NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 1 of 12
ITP FOR CONDUIT, TRAY, CABLE (E&I) Works NBL-CN-O-P-80-0113
A Nov 11,2021 Issue for Review
M.Faiz H.D.Moon S.G. YUK
REV. DATE DESCRIPTION PREPARED BY CHECKED
BY APPROVED BY
SM Accepted & Date
by OWNER
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 2 of 15
Table of Contents
1. General ......................................................................................................................... 3
2. Conduit Installation Works .......................................................................................... 3
3. Cable Tray Installation Works ..................................................................................... 4
4. Cable Installation & Testing ......................................................................................... 4
5. Compilation of Handover Documentation .................................................................. 5
6. Inspection Format ........................................................................................................ 6
Form No. 111 General Inspection Report.............................................................................................. 6
Form No. E-001 Conduit Inspection Report .......................................................................................... 7
Form No. E-002 Cable Tray Inspection Report ..................................................................................... 8
Form No. E-003 Cable Laying Inspection Report ................................................................................. 9
Form No. E-004a Electrical Power Cable Testing Report ................................................................... 10
Form No. E-004b Instrument / Control CableTesting Report .............................................................. 11
Form No. E-005 MV Cable High Voltage Withstand Test Report ........................................................ 12
Form No. E-006 Cable Termination Report ......................................................................................... 13
Form No. E-007 Final Inspection Status for Cable ............................................................................. 14
Form Punchlist .................................................................................................................................... 15
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 3 of 15
Inspection / Test items Description Applied Procedure,
Code,DWG
Verification Document
(QC Record)
Frequency of
Inspection /Test
Inspection and Test Activities by
SUB CON LGPC
1. General
1.1. Approved drawings. Latest IFC Dwg. IFC Dwg Each Drawing I/R W S
1.2. Method statement and Risk Assessment
Approved Method statements
Approved for Construction
Before starting of
works I/R R R
1.3. Incoming Materials Inspection; - Conduit material,etc - Cable ladder and tray, fittings, steel
supports, etc. - Cable Test (in drum).
1. Insulation Resistance Test
IFC DWG, Mill certificates
- Form No. 111 /Form No. E-004
Every Delivery I/R SW R
2. Conduit Installation Works
2.1. Installation of exposed conduit Latest IFC DWG/ Method statement
Form E-001 Each Area I/R W SW
2.2. Installation of concealed/embedded Conduit (equipment foundations and concrete paving area)
Latest IFC DWG/ Method statement
Form E-001 Each Area I/R W SW
2.3. Installation of underground conduit Latest IFC DWG/ Method statement
Form E-001 Each Area I/R W SW
2.4. Installation of concealed/embedded conduit.
Latest IFC DWG/ Method statement
Form E-001 Each Area I/R W SW
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 4 of 15
3. Cable Tray Installation Works
3.1. Tray support methods - Correct and strong enough - Proper installation as per drawing
Latest IFC DWG/ Method statement
Form E-002
Before starting of Works /
Each Area
I/R SW SW
3.2. Tray Route - Check correct location route and laying
Latest IFC DWG/ Method statement
Form E-002
During starting of Works /
Each Area
I/R SW SW
3.3. Cable occupation ratio - Check cable tray type, size, thickness and tray space availability
Latest IFC DWG/ Method statement
Form E-002
During starting of Works /
Each Area
I/R SW SW
3.4. Cable tray earthing - Check earthing cable bonded
Latest IFC DWG/ Method statement
Form E-002
During starting of Works /
Each Area
I/R SW SW
3.5. Tray cover(If required) Latest IFC DWG/ Method statement
Form E-002
During starting of Works /
Each Area
I/R SW SW
3.6. Final Inspection - Check appearance (No cable tray damage, sharp
edges, etc.)
