+ All Categories
Home > Documents > Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the...

Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the...

Date post: 08-Oct-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
96
Item ____IPP07 _______ - REPORTS -_______03/02/2016 ________ N O R T H S Y D N E Y C O U N C I L R E P O R T S NSIPP MEETING HELD ON 03/02/2016 Attachments: 1. Site Plan 2. Architectural plans 3. Clause 4.6 submission (Building height) ADDRESS/WARD: 467-473 Miller Street, Cammeray (T) APPLICATION No: DA280/15 PROPOSAL: Demolition of the existing buildings and the construction of a five storey mixed use building consisting basement parking for 34 vehicles, retail tenancies on the ground floor, 24 apartments on the levels above and roof top communal facilities including strata subdivision PLANS REF: Plan No. Rev. Title Drawn by: Plot Date/Rev Date DA01 - Site Plan/Site Analysis Plan Wolski. Coppin Architecture 8/12/2015 DA02 - Lower Basement Plan Wolski. Coppin Architecture 8/12/2015 DA03 - Basement Plan Wolski. Coppin Architecture 6/11/2015 DA04 A Ground Floor Plan Wolski. Coppin Architecture 6/11/2015 DA05 B Typical Floor Plan (L1 & L2) Wolski. Coppin Architecture 22/12/2015 DA06 B Level 3 Floor Plan Wolski. Coppin Architecture 22/12/2015 DA07 A Level 4 Floor Plan Wolski. Coppin Architecture 6/11/2015 DA08 A Roof Plan Wolski. Coppin Architecture 6/11/2015 DA09 A Longitudinal Section (Section AA) Wolski. Coppin Architecture 6/11/2015 DA10 A Cross Section (Section BB) Wolski. Coppin Architecture 6/11/2015 DA11 A North Elevation Wolski. Coppin Architecture 6/11/2015 DA12 A East Elevation Wolski. Coppin Architecture 6/11/2015 DA13 A West Elevation Wolski. Coppin Architecture 6/11/2015 DA14 A South Elevation Wolski. Coppin Architecture 6/11/2015 L1 D Landscape Concept Plan Ground Floor Wallman Partners Pty Ltd Landscape Architects 8/12/2015 L2 B Landscape Concept Plan Level 1 Wallman Partners Pty Ltd Landscape Architects 8/12/2015 L3 A Landscape Concept Plan Level 4 Wallman Partners Pty Ltd Landscape Architects 8/12/2015 OWNER: Pavilion Residences No.2 P/L APPLICANT: Ted Byrne AUTHOR: Luke Donovan, Senior Assessment Officer DATE OF REPORT: 27 January 2016 DATE LODGED: 11 August 2015 AMENDED: 8 December 2015 RECOMMENDATION: Deferred Commencement Approval
Transcript
Page 1: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Item ____IPP07_______ - REPORTS -_______03/02/2016________

N O R T H S Y D N E Y C O U N C I L R E P O R T S

NSIPP MEETING HELD ON 03/02/2016

Attachments:

1. Site Plan

2. Architectural plans

3. Clause 4.6 submission (Building height)

ADDRESS/WARD: 467-473 Miller Street, Cammeray (T)

APPLICATION No: DA280/15

PROPOSAL: Demolition of the existing buildings and the construction of a

five storey mixed use building consisting basement parking for

34 vehicles, retail tenancies on the ground floor, 24 apartments

on the levels above and roof top communal facilities including

strata subdivision

PLANS REF:

Plan No. Rev. Title Drawn by: Plot Date/Rev

Date

DA01 - Site Plan/Site Analysis Plan Wolski. Coppin Architecture 8/12/2015

DA02 - Lower Basement Plan Wolski. Coppin Architecture 8/12/2015

DA03 - Basement Plan Wolski. Coppin Architecture 6/11/2015

DA04 A Ground Floor Plan Wolski. Coppin Architecture 6/11/2015

DA05 B Typical Floor Plan (L1 & L2) Wolski. Coppin Architecture 22/12/2015

DA06 B Level 3 Floor Plan Wolski. Coppin Architecture 22/12/2015

DA07 A Level 4 Floor Plan Wolski. Coppin Architecture 6/11/2015

DA08 A Roof Plan Wolski. Coppin Architecture 6/11/2015

DA09 A Longitudinal Section (Section

AA)

Wolski. Coppin Architecture 6/11/2015

DA10 A Cross Section (Section BB) Wolski. Coppin Architecture 6/11/2015

DA11 A North Elevation Wolski. Coppin Architecture 6/11/2015

DA12 A East Elevation Wolski. Coppin Architecture 6/11/2015

DA13 A West Elevation Wolski. Coppin Architecture 6/11/2015

DA14 A South Elevation Wolski. Coppin Architecture 6/11/2015

L1 D Landscape Concept Plan Ground

Floor

Wallman Partners Pty Ltd

Landscape Architects

8/12/2015

L2 B Landscape Concept Plan Level 1 Wallman Partners Pty Ltd

Landscape Architects

8/12/2015

L3 A Landscape Concept Plan Level 4 Wallman Partners Pty Ltd

Landscape Architects

8/12/2015

OWNER: Pavilion Residences No.2 P/L

APPLICANT: Ted Byrne

AUTHOR: Luke Donovan, Senior Assessment Officer

DATE OF REPORT: 27 January 2016

DATE LODGED: 11 August 2015

AMENDED: 8 December 2015

RECOMMENDATION: Deferred Commencement Approval

Page 2: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 2

Re: 467-473 Miller Street, Cammeray

EXECUTIVE SUMMARY

The development applicant seeks NSIPP approval for the demolition of the existing buildings and

the construction of a five storey mixed use building consisting basement parking for 34 vehicles,

retail tenancies on the ground floor, 24 apartments on the levels above and roof top communal

facilities including strata subdivision on land at 467-473 Miller Street, Cammeray.

The application is reported to NSIPP because the non compliance with the building height

control in Clause 4.3(2) in NSLEP 2013 is greater than 10% requiring determination by

NSIPP as directed by the Department of Planning and Environment.

Council’s notification of the original proposal attracted nine (9) submissions against the

application and one (1) submission in support of the application. The submissions against the

application raised particular concerns about the non compliance with the building height control,

loss of sunlight, excessive excavation, lack of car parking, noise and traffic impacts.

The application proposes new retail tenancies on the ground level to enhance street activation

along Miller Street and Miller Lane. A through site pedestrian link provides improved access

between Miller Street and Miller Lane. The central lightwells and dual frontage ensures

reasonable levels of light and ventilation to the apartments without materially impacting on the

amenity of adjoining properties.

The three storey podium height to Miller Street is consistent with the adjoining developments on

the eastern side of Miller Street (No’s 463 and 465 Miller Street). The fourth storey is setback

from both Miller Street and Miller Lane which is generally consistent with the mixed use

developments that are directly opposite on the western side of Miller Street (No’s 510, 514 and

518-520 Miller Street) and generally compliant with the height control.

The proposed communal facilities on the fifth storey are significantly above the height control are

likely be highly visible from the public domain and set an undesirable precedent for future

redevelopment along the eastern side of Miller Street. The communal facilities on the fifth storey

are therefore not supported.

It is recommended that a deferred commencement approval be granted subject to the

deletion of the fifth storey and the submission of an amended strata plan.

Page 3: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Re: 467- 473 Miller Street, Cammeray - DA 280/15

LOCATION MAP

Page 3

oa@@o

N

ø

SPSP

No

Nf)oNo

2

b@oo

32

06

oNk)b@o

sP 12390

a

@

o-(t)

3

boa

@4895

ooø

o_U)

@oo

935933

926645

oNf,

oòøo6o-(/)

6E

r)

o_Ø

D

2

o

O)

60

630862

1

@k)6

o_Ø

No

oa@

ho_Ø

6

(f)-o¡

loo

sP 52968

o@

%

@

6o

4679 'o

sP 17000

a

@oo

(oo

rD--ó

1òo

P

a

SP

sP 15s0

N

sP 11614

%

o-

No

o_Ø

NññN

sP 1 ?880

70266

r)NbO)

u,

SÌREEI

CARIER

PL4CÈ

sl¡JJà

Éw

Ezwao

t¡JËlr

tU,I4SDEN

I

sP 87345

102431

sP 68840

sP 20939

9bõ9r86

@o()

oo(oo_CD

boo@

o_a)

a

Property/Applicant O Submittors - Properties Notified

Page 4: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 4

Re: 467-473 Miller Street, Cammeray

DESCRIPTION OF PROPOSAL

The applicant is seeking development consent for the demolition of the existing buildings and

the construction of a five storey mixed use building consisting of basement parking for 34

vehicles, retail tenancies on the ground floor, 24 apartments on the levels above and roof top

communal facilities including strata subdivision.

Specific details of the proposal are as follows:

Lower Basement Level

The basement level contains 17 car parking spaces including 2 disabled car spaces, 3

visitor car spaces, plant/ storage area, dedicated storage areas for a number of

residential apartments, motor cycle parking spaces and bicycle racks for 22 bikes.

Internal stair and pedestrian lift access is provided to all levels of the development.

Upper Basement Level

The basement level contains 17 car parking spaces including 3 disabled car spaces, 1

visitor car space, pump room plant/ storage area, dedicated storage areas for a number

of residential apartments, separate residential and commercial garbage storage area, a

unisex accessible toilet and a loading bay for a small rigid vehicle.

Access to the basement levels are obtained from Miller Lane via a single lane access

driveway with a passing bay.

Internal stair and pedestrian lift access is provided to all levels of the development.

Ground Floor Level (RL 83.270 and RL84.500)

The ground floor contains 4 retail tenancies. Two (2) of the retail tenancies have a

frontage and street activation to Miller Street. The other two retail tenancies are

setback 3.8metres from Miller Lane.

A 2.2metre wide through site link is proposed between Miller Street and Miller Lane

A separate residential lobby and lift from Miller Street will provide access to the

residential levels above.

Levels 1 and 2 (RL 87.60 and RL90.63m)

Levels 1 and 2 each contain four x 1 bedroom and four x 2 bedroom apartments being

a total of 8 apartments per floor level. The apartments have been oriented to the front

and rear of the site. Lightwells are proposed on the northern and southern side of the

development.

Sliding louvre screens are proposed to the front and rear facing balconies of the

apartments.

Internal stair and lift access is provided to all other levels of the development.

Page 5: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 5

Re: 467-473 Miller Street, Cammeray

Level 3 (RL 93.660)

Level 3 contains four studio and four x 2 bedroom apartments being a total of 8

apartments on this level. The apartments have also been oriented to the front and rear

of the site

The studio apartments are cross ventilated by way of a ventilation shaft.

Metal framed sun shades are proposed over the west facing balcony areas.

Internal stair and lift access is provided to all other levels of the development.

Level 4 Floor Plan (RL 96.690)

Level 4 contains communal facilities including undercover seating, BBQ areas, toilets

and a spa.

Materials

Building materials include horizontal terracotta cladding to the upper level, rendered

masonry to the lower levels in neutral colours, timber sliding louvred screens, aluminium

framed windows and doors and glass balustrades.

STATUTORY CONTROLS

North Sydney LEP 2013

Zoning – B1 Neighbourhood Centre

Item of Heritage - No

In Vicinity of Item of Heritage - No

Conservation Area – No (opposite Cammeray Conservation Area)

S94 Contribution

Environmental Planning & Assessment Act 1979

SEPP No. 55 – Remediation of Land

SEPP No.65 – Design Quality of Residential Apartment Development

SEPP (Building Sustainability Index – BASIX) 2004

SREP (Sydney Harbour Catchment) 2005

Local Development

POLICY CONTROLS

NSDCP 2013

DESCRIPTION OF LOCALITY

The subject site comprises the following separately titled allotments:

Lot 4, DP 1985, No. 467 Miller Street;

Lot 3, DFP 983635, No. 469 Miller Street; and

Lot 2, DP 983635, No. 471 to 473 Miller Street.

Page 6: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 6

Re: 467-473 Miller Street, Cammeray

The subject site is rectangular in shape having a primary frontage and address to Miller Street of

21 metres, a secondary frontage to Miller Lane, a depth of 38.05 metres and a total site area of

813m². The subject site has a slight fall from Miller Lane to Miller Street.

Currently located on the subject site are part one and two storey commercial buildings with

residences and office space at first floor level. Rear laneway access and parking is available off

Miller Lane.

Figure 1 – Miller Street frontage of the subject site

Figure 2 - Miller Lane frontage of the subject site

To the north of the subject site is a Shell Service Station (No.475 Miller Street) which is located

on the corner of Miller and Palmer Streets.

To the south of the subject site is a three storey mixed use building (No.465 Miller Street). The

western part of this building fronting Miller Street contains a restaurant with parking at the rear

on the ground floor and offices on the first and second floors. The eastern part of this building

fronting Miller Lane contains a residential apartment on the first and second floor facing Miller

Lane with central courtyards.

Page 7: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 7

Re: 467-473 Miller Street, Cammeray

Figure 3 – Looking west from Miller Lane towards the adjoining mixed use developments

at No’s 463-465 Miller Street

The properties located on the western side of Miller Street are occupied by predominately 4 and 5

storey mixed use developments.

Figure 4 – Four and five storey mixed use developments on the western side of Miller Street

opposite the subject site

The properties located to the east of Miller Lane, opposite Council’s car park are a mixture of one

and two storey attached, detached, semi detached and multi dwelling housing. This low scale

residential area forms part of the Cammeray Conservation Area.

Page 8: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 8

Re: 467-473 Miller Street, Cammeray

Figure 5 – Council’s car park and the dwellings to the east of Miller Lane

RELEVANT HISTORY

Previous applications across the site

467 Miller Street

Development Application DA554/06 proposing alterations and additions to existing premises and

its use as a medical centre was approved under delegated authority on 12 January 2007.

471-473 Miller Street

Development Application DA537/04 proposing the internal fit out of existing commercial

premises to provide a beauty salon was approved under delegated authority on 2 December 2004.

Current application

A brief history of the subject development application is summarised in the table below:

Date Action

11 August 2015 The subject application was lodged with Council.

24 August 2015 A letter was sent to the applicant requesting the following additional

information:

Revised shadow diagrams

Solar access and cross ventilation report must be updated to reflect

the changes to SEPP 65 and Apartment Design Guide

21 August and 4

September 2015

The original application was notified to adjoining properties and the Plateau

Precinct Committee. A total of nine (9) submissions were received against

the original application and one (1) submission in support of the original

application.

8 September 2015 The application was considered by the Design Excellence Panel.

Page 9: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 9

Re: 467-473 Miller Street, Cammeray

9 October 2015 A further letter was sent to the applicant requesting the following

information and amendments:

The proposed residential apartments above the permissible building

height (Level 5) are not supported.

The proposal should maintain a two storey podium to Miller Street

consistent with the character statement.

The proposal should ensure 70% of the apartments receive a minimum

of 2 hours of solar access between 9am and 3pm during the winter

solstice.

The proposed residential entry off Miller Street should be increased in

width to improve social interaction amongst residents and visitors.

The through site pedestrian link should also be increased in width to

provide for a safer and more useable walkway.

The proposal should provide a garbage chute within the development

and a garbage holding bay on the Miller Lane frontage of the site.

A loading and un-loading bay must be provided on site.

The proposal should provide additional bicycle spaces consistent with

the provisions of NSDCP 2013.

The proposal could incorporate green walls and a green roof.

The proposed finishes, in particular the timber louvers, do not appear to

complement the neutral colours of the development.

8 December 2015 The applicant submitted amended plans in response to Council’s letter dated

24 August and 9 October 2015. The key amendments included:

Deletion of the residential apartments on Level 5 and replacement

with rooftop communal facilities.

The development has provided a greater mix of studios and 1

bedroom apartments consistent with the provision in NSDCP 2013.

The width of the residential lobby has been increased to 2.2m.

The through site pedestrian link has been increased to a width of 2m.

A garbage holding bay has been added to the ground floor Miller

Street frontage of the site.

A garbage storage room has been added to Levels 1, 2 and 3 of the

development.

A loading bay for a small rigid vehicle has been added to the upper

basement level.

Additional bicycle storage has been added to the lower basement

level.

Changes to the colours and finishes.

Green walls and a green roof have been incorporated into the design.

18 December 2015

to 15 January 2016

The amended application was notified to adjoining properties and the

Plateau Precinct Committee. One (1) submission was received against the

amended application.

Page 10: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 10

Re: 467-473 Miller Street, Cammeray

REFERRALS

Building

The application was referred to Council’s Senior Building Surveyor who recommended

appropriate conditions of consent to ensure compliance with the Building Code of Australia and

Disability (Access to Premises – Buildings) Standards 2010 (refer to Conditions C34, F1, G5,

K1, K2, K3 and K6).

Engineering

The application was referred to Council’s Development Engineer who supported the application

on engineering grounds subject to conditions of consent (refer to Conditions C5, C8, C15, C19,

C20, C21, C22, C23, C25, E7, G4, G10 and G11).

Traffic

The application was referred to Council’s Manager Traffic and Transport Operations, who

provided the following comments on the original application:

Car Parking Provisions

The original application proposed 38 car parking spaces within the basement levels

as outlined in the table below:

Development Component DCP 2013

Rate

DCP 2013

Max. No.

No. Proposed

Res. 24 x 1-2 bed 1 space/ 1+2

bedroom

dwelling

24 24

2 x 3 bed 1.5 space/3

bedroom

dwelling

3 3

Visitor/Car

Wash

0.25

space/dwelling 6.5 7

Motorcycle 1 space/10

cars 3.8 1

Retail 415m2 0.01 4 4

TOTAL 42 39

The proposal complies with maximum parking rate specified in Part B, Section 10.2.1

in NSDCP 2013.

Bicycle Parking

The proposed development has not included any bicycle parking for staff of the retail

component. Bicycle parking should be provided in accordance with P1 in Part B,

Section 10.5 in NSDCP 2013 to encourage cycling trips to and from the workplace.

These should be provided in a secure and convenient location such as the upper

basement level. The plans indicate a shower in each of the retail areas as well as one

within the upper basement level which will enable staff to change at the end of their

cycling trip.

The plans indicate 25 storage areas in the basement levels of the development. In

Page 11: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 11

Re: 467-473 Miller Street, Cammeray

order for these to be considered appropriate for bicycle parking they must be a

minimum of 1200mm x 500mm to accommodate a bike.

The visitor parking rails are provided on the lower basement level. Ideally the visitor

bike parking should be located on the upper basement level. The car park will require

an intercom system to enable visitors to conveniently access the carpark.

The customer bike rails should be located in a convenient area near the entrance to

the shops.

Loading Facilities

The existing buildings have open off-street parking for a minimum of 1 vehicle off

Miller Lane. The site therefore currently has some capability for deliveries to occur

on-site.

The proposed development does not include any provision for off-street loading. It

can be reasonably expected that the residential component will require space for

removalist trucks and the retail component will have deliveries and service vehicles. If

no on-site loading facilities are provided then delivery vehicles will be forced to park

on-street either on Miller Street or in Miller Lane. Miller Lane has angle parking for

vehicles under 6 metres opposite the development and ‘No Parking’ adjacent to the

site. It is likely that delivery and service trucks will park adjacent to the site in the ‘No

Parking’ area. This could potentially block the laneway and restrict access to the

angle parking spaces. It is therefore recommended that a loading area be provided

on-site to accommodate a small rigid vehicle.

Traffic Generation

The proposed development is unlikely to have any unacceptable traffic implications in

terms of road network capacity.

Comment:

The applicant submitted amended plans which reduced the number of parking spaces to 34,

increased the number of bicycle spaces to 22 and provided a loading zone for a small rigid

vehicle. The amended plans were referred to Council Manager of Traffic and Transport

Operations who was satisfied with the proposed parking and loading facilities subject to

recommended conditions of consent (refer to Conditions C16, C17 and G20).

Environmental Health

The application was referred to Council’s Team Leader (Environmental Health) who provided

the following comments:

Page 12: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 12

Re: 467-473 Miller Street, Cammeray

The STS GeoEnvironmental report dated July 2015 submitted as part of the application

advises that benzene and TPH were found in the groundwater at the site in

concentrations that present a potential risk to human health and the environment. The

benzene levels noted are indicative of potential vapour emissions which could present a

risk to human health.

The groundwater impacts are expected to be the result of leakages from the UPSS

facilities on the neighbouring Shell Service station.

The report advises that further assessment is necessary to determine the extent of

remedial works, if any, which may be necessary to make the site suitable for the proposed

use. The further investigation will require comprehensive soil sampling and additional

ground water testing following demolition of the existing buildings on the site.

The report advises that there is no reason to expect that the site cannot be made suitable

for its intended use subject to remediation work been undertaken by an EPA licensed Site

Auditor. It is the site auditors role to oversee the remediation process and sign

off/validate that the site, post remediation, is suitable for its intended use.

A condition of consent is recommending that the site be remediated and then validated by

an EPA site auditor prior to the issue of the Construction Certificate (refer to Condition

C40). A further condition of consent is recommended that following demolition and prior

to excavation works a Remediation Action Plan is prepared and submitted to Council

(refer to Condition D1).

Landscaping

The application was referred to Council’s Landscape Development Officer who raised no

objection to the application subject to a condition requiring a tree bond for the protection of the

two (2) Hills Fig trees growing on the Miller Street footpath in front of the subject site (refer to

Condition C27).

