Date post: | 20-Jan-2017 |
Category: |
Documents |
Upload: | ferdie-cruz |
View: | 254 times |
Download: | 0 times |
2
Project: Improvement of CLI –IQA Inspection
Turn around Time and Productivity
Project Start: January 2, 2007
Project End: July 31, 2007
Location: Laguna, Philippines
Champion: Lito FLores
Process Owner: Ferdinand Cruz
Green Belt: Ferdinand Cruz / Jonash Rocamora
Team Members: Joszal Anchoriz, Alvin Ibanez, Tina
Mendoza, Sunny Caparas
Problem Statement:
After the acquisition of Powerwave Philippines by Celestica (Mar 2006), now known as Celestica Laguna Inc. Different commodity network Teams (e.g. IC, Logic, Metals, PWB, Discrete, Passive, Power Supply, Optics and Plastics ) and metrics ( e.g. Turn Around Time, SPM, SCAR etc.) were introduced. The separation/resignation of two IQA inspectors (Reinor and Myla) and the addition of new products such as Halfdome (April 2006) and Royale (July 2006) resulted to massive parts queue for inspection at IQA. Previous Inspection turn Around Time (cycle time) from an average of 72 hours to 20 hours Celestica corporate/regional requirement should be met. Regular submission of reports such SQE Global reports, Supplier Performance Measurements (SPM), Supplier scorecards should also be accomplished and submitted.
Objective Statement:
• Improve inspection cycle time from previous average target of 72 hours to average of 20 hours.
• Maximize IQA space to accommodate more parts queue for inspection.
• Increase inspectors productivity by 20% from average of 17 line items inspected to 20 line items (without NCMR) for 10 hr/shift work schedule and 7 to 12 line items with some NCMR.
• Fast and accurate data retrieval from manual paper trail to computerized data miner
Current Project Savings: To be computed/ To be determined
Project Phase:
Accomplishments: Team formation/ Organization, DONE ww01 2007 Macro Mapping of Process , DONE ww01 2007 Data Gathering , DONE ww02 2007 Data Analysis, DONE ww03 2007 Program logic / flow discussion with IT, DONE ww04 Programming of sub-modules and major modules including screenshots, Started ww05 2007 Review/test completed sub modules and major modules, ww06 2007 Program debugging ( as needed) Part number set-up and inspection requirement set-up, Started ww07 2007 as needed. Set-up hardware requirements and PR additional requirement to support full
implementation. DONE ww07, 2007 Review IQA layout and material flow. DONE ww07 2007 Re-layout IQA according to plan. DONE ww7 2007 Train IQA inspector on how to use the program ww08 2007 Start parallel paper trail method and automated QA records, DONE ww08 2007 (All Inspectors) Roll-out automated QA records without paper QA records with two inspectors. Linked QA records to MID system eliminating redundant encoding of parts traceability, 4/15/07 Full implementation of Automated QA records to all IQA inspectors, May15, 2007 Auto report (SQRR) module, May 15, 2007
To Do’s: Pilot run Auto report (SQRR) on ww21 report Enhance Auto reports program (SQRR) Target Date June to July 2007 Revise IQA procedure to document the system change , Target Date June 2007
Project Summary:
Completed QA records minor and major modules programming. Started using the QA records parallel with the manual paper trail method for comparison and buy-off purposes. Pilot run of the QA records were successful . Two inspector were tasked to use the QA records without the paper trail (inspection records). Daily review of the QA records shows that the two inspectors were able to utilize the system properly. Full benefits of the system will be realized after completion of the auto reports generation and auto IDR/IR generation in case of failed inspection result.
Opportunities:
(Consider the next utilizations of achieved results)
Six Sigma Project Summary
D M A I C
3
Project: Improvement of CLI –IQA Inspection
Turn around Time and Productivity
Project Start: January 2, 2007
Project End: July 31, 2007
Location: Laguna, Philippines
Champion: Lito FLores
Process Owner: Ferdinand Cruz
Green Belt: Ferdinand Cruz and Jonash Rocamora
Team Members: Joszal Anchoriz, Alvin Ibanez, Tina Mendoza, Sunny Caparas
4
Problem Statement:
After the acquisition of Powerwave Philippines by Celestica (Mar 2006), now known as Celestica Laguna Inc. Different commodity network Teams (e.g. IC, Logic, Metals, PWB, Discrete, Passive, Power Supply, Optics and Plastics ) and metrics ( e.g. Turn Around Time, SPM, SCAR etc.) were introduced. The resignation of two IQA inspectors and the addition of new products such as Halfdome (April 2006) and Royale (July 2006) resulted to massive parts queue for inspection at IQA. Previous Inspection turn Around Time (cycle time) target of 72 hours from the time parts received at IQA until parts approval were not measured effectively since the current ERP (Baan) system measures the cycle time from Receiving time up to part approval. Currently 20 hours T.A.T. Celestica corporate/regional requirement should be met. Regular submission of reports such SQE Global reports, Supplier Performance Measurements (SPM), Supplier scorecards should also be accomplished and submitted on time.
