+ All Categories
Home > Documents > ISOLDE & HIE ISOLDE Status and Plans

ISOLDE & HIE ISOLDE Status and Plans

Date post: 07-Feb-2016
Category:
Upload: keegan
View: 60 times
Download: 0 times
Share this document with a friend
Description:
ISOLDE & HIE ISOLDE Status and Plans. Richard Catherall EN-STI ISOLDE Technical Coordinator IEFC Workshop 7 th – 9 th March 2012. Outline. Status and plans for 2012 experiments Shifts and schedule RILIS and REX operation New experiments for post accelerated beams 2012 - PowerPoint PPT Presentation
Popular Tags:
46
ISOLDE & HIE ISOLDE Status and Plans Richard Catherall EN-STI ISOLDE Technical Coordinator IEFC Workshop 7 th – 9 th March 2012
Transcript
Page 1: ISOLDE & HIE ISOLDE Status and Plans

ISOLDE & HIE ISOLDE Status and Plans

Richard Catherall EN-STIISOLDE Technical Coordinator

IEFC Workshop7th – 9th March 2012

Page 2: ISOLDE & HIE ISOLDE Status and Plans

Outline• Status and plans for 2012 experiments

• Shifts and schedule• RILIS and REX operation• New experiments for post accelerated beams 2012

• HIE-ISOLDE status and plans• Reports and recommendations from the IAP• Cavity design and tests• Civil engineering and installation work LS1

• Foreseen activities for LS1• Target area activities• Modifications in the experimental hall• Other plans

Page 3: ISOLDE & HIE ISOLDE Status and Plans

Injector schedule 2012

35 weeks of physics(vs 29 in 2010,2011)

Protons for ISOLDE restart in spring 2014

Guaranteed protons (46% requested):

(Possible increase at next research board)

Page 4: ISOLDE & HIE ISOLDE Status and Plans

ISOLDE schedule 2012

Status today:9 IS experiments and 2 LOIs CLOSED this month79 IS experiments and 9 LOIs OPEN (711 + 30 requested shifts)+ 14 IS experiments and 5 LOIs SUBMITTED to this INTC (193 + 17 requested shifts)1059 remaining shifts for proposals and LOIs904 + 47 (LOIs) shifts requested so far (66 more might be still requested)

Reasonable number of shifts that can be scheduled in 2012: 590

Page 5: ISOLDE & HIE ISOLDE Status and Plans

5

Beam Sm Ga Mg At Pb Dy Nd Pr Ag Tl Cd Mn Ni Yb ZnPlanned 80 104 256 160 184 64 136 - 112 208 288 120 272 - 376

Real 89 101 146 269 221 35 110 4 92 231 242 390 348 73 407

0

500

1000

1500

2000

2500

3000

Hou

rs

1994 1996 1998 2000 2002 2004 2006 2008 2010

Year

RILIS operation

2756 h – Total 2527 h – On-line

• > 50 % of the Total running time of ISOLDE facility197 (250) shifts in 2011~ 250 (300) planned for 2012

Laser ON timein 2011:

Ion beams of 15 elements were produced

Page 6: ISOLDE & HIE ISOLDE Status and Plans

REX Operation

• Delivered shifts for experiments and LOIs in 2011:

– REX – 147 shifts (160 shifts scheduled)

• Similar plans for 2012: ~200 shifts to be scheduled

– Enable 2 ms RF pulse length on all amplifiers for slow extraction tests to be done in 2012– A few “difficult” light beams will require testing and further tuning

Page 7: ISOLDE & HIE ISOLDE Status and Plans

New experimental setups using post-accelerated beamsRare decays of 6He

with an optical chamber

TriggerRecording

system

d

a

charge amplification zone GEM foils

e

E

ionizationelectrons

light

HV electrodes

gas at atmospheric pressureincoming

6He ions

gating electrode

CCD PMT

REX

Page 8: ISOLDE & HIE ISOLDE Status and Plans

New experimental setups using post-accelerated beams

Scattering chamber for studies of nuclosynthesis

(rapid proton-capture)

Nuclear structure of very light nuclei with an active target

p

ΔE-E

Ec.m.