Waste

The amended plans indicate a garbage holding bay adjacent to the Miller Lane frontage of the site

and a garbage room on each of the residential levels of the development to satisfy the waste

requirements of Council’s Environmental Education Officer.

Design Excellence Panel

Council’s Design Excellence Panel considered the original application on 8 August 2015 and

provided the following comments having regard to the nine design quality principles under SEPP

65:

Page 13: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 13

Re: 467-473 Miller Street, Cammeray

Principle 1 - Context and Neighbourhood Character

The site is not located on the corner and is not considered to be a gateway site. The top

floor exceeds the height control and is not in keeping with the desired character of the

area (13m height in neighbourhood business zone). The site on the south western corner

of Palmer Street and Miller Street (No. 518-520 Miller Street) is more of a gateway site

and only communal space was allowed on the roof above the height control. There are no

concerns with the general appearance of a four storey building on the site. The two

apartments on the top floor are therefore not supported. The ground level of the building

will utilise small scale commercial activities thereby activating the streets, laneways and

the public car park with a mix of residential uses above.

There is a lack of information that describes how the proposal fits into its wider context.

Elevations of existing and likely future adjacent buildings, together with a street section

would assist in understanding how this proposal will integrate with its setting.

Principle 2 - Built Form and Scale

The built form is supported other than the fifth storey.

Principle 3 - Density

The density of the site was not discussed other than the upper level apartments.

Principle 4 - Sustainability

It was noted that a BASIX certificate was submitted with the application. It was suggested

that a green roof be provided as well as skylights to the Level 3 apartments.

Principle 5 - Landscape

There are limited opportunities to introduce a landscaping component. Deep soil

planting is not possible due to the 100% site coverage and commercial use at ground

level. Planter boxes have been introduced into the ground floor central courtyard area.

Planters at the Miller Lane street frontage define the pedestrian entry to the building.

Some light on structure planting has also been incorporated on the first floor residential

courtyard spaces. The ground level ‘courtyards’ are in reality only lightwells with

limited amenity , and further detail is required as to how these would be used and treated

e.g. the side walls might be able to provide some greenery. Use of part of the roof for

communal open space was recommended with the remainder being a green roof.

Principle 6 - Amenity

Balcony and window openings have been offset so as not to result in direct overlooking

between apartments, with habitable rooms facing blank walls with a separation of close

to 7 metres. Although visual privacy issues would be resolved by this configuration,

acoustic privacy is also an issue with a narrow lightwell. If there were to be substantial

planting including a ‘green’ wall(s) this issue might be adequately addressed.

Unit orientation to the streets allows 2 hours of solar access between 9am and 3pm in

Page 14: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 14

Re: 467-473 Miller Street, Cammeray

mid winter to 12 of the apartments (46%). A further 7 apartments achieve 2 hours

between 8am and 3pm (73% total). However the deep terraces and screens may make this

difficult because of site constraints and under these circumstances the proposal is

considered to be acceptable. The proposed design achieves cross ventilation to 69% (19)

of apartments. Although the snorkel bedrooms don’t comply with the new Apartment

Design Code, they are considered to be acceptable in this instance.

The drawings do not indicate any windows in the bathrooms facing the lightwells so they

would have to rely on mechanical ventilation and artificial lighting. It appears that

windows could readily be included.

Washrooms opening directly into retail spaces are not acceptable. Shared, discreetly

located washrooms would be a better alternative.

Principle 7 - Safety

There is concern with the width of the residential entry and the stair access for the

apartments not being convenient from the residential lobby. It should be widened to at

least provide a small seating area, and the stair made accessible from the lobby. The

entrance doors to both the residential flats and the arcade are recessed and this would

create a potential security problem after dark.

Principle 8 - Housing Diversity and Social Interaction

The residential lobby is too narrow, restricting social interaction. There is no communal

space provided for the future residents and this is not acceptable. Although a breach of

the height control is not supported for the apartments themselves, a small communal

space on the roof would be supported provided it did not adversely impact on

surrounding development. The space could incorporate a small enclosed room with tea

making facilities etc, north facing terrace, toilet and BBQ.

Principle 9 - Aesthetics

The aesthetics of the building are acceptable in principle, however well-considered

façade details and materials selection will be essential in achieving a high level of design

quality. Windows and any openings or screening on the northern elevation are not

protected from future development and are likely to be built over. Council could impose a

condition requiring a covenant on any strata advising purchasers that the openings are

not protected from future developments (refer to Condition G2). Better details of

materials and finishes are required, and there should be an indication of how drainage

and services are configured.

Conclusion

The level 5 apartments over the building height control are not supported. The ground

level entrance, through site link and courtyard require further review.

Page 15: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 15

Re: 467-473 Miller Street, Cammeray

Comment:

The applicant submitted amended plans to resolve the main issues identified by the Design

Excellence Panel (DEP). Whilst the DEP recommended a small communal rooftop area, this is

not supported by Council’s Assessment Officer as it would result in further non compliances with

Council’s height control and likely to be highly visible from the public domain in its current form

and set a precent for future redevelopment along the eastern side of Miller Street (refer to

Condition AA1). Whilst it is considered that such provisions have been accepted in the past this

has been in the much high scale and density mixed use area as that of St Leonards. It’s clear that

in determining the relevant heights for the neighbourhood of Cammeray the Council had clear

regard for the lower scaled dwellings of the conservation area and set the height constraints on

the eastern side of Miller Street accordingly. This has been consistently applied and there is no

good case presented here to vary it.

External Referrals

Roads and Maritime Services

The application was referred to the Roads and Maritime Services in accordance with the

requirements SEPP (Infrastructure) 2007. Roads and Maritime Services raised no objection to the

application subject to standard conditions of consent (refer to Condition C1).

Ausgrid

The application was referred to Ausgrid who raised not objection to the application subject to

standard conditions of consent (refer to Condition E1).

SUBMISSIONS

Original application

The original application was notified to adjoining properties and the Plateau Precinct Committee

between 21 August and 4 September 2015. A total of nine (9) submissions were received against

the original application and one (1) submission in support of the original application.

The issues raised in the submissions against the application are summarised in the table below

and addressed later in this report:

Basis of Submissions

The proposed retail tenancies on the ground floor are likely to result in adverse noise

impacts for surrounding properties.

The height of the proposed development will adversely impact the telecommunication

coverage and service for mobiles and emergency calls in the surrounding area.

The proposal is non compliant with the permissible building height in Clause 4.3(2) in

NSLEP 2013.

The five storey scale is considered to be excessive and will detract from the character of the

locality.

The proposal will result in an increase in afternoon shadows to the properties on the eastern

Page 16: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 16

Re: 467-473 Miller Street, Cammeray

side of Miller Lane.

The proposal provides inadequate carparking for residents and visitors to the site.

The likely noise impacts on the locality during excavation and construction works.

The proposal is likely to result in the loss of daylight and outlook for No.6 Raleigh Street

The proposal is likely to result in traffic congestion along Miller Lane.

The fenestration on the balconies, in particular the louvre screens, are not compatible with

the streetscape.

The proposal is likely to overshadow the existing landscaped area alongside Council’s

public car park.

Amended application

The amended application was notified to adjoining properties and the Plateau Precinct

Committee between 18 December 2015 and 15 January 2016. One (1) submission was received

against the application that raised no new issues.

CONSIDERATION

The relevant matters for consideration under Section 79C of the Environmental Planning and

Assessment Act 1979, are assessed under the following headings:

SEPP 55 – Remediation of Land

The provisions of SEPP 55 require Council to consider the likelihood that the site has

previously been contaminated and the methods required to address any land contamination at

the site. The STS GeoEnvironmental report dated July 2015 submitted as part of the

application indicates that benzene and TPH were found in the groundwater at the site in

concentrations that present a potential risk to human health and the environment. The report

concluded that the groundwater impacts are expected to be the result of leakages from the

UPSS facilities on the neighbouring Shell Service station.

Council’s Team Leader (Environmental Health) has recommended that the site be remediated and

then validated by an EPA site auditor prior to the issue of the Construction Certificate (refer to

Condition C40). A further condition of consent is also recommended that following demolition

and prior to excavation works a Remediation Action Plan is prepared and submitted to Council

(refer to Condition D1). These conditions are recommended to minimise the risk of harm to

public health and the environment to satisfy the requirements of SEPP 55.

SREP (Sydney Harbour Catchment) 2005

Having regard to the SREP (Sydney Harbour Catchment) 2005 (gazetted on 28 September 2005),

the proposed development is not considered to be detrimental to the Harbour and will not unduly

impose upon the character of the foreshore given there are no primary views to the site from the

harbour. As such, the development satisfies the provisions contained within the above SREP.

SEPP No.65 (Design Quality of Residential Flat Development)

Page 17: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 17

Re: 467-473 Miller Street, Cammeray

The application has been assessed by the Design Excellence Panel (DEP) having regard for the

Design Quality Principles set out in SEPP 65. The DEP generally supported the proposed

development subject to recommended amendments which the applicant addressed through

amended plans. The proposal is assessed against the principles as follows:-

Principles 1, 2 and 3: Context, Scale and Built Form: The three storey podium with the fourth

storey setback is considered to be generally in keeping with mixed use developments that are

directly opposite on the western side of Miller Street (No’s 510, 514 and 518-520 Miller Street).

Figures 6 and 7 – Developments on the western side of Miller Street, opposite the subject

site

The proposed three storey podium height to Miller Street is also consistent with the adjoining

developments on the eastern side of Miller Street at No’s 463 and 465 Miller Street.

The fourth storey is setback above the podium consistent with the Cammeray Village Centre

Character Statement. The fifth storey is above the height control, would be visible from the

public domain and set an undesirable precent for future redevelopment along the eastern side of

Miller Street. The fifth storey is therefore not supported (refer to Condition AA1).

Figure 8 – Subject site and adjoining developments to the south

518-520 Miller Street

(4 storey)

510Miller Street

(4 storey)

No’s 463 (right) and 465 (left) Miller Street

– 3 storey podiums

Subject site

Page 18: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 18

Re: 467-473 Miller Street, Cammeray

Principle 4: Density – The amended plans have reduced the density of the development which is

considered to be acceptable as detailed within this report.

Principle 5: Resource, energy and water efficiency - A valid ‘multi dwelling’ BASIX Certificate

has been provided with the application. The proposal provides adequate light and ventilation to

the apartments.

Principle 6: Landscape – Limited opportunity exists on the site for plantings given the mixed use

zoning and the current site coverage. Notwithstanding, the amended plans have provided some

landscaping within the ground level courtyards, green walls to the lightwell and a green roof.

Principle 7: Amenity – Given the eastern and western orientations of the apartments, the

balconies and living spaces of the apartments will receive reasonable morning or afternoon

sunlight during mid winter and the equinox.

Louvred screens are provided to the balconies and windows to the lightwell to maximise internal

amenity for the apartments. The floor area for each balcony complies with the minimum areas

specified in the Apartment Design Guide.

Twelve (12) of the apartments will receive natural cross ventilation by virtue of the lightwells

and four (4) of the apartments will rely on a ventilation shaft to provide mechanical ventilation.

It is concluded that reasonable levels of amenity will be provided to the apartments.

Principle 8: Safety and Security - The amended plans have increased the width of both the

residential entry lobby and the through site pedestrian link to provide greater social interaction

amongst residents and a safe and usable pedestrian space. A condition is recommended requiring

the provision of an intercom system and a security door at the entry to the residential lobby and

that there be restrictions on the hours of the through site pedestrian link to maintain safety and

security for the residents, visitors and commercial tenants (refer to Condition G1).

Principle 9: Social Dimensions - The proposed development provides an acceptable mix of

dwellings (studio, one and two bedroom apartments) to accommodate a mix of housing needs in

Cammeray. Rooftop communal facilities are proposed to encourage social interaction amongst

residents and visitors to the apartments. However, the proposed communal facilities in their

current form are considered to dominate the upper level of the building causing an increase in

visual mass of the building that is not supported (refer to Condition AA1).

Principle 10: Aesthetics – The amended plans indicate rendered masonry to the middle levels

and ‘terracade’ wall cladding to the ground and top floors. The proposed colours are generally

compatible with surrounding developments in the locality.

Page 19: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 19

Re: 467-473 Miller Street, Cammeray

Figure 9 – Photomontage of proposed development from Miller Lane

The proposed development has also been considered against the Apartment Design Guide

(relevant upon commencement of SEPP 65 Amendment No.3 which came in to affect on 19 July

2015) and is considered to be generally acceptable.

SEPP (Building Sustainability Index: BASIX) 2004

A suitable ‘Multi Dwelling’ BASIX Certificate (640776M) has been submitted with the

application. Appropriate conditions are recommended requiring compliance with the

commitments contained in the certificate (refer to Condition C39 and G15).

SEPP (Infrastructure) 2007

SEPP (Infrastructure) 2007 establishes a framework for certain types of development to be

referred to the RMS for consideration. RMS has raised no objection to the application subject to

recommended conditions of consent (refer to Condition C1). Vehicular access is proposed off

Miller Lane to ensure there are no adverse impacts on Miller Street. Acoustic measures have been

incorporated into the design (including sliding louvre screen to the facades) to maintain

acceptable amenity to the apartments. The proposal is therefore considered satisfactory having

regard to Clause 101 of SEPP (Infrastructure) 2007.

North Sydney Local Environmental Plan 2013

Permissibility within the zone:

The site is zoned ‘B1 Neighbourhood Centre’ under the provisions of the North Sydney Local

Environmental Plan 2013. The application proposes shop top housing which is permissible form

of development in the B1 Neighbourhood Centre zone with development consent from Council.

Page 20: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 20

Re: 467-473 Miller Street, Cammeray

Objectives of the zone (B1 Neighbourhood Centre)

The application proposes retail premises on the ground floor of the development to encourage

greater street and lane activation whilst also servicing the needs of the people who live and work

in the surrounding neighbourhood. The proposed residential apartments on the upper levels of the

development have been designed to provide maximum internal amenity whilst not having a

detrimental nor adverse impact on the amenity of surrounding developments. The proposed fifth

storey is significantly non compliant with Council’s height control and is not supported. Subject

to the recommended deletion of the fifth storey, the proposal is considered to achieve the

objectives of the B1 Neighbourhood Centre zone.

Building Heights

Under the provisions of Clause 4.3(2), the maximum height of a building permitted on the

subject site is 13m. The roof over the communal facilities on the fifth storey has a height of

16.2m. The top of the lift over run and ventilation shaft has a height of 17.5m. The parapet over

the Level 4 residential apartment has a height of 13.3m. The fifth storey, lift over run and

ventilation shaft are the main parts of the development that are non compliant with the building

height control in Clause 4.3(2) in NSLEP 2013 as shown in figure 10.

Figure 10 – Section through the proposed development indicating relationship to

building height control

The applicant has submitted a written statement justifying the proposed variation to the building

height control. The proposed breach has been assessed in accordance with the requirements of

Clause 4.6 in NSLEP 2013. These matters have been considered below:

(a) to promote development that conforms to and reflects natural landforms, by stepping

development on sloping land to follow the natural gradient,

13m height control

Page 21: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 21

Re: 467-473 Miller Street, Cammeray

The proposal generally maintains the natural landform of the site. Moreover the site is that being

at the top of the Cammeray plateau. There is no need to step the building and this is no reason to

exceed the height control by approximately 20%. The communal facilities on the fifth storey

would be visible from the public domain and significantly add to the bulk and scale of the

development and is therefore not supported.

(b) to promote the retention and, if appropriate, sharing of existing views,

The proposed works would not cause any significant view loss for the properties on the western

side of Miller Street.

(c) to maintain solar access to existing dwellings, public reserves and streets, and to

promote solar access for future development,

The proposed development would result in some reduction in solar access to the central courtyard

and balconies on the adjoining mixed use development at No.465 Miller Street. The extent of

impact is considered reasonable as morning solar access will be retained to the east facing living

room and balconies of the upper floor units at No.465 Miller Street.

The proposed southern lightwell is located directly opposite the central courtyard at No.465

Miller Street which assists in minimising the level of overshadowing to this adjoining property.

The extent of the impact is considered reasonable as it is largely caused by complying elements

of the proposed development.

The proposal is considered to maintain reasonable solar access to the adjoining properties and the

public domain during the winter solstice and the equinox.

(d) to maintain privacy for residents of existing dwellings and to promote privacy for

residents of new buildings,

The area of the communal space on the fifth storey is significant (240m²) and will likely result in

adverse acoustic impacts for developments on surrounding properties.

(e) to ensure compatibility between development, particularly at zone boundaries,

(f) to encourage an appropriate scale and density of development that is in accordance

with, and promotes the character of, an area.

The three storey podium height is generally characteristic of developments on adjoining

properties at No’s.463 and 465 Miller Street. The proposed fourth storey is setback 2.5meres

above the podium consistent with the desired built form in the Cammeray Village Centre

Character Statement. The fifth storey is significantly above the height control and would likely be

visible from the public domain. The fifth storey is inconsistent with the desired bulk and scale

that is envisaged by the controls within the B1 Neighbourhood Centre zone and with the smaller

scale Cammeray Conservation Area to the east.

Page 22: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 22

Re: 467-473 Miller Street, Cammeray

Figure 11 – Photomontage of proposed development from the northern end of Miller Street

Figure 12 – The fifth storey would likely be highly visible when coming into Cammeray

from the north.

It is concluded that the applicant’s written submission pursuant to Clause 4.6 is not considered to

be well founded and the deletion of the fifth storey, is considered reasonable in the site

circumstances.

Non residential floor space ratio

The proposed non residential floor space ratio is 0.60:1 and is compliant with the non-residential

floor space range for the site pursuant to Clause 4.4A(2) in NSLEP 2013. The lightwells between

the retail spaces are considered to constitute non residential floor space ratio as the retail

tenancies are proposed to open onto these lightwells and be used for retail purposes consistent

with the definition in Clause 4.4A(8) in NSLEP 2013. The proposed retail tenancies will

encourage greater activation along both Miller Street and Lane consistent with the objectives of

the control.

Heritage Conservation

The subject site is not listed as a heritage item nor is it located within a heritage conservation

area. Clause 5.10 in NSLEP 2013 is therefore not applicable.

Page 23: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 23

Re: 467-473 Miller Street, Cammeray

Earthworks

Council’s Development Engineer and RMS have recommended appropriate conditions of consent

requiring dilapidation reports and surveys, shoring of adjoining properties and a certificate from

an appropriately qualified geotechnical engineer certifying that the existing rock formations are

capable of withstanding the proposed loads without adversely impacting drainage or adjoining

properties. Through the recommended conditions of consent the proposal is considered

satisfactory having regard to Clause 6.10 in NSLEP 2013.

Office Premises in Zone B1 Neighbourhood Centre

The application does not propose office premises on the ground floor of the development in

accordance with clause 6.14 in NSLEP 2013. The ground floor is proposed to be activated by

retail tenancies consistent with the objectives of the zone. The proposal is considered

satisfactory having regard to Clause 6.14 in NSLEP 2013.

NSDCP 2013

DEVELOPMENT CONTROL PLAN 2013 – Part B Section 2- Commercial and Mixed Use Development

complies Comments

2.2 Function

Diversity of Activities Yes The proposed non-residential spaces would allow for a variety of uses and

responds well to the surrounding mixed use development.

The retail tenancies are designed to address the Miller Street and Miller Lane

frontages of the site.

Maximise Use of Public

Transport

Yes The site is located along Miller Street and within the Cammeray

Neighbourood Centre. The site is ideally located to maximise public transport

and provides appropriate end of trip facilities to encourage alternative forms

of transport.

The development has provided an adequate bicycle parking to encourage

alternative forms of transport.

Mixed Residential

Population

Yes Provision P2 requires that a mixed use development must contain at least 2 of

the following dwelling types, being a studio, one bedroom, two bedroom and

3 bedroom apartment.

The application proposes a mix of 4 x studio, 8 x 1 bedroom and 12 x 2

bedroom apartments. The percentage of studio and 1 bedroom apartments

(50%) is compliant with the maximum requirements (55%) in P3 in Part B,

Section 2.2.3 in NSDCP 2013.

Apartments L108, L208 and L308 are designed as adaptable units consistent

with the requirement in Provision P6 in Part B, Section 2.2.3 in NSDCP 2013.

2.3 Environmental Criteria

Clean Air Yes The proposed number of car parking spaces is in accordance with Part B,

Section 10.2.1 in NSDCP 2013. The development is appropriately located

along Miller Street to encourage alternate forms of travel. The proposal is

unlikely to adversely affect air quality.

Noise Yes (via

conditions)

Appropriate conditions of consent are recommended to address noise from

plant (lift and air conditioning units) (refer to Conditions C30, C31, C32

and C33).

Page 24: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 24

Re: 467-473 Miller Street, Cammeray

Wind Speed Yes Pedestrian comfort is unlikely to be adversely affected by wind when

walking along Miller Street given the scale of the development.

Reflectivity Yes The proposal provides a good proportion of solid to glass, with sliding

louvred screens provided to the balconies to minimise reflectivity impacts.

Metal framed sun shades are provided to the west facing balconies on

Level 4.

Artificial Illumination N/A No artificial illumination of the building is proposed.

Awnings Yes A metal framed awning is proposed along the Miller Street frontage of the

site. The design of the awning is generally in accordance with P2 in Part B,

Section 2.3.6 in NSDCP 2013. Council’s Director of Engineering Services

has provided written consent for the construction of the awning.