Objective Statement:
• Effectively measure IQA inspection cycle time and meet 20 hours target.
• Maximize IQA space to accommodate more parts queue for inspection.
• Increase inspectors productivity by 20% from average of 17 line items inspected to 20 line items (without NCMR) for 10 hr/shift work schedule and 7 to 12 line items with some NCMR.
• Fast and accurate data retrieval from manual paper trail to computerized data miner
Current Project Savings: To be computed/ To be determined
Six Sigma Project Summary
5
Project Phase:
Accomplishments: Team formation/ Organization, DONE ww01 2007 Macro Mapping of Process , DONE ww01 2007 Data Gathering , DONE ww02 2007 Data Analysis, DONE ww03 2007 Program logic / flow discussion with IT, DONE ww04 Programming of sub-modules and major modules including screenshots,
Started ww05 2007 Review/test completed sub modules and major modules, ww06 2007 Program debugging ( as needed) Part number set-up and inspection requirement set-up, Started ww07 2007 as needed. Set-up hardware requirements and PR additional requirement to support full
implementation. DONE ww07, 2007 Review IQA layout and material flow. DONE ww07 2007 Re-layout IQA according to plan. DONE ww7 2007 Train IQA inspector on how to use the program ww08 2007 Start parallel paper trail method and automated QA records, DONE ww08 2007 (All Inspectors) Roll-out automated QA records without paper QA records with two inspectors. Linked QA records to MID system eliminating redundant encoding of parts traceability, 4/15/07 Full implementation of Automated QA records to all IQA inspectors ,DONE May 15, 2007 Auto report (SQRR) module, May 15, 2007
To Do’s:
Pilot run Auto report (SQRR) on ww21 report Enhance Auto reports program (SQRR) Target Date June to July 2007 Revise IQA procedure to document the system change , Target Date June 2007
Six Sigma Project Summary
D M A I C
6
Project Summary:
Completed QA records minor and major modules programming. Started using the QA records parallel with the manual paper trail method for comparison and buy-off purposes. Pilot run of the QA records were successful . Two inspector were tasked to use the QA records without the paper trail (inspection records). Daily review of the QA records shows that the two inspectors were able to utilize the system properly. Full benefits of the system will be realized after completion of the auto reports generation and auto IDR/IR generation in case of failed inspection result.
Opportunities:
(Consider the next utilizations of achieved results)
Six Sigma Project Summary
7
Team Organization
Lito Flores(Champion)
Ferdie CruzJonash Rocamora
(Green Belt)
Team MembersJoszal AnchorizSunny Caparas
Alvin IbanezTina Mendoza
8
Macro Map
Parts received from supplier at Receiving
QTY Audit verification
Baan/System Encoding
Endorse item to IQA
Record to logbook
Refer to priority list
from Planning
Perform Inspection
Prepare Quality
Records
Baan Transaction
MID Generation
Prepare NCMR
Receiving
Process Non-Value Add
Non-Value add but essential
Record to logbook X
Refer to priority list from planning X
Perform inspection X
Baan Transaction X
MID generation X
Prepare Quality records X
NCMR Preparation X
Endorse parts to warehouse & log X
Note:
Process inside dotted lines are activities outside IQA
Endorse parts to Warehouse
and log to logbook
9
Data Gathering
Productivity Monitoring (1 month Data)
•Highlighted in yellow are not full time inspectors•Highlighted in gray are new inspectors•Encircled are the max line items inspected by full time inspectors•Maximum Line items that can be inspected in a 10 hr shift schedule = (14+19+19) / 3 = 17 line items (without Failure/NCMR) using old inspectors as base line.