Page 9: ISOLDE & HIE ISOLDE Status and Plans

Source of 44Ti:PSI

Core collapse supernovae

Ejected 44Ti becomes gamma emitter=> Sensitive diagnostic of explosion mechanism

Exotic radionuclides from accelerator waste for science and technology ~1018 atoms available

Offline experiment: Measure 44Ti(a,p) reaction at supernova energy

Extraction and acceleration:Material: Experiment:

Page 10: ISOLDE & HIE ISOLDE Status and Plans

Outline• Status and plans for 2012 experiments

• Shifts and schedule• RILIS and REX operation• New experiments for post accelerated beams 2012

• HIE-ISOLDE status and plans• Reports and recommendations from the IAP• Cavity design and tests• Civil engineering and installation work LS1

• Foreseen activities for LS1• Target area activities• Modifications in the experimental hall• Other plans

Page 11: ISOLDE & HIE ISOLDE Status and Plans

Highlights from the IAP report:Cryomodule Design

• The top loading design is a good choice with examples in ISAC-II, LNL, MSU and ANL.

• For the cryogenic safety the IAP has the impression that the numbers presented for the burst disk size to mitigate overpressure in the case of a venting accident are over conservative

• Concerns about the use of MLI => consider nickel plating of thermal shield and electro-polishing large surfaces (mirror-like) helium reservoir

• The cryomodule assembly sequence should be optimized to give adequate access to the cavities in case they have to be rinsed in the future

• The capability to helium condition the cavities by adding a leak system to the cryomodule should be analyzed at the cavity testing stage

• A 1400 W cryogenic plant should have sufficient margin.

Page 12: ISOLDE & HIE ISOLDE Status and Plans

Highlights from the IAP reportRF Cavities

• Work on the cavity has made good progress and is on the right path although many cold tests are still necessary to get things settled

• It is almost certain that the very stringent specification on the inner conductor beam port is too tight by probably a factor of ten at least. It is suggested that cavity development should proceed with this as a fact while beam simulations are done in parallel to confirm.

• It is noted that one of the RF performance curves reaches the high field value 6 MV/m and has a very low Q-slope for a sputtered cavity but a Qo which is a factor of ten from the goal.

– evaluate influence of tuner plate

Page 13: ISOLDE & HIE ISOLDE Status and Plans

Highlights from the IAP report:General

• Possible concerns are related to realities of funding which may cause complicated procurement strategies

• Synergies between ESS and HIE-ISOLDE should be explored with regard to the training of people

• The goal of having the 5.5 MeV/u linac commissioned in 2014 is tight but still possible => risk analysis by Sep. 2012

• Diagnostics look well thought out and conceptually well advanced for this stage of the project.

• Compare safety protocols with other operating facilities

• A finalization of the experimental layout is required

• The IAP suggests that attention must be given on the production of x-rays

• The IAP strongly support the addition of the storage ring to the ISOLDE infrastructure

Page 14: ISOLDE & HIE ISOLDE Status and Plans
Page 15: ISOLDE & HIE ISOLDE Status and Plans

RF Measurements @ 4.5K (2011)

0 1 2 3 4 5 6 71E+06

1E+07

1E+08

1E+09Q1 Mag Dec 2010-1st (150ºC) Q1 Mag Feb 2011-2nd (150ºC) Q1 Diode Jul 2011 (150ºC)

Q2 Mag Sept 2011 (150ºC) Q1 Mag Nov 2011 (370 ºC) Q2 Diode Dec 2011 ( 470ºC)

HIE-ISOLDE specification

Eacc(MV/m)

Qua

lity

Fact

or

Page 16: ISOLDE & HIE ISOLDE Status and Plans

RF Measurements (2012)

0 1 2 3 4 5 6 7 81E+07

1E+08

1E+09

Q2_6 January 2012Q1_9 cal1Q1_9 cal2

Eacc (MV/m)

Qua

lity

fact

or

~ 70 W @ 6 MV/m

~ 35 W @ 6 MV/m

Page 17: ISOLDE & HIE ISOLDE Status and Plans

Outlook for 2012

Completion of Civil Engineering Works by Q3 2012

Installation of Main Services (EL, CV, Transport)

Launch procurement of Cryogenic Plant (FC Mar. 2012)

Launch procurement of first batch of 5 (+5 option) high-beta cavities + ancillaries by Q1 2012.

Review Cryomodule Design (26-27 Apr. 2012) and launch procurement of CM1 by Q2 2012.