Solar Access Yes

Yes

The proposed development would result in some reduction in solar access to

the central courtyard and balconies on the adjoining mixed use development

at No.465 Miller Street. The extent of the impact is considered reasonable as

morning solar access will be retained to the east facing living room and

balconies of the upper floor units at No.465 Miller Street.

The proposed southern lightwell is located directly opposite the central

courtyard at No.465 Miller Street which assists in minimising the level of

overshadowing to this adjoining property. The extent of impact is considered

reasonable as it is largely caused by complying elements of the proposed

development.

The proposed development will maintain reasonable solar access to the

public spaces along Miller Lane and to the townhouse development at No.6

Raleigh Street.

A total of 17 (71%) of the apartments would receive more than 2 hours of

solar access between 8am and 4pm during the winter solstice. Early

morning (8am-9am) and late afternoon (3pm-4pm) solar access is included

as it contributes to the solar amenity of the apartments. Given the east/west

orientation and the site’s dual frontage early morning and late afternoon

solar access to these apartments is unlikely to be impacted by any future

developments.

Views Yes The proposed works would not cause any significant view loss for

adjoining properties or from the public domain.

Acoustic Privacy Yes

No

The design and layout of the apartments would provide reasonable acoustic

separation to minimise noise nuisance. A satisfactory buffer is provided

between the lift and the bedrooms of the apartments. Sliding louvred screens

have been added to the balconies to improve the internal amenity for the

apartments.

The area of the communal space on the fifth storey is significant (240m²) and

likely to result in adverse acoustic impacts for developments on surrounding

properties and not supported.

Vibration Yes Subject to recommended conditions imposed by RMS, the proposal is

unlikely to have an adverse vibration impacts on the adjoining lands.

Visual Privacy Yes Balcony and window openings that face the lightwells have been offset so

as not to result in direct overlooking between apartments. Planter boxes are

proposed to the Level 1 courtyards and sliding screens have been added to

the bedroom windows to further assist in this regard. The proposal is

considered acceptable having regard to privacy.

2.4 Quality built form

Context Yes The three storey podium with the fourth storey setback is considered to be

generally in keeping with mixed use developments in the locality.

The fifth storey is significantly above the height control and is likely be

visible from the public domain and set an undesirable precent for future

Page 25: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 25

Re: 467-473 Miller Street, Cammeray

redevelopment along the eastern side of Miller Street. The fifth storey is

inconsistent with the desired bulk and scale that is envisaged by the controls

within the B1 Neighbourhood Centre zone. Site consolidation Yes The building façade is appropriately articulated, with a good variation in

materials to reflect the existing subdivision patterns along the eastern side of

Miller Street. The wider frontage allows for improved street activation while

permitting a range of different sized commercial tenancies. Setback and Podium Yes

No

The proposal maintains a nil setback to Miller Street and Miller Lane

consistent with the established setback pattern. Council’s Development

Engineer raised no objection to the proposed basement built to the Miller

Lane boundary of the site. A setback is provided at ground level to provide

some public access.

The proposal provides a three storey podium with the fourth storey setback

2.5m from both the Miller Street and Miller Lane frontages consistent

surrounding developments and the desired built form in the Cammeray

Village Centre Character Statement.

The proposed fifth storey would significantly add to the bulk and scale of

the development and is not supported.

Building Design Yes The floor to ceiling height of the ground floor ranges between 2.8m and

4.1m by virtue of the stepped nature of the design which corresponds to the

fall of the site. The floor to ceiling height of the upper levels is 2.8m which

complies with the minimum requirements in Part B, Section 2.4.5 in

NSDCP 2013.

The balconies are incorporated into the design and the variation in colours

and materials assists in minimizing the apparent scale of the development.

Skyline Yes A fifth storey is significantly non compliant with the height control and is

likely interrupt the skyline and is therefore not supported for the reasons

detailed within this report.

Junction and

Termination of Streets

N/A The subject site is not located at any street junction or where a street

terminates.

Balconies - Apartments Yes Balconies are provided to all apartments. The areas of the balconies are

compliant with the Apartment Design Guide. The balconies are

incorporated into the overall design of the development.

Through Site

Pedestrian Links

Yes (via

condition) The amended plans indicate a 2.2m wide through site pedestrian link between

Miller Street and Miller Lane. The width of the through site pedestrian link is

considered appropriate given the size of the development. The pedestrian link

is lined with retail tenancies on both sides, appropriately graded and free of

obstructions to allow access for all persons regardless of mobility.

A condition is recommended requiring the applicant to create an easement

enabling the area to be maintained as a public right of way between 7am and

10pm Mondays to Sundays (refer to Condition G1).

Streetscape Yes The application proposes activation along both the Miller Street and Miller

Lane frontages of the site. The variation in materials assists in providing

visual interest to the building. The clear glazed windows to the ground

floor commercial tenancies assist in promoting active surveillance of the

public domain.

Entrances and Exits Yes The residential lobby and retail tenancies are clearly visible and provide a

sense of address to the building. The amended plans have increased the

width of both the residential lobby and the through site pedestrian link to

improve amenity and provide opportunities for social interaction.

Nighttime appearance Yes The building will have an acceptable night time appearance.

Public Spaces and

facilities

Yes The building contributes positively to its surroundings with improved

activation at street level.

2.5 Quality Urban Environment

Accessibility Yes (via Lift access is provided to all levels of the building ensuring compliance

Page 26: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 26

Re: 467-473 Miller Street, Cammeray

condition) with the requirements of the BCA. Apartments L108, L208 and L308 are

designed as adaptable units. A condition will be imposed requiring

compliance with the relevant BCA provisions (refer to Condition F1).

Safety and Security Yes (via

conditions)

There are no known safety and security concerns arising from the proposed

development. The activation of Miller Lane will assist in improving natural

surveillance of the carpark. A condition is recommended that an intercom

system, a security door is proposed at the entry to the residential lobby and the

restrictions placed on the through site pedestrian link would maintain safety

and security for the residents, visitors and commercial tenants.

Illumination Yes The application does not propose any building illumination.

High Quality

Residential

Accommodation

Yes The areas of the apartments are all compliant with the minimum requirements

in the Apartment Design Guide.

Given the eastern and western orientation of the apartments, the balconies and

living spaces of the apartments will receive reasonable morning or afternoon

sunlight during mid winter and the equinox. Sun shades are provided to the

upper floor western balconies to control sunlight.

Balconies are provided to each apartment to allow functional private open

space for the residents with good solar access. The areas of the balconies are

compliant with the areas specified in the Apartment Design Guide.

Each apartment has a minimum width greater than 4m and all apartments

will receive satisfactory ventilation. Operable windows are provided to all

living rooms and the kitchens to the apartments are less than 8m from these

windows ensuring reasonable amenity.

The two bedroom apartments have windows to the lightwells to maximise

light and ventilation.

Lightwells Yes The dimensions of the lightwells generally comply with the minimum

dimensions specified in P1 in Part B, Section 2.5.5 in NSDCP 2013. The

lightwells are open to the sky and windows within the lightwells are offset

to minimise the potential for overlooking.

Private Open Space Yes

No

(acceptable

on merit)

Balconies are provided to all apartments.

A communal roof top facility is not consisted appropriate for this

development for the reasons provided throughout this report. The site is

well located in close proximity to Tunks, Cammeray and St Leonards Parks

to provide some further opportunities for social interaction.

Vehicular Access Yes (via

conditions)

Council’s Development Engineer has recommended appropriate conditions

to ensure compliance with Council’s current Vehicular Access Application

Guidelines, Specification and relevant Australian Standards (refer to

Conditions C21).

Car, Bicycle and

Motorcycle Parking

Yes

Car parking

The proposed car parking complies with the maximum parking rate

specified in Part B, Section 10.2.1 in NSDCP 2013 as detailed in the table

below:

Development

Component

DCP 2013 Rate DCP 2013

Max. No.

No.

Proposed

Res. 24 x

Studio, 1

& 2 bed

1 space/Studio,

1 & 2 bedroom

dwelling

24 24

Page 27: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 27

Re: 467-473 Miller Street, Cammeray

Yes

Yes

Visitor/Car

Wash

0.25

space/dwelling 6 6

Retail 489m2 0.01 5 4

TOTAL 35 34

Bicycle and Motorcycle

The amended plans provide a motor cycle car parking space and racks for

22 bicycles which is generally compliant with the requirements in P1 in

Part B, Section 10.5 in NSDCP 2013. Additional bicycle spaces have been

provided for the retail tenancies. End of trip facilities are also provided on

the ground level and within the Lower Basement Level for use by the non

residential uses consistent with P11, Part B, Section 10.5 in NSDCP 2013.

Loading and unloading

A loading and unloading zone is provided on the upper basement level for

a small rigid vehicle consistent with the requirements in P1, Part B, Section

10.4 in NSDCP 2013.

Garbage Storage Yes The amended plans indicate a garbage holding bay adjacent to the Miller Lane

frontage of the site and a garbage room on each of the residential levels of the

development which satisfy the waste requirements of Council’s Environmental

Education Officer.

Site Facilities Yes Letterboxes are provided alongside the entry to the residential lobby and

adequate storage space has been provided for each apartment.

2.6 Efficient Use of Resources

Energy Efficiency Yes (via

condition)

A valid ‘multi dwelling BASIX Certificate was submitted with the

application demonstrating the efficient use of resources.

Stormwater

Management

Yes (via

condition)

Council’s Development Engineer has recommended appropriate conditions

to ensure stormwater runoff and subsoil drainage generated by the

approved dwellings is conveyed in a controlled manner via an on-site-

detention system to Council’s kerb in Miller Street (refer to Condition

C21).

Green Roofs Yes The amended plans incorporate green walls and a green roof to provide

improved amenity and aesthetics.

2.7 Public Domain

Street Furniture,

Landscaping Works

Yes The application proposes to retain the seat on the Miller Street footpath in

front of the subject site.

Cammeray Planning Area (Cammeray Village Centre)

Consideration has been given to Part C of NSDCP 2013 and in particular Section 4 of the

Character Statement for the Cammeray Planning Area and Section 4.1 for the Cammeray Village

Centre. Subject to the deletion of the fifth storey, as detailed within this report, the proposal is

considered to be generally in keeping with the desired future character and built form for the

following reasons:

The new retail tenancies are proposed at ground level to improve street activation along

Miller Street and Miller Lane.

Residential apartments are proposed above the retail tenancies.

The proposal will not adversely impact district views towards Middle Harbour.

The proposal maintains a three storey parapet to Miller Street consistent with the

adjoining developments. The fourth storey is setback 2.5m from both the Miller Street

and Miller Lane boundary consistent with the setback control.

The building façade is appropriately articulated to reflect the existing subdivision pattern

along the eastern side of Miller Street.

Page 28: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 28

Re: 467-473 Miller Street, Cammeray

An awning is proposed along the Miller Street footpath consistent with the established

streetscape.

Basement carparking is provided off Miller Lane.

Sliding louvre screens have been proposed to the balconies to assist in improving internal

amenity to the apartments.

The proposal is unlikely to adversely impact the Miller Street trees in front of the site.

The proposal is therefore considered acceptable having regard to the Cammeray Village

Character Statement.

SECTION 94 CONTRIBUTIONS

Due to the provision of new residential apartments (4 x Studios, 8 x 1B and 12 x 2B) and

additional retail spaces (489m²), a contribution would be levied in accordance with Council’s

Section 94 Contributions Plan. A credit will be provided for the existing commercial floor space

(674m²) and the existing residential apartment (1 x 1B). The contribution amount for the

development is $261,542.69, as shown in the table below

Facility

Residential

contribution (4 x

S, 8 x 1B, 12 x

2B)

Residential

credit (1 x

1B)

Commercial

contribution

(489m²)

Commercial credit

(674m²) Total

Administration 2,700.07 100.80 1,056.97 1,456.85 2,199.39

Community Centres 12,257.88 457.64 2,576.54 3,551.31 10,825.47

Childcare Facilities 4,676.93 174.61 4,474.59 6,167.44 2,809.47

Library and Local

Studies Acquisitions 2,286.40 85.36 525.43 724.21 2,002.26

Library Premises

and Equipment 7,073.26 264.07 1,597.32 2,201.62 6,204.89

Multi Purpose

Indoor Sports

Facility 1,931.31 72.10 604.40 833.06 1,630.55

Olympic Pool 6,290.76 234.86 1,969.69 2,714.87 5,310.72

Open Space

Acquisitions 77,094.20 2,878.24 1,926.42 2,655.22 73,487.16

Open Space

Increased Capacity 152,813.97 5,705.17 3,818.36 5,262.93 145,664.23

Public Domain

Improvements 6,040.89 225.53 4,084.62 5,629.92 4,270.06

Traffic

Improvements 7,415.33 276.84 - - 7,138.49

Total

$261,542.69

DESIGN & MATERIALS

The comments from the Design Excellence Panel with respect to design and materials have been

generally addressed by the amended plans as detailed within this report.

SITE SUITABILITY

The proposal is considered to be suitable for the subject site as detailed within this report.

Page 29: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 29

Re: 467-473 Miller Street, Cammeray

ALL LIKELY IMPACTS OF THE DEVELOPMENT

All likely impacts of the proposed development have been considered within the context of this

report.

ENVIRONMENTAL APPRAISAL CONSIDERED

1. Statutory Controls Yes

2. Policy Controls Yes

3. Design in relation to existing building and Yes

natural environment

4. Landscaping/Open Space Provision Yes

5. Traffic generation and Carparking provision Yes

6. Loading and Servicing facilities Yes

7. Physical relationship to and impact upon adjoining Yes

development (Views, privacy, overshadowing, etc.)

8. Site Management Issues Yes

9. All relevant S79C considerations of Yes

Environmental Planning and Assessment (Amendment) Act 1979

SUBMITTORS CONCERNS

The original application was notified to adjoining property owners and the Plateau Precinct

Committee between 21 August and 4 September 2015. A total of nine (9) submissions were

received against the original application and one (1) submission in support of the original

application. The amended application was also notified to the Plateau Precinct Committee and

adjoining properties between 18 December 2015 and 15 January 2016. One (1) submission was

received against the amended application.

The issues raised in the submissions are summarized and addressed below with planning

comments:

The proposed retail tenancies on the ground floor of the development are likely to

result in noise nuisance for surrounding properties.

The proposed retail tenancies are unlikely to result in any adverse noise impacts on surrounding

properties given the high proportion of residential tenants within the development. The subject

site is zoned B1 Neighbourhood Centre and is located within the Cammeray Village Centre

where shop top housing is encouraged by the controls. Nevertheless, a condition is

recommended requiring the first use of the retail tenancies to submit a new development

application to Council for assessment in particular the likelihood of noise nuisance arising from

any future use of the commercial component of the development.

Page 30: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 30

Re: 467-473 Miller Street, Cammeray

The likely loss of sunlight and privacy from the proposed development

The proposed development would result in some reduction in solar access to the central courtyard

and balconies on the adjoining mixed use development at No.465 Miller Street, Miller Lane and

the townhouse development at No.6 Raleigh Street. The reduction is largely caused by complying

elements of the proposed development. The location of the proposed southern lightwell directly

opposite this central courtyard at No.465 Miller Street would assist in minimising the level of

overshadowing to this adjoining property. The proposal would maintain solar access to the east

facing balconies and living rooms of the apartments at No.465 Miller Street.

The height of the proposed development will have a negative impact on mobile service

coverage and/or emergency calls in the surrounding area

A condition is recommended that the fifth storey be deleted which will likely assist in minimising

any adverse impacts on telecommunications coverage, mobile services and emergency calls in the

surrounding area.

The proposal is non compliant with the permissible building height in Clause 4.3(2) in

NSLEP 2013.

A condition is recommended requiring the deletion of the communal facilities on the fifth storey

which will ensure the proposal satisfies the objectives of the height control.

The five storey scale is considered to be excessive and will detract from the character of

the locality

The proposed three storey podium height to Miller Street is also consistent with the adjoining

developments on the eastern side of Miller Street at No’s 463 and 465 Miller Street. The fourth

storey is setback above the podium consistent with the Cammeray Village Centre Character

Statement. The fifth storey is above the height control, would be visible from the public domain

and set an undesirable precent for future redevelopment along the eastern side of Miller Street.

The fifth storey is therefore not supported.

The proposal will result in an increase in afternoon shadows to the properties on the

eastern side of Miller Lane

The proposed development will maintain reasonable solar access to the public spaces along

Miller Lane and to the townhouse development at No.6 Raleigh Street.

The proposal provides inadequate carparking for residents and visitors of the

development

The proposed car parking complies with the maximum parking rate specified in Part B, Section

10.2.1 in NSDCP 2013 as detailed earlier within this report.

The proposal will likely result in traffic congestion along Miller Lane.

Council’s Manager of Traffic and Transport Operations considers that the proposed development

is unlikely to have any unacceptable traffic implications on Miller Lane or the surrounding road

network.

Page 31: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 31

Re: 467-473 Miller Street, Cammeray

The likely amenity impacts on the locality during excavation and construction works

Appropriate conditions are recommended during demolition, excavation and construction to

minimise adverse impacts on the locality (refer to Condition B1, E3, E4, E6, E9, E10, E15,

E17, E18 and E23).

The proposed fenestration on the balcony, in particular the louvre screens are not

compatible with the streetscape.

The amended colours and finishes are generally compatible with surrounding developments in

the locality as agreed by the Designed Excellence Panel.

PUBLIC INTEREST

The proposal is unlikely to offend the public interest as discussed throughout this report.

CONCLUSION

The development application has been assessed against the North Sydney Local Environmental

Plan 2013, the North Sydney Development Control Plan 2013 and the relevant State and

Regional Planning Policies and generally found to be acceptable.

The applicant has submitted a Clause 4.6 objection to Clause 4.3 (Building Height). The fifth

storey communal facilities which breach the building height control are not supported as they

would dominate the upper levels of the building contrary to the objectives of the control and the

zone.

The application proposes new retail tenancies on the ground level to enhance street activation

along Miller Street and Miller Lane. A through site pedestrian link provides improved access

between Miller Street and Miller Lane. The central lightwells and dual frontage ensures

reasonable levels of light and ventilation to the apartments without materially impacting on the

amenity of adjoining properties.

The three storey podium height to Miller Street is consistent with the adjoining developments on

the eastern side of Miller Street (No’s 463 and 465 Miller Street). The fourth storey is setback

from both Miller Street and Miller Lane which is generally consistent with the mixed use

developments that are directly opposite on the western side of Miller Street (No’s 510, 514 and

518-520 Miller Street) and generally compliant with the height control. Development on the

western side of Miller Street should not be taken as a precedent for exceedance of the height

control on the eastern side which relates to the Cammeray Conservation Area.

The proposed communal facilities on the fifth storey are significantly above the height control

and would likely be visible from the public domain and set an undesirable precent for future

redevelopment along the eastern side of Miller Street. The facilities are of such a size that they

present a ready opportunity for conversion to habitable space at a later date. The communal

facilities on the fifth storey are therefore not supported.

It is recommended that a deferred commencement approval be granted subject to the

deletion of the fifth storey and the submission of an amended strata plan.

Page 32: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 32

Re: 467-473 Miller Street, Cammeray

RECOMMENDATION

PURSUANT TO SECTION 80 OF ENVIRONMENTAL PLANNING AND ASSESSMENT

ACT 1979 (AS AMENDED)

THAT the North Sydney Independent Planning Panel, under the delegation of the General

Manager as the consent authority, assume the concurrence of the Director General of the

Department of Planning and invoke the provisions of Clause 4.6 NSLEP2013 with regards to the

non-compliance with Clause 4.3 (Building Height) and grant deferred commencement consent

to Development Application No. 280/15 for the demolition of the existing buildings and the

construction of a four storey mixed use building consisting basement parking for 34 vehicles,

retail tenancies on the ground floor, 24 apartments on the levels above including strata

subdivision on land at No.467-473 Miller Street, Cammeray subject to the following site specific

and the attached conditions of consent:-

Deletion of the roof top communal facilities on Level 5 (Deferred Commencement)

AA1. No approval is given under this consent for any communal facilities on level 5 of the

development. The roof over level 4 of the development may only be accessible for

maintenance purposes.

Amended architectural and landscape plans complying with this condition must be

submitted to Council for approval prior to the development consent becoming

operational.

(Reason: To ensure greater compliance with Council’s controls)

Amended strata plan (Deferred Commencement)

AA2 An amended strata plan incorporating the changes as required by Condition AA1 must be

submitted to Council for approval prior to the development consent becoming

operational.

(Reason: To ensure the approved strata scheme is in accordance with the approved plans)

Upon satisfaction of the deferred commencement condition, the following site specific

conditions apply:

Roads and Maritime Requirements

C1. Prior to the issue of a Construction Certificate:

1. All buildings and structures (other than pedestrian footpath awnings), together

with any improvements integral to the future use of the site must be wholly

contained within the freehold property (unlimited in height or depth), along the

Miller Street boundary.

2. Any changes to the stormwater drainage system must be submitted to the Roads

and Maritime Service for approval prior to the commencement of any works.

Page 33: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 33

Re: 467-473 Miller Street, Cammeray

Detailed design plans and hydraulic calculations of any changes to the stormwater

drainage system are to be submitted to Roads and Maritime for approval, prior to

the commencement of any works. Details should be forwarded to:

The Sydney Asset Management Roads and Maritime Services PO Box 973

Parramatta CBD 2124

A plan checking fee will be payable and a performance bond may be required

before Roads and Maritime approval is issued. With regard to the Civil Works

requirement please contact the Roads and Maritime Project Engineer, External

Works Ph: 8849 2114 or Fax: 8849 2766.