•Average Line items that can be inspected in a 10 hr shift schedule with some NCMR preparation = (6+6+9) / 3 = 7 line items
10
Analyze
Inspection Turn Around Time
People Materials Work Methods
Environment Equipment
Skills
Education
Work Attitude
Not Motivated
Low Salary
High Volume
Large geometry and parameters to inspect Manual paper Trail
method
Inspection, endorsement,
approval, docs done by one inspector
Insufficient manpower
Not comfortable
Warm / cold
Crowded work space
Sharing of test equipment
Proximity to inspection area (CMM, ht gages
etc.)
Old equipment
`Uses Baan
11
Analyze
Received parts from Receiving
Allocate parts to
inspectors
Perform Inspection
Baan Transaction
MID Generation
Quality Records
NCMR/ IDR
Endorse Parts
Record parts details on log sheet
PO#/ /Receipt #
Quantity
Record endorsement
details on log sheet
Endorse by
Received by
Inspect according Refers to
priority list
Inspect according to
age
Waiting for priority list
from planning
Waiting for part
age status
from IT
AML Check
Refer to Baan for
AML Check
Visual inspection
Dimensional Inspection
Electrical test
Create NCMR manually
System rejection
Refers to quality
record and master list
Manually Record parts
traceability details
Auto generate MID
number
Part No
Lot code/date code
Manually Record parts
traceability details
inspector
IR No./ Part Number
Redundant / repeated
Take picture
Manually Draft the
report with parts details
Create IDR manually for
MRB purposes
Manually write parts
rejection details and inspection
details
Manually pull-out quality
records folder
Endorse parts to ware
house
Record endorsement
details on log sheet
System Approval
12
AnalyzeCurrent VSM Considering no failure
Note: Highlighted in yellow are process that can be improved
IQA VSM Before
14
Analyze
Activity Off the shelf Item (e.g. Component)
Approval 0.717
Inspection 8.317
Manual/Paper Method 10.000
Staging and Endorsement 2.850
Traceability 10.517
Total 32.400
Off the shelf Item (e.g. Component) Inspection Elements
2%
26%
31%
9%
32%
Approval
Inspection
Manual/PaperMethod
Staging andEndorsement
Traceability
15
Analyze
Custommized Items (e.g. Mech'l, PCB, Cable) Inspection Elements1%
75%
11%
2%
11%
Approval
Inspection
Manual/PaperMethod
Staging andEndorsement
Traceability
Activity Custommized Items (e.g. Mech'l, PCB, Cable)
Approval 0.717
Inspection 106
Manual/Paper Method 14.82
Staging and Endorsement 2.85
Traceability 15.75
Total 140.137
16
Analyze
Consumables Inspection Elements3%
27%
35%
9%
26%
Approval
Inspection
Manual/PaperMethod
Staging andEndorsement
Traceability
Activity Consumables
Approval 0.75
Inspection 8.1
Manual/Paper Method 10.583
Staging and Endorsement 2.849
Traceability 7.713
Total 29.995
18
MAJOR MODULES
ITEM MODULE DESCRIPTION USER SCREEN SHOT REMARKS
1 IR FormInspectionReportFrom
Generates an excel file with an automated serial IR number, a form used by IQA to record the quality inspection of the item. (For hard copy purposes)
ALL IQA
Status Completed: This tool create inspection report form with smart serial numbers. This also eliminates the purchase of carbonized IDR forms used during MRB and parts disposition at IQAAverage IDR Form consumption Is about 4 rims per month.
To be used for failed Status only
2 ITEM STATUS
A module that is designed to monitor the flow of material and its status at IQA. It alerts all concern engineer, planners, managers, finance personnel regarding the item on hold/pending at IQA.
ALL Status Completed: This session allows SQE and IQA staff to work continuously without interruption from different person making follow-ups and asking for parts status. Previously tracking of parts status were done manually and usually summary status were released the following day. With the use of this tool everything is just a click away.
19
MAJOR MODULES
ITEM MODULE DESCRIPTION USER SCREEN SHOT REMARKS
3 CYCLE TIME
Tracks the actual time and date received of the items endorsed by receiving personnel.
ALL IQA
Status completed . This modules eliminates manual tracking of date and time the parts were received, this is essential for the computation of actual inspection turn around time. The inspector would just have to key-in the receipt number and all items contained on that receipt will automatically tagged with the actual date and time it was received by IQA. Target inspection completion date is also computed automatically. This replaces manual recording and log books.
