+ All Categories
Home > Documents > Israel Gas Transmission Project - Israel Trade … 1 of 89 89 PLE601enpro/06.04.dot C:\Documents and...

Israel Gas Transmission Project - Israel Trade … 1 of 89 89 PLE601enpro/06.04.dot C:\Documents and...

Date post: 24-May-2018
Category:
Upload: buiminh
View: 215 times
Download: 1 times
Share this document with a friend
89
Page 1 of 89 89 PLE601enpro/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical Information.doc COMPANY Israel Gas Transmission Project 21/03/2012 Approved BC OA AZ Date Description Prepared Checked Approved Date Approved Document Title General Technical Information COMPANY Representative : A. Zauberman Reference : 179000 Document-No. ENG-CSE-SPC-0013 Rev. 2 Document Originator : B. Carmel CON- TRAC- TOR Dis.- Code Doc.- Type Ser. No.
Transcript

Page 1 of 89 89

PLE601enpro/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical Information.doc

COMPANY

Israel Gas Transmission Project

21/03/2012 Approved BC OA AZ

Date Description Prepared Checked Approved Date Approved

Document Title

General Technical Information

COMPANY Representative : A. Zauberman

Reference : 179000 Document-No.

ENG-CSE-SPC-0013

Rev.

2

Document Originator : B. Carmel CON-

TRAC-TOR

Dis.-

Code

Doc.-

Type

Ser.

No.

Page 2 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

Table of Contents

1 ....................... Background 7

1.1 ................... Description of the Gas Transmission System 7

1.2 ................... Project Goals 8

1.3 ................... Schedule 9

2. ..................... Definitions and Abbreviations 10

3. ..................... Mandatory Documents Codes and Standards (Laws, Codes, Specifications, Norms and Regulations) 11

3.1 ................... Israeli Laws and Standards 11

3.2 ................... Dutch Standards 11

3.3 ................... U.S. – API Standards 11

3.4 ................... U.S. – ANSI/ASME Standards 11

3.5 ................... U.S. – ASTM Standards 12

3.6 ................... International Standards 12

3.7 ................... European Standards 12

3.8 ................... COMPANY Specifications 13

3.9 ................... The “Blue Book” 13

3.10 ................. General Instruction 14

4. ..................... Statutory 16

4.1 ................... Statutory Background 16

4.2 ................... Building Permits 16

5. ..................... Design 18

5.1 ................... Basic Design 18

5.1.1 ................ Design Data for Pipeline Stations 18

5.1.2 ................ Corrosion Protection 19

5.1.3 ................ Crossings 19

5.1.4 ................ Marking of the Pipeline 20

5.1.5 ................ Depth of Cover 20

5.1.6 ................ Pressure Testing 20

5.1.7 ................ Pipeline Stations 21

5.1.8 ................ Pipeline Components 22

5.1.9 ................ Special Construction Considerations 24

5.1.10 .............. Cathodic Protection System 25

5.1.11 .............. Electrical, SCADA, Station Control and Telecommunication System 26

5.2 ................... Design Documents 26

5.3 ................... CONTRACTOR's Review of the Design 27

Page 3 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

5.4 ................... Crossings 27

6. ..................... Sub – Projects General Description 28

6.1 ................... Yessodot to Messilat Tsion (Jerusalem West) and Messilat Tsion to Jerusalem (Jerusalem East) 28

6.2 ................... The Eastern Line: Nehser to NATBAG (Ben Gorion Airport), NATBAG (Ben Gorion Airport) to Nitzaney Oz and Nitzaney Oz to Hagit 29

6.3 ................... Kfar Baruch to Nilit 31

6.4 ................... Dovrat to Ziporit 31

6.5 ................... Ashkelon to Kiryat Gat (doubling) 31

6.6 ................... Mavo Ashdod to Palmachim 32

6.7 ................... Ashdod to Sorek and Sorek to Nesher (doubling) 32

7. ..................... Execution of the Works 34

7.1 ................... General 34

7.2 ................... Environmental Impact Assessment 36

7.3 ................... Traffic Plan 36

7.4 ................... Access to the Right of Way 36

7.5 ................... Route Alignment 36

7.6 ................... Definition of the Working Width 36

7.7 ................... Land Liaison 37

7.8 ................... Marking of the Working Width 37

7.9 ................... Existing Foreign Services 37

7.10 ................. ROW Preparation 37

7.10.1 .............. Clearing the ROW 37

7.10.2 .............. Topsoil Stripping 38

7.10.3 .............. Grading the ROW 38

7.10.4 .............. Cross Spread Accesses 38

7.10.5 .............. Overhead Utility Lines 39

7.10.6 .............. Fluming and Bridging of Watercourses 39

7.10.7 .............. Fencing 39

7.11 ................. Pipe Dumps (Pipe Storage Yards) 39

7.11.1 .............. General 39

7.11.2 .............. Receipt and Inspection of Line Pipe 39

7.11.3 .............. Stacking of Pipes 40

7.12 ................. Load, Haul, and String 40

7.12.1 .............. Pipe Loading 40

7.12.2 .............. Pipe Hauling 40

7.12.3 .............. Pipe Stringing 40

7.13 ................. Trenching 41

7.13.1 .............. Excavation 41

7.13.2 .............. Underground Utility Crossings 42

7.14 ................. Bedding Excavation 42

7.15 ................. Factory Bends and Cold Field Bending 43

Page 4 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

7.16 ................. Pipeline Welding 44

7.16.1 .............. Welding Joints 44

7.17 ................. Non-Destructive Testing 45

7.18 ................. External Coatings 46

7.19 ................. Lower and Lay 46

7.20 ................. Pipeline Crossings 47

7.20.1 .............. General 47

7.20.2 .............. Road Crossings 48

7.20.3 .............. Railroad Crossings 48

7.20.4 .............. Watercourse Crossings 48

7.20.5 .............. Foreign Service Crossings 49

7.21 ................. Cathodic Protection 50

7.22 ................. Intermediate Line Valves and Launcher/ Receiver Stations 50

7.23 ................. Backfilling 51

7.23.1 .............. General 51

7.23.2 .............. As Built Survey 51

7.23.3 .............. Pipe Protection 51

7.23.4 .............. Backfill 51

7.23.5 .............. Pressure Testing, Cleaning, Gauging, Drying and Conservation of Pipeline 52

7.24 ................. Reinstatement 52

7.24.1 .............. General 52

7.24.2 .............. Reinstatement in Agricultural Land 53

7.25 ................. Valve Stations 53

7.26 ................. Completion for operation approbation (Gassing up) 53

7.27 ................. Handover 53

8. ..................... Materials Provided by the COMPANY to the CONTRACTOR: 54

9. ..................... Checking the work conditions by the CONTRACTOR: 55

9.1 ................... Preliminary inquiries 55

9.2 ................... Coordination with other works 55

9.3 ................... Soil investigations 55

10. ................... Site: 56

10.1 ................. Notice to enter the Site 56

10.2 ................. Coordination with Landowners/Landholders 56

10.3 ................. Work Site 56

11. ................... Crossings: 59

11.1 ................. Utilities Detection 59

11.2 ................. Coordination with Utilities Owners/operators and Relevant Authorities 59

11.3 ................. Relocation and protection of existing Utilities: 59

11.4 ................. Supervision by Utilities Owners/operators and Relevant Authorities: 60

Page 5 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

11.5 ................. Work near existing utility systems (infrastructure) 60

12. ................... Quality Control: 62

12.1 ................. General 62

12.2 ................. Inspection of Fabrication, Installation and Construction 63

12.3 ................. Additional Conditions to Ensure the Quality of Works 65

13. ................... Temporary access Roads 66

14. ................... Organization of CONTRACTOR's Site Facilities 67

15. ................... Engineer's Offices 68

15.1 ................. General 68

15.2 ................. Office furniture and equipment per office-room 70

15.3 ................. Office furniture and equipment per Site-office 71

15.4 ................. Kitchen furniture and equipment 71

15.5 ................. Clothing and personal safety items 71

16. ................... Laboratory 73

17. ................... The work team employed by the CONTRACTOR 74

17.1 ................. General 74

17.2 ................. Construction Manager - the CONTRACTOR’s representative 74

17.3 ................. Foreman 74

18. ................... SubCONTRACTORs 76

19. ................... Avoidance of nuisance from the Works 77

20. ................... Traffic Requirements 78

21. ................... Day and night shifts 80

22. ................... Temporary Approaches Bridges, Gangways, and Similar Facilities81

23. ................... Works to be Kept Clear of Water 82

24. ................... Discharge of Water from Works 83

25. ................... Restoration of Existing Ditches and Open Drains 84

Page 6 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

26. ................... Water Supply 85

27. ................... Supply of Electricity 86

28. ................... Surveying and Setting Out 87

28.1 ................. General 87

28.2 ................. Basic Survey 87

28.3 ................. Intermediate Surveys 88

29. ................... Revision Record 89

Page 7 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

1 Background

1.1 Description of the Gas Transmission System

The Government of Israel intends to further develop the natural gas transmission system

based on the updated Master Development Plan (not finalized) of the COMPANY and

the local market demand. This involves the establishment of a natural gas infrastructure

project of national significance. This also entails the introduction of international state-of-

the-art codes and other standards, other authorities procedures, supply security and the

consideration of environmental aspects.

Feed-in to the system are from offshore pipelines from the Israeli production platform

Merry B (Mary B) and an Egyptian supplier (EMG). The battery limit for the system to be

considered is the transmission point to the Receiving stations in Ashkelon and in Ash-

dod. The offshore supply pipelines which are landing in are not part of this manual.

The existing transmission system, which is under operation, is divided into four main

parts: Offshore pipeline Ashdod – Reading (Tel Aviv) – Dor; Phase 1 (Ashdod – Nesher

+ Ashkelon – Qiryat Gat – Soreq); Phase 2 (Qiryat –Gat – Sdom (Dead Sea)); and

Phase 3 – Northern Section (Dor – Tel Kashish – Haifa, Tel Kashish – Alon Tavor). The

existing parts of the system consist of approx. 400 km of onshore and offshore pipeline

with different diameters and 18 gas delivery points to customers (power plants, industrial

areas, cities, etc.).

Up to year 2017, the COMPANY is planning to design, build and operate additional ~

350 km of onshore pipelines and at least 30 gas delivery points to customers (PRMS).

The current development plan of the Company includes the construction of high pres-

sure natural gas transmission pipelines and valve stations in the following sub – projects

(Sections):

Page 8 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

No. Sub Project (Section) Length

(Km)

Pipe dia.

(inch)

1 Yessodot to Messilat Tsion (Jerusalem West) 17 18

2 Nehser to NATBAG (Ben Gorion Airport) 9 36

3 Messilat Tsion to Jerusalem (Jerusalem East) 18 18

4 Eastern Line (South Section) (NATBAG (Ben Gorion

Airport) to Nitzaney Oz)

40 36

5 Eastern Line (North Section) Nitzaney Oz to Hagit 40 36

6 Ashkelon to Kiryat Gat (doubling) 26 30

7 Dovrat to Ziporit 26 18

8 Kfar Baruch to Nilit 15 18

9 Mavo Ashdod to Palmachim 14 18

10 Sorek to Nesher (doubling) 15 30

11 Ashdod to Sorek (doubling) 22 30

Note that Sections 7 – 11 are not included in the Tender (yet may be ordered as Addi-

tional Sections as provided for in the Tender Documents).

1.2 Project Goals

Each of the sub – projects is a vital element in Israel's national natural gas transmission

system, set at providing the power generation facilities and the industry with natural gas

supply.

Page 9 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

1.3 Schedule

The basic schedule is attached as Annex BB4 Schematic Frame Schedule. The updat-

ed and binding Schematic Frame Schedule shall be issued to the CONTRACTOR upon

issuance of the Work Commencement Order.

Detailed schedule for the construction of each of the sub – projects would be provided

separately by to CONTRACTOR for the COMPANY approval prior to the execution of

the works.

Page 10 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

2. Definitions and Abbreviations

QA/QC Quality Assurance / Quality Control

HSE Health, Safety and Environment

ROW Right of Way

COMPANY Israel Natural Gas Lines Ltd. (COMPANY) or its nominated rep-

resentative

CONTRACTOR is the appointed Pipeline Construction Organization and its sub-

CONTRACTORs, performing the Procurement, Construction, In-

stallation and Commissioning for the COMPANY

TAMA National Outline Plan for the Natural Gas Transmission System

in Israel

EP Engineering Plan

Engineer The Chief Construction Works of the Company (The Company

Representative according to the Contract)

Page 11 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

3. Mandatory Documents Codes and Standards (Laws, Codes, Specifications, Norms

and Regulations)

3.1 Israeli Laws and Standards

o Natural Gas Market Law, 5762-2002, January 03, 2002.

o Natural Gas Safety Decree, 5757-1997.

o TAMA 37 – National Outline Plan, November 2001 – Plan Instructions and its all

derivatives.

o Israeli Standards (IS) for building

o IS 413 – Building in Seismic Areas.

o Electricity Law – Israel Electricity Law (Hok Hahashmal)

3.2 Dutch Standards

o NEN 3650-1:2003 Requirements for Pipeline Systems – Part 1: General

o NEN 3650-2:2003 Requirements for Pipeline Systems – Part 2: Steel

o NEN 3651:2003 Supplementary requirements for Steel Pipeline crossing major

public works.

.

3.3 U.S. – API Standards

o API Spec 5L Specification for Line Pipes.

o API RP 5L Recommended Practice for railroad transportation of line pipe.

o API Spec 6D Pipeline Valves

3.4 U.S. – ANSI/ASME Standards

o ASME B16.5 Pipe flanges and flanged fittings

o ASME B16.9 Factory-made wrought iron steel butt welding fittings.

o ASME B16.20 Metallic Gaskets for Pipeline Flanges – Ring Joint, Spiral

Wound and Jacketed.

