+ All Categories
Home > Documents > ITER Vacuum Vessel Status and ProcurementITER VV Field Joint Welding R&D Outer Shell Welding Machine...

ITER Vacuum Vessel Status and ProcurementITER VV Field Joint Welding R&D Outer Shell Welding Machine...

Date post: 14-Mar-2020
Category:
Upload: others
View: 32 times
Download: 0 times
Share this document with a friend
37
1 ITER Vacuum Vessel Status and ITER Vacuum Vessel Status and Procurement Procurement IBF, Nice 11 December 2007 Presented by K. Ioki Tokamak Department, ITER Organization
Transcript

1

ITER Vacuum Vessel Status and ITER Vacuum Vessel Status and Procurement Procurement

IBF, Nice 11 December 2007

Presented by K. IokiTokamak Department, ITER Organization

2

ContentsContents

• VV design• Design Review

Activities• VV Procurement

Main Vessel

Ports

3

Vacuum vessel Analysis Vacuum vessel Analysis -- Analysis report will be updated in Analysis report will be updated in preparation for assessment by preparation for assessment by Accepted Notified Body (ANB) Accepted Notified Body (ANB)

Vacuum Vessel Design and ActivitiesVacuum Vessel Design and Activities

Vacuum vessel Code & standardsVacuum vessel Code & standards-- RCCRCC--MR 2007 VersionMR 2007 Version-- PED/ESPNPED/ESPN- IO will be “manufacturer”- Selection of ANB

Vacuum vessel CAD model (2007)Vacuum vessel CAD model (2007)

Importance of the Vacuum vessel Importance of the Vacuum vessel -- First safety barrier (SIC: Safety Class First safety barrier (SIC: Safety Class Component)Component)-- Magnet and VV are the critical path in Magnet and VV are the critical path in the ITER construction schedule.the ITER construction schedule.

Vacuum vessel design Vacuum vessel design -- Basic structure is unchanged.Basic structure is unchanged.-- Double wall allDouble wall all--welded structurewelded structure- Detail CAD models are being prepared (well advanced).- Definition of interfaces is critical.

Inter-modular

key

Upper segment of Main Vessel (w/o outer shell)

Blanket flexible support housing

Inter-modular

key

4

Upper Port StructurePort stub

Connecting duct

Additional shielding

Blanket cooling pipes

Vacuum Vessel Port Design

5

InIn--wall shielding of the Vacuum Vesselwall shielding of the Vacuum Vessel

Function Function -- Neutron shielding.Neutron shielding.-- Ripple mitigationRipple mitigation

Corrosion test is starting Corrosion test is starting -- SCC/Crevice corrosionSCC/Crevice corrosion-- WorkWork--hardened stainless hardened stainless steelsteel-- Galvanic corrosion (mixed Galvanic corrosion (mixed materials)materials)

Ferromagnetic steel plates Ferromagnetic steel plates -- EM forces calculated. EM forces calculated. -- Support design progressing.Support design progressing.

Structure and Materials Structure and Materials -- MultiMulti--plates mechanically assembled.plates mechanically assembled.- Borated steel and Ferritic steel (SS 430)- Eddy currents are minimized in this design.

Optimization for Ripple minimization Optimization for Ripple minimization -- Detail calculation onDetail calculation on--going.going.

-- ProgressingProgressing --

6

Ripple Requirement from Plasma Physics Updated

-2.5

-2.0

-1.5

-1.0

-0.5

0.0

0.5

1.0

1.5

2.0

2.5

Z(m)

-2.5

-2.0

-1.5

-1.0

-0.5

0.0

0.5

1.0

1.5

2.0

2.5

E1

C2

Toroidal field ripple without additional

ferromagnetic insets (Full TF current )

 

Additional Ferromagnetic

Inserts

NB port

opening

Regular equatorial port region

NB equatorial port region

-2.5

-2.0

-1.5

-1.0

-0.5

0.0

0.5

1.0

1.5

0.0 0.2 0.4 0.6 0.8 1.0

Filling factor

Ripple %

Full TF current

Half TF current

In the 2005 design, the maximum ripple is ~1% (loca lized) which was accepted at the previous stage.