4 QA RECORDS
Maintains details and status of incoming inspection per part number (visual inspection, dimensional, electrical and document requirement)
ALL IQA
Status: In Progress, ongoing elimination of program glitch. This module will replace the Quality Records folder that are used to record and trace parts history . In return purchase of quality records folder is also eliminated.
20
MAJOR MODULE
ITEM MODULE DESCRIPTION USER SCREEN SHOT REMARKS
5 MID A system that generate and print a unique serial number used to identify the material after inspection. (pass tracking of material used)
ALL IQA
Status: Existing system during REMEC times. This system was modified to fit the current need of Celestica Laguna operations. Inspector can now assign MID number in online or offline mode. Previously when the Baan system is down, parts approval and MID generation is not possible. With the introduction of manual MID session MID assignment is now possible without any compromise because the online and offline database are the same eliminating double MID number.
6 DATA MINER
The program is design to gather information and data collection and can extract information in excel format. The system support the following modules: MID, For Approval, & Inspection Record.
ALL IQA
Status: Completed. This tool replaces the tedious method of retrieving parts history/traceability.Previously, when parts info such as lot code or date code is required hard copies of quality records are retrieved from archive, but with this new tool everything is available in just a click of a finger tips.
21
OTHER MAINTENANCE SUB-MODULE
ITEM MODULE DESCRIPTION USER SCREEN SHOT REMARKS
1 CYCLE TIME CALENDAR
Maintains inspection working days for cycle time reference.
SYSTEM
ADMIN /CLERK/
SQE
Status: Completed. This sub-module supports the Cycle Time Module. The System Admin/Clerk/SQE manage the session by identifying the dates without work schedule such as weekends and holidays which should not be included in the cycle time computation.
2 AQL SETUP Maintains the Accept Quantity Lot (AQL) table as being referenced in the QA Records module.
SYSTEM
ADMIN /CLERK/
SQE
Status: Completed. The System Admin/Clerk/SQE manage this session by defining the AQL percentage and level according to define lot size ranges.
22
OTHER MAINTENANCE SUB-MODULE
ITEM MODULE DESCRIPTION USER SCREEN SHOT REMARKS
3 COMMODITY TYPE
Maintains the list of all commodity type
SYSTEM
ADMIN /CLERK/
SQE
Status: Completed, This session is manage by the System Admin/Clerk/SQE in reference with the commodity grouping provided by corporate/regional SQE. This supports the QA records module and the part number set-up sub-module. This identifies the commodity type a part number belongs.
4 COMMODITYCODE
Maintains the list of all parent commodity codes in a commodity group
SYSTEM
ADMIN /CLERK/
SQE
Status: Completed, This session is manage by the System Admin/clerk/SQE in reference with the commodity grouping provided by corporate/regional SQE. This supports the QA records module and the part number set-up sub-module. This identifies the commodity group where the part number belongs.
23
OTHER MAINTENANCE SUB-MODULE
ITEM MODULE DESCRIPTION USER SCREEN SHOT REMARKS
5 COMMODITY GROUP
Maintains the list of all commodity sub-group codes being mapped in component part numbers.
SYSTEM
ADMIN /CLERK/
SQE
Status: Completed, This session is manage by the System Admin/clerk/SQE in reference with the commodity grouping provided by corporate/regional SQE. This supports the QA records module and the part number set-up sub-module. This identifies the commodity group.
6 DEFECT SETUP
Maintains the list of all defects by commodity encountered at incoming inspection.
SYSTEM
ADMIN /CLERK/
SQE
Status: Completed, This modules allows the System Admin/Clerk/SQE to identify all possible defects per commodity. This support the QA records inspection details.
24
OTHER MAINTENANCE SUB-MODULE
ITEM MODULE DESCRIPTION USER SCREEN SHOT REMARKS
7 ITEM STATUS (For Approvals) REMARKS SETUP
Contains the list of status of item in for Item Status module.
SYSTEM ADMIN /CLERK/S
QE
Status: Completed, In this session the System Admin/Clerk/SQE define remarks category e.g. MRB, Non COC etc.
8 LOCATION SETUP
Contains the list of all location of defect encountered at incoming inspection.
SYSTEM ADMIN /CLERK/S
QE
Status: Completed. In this session the System Admin/Clerk/SQE define all possible location of defects e.g. top, side, etc.
