Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011
Transcript
Page 1: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Irregularities in Engineering Works

Sanjay Jain, GM(Vig)

DATE: 8th September’ 2011

Page 2: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

PUBLIC PROCUREMENT...

The process of Public Procurement can be

categorized in three distinct Stages- Pre-tender Stage (Project formulation, Appointment of

Consultants, Preparation of Detailed Project Report/

Detailed Estimate)

Tender Stage (Preparation of tender documents, inviting

& opening of tenders, prequalification, tender evaluation &

award of work, Integrity Pact)

Execution Stage (Compliance of agreement conditions,

making payments, ensuring quality & timely completion)2

Page 3: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

PRE-TENDER STAGE...Shortcomings

Appointment of Consultants:

Consultant be appointed in a transparent and competitive manner for need based and specialized jobs.

Consultant’s fee be based on some fixed value of the contract.

3

Page 4: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Pre – Tender Stage: Shortcomings

DPR & estimates not prepared based on soil condition and survey at site resulting into large scale deviations.

Tenders invited without acquisition of land, site approvals and statutory clearances from local authorities resulting in delays and disputes.

Page 5: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.
Page 6: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Pre – Tender Stage: Shortcomings

Consultancy fee given on % basis on packages wherein there is no input required. No ceiling limit stipulated.

Consultant appointed without well defined responsibilities. Payment not linked to the work progress and final completion.

Penal clause for deficiency in services by the consultant not stipulated in the contract agreement.

Page 7: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Pre – Tender Stage: Shortcomings

Tender specifications tailor made to suit particular firm/select firms inviting allegations of favour and bias from the competing firms.

Restrictive eligibility criteria included in the NIT resulting into inadequate response.

Gross over–provision in capacity of new DG sets procured for power house affecting system efficiency.

Page 8: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Tender Stage: Shortcomings

Firm pre-qualified on the basis of their experience in on-going work/work in progress as against the requirement of completed work.

Tender evaluated in deviation to the Ambiguity Clause.

Interest free ‘Mobilization Advance’ stipulated in one of the tenders in violation of CVC guidelines.

Page 9: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Tender Stage: Shortcomings Two firms who had produced

completion certificate for the same work were qualified without verification.

Post bid relaxation of the qualification criteria. (Had the relaxation been included in the NIT more firms would have participated with a competitive response).

Price variation clause – Fixation of star price.

Contd…

Page 10: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Tender Stage: Shortcomings….. Condition for vetting of structural

designs by IIT/ Engineering College.

Design Based tender called for HVAC, PA system without stipulating design experience.

Adequate Safeguard not taken for supply of spares & technological support for the design life of the system.

Contd…

Page 11: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Tender Stage: Shortcomings

Repeat order was placed on a firm without ensuring fulfillment of the conditions stipulated in the DOP.

Abnormally long time taken to decide and award the work. (Directions issued by the Chairman for time bound processing i.e. award of contract within 30- days of opening of tenders vide letter dt. 30.08.07).

Contd…

Page 12: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.
Page 13: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Tender Stage: Shortcomings Time period increased and tender

condition(s) changed during negotiations, thereby denying level playing field to the other bidders.

Evaluation criteria/exclusion criteria followed to decide L-1 bidder not made part of the tender.

Contract awarded without establishing reasonability of the offer received.

Contd…

Page 14: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Tender Stage: Shortcomings Budgetary offers received for

procurement of insecticides and weedicide chemicals were considered as commercial offers leading to procurement at high rates.

Tenders splited so as to bring them within the approval limit of local authorities.

Improper provisioning of store purchases without taking into consideration the available stock, past consumption pattern and shelf life of the item.

Contd…

Page 15: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Tender Stage: Shortcomings Inflated justification statement

prepared by including unjustified components and loading factors.

Technical evaluation not done objectively on equitable basis. (Without considering the extent of deviations, when the offers suffer from deficiencies, equal opportunity should be given to all).

Splitting of award in a supply contract after techno-commercial evaluation, although multi sourcing not stipulated in NIT

Page 16: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Execution Stage : Shortcomings BGs accepted with conditional

stipulation and not verified from the Issuing Bank.

Use of departmental machinery was allowed to be used in cargo without recovery of charges as per contract provisions.

Payment of substituted item without making financial adjustments

Page 17: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Execution Stage : Shortcomings Acceptance of tack welding in place

specified continuous welding in steel fabrication work.

Filing system adopted in project was not in order. Part files are opened as and when new action are initiated, but subsequently not merged with the main file. No pagination.

Payment of secured advance against certain items without obtaining requisite insurance cover.

Page 18: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Execution Stage : Shortcomings

Non/part implementation of contract clauses related to Insurance policy (CAR), Workmen Compensation, ESI, labour licenses.

Defective contract management: Not maintaining mandatory site records/registers.

Large scale sub contracting by the main agency without approvals of the competent authority.

Page 19: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Execution Stage : Shortcomings Liquidated damages not levied

despite time over-run attributed to the contractor.