Page 12 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

3.5 U.S. – ASTM Standards

o ASTM A-105 Specification for forgings, carbon steel for piping components.

o ASTM A-106-B Specification for seamless carbon steel pipe.

o ASTM A234 Specification for piping fittings of wrought carbon steel and alloy

steel for moderate and elevated temperatures.

o ASTM A381 Metal-Arc welded steel pipe for use with High Pressure trans-

mission systems.

o ASTM A694 Carbon and alloy steel forgings for pipe flanges, fittings, valves

and parts for High Pressure transmission service.

3.6 International Standards

o ISO 8501-1 Preparation of Steel Substrates Before Application of Paints

and Related Products-Visual Assessment of Surface Cleanliness - Part 1 - Rust

Grades and Preparation Grades of Uncoated Steel Substrates after Overall Re-

moval of Previous Coatings.

o ISO 15589-1 Petroleum and natural gas industries – Cathodic protection of

pipeline transportation systems – Part 1: on-land pipelines

o ISO 15590-1 Petroleum and natural gas industries – Induction bends, fittings

and flanges for pipeline transportation systems – Part 1: induction bends

o ISO 15590-2 Petroleum and natural gas industries – Induction bends, fittings

and flanges for pipeline transportation systems – Part 2: Fittings

3.7 European Standards

o EN 287 Approval testing of welders.

o EN 1594 Gas supply Systems – Pipelines for maximum operating pressure over

16 bar – Functional requirements

o EN 1708-1 Welding – Basic weld joints details in steel – Part 1: pressurised

components

Page 13 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

o DIN 30670 Polyethylene coatings for steel pipes and fittings; Requirements

and testing.

o EN 10204 Metallic products – Types of inspection documents

o EN 12068 Cathodic protection - External organic coatings for the corrosion pro-

tection of buried or immersed steel pipelines used in conjunction with Cathodic

Protection - Tapes and shrinkable materials

o EN 12327 Gas supply systems – Pressure testing, commissioning and decom-

missioning procedures – Functional requirements

o EN 12732 Gas supply systems - Welding steel pipework - Functional require-

ments

o EN 12954 Cathodic Protection of buried or immersed metallic structures - General

principles and application for pipelines

3.8 COMPANY Specifications

COMPANY Specifications – see Annex BB3

3.9 The “Blue Book”

The following chapters of the General Specification for construction works (published by

the Inter-Ministerial committee for Contract Document Standardization, known as the

Blue Book, may also be referred to where applicable to works being undertaken, within

this Contract:

Chapter 1 – Earthworks

Chapter 2 – Concrete Cast in Site

Chapter 3 – Pre-cast Concrete Products

Chapter 54 – Underground excavation.

More Chapters are relevant in case of missing relevant reference.

The provisions of Chapter 00 – Preliminaries, as well as all provisions for measurements

and payments are not applicable to the Works.

Page 14 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

3.10 General Instruction

The CONTRACTOR shall perform the works in according to the design and the Engi-

neering Plan (EP). The EP includes all relevant codes and STANDARD.

The CONTRACTOR shall fulfill all requirements and obligations under all Clauses of the

Specifications applicable to the Design, Supply, Construction, Installation and Commis-

sioning of works involved in the Contract. Neither the following clauses of this Document

and the detailed description therein, nor the quantities, shall diminish the obligations of

the CONTRACTOR under the Conditions of Contract. All Standards and Norms men-

tioned herein shall be deemed to form part of this Document.

The CONTRACTOR shall inform the COMPANY in writing when there is a conflict be-

tween the “Mandatory Documents” or in case of any updates to any of them.

All references to Codes, Specifications, Standards, Norms and Regulations etc. shall be

to the latest edition or revisions thereof in-force at the time of bidding as specified on the

Contract Documents. Where a standard is referred to in this Specification, another

standard shall not be acceptable, even if it ensures an equal or higher quality of materi-

als and workmanship. The CONTRACTOR shall not order any material or perform any

work until he has obtained the Engineer approval of such standard.

Brand names where used in the Specification are only intended to define a standard of

quality and performance and the CONTRACTOR may use other equivalent products if

approved as equivalent by the Engineer.

The requirements of the last edition Part 1 and Part 2 of NEN 3650 “Requirements for

Pipeline Systems” take priority over all other referenced Codes, Specifications, Stand-

ards, Norms and Regulations.

All the Israeli, Dutch, European and U.S. Codes, Standards, Norms and Regulations

listed in the Israeli Natural Gas Law and in those Codes, Specifications, Standards,

Norms and Regulations mentioned in the Safety Decrees should also apply.

CONTRACTOR shall acknowledge himself with all the documents listed above and addi-

tional ones, as may be necessary, in order to perform the work fully and properly, as re-

quested by the Natural Gas Law and Safety Decrees.

CONTRACTOR shall make himself confident regarding the accuracy and completeness

Page 15 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

of any information included in the laws, Codes, Specifications, Standards, Norms and

Regulations etc. which supply information. CONTRACTOR may have to hire profession-

al services of appropriate professional bodies and their fees should be included in the

unit prices of the CONTRACTOR.

Page 16 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

4. Statutory

4.1 Statutory Background

The work is defined in the following approved statutory plans:

a) National Outline Plan (NOP) for natural gas TAMA 37 / B

b) National Outline Plan (NOP) for natural gas TAMA 37 / A / 1

c) Any other National Outline Plan (NOP) for natural gas which constitute part of or is

based on TAMA 37.

4.2 Building Permits

COMPANY will obtain, by the date of commencement of the works by the CONTRAC-

TOR, the part of the building permits which shall enable the CONTRACTOR to perform

the works in an uninterrupted fashion, subject to fulfillment of all conditions set in the

building permits.

Where the building permits will be provided in stages, as set forth below, the COMPANY

shall obtain and provide that part of the building permits which is sufficient to commence

the works in accordance to the COMPANY's judgment and the schedules approved by

the COMPANY.

The building permits shall include the working strip, the organizational sites, the stations,

the environmental and landscaping requirements and access roads from any existing

paths and roads.

The building permits documents will be provided in Hebrew. Where information is pro-

vided in both Hebrew and English, the Hebrew version will prevail. The translation of

such documents into English shall be carried out by the Contractor at its sole expense.

The CONTRACTOR is fully responsibility to work in full accordance with the terms and

conditions set in the building permits and all the relevant laws and regulations.

The CONTRACTOR's work would be subject to supervision by the relevant permitting

authorities as set in the laws and regulations. The CONTRACTOR is fully responsible to

cooperate with the relevant supervisors and work in full accordance to their instructions.

The CONTRACTOR would be fully responsible to obtain all the permits, including Work

Permits and Excavation Permits required for performing the work. Obtaining all docu-

Page 17 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

ments and permits required for performing the work, beyond the building permits provid-

ed by COMPANY, is under the CONTRACTOR's full and sole responsibility and ex-

pense.

Page 18 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

5. Design

5.1 Basic Design

The principles to be obeyed for project, design, construction, operation and maintenance

of gas pipelines are fixed in the Natural Gas Market Law - 2002, the Gas Law (Safety

and Licensing) – 1989, the Gas Order (Safety and Licensing)(Facilities for Transporting

Natural Gas) – 1997 and furthermore by the National Outline Plan for the Natural Gas

Transmission System in Israel No. 37 (TAMA 37) including all its derivatives.

According to the above Law and the TAMA 37, the design basis for the pipeline system

are the following international standards (latest edition):

o NEN 3650 (Main Standard, by Law*)

o ASME B 31.8

o ASME B 16.5

o ASME B 16.9

o API 5 L

o API 6 D

o API 1104

In addition, other international recognized and accepted codes like EN Standards,

DVGW G Standards, VdTÜV and AD Leaflets, ASME-Guide and ASTM Standards have

been applied on design calculations and material selections.

Transport pipelines shall be designed and constructed in such way that the probability of

a limit state being exceeded during the planned service life is sufficiently low.

Design Pressure (DP) = 80 barg

Design Temperature

Maximum (underground) = +50 °C

Maximum (above ground) = +65 °C

Minimum = -10 °C

5.1.1 Design Data for Pipeline Stations

Page 19 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

Pipelines of the transmission system are "Piggable" therefore using Hot formed bends

must be included and will be fabricated with a minimum radius of R = 10 x D.

In dedicated areas hot formed bends of R= 5 x Dout can be used when decided by the

designer.

The design for the vent stack and bypass diameter is based on need of venting pipeline

section within an hour.

5.1.2 Corrosion Protection

All buried parts and components of the gas transmission system, including the joints and

welds, shall be primarily protected against corrosion with an external coating (Passive

cathodic protection).

For the coating on site shall be prepared.

An temporary active cathodic protection system has to be installed from the begining of

the construction, until the final cathodic protection system has been installed and com-

missened.

5.1.3 Crossings

In crossings with all Highways, National Roads, Railways and selected Municipality

Roads shall be installed without casing pipe if it has been approved by third party owner.

Nevertheless, if the installation can't be done with open cut, the carrier pipe shall be de-

signed for the category of the area where the crossing is located in. The pipeline shall be

laid without bends under roads with an improved surface (asphalt, concrete slabs).

Diameter of pipes used as casings shall be approx. 300 mm larger than the diameter of

the line pipes.

At cased crossings, the fiber optic cable (if applicable) shall be carried through the pipe-

line casing pipes in separate HD-PE cable conduits installed inside the casing pipe.

At water crossings such as small rivers, streams and ditches, the pipeline shall be in-

stalled by the open cut method (if not requested by authorities otherwise) and protected

against buoyancy.

Page 20 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

Crossing of infrastructures, facilities, private lands etc, shall be coordinated with all par-

ties including COMPANY operation department. The coordination should be considered

in the design and construction.

5.1.4 Marking of the Pipeline

Warning Tape

A warning tape shall be placed at 0.3 m above the top of pipe over the whole length of

the pipeline between stations. See spec in Annex BB3

Marker Posts

Marker posts shall be installed to mark the position of the installed pipeline. The location

of marker posts shall be determined during the detail design.

Marker posts to mark the position of the pipeline shall be installed with a spacing of max.

500 m, but all changes of direction and other characteristic points along the route shall

also be identified. Major crossings shall be supplied with pipeline marker posts at both

sides of the crossing. See spec in Annex BB3

5.1.5 Depth of Cover

The depth of cover for the pipelines will be adapted to local conditions. The normal min-

imum depth of cover shall be 1.2 m and in additional the expected erosion for at least 30

years.

The minimum depth of cover at crossings shall be designed considering the minimum

required and third party requirements at crossings.

The actual depth of cover shall be indicated on the Construction Drawings for the rele-

vant crossing sections.

5.1.6 Pressure Testing

Page 21 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

After construction, the pipeline shall be pressure tested to demonstrate the strength of

the pipeline and its leak-tightness, acc. to NEN 3650-2: 2003 and COMPANY specifica-

tion EEN-CSE-SPC-012.

The pipeline shall be subdivided into test sections which maximum lengths should not

exceed 15 km and / or the volume of the sections should not exceed 6000 m3.

The following pressure values are the minimum test pressures (at the highest point of

test section), dependent on class location:

Category Test Fluid Minimum Test Pressure

1 Water 1.5 x DP 2 Water 1.5 x DP 3 Water 1.5 x DP 4 Water 1.5 x DP

Test procedures shall be supplied by the CONTRACTOR for each test section to ensure

that the maximum stress (based on the minimum wall thickness) at the low points shall

not exceed 95% of the Specified Minimum Yield Strength (SMYS) and the stresses at

the high point is minimum 80% of SMYS (based on the maximum wall thickness) of the

pipe material. See spec in Annex BB3

5.1.7 Pipeline Stations

All pipeline equipment which contain above ground components as valve actuator or

hand wheels, scraper traps, vent stacks, etc., shall be installed in fenced areas with

lockable gates to prevent unauthorized access. The ground surface of all pipeline sta-

tions shall be gravel inside the fenced area.

Security measures shall be carried out such as concrete fences and other physical pro-

tection means.

Electrical, Instrumentation (including SCADA), lighting etc, shall be considered also in

accordance with Hazardous Area Classification (Explosion proof devices etc).

The main pipeline shall be laid at a minimum depth of cover of 1.2 m at all Stations.

However if the cover will be less than 1.2 m for design reason additional protection

measures shall be chosen.

Page 22 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

Station piping and -components as valves and fittings shall have a design factor of at

least 2.0, pipes in vent lines usable for blow down operations shall have a design factor

of 2.5.

All valve controls and other equipment which needs to be operated and maintained

should be with easy access and above ground preferably.

Buried valves and other specified items shall be installed on concrete foundations

grouped on concrete plates. All buried equipment shall be electrically insulated from rein-

forced concrete foundations by insulation mats or plates.

To avoid introduction of additional stresses, the equipment should not be fixed on foun-

dations, unless it is stated otherwise or shown in the design. In general, sliding foils will

be placed between foundation and equipment as it is shown on the standard drawings.

5.1.8 Pipeline Components

Line Pipe

Line Pipe shall be spiral or longitudinally welded. All line pipes are factory coated with

polyethylene in accordance with the coating specifications.

Line pipes >DN 450 are internal coated by Epoxy to reduce the roughness of pipe sur-

face and thereby reduce pressure loss.

The material grade for the line pipe shall be as follow:

o pipeline diameter = 36“= X70

o pipeline diameter = 30”= X60

o 24" ≥ pipeline diameter ≥ 20”= X70

o 18" ≥ pipeline diameter ≥ 8“ = X52

o pipeline diameter ≤ 6”= Grade B

Casing Pipes

Casing pipes shall be installed at major crossings as required in the design. Pipes to be

used as casings will be in accordance with API 5L.

Page 23 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

The diameter of the pipes used as casings shall be approx. 300 mm larger than the di-

ameter of the line pipes. The wall thickness and length calculations for the casing pipes

are made employing the German Code VdTÜV 1063.