3. The developer is to submit design drawings and documents relating to the

excavation of the site and support structures to Roads and Maritime for

assessment, in accordance with Technical Direction GTD201 21001.

4. The developer is to submit all documentation at least six (6) weeks prior to

commencement of construction and is to meet the full cost of the assessment by

Roads and Maritime.

The report and any enquiries should be forwarded to:

Project Engineer, External Works Sydney Asset Management Roads and

Maritime Services PO Box 973 Parramatta CBD 2124.

Telephone 8849 2114 Fax 8849 2766

If it is necessary to excavate below the level of the base of the footings of the

adjoining roadways, the person acting on the consent shall ensure that the owner/s

of the roadway is/are given at least seven (7) days notice of the intention to

excavate below the base of the footings. The notice is to include complete details

of the work.

5. A Construction Traffic Management Plan detailing construction vehicle routes,

number of trucks, hours of operation, access arrangements and traffic control

should be submitted to Council for approval prior to the issue of a Construction

Certificate.

5. A Road Occupancy Licence should be obtained from Transport Management

Centre for any works that may impact on traffic flows on Miller Street during

construction activities.

6. All demolition and construction vehicles are to be contained wholly within the

site and vehicles must enter the site before stopping. A construction zone will not

be permitted on Miller Street.

(Reason: To satisfy RMS requirements)

Right of Way through site

G1. The applicant shall create an easement pursuant to Section 88B instrument under the

Page 34: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 34

Re: 467-473 Miller Street, Cammeray

Conveyancing Act 1919 to provide for public rights of access shown on the submitted

plans (plan 5 and 6) which achieves the objectives of:-

enabling the area to be maintained as a public right of way

enabling the public to use that area for the purpose of public access at all the

times the commercial and retail parts of the building are open

ensure the rights are not subject to change or variation except with the prior

consent of Council

The public access rights are to include:-

the capacity to allow a public access linkage between Miller Street and Miller

Lane between the hours of 7am and 10pm Mondays to Sundays.

terms and conditions which both achieve the objectives identified above and are

to the satisfaction of Council’s Director of Planning and Environmental Services

The easement shall be prepared, executed and registered at the sole cost of the applicant,

including the costs of Council in obtaining advice, producing documents or otherwise

facilitating the preparation, execution and registration of the required documents, shall

bind all successors in title and shall only be subject to variation at the discretion of the

Council. The easement shall be for the life of the building and not in perpetuity.

(Reason: Public access and internal amenity)

Covenant for Windows on Northern and Southern Elevations

G2. A covenant pursuant to the provisions of Part 6, Division 4 of the Conveyancing Act shall

be placed on title indicating that the windows on or near the northern and southern

boundaries are not protected from any redevelopment of the adjoining properties that may

be allowed to build to the boundary and these windows could be blocked off. North

Sydney Council shall be nominated in the instrument as the only party authorised to

release, vary or modify the instrument. Evidence of the lodgement of the instrument

referred to in this condition is to be provided to Council with a copy of the Occupation

Certificate.

(Reason: To ensure owners, or intending owners of the property are aware that

the western windows are not protected and could be blocked by future

development)

Street Lighting in Miller Street and Miller Lane

G3. Prior to the issue of the Occupation Certificate, the developer must pay to upgrade the

street lighting in Miller Street and Miller Lane, adjacent to the site, to the satisfaction of

Council. The developer must engage a lighting consultant to ensure the lighting is in

accordance with the relevant Australian Standard and to the satisfaction of Council’s

Traffic Operation’s Officer, Maria Coyne.

(Reason: To ensure consistency with the terms of the consent)

Page 35: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Report of Luke Donovan, Senior Assessment Officer Page 35

Re: 467-473 Miller Street, Cammeray

Luke Donovan Robyn Pearson

SENIOR ASSESSMENT OFFICER TEAM LEADER (ASSESSMENTS)

Stephen Beattie

MANAGER OF DEVELOPMENT SERVICES

Page 36: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

NORTH SYDNEY COUNCIL

CONDITIONS OF DEVELOPMENT APPROVAL

467-473 MILLER STREET, CAMMERAY

DEVELOPMENT APPLICATION NO. 280/15

DEFERRED COMMENCEMENT CONDITIONS This consent shall not operate until the following deferred commencement conditions have been satisfied. The applicant must satisfy Council as to the matters specified in the deferred commencement conditions within 12 months of the date of the granting of this consent. If the applicant fails to satisfy Council as to the matters specified in the deferred commencement conditions within 12 months of the date of the granting of this consent, this consent will lapse in accordance with Section 95(6) of the Environmental Planning and Assessment Act 1979. NOTE: Consideration should be given to providing the evidence to Council to allow sufficient time consider the same and form a view as to whether the deferred commencement conditions are satisfied or not. You are also advised of your appeal rights under clause 95(6) of the Environmental Planning and Assessment Regulation 2000, which provides that: If the consent authority has not notified the applicant within the period of 28 days after the applicant’s evidence is produced to it, the consent authority is, for the purposes only of section 97 of the Act, taken to have notified the applicant that it is not satisfied as to those matters on the date on which that period expires. AA. Deferred Commencement Conditions Deletion of the roof top communal facilities on Level 5 (Deferred Commencement) AA1. No approval is given under this consent for any communal facilities on level 5 of the

development. The roof over level 4 of the development may only be accessible for maintenance purposes.

Amended architectural and landscape plans complying with this condition must be submitted to Council for approval prior to the development consent becoming operational. (Reason: To ensure greater compliance with Council’s controls)

Amended strata plan (Deferred Commencement) AA2. An amended strata plan incorporating the changes as required by Condition AA1 must

be submitted to Council for approval prior to the development consent becoming operational.

(Reason: To ensure the approved strata scheme is in accordance with the approved

plans)

ATTACHMENT TO IPP07 - 03/02/2016 Page 36

Page 37: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 2 of 52 Upon satisfaction of the deferred commencement condition, the following conditions apply: Development in Accordance with Plans/documentation A1. The development must be carried out in accordance with the following drawings and

documentation and endorsed with Council’s approval stamp, except where amended by the following conditions of this consent.

Plan No. Rev. Title Drawn by: Plot Date/Rev

Date DA01 - Site Plan/Site Analysis Plan Wolski. Coppin Architecture 8/12/2015 DA02 - Lower Basement Plan Wolski. Coppin Architecture 8/12/2015 DA03 - Basement Plan Wolski. Coppin Architecture 6/11/2015 DA04 A Ground Floor Plan Wolski. Coppin Architecture 6/11/2015 DA05 B Typical Floor Plan (L1 & L2) Wolski. Coppin Architecture 22/12/2015 DA06 B Level 3 Floor Plan Wolski. Coppin Architecture 22/12/2015 DA07 A Level 4 Floor Plan Wolski. Coppin Architecture 6/11/2015 DA08 A Roof Plan Wolski. Coppin Architecture 6/11/2015 DA09 A Longitudinal Section (Section

AA) Wolski. Coppin Architecture 6/11/2015

DA10 A Cross Section (Section BB) Wolski. Coppin Architecture 6/11/2015 DA11 A North Elevation Wolski. Coppin Architecture 6/11/2015 DA12 A East Elevation Wolski. Coppin Architecture 6/11/2015 DA13 A West Elevation Wolski. Coppin Architecture 6/11/2015 DA14 A South Elevation Wolski. Coppin Architecture 6/11/2015 Draft Strata Plan – Plan of

subdivision of Lots 2 and 3 in DP 983635 and Lot 4 in DP1985

L1 D Landscape Concept Plan Ground Floor

Wallman Partners Pty Ltd Landscape Architects

8/12/2015

L2 B Landscape Concept Plan Level 1 Wallman Partners Pty Ltd Landscape Architects

8/12/2015

L3 A Landscape Concept Plan Level 4 Wallman Partners Pty Ltd Landscape Architects

8/12/2015

(Reason: To ensure that the form of the development undertaken is in

accordance with the determination of Council, Public Information) Plans on Site A2. A copy of all stamped approved plans, specifications and documents (including the

plans, specifications and documents submitted and approved with the Construction Certificate) must be kept on site at all times so as to be readily available for perusal by any officer of Council or the Principal Certifying Authority. All documents kept on site in accordance with this condition must be provided to any officer of the Council or the certifying authority upon their request.

(Reason: To ensure that the form of the development undertaken is in

accordance with the determination of Council, Public Information and to ensure ongoing compliance)

ATTACHMENT TO IPP07 - 03/02/2016 Page 37

Page 38: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 3 of 52 External Finishes & Materials A3. External finishes and materials must be in accordance with the submitted schedule

Drawing Number F01 ‘Finishes Schedule’, Revision A dated 6/11/2015 drawn by Wolski. Coppin Architecure and received by Council on 8/12/2015 unless otherwise modified by Council in writing.

(Reason: To ensure that the form of the development undertaken is in

accordance with the determination of Council, Public Information) B. Matters to be Completed before the lodgement of an Application for a Construction

Certificate Construction Management Program – Local Traffic Committee Approval B1. A Construction Management Program prepared by a suitably qualified and

experienced traffic consultant must be submitted and approved in writing by North Sydney Traffic Committee PRIOR TO THE ISSUE OF ANY Construction Certificate. Any use of Council property will require appropriate approvals prior to any work commencing. At a minimum, the Construction Management Program must specifically address the following matters:

a) A plan view (min 1:100 scale) of the entire site and frontage roadways

indicating: i. Dedicated temporary construction site driveway entrances and exits,

controlled by a certified traffic controller, to safely manage pedestrians and construction related vehicles in the frontage roadways and footways;

ii. The proposed signage for pedestrian management to comply with the relevant Australian Standards, including pram ramps;

iii. Turning areas within the site for construction and spoil removal vehicles, allowing a forward egress for all construction vehicles on the site;

iv. The locations of any proposed Work Zones in the frontage roadways (to be approved by Council’s Traffic Committee);

v. Locations of hoardings proposed; vi. Location of any proposed crane standing areas; vii. A dedicated unloading and loading point within the site for all

construction vehicles, plant and deliveries; viii. Material, plant and spoil bin storage areas within the site, where all

materials are to be dropped off and collected; and ix. The provision of an on-site parking area for employees, tradesperson and

construction vehicles as far as possible.

b) A detailed heavy vehicle access route map through the Council area to Arterial Roads. Provision is to be made to ensure through traffic is maintained at all times.

ATTACHMENT TO IPP07 - 03/02/2016 Page 38

Page 39: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 4 of 52

c) The proposed phases of works on the site, and the expected duration of each phase.

d) How access to neighbouring properties will be maintained at all times and the

proposed manner in which adjoining property owners will be kept advised of the timeframes for completion of each phase of process.

e) The road is not to be used as a waiting area for trucks delivering to or awaiting

pick up of materials.

f) The proposed method of support to any excavation adjacent to adjoining properties, or the road reserve. The proposed method of support is to be designed and certified by an appropriately qualified and practising structural engineer and must not involve any permanent or temporary encroachment onto Councils property.

g) Proposed protection for Council and adjoining properties. Details are to

include site fencing and the provision of “B” class hoardings over footpaths and laneways.

h) A Waste Management Plan. The Waste Management Plan must include, but

not be limited to, the estimated volume of waste and method of disposal for the construction and operation phases of the development, design of on-site waste storage and recycling area and administrative arrangements for waste and recycling management during the construction process.

All traffic control work and excavation, demolition and construction activities must be undertaken in accordance with the approved Construction Management Program and any conditions attached to the approved Program. A certificate of compliance with this condition must be obtained from Council’s development engineers. The certificate and the approved Construction Management Program must be submitted as part of the documentation lodged with the application for approval of a construction certificate. A copy of the approved Construction Management Program and any conditions imposed on that Program, must be kept on the site at all times and made available to any officer of Council upon request. Notes: 1) North Sydney Council’s adopted fee for certification of compliance with this

condition shall be payable on lodgement, or in any event, prior to the issue of the relevant approval.

2) Any use of Council property will require appropriate approvals and demonstration of liability insurances prior to such work commencing.

3) Failure to provide complete and detailed information may result in delays. It is recommended that your Construction Management Plan be lodged with Council as early as possible, as a minimum six (6) weeks notice is required to refer items to the Traffic Committee.

4) Dependent on the circumstances of the site, Council may request additional information to that detailed above.

ATTACHMENT TO IPP07 - 03/02/2016 Page 39

Page 40: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 5 of 52

(Reason: To ensure appropriate measures have been considered for site access, storage and the operation of the site during all phases of the demolition process in a manner that respects adjoining owner’s property rights and residential amenity in the locality, without unreasonable inconvenience to the community)

C. Prior to the Issue of a Construction Certificate (and ongoing, where indicated). Roads and Maritime Requirements

C1. Prior to the issue of a Construction Certificate:

1. All buildings and structures (other than pedestrian footpath awnings), together

with any improvements integral to the future use of the site must be wholly contained within the freehold property (unlimited in height or depth), along the Miller Road boundary.

2. Any changes to the stormwater drainage system must be submitted to the

Roads and Maritime Service for approval prior to the commencement of any works.

Detailed design plans and hydraulic calculations of any changes to the stormwater drainage system are to be submitted to Roads and Maritime for approval, prior to the commencement of any works. Details should be forwarded to: The Sydney Asset Management Roads and Maritime Services PO Box 973 Parramatta CBD 2124 A plan checking fee will be payable and a performance bond may be required before Roads and Maritime approval is issued. With regard to the Civil Works requirement please contact the Roads and Maritime Project Engineer, External Works Ph: 8849 2114 or Fax: 8849 2766.

3. The developer is to submit design drawings and documents relating to the

excavation of the site and support structures to Roads and Maritime for assessment, in accordance with Technical Direction GTD201 21001.

4. The developer is to submit all documentation at least six (6) weeks prior to

commencement of construction and is to meet the full cost of the assessment by Roads and Maritime.

The report and any enquiries should be forwarded to: Project Engineer, External Works Sydney Asset Management Roads and Maritime Services PO Box 973 Parramatta CBD 2124. Telephone 8849 2114 Fax 8849 2766

ATTACHMENT TO IPP07 - 03/02/2016 Page 40

Page 41: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 6 of 52

If it is necessary to excavate below the level of the base of the footings of the adjoining roadways, the person acting on the consent shall ensure that the owner/s of the roadway is/are given at least seven (7) days notice of the intention to excavate below the base of the footings. The notice is to include complete details of the work.

5. A Construction Traffic Management Plan detailing construction vehicle routes, number of trucks, hours of operation, access arrangements and traffic control should be submitted to Council for approval prior to the issue of a Construction Certificate.

5. A Road Occupancy Licence should be obtained from Transport Management

Centre for any works that may impact on traffic flows on Miller Street during construction activities.

6. All demolition and construction vehicles are to be contained wholly within the

site and vehicles must enter the site before stopping. A construction zone will not be permitted on Miller Street.

(Reason: To satisfy RMS requirements)

Dilapidation Report Damage to Public Infrastructure C2. A dilapidation survey and report (including photographic record) must be prepared by

a suitably qualified consultant which details the pre-developed condition of the existing public infrastructure in the vicinity of the development site. Particular attention must be paid to accurately recording any pre-developed damaged areas so that Council is fully informed when assessing any damage to public infrastructure caused as a result of the development. A copy of the dilapidation survey and report is to be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The developer may be held liable for all damage to public infrastructure in the vicinity of the site, where such damage is not accurately recorded and demonstrated as pre-existing under the requirements of this condition.

The developer shall bear the cost of carrying out works to restore all public infrastructure damaged as a result of the carrying out of the development, and no occupation of the development shall occur until damage caused as a result of the carrying out of the development is rectified. A copy of the dilapidation survey and report must be lodged with North Sydney Council by the Certifying Authority with submission of the Construction Certificate documentation. (Reason: To record the condition of public infrastructure prior to the

commencement of construction)

ATTACHMENT TO IPP07 - 03/02/2016 Page 41

Page 42: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 7 of 52 Dilapidation Report Private Property (Excavation)

C3. A full dilapidation survey and report on the visible and structural condition of all neighbouring structures within the ‘zone of influence’ of the required excavations must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The zone of influence is to be defined as the horizontal distance from the edge of the excavation face to twice the excavation depth. The dilapidation report and survey is to be prepared by a consulting structural/geotechnical engineer agreed to by both the applicant and the owner of any affected adjoining property.

All costs incurred in achieving compliance with this condition shall be borne by the person entitled to act on this Consent.

In the event that access for undertaking the dilapidation survey is denied by an adjoining owner, the applicant MUST DEMONSTRATE, in writing, to the satisfaction of Council that all reasonable steps have been taken to obtain access and advise the affected property owner of the reason for the survey and that these steps have failed. Written concurrence must be obtained from Council in such circumstances.

Note: This documentation is for record keeping purposes only, and may be used by the developer or affected property owner to assist in any action required to resolve any dispute over damage to adjoining properties arising from the works. It is in the applicant’s and adjoining owner’s interest for it to be as full and detailed as possible.

(Reason: To record the condition of property/ies prior to the commencement of construction)

Dilapidation Survey Private Property (Neighbouring Buildings) C4. A photographic survey and dilapidation report of adjoining properties No’s. 465 and

475 Miller Street, Cammeray detailing the physical condition of those properties, both internally and externally, including, but not limited to, such items as walls, ceilings, roof, structural members and other similar items, SHALL BE submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The survey and report is to be prepared by an appropriately qualified person agreed to by both the applicant and the owner of the adjoining property. A copy of the report is to be provided to Council, if Council is not the Certifying Authority, prior to the issue of any Construction Certificate.

All costs incurred in achieving compliance with this condition shall be borne by the person entitled to act on this Consent.

In the event that access for undertaking the photographic survey and dilapidation report is denied by an adjoining owner, the applicant MUST DEMONSTRATE, in writing, to the satisfaction of Council that all reasonable steps have been taken to obtain access and advise the affected property owner of the reason for the survey and that these steps have failed. Written concurrence must be obtained from Council in such circumstances.

ATTACHMENT TO IPP07 - 03/02/2016 Page 42

Page 43: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 8 of 52

Note: This documentation is for record keeping purposes only, and may be used by an applicant or affected property owner to assist in any action required to resolve any dispute over damage to adjoining properties arising from the works. It is in the applicant’s and adjoining owner’s interest for it to be as full and detailed as possible.

(Reason: Proper management of records)

Shoring for Adjoining Property C5. Where any shoring for excavation is to be located on or is supporting Council’s

property, or any adjoining private property, engineering drawings certified as being adequate for their intended purpose by an appropriately qualified and practising structural engineer, showing all details, including the extent of excavation, encroachment and the method of removal and de-stressing of shoring elements, backfilling and compacting of over-excavated cavities on Council’s and/or private property with fill suitable for its purpose, must be submitted to the Certifying Authority for approval with the Construction Certificate. A copy of this documentation must be provided to the Council for record purposes. Backfilling and compacting of over-excavated cavities must be addressed as the build up is progressing through the basements to ensure that compaction is reliable. A separate application must be made with Council for tieback anchors.

Note: Approval of engineering drawings for shoring works to be located on adjoining property by the Certifying Authority does not authorise a trespass on private or public land. All relevant permissions/ legal rights must be obtained to undertake any works on adjoining land.

(Reason: To ensure the protection of existing public infrastructure and adjoining

properties)

Structural Adequacy of Adjoining Properties – Excavation Works C6. A report prepared by an appropriately qualified and practising structural engineer

detailing the structural adequacy of adjoining properties No’s. 465 and 475 Miller Street, Cammeray, which certifies their ability to withstand the proposed excavation and outlines any measures required to be implemented to ensure that no damage will occur to adjoining properties during the course of the works, must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The measures outlined in the certified report must be complied with at all times. (Reason: To ensure the protection and structural integrity of adjoining properties

in close proximity during excavation works)

ATTACHMENT TO IPP07 - 03/02/2016 Page 43

Page 44: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 9 of 52 Structural Adequacy C7. A report from an appropriately qualified and practising structural engineer, certifying

the structural adequacy of the adjoining property No. 465 Miller Street, Cammeray which certifies its ability to withstand the proposed works and outlines any measures required to be implemented to ensure that no damage will occur to adjoining premises during the course of the works, must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The measures outlined in the certified report must be complied with at all times.

Under no circumstances shall the party or common wall be extended or altered without the prior written consent of the adjoining owner. Any such extension of the party wall shall be noted on title by way of appropriate easement or Section 88B instrument.

(Reason: To ensure the protection and structural integrity of adjoining

properties, and that common law property rights are recognised) Geotechnical Report C8. A report prepared by an appropriately qualified Geotechnical Engineer certifying that

the existing rock formations and substrate on the site is capable of: a) withstanding the proposed loads to be imposed; b) withstanding the extent of the proposed excavation, including any

recommendations for shoring works that may be required to ensure the stability of the excavation;

c) providing protection and support of adjoining properties; and d) the provision of appropriate subsoil drainage during and upon completion of

construction works must be submitted for approval by the Certifying Authority prior to the issue of any Construction Certificate. Recommendations made in the certified report must be complied with at all times.

Building plans and specifications submitted for approval with any construction

certificate application must comply with (a), (b), (c) and (d) above and the certified report, including any recommendations made in the said certified report.

The Certifying Authority must ensure that the building plans and specifications

submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

(Reason: To ensure the structural integrity of the subject site and adjoining sites during the excavation process)

ATTACHMENT TO IPP07 - 03/02/2016 Page 44

Page 45: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 10 of 52 Sediment Control C9. Where construction or excavation activity requires the disturbance of the soil surface

or existing vegetation, erosion and sediment control techniques, as a minimum, are to be in accordance with the publication Managing Urban Stormwater: Soils & Construction (4th edition, Landcom, 2004) commonly referred to as the “Blue Book” or a suitable and effective alternative method. A Sediment Control Plan must be prepared and submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate and prior to any works commencing. The Sediment Control Plan must be consistent with the Blue Book and disclose:

a) All details of drainage to protect and drain the site during the construction

processes; b) All sediment control devices, barriers and the like; c) Sedimentation tanks, ponds or the like; d) Covering materials and methods; and e) A schedule and programme of the sequence of the sediment and erosion

control works or devices to be installed and maintained. f) Methods for the temporary and controlled disposal of stormwater during

construction.

All works must be undertaken in accordance with the approved Sediment Control plan. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

(Reason: To protect the environment from the effects of sedimentation and

erosion from development sites) Waste Management Plan C10. A Waste Management Plan is to be submitted for approval by the Certifying Authority

prior to the issue of any Construction Certificate. The plan must include, but not be limited to:

a) The estimated volume of waste and method of disposal for the construction

and operation phases of the development; b) The design of the on-site waste storage and recycling area; and

ATTACHMENT TO IPP07 - 03/02/2016 Page 45

Page 46: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 11 of 52

c) Administrative arrangements for waste and recycling management during the construction process.

The approved Waste Management Plan must be complied with at all times in the carrying out of the development. (Reason: To encourage the minimisation of waste and recycling of building

waste) External Finishes and Materials C11. The external colours and finishes must be in accordance with the approved schedule

of finishes and materials. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

(Reason: To ensure quality built form of development)

Reflectivity Index of Glazing C12. The reflectivity index (expressed as a percentum of the reflected light falling upon any

surface) of external glazing for windows, walls or roof finishes of the proposed development is to be no greater than 20%. Plans and specifications which comply with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

Note: The reflectivity index of glazing elements can be obtained from glazing

manufacturers. Glass with mirrored or reflective foil finishes is unlikely to achieve compliance with this requirement.

(Reason: To ensure that excessive glare or reflectivity nuisance from glazing

does not occur as a result of the development) Roofing Materials - Reflectivity C13. Roofing materials must be factory pre-finished with low glare and reflectivity

properties to be compatible with the colours of neighbouring buildings. The selected roofing material must not cause a glare nuisance or excessive reflectivity to adjoining or nearby properties. Plans and specifications which comply with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

(Reason: To ensure that excessive glare or reflectivity nuisance from roofing

materials does not occur as a result of the development)

ATTACHMENT TO IPP07 - 03/02/2016 Page 46

Page 47: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 12 of 52 No External Service Ducts C14. Service ducts must be provided within the building to keep external walls free of

plumbing, drainage or any other utility installations. Plans and specifications which comply with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition. (Reason: To ensure quality built form of the development)

Work Zone C15. If a Work Zone is proposed, an application must be made to the North Sydney Local

Traffic Committee to install the ‘Work Zone’. A Work Zone permit is required to be issued by the Council prior to the issue of any Construction Certificate. Work Zones are provided specifically for the set down and pick up of materials and not for the parking of private vehicles associated with the site. Works Zones will generally not be approved where there is sufficient space on-site for the setting down and picking up of goods being taken to or from a construction site. If the Works Zone is approved by the Committee, the Applicant must obtain a written copy of the related resolution from the North Sydney Local Traffic Committee and submit a copy of this to the Certifying Authority to enable issue of the Construction Certificate.

Where approval of the ‘Work Zone’ is given by the Committee, the requirements of the Committee, including installation of the necessary ‘Work Zone’ signage and payment of any fees, must occur prior to commencement of any works on the site. Further, at the expiration of the Work Zone approval, the developer is required to remove the Work Zone signs and reinstate any previous signs, all at the developer's cost. The requirements imposed by the Committee on the Work Zone permit (or permits) must be complied with at all times.

(Reason: Amenity and convenience during construction)

Bicycle Storage and Parking C16. The bicycle storage areas within the basement levels must accommodate a minimum

of 22 bicycles. Additional bicycle storage areas must be provided within the ground floor retail tenancies as indicated on the plans that form part of Condition A1 of this consent. The bicycle storage lockers and bicycle rail shall be designed in accordance with the applicable Australian Standards. Plans and specifications which comply with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

(Reason: To promote and provide facilities for alternative forms of transport)

ATTACHMENT TO IPP07 - 03/02/2016 Page 47

Page 48: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 13 of 52 Staff Shower & Change Facilities (Mixed Use) C17. Shower and change facilities within the basement level of the building must be made

accessible without charge to staff who work in the building. Plans and specifications which comply with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

(Reason: To promote and provide facilities for alternative forms of transport)

Accessible parking spaces to be provided C18. A total of four (4) accessible parking spaces for residents and one (1) accessible space

for a visitor shall be provided as part of the total car-parking requirements. Consideration must be given to the means of access from the car-parking spaces to adjacent buildings, to other areas within the building and to footpath and roads. All details shall be prepared in consideration of, and construction completed in accordance with applicable Australian Standards to achieve compliance with the Disability Discrimination Act. Plans and specifications which comply with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate.

(Reason: To ensure equity of access and appropriate facilities are available for

people with disabilities in accordance with Federal legislation) Basement Car park to comply with relevant standards C19. The basement layout must comply with all requirements of Australian Standard

AS2890.1. Certification from a suitably qualified and practicing Civil Engineer that the basement design will comply with the requirements of the Australian Standard must be provided to the Certifying Authority for approval prior to issue of any Construction Certificate. The loading bay must accommodate a small rigid vehicle and must comply with the Australian Standard AS2890.2 Off-Street Parking for Commercial Vehicles. (Reason: To ensure the basement layout complies with relevant standards)

Required Infrastructure Works –Roads Act 1993 C20. Prior to issue of any Construction Certificate engineering design plans and

specifications must be prepared by a qualified civil design engineer. The plans and specifications must be to a detail suitable for construction issue purposes and must provide detail and specification for the following infrastructure works to be completed as part of the development. The responsibility for accuracy of the design fully rests with the designing engineer. All responsibility on implementation and supervision of works specified on design plans fully rests on designing engineer or whoever is chosen to be applicant’s engineering representative:

ATTACHMENT TO IPP07 - 03/02/2016 Page 48

Page 49: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 14 of 52

Road Works

a) Construction of a fully new replacement concrete footpath is required across the entire site frontage in Miller Street. A longitudinal section is required along the footpath property boundary at a scale of 1:50 extending 5m past the property boundary line. The footpath pavement must be placed on a single straight grade of 3.0% falling to the top of kerb. The footpath pavement must be constructed for the full width using the construction required as specified in Public Domain Style Manual and Design Codes, so that it is uniform without showing signs of dipping or rising particularly at entrances.

b) Full width full property frontage Road Surface Reconstruction (if damaged during construction process) in Miller Lane.

c) construction of a new replacement kerb and gutter is required across the entire

site frontage in Miller Street. A longitudinal section is required along the gutter line (existing and proposed levels), at a scale of 1:50 extending 5m past the property boundary line.

d) cross sections at a scale of 1:50 along the centre-line of each access point to

the building must be provided and are to show the calculated clearance to the underside of any overhead structure. All the entry points are to comply with the Building Code of Australia (BCA), including disability requirements. The Council approved footpath levels must be accommodated at the building entry points.

Plans and specifications which comply with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. Certifying Authorities must not issue a Construction Certificate without the formal written approval of Council (as Roads Authority) under the Roads Act 1993.

The required plans and specifications are to be designed in accordance with North Sydney Council’s current documents Infrastructure Specification for Road Works, Drainage and Miscellaneous Works and Performance Guide for Engineering Design and Construction. The drawings must detail existing utility services and trees affected by the works, erosion control requirements and traffic management requirements during the course of works. A detailed survey must be undertaken as required. Traffic management is to be certified on the drawings as being in accordance with the documents SAA HB81.1 – 1996 – Field Guide for Traffic Control at Works on Roads – Part 1 and RMS Traffic Control at Work Sites (1998). Construction of the works must proceed only in accordance with any conditions attached to the Council Roads Act 1993 approval.

ATTACHMENT TO IPP07 - 03/02/2016 Page 49

Page 50: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 15 of 52

Note: A minimum of 21 days will be required for Council to assess Roads Act submissions. Early submission is recommended to avoid any delays in obtaining a Construction Certificate. A fee to cover cost of assessment (set out in Council’s adopted fees and charges) is payable and Council will withhold any consent and approved plans until full payment of the correct fees. Plans and specifications must be marked to the attention of Council’s Development Engineers. In addition, a copy of this condition must be provided, together with a covering letter stating the full address of the property and the accompanying DA number.

(Reason: To ensure infrastructure works are designed and constructed to appropriate standards and requirements of the Roads Act 1993)

Obtain Driveway Crossing Permit

C21. Prior to the issue of the Construction Certificate, North Sydney Council must issue the applicant with a driveway crossing and road infrastructure works permit to suit the approved off-street parking facilities. To obtain the permit, an application must be made to Council on a ‘Vehicular Access Application’ form with payment of the adopted assessment/inspection fees. Council will require civil design construction drawings and certification from the applicant’s Civil Engineer to verify design details and enable permit issue. The responsibility for accuracy of the design fully rests with the designing engineer. All responsibility on implementation and supervision of works specified on design plans fully rests on designing engineer or whoever is chosen to be applicant’s engineering representative. The civil design drawings shall detail the following infrastructure construction requirements of Council in relation to the consent:

a) The proposed vehicular access ways must comply with AS 2890.1 and Council’s current Vehicular Access Application Guidelines and Specification (gutter bridges not permitted) to ensure that a B85 vehicle will not scrape/strike the surface of the carriageway, layback, vehicular crossing or parking floor.

b) The vehicular access way must be built from standard interlocking concrete pavers, as specified in Public Domain Style Manual and Design Codes and designed to comply with AS 2890.1 to ensure that a B85 vehicle will not scrape/strike the surface of the carriageway, layback, vehicular crossing or garage floor.

c) The width of the vehicular crossing must be 6.0m (continuous layback with surrounding laybacks).

d) The property boundary line level must be set no more than 100 mm above the existing gutter levels.

e) The gutter invert levels must match the existing levels and shall not be altered unless agreed to by Council.

f) Alignment levels at the property boundary line have an important impact on the proposed levels for new driveway. No work must not start until first obtaining boundary alignment levels from Council. Council has the authority to remove any unauthorized works at the cost of the property owner.

g) The Certifying Authority must ensure that the internal property levels at boundary matches councils required levels.

ATTACHMENT TO IPP07 - 03/02/2016 Page 50

Page 51: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 16 of 52

h) All inspection openings, utility services must be adjusted to match the proposed driveway levels and location.

i) The design detail has to be provided with vehicular access application and must include sections along centre-line and extremities of the crossing at a scale of 1:25. Sections are to be taken from the centre of the roadway through to the parking area itself and shall include all changes of grade and levels, both existing and proposed.

j) A longitudinal section along the boundary line at a scale of 1:50 is required and shall include all changes of grade and levels, both existing and proposed.

k) The sections must show the calculated clearance to the underside of any overhead structure.

l) All details of internal ramps between parking levels. m) A swept path analysis is required demonstrating that an 85th percentile vehicle

can maneuver in and out of the garage spaces in accordance with AS 2890.1 2004 "Off Street Parking".

n) Pipelines within the footpath area must be hot dipped galvanized rectangular steel hollow section with a minimum wall thickness of 4.0 millimetres and a section height of 100 millimetres.

All driveway and infrastructure works on the road reserve must proceed in accordance with the terms of the permit issued by Council. Inspections by Council will be required as specified on the permit. The Certifying Authority issuing the Construction Certificate must ensure that the permit issued by Council is obtained prior to its issue, is referenced on and accompanies the Construction Certificate issued.

(Reason: To facilitate appropriate vehicular access to private sites, without disruption to pedestrian and vehicular traffic)

Stormwater Management and Disposal Design Plan – Construct. Issue

C22. Prior to issue of the Construction Certificate, the applicant shall have a site drainage management plan prepared by a qualified drainage design engineer. The site drainage management plan must detail the following requirements of North Sydney Council:

a) Compliance with BCA drainage requirements, Councils Engineering Performance guide and current Australian Standards and guidelines, such as AS/NZ3500.3.2 1998, National Plumbing and Drainage Code.

b) Stormwater runoff and subsoil drainage generated by the approved dwellings must be conveyed in a controlled manner via On-site-detention system by gravity to Council’s kerb in Miller Street.

c) All redundant stormwater pipelines within the footpath area shall be removed and the footpath and kerb reinstated.

d) Pipelines within the footpath area shall be hot dipped galvanised steel rectangular hollow section with a minimum wall thickness of 4.0 millimetres and a section height of 100 millimetres.

e) All sub-soil seepage drainage shall be discharged via a suitable silt arrester pit, directly to Council’s nearest stormwater drainage line. Details of all plans certified as being adequate for their intended purpose and complaint with the provisions of AS3500.3.2 by an appropriately qualified and practising civil

ATTACHMENT TO IPP07 - 03/02/2016 Page 51

Page 52: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 17 of 52

engineer, shall be submitted with the application for a Construction Certificate.

f) The design and installation of the Rainwater Tanks shall comply with Basix and Sydney Water requirements. Overflow from tank shall be connected by gravity to the stormwater disposal system.

g) Provide subsoil drainage to all necessary areas with pump out facilities as required.

Details demonstrating compliance are to be submitted with the Construction Certificate.

The Certifying Authority issuing the Construction Certificate must ensure that the approved drainage plan and specifications, satisfying the requirements of this condition, is referenced on and accompanies the Construction Certificate.

(Reason: To ensure controlled stormwater management and disposal without nuisance)

On-Site Stormwater Detention

C23. On site detention must be provided to ensure that the maximum discharge from the site is not exceeded discharge which would occur during a 1 in 5 year storm of 1 hour duration for the existing site conditions. All other stormwater run-off from the site for all storms up to the 1 in 100 year storm is to be retained on the site for gradual release to the kerb and gutter or drainage system as required by Director of Assets and Infrastructure Services. Provision is to be made for satisfactory overland flow should a storm in excess of the above parameters occur.

Determination of the require cumulative storage must be calculated by the mass curve technique as detailed in Technical Note 1, Chapter 14 of the Australian Rainfall and Runoff Volume 1, 1987 Edition.

Engineering calculations, design and certification complying with this condition must be provided by an appropriately qualified and practicing Civil Engineer and submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate.

(Reason: To ensure appropriate provision is made for the disposal and

management of stormwater generated by the development, and to ensure that public infrastructure in Council’s care and control is not overloaded)

Pump-Out System Design for Stormwater Disposal C24. The design of the pump-out system for stormwater disposal will be permitted for

drainage of basement areas only, and must be designed in accordance with the following criteria: -

ATTACHMENT TO IPP07 - 03/02/2016 Page 52

Page 53: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 18 of 52

a) The pump system shall consist of two pumps, connected in parallel, with each pump being capable of emptying the holding tank at the rate equal to the rate of inflow for the one-hour duration storm. The holding tank shall be capable of holding one hour’s runoff from a one-hour duration storm of the 1 in 20 year storm;

b) The pump system shall be regularly maintained and serviced, every six (6)

months; and c) Any drainage disposal to the street gutter from a pump system, must have a

stilling sump provided at the property line, connected to the street gutter by a suitable gravity line.

Engineering details demonstrating compliance with these criteria, and certified by an appropriately qualified and practising civil engineer shall be provided to the Certifying Authority for approval prior to the issue of any Construction Certificate.

(Reason: To ensure adequate provision is made for the discharge of sub-surface

stormwater from the excavated parts of the site) Bond for Damage and Completion of Infrastructure Works – Stormwater, Kerb and Gutter, Footpaths, Vehicular Crossing and Road Pavement C25. Prior to the issue of any Construction Certificate, security deposit or bank guarantee

must be provided to Council to the sum of $78,500.00 to be held by Council for the payment of cost for any/all of the following:

a) making good any damage caused to any property of the Council as a consequence of the doing of anything to which this consent relates,

b) completing any public work (such as road work, kerbing and guttering, footway construction, stormwater drainage and environmental controls) required in connection with this consent

c) remedying any defects in any such public work that arise within 6 months after the work is completed.

The security in accordance with the schedule contained later in these conditions and must be provided by way of a deposit with the Council; or a guarantee satisfactory to Council (such as a satisfactory bank guarantee).

The security will be refundable following the expiration of 6 months from the issue of any final Occupation Certificate or completion of public work required to be completed (whichever is the latest) but only upon inspection and release by Council’s Engineers. Council shall have full authority to make use of the bond for such restoration works as deemed necessary by Council in circumstances including the following: -

• where the damage constitutes a hazard in which case Council may make use of the security immediately;

• the applicant has not repaired or commenced repairing damage within 48 hours of the issue by Council in writing of instructions to undertake such repairs or works;

ATTACHMENT TO IPP07 - 03/02/2016 Page 53

Page 54: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 19 of 52

• works in the public road associated with the development are to an unacceptable quality; and

• the Certifying Authority must ensure that security is provided to North Sydney Council prior to issue of any Construction Certificate.

(Reason: To ensure appropriate security for works on public land and an appropriate quality for new public infrastructure)

Footpath, Entries and Fire Exit Details (Mixed Use) C26. Footpaths, entries and exits and fire exits for the development must be designed by an

appropriately qualified and practising Civil Engineer and submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The design must include (but is not limited to) the following: -

a) cross section along the centre-line of each access point to the building

including fire exits at a scale of 1:50 to be taken from the centre of the road and shall include all changes of grade both existing and proposed;

b) the sections must show all relevant levels and grades (both existing and

proposed) including those levels stipulated as boundary levels; c) the sections must show the calculated clearance to the underside of any

overhead structure; d) a longitudinal section along the boundary line showing how it is intended to

match the internal levels of the building with the boundary footpath levels. The footpath must be designed (at a single straight grade of 3% falling to top of kerb) so that it is smooth without showing signs of dipping or rising particularly at entrances; and

e) A longitudinal section along the gutter and kerb line extending 5 metres past

property lines showing transitions.

f) Awnings edges, parallel to the kerb line must not exceed edges of existing awnings in the same city block or if no other neighbouring awnings to compare, the edges of proposed awning must be offset at least 600 mm from the kerb line.

Details, plans and specifications complying with this condition are to be certified as complying with the Building Code of Australia (BCA) and Council’s standard footpath specifications, and the certification, details, plans and specifications must be provided to the Certifying Authority for approval prior to the issue of any Construction Certificate. Written concurrence confirming there will be no change to existing boundary and footpath levels is to be provided to the Certifier and North Sydney Council, prior to issue of any Construction Certificate.

(Reason: To facilitate suitable pedestrian and disabled access to private sites,

and to ensure that internal levels reflect footpath boundary levels)

ATTACHMENT TO IPP07 - 03/02/2016 Page 54

Page 55: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 20 of 52 Tree Bond for Public Trees C27. Prior to the issue of any construction certificate, security in the sum of $3,000.00 must

be provided to Council for the protection of trees in public places, including the making good of any damage caused to such trees. The security is to be provided in accordance with the Schedule below. The security must be provided by way of:

a deposit with the Council; or

a guarantee satisfactory to Council (such as a satisfactory bank guarantee).

The security will be refundable following the expiration of 6 months from the issue of any final Occupation Certificate but only upon inspection and release by Council's Landscape Development Officer.

If any tree is removed or damaged Council may deduct from this security the reasonable cost of replacement with a tree of the same species and to a similar stage of growth it would have attained at the completion of the work.

In the case of any tree, which cannot be replaced with a similar specimen, the security for that tree will be forfeited to Council and used to provide replacement street plantings.

SCHEDULE 2 x Ficus Hillii (Hills Fig) located on Council’s footpath

(Reason: Protection of existing environment public infrastructure, community assets and significant trees)

Garbage and Recycling Facilities C28. The following requirements must be met for the storage of garbage bins and recycling

containers:

a) all internal walls of the storage area must be rendered to a smooth surface, coved at the floor/wall intersection, graded and appropriately drained with a tap in close proximity to facilitate cleaning;

b) provision for the separation and storage in appropriate categories of material suitable for recycling;

Plans and specifications which comply with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate.

The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

ATTACHMENT TO IPP07 - 03/02/2016 Page 55

Page 56: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 21 of 52

Note: The applicant may wish to discuss bin storage requirements and location with Council’s Environmental Services prior to finalisation of the required detail, and a copy of Council’s Waste Handling Guide should be obtained for reference purposes before the design is finalised.

