+ All Categories
Home > Documents > ISPE_CCChImplementing

ISPE_CCChImplementing

Date post: 08-Aug-2018
Category:
Upload: aakritich
View: 213 times
Download: 0 times
Share this document with a friend

of 32

Transcript
  • 8/22/2019 ISPE_CCChImplementing

    1/32

    Implementing Best Practices In

    Capital Project Management

    R.W. Dietrich

    Director, Engineering Servicessanofi pasteur limited

  • 8/22/2019 ISPE_CCChImplementing

    2/32

    Agenda

    Introduction

    Context Best Practices Overview

    The Seven Project Stages The Stage Gate Review Process

    Project Performance Metrics Results to Date

    Next Steps

  • 8/22/2019 ISPE_CCChImplementing

    3/32

    Introduction

    Who is sanofi pasteur?

    Where is sanofi pasteur? Engineering at sanofi pasteur

    Capital projects at sanofi pasteur

  • 8/22/2019 ISPE_CCChImplementing

    4/32

    Context

    2002 benchmarking of capital projects

    determined0.90

    0.95

    1.00

    1.05

    1.10

    1.15

    1.20

    1.25

    1.30

    Industry

    Pharms

    sanofi pasteur 2002

    Absolute Capital Cost

    0.90

    0.95

    1.00

    1.05

    1.10

    1.15

    1.20

    1.25

    1.30

    Industry

    Pharms

    sanofi pasteur 2002

    Overall Schedule

    (excluding qualification)

  • 8/22/2019 ISPE_CCChImplementing

    5/32

    Best Practices Overview

    Derived principally from

    Current sanofi pasteur practices PMI PMBOK

    ISPE

    IPA

    Focuses on planning (aka Front End Loading,

    or FEL)

  • 8/22/2019 ISPE_CCChImplementing

    6/32

    Best Practices Overview

    The 7-stage PM Process:

    Stage 0: Needs Analysis Stage 1: Feasibility Study

    Stage 2: Preliminary Engineering

    Stage 3: Basic Engineering

    Stage 4: Execution

    Stage 5: Qualification Stage 6: Close-Out

  • 8/22/2019 ISPE_CCChImplementing

    7/32

    The Seven Project Stages

  • 8/22/2019 ISPE_CCChImplementing

    8/32

    The Seven Project Stages

    Stage 0: Needs Analysis

    Pre-project stage, concluded by a Go/No-Godecision

    Typically involves a Project Sponsor, Engineering

    Director, Area V.P. Rarely involves external support

    Goal is to establish technical solutions for end-

    user needs and develop a supporting businesscase

    Establishes order-of-magnitude boundaries forpotential project (cost, schedule)

  • 8/22/2019 ISPE_CCChImplementing

    9/32

    The Seven Project Stages

    Stage 1: Feasibility Study

    Project Leader is identified in this phase SMEs are used on an as-needed basis

    Project feasibility is assessed with respect to

    resources, risk

    Options are assessed with respect to benefits,economic justification, functionality

  • 8/22/2019 ISPE_CCChImplementing

    10/32

    The Seven Project Stages

    Stage 1: Feasibility Study

    Key activities and deliverables: Project charter

    Initial User Requirements Specifications

    Process description Block diagrams

    Material balances

    General arrangement diagrams Cost/benefit analysis

    Early stage risk analysis

  • 8/22/2019 ISPE_CCChImplementing

    11/32

    The Seven Project Stages

    Stage 2: Preliminary Engineering

    Project team and steering committee are definedand engaged at this stage

    Objective is to define the project scope

    External resources are assigned Design consultants

    Construction manager

    This stage (and stage 3) may be subject to capitalfunding

  • 8/22/2019 ISPE_CCChImplementing

    12/32

    The Seven Project Stages

    Stage 2: Preliminary Engineering

    Key activities and deliverables: Team charter

    Scope statement

    Preliminary project plan

    Final User Requirements Specifications

    Process and utility flow sheets

    Impact assessment (on site and environment)

    Preliminary cost estimate and time schedule ( 25%) Initial VMP development

    Initial procurement plan

  • 8/22/2019 ISPE_CCChImplementing

    13/32

    The Seven Project Stages

    Stage 3: Basic Engineering

    Objective of this stage is to develop the designbased on scope established in stage 2

    At the completion of this stage, the project is

    ready for full capital funding

  • 8/22/2019 ISPE_CCChImplementing

    14/32

    The Seven Project Stages

    Stage 3: Basic Engineering

    Key activities and deliverables: P&IDs

    Architectural layouts

    Material, personnel, product flow diagrams Major equipment specifications

    Project reviews:

    Constructability Maintainability

    HAZOP

    FMEA

  • 8/22/2019 ISPE_CCChImplementing

    15/32

    The Seven Project Stages

    Stage 3: Basic Engineering

    Key activities and deliverables (cont.): Product impact assessment

    Further development of VMP

    Functional design specifications Enhanced design review and qualification

    Finalized project plan with control schedule and cost

    estimate ( 5%) Final procurement plan

    Purchase of long lead equipment

  • 8/22/2019 ISPE_CCChImplementing

    16/32

    The Seven Project Stages

    Stage 4: Execution

    Objective of this phase is to complete the designdetails and carry out construction/installation