Review HEBT Layout (25 Apr. 2012) and launch procurement

Validate LLRF system and tuner plate design

Page 18: ISOLDE & HIE ISOLDE Status and Plans

18

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

2011 2012 2013 2014 2015 2016

Civil

Main servicesCryo

CM 1&2 CM 3&45.5MeV/u

10MeV/u

Beam Transfer Lines

CM 5&6

Hie-Isolde Planning

A simplified presentation of the different stages:

-What is the impact on operations?Dec 2012 - Apr 2014

sd sd sdCM1&2

Isolde & REX Ops shutdown

LS1

Cryo Mod 1 & 2 install(Isolde normal operations)(REX perturbations)

Timeline:

sd

VentilationDemi waterElectrical syst.s

Page 19: ISOLDE & HIE ISOLDE Status and Plans

Civil EngineeringNew SAS

January 2012

Page 20: ISOLDE & HIE ISOLDE Status and Plans

Main ServicesElectrical systems, Cooling & Ventilation

Start installation main services July 2012

Page 21: ISOLDE & HIE ISOLDE Status and Plans

Electrical systems

Electrical systems: July 2012 – June 2013

Page 22: ISOLDE & HIE ISOLDE Status and Plans

Cooling & Ventilation

Cooling & Ventilation: July 2012 – June 2013

Page 23: ISOLDE & HIE ISOLDE Status and Plans

23

Cryogenics

Compressors: July 2013 – December 2013

Cold Box: Jan 2014 – June 2014

Page 24: ISOLDE & HIE ISOLDE Status and Plans

Tunnel and Cryo Line

Cutting walls & install tunnel: Sep 2013 LS1 Cryo Cold Line: January 2014 – June 2014

Page 25: ISOLDE & HIE ISOLDE Status and Plans

Hie-Isolde SC Linac

First 10MeV/u by March 2016

Hie-Isolde SC Linac:

Bunched beam by 2017 ?

5.5MeV/u by the autumn of 2014

Page 26: ISOLDE & HIE ISOLDE Status and Plans

Outline• Status and plans for 2012 experiments

• Shifts and schedule• RILIS and REX operation• New experiments for post accelerated beams 2012

• HIE-ISOLDE status and plans• Reports and recommendations from the IAP• Cavity design and tests• Civil engineering and installation work LS1

• Foreseen activities for LS1• Target area activities• Modifications in the experimental hall• Other plans

Page 27: ISOLDE & HIE ISOLDE Status and Plans

LS1 Activities for ISOLDE• Robot replacement

• Hot Cell Installation• Medicis

• Target storage area

• Miniball move• ISOLTRAP platform

• RFQ Cooler alignment• HIE-ISOLDE

• PAD-MAD installation– Building 115 move/installation– Building 507 (light building)

Target Area

Experimental Area

Page 28: ISOLDE & HIE ISOLDE Status and Plans

Target Area:Robot replacement

• The current ISOLDE robots:– are coming to the end of their lifetime.

• No compatible spare parts

– Are prone to faults– Have no back-up redundancy– Are limited in flexibility

• No further programming possible

• Part of the long term improvements in operation is to replace the existing robots.

Page 29: ISOLDE & HIE ISOLDE Status and Plans

Target Area:Replacement robot

• New robot system based on “known” system.

Installation in target area – Q4 2013

Page 30: ISOLDE & HIE ISOLDE Status and Plans

Target Area: ISOLDE Hot Cell• For the dismantling and oxidation of used

ISOLDE targets• Pre-conditioning prior to shipment to PSI for

waste treatment

Location of new Hot Cell

Installation scheduled for long shutdown 2013

Building 179 with target area

Page 31: ISOLDE & HIE ISOLDE Status and Plans

Target Area: MedicisMedical Isotopes Collected from ISOLDE

• At present 1.4GeV, 2μA p. May have 2GeV, 4-8μA protons in 2018, of which 90% can be recuperated at the dump position.

• Samples can be transferred to Class A labs via a pneumatic transport system

• "Presentation at ICTR-PHE 2012 conference“ by Thierry STORA

Page 32: ISOLDE & HIE ISOLDE Status and Plans

• - Ta(p,X)149Tb is one of the most efficient production method. G. Beyer et al., Radiochim. Acta 90, 247 (2002)

• Can use CERN specific technologies for isotope production (i.e. nano-structured target, patent WO2010/034364, CERN)

• Large variety of isotopes accessible

Target Area: Medicis

Page 33: ISOLDE & HIE ISOLDE Status and Plans

• Beam transfer line– 1 straight section with 2 branches– Oct 2013 – Sept 2014

• MINIBALL move– Oct 2013 – April 2014

• Planning to be discussed in upcoming MINIBALL Collaboration meeting in 2 weeks

Miniball

Actar / Helios

Beam diagnostics

Exp.station

Miniball

Exp. Hall: MINIBALL Move

Page 34: ISOLDE & HIE ISOLDE Status and Plans

Exp Hall: ISOLTRAP• Mass measurement

experiment situated in the middle of the ISOLDE hall

• Platform made of wood– Inacceptable for a Class C

type laboratory• Plans to re-furbish the

platform– Replace wooden platform

with an aluminium platform

Page 35: ISOLDE & HIE ISOLDE Status and Plans

Exp Hall: RFQ Cooler• RFQ Cooler Alignment check• Laser at limit of transmission for optical

cooling experiments• External alignment checks done at the end of

2011– But to no avail

• Internal alignment checks need to be done

Page 36: ISOLDE & HIE ISOLDE Status and Plans

PAD & MAD Installation

Page 37: ISOLDE & HIE ISOLDE Status and Plans

PAD & MAD Installation

• Integration currently under discussion• Limited space in hall (especially near HRS entrance)• Integration in target area