(Reason: To ensure the provision of appropriate waste facilities for residents and

protect community health, and to ensure efficient collection of waste by collection contractors)

Asbestos Material Survey C29. A report must be prepared by a suitably qualified person in relation to the existing

building fabric to be demolished and/or disturbed identifying the presence or otherwise of asbestos contamination and, if asbestos contamination is present, making recommendations as to the work required to safely address the contamination. Any demolition works or other works identified in the report as having to be carried out must be carried out in accordance with the recommendations of the report and the following: a) the removal of asbestos must be undertaken by a WorkCover licensed

contractor; b) all removal must be in strict accordance with the requirements of the

WorkCover Authority in relation to the removal, handling and disposal of material containing asbestos and any Work Safe Australia requirements.

c) during the removal of any asbestos a sign stating “DANGER ASBESTOS REMOVAL IN PROGRESS” must be erected in a visible position at the boundary of the site; and

d) Waste disposal receipts must be provided to the Certifying Authority as proof of correct disposal of asbestos laden waste.

The report must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the report, and other plans, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

(Reason: To ensure the long term health of workers on site and occupants of the building is not put at risk unnecessarily)

Location of Plant C30. All plant and equipment (including but not limited to air conditioning equipment) is to

be located within the basement of the building and is not to be located on balconies or the roof. Plans and specifications complying with this condition must be submitted to the Certifying Authority for Approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

ATTACHMENT TO IPP07 - 03/02/2016 Page 56

Page 57: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 22 of 52

(Reason: Minimise impact on surrounding properties, improved visual appearance and amenity for locality)

Noise from Plant and Equipment C31. The use of all plant and equipment installed on the premises must not:

(a) Contribute an LAeq(15min) which will cause the total LAeq(15min) from all plant and equipment operating contemporaneously on the site or in the strata scheme or in the mixed strata schemes to exceed the RBL by more than 5dB when measured at the boundary of any affected receiver . The modifying factor adjustments in Section 4 of the EPA Industrial Noise Policy shall be applied.

(b) Cause “offensive noise” as defined in the Protection of the Environment Operations Act 1997.

“affected receiver” includes residential premises (including any lot in the strata scheme or another strata scheme), premises for short-term accommodation, schools, hospitals, places of worship, commercial premises and parks and such other affected receiver as may be notified by the Council in writing. “boundary” includes any window or elevated window of an affected receiver. Terms in this condition have the same meaning as in the Noise Guide for Local Government and the Industrial Noise Policy published by the NSW Environment Protection Authority. (Reason: To maintain an appropriate level of amenity for adjoining land uses)

Vibration from Plant and Equipment C32. The use of all plant and equipment to be installed on the premises must comply with

the vibration limits specified in “Assessing Vibration: a technical guideline” issued by the NSW Environment Protection Authority, at the boundary of any affected receiver. A certificate from an appropriately qualified acoustical consultant eligible for membership of the Association of Australian Acoustic Consultants must be submitted to the Certifying Authority, certifying that all plant and equipment on the site, together with the proposed plant and equipment, operating contemporaneously will comply with the requirements of this condition. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition. “affected receiver” includes residential premises (including any lot in the strata scheme or another strata scheme), premises for short-term accommodation, schools,

ATTACHMENT TO IPP07 - 03/02/2016 Page 57

Page 58: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 23 of 52

hospitals, places of worship and commercial premises and such other affected receiver as may be notified by the Council in writing. “boundary” includes any window or elevated window of an affected residence. “contemporaneously” means existing at or occurring in the same period of time (Macquarie Dictionary 3rd rev. ed. 2004).

(Reason: To maintain an appropriate level of amenity for adjoining land uses)

Air Conditioners in Residential Premises C33. The use of any air conditioner installed on the premises must comply with the

requirements of the Protection of the Environment Operations (Noise Control) Regulations 2008 and State Environmental Planning Policy (Infrastructure) 2007 and must not:

(a) emit a noise that is audible within a habitable room in any affected residence (regardless of whether any door or window to that room is open);

(i) before 8.00am and after 10.00pm on any Saturday, Sunday or Public Holiday; or

(ii) before 7.00am or after 10.00pm on any other day

(a) cause an LAeq(15min) which exceeds the RBL background noise level by more than 5dB when measured at the boundary of any affected residence. The modifying factor adjustments in Section 4 of the EPA Industrial Noise Policy will be applied.

“affected residence” includes residential premises (including any lot in the strata scheme or another strata scheme), premises for short-term accommodation and hospitals.

“boundary” includes any window or elevated window of an affected residence.

Terms in this condition have the same meaning as in the Noise Guide for Local Government and the Industrial Noise Policy published by the NSW Environment Protection Authority. (Reason: To maintain residential amenity)

Provision of Accessible Paths of Travel C34. The building must be designed and constructed to provide access and facilities in

accordance with the Building Code of Australia and Disability (Access to Premises – Buildings) Standards 2010. Plans and specifications complying with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

ATTACHMENT TO IPP07 - 03/02/2016 Page 58

Page 59: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 24 of 52

Notes: 1. If, in complying with this condition, amendments to the development are

required, the design changes must be submitted for the approval of Council prior to a Construction Certificate being issued. Approval of a modification application may be required.

2. It is not within Council’s power to set aside National legislation which requires the upgrade of buildings to meet modern access standards. Such decisions remain the jurisdiction of the Building Professionals Board Access Advisory Committee who may grant an exemption in certain exceptional circumstances.

3. Information on making an application for an “unjustifiable hardship exemption” under the accessibility standards can be found in the website of the NSW Building Professional Boards at http://www.bpb.nsw.gov.au/page/premises-standards

(Reason: To ensure the provision of equitable and dignified access for all people

in accordance with disability discrimination legislation and relevant Australian Standards)

Underground Electricity and Other Services C35. All electricity and telecommunication provision to the site is to be designed in

conjunction with Energy Australia and any other relevant authority so that it can be easily connected underground when the street supply is relocated underground. Plans and specifications complying with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

(Reason: To provide infrastructure that facilitates the future improvement of the

streetscape by relocation of overhead lines below ground) Adaptable Housing C36. Apartments L108, L208 and L308 are to be designed with accessible features for

disabled persons, and must incorporate level entries and wider doorways and corridors, slip resistant surfaces, reachable power points, disabled toilet, and lever door handles and taps. These features are to be designed generally in accordance with the relevant Australian Standard 4299 - 1995. Plans and specifications complying with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

(Reason: To ensure equity of access and availability of accommodation in the

future for an ageing population)

ATTACHMENT TO IPP07 - 03/02/2016 Page 59

Page 60: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 25 of 52 Section 94 Contributions C37. A monetary contribution pursuant to the provisions of Section 94 of the

Environmental Planning and Assessment Act 1979, in accordance with the North Sydney Council Section 94 Contribution Plan for the public amenities/ services detailed in column A below and, for the amount detailed in column B below, must be paid to Council.

Administration $2,199.39 Community Centres $10,825.47 Childcare Facilities $2,809.47 Library and Local Studies Acquisitions $2,002.26 Library Premises and Equipment $6,204.89 Multi Purpose Indoor Sports Facility $1,630.55 Olympic Pool $5,310.72 Open Space Acquisitions $73,487.16 Open Space Increased Capacity $145,664.23 Public Domain Improvements $4,270.06 Traffic Improvements $7,138.49 Total $261,542.69

The contribution MUST BE paid prior issue of any Construction Certificate. The above amount, will be adjusted for inflation by reference to the Consumer Price (All Ordinaries) Index applicable at the time of the payment of the contribution. A copy of the North Sydney Section 94 Contribution Plan can be viewed at North Sydney Council’s Customer Service Centre, 200 Miller Street, North Sydney or downloaded via Council’s website at www.northsydney.nsw.gov.au

(Reason: To retain a level of service for the existing population and to provide the same level of service to the population resulting from new development)

Security Deposit/ Guarantee Schedule

C38. All fees and security deposits/ guarantees in accordance with the schedule below must be provided to Council prior to the issue of any Construction Certificate:

Security deposit/ guarantee Amount ($) Street Tree Bond (on Council Property) $1,500.00 Road Carriageway Surface Damage Bond $16,500.00 Engineering Construction Bond $62,000.00 TOTAL BONDS $80,000.00

(Reason: Compliance with the development consent)

ATTACHMENT TO IPP07 - 03/02/2016 Page 60

Page 61: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 26 of 52 BASIX Certificate C39. Under clause 97A(3) of the Environmental Planning & Assessment Regulation 2000,

it is a condition of this development consent that all the commitments listed in BASIX Certificate No. (A640776) dated July 2015 for the development are fulfilled. Plans and specifications complying with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

(Reason: To ensure the proposed development will meet the Government’s requirements for sustainability and statutory requirements)

Remediation

C40. Prior to the release of the Construction Certificate the site must be remediated in accordance with:

(a) an approved Remedial Action Plan; and (b) North Sydney Development Control Plan 2013 – Section 14 – Contamination

and Hazardous Building Materials; and (c) state Environmental Planning Policy No. 55 – Remediation of Land; and, (d) the guidelines in force under the Contaminated Land Management Act.

Within thirty (30) days after the completion of the remediation works, and prior to the issue of any construction certificate, a notice of completion, including validation and/or monitoring report is to be provided to Council. This notice must be consistent with State Environmental Planning Policy No. 55 – Remediation of Land.

Prior to the issue of any Construction Certificate, the validation and/or monitoring report is to be independently audited and a Site Audit Statement issued. A copy of the Site Audit Statement is to be provided to the Certifying Authority and Council (if Council is not the Certifying Authority). The audit is to be carried out by an independent auditor accredited by the Environment Protection Authority. Any conditions recorded on the Site Audit Statement must be complied with at all times.

(Reason: To ensure the land is suitable for its intended purpose) D. Prior to the Commencement of any Works (and continuing where indicated) Notice of Proposed Work (Remediation Work) D1. Notice of proposed work must be given to the Council in accordance with Clause 16

of State Environmental Planning Policy No 55—Remediation of Land. The following additional information must be submitted with the notice to the Council:

ATTACHMENT TO IPP07 - 03/02/2016 Page 61

Page 62: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 27 of 52

a) Copies of any preliminary investigation, detailed investigation and remediation action plan for the site; and

b) Contact details for the remediation contractor and any other party responsible for ensuring compliance of remediation work with regulatory requirements.

Note: 30 days notice is required for any remediation work. In the case of work required to be carried out immediately under the terms of a remediation order a minimum of 2 days notice is required)

(Reason: Protection of the environment, SEPP 55 compliance)

Public Liability Insurance – Works on Public Land D2. Any person or contractor undertaking works on public land must take out Public Risk

Insurance with a minimum cover of $20 million in relation to the occupation of public land and the undertaking of approved works within Council’s road reserve or public land, as approved by this consent. The Policy is to note, and provide protection/full indemnification for North Sydney Council, as an interested party. A copy of the Policy must be submitted to Council prior to commencement of any works. The Policy must be valid for the entire period that the works are being undertaken.

(Note: Applications for hoarding permits, vehicular crossings etc will require

evidence of insurance upon lodgement of the application.)

(Reason: To ensure the community is protected from the cost of any claim for damages arising from works on public land)

Notification of New Addresses D3. Prior to the commencement of any building works, an application must be made and

written confirmation received from North Sydney Council of the allocated street address (house number) and/ or unit numbers of the completed project. To assist Council, a plan for unit numbering should be submitted for concurrence. These details will be recorded in Council records and must be displayed at the property in accordance with the provisions of the applicable Australian Standard relating to rural and urban addressing. A copy of the allocation confirmation must be submitted to the Certifying Authority with the application for a Construction Certificate. (Reason: To ensure that Council records are accurate, and that house numbering

complies with the requirements of Council’s House Numbering Policy. Proper house numbering also assists emergency services in readily locating properties)

ATTACHMENT TO IPP07 - 03/02/2016 Page 62

Page 63: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 28 of 52 Sydney Water Approvals D4. Prior to the commencement of any works, the approved plans must be submitted to a

Sydney Water Quick Check agent or Customer Care Centre to determine whether the development application will affect Sydney Water’s sewer and water mains, stormwater drains and/or easements, and if further requirements need to be met. The approved plans will be appropriately stamped. The Certifying Authority must ensure that a Quick Check agent/Sydney Water has appropriately stamped the plans before the commencement of building works. Note: For Quick Check agent details please refer to “Your Business” section of Sydney Water’s web site at www.sydneywater.com.au then see Building and Renovating under the heading Building and Developing, or telephone 13 20 92. (Reason: To ensure compliance with Sydney Water requirements)

Asbestos Material Survey

D5. Prior to the commencement of any works, a report must be prepared by a suitably

qualified person in relation to the existing building fabric to be demolished and/or disturbed identifying the presence or otherwise of asbestos contamination and, if asbestos contamination is present, making recommendations as to the work required to safely address the contamination. Any demolition works or other works identified in the report as having to be carried out must be carried out in accordance with the recommendations of the report and the following: a) the removal of asbestos must be undertaken by a WorkCover licensed

contractor; b) all removal must be in strict accordance with the requirements of the

WorkCover Authority in relation to the removal, handling and disposal of material containing asbestos and any Work Safe Australia requirements.

c) during the removal of any asbestos a sign stating “DANGER ASBESTOS REMOVAL IN PROGRESS” must be erected in a visible position at the boundary of the site; and

d) Waste disposal receipts must be provided to the Certifying Authority as proof of correct disposal of asbestos laden waste.

The report must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the report, and other plans, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition. (Reason: To ensure the long term health of workers on site and occupants of the

building is not put at risk unnecessarily)

ATTACHMENT TO IPP07 - 03/02/2016 Page 63

Page 64: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 29 of 52 Commencement of Works Notice

D6. Building work, demolition or excavation in accordance with this development consent

must not be commenced until the developer has given at least 2 days notice to North Sydney Council of the person’s intention to commence building work, demolition or excavation in accordance with this development consent.

(Reason: To ensure appropriate safeguarding measures are in place prior to the

commencement of any building work, demolition or excavation) E. During Demolition and Building Work

Ausgrid Requirements

E1. Adequate clearances between the development and the adjacent existing overhead electricity mains in Miller St are to be maintained in accordance with Section 3.11.2 of AS 7000. In particular, action should be taken to ensure compliance with the clearance requirements relating to openable windows, balconies and awnings. In addition, the clearance requirements in the WorkCover NSW Code of Practice - “Work Near Overhead Power Lines” 2006 - should be complied with during construction works. In both cases, the relevant mains are to be regarded as “bare active” mains with a voltage less than 1000V.

The future supply of electricity to the proposed development will be dependant upon the proposed maximum demand of the development and the existing electrical loading of the surrounding area, and should not be assumed to be available until confirmed by Ausgrid. The developer is advised to submit a Connection Application for the development as soon as their maximum demand has been determined.

(Reason: To ensure compliance with Ausgrid requirements)

Cigarette Butt Receptacle E2. A cigarette butt receptacle is to be provided on the site for the duration of

excavation/demolition/construction process, for convenient use of site workers.

(Reason: To ensure adequate provision is made for builders’ waste) Parking Restrictions

E3. Existing public parking provisions in the vicinity of the site must be maintained at all

times during works. The placement of any barriers, traffic cones, obstructions or other device in the road shoulder or kerbside lane is prohibited without the prior written consent of Council. Changes to existing public parking facilities/restrictions must be approved by the North Sydney Local Traffic Committee. The Developer will be held responsible for any breaches of this condition, and will incur any fines associated with enforcement by Council regulatory officers. (Reason: To ensure that existing kerbside parking provisions are not

compromised during works)

ATTACHMENT TO IPP07 - 03/02/2016 Page 64

Page 65: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 30 of 52 Road Reserve Safety E4. All public footways and roadways fronting and adjacent to the site must be maintained

in a safe condition at all times during the course of the development works, with no obstructions caused to the said footways and roadways. Construction materials and plant must not be stored in the road reserve without approval of Council. A safe pedestrian circulation route and a pavement/route free of trip hazards must be maintained at all times on or adjacent to any public access ways fronting the construction site.

Where public infrastructure is damaged, repair works must be carried out in when and as directed by Council officers (at full Developer cost). Where pedestrian circulation is diverted on to the roadway or verge areas, clear directional signage and protective barricades must be installed in accordance with AS1742-3 (1996) “Traffic Control Devices for Work on Roads”. If pedestrian circulation is not satisfactorily maintained across the site frontage, and action is not taken promptly to rectify the defects, Council may undertake proceedings to stop work.

(Reason: Public Safety)

Service adjustments

E5. Where required, the adjustment or inclusion of any new utility service facilities must

be carried out by the person acting on the consent and in accordance with the requirements of the relevant utility authority. These works shall be at no cost to Council. It is the Applicants full responsibility to make contact with the relevant utility authorities to ascertain the impacts of the proposal upon utility services at the appropriate stage of the development (including water, phone, gas and the like). Council accepts no responsibility whatsoever for any matter arising from its approval of this application involving any influence upon utility services provided by another authority. (Reason: To ensure the service requirements are met)

Temporary Disposal of Stormwater Runoff E6. During construction, stormwater runoff must be disposed in a controlled manner that

is compatible with the erosion and sediment controls on the site. Immediately upon completion of any impervious areas on the site (including roofs, driveways, paving) and where the final drainage system is incomplete, the necessary temporary drainage systems must be installed to reasonably manage and control runoff as far as the approved point of stormwater discharge. Such ongoing measures must be to the satisfaction of the Certifying Authority.

(Reason: Stormwater control during construction)

ATTACHMENT TO IPP07 - 03/02/2016 Page 65

Page 66: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 31 of 52 Council Inspection of Public Infrastructure Works

E7. During the works on public infrastructure reverting to Councils care and control,

Councils development engineer must undertake inspections of the works at the following hold points: -

a) Vehicular access; and associated road civil works. All works must proceed in accordance with Roads Act 1993 approvals or other permits relating to roads issued by Council. A minimum of 48 hours notice must be given to Council to book an inspection. Work must not proceed until the works or activity covered by the inspection is approved. (Reason: To ensure quality of construction joints and connections in the drainage

system)

Progress Survey

E8. In order to ensure compliance with approved plans, a Survey Certificate, to Australian Height Datum, must be prepared by a Registered Surveyor as follows: -

a) at the completion of the first structural floor level indicating the level of that

floor and the relationship of the building to the boundaries; b) at the completed height of the building, prior to the placement of concrete

inform work, or the laying of roofing materials; and c) at completion, the relationship of the building, and any projections thereto, to

the boundaries. Progress certifications in response to points (a) through (c) must be provided to the Certifying Authority for approval at the time of carrying out relevant progress inspections. In the event that such survey information is not provided or reveals discrepancies between the approved plans and the proposed works, all works, save for works necessary to bring the development into compliance with the approved plans, must cease. Works may only continue upon notification by the Certifying Authority to the Applicant that survey information (included updated survey information following the carrying out of works to comply with the approved plans) complies with this condition.

(Reason: To ensure compliance with approved plans)

Dust Emission and Air Quality E9. The following must be complied with at all times:

(a) Materials must not be burnt on the site.

ATTACHMENT TO IPP07 - 03/02/2016 Page 66

Page 67: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 32 of 52

(b) Vehicles entering and leaving the site with soil or fill material must be covered.

(c) Dust suppression measures must be carried out to minimise wind-borne emissions in accordance with the NSW Department of Housing’s 1998 guidelines - Managing Urban Stormwater: Soils and Construction.

(d) Odour suppression measures must also be carried out where appropriate so as to prevent nuisance occurring at adjoining properties.

(Reason: To ensure residential amenity is maintained in the immediate vicinity)

Noise and Vibration

E10. The works must be undertaken in accordance with the “Interim Construction Noise Guideline” published by the NSW Environment Protection Authority, to ensure excessive levels of noise and vibration do not occur so as to minimise adverse effects experienced on any adjoining land.

(Reason: To ensure residential amenity is maintained in the immediate vicinity) No Work on Public Open Space E11. No work can be undertaken within adjoining public lands (ie. Parks, Reserves, Roads

etc) without the prior written consent of Council. In this regard the developer is to liaise with Council prior to the commencement of any design works or preparation of a Construction and Traffic Management Plan.

(Reason: Protection of existing public infrastructure and land and to ensure

public safety and proper management of public land) Developer's Cost of Work on Council Property E12. The developer must bear the cost of all works associated with the development that

occurs on Council’s property, including the restoration of damaged areas.

(Reason: To ensure the proper management of public land and funds) No Removal of Trees on Public Property E13. No trees on public property (footpaths, roads, reserves, etc.) unless specifically

approved by this consent shall be removed or damaged during construction including for the erection of any fences, hoardings or other temporary works.

(Reason: Protection of existing environmental infrastructure and community

assets)

ATTACHMENT TO IPP07 - 03/02/2016 Page 67

Page 68: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 33 of 52 Special Permits E14. Unless otherwise specifically approved in writing by Council, all works, processes,

storage of materials, loading and unloading associated with the development must occur entirely on the property. The developer, owner or builder may apply for specific permits available from Council’s Customer Service Centre for the undermentioned activities on Council’s property. In the event that a permit is granted by Council for the carrying out of works, processes, storage of materials, loading and unloading associated with the development on Council's property, the development must be carried out in accordance with the requirements of the permit. A minimum of forty-eight (48) hours notice is required for any permit: -

1) On-street mobile plant

Eg. cranes, concrete pumps, cherry-pickers, etc. - restrictions apply to the hours of operation, the area of operation, etc. Separate permits are required for each occasion and each piece of equipment. It is the developer's, owner’s and builder’s responsibilities to take whatever steps are necessary to ensure that the use of any equipment does not violate adjoining property owner’s rights.

(Reason: Proper management of public land)

2) Hoardings

Permits are required to erect Class A and Class B hoardings. If an ‘A’ Class hoarding is to alienate a section of Council’s property, that section will require a permit for the occupation of Council’s property.

(Reason: Proper management of public land) 3) Storage of building materials and building waste containers (skips) on

Council’s property

Permits to utilise Council property for the storage of building materials and building waste containers (skips) are required for each location. Failure to obtain the relevant permits will result in the building materials or building waste containers (skips) being impounded by Council with no additional notice being given. Storage of building materials and waste containers on open space reserves and parks is prohibited.

(Reason: Proper management of public land)

ATTACHMENT TO IPP07 - 03/02/2016 Page 68

Page 69: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 34 of 52

4) Kerbside restrictions, construction zones

Attention is drawn to the existing kerbside restrictions adjacent to the development. Should alteration of existing kerbside restrictions be required, or the provision of a construction zone, the appropriate application must be made and the fee paid to Council. Alternatives to such restrictions may require referral to Council’s Traffic Committee and may take considerable time to be resolved. An earlier application is suggested to avoid delays in construction programs.

(Reason: Proper management of public land) Construction Hours E15. Building construction and works must be restricted to within the hours of 7.00 am to

5.00 pm Monday to Friday and on Saturday to within the hours of 8.00 am to 1.00 pm inclusive, with no work on Sundays and Public Holidays.

Demolition and excavation works must be restricted to within the hours of 8.00 am to 5.00 pm Monday to Friday only. For the purposes of this condition:

a) “Building construction” means any physical activity on the site involved in the erection of a structure, cladding, external finish, formwork, fixture, fitting of service installation and the unloading of plant, machinery, materials or the like.

b) “Demolition works” means any physical activity to tear down or break up a structure (or part thereof) or surface, or the like, and includes the loading of demolition waste and the unloading of plant or machinery.

c) “Excavation work” means the use of any excavation machinery and the use of jackhammers, rock breakers, excavators, loaders, or the like, regardless of whether the activities disturb or alter the natural state of the existing ground stratum or are breaking up/removing materials from the site and includes the unloading of plant or machinery associated with excavation work.

All builders, excavators must display, on-site, their twenty-four (24) hour contact telephone number, which is to be clearly visible and legible from any public place adjoining the site.

(Reason: To ensure that works do not interfere with reasonable amenity expectations of residents and the community)

Out of Hours Work Permits E16. Where it is necessary for works to occur outside those hours allowed by these

conditions, an application may be made to Council's Customer Services Centre for a permit to carry out works outside of the approved hours. If a permit is issued the works approved must be carried out in accordance with any requirements specified in the permit. Permits will only be approved if public safety is at risk. Applications which seek a variation to construction hours solely to benefit the developer will require the lodgement and favourable determination of a modification application pursuant to the provisions of Section 96 of the Environmental Planning and

ATTACHMENT TO IPP07 - 03/02/2016 Page 69

Page 70: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 35 of 52

Assessment Act 1979.

Notes: 1) Failure to obtain a permit for work outside of the approved hours will result in

on the spot fines being issued, or Council pursuing any action required (including legal proceedings) to have the out of hours work cease, without prior warning.

2) Applications for out of hour’s works should be lodged with Council no later than seven (7) calendar days prior to the date of the intended works.

3) Examples of activities for which permits may be granted include: • the erection of awnings, • footpath, road and other infrastructure works which can not be

carried out for public convenience reasons within normal hours, • the erection and removal of hoardings and site cranes, and • craneage of materials which cannot be done for public convenience

reasons within normal working hours.

4) Examples of activities for which permits WILL NOT be granted include; • extended concrete pours • works which are solely to convenience the developer or client, and • catch up works required to maintain or catch up with a construction

schedule. 5) Further information on permits can be obtained from the Council website at

www.northsydney.nsw.gov.au.

(Reason: To ensure that works do not interfere with reasonable amenity expectations of residents and the community)

Installation and Maintenance of Sediment Control E17. Erosion and sediment controls must be installed and maintained at all times in

accordance with the Sediment and erosion control plan submitted and approved with the Construction Certificate. Erosion and sediment measures must be maintained in accordance with the publication Managing Urban Stormwater: Soils & Construction (4th edition, Landcom, 2004), commonly referred to as the “Blue Book” and can only be removed when development activities have been completed and the site fully stabilised.

(Reason: To protect the environment from the effects of sedimentation and

erosion from development sites)

ATTACHMENT TO IPP07 - 03/02/2016 Page 70

Page 71: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 36 of 52 Sediment and Erosion Control Signage E18. A durable sign must be erected during building works in a prominent location on site,

warning of penalties should appropriate erosion and sedimentation control devices not be maintained. A sign of the type referred to in this condition is available from Council.

(Reason: To protect the environment from the effects of sedimentation and

erosion from development sites) Remedial Action Plan (Contaminated Land) E19. The remediation work must be carried out in accordance with the Remedial Action

Plan approved under this consent and all relevant guidelines issued under the Contaminated Land Management Act.

(Reason: To ensure the proper management of contaminated land)

Site Amenities and Facilities E20. Where work involved in the erection and demolition of a building is being carried out,

amenities which satisfy applicable occupational health and safety and construction safety regulations, including any WorkCover Authority requirements, must be provided and maintained at all times. The type of work place determines the type of amenities required.

Further information and details can be obtained from the Internet at www.workcover.nsw.gov.au

(Reason: To ensure the health and safety of the community and workers on the

site)

Health and Safety E21. All work undertaken must satisfy applicable occupational health and safety and

construction safety regulations, including any WorkCover Authority requirements to prepare a health and safety plan. Site fencing must be installed sufficient to exclude the public from the site. Safety signs must be erected that warn the public to keep out of the site, and provide a contact telephone number for enquiries.

Further information and details regarding occupational health and safety requirements for construction sites can be obtained from the internet at www.workcover.nsw.gov.au

(Reason: To ensure the health and safety of the community and workers on the

site)

ATTACHMENT TO IPP07 - 03/02/2016 Page 71

Page 72: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 37 of 52 Prohibition on Use of Pavements E22. Building materials must not be placed on Council's footpaths, roadways, parks or

grass verges, (unless a permit is obtained from Council beforehand). A suitable sign to this effect must be erected adjacent to the street alignment.

(Reason: To ensure public safety and amenity on public land)

Plant & Equipment Kept Within Site E23. All plant and equipment used in the undertaking of the development/ works, including

concrete pumps, wagons, lifts, mobile cranes, hoardings etc, must be situated within the boundaries of the site (unless a permit is obtained from Council beforehand) and so placed that all concrete slurry, water, debris and the like must be discharged onto the building site, and is to be contained within the site boundaries.

Details of Council requirements for permits on public land for standing plant, hoardings, storage of materials and construction zones and the like are available on Council’s website at www.northsydney.nsw.gov.au. (Reason: To ensure public safety and amenity on public land)

Waste Disposal E24. All records demonstrating the lawful disposal of waste must be retained and kept

readily accessible for inspection by regulatory authorities such as North Sydney Council and the Environmental Protection Authority.

(Reason: To ensure the lawful disposal of construction and demolition waste)

Asbestos Removal E25. All demolition works involving the removal and disposal of asbestos cement must

only be undertaken by contractors who hold a current WorkCover Asbestos or “Demolition Licence” and a current WorkCover “Class 2 (Restricted) Asbestos Licence and removal must be carried out in accordance with National Occupational Health and Safety Commission. (Reason: To ensure works are carried out in accordance with relevant

WorkCover requirements) F. Prescribed Conditions imposed under EP&A Act and Regulations and other

relevant Legislation Building Code of Australia F1. All building work must be carried out in accordance with the provisions of the

Building Code of Australia.

(Reason: Prescribed - Statutory)

ATTACHMENT TO IPP07 - 03/02/2016 Page 72

Page 73: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 38 of 52 Home Building Act F2. 1) Building work that involves residential building work (within the meaning and

exemptions provided in the Home Building Act 1989) for which the Home Building Act 1989 requires there to be a contract of insurance under Part 6 of that Act must not be carried out unless the Principal Certifying Authority for the development to which the work relates has given North Sydney Council written notice of the contract of insurance being issued and of the following:

a) in the case of work for which a principal contractor is required to be

appointed:

i) the name and licence number of the principal contractor, and ii) the name of the insurer by which the work is insured under Part

6 of that Act, or

(b) in the case of work to be done by an owner-builder:

(i) the name of the owner-builder, and (ii) if the owner-builder is required to hold an owner-builder permit

under that Act, the number of the owner-builder permit.

2) If arrangements for doing residential building work are changed while the work is in progress such that the information submitted to Council in accordance with this conditions is out of date, work must cease and no further work may be carried out unless the Principal Certifying Authority for the development to which the work relates (not being the Council), has given the Council written notice of the updated information.

Note: A certificate purporting to be issued by an approved insurer under Part 6 of the Home Building Act 1989 that states that a person is the holder of an insurance policy issued for the purposes of that Part is, for the purposes of this clause, sufficient evidence that the person has complied with the requirements of that Part.

(Reason: Prescribed - Statutory)

Appointment of a Principal Certifying Authority (PCA) F3. Building work, demolition or excavation in accordance with the development consent

must not be commenced until the developer has appointed a Principal Certifying Authority for the building work in accordance with the provisions of the EP&A Act and its Regulations.

(Reason: Statutory; To ensure appropriate safeguarding measures are in place

prior to the commencement of any building work, demolition or excavation)

ATTACHMENT TO IPP07 - 03/02/2016 Page 73

Page 74: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 39 of 52 Construction Certificate F4. Building work, demolition or excavation in accordance with the development consent

must not be commenced until a Construction Certificate for the relevant part of the building work has been issued in accordance with the provisions of the EP&A Act and its Regulations.

(Reason: Statutory; To ensure appropriate safeguarding measures are in place

prior to the commencement of any building work, demolition or excavation)

Occupation Certificate F5. A person must not commence occupation or use of the whole or any part of a new

building (new building

includes an altered portion of, or an extension to, an existing building) unless an Occupation Certificate has been issued in relation to the building or part. Only the Principal Certifying Authority appointed for the building work can issue an Occupation Certificate.

(Reason: Statutory) Critical Stage Inspections F6. Building work must be inspected by the Principal Certifying Authority on the critical

stage occasions prescribed by the EP&A Act and its Regulations, and as directed by the appointed Principal Certifying Authority.

(Reason: Statutory)

Excavation/Demolition F7. 1) All excavations and backfilling associated with the erection or demolition of a

building must be executed safely and in accordance with appropriate professional standards.

2) All excavations associated with the erection or demolition of a building must

be properly guarded and protected to prevent them from being dangerous to life or property.

3) Demolition work must be undertaken in accordance with the provisions of

AS2601- Demolition of Structures.

(Reason: To ensure that work is undertaken in a professional and responsible manner and protect adjoining property and persons from potential damage)

ATTACHMENT TO IPP07 - 03/02/2016 Page 74

Page 75: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 40 of 52 Protection of Public Places F8. 1) A hoarding and site fencing must be erected between the work site and

adjoining public place.

2) If necessary, an awning is to be erected, sufficient to prevent any substance from, or in connection with, the work falling into the public place.

3) The work site must be kept lit between sunset and sunrise if it is likely to be

hazardous to persons in the public place.

4) Any such hoarding, fence or awning is to be removed when the work has been completed.

5) No access across public reserves or parks is permitted.

Note: Prior to the erection of any temporary fence or hoarding over property owned

or managed by Council, written approval must be obtained. Any application needs to be accompanied by plans indicating the type of hoarding and its layout. Fees are assessed and will form part of any approval given. These fees must be paid prior to the approval being given. Approval for hoardings will generally only be given in association with approved building works, maintenance or to ensure protection of the public. An application form for a Hoarding Permit can be downloaded from Council’s website.

(Reason: To ensure public safety and the proper management of public land)

Site Sign F9. 1) A sign must be erected in a prominent position on the site

a) stating that unauthorised entry to the work site is prohibited;

b) showing the name of the principal contractor (or person in charge of the work site), and a telephone number at which that person may be contacted at any time for business purposes and outside working hours; and

c) showing the name, address and telephone number of the Principal Certifying Authority for the work.

2) Any such sign must be maintained while to building work or demolition work

is being carried out, but must be removed when the work has been completed.

(Reason: Prescribed - Statutory)

ATTACHMENT TO IPP07 - 03/02/2016 Page 75

Page 76: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 41 of 52 G. Prior to the Issue of an Occupation Certificate Right of Way through site G1. The applicant shall create an easement pursuant to Section 88B instrument under the

Conveyancing Act 1919 to provide for public rights of access shown on the submitted plans (plan 5 and 6) which achieves the objectives of:-

• enabling the area to be maintained as a public right of way

• enabling the public to use that area for the purpose of public access at all the times the commercial and retail parts of the building are open

• ensure the rights are not subject to change or variation except with the prior consent of Council

The public access rights are to include:-

• the capacity to allow a public access linkage between Miller Street and Miller Lane between the hours of 7am and 10pm Mondays to Sundays

• terms and conditions which both achieve the objectives identified above and are to the satisfaction of Council’s Director of Planning and Environmental Services

The easement shall be prepared, executed and registered at the sole cost of the applicant, including the costs of Council in obtaining advice, producing documents or otherwise facilitating the preparation, execution and registration of the required documents, shall bind all successors in title and shall only be subject to variation at the discretion of the Council. The easement shall be for the life of the building and not in perpetuity. (Reason: Public access and internal amenity)

Covenant for Windows on Northern and Southern Elevations

G2. A covenant pursuant to the provisions of Part 6, Division 4 of the Conveyancing Act shall be placed on title indicating that the windows on or near the northern and southern boundaries are not protected from any redevelopment of the adjoining properties that may be allowed to build to the boundary and these windows could be blocked off. North Sydney Council shall be nominated in the instrument as the only party authorised to release, vary or modify the instrument. Evidence of the lodgement of the instrument referred to in this condition is to be provided to Council with a copy of the Occupation Certificate. (Reason: To ensure owners, or intending owners of the property are aware that

the western windows are not protected and could be blocked by future development)

ATTACHMENT TO IPP07 - 03/02/2016 Page 76

Page 77: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 42 of 52 Street Lighting in Miller Street and Miller Lane G3. Prior to the issue of the Occupation Certificate, the developer must pay to upgrade the

street lighting in Miller Street and Miller Lane, adjacent to the site, to the satisfaction of Council. The developer must engage a lighting consultant to ensure the lighting is in accordance with the relevant Australian Standard and to the satisfaction of Council’s Traffic Operation’s Officer, Maria Coyne.

(Reason: To ensure consistency with the terms of the consent)

Infrastructure Repair and Completion of Works G4. Prior to the issue of any Occupation Certificate any and all works relating to the

development: a. in the road reserve must be fully completed; and b. to repair and make good any damaged public infrastructure caused as a result

of any works relating to the development (including damage caused by, but not limited to, delivery vehicles, waste collection, contractors, sub contractors, concrete vehicles) must be fully repaired;

to the satisfaction of Council Engineers at no cost to Council.

(Reason: Maintain quality of Public assets)

Access to Premises G5. Prior to the issue of any Occupation Certificate, a certificate must be prepared an

appropriately qualified and practising Civil Engineer certifying that access and facilities for persons with a disability in accordance with the Building Code of Australia and AS Disability (Access to Premises – buildings) Standards 2010 (Premises Standards) has been provided. This certificate must be submitted to, and approved by, the Certifying Authority prior to issue of the Occupation Certificate.

(Reason: Equitable access and facilities for people with a disability)

Certification- Civil Works G6. An appropriately qualified and practicing Civil Engineer must certify to the Certifying

Authority that the vehicular crossing and associated works and road works were constructed in accordance with this consent and any approval for works in the road reserve issued by the Council. A copy of the certificate must be submitted to Council (if it is not the Certifying Authority), upon completion of the development works and prior to the issue of an Occupation Certificate.

(Reason: Compliance with the Consent)

ATTACHMENT TO IPP07 - 03/02/2016 Page 77

Page 78: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 43 of 52 Validation for Remediation G7. A validation and site monitoring report prepared in accordance with relevant

guidelines issued under the Contaminated Land Management Act 1997 must be submitted to the Council within one month of completion of the remediation work, and prior to the issuing of any Occupation Certificate.

(Reason: To ensure environmental amenity is maintained)

Utility Services G8. All utility services shall be adjusted, to the correct levels and/or location/s required by

this consent, prior to issue of an occupation certificate. This shall be at no cost to Council.

(Reason: To ensure compliance with the terms of this consent)

Covenant & Restriction (Stormwater Control Systems)

G9. An Instrument pursuant to Sections 88B and 88E of the Conveyancing Act 1919 and

one copy must be submitted to Council in registrable form, providing for::

a. a restriction as to user and positive covenant as to user as appropriate in favour of North Sydney Council burdening No.567-573 Miller Street, Cammeray requiring the ongoing retention, maintenance and operation of the stormwater facility (on-site detention, pump-out, charged lines);

b. North Sydney Council being nominated in the Instrument as the only party authorised to release, vary or modify the Instrument;

c. the wording on the Instrument making reference to the Council file/s which

hold:

(a) the Construction plans; and (b) the “Work-as-Executed” (as built) plans;

Upon Council being satisfied as to the terms of the Instrument, North Sydney Council’s official seal will be affixed to these documents, prior to submission to the Land & Property Information Office for registration

The Instrument creating the restriction and/or covenant under ss 88B and 88E required by this condition of consent must be registered on the Title of the development site prior to the issue of an Occupation Certificate or commencement of use of the site, whichever is the earlier. Typical wording for the Instrument can be sourced from Council’s “Specification for the Management of Stormwater”. Evidence of the registration of the instrument referred to in this condition is to be provided to Council prior to the issue of an Occupation Certificate.

ATTACHMENT TO IPP07 - 03/02/2016 Page 78

Page 79: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 44 of 52

All costs associated with the preparation, approval and registration of the Instrument required by this condition of consent must be borne by the person acting on this consent including the reasonable costs of Council in obtaining advice, negotiating the terms or otherwise facilitating the execution and registration of the required Instrument.

(Reason: Compliance and adequate maintenance of drainage system)

Basement Pump-Out Maintenance

G10. Prior to issue of an Occupation Certificate a Maintenance Regime must be prepared for the basement stormwater pump-out system and submitted to the Principal Certifying Authority for approval with the Occupation Certificate documentation. The regime must specify that the system is to be regularly inspected and checked by qualified practitioners. The basement stormwater pump-out system must be maintained in accordance with the approved Maintenance Regime at all times.

(Reason: To ensure future provision for maintenance of the drainage system)

Notification of New Address Developments G11. Prior to any Occupation Certificate being issued, the person acting upon this consent

must comply with the following: -

(a) Notify Australia Post of the address(es) as issued by Council and the location in plan form of any secondary, internal addresses, in relation to built public roads. Check Australia Post Website (www.auspost.com.au) to find your nearest Australia Post Delivery Facility.

(Reason: To ensure that Council records are accurate, and that house numbering

complies with the requirements of Council’s House Numbering Policy. Proper house numbering also assists emergency services in readily locating properties)

Height G12. Upon completion of the works and prior to the issue of any Occupation Certificate the

RL of the development must be surveyed and certified by an appropriately qualified and practising surveyor as compliant with the maximum approved levels in accordance with Condition A1 of this consent. This survey and certification must be submitted to the Certifying Authority with the application for an Occupation Certificate and a copy provided to Council (if it is not the Certifying Authority).

(Reason: To ensure compliance with the terms of this development consent)

ATTACHMENT TO IPP07 - 03/02/2016 Page 79

Page 80: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 45 of 52 Sydney Water G13. A Section 73 Compliance Certificate under the Sydney Water Act 1994 must be

obtained. . The final Section 73 Certificate must be submitted to the Certifying Authority prior to release of any linen plan for subdivision or prior to occupation of the development, whichever is the earlier. The Section 73 Certificate must be submitted to the Certifying Authority prior to the issue of the Strata Certificate. [Delete as appropriate]

Notes: Application must be made through an authorised Water Servicing Co-ordinator, for details see the Sydney Water web site www.sydneywater.com.au\customer\urban\index, or telephone 13 20 92. Following application, a ‘Notice of Requirements’ will be forwarded detailing water and sewer extensions to be built and charges to be paid. Please make early contact with the Coordinator since building of water/sewer extensions can be time consuming and may impact on other services and building, driveway or landscape design. (Reason: To ensure compliance with the statutory requirements of Sydney

Water)

BASIX Completion Certificate G14. In accordance with Clause 154C of the Environmental Planning and Assessment

Regulation 2000, prior to issuing a final occupation certificate the Certifying Authority must apply to the Director-General for a BASIX completion receipt.

(Reason: To ensure compliance with the specified BASIX Certificate) Landscaping G15. The landscaping shown on the approved landscape plans forming part of Condition

A1 of this consent must be completed prior to the issue of any Occupation Certificate. (Reason: To ensure compliance) Damage to Adjoining Properties G16. On completion of the development the subject of this consent and prior to the issue of

the Occupation Certificate, a report is to be prepared by an appropriately qualified consultant and is to be provided to the Certifying Authority (and a copy to Council if it is not the Certifying Authority) certifying:

ATTACHMENT TO IPP07 - 03/02/2016 Page 80

Page 81: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 46 of 52

a) whether any damage to adjoining properties has occurred as a result of the development;

b) the nature and extent of any damage caused to the adjoining property as a result of the development;

c) the nature and extent of works required to rectify any damage caused to the adjoining property as a result of the proposed development;

d) the nature and extent of works carried out to rectify any damage caused to the adjoining property as a result of the development; and

e) the nature and extent of any agreements entered into for rectification of any damage caused to the adjoining property as a result of the development.