Recent proposal is “the maximum ripple should be as small as possible (<0.2 % proposed).

Optimization of Ferromagnetic Insert DesignThe maximum ripple can be reduced to ~0.3 % in the current design. Further reduction is to be studied.

7

Measurement of outgassing rate (JA)

LPT on UHV surfaceVacuum vessel sector

Leak Testing (Proposed)

Helium enclosure, could

also be flexible oven

filled to 1 bar

He

Calibrated

leak

RGA

Outgassing rate seems to be acceptable based on the test result.

- Low impurity liquid penetrant (Dye) should be selected.

- Careful cleaning after LPT is required.

Leak rate <10-9 Pam3/s is a target value to be achieved. This is challenging for a large complicate component.

For the VV system 1 x 10-7 Pam3/s

8

200 C

Liquid Penetrant Outgassing Test for UHV use

Measurement of outgassing rate (JA)

9

Design Development of NB Port liners (On-going)

- Fabrication technology

- Mitigate high peak stresses.

- RH compatible structure

NB ports

Inside view of HNB port HNB liner structure

High heat flux element the HNB liner structure

10

removable flat strip

Exploded view of option A (Stiffeners of the strip plate are not shown)

M52 Bolts(under vacuum)

plug inner lip

Port Flange Design

VV outer lip

Port plug

- Lip seal -

“compliant” plate part of the gasket flange

Double metallic gasket seals

M52standard boltsor superbolts

Port plug

Vacuum / He feeding pipe for local and continuousleak checking

0.05 MPa tracer gas

- Gasket -

11

Flat strip

This Flange designThis Flange design allows shift allows shift from from Gasket (Hydrogen Phase) Gasket (Hydrogen Phase) toto lip weld lip weld sealing (Dsealing (D --T Phase)T Phase)

TIG welding of a 2mm flat strip

Double TIG welding of inner and outer U shape lip

One of the Two Designs can be selected depending on further design efforts, cost estimation and R&D / Qualification tests results :

Design of this part is the same

and frozen.

12

R&D: Full scale Equatorial flange mock-up

Simplified mock-upQualification of sealing

EP : 2090 x 2542

150

230

Test campaign*(k€)

400250Upper flange

680450Equatorial flange

Total cost (k€)Manufacture (k€)Mock-up

(*) Includes the baking and insulation equipment

13

Partial VV Sector Mock-up: PS2 (Curved Section) Fabrication

Welding joint connection between PS1 (straight section) and PS2 (Inboard upper curved section)

Partial Full-scale VV Sector FabricationPartial VV Sector Fabrication was completed.

- Dimensional accuracy is mostly within the required (or target) tolerances.

- Fabrication methods to be further optimized.

- EB welding was used for welding between the inner shell and keys and flexible support housings

Automatic NG TIG welding on the outer shell of the PS1-PS2 joint

Partial Full-scale VV Sector Fabrication (EU)

14

Cutting fixtures

- Observed 4-5 mm relative vertical movement of PS2 component respect to the PS1 component.

- Heavy and dirty work was required for dismantling the jigs. (To be included)

Partial Full-scale VV Sector Fabrication

Completion of PS1 and PS2 joint

Partial Full-scale VV Sector Fabrication (EU)

15

Summary: Fabrication tolerance- Poloidal movements of the PS2 respect to the PS1 was observed (~0.2°PS1 / PS2 deflection)- All Outer Shell surface is within the acceptance fabrication tolerances (±10 mm)- Some of the Inner Shell Housing positions (radial ~ +6mm) are out of the target fabrication tolerances: (radi al ±5 mm, poloidal ±3 mm). This can be improved in the future .- All Inner Shell surface is within the target fabric ation tolerances (±10 mm)

A poloidal movement (X-Z plane) of the PS2 was observed respect to the PS1, due to the jig dismantling (Laser Tracker measurement). The red line (see Left) shows this PS2 movement (amplified 10 times).