Shortfall in mandatory tests on items reflecting slackness in supervision and possibility of acceptance of sub-standard material/work.

Mobilization advance/secured advance not recovered as per provisions of the contract.

Page 20: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Execution Stage : Shortcomings Wide cracks, low density values,

settlement in portions of flexible runway noticed within 3-months of execution.

Non submission of documents like excise duties pass, custom duty receipts for imported items – Bill cleared.

Order for supply of equipment was placed on FOR destination, locations of consignees changed without freight adjustments.

Exchange of correspondence with the Contract Agency after expiry of time period and without extension of time to keep contract alive.

Page 21: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Execution Stage : Shortcomings Over payment in running bills and recovery

in final bill. Interest on over payment not deducted

properly. Over payment on A/c of party payment of

extra items / secured advance considering extra material.

Page 22: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

FINALLY……..

We may have to add one more stage

i.e. COMMISSIONING (to put into operation)

Page 23: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

General Shortcomings

Not posting summary details of contracts awarded during the month on web site.

Tender document not available on web site in down loadable format.

E-payment through ECS or RTGS not fully implemented.

Page 24: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Inference……….

Negligence in project management, contract administration and supervision.

Willful acts of omission and commission with possible malafide

Undue benefit to the contractor

Contractual disputes

Page 25: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Result……….

Additional time and cost for rectifications and remedy at Maintenance Stage

Audit observation

CTE paras

Vigilance Cases

Departmental enquiries

Page 26: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Actions taken in AAI……….Vigilance Initiatives: Leveraging Technology (e-payment,

e-billing, e-receipt, e-procurement) Time bounded processing of

procurement / tenders Introduction of ‘Integrity Pact’ Project management and clean

procurement workshops Introduction of ‘Integrity Pledge’ in

all tenders. E-tendering CTE - Type Inspection

Page 27: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Conclusion……….

Excellence is a moving target Vigilance in project management

brings Quality Assurance and cost savings – deterrent against corrupt and inappropriate practices

Need for rejuvenated approached to achieve excellence in project management and implementation……….

Page 28: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Common Points to be discussed

If application received and tender not issued the application fee to be refunded or not.

Similar Experience – Work of DG/HVAC set installation to be accepted for O&M.

In a tender – three makes are given Agency is free to choose any make.

or First priority on the product mentioned first.

Page 29: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Common Points to be discussed….

If contractor writes/ specifies one of the approved makes out of those than is it a conditional tender or not.

If tender is conditional whether EMD to be forfeited or not.

Consideration of experience certificate with levy of Penalty.

Page 30: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

EMD….

In EMD, DD is valid for 90 days and BG is valid for 180 days. If BG is valid for 179 days whether we should accept it as tender is valid only for 90 days.

Yes or No - Why?

How to verify the BG for EMD before tender opening.

Page 31: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

FINANCE A CHECK MECHANISM

BUILT IN CHECK SYSTEM INCONSISTENCY IN FINANCIAL

SCRUTINYNEED FOR FINANCE MANUALDUTIES AND RESPONSIBILITIES

Page 32: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Role of Finance Officer

Financial Concurrence (AA&ES Stage) Budget Allocation; Monitoring of utilized budget to check the

balance available; Assessment of need/ viability of project; Phasing of proposed expenditure in-line

with progress of work.

Page 33: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Role of Finance Officer…

Tender Opening Check justification of cost available; Ensure numbering of tender; Ensure opening of Cover No. 1 of all firms first; Checking of EMD(DD/BG); Ensure CIO properly; Ensure cellophane tape fixed on all cuttings/

insertion and total amount Signing of each paper in tender Check rates quoted in figure/ words Entry in register

Page 34: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Role of Finance Officer…

Tender Processing Check comparative statement (Calculate

rebate etc.); Verification of quoted rates with

comparative statement available; Check A/A & E/S, TS issued by

appropriate authority. Any other requirement

Page 35: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Role of Finance Officer…

WAB/ WAC/ RCAC proposals WAB note be processed through Finance

Directorate; Finance Officers shall ensure all the

parameters of concurrence have been followed;

Any adverse remark/ important issue must be recorded upfront.

Page 36: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Role of Finance Officer…

Billing Check agreement signed or not; Check Measurements; Test Check statement; Completion Certificate; Part rate statement/ Theoretical

statement; Check Stock Entry/ MAS/ Challan etc.; Check deduction (Statutory + contract); Check deviation so that relative position

of L1 does not change.

Page 37: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Role of Finance Officer…

Billing….. Monitoring of BG/ DD etc.; Ensuring timely recovery of various

advances (Mobilization/ secured etc.); In case of over payment, recovery of

interest as applicable; Check EOT, approval of Competent

Authority.

Page 38: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

List of Documents required at Various Stages of Contracts Preliminary Estimate; Detailed Estimate; Technical Sanction (TS); Draft NIT (DNIT); Tender Document; Agreement; Bill.

Page 39: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

CASE STUDY

Page 40: Irregularities in Engineering Works Sanjay Jain, GM(Vig) DATE: 8 th September’ 2011.

Thanks