– Conflict with hot cell operations– Access difficulties for large equipment (eg. FE’s, BTY

magnets)

Page 38: ISOLDE & HIE ISOLDE Status and Plans

38

Present situation (ground floor Jura side):

Control room

Buildings 115 & 507

Page 39: ISOLDE & HIE ISOLDE Status and Plans

39

Solid State Lab 115

1. Increasing the surface of the Solid State Lab in B.115:

Control room

Page 40: ISOLDE & HIE ISOLDE Status and Plans

40

Replace building 507

Control room

2. Replacing the existing building 507 by a new building - Ground floor (only accessible from within the surveyed area):

Page 41: ISOLDE & HIE ISOLDE Status and Plans

41

Control room

2. Replacing the existing building 507 by a new building - First floor (accessible from outside the surveyed area):

Replace building 507

Page 42: ISOLDE & HIE ISOLDE Status and Plans

Building status• Building 115 (extended solid state laboratory)

– Plans completed– Costs

• 407kCHF (to be secured)

– Make building 275 available for other users– Implies all handling of radioactive sources to within the confines of the ISOLDE

perimeter

• Building 507 (light building)– Under discussion– HIE-ISOLDE data acquisition rooms outside hall– Visitor’s room – access to visitors will be denied in future when the hall will be

defined as a controlled area.– A new version being considered based on partly metallic structure and partly

“portacabin” type modules

Page 43: ISOLDE & HIE ISOLDE Status and Plans

2 new Kuka linear RobotsIn Isolde Target Area

(2013)

Target Storage Area

Deliver the new target to the exchange point for the Kuka robots

Remove hot target and place on the shelf (during shut down)

Move the 3 years decayed target from shelf to hot cell

Move waste containers (with “standard” trans-pallet)

Handling with1 remote

controlled vehicle

To PSINew hotCell (2013) New

Target S. Marzari

Page 44: ISOLDE & HIE ISOLDE Status and Plans

44

2012 2013 2014

Isolde LS1 Planning

Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Robots

Hot Cell

PAD/MAD?

Medicis

ISOLTRAP

RFQ Cooler

Building 115

Building 507?

Target storage?

Miniball move

Target area

Exp. hall

HIE-ISOLDE installation

ISOLDE operation

Page 45: ISOLDE & HIE ISOLDE Status and Plans

Summary• Operations 2012

– A busy year ahead with a little more planned due to the extended operation time.

– The shift backlog clearly indicates the growing demand for physics at ISOLDE

• HIE-ISOLDE– Moving out of the R&D phase and into the procurement phase.– Important milestones to attain in 2012 to maintain the current schedule

• ISOLDE LS1 planning– A few tasks remain to be confirmed– A clear overlap of activities in the target area in Q4 2013– A potential conflict between HIE-ISOLDE installation and ISOLDE

operation in April 2014.

Page 46: ISOLDE & HIE ISOLDE Status and Plans

Thank you for your attention

Acknowledgements • GS/SE : DANIEL PARCHET, ELISEO PEREZ-DUENAS• EN/MEF : STEPHANE MARIDOR• BE/ABP : FREDRIK WENANDER • BE/OP : DIDIER VOULOT, ERWIN SIESLING• PH/SME : MAGDA KOWALSKA, SUZANNE KREIM• EN/HDO : YACINE KADI• BE/RF : MATTEO PASINI, MATTHEW FRASER• EN/CV : PAUL PEPINSTER, BENOIT LACARELLE• EN/EL : RENE NECCA• TE/CRG : NICOLAS DELRUELLE, JOS METSELAAR• EN/STI : THIERRY STORA, ANA-PAULA BERNARDES, VALETINE FEDOSSEEV,

BRUCE MARSH, STEFANO MARZARI• GS/DI : CYRILLE BEDEL• TE/MSC : JEAN-PHILIPE TOCK, YANN LECLERCQ,

LLOYD WILLIAMS, ARNAUD BOUZOUD• EN/HE : BRUNO FERAL, JEAN LOUIS GRENARD, KEITH KERSHAW


Recommended