Partial Full-scale VV Sector Fabrication

Result of Partial Full-scale VV Sector Fabrication (EU)

16

After welding ribs and alignment of housings(Additional ribs to avoid distortion)

Welding of inter-modular key (With protection plate)

Upper section

Lower section

EB welding on Full-scale partial mock-up (2007 JA r eport)

Welding of centering key

Welding of center rib

Welding of Flexible support housing

VV Mock-up Fabrication

17

Full-scale partial mock-up (Left: Plasma side, Righ t: Outer shell side) (2007 JA report)

VV Mock-up Fabrication

18

ITER VV Field Joint Welding R&DITER VV Field Joint Welding R&D

Outer Shell Welding Machine Outer Shell Welding Head

After fabrication, sectors A and B were welded together at the field joint on the center of the ports. This involved welding splice plates using the automatic NG-TIG process and inspecting the joint by the UT method.

Full Scale Sector Model (JA)

19

ITER VV Field Joint Welding R&DITER VV Field Joint Welding R&D

Inner Shell Splice Plate Inner Shell Welding Machine

Full Scale Sector Model (JA)

20

The lower port stub region (especially vertical gussets) is to be reinforced.

Study of Increased Vertical and Horizontal Loads

21

The VV horizontal displacement during VDE is increased. 10 mm ����15 mm

The gaps between VV/VVTS and VVTS/TFC is marginally acceptable. To be studied further.

Study of Increased Vertical and Horizontal Loads

22

Damper shall have a function of the actuator to position the VV horizontally with accuracy of 1mm.

VV Supporting System

High vertical load will be acceptable when it is tran sient.

23

80

1150

400

1150

VV Supporting System

Toroidal support (for VV center positioning)

(1) Adequate flexibility (spring constant) in the to roidal direction is required to mitigate the reaction force

(2) Active position control mechanism is under consi deration.

24

To improve the plasma vertical stability

- Wider copper cladding area

- To Minimize cut-outs

- To increase the copper coating thickness and achieve better material quality

Triangular Support Design Improvement

25

Vessels and Interfaces Activities Vessels and Interfaces Activities -- by Design Review by Design Review WGsWGs 20062006--20072007--

WG1

WG2

WG5

WG6

- ELM control coil proposal- Plasma vertical stability improvement- Ripple minimization

- Tritium inventory, Dust removal - VV ESPN categorization- VV ISI requirement

- Blanket manifold - RH 3 requirement - VV support improvement- Blanket flexible support improvement- Dome shape cryostat / Independent support structur e

- Enlargement of the DNB port opening

- Blanket manifold - RH 3 requirement - VV support improvement- Blanket flexible support improvement- Dome shape cryostat / Independent support structur e

Physics

Safety

Vessels

Heating

26

Interface with Heating System NB Port Opening Update

DNB Port Opening enlarged

[On-going job]

2004 DesignNew proposed Design

Reasons:

- Beam blocking

- Tilted angle from the perpendicular direction

27

NB Port Opening Update (VV Port #4)

Design update of the VV structure in the DNB port area

28

Interfaces with Blanket Attachments

Intermodular key

Flexible support

4 Interfaces remain the same

- Hydraulic connection

- Current straps

- Keys

- Flexible supports

No Change!!

Current strapHydraulic Connection

29

ELMELM’’ss MitigationMitigationWall Mounted Coil ConceptWall Mounted Coil Concept

This option This option was studied was studied but but droppeddroppedcconsideringonsideringcost and cost and schedule schedule impactsimpacts

30

mid+topport coils

ELMELM’’ss Mitigation Mitigation –– Port Coil ConceptPort Coil Concept

This optionThis optionis to be further is to be further studied.studied.

31

ELMELM’’ss Mitigation Coil ConceptMitigation Coil ConceptLocated Between VV Inner and Outer ShellsLocated Between VV Inner and Outer Shells

This option was proposed in a This option was proposed in a recent STAC meeting for study.recent STAC meeting for study.There is a concern on the VV There is a concern on the VV procurement schedule.procurement schedule.