  • 8/22/2019 ISPE_CCChImplementing

    17/32

    The Seven Project Stages

    Stage 4: Execution

    Key activities and deliverables: Development of final drawings, specifications and tender

    packages

    Implementation of cost and schedule monitoring andcontrol systems

    Permitting

    Development of qualification rationales Finalization and approval of the VMP

    Development of IQ and OQ protocols

  • 8/22/2019 ISPE_CCChImplementing

    18/32

    The Seven Project Stages

    Stage 4: Execution

    Key activities and deliverables (cont.): Development of commissioning plan

    Construction coordination and inspection

    Safety inspections Final acceptance of construction works

  • 8/22/2019 ISPE_CCChImplementing

    19/32

    The Seven Project Stages

    Stage 5: Qualification

    The objective of this stage is to start up,commission and qualify the systems constructedand installed in stage 4

    Commissioning and qualification are optimizedper ISPE Baseline Guide

    Includes training of end users and maintenance

    staff

  • 8/22/2019 ISPE_CCChImplementing

    20/32

    The Seven Project Stages

    Stage 5: Qualification

    Key activities and deliverables: Pre-start reviews

    Maintenance plans and task lists

    Executed commissioning plan and reports Executed IQ and OQ protocols and reports

    Operation and maintenance manuals and SOPs

    Instrument calibration Regulatory registrations

    Training

  • 8/22/2019 ISPE_CCChImplementing

    21/32

    The Seven Project Stages

    Stage 6: Close-out

    This stage involves the transition from Projectstatus to Operational status

    Includes closure of all external contracts and

    dissolution of project team Includes final reporting and financial closure of the

    project

  • 8/22/2019 ISPE_CCChImplementing

    22/32

    The Seven Project Stages

    Stage 6: Close-out

    Key activities and deliverables: Engineering turn-over package (ETOP)

    Lessons Learned

    Registration of assets Final project report

    Entry of project data into benchmark database

  • 8/22/2019 ISPE_CCChImplementing

    23/32

    The Seven Project Stages

    The Project Management Process Flowchart

  • 8/22/2019 ISPE_CCChImplementing

    24/32

    SystemOwner

    I.O.Project

    Management

    Engineering

    Services

    Manufacturing

    Tec

    hnology

    Capital

    Investment

    Review

    Committee

    Ch

    angeControl

    Facilities

    Systemsand

    Planning

    User DefinedNeed

    Project Definition

    Site StrategyReview andApproval

    UserRequirementsSpecifications

    ProjectAssignment &

    Number

    I.O. Projec t

    ManagementSupport

    EstablishProject Team

    & DefineScope

    PreliminaryDesign

    Review andApproval

    DevelopProcess and

    Validation

    Protocol

    Basic DesignEngineering

    Project PlanCapital Reques t

    Document Detail DesignEngineering

    ProjectExecution

    Start-up andCommission

    Post-projectEvaluation

    Stage 0:

    Needs Analysis

    Stage 1:

    Feasibility Study

    Stage 2:

    Preliminary Engineering

    Stage 3:

    Basic Engineering

    Stage 4:

    Execution

    Stage 5:

    Qualification

    Stage 6:

    Close-out

    Owner Hand-over and

    Acceptance

    Qualification

    GoodsReceipt

    Asset RegistrationDocument

    Issue SAPEquipment

    Number

    Validation MasterPlan

    CapitalApproval

    Change ControlNumber andNotification

    Asset ChangeTemplate

    Review andApproval

  • 8/22/2019 ISPE_CCChImplementing

    25/32

    The Stage Gate Review Process

  • 8/22/2019 ISPE_CCChImplementing

    26/32

    The Stage Gate Review Process

    Performed at the end of key project stages

    Objective is to review activities anddeliverables and approve advancement tonext stage

  • 8/22/2019 ISPE_CCChImplementing

    27/32

    The Stage Gate Review Process

    Originally, stage gate review board consisted

    of sponsor, senior area management Currently, stage gate review board consists

    of engineering services peers

    In future, development of a dedicated globalstage gate review team?

  • 8/22/2019 ISPE_CCChImplementing

    28/32

    The Stage Gate Review Process

    Stage 0:Needs Analysis

    Stage 1:Feasibility Study

    Stage 2:Preliminary Engineering

    Stage 3:Basic Engineering

    Stage 4:Execution

    Stage 5:Qualification

    Stage 6:Close-out

    Go/No-goDecision

    Pre-planning Capital

    Funding

    Turn-over to Owner and

    Maintenance

    Change ManagementInitiated

    Change Control Initiated

    StageGateReview

    Full Project Capital

    Funding

    StageGateReview

    StageGateReview

    StageGateReview

    StageGateReview

    StageGateReview

  • 8/22/2019 ISPE_CCChImplementing

    29/32

    Project Performance Metrics

    FEL Index

    Team Development Index Project Controls Index

  • 8/22/2019 ISPE_CCChImplementing

    30/32

    Results to Date

    2004 benchmarking of capital projects

    determined0.90

    0.95

    1.00

    1.05

    1.10

    1.15

    1.20

    1.25

    1.30

    Industry

    sanofi pasteur 2004

    Pharms

    sanofi pasteur 2002

    Absolute Capital Cost

    0.90

    0.95

    1.00

    1.05

    1.10

    1.15

    1.20

    1.25

    1.30

    Industry

    sanofi pasteur 2004

    Pharms

    sanofi pasteur 2002

    Overall Schedule

    (excluding qualification)

  • 8/22/2019 ISPE_CCChImplementing

    31/32

    Results to Date

    2004 benchmarking of capital projects

    determined Overall, annual savings around $38 MCDN

    Overall, average schedule reduction of 10 months

  • 8/22/2019 ISPE_CCChImplementing

    32/32

    Next Steps

    Predictive Maintenance Value Engineering

    Plant Quality

    Process Reliability

    Design to Capacity

    Technology Selection

    Customizing Standards Waste Minimization

    Constructability Reviews

    Process Simplification

    Energy Optimization

    3D CAD

    IPAs Value Improving Processes: