+ All Categories
Home > Documents > IT Services SDLC, Peer and Gate Review Approach September 2011.

IT Services SDLC, Peer and Gate Review Approach September 2011.

Date post: 17-Dec-2015
Category:
Upload: ethelbert-jordan
View: 220 times
Download: 5 times
Share this document with a friend
Popular Tags:
24
IT Services SDLC, Peer and Gate Review Approach September 2011
Transcript
Page 1: IT Services SDLC, Peer and Gate Review Approach September 2011.

IT Services

SDLC, Peer and Gate Review Approach

September 2011

Page 2: IT Services SDLC, Peer and Gate Review Approach September 2011.

Agenda

• Review three supported Methodologies Project Life Cycle Software Development Life Cycle Scrum

• Review Peer and Gate Review Approaches within methodologies

• Q&A

Page 3: IT Services SDLC, Peer and Gate Review Approach September 2011.

Product Life Cycle (PLC)

Page 4: IT Services SDLC, Peer and Gate Review Approach September 2011.

Project Life Cycle (PLC)

• Non-development life cycle Straight Forward Internal projects

Upgrades Installs Conversions

• Shared artifacts Where appropriate

Page 5: IT Services SDLC, Peer and Gate Review Approach September 2011.

Project Life Cycle (PLC)

Page 6: IT Services SDLC, Peer and Gate Review Approach September 2011.

Software Development Life Cycle (SDLC)

Page 7: IT Services SDLC, Peer and Gate Review Approach September 2011.

The GAI SDLC:•Phases provide incremental, or staged, delivery of functionality.•Iterations provide the progressive development and rework of functionality.•Provides repeatable/predictable scheduling, development, and testing processes.•Emphasizes the continual delivery of business value at predictable intervals.•Shows consistent progress while being better able to respond to changes.

The SDLC – What Is It?

The SDLC is a hybrid of the Rational Unified Process (RUP) and Agile development methodologies.

There are four distinct phases:–Inception–Elaboration–Construction–Transition

Page 8: IT Services SDLC, Peer and Gate Review Approach September 2011.

“A Phased Approach”

ProposeDefine and

Approve the Project

Prototype Capabilities & Prove-Out the Architecture

Develop the Solution Move the Solution into Production

Page 9: IT Services SDLC, Peer and Gate Review Approach September 2011.

Incremental Development

• The progressive development of features and functionality via the delivery of smaller pieces that are valuable to the customer

• Encourages progressive integration (not “big bang” integration)

• Each Phase can have 1 or more releases

• Each release can add functionality

Phase

Release

Iteration

Things of Value

Page 10: IT Services SDLC, Peer and Gate Review Approach September 2011.

Roles Within Iteration• Business Partner• Program Manager• PMO• Project Manager • Business Analyst• Architect• Development Lead• Data Modeler• Web Services• Tester

Page 11: IT Services SDLC, Peer and Gate Review Approach September 2011.

SDLC Releases

What comprises a Release?“… A stable, executable version of product, together with any artifacts necessary to use this release, such as release notes or installation instructions”

(Rational Unified Process Glossary)

GAI ITS Releases:•A release is a completed set of functionality with artifacts (business and internal).•Each Phase may deliver one or more “releases.”•A release progresses through each of the environments.•Releases begin with “1” and increment by “1” as necessary.•A release can be “major” (increment by 1) or “minor” (increment by .1).•Shows consistent progress while being better able to respond to changes.

Page 12: IT Services SDLC, Peer and Gate Review Approach September 2011.

Putting It Together - Iterative DevelopmentInceptionInception

• PM begins Project Charter• PM coordinates meeting with

Resource Managers (RM)• RM understands objectives and

assign resources• Lead PM and PMO coordinate

project plan linking sessions with all PMs

• BA begins Reqs for iteration 1

• PM begins Project Charter• PM coordinates meeting with

Resource Managers (RM)• RM understands objectives and

assign resources• Lead PM and PMO coordinate

project plan linking sessions with all PMs

• BA begins Reqs for iteration 1

• PM conducts Kick-off meeting with resources and business partner

• PM coordinates JAD sessions• Architect creates high level

design with Data Modeler• Test Lead creates test plan• PMO and PM plan gate and peer

reviews for project

• Iteration 1 begins

• PM conducts Kick-off meeting with resources and business partner

• PM coordinates JAD sessions• Architect creates high level

design with Data Modeler• Test Lead creates test plan• PMO and PM plan gate and peer

reviews for project

• Iteration 1 begins

RequestRequest

PlanningPlanning

Kick-offKick-off

• Business Partner makes requests for product development

• Program Manager evaluates request and assigns Lead Project Manger (PM)

• PM begins to gather information on request

• PMO, Program & Project Manager agree on governance approach

• Business Partner makes requests for product development

• Program Manager evaluates request and assigns Lead Project Manger (PM)

• PM begins to gather information on request

• PMO, Program & Project Manager agree on governance approach

Page 13: IT Services SDLC, Peer and Gate Review Approach September 2011.

Putting It Together - Iterative DevelopmentIteration 1Iteration 1

• BAs document Iteration 2 Reqs. • Testers begin creating test cases

for Iteration 1 Reqs.• Architects, Developers, and Data

Modelers may begin Preliminary Design for Iteration 1

• BAs validate functionality developed in Iteration 1

• BAs document Iteration 2 Reqs. • Testers begin creating test cases

for Iteration 1 Reqs.• Architects, Developers, and Data

Modelers may begin Preliminary Design for Iteration 1

• BAs validate functionality developed in Iteration 1

Iteration 2Iteration 2

• Developers and Data Modelers perform detail design for Iteration 1 Reqs.

• Developers code for Iteration 1 Reqs. Start 2

• BAs document system and data requirements to be developed in Iteration 3

• BAs validate functionality developed in Iteration 2

• Testers finalize test cases for functionality developed in Iteration 1 and start 2

• Developers and Data Modelers perform detail design for Iteration 1 Reqs.

• Developers code for Iteration 1 Reqs. Start 2

• BAs document system and data requirements to be developed in Iteration 3

• BAs validate functionality developed in Iteration 2

• Testers finalize test cases for functionality developed in Iteration 1 and start 2

Iteration 3Iteration 3

• Developers and Data Modelers perform detail design for Iteration 2 Reqs.

• BAs document system and data requirements to be developed in Iteration 4

• BAs validate functionality developed in Iteration 3

• Testers test functionality developed in Iteration 2

• Testers finalize test cases for functionality developed in Iteration 3

• UAT for functionality developed in Iteration 1 and 2

• Developers and Data Modelers perform detail design for Iteration 2 Reqs.

• BAs document system and data requirements to be developed in Iteration 4

• BAs validate functionality developed in Iteration 3

• Testers test functionality developed in Iteration 2

• Testers finalize test cases for functionality developed in Iteration 3

• UAT for functionality developed in Iteration 1 and 2

Month 1Month 1

Month 2Month 2

Month 3Month 3

Page 14: IT Services SDLC, Peer and Gate Review Approach September 2011.

Elaboration Phase – Iteration Tasks

Artifacts Developed During This Phase

• Project Plan• Project Status Report• Change Requests

Project

• Architectural Spec.• Architectural Review

Checklist• Design Review Docs• Code Review Docs• High-Level Design Docs• Detailed Design Docs

Arch., Design, Develop.

• Product Hierarchy• Coverage Matrix• Non-Functional Specs• User Dialogs• Business Rules• Data• Dictionary/Glossary• Data Mapping• GUI Screens• GUI Data Tables• Data Transformation

Requirements

• Conceptual Data Model• Logical Data Model• Physical Data Model• CXML Model• DDL /DML Scripts

Data

• Test Plan• Test Cases• Test Scripts

Testing

Page 15: IT Services SDLC, Peer and Gate Review Approach September 2011.

Elaboration Phase – Artifact Flow

SDLC - Elaboration Phase – Artifact Flow

PM

BA

Requirements

Te

ster

Dat

a

Mod

eler

De

velo

per

Le

ad

Arc

hite

ct

BA

Planning Requirements Analysis Design Build Test

PM Arch DevLead DM Tester

Project WBS

Owner

Project Audit

Checklist

Architectural Specification

Architectural Review

Checklist

System Requirements – Next Iteration

User Dialogs

GUIsBusiness

Rules

Non -Functional

Reqs.

Data Requirements – Next Iteration

Data Mapping & Transform

Data Dictionary

Coverage Matrix

PHM

High Level

Design

Data Models

Test PlanTest

Cases

Detail Design

Data Models

Test Scripts

Ch

an

ge

Req

ue

sts

DDL , DML Scripts

Code

Page 16: IT Services SDLC, Peer and Gate Review Approach September 2011.

Transition Phase – Iteration Tasks

•UAT Testing•Acceptance Criteria met

Artifacts Developed During This Phase

• Update Project Plan• Project Status Report• Change Requests• Transition Checklist• Project Close-Out Report

Project

• Update Arch. Docs• Update Design Docs• Design Review Docs• Code Review Docs

Arch., Design, Develop.

• Update Requirements

Requirements

• Update Data Models

Data

• Update Test Plans• Update Test Scripts

Testing

• Communication Plan for Delivery

• Training Materials

User Preparation

Fully tested and major defects corrected

Page 17: IT Services SDLC, Peer and Gate Review Approach September 2011.

Scrum

Page 18: IT Services SDLC, Peer and Gate Review Approach September 2011.

The Scrum Process

• Implementing Scrum Outside Consultants Time Frames Successful Teams

Page 19: IT Services SDLC, Peer and Gate Review Approach September 2011.

Peer Reviews

Page 20: IT Services SDLC, Peer and Gate Review Approach September 2011.

Formal Reviews

True Peer Review – New authors and/or high risk material (audience = peers)

Technical Review – Authors with solid material (audience = peers and internal consumers)

Combined Peer and Technical Review – Experienced authors with low risk material (audience = peers, internal consumers, and business partners)

Page 21: IT Services SDLC, Peer and Gate Review Approach September 2011.

Informal Reviews

• Code reviews, logical/physical data models, deployment plans, customer care hand-off plans, test plans, and ETL Specification reviews Audience – a peer or team mate Value add - formal meetings are not required, team/person

reviewing will record metrics and share with PMO Timing – as needed; efficient and flexible The goal is to have a knowledgeable second set of eyes

reviewing the work prior to development

Page 22: IT Services SDLC, Peer and Gate Review Approach September 2011.

Industry Standards for Proving the Value

Production

Certification Test

COST TO COST TO REPAIR 1 REPAIR 1 DEFECTDEFECT

Unit Test Unit Test

Code

$1000

$7000

$14000

Integration Test

$2500

Integration Test

$2500System

Test$4500

SystemTest

$4500

Planning AnalysisSystem Design

$140

Planning AnalysisSystem Design

$140

Page 23: IT Services SDLC, Peer and Gate Review Approach September 2011.

Proving the Value

• Dashboards Time Tracking Unit Code Coverage UAT Defects Peer Review results

• Health check Compliance with methodology

Page 24: IT Services SDLC, Peer and Gate Review Approach September 2011.

Q&A

• What’s on your mind?


Recommended