Coils Coils located located

between the between the VV inner VV inner and outer and outer

shellsshells

32

VV Procurement ScheduleVV Procurement Schedule• It is clear that the critical path activities for the project are the procurements

of the VV, the TF coils, and the buildings.• The VV Procurement Arrangement (PA) is scheduled to be issued mid-

2008. To meet this schedule the following dates must be met.

• VV Design Frozen – Sept 2007 “Design options should be eliminated (for the VV)”

– Blanket Attachment – Blanket Manifolds– Lower Ports (new proposal for blanket piping)– Divertor Support (Updated design)– ELM Control Coils (new proposal)– NB Port (Size, angle, location)– VV Port Flange Design– Triangular Support Modifications– VV Gravity Supports

• VV Interfaces Frozen – Nov 2007– Blanket– Cooling system– Diagnostics– NB - Safety– Building - Plasma– Cryostat - TS

33

Triangular support

Structures for lifting

Divertorsupport rail

VV gravity support

VV Procurement ScheduleVV Procurement Schedule

Apr-08PA* Complete

June-08PA* Signed

July-083D Models Complete

Dec 08 KOJune 09 EU

Contract Awarded

July 08 KOSept 08 EU

Call for Tender

Dec-07Code Selection: RCC-MR 2007

Nov-07Interfaces Frozen

Sept-07Design Frozen

Date1.5 Vacuum Vessel

PA*: Procurement Arrangement between IO and DasPA*: Procurement Arrangement between IO and Das

-- Design and interface freeze dates are critical Design and interface freeze dates are critical to allow the VV Pto allow the VV P 3333rocurement to proceed on rocurement to proceed on schedule.schedule.-- These dates may drive blanket and These dates may drive blanket and divertordivertordesign activities.design activities.

34

Vacuum Vessel Manufacturing Scheme (w/o Consortium)

ManufacturerIO

ManufacturerIO

Fabrication:- Welding- Materials- NDT- Test (pressure)- Etc.

Notified Body:

Check design, Manufacture,and issue the statement of

conformity

Design/ESR:- Strength, - Seismic, - hazard- Etc.

Dossier Manufacturer (IO):

Declaration of Conformity Global

Conformity

Contract

Subcontractor –Control of fabrication

Subcontractor –Control of fabrication

Equatorial and Lower

PortsKO

Equatorial and Lower

PortsKO

UpperPorts

RF

UpperPorts

RF

VVIW Shield

IN(non structural)

VVIW Shield

IN(non structural)

FJ WeldingIO

FJ WeldingIO

Main VV20%-KO

Main VV20%-KO

Main VV80%-EU

Main VV80%-EU

35

52 months4/2013

40 months 4/2012

12/2008KO plan

(47 months from 12/2008)(41 months from 6/2009)

11/2012

(35 months from 12/2008) (29 months from 6/2009)

11/2011

(12/2008)(6/2009)

IPS Case A Rev 0

Last sector deliveryFirst sector deliveryContract Award

VV Sector Fabrication Schedule (Delivery to the ITER Site)

In-wall shielding

VV supportsNB liners

Others

IN

Upper portsRF

Equatorial portsLower ports

2 VV sectorsKO

7 VV sectorsEU

PortsMain VesselProcurement DA

Procurement sharing of the VV components

36

5360Main vessel and ports Grand total

1858Ports(316 L(N) IG, 304 L)

3502Main vessel total

159Water

54Additional shielding

1679In-wall shielding(1% and 2% Borated steel and 430)

1611Main Vessel(316 L(N) IG)

Weight (ton)

Materials for the VV fabrication

37

SummarySummary

1. VV/ports detail design, analysis and R&D are progressing towards the Procurement Arrangement (PA) and call-for-tender.

2. The VV procurement schedule is very critical. (VV design freeze - Sept 2007, interface freeze - Nov 2007, PA signed - June 08)

3. New proposals and design improvements have been discussed and concluded in 2006-07 Design Review Meetings. Results of the Design Review Meetings are being incorporated into the 2007 ITER baseline design.


Recommended