Casing pipes at road- and railway crossings shall be installed by a closed crossing tech-

nique, and shall be equipped with a coating sufficiently resilient to minimize damage dur-

ing installation.

Line pipes shall be electrically isolated from casings using plastic isolating spacers with

slides and without any metal parts. The annular space between the line pipe and the

casing shall be sealed at both ends. A test post shall be installed at each casing to moni-

tor the effectiveness of the insulation between the line pipe and the casing.

Casing pipe configurations shall be designed with conduits for cathodic protection and fi-

ber optic cables and shall be equipped with the following accessories:

o Isolating spacers

o Polyethylene pads (saddles)

o Thrust blocks and anchors

o Casing end seals

o Cable conduits for the fiber optic cable and a separate cable conduit for

the cathodic protection measurement cable and one spare (three conduits

in total)

Bends

The three types of bends to be used for the “pigable” pipeline sections are hot-formed

bends, field bends and elastic bends.

Hot-formed Bends:

Pipelines of the transmission system are "Piggable" therefore using Hot formed bends

must be included with a minimum radius of R = 10 x D.

In dedicated areas hot formed bends of R= 5 x Dout can be used when decided by the

designer

Page 24 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

The wall thickness has been calculated by the manufacturer in accordance with the re-

quirements of EN Standard No. 13480-3.

Field Bends:

Field Bends shall be made on site according to the relevant specification.

The maximum out-of -roundness of field bends shall not exceed 3 %.

The radius of field bends, taking into consideration bending steps, bending angles and

the length of straight pipes required at each end of a bend shall not be less than 40

times the outside diameter of the pipe.

Elastic Bends

Elastic Bends shall be used for minor changes in direction or elevation and shall not be

less then 1000 times the outside diameter of the pipe. 5.1.9 Special Construction Considerations

Special Soil Conditions

Swampy and Flood Areas

In all areas with a groundwater level (primary or secondary) or potential groundwater

levels (i.e. flood areas) above the pipe bottom, and organic soil, the buoyancy will be

compensated with concrete flotation shells or other constructive measures. The safety

factor against buoyancy shall be 1.3.

Steep Slopes Areas with Soil Erosion

In slope areas, erosion and washout of the soil covering the pipeline is possible. To

avoid this, precautions have to be taken, using one of the following methods:

o Pipe Protection in Washout Area (concrete shells etc.)

o Protection Against Erosion with Sand Bags

o Protection Against Erosion with Sand-Cement Bags

o Protection Against Erosion with Concrete Wall

Page 25 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

Additional unforeseen areas of erosion shall require the CONTRACTOR to engage the

ser- vices of specialists to resolve the various Geographical conditions.

Rocky Areas

In the rocky areas, the pipeline shall have at least 1.2 m cover. In such areas, the pipe-

line shall also be surrounded by sand padding with a thickness of at least 20 cm, and

where necessary additional, with rock shield.

5.1.10 Cathodic Protection System

In accordance with the applicable standards, the entire below ground pipeline system

shall be protected passively by coating and actively by an impressed current cathodic

protection system, which consists of two major components:

1. The CP stations with anode ground beds and transformer / rectifier units and

2. Test points for regular checking of the system operation.

The requirements for operation of a cathodic protection system are listed below:

o the entire pipeline system shall be polyethylene coated

o the pipeline shall be electrically isolated from steel casings and reinforced

foundations at valves, vent stacks and scraper traps

o instrumentation and devices (e. g. electric actuators) require electrical

earthing isolated from the pipeline by insulating couplings

o max. pipeline temperature 50°C

Temporary cathodic protection system shall be installed for the pipeline from the begin-

ning of the construction.

At all points where the soil resistively survey indicates a soil resistively of less than 20

ohms x m, the permanent cathodic protection system shall be installed and energized

immediately after the pipeline has been backfilled. Where this is not possible, a tempo-

Page 26 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

rary cathodic protection system using sacrificial anodes (Mg) or impressed current shall

be installed and operated after backfilling.

The potential criteria of UoffCu/CuSO4 = 0.95 V must be achieved as a minimum.

The CONTRACTOR shall ensure that the temporary cathodic protection systems with

impressed current or Mg anode is adequate for at least 2 years of independent opera-

tion.

5.1.11 Electrical, SCADA, Station Control and Telecommunication System

The main operational requirement for delivery of contracted volumes to the market is to

maintain the flow of natural gas through the pipeline and reduce the downtime to an ab-

solute minimum. This requirement can be achieved by operating the pipeline network as

close as possible to its maximum efficiency enabling rapid identification of abnormal

conditions of flow or growth of unaccounted volumes and verifying instrument inaccura-

cies.

Main criteria to get this achieved is the implementation of reliable field proven state-of-

the-art equipment in combination with a proper redundancy concept for all main electrical

equipment at the stations, for the communication and in the Dispatching Centers.

Pressure regulating and metering stations and block valve / scraper trap stations shall be

designed for unmanned operation. However, at all stations remote operating capabilities

are required.

In case of failure of the Supervisory Control and Data Acquisition (SCADA) system the

control of the stations shall be maintained, so that a hazardous situation can be pre-

vented

5.2 Design Documents

The design documents provided by COMPANY to CONTRACTOR would be based on

initial survey of the Site and the information known to the COMPANY's during the design

phase.

The design is based on the Dutch NEN 3650 code and the COMPANY Basis of Design

which is following EN standards

Page 27 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

The design documents should always be read in conjunction with the relevant building

permits and statutory documents.

See Design references in Annex BB8 to BB13

5.3 CONTRACTOR's Review of the Design

The Contactor is obliged to review the design in consideration of the detailed site condi-

tions, his professional experience and the utilities detection, and advice COMPANY with-

in seven (7) days from receipt of the documents if any comments and / or proposals for

changes and modifications exist.

5.4 Crossings

The design of the crossing has been coordinated with the infrastructure owner and the

relevant authority in order to receive the building permit, if so requested by the Planning

Authority so requested by the Planning Authority. The design is being done in accord-

ance with the mentioned code and standards, surveying, investigations and good engi-

neering practice. However, in all crossing of major obstacles along the pipe route, includ-

ing roads and highways, railroads, streams and any other element identified in the de-

sign documents, the CONTRACTOR shall prepare a detailed working plan and Shop

Drawings in order to assure that the design performed by the COMPANY or the designer

is feasible. The CONTRACTOR will be fully responsible for the detailed working plan and

shop drawings of the crossing.

The detailed working plan of the crossing would be conducted in full accordance to the

conditions set in the statutorily documents

The detailed working plan would be coordinated by the CONTRACTOR with the utility

owners /operators and all the relevant infrastructure owners /operators and relevant au-

thorities.

The work plan and shop drawings would be provided for COMPANY review in sufficient

time to allow detailed review and approval prior to construction

Page 28 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

6. Sub – Projects General Description

6.1 Yessodot to Messilat Tsion (Jerusalem West) and Messilat Tsion to Jerusalem (Je-

rusalem East)

As part of the development of the transmission NG system, the Israeli Committee ap-

proved the NOP TAMA 37/ B for the gas transmission route of the transmission section

V - Phase V – which is the connecting section to Jerusalem.

The pipeline section of 35 km to Jerusalem was divided into two (2) sub – projects (Sec-

tions) because of statutory reasons. The pipeline diameter is 18”.

The First sub – project from YESSODOT to MESSILAT TSION is about 17 km long and

the second sub – project from MESSILAT TSION to BEIT ZAIT is about 18 km long. BE-

IT ZAIT station is not included in this tender.

The number of Sub–project section from YESSODOT to MESSILAT TZION is 1027. See

design in Annex BB9. YESSODOT station is pressurized and under operation. The

work in the station shall be under close supervision of the COMPANY O&M department.

This sub-project (1027) includes three stations: YESSODOT station, HAREL station and

MESSILAT TSION station. The section contains several road crossings and railway

crossing. In addition crossings of other infrastructures such as water lines, oil lines and

communication.

Part of this pipeline section passes in an area which is specified as sensitive by the envi-

ronmental (and “Green”) authorities. MESSILAT TSION station also is located in this ar-

ea. Furthermore, there is an existing oil pipeline which is located in parallel to the planed

NG pipeline (Approximately 3 m to 10 m).

The number of Sub–project section from MESSILAT TSION to BEIT ZAIT (Jerusalem) is

1026. See design in Annex BB11. MESSILAT TSION station does not exist yet.

Page 29 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

This sub-project (1026) includes one station: SHOEVA station. The section is quite

mountainous and contains several road crossings. In addition crossings of other infra-

structures such as water lines, oil lines and communication.

Most of this pipeline section passes in area which is specified as sensitive by the envi-

ronmental (and “Green”) authorities. Furthermore, there is an existing oil pipeline and a

communication cable which are located in parallel to the planed NG pipeline (Approxi-

mately 2 m to 7 m). The working strip in this sub-project is relatively narrow (!) and con-

tains inclined areas.

6.2 The Eastern Line: Nesher to NATBAG (Ben Gorion Airport), NATBAG (Ben Gorion

Airport) to Nitzaney Oz and Nitzaney Oz to Hagit

These sections are a part of the eastern system, connecting from NESHER station to

HAGIT station, according The National Outline Plan (NOP) for natural gas TAMA 37B.

The pipeline diameter is 36".

The length of this pipeline section, from NESHER station to HAGIT station is about 90

km. the section is divided into three sub – projects because of statutorily, building per-

mits scheduling reasons. The First sub – project from NESHER to NATBAG is about 9

km long, the second sub – project from NATBAG to NITZANEY OZ is about 40 km long

and the third sub project from NITZANEY OZ to HAGIT is also about 40 km long.

The number of Sub–project section from NESHER to NATBAG is 1008. See design in

Annex BB8. NESHER station is pressurized and under operation. The work in the sta-

tion shall be under close supervision of the COMPANY O&M department.

This sub-project (1008) includes another PRMS station, NATBAG which is being con-

structed by a local CONTRACTOR. The section contains several road crossings (includ-

Page 30 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

ing Road No. 1 – highway between Tel Aviv and Jerusalem) and railway crossing. In ad-

dition crossings of other infrastructures such as water lines, oil lines and communication.

This section is being characterized as crowded with many infrastructures and relatively

close to residences.

The number of Sub–project section from NATBAG to NITZANEY OZ is 1065. See de-

sign in Annex BB12. NATBAG PRMS station does not exist yet.

This sub-project (1065) includes three stations: GIVAT KOACH station, KESEM (PRMS

in the future) and NIR ELIYAHU. The section contains several road crossings (including

Road No. 6 – main toll highway) including HDD and railway crossings. In addition cross-

ings of other infrastructures such as water lines, oil lines and communication (and more).

This section is generally planned parallel to the railway and Road No. 6. In addition, this

section is being characterized as crowded with many infrastructures and with many pri-

vate land owners.

The number of Sub–project section from NITZANEY OZ to HAGIT is 1066. See design

in Annex BB13. HAGIT PRMS station already exists and the additional outlet to this

sub-project is being constructed by a local CONTRACTOR.

This sub-project (1066) includes four stations: NITZANEY OZ station, MAGAL station,

HARISH (PRMS in the future) and REGAVIM station. The section contains several road

crossings (including Road No. 6 – main toll highway) including HDD and railway cross-

ings. In addition crossings of other infrastructures such as water lines, oil lines and

communication (and more).

This section is generally planned mainly parallel to Road No. 6. In addition, this section

is being characterized as crowded with many infrastructures and with many private land

Page 31 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

owners. The northern part of this section is specified as sensitive by the environmental

(and “Green”) authorities.

6.3 Kfar Baruch to Nilit

As part of the developing of the transmission NG system, the COMPANY is planning to

connect NILIT industry area to the transmission system. This section is planned to be

18” diameter and it is about 15 km long. This Section is not part of the Batches included

in the Tender, yet may be ordered as an Additional Section.

6.4 Dovrat to Ziporit

As part of the developing of the transmission NG system, the COMPANY is planning to

connect ZIPORIT industry area to the transmission system. This section is planned to be

24” diameter and it is about 26 km long. This Section is not part of the Batches included

in the Tender, yet may be ordered as an Additional Section.

6.5 Ashkelon to Kiryat Gat (doubling)

As part of the developing of the transmission NG system the COMPANY has decided to

increase the flow capacity of the existing pipeline between ASHKELON to KIRYAT GAT

based on NOP TAMA 37/A/1. This section is connected with a 24” pipeline and is about

26 km long. The additional pipeline diameter is planned to be 30”.

The number of Sub–project section from ASHKELON to KIRYAT GAT is 1029. See de-

sign in Annex BB10. ASHKELON and KIRYAT GAT stations are pressurized and under

operation. The work in these stations and the intermediate LAPIDOT station shall be un-

der close supervision of the COMPANY O&M department.

This sub-project (1029) includes two stations: LAPIDOT station and KIRYAT GAT sta-

tion. Both stations exist. The section contains several road crossings and railway cross-

ing. In addition crossings of other infrastructures such as water lines, oil lines and com-

munication.

Page 32 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

The new pipeline is planned to be installed next to the existing one at the same NG strip

with a nominal distance of 5 m. in some locations the distance is closer and also cross-

ings. Most of this pipeline is parallel to railway.

6.6 Mavo Ashdod to Palmachim

As part of the developing of the transmission NG system, the COMPANY is planning to

connect desalination plant and Power plants located in PALMACHIM area to the trans-

mission system. This section is planned to be 18” diameter and it is about 14 km long.

This Section is not part of the Batches included in the Tender, yet may be ordered as an

Additional Section.

The number of Sub–project section from MAVO ASHDOD to PALMACHIM is 1004.

This sub-project (1004) includes three stations: MAVO ASHDOD station, SHAFDAN

PRMS station and PALMACHIM PRMS station. The section contains several road cross-

ings. In addition crossings of other infrastructures such as water lines, oil lines and

communication.

The pipeline is planned to be installed next to new 100” water pipeline at the same strip

with a nominal distance of 15 m. in some locations the distance mite be closer. The route

is also parallel to roads and electrical lines.

6.7 Ashdod to Sorek and Sorek to Nesher (doubling)

As part of the developing of the transmission NG system the COMPANY has decided to

increase the flow capacity of the existing pipeline between ASHDOD to NASHER based

on NOP TAMA 37/A/1. This section is connected with a 24” pipeline and is about 37 km

long. This section was divided into two (2) sub-projects because of statutory reasons.

The pipeline diameter is planned to be 30”. These Sections are not part of the Batches

included in the Tender, yet may be ordered as an Additional Section.

Page 33 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

The First sub – project from ASHDOD to SOREK is about 22 km long and the second

sub – project from SOREK to NESHER is about 15 km long.

The number of Sub–project section from ASHDOD to SOREK is 1052. All the stations

are pressurized and under operation. The work in these stations and the intermediate

stations shall be under close supervision of the COMPANY O&M department.

This sub-project (1052) includes three stations: ASHDOD RECIEVING station, KFAR

AVIV station and MEISHAR station. All stations exist. The section contains several road

crossings (including HDD) and railway crossing. In addition crossings of other infrastruc-

tures such as water lines, oil lines and communication.

The number of Sub–project section from SOREK to NESHER is 1062. All the stations

are pressurized and under operation. The work in these stations and the intermediate

stations shall be under close supervision of the COMPANY O&M department.

This sub-project (1062) includes ONE station: SOREK station. YESSODOT station and

NESHER stations are being executed in other sub-projects. All stations exist. The sec-

tion contains several road crossings (including HDD) and railway crossing. In addition

crossings of other infrastructures such as water lines, oil lines and communication.

Both new pipelines are planned to be installed next to the existing one at the same NG

strip with a nominal distance of 5 m. in some locations the distance is closer and also

crossings. The route is also parallel to roads and with vicinity to residences.

Page 34 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

7. Execution of the Works

7.1 General

Pipeline construction activities, by their very nature, are fraught with potential risks of ac-

cidents causing personal injuries. All personnel associated with pipeline construction ac-

tivities, shall undergo a safety induction course specifically related to the pipeline con-

struction industry, upon commencement of employment on the project.

All construction equipment employed on, or associated with, the pipeline construction,

shall be properly maintained and fit for purpose. A schedule of inspection and mainte-

nance shall be developed for all construction equipment.

Particular care shall be taken when operating under or near overhead power lines. The

relevant governing authority shall be consulted, to ascertain their particular requirements

with regard to such working. Height gauges shall be erected on each side of the over-

head power line and the crossing point clearly signposted.

All works will be performed in accordance with the approved design supplied by the

COMPANY and that has been approved by the authorities (“Design”). Any change from

the Design shall be approved in writing by the COMPANY or the Designer.

Preparations Prior to Construction:

o Obtain site access as needed for the construction

o Review COMPANY's design

o Detect existing utilities

o Prepare shop drawings for Crossings

o Coordinate work with utilities owners

o Obtain working permits from utilities owners and relevant authori-

ties

o Prepare and install Quality Control system and supervision

Page 35 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

o Insure that supervision by utilities owners and other relevant au-

thorities will be performed as needed

.

The work to be performed shall include, but is not limited to; the provision of all supervi-

sion, plant, equipment, labour and consumables necessary for the construction, and as-

sociated operations, on the Israel Gas Transmission System as follows:

• Site cleaning

• Excavation including rock excavation.

• Retaining walls and supporting structures.

• Separation and disposal or storage of the topsoil.

• Welding of pipes.

• Coating repairing including coating of the welds.

• Rehabilitation works and backfilling

• Preparation of the trench floor for laying of the pipes and accessories, and con-

struction of the structures.

• Controlled filling and compaction around the pipes, accessories and manhole

structures.

• Construction of embankments and surfaces with controlled compacted backfill.

• Transport of materials to the site, stockpiling and handling.

• Dismantling and bevelling of retaining walls, thrust blocks and thrust walls as re-

quired.

• Testing of pipeline sections including loading tests, tightness tests and non-

destructive testing.

• Restoration of the site surface.

• Dewatering and water removal.

• Other works.

Page 36 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

7.2 Environmental Impact Assessment

The Environmental Impact Assessment was approved during the Detailed Engineering

Phase. The CONTRACTOR is required to implement all the recommendations, and

strictly adhere to all constraints, identified in the Environmental impact Assessment.

7.3 Traffic Plan

Prior to the commencement of any pipeline construction activity, a detailed and compre-

hensive traffic plan shall be developed in close coordination with Local, Regional, and

National Agencies. The traffic plan shall identify all highways, roads, tracks, and access-

es authorised for use by construction traffic. Construction traffic shall not travel on any

public or private land, roads, or tracks, except where expressly permitted to do so by the

traffic plan.

7.4 Access to the Right of Way

Where access is granted from asphalt paved highways and roads, an area of compacted

crushed stone shall be constructed to mitigate damage to the existing road surfaces. All

pipeline stations shall be furnished with all weather access roads. The need for new

roads, or access from existing roads to pipeline stations, shall be determined during the

Detailed Design Phase. All access roads and access points shall be subjected to regular

maintenance and upkeep.

7.5 Route Alignment

Preliminary 1:5,000 scaled Plot Plans are providing the approved route corridor (100 m)

according to the TAMA. During the Detailed Engineering Phase, this route shall be veri-

fied by conducting detailed surveys together with thorough soils and terrain evaluations.

7.6 Definition of the Working Width

The pipeline ROW working width is depending on the pipeline diameter and can be up to

28 m for a 30" pipeline. However, there will be certain areas of restricted working, which

Page 37 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

shall be defined during the Detailed Engineering Phase following approval of the Envi-

ronmental Impact Assessment.

7.7 Land Liaison

Experienced Land Liaison Officers shall be employed, with the prime responsibility of li-

aising with all Landowners, Occupiers, and Local and Regional Authorities along the

pipeline route. Prior to any entry onto the pipeline ROW for construction purposes, the

Land Liaison Officers shall agree and compile a Pre-Entry Condition Log with all land

users.

7.8 Marking of the Working Width

The CONTRACTOR shall establish and maintain permanent reference points along the

pipeline route to create a pipeline geodetic network. The limits of the working width, and

any extra working width required at crossings, shall also be marked by staking. The pipe-

line trench centreline shall be established and any stakes disturbed or removed prior to

the trenching operation shall be replaced.

Kilometre point markers shall be placed at the ROW boundaries for progress reporting

purposes. Stakes and markers shall not be removed until ROW restoration. Any perma-

nent reference point disturbed or removed shall be immediately replaced.

7.9 Existing Foreign Services

Liaison shall be established with Local and Regional Authorities to identify and locate all

known foreign service crossings, both overhead and underground. All foreign services

shall be located, adequately protected, and clearly signposted throughout the construc-

tion period.

7.10 ROW Preparation

7.10.1 Clearing the ROW

The contractor shall clean the Site before commencement of the works. All existing tree

stumps, saplings, bushes, and scrub within the working width shall be taken off site to an

Page 38 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

approved disposal area. All ROW clearing debris shall be removed offsite, and shall not

be allowed to foul watercourses. The burning of brushwood or any other material is not

permitted on the ROW. Saleable timber shall be cut into manageable lengths and

stacked to the side of the ROW, for disposal as directed. Care shall be taken to protect

all survey markers during the operations.

7.10.2 Topsoil Stripping

The Pre-Entry Condition Log will define areas to be topsoil stripped. Where topsoil strip

is requested for the full working width, the full depth of topsoil (to a maximum depth of 30

cm) shall be pushed to the running track side of the ROW to ensure topsoil and subsoil

remain segregated during the trenching operations. In areas of wetlands and peat, top-

soil stripping should be avoided where possible, to maximise the ground bearing capaci-

ty of the soils.

7.10.3 Grading the ROW

The working width shall be graded, only as much as to provide a safe and level running

track and working strip, and where practical, minimise the requirement for cold field

bending. Grading operations shall be confined to the limits of the working width, and any

agreed additional working areas. Specific procedures shall be developed for the grading

or benching of steep slopes and side slopes. Under no circumstances are the banks of

any watercourse to be breached, until such time as crossing installation is imminent.

Survey markers removed during grading operations shall be replaced.

7.10.4 Cross Spread Accesses

Where directed by the Pre-Entry Condition Log, accesses shall be provided across the

working width for landowners, pedestrian, and livestock traffic. Care shall be taken to

fence off potential danger areas such as open excavations, spoil heaps, and other such

obstructions.

Page 39 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

7.10.5 Overhead Utility Lines

The particular requirements of the Governing Authorities for overhead utility lines with

regard to safety barriers and warning signs shall be strictly observed. Crossing points

must be clearly identifiable by construction equipment operators.

7.10.6 Fluming and Bridging of Watercourses

All natural watercourses shall be flumed or bridged, and designed in order to maintain

flow and minimise disturbance. Special consideration shall be given to seasonal varia-

tions in flow, with regard to flume pipe sizing, and freeboard under bridges. The crossing

point shall be constructed to effect a smooth and safe transition between the crossing

and the running track. Construction equipment shall not be permitted to ford watercours-

es.

7.10.7 Fencing

The CONTRACTOR shall supply and install fences along the working strip. The fences

shall be made of at least 3 mm fabric (wire mesh).

7.11 Pipe Dumps (Pipe Storage Yards)

7.11.1 General

In order to avoid excessively long hauls to, and from the ROW, it is inevitable that sever-

al pipe storage dumps will be necessary along the route. Suitable and acceptable loca-

tions shall be selected, and agreements negotiated with the Landowner/Occupiers. Local

Authorities must be consulted in order to obtain the necessary temporary planning con-

sent. The locations of all temporary pipe dumps must be taken into consideration when

formulating the traffic plan.

7.11.2 Receipt and Inspection of Line Pipe

A formal computerised control system shall be developed and approved, for recording

materials throughout receipt, storage, issue, and installation. Pipe lengths shall be han-

dled by using slings, pipe hooks, and spreader bars, suitably protected to prevent pipe

Page 40 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

and coating damage. Tag lines shall be attached to both ends of the pipe, to control

movement when the pipe is in the slung position. The pipe lengths shall be inspected

during offloading and all defects shall be marked. Where practical, coating repairs shall

be effected prior to load out.

7.11.3 Stacking of Pipes

All lifting plant and equipment shall be suitably padded, to avoid damage to the pipe or

coating during offloading/stacking. Pipes shall be stacked on timber or steel grillages,

suitably cushioned to avoid pipe coating damage; or on sand rows, covered with a poly-

thene sheeting material. Pipes of differing wall thickness shall be stacked separately.

7.12 Load, Haul, and String

7.12.1 Pipe Loading

Pipes shall be loaded and unloaded using side booms or cranes. Tag lines shall be at-

tached to control pipe movement when in the slung position. Lengths of pipe shall be

separated by protective pads, or nylon rope hoops. Where trailer side supports are used

to secure loads, they shall be padded to prevent coating damage. Nylon straps or similar

shall be used for securing pipes to trailers, strap tightening buckle devices shall not

make contact with the pipe coating.

7.12.2 Pipe Hauling

Road hauling trailers shall be purpose rigged, and fitted with fender guards to prevent

road debris damaging the pipe coating on the overhang. All pipe hauling activities shall

comply with the approved traffic plan. Sufficient trailers shall be employed to ensure a

continuous supply of line pipe to the stringing operations.

7.12.3 Pipe Stringing

Whenever possible, pipe lengths shall be strung directly from road going transport.

Where ground or weather conditions do not allow this, pole trailers and tractor units, or

pipe carriers shall be used. Pipe lengths shall be supported on pack pads and timber

Page 41 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

skids, or other approved methods. Changes in line pipe wall thickness shall be designat-

ed on the alignment sheets. Gaps in the stringing shall be left where requested by land-

owners, and beneath overhead power lines.

7.13 Trenching

7.13.1 Excavation

The excavation/rock excavation works shall be carried out in accordance with the work

safety instructions (revised version) and work safety regulations (construction works), as

well as any additional and updated instruction of the Ministry of Labor and the Safety and

Hygiene Institute relating thereto, and any relevant additional law.

The excavation works include:

• Excavation. • Storage of the excavated material and separation of topsoil, which is suitable for

backfill. • Loading, transport from the site and dispersion of the surplus material at a dump-

ing site to be determined by the COMPANY. • Any additional work required for proper performance of the excavation works

The centreline of the trench shall be marked by the construction survey team. Generally,

in reasonable ground conditions, the trench is dug with conventional backhoes. The

trench bottom width shall exceed the pipe diameter by the specified margin, to ensure

proper backfilling and compaction.

The trench bottom shall be prepared to permit even bedding of the pipe, and shall be

free of all objects and material, which could be injurious to the pipe or coating. Minor var-

iations in contour shall be excavated to minimise cold field bending. In rocky ground

conditions, heavy backhoes, rippers, and hydraulic hammers may be necessary. In are-

as of hard rock conditions, a rocktrencher should be considered.

Page 42 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

Excavated spoil shall be deposited at a safe distance from the lip of the trench, to mini-

mise the possibility of trench collapse. Open trenches shall be kept free of water. Where

conventional pumping equipment is inadequate, dewatering systems must be consid-

ered. Whenever necessary, trench support systems shall be installed to safeguard the

stability of the excavation.

7.13.2 Underground Utility Crossings

Prior to any excavation activity in the vicinity of existing underground utilities, the authori-

ty having jurisdiction over the service shall be notified. Such notification, shall allow suffi-

cient time for the relevant authority to have a representative present, during the excava-

tion operation. All utilities at crossings shall be fully exposed, and where necessary ade-

quately supported or relocated.

7.14 Bedding Excavation

On completion of the excavation, sand bedding has to be performed. The layer thickness

should be 0,2m. The surface of the excavation base shall be free of all defects that are

liable to cause local loads on the pipeline. In addition, the soil on the excavation base

must be free of all organic material, stones, rocks, boulders and waste.

During the course of trench excavation, the excavation base shall be deepened by about

20 cm below the planned pipe laying depth. The resultant empty space shall be filled

with a bedding layer as detailed in the drawings.

Details see COMPANY Specification EEN-CSE-SPC-010 and EEN-CSE-SPC-014.

The natural granular bedding shall be compacted, as shown in the drawings. In places

where natural subsoil of the following types is exposed at the base of the excavation, it

shall be removed and replaced with compacted fill, as indicated in the drawings:

• Soft material (clay and/or granular material with a density less than 85% Stand-

ard Proctor).

Page 43 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

• Hard material (composed of rock and/or soil with a density higher than 98%

Standard Proctor).

• Soils subject to swelling (clay and/or soils containing organic material).

• Unstable soils.

The pipes shall be laid only after the height is checked and approved by a licensed sur-

veyor and an approval is obtained from the COMPANY.

Soil that is excavated at the site or imported, free of waste and organic matter, and with

a content of fines and gravel as shown in the drawings, shall be suitable for use as gran-

ular material. The CONTRACTOR shall conduct laboratory tests to the extent required

before confirming compliance with the detailed requirements.

7.15 Factory Bends and Cold Field Bending

Where the use of cold field bending is impractical, factory made hot formed bends shall

be used. A hot bend schedule shall be produced, initially from the alignment sheets, and

to be confirmed by the bending engineer’s survey. Hot bends shall be of a minimum ra-

dius of 5 D, and shall have a tangent/pup piece welded to both ends, to correspond to

the adjacent line pipe wall thickness.

For cold field bending, detailed procedures shall be produced and qualified, prior to any

production line bending. Pipe shall be bent by using a Bending Machine supplied with

lined bending shoes, and an expanding mandrel.

Pipes shall not be bent within 1 m of a girth weld, or 2 m from the ends of a pipe length.

Pipe lengths shall be placed in the bending machine, with the longitudinal weld seam

(where applicable) in the neutral axis. Combination bends shall have the longitudinal

weld seam placed as close as is possible to the neutral axis.

On completion of the bending operation, the pipe shall be gauged, and examined for

wrinkles, buckles, ovality, or any other signs of mechanical damage. Should the bending

Page 44 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

operations show a trend to damaging the pipe coating, all bending operations shall

cease, until the cause has been established and rectified.

7.16 Pipeline Welding

All welding works for the Natural Gas Piping, will be performed in accordance with weld-

ing procedures approved for the Natural Gas Project regardless of previous qualification

that the CONTRACTOR might have. The welding processes will be performed by the

CONTRACTOR and should include all data required in NEN 3650-2, Appendix C1, and

EN 288-2 / EN 15614.

All welders and welding operators should undergo authorization for the Gas Project ac-

cording to the requirements in NEN 3650-2, Appendix C1, and EN 287-1.

All authorizations will be performed EC (European Committee) accredited 3rd party or

approved by an EC accredited Notified Body, experienced in Dutch Standards / NEN

Procedures and approved by the COMPANY.

All pipelines welding shall be carried out in accordance with NEN EN 12732 and sup-

plementary and/or deviating provision of NEN 3650-2, Appendix C.

The provisions of project specification Field Welding – EEN-CSE-SPC-001, should be

met.

7.16.1 Welding Joints

The fabrication and inspection Standard is NEN 3650-2, Appendix C and NEN-EN

12732, and specification EEN-CSE-SPC-001.

All welding joints will be visually inspected and non-destructive tested, according to

NEN-EN 12732, para. 8.

All welding consumables for gas pipelines shall be according to the relevant EN Stand-

ard. The material certificates shall be in accordance with requirements of the Standard

EN 10204 Type 3.1..

After removing the original wrapping, all electrodes will be protected and stored in ac-

cordance with manufacturer's requirements so that their quality and welding properties

should not be damaged.

Page 45 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

Field welding is generally carried out by the utilisation of A special point welding crew

followed by the main line welding crew and at last the Tie-In crew.

Welding Procedure Specifications shall be established, to meet the requirements of

Specification NEN 3650, latest edition, Welding of Pipelines and Related Facilities. The

Welding Procedure Specifications, shall be qualified by none destructive testing and

mechanical testing to demonstrate that welds having the suitable quality and soundness,

can be continuously produced. Girth welding may be undertaken by automatic, or man-

ual welding processes.

Welding procedures, and each welder or welding operator, shall be qualified to ensure

compliance with NEN 3650. The qualified welding procedure shall specify pre-heating

and interpass temperatures, and postweld heat treatment followed when: materials,

welding consumables, mechanical restraints, or weather conditions, make any or all of

them necessary.

Section tie-in welding is generally carried out utilising separate fully equipped crews,

with full provision being made for lifting and positioning, without imposing undue stress-

es on the line pipe.

7.17 Non-Destructive Testing

Radiographic tests of pipeline walls will be done according to Standard NEN 3650-2 Ap-

pendix C. Examination of the radiographic photography will be done according to EN

1435 and EN 12732. The requirements of specification: EEN-CSE-SPC-002 should be

met.

Full and detailed non-destructive procedures shall be developed in accordance with

Specification NEN 3650, latest edition, and submitted for approval. Radiographic proce-

Page 46 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

dures shall be qualified, and all production radiography shall be in accordance with the

approved procedures.

All tests required will be performed by authorized laboratories in accordance with ISO

17025 by a certified body or organization. The tests results should comply with the re-

quirements according to EN 12732 and EEN-CSE-SPC-002. All butt welds shall be

100% tested by X-Ray.

7.18 External Coatings

Buried line pipe shall be externally factory coated with a 3-layer FBE polyethylene coat-

ing system. Field joints, uncoated pipes and factory made hot bends shall be coated with

a tape system according to EN 12068, clas C50, which shall be used exclusively. The to-

tal system thickness shall be 3.2 mm after application..

Material storage requirements, and field application, shall be in strict accordance with the

latest manufacturer’s published recommendations and procedures.

All buried coating systems shall be inspected both visually, and by holiday detection, in

accordance with the Contract Codes, Standards, and Specifications.

7.19 Lower and Lay

Prior lower and lay, the line survey for as built and the padding and backfill operation has

to be organized in order to minimize the time between in between them. The duration be-

tween lower and lay and padding shall never be more than 1 day. Backfilling should be

completed within 3 working days

Line pipe shall be lifted and handled at all times, in a manner which shall minimise dam-

age to the pipe coating, and avoid overstressing the pipe. The “A” frames of side booms,

and any other surface likely to cause damage, shall be padded to afford protection to the

pipe coating.

Page 47 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

Side-booms shall be equally spaced along the pipe section, to avoid overstressing the

pipe during the lowering in operations. Quick release wide belt (width of belt minimum

0.5 times pipe diameter) lifting straps shall be used to lift the pipe section. While the pipe

is in the slung position, the final coating inspection shall be carried out on areas previ-

ously inaccessible.

Prior to lowering in the pipe, the trench bottom shall be inspected for the presence of the

required sand bedding of 0.2 m, sharp objects, or any other extraneous material, and

where necessary cleaned out. The bottom of the trench shall be prepared in a way to

provide continuous and even support and protection to the pipe.

The pipe section shall be lowered off in a safe and controlled manner, ensuring, no con-

tact is made with the trench sides, that the pipe is positioned to afford all round protec-

tion of backfill, and in such a way that the lifting straps can be released and withdrawn

without damaging the pipe coating.

The minimum bending radius for elastic bending is shown in the relevant specification.

Immediately after lowering and lay, the survey has to be performed and padding with

sand up to 20cm on top of pipe has to be executed

7.20 Pipeline Crossings

7.20.1 General

Detailed crossing procedures and method statements, for each type of crossing, shall be

developed and submitted for approval. In the case of crossings classified as major, site

specific drawings, procedures and method statements shall be developed.

Consideration should be given to the importance, and specific location of each crossing,

with regard to pre-testing the fabrication prior to installation.

Excavation on open-cut crossings shall not commence unless the fabrication is complete

and accepted, and all the necessary plant, equipment labour and materials are onsite.

Page 48 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

Crossing installations should be a continuous operation until completion has been

achieved.

7.20.2 Road Crossings

Unless specified elsewhere, all roads and tracks not classed as major, shall be installed

by the open-cut method. Crossing installation shall be carried out in a manner that shall

minimise disruption to traffic, pedestrians, and the public in general.

Where necessary, or instructed, temporary traffic bypasses shall be constructed, giving

consideration to the Statutory and Local Authority requirements for warning signs and

hazard lighting. Where paved roads are to be crossed, the paving shall be saw-cut prior

to excavation, to ensure a smooth transition when reinstated. Cutting shall be done with

a cutting machine of approved type, following which the CONTRACTOR shall remove

the asphalt layer, taking care to ensure the integrity of the asphalt section beyond the

removed section. The CONTRACTOR shall haul and dispose the removed asphalt lay-

ers in a waste disposal dumping site approved by the COMPANY.

Major roads and highways shall generally be crossed using the auger, or thrust boring

technique. Cased crossings shall only be installed where explicitly requested by the

Governing Authority. Major roads and highways shall be site-specific crossings.

7.20.3 Railroad Crossings

Railroad crossings, shall generally be bored and cased crossings, and subject to the

Statutory Safety Regulations and the particular requirements of the Authority exercising

jurisdiction over the crossing. All railroad crossings shall be site-specific crossings.

7.20.4 Watercourse Crossings

Generally, all natural watercourse crossings shall be installed by the open cut method,

and subject to the approval of the Government Agency exercising jurisdiction over the

Page 49 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

crossing. Particular attention shall be given to any environmental constraints placed up-

on the individual crossing, and to watercourse crossings in general. The depth of cover

from the true bed level to the top of pipe shall be not less than 1.5 m. Above ground

crossings shall not be used.

Under no circumstances shall the banks of any watercourse be breached, until installa-

tion of the fabrication is imminent.

Various construction techniques are used for open-cut watercourse crossings, and as-

sessment should be made on a case-by-case basis, which shall dictate the particular

technique to be adopted.

For drainage ditches and dykes, where annual ditch cleaning is likely to occur, a protec-

tive concrete slab should be placed in the backfill. The slab should be situated a mini-

mum of 30 cm below the firm ditch bottom.

Pre-cast concrete irrigation channels shall normally be crossed by one of the bored

crossing techniques, to avoid disturbance and disruption to the irrigation system.

In natural wetlands, areas of peat, floodplains, and areas with high ground water tables,

consideration shall be given to the installation of concrete saddle weights or gravel filled

saddlebags, for buoyancy control.

7.20.5 Foreign Service Crossings

The location of underground services intersecting the pipeline trench shall be determined

in advance of construction activities, to prevent damage to such utilities. A minimum

clearance of 30 cm shall be maintained between the outside surface of the pipeline, and

the outside surface of the foreign service.

Page 50 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

7.21 Cathodic Protection

The pipeline system shall be protected against external corrosion, by a cathodic protec-

tion system designed in accordance with NEN EN 12964 and NEN 50162. The cathodic

protection system shall be designed to meet a 40 year life span.

“Instantaneous off” potentials along the entire pipeline route, of (-) 950 mV versus a

Cu/CuSO4 reference electrode shall be achieved.

Protection shall be applied in two stages, a temporary system shall be installed during

pipe laying activities, to protect the system until such time as the permanent cathodic

protection system becomes operational.

Immediately following backfill and hydrostatic testing, a coating integrity survey i.e. Pear-

son Survey by CP current drainage shall be carried out like specified by COMPANY.. All

coating defects identified shall be excavated and investigated, and where necessary, re-

pairs effected.

7.22 Intermediate Line Valves and Launcher/ Receiver Stations

Intermediate line valve and scraper launcher / receiver stations are located along the

pipeline route in accordance with the design and environmental requirements. The line

valves will be normally buried and either manual or electrically operated.

Each station will have an electrical cabinet equipped with air conditioning for housing

UPS, electrical panels and panels for lighting, security and Scada.

All stations will have adequate security fencing to prevent third party intrusion, with main

vehicle entrance gates, and emergency evacuation personnel gates. All weather access

roads shall be provided to all line valve stations.

Details are shown on the relevant drawings and documents.

Page 51 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

7.23 Backfilling

7.23.1 General

All pipeline backfilling shall follow as closely as possible to the lower and lay operations.

Therefore the contractor shall coordinate all operations in advanced. The CONTRAC-

TOR has the responsibility to ensure (where possible), that the trench is kept free of wa-

ter during backfilling.

7.23.2 As Built Survey

Prior to the commencement of any backfilling, survey crews shall record all the data

necessary for the as built survey, to comply with the requirements of the Contract Docu-

ments and Specifications.

7.23.3 Pipe Protection

Care shall be taken during the initial stages of backfilling to ensure that the intimate

backfill reaches around and under, all quadrants of the pipe. Initial stage backfill should

be carried out by backhoes, in order to place the material around and over the pipe, and

to avoid dropping the backfill from an unacceptable height.

Where suitable intimate backfill cannot be imported, or achieved by screening, a rock-

guard type material shall be used to protect the pipe coating. Under no circumstances

shall topsoil be utilised as intimate backfill.

7.23.4 Backfill

When the initial stage backfill has been compacted, second stage backfill can be ac-

complished by pushing in the native material with bulldozers, working at right angles to

the trench line. Backfill material shall be free of carbonaceous material i.e. tree roots,

branches etc. Backfilling shall be completed in not more than 30 cm compacted layers.

Each subsequent layer being properly compacted to the same consistency as the sur-

rounding soil, up to the underside of the topsoil level.

Page 52 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

In areas of rock, the rock shall not be backfilled to an elevation higher than the surround-

ing original level. All surplus rock shall be removed from site to an approved disposal ar-

ea.

Where indicated on the alignment sheets, or where directed by the COMPANY, erosion

protection trench plugs shall be installed during the backfill operations to prevent trench

washout. Where applicable a suitable drain to a soakaway shall be installed.

