 4 5 - - - - - - - - - - - - - -
Monitoring Plan - Sample LocationAnalytical
Suite(*)
Aeration Tank Feed Pump Discharge 1 X X X X X X X X X X X X X X X X X X X
Filter Feed Pump Discharge 2 X X X X X X
Post Multi-Media Filters 2 X X X X X X
Air Stripper Discharge Pump 3 X X X X X X X X X X X X X X X X X X X
Decant Pump Discharge 2 X X
Backwash Solids (to disposal) 2
RW-2 3 X X X X
RW-3 3 X X X X
RW-4 3 X X X X
RW-5 3 X X X X
AOP-200 Feed Pump Discharge 1 X X X X X X X X X X X X X X X X X X X
Post AOP-200 1 X X X X X X X X X X X X X X X X X X X
Post EQ Tank (2 Tanks) 4 X X X X X X X X X X X X X X X X X X X
AOP Treatment System
X
X
X
X
X
X
1
1
Year 1 (Modified ISR System operations are expected to be 6 -12 months)
X
AOP Pre-Treatment System
X
Post AOP-100 1 X X X X X X X X X X X X X X X X X X X
Filter Feed Pump Discharge 2 X X X X X X
Post Catalytic Media Filters 2 X X X X X X
Post Multi-Media Filters 2 X X X X X X
Intermediate GAC 3 X X X X
Post GAC (Final Effluent) 5 X X X X X X X X X X X X X X X X X X X
Post VPGAC (2 Vessels) 6 X X X X X X X X X X X X X X
X X X X X X X X X X X X X X X X X X X
X X X X X X X X X X X X X X X X X X X
X X X X X X X X X X X X X X X X X X X
AOP-100 Feed Pump Discharge (part of HiPOxTM) X X X X X X X X X X X X X X X X X X X
Filter Feed Pump Discharge X X X X X X X X X X X X X X X X X X X
Quarterly Reports A X X X X
X X X X X X X X X X X
AOP Pre-Treatment System
AOP Treatment System
X
X
X
X
Volume Measurements - Minimum Frequency
X
Aeration Tank Feed Pump Discharge
Air Stripper Discharge Pump
AOP-200 Feed Pump Discharge
Treated Water Discharge
Reporting
IWD Permit Periodic Compliance Reports B
Continuous
Footnotes:VPGAC - Vapor-Phase Granular Activated CarbonAOP - Advanced Oxidation ProcessLPGAC - Liquid-Phase Granular Activated CarbonPOTW - Publicly Owned Treatment WorksIWD - Industrial Wastewater DischargeUSEPA - United States Environmental Protection AgencyVOC - Volatile Organic CompoundSIM - Selective Ion Monitoring(*) - Analytical Suites:
1
2 USEPA Method 200.7 iron and Method SM 2540D total suspended solids.3 USEPA Method 8260B VOCs and USEPA Method 8260 SIM 1,4-dioxane.
4
5 Parameters specified by the City of St. Petersburg POTW - IWD Permit.6 Field measurement using Photoionization Detector (PID).
B Submittal to City of St. Petersburg. In accordance with IWD Permit, reports are due 30 days after the last day of the month in which the samples were collected.
A Submittal to the Florida Department of Environmental Protection (FDEP) within 60 days of the end of the reporting period.
USEPA Method 8260B VOCs; USEPA Method 8260 SIM 1,4-dioxane; USEPA Method 300.0 bromide/bromate; USEPA Method 200.7 iron.
USEPA Method 8260B VOCs; USEPA Method 8260 SIM 1,4-dioxane; USEPA Method 300.0 bromide/bromate; USEPA Method 200.7 iron, RCRA Metal Method 200.8.
G:\ENV\TF\901-1000\TF922\Reports\2010\RAPA 2010\Final FDEP RAPA\Appendix J\Tab #20\(2) Table J-9 (Tab #20)_Schedule.xlsx ARCADIS