The report and certification must reference the dilapidation survey and reports required to be provided to the Certifying Authority in accordance with this consent.

Where works required to rectify any damage caused to adjoining property as a result of the development identified in the report and certification have not been carried out, a satisfactory agreement for rectification of the damage is to be made with the affected person/s as soon as possible prior to the issue of an Occupation Certificate. All costs incurred in achieving compliance with this condition shall be borne by the developer.

(Reason: To ensure adjoining owner’s property rights are protected in so far as

possible) Verification Statement (External Finishes and Materials) G17. Prior to the issue of any Occupation Certificate, a verification statement from a

qualified designer or architect (preferably the original designer), must be submitted to Council and the Certifying Authority certifying that the external finishes and materials are in accordance with the approved schedule of finishes and materials identified in this consent. “qualified designer” means a person registered as an architect in accordance with the Architects Act 2003 cf 50(1A) EP & A Regs 2000.

(Reason: To ensure the design quality and finishes for residential flat

development) Intercom G18. An intercom system must be provided in the following location:

• Adjacent to the visitor parking entry to enable easier and safe access to visitor parking

• Adjacent to the residential lobby on the Miller Street frontage of the site

ATTACHMENT TO IPP07 - 03/02/2016 Page 81

Page 82: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 47 of 52

These intercom systems must be installed prior to issue of any occupation Certificate.

(Reason: To ensure convenient access is available for residents and visitors to the building)

Allocation of Spaces G19. Car parking spaces must be provided and maintained at all times on the subject site.

The spaces shall be allocated to uses within the building in accordance the following table:

24 Residential 4 Residential – Visitors 1 Residential – Visitor/carwash

bay 4 Accessible 1 Accessible - Visitor

The car parking spaces are to be identified on-site by line-marking and numbering upon the completion of the works and prior to issue of Occupation Certificate. Car parking spaces provided must only be used in conjunction with the approved uses contained within the development. In the case of Strata subdivision any car parking for strata lots for residential purposes must be individually allocated to its corresponding residential strata lot as part of each lots' unit entitlement. Visitor parking facilities must be designated as common property on the strata plan. Visitor parking facilities must not at any time be allocated, sold, licensed or leased for the exclusive use of any occupier or owner and must be retained as common property by the Owners Corporation for use by building visitors.

(Reason: To ensure that adequate parking facilities to service the development

are provided on site) Compliance with Certain conditions G20. Prior to the issue of any Occupation Certificate Condition C1 must be certified as

having been implemented on site and complied with.:

(Reason: To ensure the development is completed in accordance with the requirements of this consent)

ATTACHMENT TO IPP07 - 03/02/2016 Page 82

Page 83: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 48 of 52 I. On-Going / Operational Conditions First Use of Premise – Further consent required I1. A separate development application for the fitout and use of four (4) ground floor

tenancies must be submitted to and approved by Council prior to that fitout or use commencing.

(Reason: To ensure development consent is obtained prior to uses commencing)

Visitors Parking Sign I2. A sign, legible from the street, must be permanently displayed to indicate that visitor

parking is available on the site and the visitor car parking spaces must be clearly marked as such.

(Reason: To ensure that visitors are aware that parking is available on site and to

identify those spaces to visitors) Use of Car parking Spaces I3. Car parking spaces provided must only be used in conjunction with the approved uses

contained within the development. Visitor parking facilities must be designated as common property on any strata plan. Visitor parking facilities must not at any time be allocated, sold, licensed or leased for the exclusive use of any owner or occupier or third party and must be retained as Common Property by the owners corporation for use by building visitors. (Reason: To ensure that visitor parking is not allocated to building occupants

and remains available on an ongoing basis)

Allocation of Spaces I4. The allocation of Carparking spaces within the development must be maintained at all

times in accordance with the terms of this consent. The allocation of spaces must be maintained in accordance with the following table:

24 Residential 4 Residential – Visitors 1 Residential – Visitor/carwash

bay 4 Accessible 1 Accessible - Visitor

Car parking spaces provided must only be used in conjunction with the approved uses contained within the development.

ATTACHMENT TO IPP07 - 03/02/2016 Page 83

Page 84: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 49 of 52

In the case of Strata subdivision any car parking for strata lots for residential purposes must be individually allocated to its corresponding residential strata lot as part of each lot’s unit entitlement. Visitor parking facilities must be designated as common property on the strata plan. Visitor parking facilities must not at any time be allocated, sold, licensed or leased for the exclusive use of any occupier or owner and must be retained as common property by the Owners Corporation for use by building visitors.

(Reason: To ensure that adequate parking facilities to service the development

are provided on site) Loading within Site I5. All loading and unloading operations must be carried out wholly within the confines

of the site, at all times and must not obstruct other properties or the public way.

(Reason: To ensure that deliveries can occur safely within the site and does not adversely affect traffic or pedestrian amenity)

Commercial Waste and Recycling Storage I6. Commercial waste and recycling material/storage bins must be stored in a separate

area to the residential waste and recycling material/storage bins.

(Reason: To ensure that commercial waste and residential waste is not mixed and is properly managed)

Waste Collection I7. Waste and recyclable material, generated by this premises, must not be collected

between the hours of 10pm and 6am on any day.

(Reason: To ensure the amenity of surrounding properties) Delivery Hours I8. No deliveries, loading or unloading associated with the premises are to take place

between the hours of 10pm and 6am on any day.

(Reason: To ensure the acoustic amenity of surrounding properties)

Right of way through site I9. The right of way through the site must remain for the life of the development and

operate in accordance with the registered easement.

(Reason: To ensure on-going compliance with the terms of this consent)

ATTACHMENT TO IPP07 - 03/02/2016 Page 84

Page 85: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 50 of 52 K. Prior to the Issue of any Strata Certificate Strata Subdivision K1. A Strata Certificate pursuant to the Strata Schemes (Freehold Development) Act 1973,

that authorises registration of the strata plan, strata plan of subdivision or notice of conversion at NSW Land and Property Information Office must be obtained. The fifth storey must be deleted from the strata plans. If the Strata Certificate is obtained from an Accredited Certifier, other than the Council, the certifier is to provide Council with a copy of the endorsed Strata Certificate within 7 days of issuing the same, pursuant to the Strata Schemes (Freehold Development) Regulation 2002.

NOTES: For approval of the Strata Certificate by North Sydney Council, the following must be submitted to Council: - a) the original strata plans or strata plans of subdivision and administration sheets

plus two (2) copies of each, and any original Instrument (including but not limited to any section 88B or 88E instruments) to be endorsed, all enclosed in a protective cardboard tube (to prevent damage during transfer);

b) 2 additional copies of the strata plans or strata plans of subdivision and any

relevant Instrument for submission to Council Customer Services and records department for electronic database scanning and copying;

c) a completed Subdivision or Strata Certificate Application form together with

payment of fee current at lodgement; d) written evidence that all applicable conditions of consent required to be

satisfied, prior to issue of the Strata Certificate, have been satisfied. Council will check the consent conditions on the relevant consent(s). Failure to submit the required information will delay endorsement of the Strata Certificate, and may require payment of rechecking fees;

e) plans of subdivision and copies must not be folded; and f) council will not accept bonds in lieu of completing subdivision works. (Reason: To ensure compliance with relevant legislative requirements and

maintenance of up to date Council records) Sydney Water K2. A Section 73 Compliance Certificate under the Sydney Water Act 1994 must be

obtained. .

The Section 73 Certificate must be submitted to the Certifying Authority or North Sydney Council with the documentation to enable the issue of the Strata Certificate.

ATTACHMENT TO IPP07 - 03/02/2016 Page 85

Page 86: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 51 of 52

Notes:

1. Application must be made through an authorised Water Servicing Co-ordinator, for details see the Sydney Water web site www.sydneywater.com.au or telephone 13 20 92.

2. Following application, a ‘Notice of Requirements’ will be forwarded detailing water and sewer extensions to be built and charges to be paid. Please make early contact with the Coordinator since building of water/sewer extensions can be time consuming and may impact on other services and building, driveway or landscape design.

(Reason: To ensure compliance with Sydney Water requirements)

Release of Strata Certificate K3. The Strata Certificate that authorises registration of the Strata Plan, Strata Plan of

Subdivision or Notice of Conversion at NSW Land and Property Information shall not be issued until bounding walls, floors and ceilings between proposed strata lots have been constructed in accordance with the approved plans identified in Condition A1 of this Consent.

(Reason: To ensure that the registered strata plan relates to approved

development)

Allocation of Parking and Visitor Parking K4. Car-parking provided must only be used in conjunction with the units and tenancies

contained within the development. Any carparking for strata lots for residential purposes must be individually allocated to its corresponding residential strata lot as part of each lot’s unit entitlement. The allocation of spaces must be maintained in accordance with the following table:

24 Residential 4 Residential – Visitors 1 Residential – Visitor/carwash

bay 4 Accessible 1 Accessible - Visitor

The car parking spaces are to be identified on-site by line-marking and numbering upon the completion of the works and prior to issue of Occupation Certificate. Carparking spaces provided must only be used in conjunction with the approved uses contained within the development. In the case of Strata subdivision any carparking for strata lots for residential purposes must be individually allocated to its corresponding residential strata lot as part of each lot’s unit entitlement.

ATTACHMENT TO IPP07 - 03/02/2016 Page 86

Page 87: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

467-473 MILLER STREET, CAMMERAY DEVELOPMENT APPLICATION NO. 280/15 Page 52 of 52

Visitor parking facilities must be designated as common property on the strata plan. Visitor parking facilities must not at any time be allocated, sold, licensed or leased for the exclusive use of any occupier or owner and must be retained as common property by the Owners Corporation for use by building visitors.

(Reason: To ensure that adequate parking facilities to service the development are provided on site)

Building and Unit Numbering (Strata Subdivisions) K5. Prior to issue of the Strata Certificate, the person acting upon this consent must apply

to North Sydney Council and receive written confirmation of the allocated street address and unit numbers for the building and the approved strata allotments within the completed project. These are the property addresses that will be recorded in Council records and must be displayed at the property in accordance with the provisions of the applicable Australian Standard (AS/NZS 4819:2011).

To assist Council, a draft proposal for numbering within the strata scheme or street should be submitted for concurrence to Council, as these numbers will be used to maintain Council’s property and mapping database.

(Reason: To ensure that Council records are accurate, and that building and unit

numbering complies with the requirements of Council’s Property Addressing Policy. Proper building and unit numbering also assists emergency services in readily locating properties)

Services within Lots K6. A report must be provided by a Registered Surveyor certifying that all services

(including but not limited to stormwater drainage, gas, electricity, telephone cable) as constructed or to be constructed are/will be contained within each lot or within the necessary easements to accommodate such services. The report must be submitted to the Certifying Authority for approval prior to the issue of any Subdivision Certificate.

(Reason: To ensure adequate servicing of the development)

ATTACHMENT TO IPP07 - 03/02/2016 Page 87

Page 88: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

STREET

O

o

5

\

s

o-Ø

652o

t2

c D

Race

Ew

E

o

C!o

o

1SP 81068

ATTACHMENT TO IPP07 - 03/02/2016 Page 88

Page 89: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

For privacy reasons, the architectural plans have been removed

from this document prior to publishing on the web. The plans

attached to the hard copy report may be viewed at Stanton Library

during opening hours or at the Customer Service Centre in Council

Chambers between 9.00am and 4.00pm Monday to Friday.

Page 90: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

4.2.2 Building Heights - Exceptions to developmentstandards

Pursuant to Clause 4.3 of MLEP 2013 the height of a buildingon the subject land is not to exceed 15 metres in height. Theobjectives of this control are as follows:

(a) to promote development that conforms to andreflects natural landforms, by steppingdevelopment on sloping land to follow the naturalgradient,

(b) to promote the retention and, if appropriate,sharing of existing views,

(c) to maintain solar access to existing dwellings,public reseryes and streets, and to promote solaraccess for future development,

(d) to maintain privacy for residents of existingdwellings and to promote privacy for residents ofnew buildings,

(e) to ensure compatibility between development,particularly at zone boundaries,

(f) to encourage an appropriate sca/e and density ofdevelopment that is in accordance with, andpromotes the character of, an area.

Building height is defined as follows

building height (or height of building) means theveftical distance between ground level (existing) andthe highest point of the building, including plant and liftoverruns, but excluding communication devices,antennae, satellite drshes, masfs, flagpoles,chimneys, flues and the like

The development has a maximum building height of 16.3metres measured to the upper roof parapet and 17.5 metresmeasured to the top of the lift overrun and ventilation shaft.Such building heights exceed the 13 metre height standard by3.3 and 4.5 metres respectively representing a storey inheight.

ATTACHMENT TO IPP07 - 03/02/2016 Page 109

Page 91: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

I

I

iÌ)

rtñlv-!__

Figure l1 - Height breach diagram

Clause 4.6 of MLEP 2013 provides a mechanism by which adevelopment standard can be varied. The objectives of thisclause are:

(a) to provide an appropriate degree of flexibility inapplying certain development standards toparticular development, and

(b) to achieve better outcomes for and fromdevelopment by allowing flexibility in particularcircumstances.

Pursuant to clause 4.6(2) consent may, subject to this clause,be granted for development even though the developmentwould contravene a development standard imposed by this orany other environmental planning instrument. However, thisclause does not apply to a development standard that isexpressly excluded from the operation of this clause.

This clause applies to the clause 4.3 Height of BuildingsDevelopment Standard.

ATTACHMENT TO IPP07 - 03/02/2016 Page 110

Page 92: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Clause 4.6(3) states that consent must not be granted fordevelopment that contravenes a development standardunless the consent authority has considered a written requestfrom the applicant that seeks to justify the contravention of thedevelopment standard by demonstrating:

(a) that compliance with the development standard isunreasonable or unnecessary in the circumstances ofthe case, andthat there are sufficient environmental planninggrounds to justify contravening the developmentstandard.

whether contravention of the development standardraises any matter of significance for Sfafe or regionalenvironmental planning, andthe public benefit of maintaining the developmentstandard, andany other matters required to be taken intoconsideration by the Director-General beforegranting concurrence.

Clause 4.6(4) states consent must not be granted fordevelopment that contravenes a development standardunless:

(a) the consent authority rs safisfied thaf;

(i) the applicant's written request has adequatelyaddressed the matters required to bedemonstrated by suöc/ause (3), and

(i¡) the proposed development will be in the publicinterest because it is consistenf with theobjectives of the particular standard and theobjectives for development within the zone inwhich the development ,s proposed to becarried out, and

(b) the concurrence of the Director-General has beenobtained.

Clause 4.6(5) states that in deciding whether to grantconcurrence, the Director-General must consider:

(a)

(b)

(b)

(c)

ATTACHMENT TO IPP07 - 03/02/2016 Page 111

Page 93: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Boston Blvth Fleminq - Town Planners Paqe 22

Claim for Variation

Zone and Zone Obiectives

The permissibility of the development and its performancewhen assessed against the associated objectives has beenaddressed in detail in section 4.2.1 of this report. Thedevelopment has been found to be permissible and consistentwith the zone objectives as outlined.

Accordingly there are no statutory zoning or zone objectiveimpediment to the granting of approval to the proposeddevelopment.

Heioht of Buildinqs Standard and Obiectives

Pursuant to Clause 4.3 MLEP 2012 the height of any buildingon the land shall not exceed a height of 13 metres. Theobjectives of this clause are:

(a) to promote development that conforms to andreflects natural landforms, by steppingdevelopment on sloping land to follow the naturalgradient,

(b) to promote the retention and, if appropriate,sharing of existing views,

(c) to maintain solar access to existing dwellings,public reserves and sfreefs, and to promote solaraccess for future development,

(d) to maintain privacy for residents of existingdwellings and to promote privacy for residents ofnew buildings,

(e) to ensure compatibility between development,pafticularly at zone boundaries,

(f) to encourage an appropriate scale and density ofdevelopment that is in accordance with, andpromotes the character of, an area.

The development has a maximum building height of 16.3metres measured to the upper roof parapet and 17.5 metresmeasured to the top of the lift overrun and ventilation shaft.Such building heights exceed the 13 metre height standard by3.3 and 4.5 metres respectively representing a storey in

height.

Having regard to the stated objectives it is considered thatstrict compliance is both unreasonable and unnecessary forthe following reasons:

ATTACHMENT TO IPP07 - 03/02/2016 Page 112

Page 94: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

o

a

a

Detailed site and context analysis with particularconsideration given to development located on thewestern side of Miller Street given that this side of thestreet has already been developed and represents, inour opinion, the existing and desired future character ofthe Cammeray Village Centre. Through such analysisappropriate setbacks, building envelopes andtransitional building heights were identified providing forthe highly articulated and modulated complimentaryand compatible building form currently proposed.

It was determined that the critical issue was how thefloor space was distributed across the site to achieve acontextually appropriate built form response whilstproviding appropriate residential amenity to theadjoining apartments and future occupants. In thisregard, the upper levels have been stepped backbeyond the levels below with the uppermost levelconstrained in size and footprint. The southerncourtyard/ void/ light well area generally aligns with thecourtyard established on No. 465 Miller Streetmaintaining appropriate separation distances to theadjoini ng residential apartments.

The height, bulk, scale of the building are entirelyconsistent with the built form characteristicsestablished by development located on the westernside of Miller Street with this development representingthe first consolidated allotment located on the easternside of Miller Street within this village precinct to bedeveloped pursuant to the current statutory planningregime.

It has been determined that the additional buildingheight will not give rise to any adverse residentialamenity impacts in terms of view loss, overshadowing,privacy or visual bulk. The proposal provides for thesharing of public and private views.

The upper floor level is highly recessive in form anddesign and setback behind the front building facadesuch that it will not be readily discernible in astreetscape context.

o

ATTACHMENT TO IPP07 - 03/02/2016 Page 113

Page 95: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

Boston Blvth Fleminq - Town Planners Paoe 24

Consistent with the conclus¡ons reached by SeniorComrnissioner Roseth in the matter of Project VentureDevelopments v Pittwater Council (2005) NSW LEC191 | have formed the considered opinion that mostobservers would not find the height of the proposeddevelopment offensive, jarring or unsympathetic in astreetscape context nor the built form characteristics ofdevelopment within the sites visual catchment.Accordingly it can be reasonably concluded that theproposal is compatible with its surroundings whenviewed from the harbour, foreshore areas, publicdomain and surrounding properties.

Having regard to the matter of Veloshin v RandwickCity Council [2007] NSWLEC 428 this is not a casewhere the difference between compliance and non-compliance is the difference between good and baddesign.

o

a

Further, we have formed the considered opinion that there aresufficient site specific environmental planning grounds tojustify the variation sought including the public benefitassociated with providing a through site link between MillerLane and Miller Street, the high probability that the adjoiningproperty to the north will remain a service station for aconsiderable period of time which promotes the subject site toforming the southern "gateway" to the Village Precinct with theheights proposed entirely consistent with that established bythe existing mixed use building on the opposite "gateway"corner.

Gonclusions

Having regard to the clause 4.6 variation provisions we haveformed the considered opinion:

(a) that the contextually responsive development isconsistent with the zone objectives, and

(b) that the contextually responsive development isconsistent with the objectives of the height of buildingsstandard, and

that there are sufficient environmental planninggrounds to justify contravening the developmentstandard, and

(c)

ATTACHMENT TO IPP07 - 03/02/2016 Page 114

Page 96: Item - REPORTS...unisex accessible toilet and a loading bay for a small rigid vehicle. Access to the basement levels are obtained from Miller Lane via a single lane access driveway

(d) that having regard to (a), (b) and (c) above thatcompliance with the building height developmentstandard is unreasonable or unnecessary in thecircumstances of the case, and

(e) that given the developments ability to comply with thezone and height of buildings standard objectives thatapproval would not be antipathetic to the publicinterest, and

(g) that contravention of the development standard doesnot raise any matter of significance for State orregional environmental planning.

As such we have formed the highly considered opinion thatthere is no statutory or environmental planning impediment tothe granting of a height of buildings variation in this instance.

4.2.3 Non-Residential Floor Space

Pursuant to clause 4.4431 of the NSLEP the non-residentialfloor space for all buildings on the site must not be less than0.5:1 and no greater than 2:1.The stated objectives of thisclause are as follows:

(a)

(b)

(c)

(d)

to provide for development with continuous andactive sfreef frontages on ceftain land in Zone81 Neighbourhood Centre, Zone 84 Mixed Useand Zone SP2 lnfrastructure,to encourage an appropriate mix of residentialand non-residential uses,to provide a level of flexibility in the mix of landuses fo cater for market demands,to ensure that a suitable level of non-residentialfloor space is provided to reflect the hierarchy ofcommercial centres.

The development has a non-residential floor area of 407square metres representing an FSR of 0.501:1 in strictaccordance with the control. The retail floor space has beendistributed across the site such that both street frontages areactivated with the majority of retail tenancies also benefitingfrom internal courtyard areas.

ln this regard Council can be satisfied that the developmentcomplies with the standard and associated objectives asoutlined.

ATTACHMENT TO IPP07 - 03/02/2016 Page 115


Recommended