7.23.5 Pressure Testing, Cleaning, Gauging, Drying and Conservation of Pipeline

At the start of the construction work, contractor shall provide a pressure test planning in

regard to maximum section volume and elevation difference, in order to minimize the

number of test sections and consequently to minimize the number of "Golden Welds" to

a minimum.

After completion of a pipeline section, a hydraulic pressure test (strength and tightness

test) has to be performed in accordance to INGL specification EEN-CSE-SPC-012.

Cleaning of the pipeline section may be performed together with the water filling opera-

tion. After successful pressure testing, the pipeline section has to be gauged.

Drying of the pipeline section shall normally be done with foam pigs and pre dried air to a

dew point of -25ºC or lower. Detailed requirements are specified in EEN-CSE-SPC-015.

The dew point of the pipeline or a part system has to be kept and monitored until the fi-

nal handing over.

7.24 Reinstatement

7.24.1 General

The ROW shall be restored as closely as possible to the pre-construction condition. All

requirements of the Environmental Impact Assessment, the Pre-Entry Condition Log,

and Local and Government Authorities shall be strictly observed.

As soon as is possible after backfilling, in areas where there is evidence of compaction

or rutting, the subsoil shall be ripped or ploughed, to leave the soil in a loose and friable

Page 53 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

condition. Prior to any topsoil placement, all surplus material and construction debris

shall be hauled offsite to an approved disposal area.

7.24.2 Reinstatement in Agricultural Land

Following the loosening of subsoil, the topsoil shall be replaced across the working

width, ensuring that an even distribution is achieved. The topsoil shall be graded and

tilled to leave a smooth, workable, and natural appearance to match the original con-

tours.

7.25 Valve Stations

Build intermediate block valve stations. Perform all Earthworks; preparation, and pipe

works; Perform civil and concrete works; Perform electrical and instrumentation works

and other works in accordance with the design.

7.26 Completion for operation approbation (Gassing up)

Submit all documents as per the quality plan required for obtaining the Gas Authority’s

approval for operation.

7.27 Handover

Prepare As Built documentation, Support COMPANY in gassing up of the system; Test,

commission and handover to COMPANY.

Page 54 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

8. Materials Provided by the COMPANY to the CONTRACTOR:

The CONTRACTOR would be provided by COMPANY with the natural gas pipes, fittings

and valves in various diameters as required to perform the works.

All the other materials required for the full performance of the works would be provided

by the CONTRACTOR.

The CONTRACTOR will return all unused material to COMPANY’s storage together with

a report based on the AS BUILT that shows that all other materials were installed.

The unused materials shall be returned with all quality documents and without defects.

Materials with defects or can’t be used, will not be accepted in COMPANY’s storage and

the CONTRACTOR will be charged with the material costs.

Page 55 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

9. Checking the work conditions by the CONTRACTOR:

9.1 Preliminary inquiries

The CONTRACTOR must, before starting the Works, consult and coordinate with the

Engineer, the relevant authorities, the holders of land rights and any kind of utility own-

ers/operators, in order to obtain information on the following matters:

o Irrigation systems

o Third party installations.

o Permits required for conducting work in the working site.

o Permits for temporary use of land outside the working site for the storage of ma-

terials and equipment, maintenance of equipment, temporary structures, storage

and removal of soil and waste, and for any other activity required for the execu-

tion of the Works.

9.2 Coordination with other works

The Works under this contract may coincide with the work of other CONTRACTORs.

Upon Engineer’s instructions, the CONTRACTOR must promptly and without compensa-

tion, allow any person or organization to perform work at or near the site. The CON-

TRACTORCONTRACTOR must coordinate this work and allow the use, of facilities in-

stalled by him, to the extent possible.

9.3 Soil investigations

The CONTRACTOR shall check and verify the subsurface conditions along the pipeline

route. The CONTRACTOR shall visit the work site, and thoroughly check the conditions,

the soil, services, access roads, structures, and shall base his proposal on his findings. It

is emphasized that the CONTRACTOR must conduct his own responsibility and expense

site and laboratory tests (including of laboratories outside the site) for the performance of

his work. The Engineer will not accept any claim related to the CONTRACTOR’s

knowledge or lack of knowledge of the soil and working conditions.

Page 56 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

10. Site:

10.1 Notice to enter the Site

COMPANY would provide the Land Owners along the route the legal notice as provided

for under relevant law.

The notice to the landowners would cover the entire working strip, and access roads and

the mobilizations areas, per the relevant building permit documents.

10.2 Coordination with Landowners/Landholders

The CCONTRACTOR is required to coordinate the entrance to the site with each of the

landowners/holders along the route. This will be done in coordination with the Engineer.

The CONTRACTOR is required to plan the construction activities in consideration of the

detailed evaluation of each of the work section characteristics and landownership details.

Should the CONTRACTOR be of the opinion that additional land is needed for the con-

struction of the project, for access roads and/or mobilization sites, it shall be his full re-

sponsibility for obtaining those sites, including the approval of the relevant authori-

tiesCONTRACTOR.

10.3 Work Site

The areas within the Site of Works in which the CONTRACTOR will be permitted to exe-

cute the Works, to assemble his equipment, materials, plants and tools, to erect his

stores and to accommodate his personnel , as well as the rights of way for access to the

said areas, shall be coordinated by the CONTRACTOR with the relevant agencies. The

Engineer will determine the final limits of the above areas in co-operation and mutual

agreement with the relevant authorities and these areas shall be deemed to be sufficient

for the performance of the Works by the CONTRACTOR. Before entering any areas the

CONTRACTOR shall make all necessary arrangements with the relevant third parties

and agencies. The CONTRACTOR shall fence the areas while any Work is in progress,

so as to prevent any accident and he shall take full responsibility for preventing unau-

thorized persons from entering the Site of the Works.

Page 57 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

The work area along the pipelines route (“working strip”) is as shown on the drawings.

Prior to commencement of the Works, the CONTRACTOR shall record the working strip

area and surroundings by means of a video movie. The working strip excludes areas in

which the full width may not be realized. The CONTRACTOR is not allowed to deviate

from the working strip and make use of any land outside the working strip without written

agreement from the holders of land rights, operators of adjacent service lines, relevant

authorities and the Engineer. In addition, the CONTRACTOR is not allowed to place

equipment or perform activities within services line limits, roads, and yards of houses,

even if these extend into the working strip, without written agreements. Before starting

the Works, the CONTRACTOR must obtain the required agreements, permits and ap-

provals from the relevant authorities, from the holders of land rights, utility owners/ oper-

ators, and the Engineer (hereinafter “permits”). The CONTRACTOR must show the per-

mits to the Engineer, upon request, including among others:

o Permits for performing the Works within the working strip.

o Permits for the temporary use of access roads to the working strip.

o Permits for the temporary use of land outside the working strip limits for storage

of materials and equipment, maintenance of equipment, erection of offices for the

CONTRACTOR’s and the Engineer , storage and removal of excess soil and

waste materials, and any other activity needed for the execution of the Works.

The CONTRACTOR shall bear on its sole expense, all the costs for all the taxes, com-

pensations, payments and other expenditures for obtaining the permits and the fulfill-

ment of their conditions, and for the preparation of access roads (if required), the prepa-

ration of areas, erections of temporary structures, support and for all other work within

the working strip. The CONTRACTOR shall be responsible for all damages to property

and persons made by him, within and outside the working strip.

The CONTRACTOR must study the conditions prevailing within the working strip before

commencement of the Works. No consideration will be given to any claim, by the CON-

Page 58 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

TRACTOR, which is directly or indirectly related to his knowledge, or lack of knowledge,

of conditions prevailing in the working area or working strip.

Page 59 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

11. Crossings:

11.1 Utilities Detection

Prior to construction the CCONTRACTOR is required to detect in detail all utilities along

the route and those that might be affected from the construction activities.

The detection of the utilities would include coordination with the utility companies and au-

thorities, including obtaining their supervision for the detection works, detailed topo-

graphical survey, performing of trial pits, electronic detection and all other activity re-

quired for full and detailed detection of the utilities.

The CONTRACTOR is fully responsible, at his own cost, to detect and identify all utilities

within the site and/or effecting his work.

11.2 Coordination with Utilities Owners/operators and Relevant Authorities

All works, including detection and construction in the vicinity of existing utilities, should

be performed in full coordination with the owners/operators companies and authorities.

All work should be coordinated by the CONTRACTOR with all the relevant authorities in

accordance to the regulations and relevant laws and performed only after obtaining full

permission by the CONTRACTOR.

11.3 Relocation and protection of existing Utilities:

The site has not been cleared from existing utilities at the site boundaries and as stated,

the CONTRACTOR is required to detect the existing utilities in detail and assess their

impact on the construction.

Following the detection and coordination with the utilities owners by the CONTRACTOR,

the design would be updated by COMPANY to reflect the activities required to either pro-

tect or relocate the existing utilities

The CONTRACTOR is fully responsible to provide the utilities information in sufficient

time to allow the design update. All delays and or changes due to late or incomplete in-

formation would be under the CONTRACTOR's full responsibility.

Page 60 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

The CONTRACTOR would be fully responsible to perform the relocation and / or protec-

tion works in full accordance to the design and schedule.

The following are some of the works to be required:

o Infrastructure for communication lines

o Water supply lines and systems.

o Irrigation lines and systems

o Sewage lines and systems

11.4 Supervision by Utilities Owners/operators and Relevant Authorities:

The CONTRACTOR would be fully responsible to coordinate with the utility own-

ers/operators and relevant authorities for their supervision during the construction.

11.5 Work near existing utility systems (infrastructure)

Any damage caused to existing utilities or interference with their operation is a criminal

offence. The CONTRACTOR bears sole responsibility for any damage to property and

harm to persons, and for irreversible damage to the environment (pollution of soil and

water, etc.). The CONTRACTOR shall bear the direct and indirect consequences and

expenses resulting from his activities.

Any work by the CONTRACTOR near existing utility systems such as but not limited to

electricity, power, lighting, control lines, communication, fuel, gas, water, sewage drain-

age etc. ("utility systems"), must be performed with utmost care, in order to ensure the

integrity and functioning of the existing utility systems. Excavation near these utility sys-

tems shall be performed in the presence of the Engineer and of official representatives

of the operators/owners of the lines. Ensuring the presence of the supervision represent-

ing to the utility operators/owners is the responsibility of the CONTRACTOR and the cost

of this supervision shall be borne solely by the CONTRACTOR.

In any case when damage is caused to buried or exposed piping, as a result of the

CONTRACTORs activities, the damage shall be repaired immediately upon and as in-

structed by Engineer. The CONTRACTOR shall bear the sole responsibility for all costs

and for all other consequences of the damage.

Page 61 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

Before starting the Works, the CONTRACTOR must establish the exact location of the

various utility systems, within and near his work area. The exact location of the utility

systems must be established by detecting equipment, test pits etc. The test pits must be

performed in the presence of the Engineer, and in the presence of the Representative

appointed by the relevant agency, third party or authority, in charge of operating the utili-

ty systems.

The CONTRACTOR shall immediately notify the Engineer of any deviation between the

location of the utility systems, as detected in the field, and its location as shown on

plans. All expenses for activities in connection with the securing the integrity of utility

systems shall be borne solely by the CONTRACTOR. These activities include excava-

tion of test pits for the detection of buried pipes, cables and trenches, the use of special

detecting equipment, gathering information, and coordination with the authorities and the

utility owners/operators.

Obtaining of permits, planning the relocation of utility systems, whether performed by the

CONTRACTOR or by the designer representing the owner/operator of the utility sys-

tems, coordination before and during execution of the Works near utility systems and

systems are the CONTRACTORs responsibility, with approval of Engineer. The Engi-

neer will not recognize any claim related to the identification, on plans, of the buried utili-

ty systems.

The CONTRACTOR shall comply with all local requirements for safe working in close

proximity to existing roads and (aboveground and underground) utilities such as fuel

pipelines and other services. The CONTRACTOR shall establish adequate emergency

procedures according to the instruction of the relevant utility systems operators in con-

sultation with them and the Engineer.

Page 62 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

12. Quality Control:

12.1 General

The CONTRACTOR shall establish an independent Quality Control (QC) plan for super-

vising the Works and checking the quality of the Works, the materials, plant and equip-

ment incorporated in the Works, and the quality of all manufactured parts of the Works,

such as concrete, metal components, welding, painting, and related works, and testing of

completed installations and all surveying. No work shall be performed until the Q.C. Unit

has approved the preceding Work

The approval by COMPANY would be provided by a local supervision firm and the Third

Party COMPANY.

Work would be considered as approved only once an approval by COMPANY though the

local supervision firm and the Third Party COMPANY has been obtained.

The Q.C. shall be a permanent organization staffed by qualified personnel experienced

in their respective fields. The organization, staff and procedures related to Q.C. require

the approval of the Engineer. All activities of Q.C. shall be performed in accordance with

the Standards specified in the Contract Documents and when required in the presence

of the Engineer.

COMPANY’s Supervisor shall witness all testing activities. The Engineer shall receive at

least 72 hours advance notice of any QC activities to be performed on Site, and a longer

period, established by the Engineer, for tests to be performed off Site. Each test result

shall be presented to the Engineer for his approval not later than 24 hour after being per-

formed, with sufficient copies for the Engineer records. All test results shall be filed by

Q.C. in an orderly and easily accessible manner and shall be submitted for inspection

and approval by the Engineer. Furthermore, Q.C. shall record and submit all required

analyses of the test results to the Engineer for his approval.

When the Engineer considers it necessary, it may order re-testing or additional standard

or non-standard tests at the CONTRACTOR’s expense. These shall be performed on

Site by Q.C. or by an independent testing agency, as instructed by the Engineer.