25
OTHER MAINTENANCE SUB-MODULE
ITEM MODULE DESCRIPTION USER SCREEN SHOT REMARKS
9 PACK SETUP
Contains the list of all type of material packaging.
SYSTEM
ADMIN /CLERK/
SQE
Status: Completed. In this session the System Admin/Clerk/SQE define all possible packaging available. This support the QA records module
10 PART NUMBER SETUP
A module which specifies the details of the item particularly the commodity group, type, and its application.
SYSTEM
ADMIN /CLERK/
SQE
Status: Completed, This session supports the QA records modules. The SQE/System Admin/Clerk define parts New commodity, commodity group and commodity type details.
26
OTHER MAINTENANCE SUB-MODULE
ITEM MODULE DESCRIPTION USER SCREEN SHOT REMARKS
11 UNIT OF MEASURE
Contains the list of all unit of measurement for media use at incoming inspection.
SYSTEM
ADMIN /CLERK/
SQE
Status: Completed. This is the session where the unit of measurement is define by the System Admin/Clerk/SQE e.g. cm, inches, mm, microns etc.This supports the QA records inspection details.
12 AML Retriever
This module allows the user to check the existing AML without using the Baan
ALL Status: Completed
27
OTHER MAINTENANCE SUB-MODULE
ITEM MODULE DESCRIPTION USER SCREEN SHOT REMARKS
13 COC Up loader
Uploads the COC softcopy into the IQA database
ALL Status: CompletedAllows the IQA to upload soft copy of COC into the system, making future retrieval faster and eliminate possible loss of documents. It also lessen the paper for retention that requires space and other resources.
14 Media Used Maintains the list of all measuring equipment used
SYSTEM
ADMIN /CLERK/
SQE
Status: Completed, This modules allows the System Admin/Clerk/SQE to identify all possible MTE and inspection media used during inspection. This support the QA records inspection details.
28
Tangible Benefits
Factors Before EXPECTED
Recoverability of data
Retrievable in couple of hours or even longer depending on the extent or details needed.
With the use of data miner module of the data base, data retrieval is possible in minute or less
Resources Required papers, forms, cabinet and large storage space to house document for temporary repository and archiving.
Minimal resources needed, eliminated other forms being used and the need for additional cabinets and space for repository and archiving.
Accessibility/availability
Used to take couple of hours to identify status of all raw materials at IQA location, every line item has to checked manually from time to time versus the list provided by IT clerk. Information was disseminated to concerned person thru phone call and e-mails.
Made readily accessible in real time. Engineers, Buyers, Planner, Finance Personnel and Managers can now view the actual parts status queue at IQA whether it is For Inspection, HOLD, for MRB disposition, for RTV, etc.
Record Security Paper records can be misplace, lost or damage over time Incoming quality material record (soft copy) is secured and regularly back-up in the network and remote location
Cycle TimeMeasurement
Cycle time measurement is computed using a separate excel file because the cycle time measured by Baan is from the time of parts received up to parts approval in the system. This includes the MRB time, hold time, receiving time. Etc.
With the use of cycle time module, cycle time can be measured automatically from the actual time of endorsement of parts to IQA up to complete inspection. Manual logging on logbook and encoding on excel file was eliminated.
Savings Need to allocate CAPEX for the purchase of locally available software.
Realized approximately $2800 of savings as the database was developed in house
Connectivity Uses paper trail method, connectivity to ODC is not possible. Current ODC capability is from SMT to Box build.
Linkable to ODC making traceability from IQA inspection to Box built possible.
Productivitymonitoring
Monitors manually, checking done at the end of the shift or every start of the shift.
Can determine productivity of each inspector quickly through the data miner module.
Data Accuracy Summary of failure were collected and summarized manually Summary are populated automatically with the use of data miner.
Headcount Requires replacement for the two resigned employee Man-hour requirement were covered by the productivity improvement. Therefore replacement is not needed
29
Intangible benefits
•Demonstrated CAN DO ATTITUDE, the team created a new tool even with limited resources available. The limited working schedule and skills set has never been an issue to the team to complete the project. The team patiently worked together and reached their goal.
•TEAM WORK was exemplified by the team members. The member of the group are from different departments with different tasks, but were able to work as one to reach a common objective of making IQA operation easy. The teams synergy produced an effect greater than the sum of their individual capabilities.
•The team’s morale was uplifted. The development of the project provided them confidence and a sense of accomplishment. They feel proud of what they have done