Prior to commencing the construction activities, the CONTRACTOR shall present a fully-

detailed QC program of his proposed Q.C. activities for the Engineer approval, including

Page 63 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

details of all staff, timetable, equipment, laboratory facilities, procedure, administration,

etc. that he intends employing in performing Q.C. In his staff details, the CONTRACTOR

shall include the name and qualifications of his Chief Q.C. Supervisor and the names

and qualifications of the Sub- Supervisors in charge of the various disciplines.

Prior to purchasing any equipment and materials for inclusion in the Works, the CON-

TRACTOR shall present, for the Engineer approval, the manufacturer's specification for

the said items and details of the Q.C. Procedure to be adopted in order to ensure that

they are up to Standard. The CONTRACTOR will be permitted to order the materials on-

ly after all the above requirements have been approved by the Engineer.

CONTRACTOR shall implement an Inspection procedure to assure the full traceability of

piping parts by marking all pipe segments with low stress-dye stamping after cutting and

by recording their location. The CONTRACTOR shall also monitor and record all the

changes and all the relevant data, on drawings, registration sheets, as required by Spec-

ifications Procedures and by the Engineer per the Special Specifications.

12.2 Inspection of Fabrication, Installation and Construction

Inspection: Supervision will be performed by Managing Firm.

In addition COMPANY will appoint a Third Party COMPANY that shall have the power to

perform on behalf of the COMPANY, the following inspection and approval works:

o Checking and certifying the welding procedures

o Witnessing and certifying the welding procedure tests including the results of the

related NDT and destructive testing including

o Yield test

o Bending test

o Tensile test

o Macro grinding investigation

o Witnessing and certifying of Cadweld-welding

o Checking welder certificates

o Witness and certifying welder qualification tests

o Inspection of the pipe-laying/installation and welding work of the pipeline/stations

Page 64 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

o Review and approve the documents of NDT carried out during construction

o The pipe book in respect to the installed pipes and other material

o The completeness of the NDT documents

o Acceptance documentation of the hydrostatic and tightness tests

o Issue of the provisional Certificate in respect to hydrostatic and tightness test and

available safety equipment

o Issue of final certificate

The COMPANY and the Inspector on its behalf, shall have access at any time to any lo-

cation where works related to fabrication, installation or construction are being done and

the CONTRACTOR shall cooperate and give all the necessary assistance to enable an

effective inspection of the works at any time.

The COMPANY and the Inspector on its behalf will be entitled to supervise the fabrica-

tion, installation and construction at all stages and processes, but this supervision or lack

of supervision or fulfillment of the COMPANY requirements shall not relieve the CON-

TRACTOR from his sole responsibility to the quality of the works, their accuracy and ful-

fillment of all conditions in the Contract. The CONTRACTOR shall repair at his expense

any defect and damage discovered, immediately upon discovering the defect or damage.

The COMPANY will check the prefabricated works before bringing them to the construc-

tion sites and will confirm its acceptance, if in his opinion they will suit the specification

requirements. The COMPANY will not receive any work unless it has been approved by

the Inspector as aforesaid, however the Inspector’s approval of the work’s quality and

receipt by the COMPANY as well as the Inspector’s approval of the fabrication, installa-

tion and construction, shall not release the CONTRACTOR of his full responsibility to the

quality and accuracy of the construction in accordance with the specification, or from any

other obligation whatsoever related to the Contract Conditions.

Page 65 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

12.3 Additional Conditions to Ensure the Quality of Works

In addition to all that is said in the Contract documents, following are the detailed re-

quirements of the CONTRACTOR, to ensure the fabrication quality.

The Quality Inspector on behalf of the CONTRACTOR shall be present during all stages

of the work in the workshop where works are performed and on site, and shall coordinate

the inspections that will be done by the Inspector of the COMPANY.

The framework of the inspections and responsibility for execution are as detailed in the

COMPANY Specifications. The Quality Inspector on behalf of the CONTRACTOR shall

submit a Check Form signed by him at each stage, properly filled, for approval of the

COMPANY’s Inspector.

This framework may be extended and applied for all the activities of the project, even if

they are not included in this Specification.

It is emphasized that for Natural Gas Piping, fabrication works, welding and checking will

be done in accordance with the Dutch Standard NEN 3650.2003-1, Chapter 9 and as

mentioned in the relevant paragraphs above NEN 3650.2003-2, Appendix C and the

Special Specifications . The CONTRACTOR should apply the maximum between NEN

requirements and COMPANY’s specifications as above mentioned.

Page 66 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

13. Temporary access Roads

The CONTRACTOR shall coordinate with the relevant authorities and utility own-

ers/operators, the possible use of existing roads for access to the Site, as well as the

temporary construction of access roads from the existing roads to the Site, and all other

bypass roads and internal Site roads, as may be required. Including traffic and road de-

sign and precautions.

These roads will be available to the CONTRACTOR and others, and the CONTRACTOR

shall have the right of access to the Site and within the Site through these roads. The ex-

isting roads, curbs and other existing paved areas shall be adequately protected, and

any portions which may become damaged as a result of the Works under this Contract

shall be replaced and repaired immediately without cost to the COMPANY. All necessary

traffic safety gear required by the authorities to allow such use shall be also at the CON-

TRACTOR expense. The CONTRACTOR shall maintain the access roads to the Site

during his Work. For this purpose he shall keep at the Site, equipment, materials, grader,

water-tanker, foreman, workers whenever needed for the maintenance works. The

CONTRACTOR shall have no rights to claim any additional payments or extension of

time, because of problems caused by road conditions. Prior to leaving the Site the CON-

TRACTOR shall make good all temporary and permanent roads used by him.

Page 67 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

14. Organization of CONTRACTOR's Site Facilities

The "Building Permit" includes a specific number of CONTRACTOR fenced organization

camps as shown on the drawings.

If the CONTRACTOR wishes to establish some camp in a different location it shall be his

responsibility to obtain all the necessary permits and approvals from the relevant authori-

ties and from the land owners.

The CONTRACTOR will be permitted to establish his Site facilities for performing the

Works, in accordance with the conditions specified in the permits he obtained from the

relevant authorities, and according to the written instructions of the Engineer. The CON-

TRACTOR shall exhibit the permits whenever he will be required to do so. No plant,

equipment, materials or temporary structures shall be located outside the areas allotted

to the CONTRACTOR's Site facilities. Upon completion of the Contract and as approved

by the Engineer the CONTRACTOR shall remove his plant and equipment, materials

and temporary structures, except for structures which the Engineer and the CONTRAC-

TOR shall agree upon. Prior to establishing any Site facilities the CONTRACTOR shall

submit detailed plans of these facilities for the Engineer approval. After the approval, the

CONTRACTOR shall prepare the area.

Page 68 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

15. Engineer's Offices

15.1 General

All Site accommodation and equipment for the Engineer's Site staff shall be new. Se-

cond-hand equipment shall not be permitted unless approved in writing by the Engineer.

The office accommodation at each spread/ and CONTRACTORs head offices for the

sole use of the Engineer and his staff shall be under one roof and comprise the follow-

ing:

Nine (9) lockable offices each of minimum floor area of 10.0 m2each. .

o One conference room, of minimum floor area of 15.0 m2, with separate access,

to be well organized and equipped for visitors.

o One kitchen of minimum floor area of 10.0 m2.

o Two toilets (1 male 1 female) with hand wash basins.

o One separate shower room with shower cubicle.

o The offices, conference room and kitchen shall be fully air-conditioned and heat-

ed.

The following telephone connections shall be supplied by the CONTRACTOR for the

Engineer’s use:

o A telephone switchboard with a separate connection to the telephone exchange,

with 8 extensions; to the Engineer's offices, conference room, and kitchen.

o A separate connection to the telephone exchange for the Fax machine.

The communication, whether by Bezeq or cellular, is under the responsibility of the

CONTRACTOR and it must be fully operational one week prior to commencement of

works.

All telephone bills shall be paid by the CONTRACTOR. Broad band access to Internet

shall be arranged and paid by the CONTRACTOR with guaranteed round the clock ser-

vice.

4 telephones and 1 plain paper fax machine shall be supplied by the CONTRACTOR for

the Engineers use.

Page 69 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

Offices and other accommodation shall be erected, decorated, furnished, equipped and

made ready for occupation within 14 working days from the Date of Commencement of

the Works.

The layout and location of the accommodation shall be submitted to the Engineer for ap-

proval, prior to commencement of installation.

All accommodation shall be lockable, with three keys provided for each lock. A suitable

security system shall be installed to protect the accommodation.

The accommodation shall be properly supported and erected to the manufacturer in-

structions. Floor level within the accommodation shall be as stipulated by the Engineer.

Window area shall be 40% of the floor area with opening windows being 20% of the floor

area. All windows shall be fitted with external shutters that can be secured internally.

The electricity supply to the offices (for heating, air-conditioning, lighting and all charges)

shall be to 240V. All internal wiring shall be well secured.

Every office/rooms shall be provided with adequate sockets for power supply (minimum

4 no. per office/room).

The accommodation shall be connected to a potable water supply and drainage shall be

to the public sewerage system or septic tank at the CONTRACTORs expense. All instal-

lation work shall be in accordance with current appropriate regulations and by-laws.

All toilets shall have a flushing W.C. and all washing facilities shall be provided with hot

and cold running water.

The CONTRACTOR shall provide for the cleaning of the Engineer's accommodation on

a daily basis and provide an adequate supply of consumable items (toilet rolls, soap), a

weekly laundering service, a fully equipped first aid kit, adequate fire extinguishers and

smoke detection equipment for the full duration of the Contract.

The CONTRACTOR shall provide adequate waste disposal receptacles and dispose of

domestic rubbish on a regular basis as agreed with the Engineer.

Adequate car park spaces are to be provided (4 cars minimum) close to the accommo-

dation for the sole use of the Engineer staff. The access road, parking area and connect-

ing footways to the accommodation shall be properly surfaced, drained, kept free of

mud, debris and obstructions.

Page 70 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

On completion of the Contract, the CONTRACTOR shall remove the accommodation,

break out and remove all surfacing, hard standing, foundations and debris, seal and

grout any abandoned drains and return the site to as near its original condition as possi-

ble to the satisfaction of the Engineer.

The CONTRACTOR shall provide, maintain, clean and replace, as necessary, the follow-

ing items for the sole use of the Engineer and his staff, for the full duration of the Con-

tract:

15.2 Office furniture and equipment per office-room

All equipment shall be new and shall be maintained in full working order throughout the

project

o Writing desks with lockable drawers and chairs with arm rests * 2

o Office chairs * 4

o A0 size 6 drawer chest * 1

o Table (approx. 4.0m x 1.5m) * 1

o Incidental table (fax, photocopier and associated parts) * 1

o Steel lockable 4 drawer filing cabinet complete with inserts * 2

o Lockable cupboard (nominal size 1.8m high x 0.9m wide x 0.5m deep) * 1

o 3-tier filing basket * 2

o Adjustable desk top lamps * 2

o Length of shelving * 3.0 m

o Pin board (2.4m x 1.2m) * 2

o PC with the following minimum requirements: Pentium IV minimum 2600 MHz

processor, with a minimum 40 GB hard disk, 52 speed CD/ DVD drive, CD writer

(CDRW), 3.5" disc drive, minimum 256 MB RAM, ISDN Modem with e-mail and

fax connection, a minimum 17" colour SVGA display. The following programs

shall be installed on the PC: Windows XP, Microsoft Office XP professional, MS

Project (as per instructed version), Adobe file creator for five stations, Autocad

(as per instructed version) for five stations only and Volo view. Floppy 3.5 "discs

and rewritable CD discs as required throughout the contract and internet connec-

tion * 2.

Page 71 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

o A HP A4/A3 colour ink jet printer or similar approved with paper, toner, and relat-

ed facilities as required throughout the contract. * 1

o Ancillaries: waste paper bins, staplers, hole punches, coat hooks, doormats,

boot scrapers, to under office facilities complete in all respects.

15.3 Office furniture and equipment per Site-office

o Plain Paper Fax, with toner cartridges as required throughout the contract * 1

o Photocopier A3/A4, with full reducing enlarging and document handling facilities,

with paper, toner, and related facilities as required throughout the contract * 1.

o A HP A4/A3 colour ink jet printer or similar approved with paper, toner, and relat-

ed facilities as required throughout the contract * 1.

o TV set and video playback machine (including any necessary licenses) * 1

15.4 Kitchen furniture and equipment

The CONTRACTOR shall provide, maintain, clean and replace the following items as

necessary for the full duration of the Contract:

o Chairs * 10.

o Sink and water heater * 1

o Microwave oven 800 watts with carousel,/or 4 ring electric cooker with full size

oven * 1

o Electric kettle * 1

o Electric refrigerator with freezer compartment * 1

o Cooler for Mineral Water * 1

o Sufficient crockery, cutlery and kitchen utensils for four people and occasional

visitors.

15.5 Clothing and personal safety items

The CONTRACTOR shall provide, maintain clean and replace the following items as

necessary for the full duration of the Contract.

Page 72 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

o Protective clothing as required including overalls, waterproof suits/overalls, safety

helmets (with lamp clips and ear protectors), safety boots (all boots shall have

200 joule toe and under sole protection), safety goggles, protective gloves as re-

quired (approx. 50 pairs) * 7

o Intrinsically safe waterproof hand lamps (batteries as required) * 3

o Miners cap lamps with batteries and chargers * 3

o Electronic combined gas detectors, capable of testing for oxygen, carbon dioxide,

carbon monoxide, hydrogen sulfide and flammable gases, complete with batter-

ies and mains charger. * 2

o 10-minute emergency life support set * 6

o Full safety harness with 35m safety line * 2

Page 73 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

16. Laboratory

The CONTRACTOR shall contact a competent laboratory as approved by the Engineer

to carry out laboratory testing of materials and workmanship as required by the Engineer

or these Specifications. The location of the laboratory shall require the prior approval of

the Engineer. The CONTRACTOR shall not be allowed to start any work on Site prior to

the laboratory being established to the Engineer satisfaction. All costs relate to testing of

the works and materials, including but not limited to, establishing the laboratory, taking

samples and performance of the tests shall be born solely by the CONTRACTOR.

Page 74 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

17. The work team employed by the CONTRACTOR

17.1 General

The CONTRACTOR’s work team for the execution of the Works must include an em-

ployee in charge solely for safety (reference is also made to CSA-38-E) of the Works,

not engaged with any other duties on behalf of the CONTRACTOR.

17.2 Construction Manager - the CONTRACTOR’s representative

The CONTRACTORCONTRACTOR must employ a Construction Manager experienced

in the work performed under the present contract. The Construction Manager shall be

responsible for the execution of the work at the site. The engineer’s name, qualifications

and experience shall be submitted to the Engineer, and the Engineer must give written

approval for his employment. The engineer shall have minimum 10 years experience in

the works performed under the contract. The Construction Manager shall be the officially

appointed representative of the CONTRACTOR at the site. The Construction Manager

must be present at the site continuously throughout work period and must maintain full

and close contact with the Engineer. The official contact between the CONTRACTOR

and the Engineer shall be maintained by means of the site-engineer. The Engineer may

instruct the CCONTRACTOR to replace the site-engineer if, in the Engineer opinion, the

site-engineer does not fulfill his duties satisfactory or if his qualifications are inadequate

for the performance of the work. Upon the Engineer instruction an engineer with ade-

quate qualifications shall replace the site-engineer, within 7 calendar days. The Engineer

decision in this matter is final.

17.3 Foreman

The Construction Manager shall conduct the managing of the work by means of a fore-

man, qualified by the ministry of Labour or other authority. The foreman must be experi-

enced in managing works similar to those included in the present contract. The foreman

shall be present at the site during all working hours and for the entire period of the work.

A foreman, qualified by the ministry of Labour or other authority, shall manage the work

of any subCONTRACTOR, engaged by the CONTRACTOR. The subCONTRACTOR’s

foreman shall represent the subCONTRACTOR, but the overall management of the work

shall be the responsibility of the CONTRACTOR’s Construction Manager. The Engineer

Page 75 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

must approve the CONTRACTOR’s foreman and sub CONTRACTORs. The minimal re-

quired experience of the foreman is 6 years in work similar to that performed under the

present contract.

Page 76 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

18. SubCONTRACTORs

The engagement of any subCONTRACTOR requires prior approval by the Engineer.

The CONTRACTOR must immediately replace the subCONTRACTOR or any of his

workers if the Engineer requests such a replacement. The CONTRACTOR is not entitled

to any compensation or work extension because of the replacement of his subCON-

TRACTOR or any of his workers.

Page 77 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

19. Avoidance of nuisance from the Works

The CONTRACTOR shall comply with the requirements of the relevant Israeli Authorities

for avoiding "Noise and Pollution" nuisance, and shall use the best practicable means to

ensure that all plant used on the construction of the works shall be suitably maintained to

meet the above-mentioned regulation.

The permissible noise levels on site may be further restricted by local regulations should

justifiable complaints be received.

In order to assure compliance with the requirements of the law, the CONTRACTOR shall

use all good engineering practice that may be required to reduce the amount of noise

from his equipment.

Page 78 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

20. Traffic Requirements

Where ramps are required, they shall be provided and maintained to a standard suitable

in all respects for the class or classes of traffic or pedestrians requiring using them.

The CONTRACTOR shall take all reasonable steps to prevent vehicles entering and

leaving the Site from depositing mud or other debris on the surface of adjacent roads or

footways, and shall remove expeditiously any materials so deposited.

Traffic and work on existing roads used for transportation or any other purpose, shall on-

ly be executed by vehicles fitted with pneumatic tires. The CONTRACTOR, as specified

in the technical specifications herein, shall repair any damage, which may be caused to

the existing roads and/or pavements and surfaces and to the full satisfaction of the Engi-

neer.

The CONTRACTOR shall be responsible for arranging any road and footpath diversions

or closures he requires with the relevant third parties. The CONTRACTOR shall allow

adequate time so that all requirements and procedures are followed and approvals ob-

tained without delay to the Works.

If the Engineer shall be required to organize these closures, all associated charges shall

be re-charged to the CONTRACTOR.

The CONTRACTOR shall note that local roads are narrow and were not intended for

construction Site traffic. Due consideration shall be given to the size, weight and speed

of vehicles delivering labor, plant, goods and materials to site.

The CONTRACTOR shall plan, supply and place devices needed for safe traffic at the

site and for incoming and outgoing traffic, during the entire Works period. The CON-

TRACTOR must submit a traffic arrangement plan for approval by the Engineer and for

obtaining permits from the relevant authorities.

The coordination for obtaining the required permits from the authorities is the sole re-

sponsibility for the CONTRACTOR. The CONTRACTOR must implement the temporary

traffic arrangements. The CONTRACTOR must implement the permit requirements giv-

en by the authorities, whether these requirements are given to him, directly of indirectly

by means of the Engineer. It is the CONTRACTOR’s specific duty to ensure the opera-

Page 79 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

tion and integrity of the equipment and devices for the safe traffic during the work at the

site.

Page 80 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

21. Day and night shifts

The CONTRACTOR is not entitled to any change in unit prices because of work at night,

whether such work shall be required by the Engineer or will be required by the CON-

TRACTOR, and approved by the Engineer, in order to meet the time- schedule.

Page 81 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

22. Temporary Approaches Bridges, Gangways, and Similar Facilities

The CONTRACTOR shall provide and maintain without extra charge all such fenced ap-

proaches, gangways, bridges and ladders as may be necessary for safe and expeditious

access to different parts of the Works. Particularly, the CONTRACTOR shall provide

means of access to enable the adjacent occupiers to carry on their normal occupation,

and shall indemnify the COMPANY against any claims for loss of business of amenities.

All approaches or gangways to mortar, concrete or block work upon which workmen are

required to tread shall be provided with grids to enable the men to clean their feet, and

the CONTRACTOR shall control such means of access as may be necessary and, es-

pecially in wet weather, shall provide suitable means to prevent fouling of mortar, con-

crete or block work with marl, clay or other foreign materials.

Page 82 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

23. Works to be Kept Clear of Water

The CONTRACTOR shall keep the whole of the Works at all times during construction

free from water, and shall perform all shuttering, pumping or diversion of surface and

groundwater, as may be necessary in carrying out the Works under dry conditions. He

shall pay special attention to the protection, from water damage, of pipelines, roads,

plant, equipment and materials that have been brought to Site. At every point in the

Works, at which water is liable to accumulate, proper drains and, if required, sump holes

or wells shall be formed. Such sump holes shall be placed entirely outside the limits of

the Works. Any pumping that may be necessary during the shaft sinking or subsequent-

ly, shall be so conducted from such sump holes that no wash or disturbance of the bot-

tom or sides of the excavations shall occur. During the process of casting any concrete,

or performing any other work, the water in the sump holes shall be maintained below the

lowest level of such work. In cases of foundations and trenches, the water shall be kept

at least 50 cm below the bottom of the excavation. The water shall be led to such sump

holes or wells by specially constructed drains, which shall, if necessary, be carried

across the concrete or other works in troughs. Unless required for shaft construction,

dewatering or lowering groundwater level is not permitted.

Page 83 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

24. Discharge of Water from Works

The CONTRACTOR shall make such provision for the discharge of any water, whether

fouled or discoloured or otherwise, from the Works as shall be satisfactory to the Engi-

neer and to any persons having rights over the lands or water courses where such water

is discharged and in full coordination with the authorities and in accordance to the regu-

lations. The CONTRACTOR shall hold the COMPANY indemnified against any claim

that may be made through non-compliance with this Clause.

In the event of there being any interference with the existing land or road drainage due to

the construction of the Works or to damping of spills, within or outside the limits of the

Works, the CONTRACTOR shall take immediate steps to restore the drainage to the sat-

isfaction of the Engineer, the COMPANY, occupiers, or the authority concerned.

Page 84 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

25. Restoration of Existing Ditches and Open Drains

Where existing ditches or open drains are crossed they shall be kept open for as long as

may be required to allow for the passage of the actual quantity of water (taking into ac-

count the season). On completion of the Works, the ditch or drain shall be restored over

the working width to a condition at least equal to that existed before the commencement

of the Works.

Page 85 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

26. Water Supply

The CONTRACTOR shall supply, at his own expense, the necessary quantities of water

required to perform the Works including pressure tests. The CONTRACTOR at his own

expense shall make the connection to the water supply point, under arrangements that

will require the prior approval of the Engineer. The CONTRACTOR at his own expense

shall provide all the means necessary for the transport of water from the said connection

point to the points of use. The quantities of water to be supplied to the CONTRACTOR at

the connection point will be subject, first, to the supply conditions coordinated with the

supplier, and second, to the total water requirements at the Site (for use by CONTRAC-

TOR and others). The CONTRACTOR must provide reserve water storage and sufficient

water supply where necessary. Any delays and expenses due to inadequate water sup-

ply shall be born solely by the CONTRACTOR

Prior to commencement of work the CONTRACTOR's would obtain all the approvals for

the water quality and usages by the Relevant Authorities.

Page 86 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

27. Supply of Electricity

The CONTRACTOR shall supply any electricity necessary to construct the Works by

means of a generator. The CONTRACTOR shall make the connection of electricity to a

connection point on Site, the details of which shall be subject to the prior approval of the

Engineer. The CONTRACTOR shall also supply the cables, transformers, condensers,

equipment and accessories necessary for supplying electricity from the connection point

to the points of use. All electrical installations must be installed according to Israel Elec-

trical Regulations, and must be certified by Certified Electrical Control Management. If so

required by the Engineer, the CONTRACTOR shall make available a copy of all certifi-

cates prepared upon completion of electrical installations and prepared for all required

periodic checks. The CONTRACTOR shall appoint a competent person to be solely re-

sponsible for ensuring the safety of all temporary electric equipment on Site.

Page 87 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

28. Surveying and Setting Out

28.1 General

The CONTRACTOR shall perform all surveying, setting out, control and measurement of

Works, specified and/or required by the Engineer. The CONTRACTOR shall retain a

Chartered Surveyor, and other qualified surveying personnel, on Site, throughout the

performance of the Contract, for executing all survey and measurement operations. The

CONTRACTOR shall keep permanently on Site the required surveying instruments of

type and quantity approved by the Engineer. The CONTRACTOR shall verify the accu-

racy of the Site maps provided with the Contract Documents including the location and

elevation of each benchmark relative to official government beacons. The CONTRAC-

TOR shall replace missing benchmarks. The CONTRACTOR shall confirm his ac-

ceptance of the benchmarks in writing. All surveying activities shall be performed with

the knowledge and approval of the Engineer who shall be given prior notification well in

advance of any such intended work. Upon completion of any surveying the CONTRAC-

TOR shall present to the Engineer all the pertinent data for checking and approval, how-

ever this shall not relieve the CONTRACTOR of the sole responsibility for their accuracy.

28.2 Basic Survey

The CONTRACTOR shall be provided by Engineer with a Baseline which shall be

marked in the drawings and a list of coordinates, including elevations, benchmarks with

defined coordinates, which shall be marked (by the CONTRACTOR), on Site. The CON-

TRACTOR shall secure the existing benchmarks, increase their number as required, and

shall keep the baseline during the execution of the Works enabling its reestablishment

as needed or as instructed by the Engineer.

The CONTRACTOR shall check and verify the accuracy and validity of the markings

(Baselines) given to him before the commencement of the Works at the Site and shall

mark the pipeline centreline and the locations of shafts, and shall submit them to the En-

gineer approval. Should the CONTRACTOR wish to dispute any level he shall submit to

the Engineer a schedule of the position of the levels considered being at error, and a set

of revised levels. The existing ground, relevant to the disputed levels, shall not be dis-

turbed before the Engineer decision as to the correct levels is given.

Page 88 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

Within 10 Calendar days from OTC the Works, the CONTRACTOR shall carry out a

topographical survey of the CONTRACTOR’s yards on Site, as well as the surrounding

areas extending at least 25 meters beyond the borders of the CONTRACTOR’s yards.

The CONTRACTOR shall submit to the Engineer the following survey data:

o Full records of fieldwork including original field books dated and certified by the

Chartered Surveyor.

o A topographical map based upon above survey, drawn to a scale of 1:250 with

contour intervals of 0.5 m.

o All above and underground utilities and services.

o Blocks and Parcels.

o Land ownerships.

o Cross-sections to a scale of 1:100 showing locations and elevations. The Engi-

neer will, after receipt of the above documents, check the surveys and will issue

a "First Survey Certificate" acknowledging acceptance of the above survey mate-

rial that shall be deemed to be the "Basic survey" for the location of the Works.

28.3 Intermediate Surveys

The CONTRACTOR shall perform intermediate surveys to verify compliance with the

tolerances, and shall submit the results of said surveys to the Engineer. The survey shall

be performed weekly or every 50m advance according to the Engineer instructions. The

method of survey shall be at the CONTRACTOR’s discretion provided the method cho-

sen is customary for such surveys. The field books of such intermediate surveys shall be

made available to the Engineer, if he so requires. The CONTRACTOR shall afford full

opportunity for the Engineer surveyor to perform intermediate surveys within the pipeline

whenever the Engineer will require doing such survey. In that case, the Engineer will

give the CONTRACTOR a prior notice of 24 hours.

Page 89 of 89 89

Document Title: General Technical Information Document No.: ENG-CSE-SPC-0013

Revision: 2 Date: 21/03/2012 CoversheetForm_601e_proCOMPANY/06.04.dot C:\Documents and Settings\zauberman\Documentum\Checkout\ENG-CSE-SPC-013 General Technical

Information.doc

29. Revision Record

Rev. Date Description Prepared Checked Approved Date Approved

No.

1 14/03/2012 Internal review B CAR-

MEL O AZ-ULAY

A ZAU-BERMAN


Recommended