Latest IFC DWG/ Method statement
Form E-002 / Punchlist
After Finished Works /
Each Area I/R W SW
4. Cable Installation & Testing
4.1. Cable Laying - Visual check with no damage and
proper dressing - Check on cable bending radius - Check on cable marker installation - Check on cable separation
between E&I
Latest IFC DWG/ Method statement
Form E-003 Each Area I/R W W
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 5 of 15
- For underground cable required witness by client before backfilling
4.2. Cable Test - Continuity test (end to end) - Insulation Resistance Test (as per
PTS guideline)
Latest IFC DWG/ Method statement
Form E-004a Form E-004b
Each Area I/R W W
4.3. MV Cable High Voltage Withstand Test (Hi-Pot Test)
Latest IFC DWG/ Method statement
Form E-005 / Punchlist
Each Area I/R W W
4.4. Cable Termination and Final Check - Core marker as per schedule - Torque as per material size or
vendor recommendation. - MV&HV cable termination done by
competence cable jointer
Latest IFC DWG/ Method statement
Form E-006 / Punchlist
Each Area I/R W W
5. Compilation of Handover
Documentation
5.1 Site Work Conformance File(SWCF) Compile handover Documentation as per SWCF Format and Index
SWCF/ Form E-006
Before Completion I/R W R
Legend Definition : SUB : Subcontractor
CON : Contractor
OWNER : LG PETRONAS
H : Hold point
W : Witness Point
SW :Spot witness Point
R : Review / Report point
I : Inspection
S : Surveillance
i) Hold Point (H) : The following activity is not allowed to proceed until the document is reviewed and Accepted ii) Inspection (I) : RFI is required to be submitted. iii) Witness (W) : RFI is required to be submitted. iv) Spot Witness(SW) : NOI is required to be submitted.
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 6 of 15
6. Inspection Format
Form No. 111 General Inspection Report
Rev. A Page 1 of 1
ITEM DESCRIPTION:
ITEM NO: REF. DWG. NO. :
TYPE OF INSPECTION: DATE:
NBL Project
FORM NO 111
GENERAL INSPECTION REPORT
Report No.:
Job No:
Date
INSPECTION DESCRIPTION:
AC
CE
PT
ED
BY Sec. Sub-Contractor Contractor Owner (if Required)
Name
Signature
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 7 of 15
Form No. E-001 Conduit Inspection Report
Rev A Page 1 of 1 Job No.:
Subcon:
Item No.:
Inspection Type:
ACCEPT REJECT N/A
AC
CE
PT
ED
BY
:
NBL Project
FORM NO. E-001
Conduit Inspection Report
Report No.:
Area / Location:
Item Description:
9) Confirm conduits are not supported from process piping.
DWG No:
Remarks:
8) Conduit fittings and accessories are installed completely as required.
7) Conduit stubs- ups are properly protected and de-burred.
6) The conduit system is supported and fastened firmly.
5) The overall layout of conduit system is acceptable with proper alignmnet without any defects and as per drawing.
4) The bending, threading and connection of conduits is acceptable.
Result
1) The construction drawings and documents are in latest revision.
3) Conduit specification, size and quantity as per approved drawings.
2) Conduit support and spacing shall as per approved for construction drawings and typical installation details.
Item to be Checked
Sub-Contractor Contractor Owner (if Required)
Name
Sec.
Signature
Date
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 8 of 15
Form No. E-002 Cable Tray Inspection Report
Rev A Page 1 of 1 Job No.:
Subcon:
Item No.:
Inspection Type:
ACCEPT REJECT N/A
8) Check cleanliness of the tray and remove any unused materials.
7) Check cable tray cover (if required)
Area / Location:
Item Description:
NBL Project
FORM NO. E-002
Cable Tray Inspection Report
Report No.:
2) Cable tray size, type, material and routing as per approved drawings.
3) Check interference with other discipline.
4) Grounding and bonding jumpers installed as per drawing.
1) Steel support installed are adequate and strong enough to handle the weight tray and cables and as per drawing.
DWG No:
Sub-Contractor Contractor
Remarks:
Sec.
AC
CE
PT
ED
BY
:
Item to be CheckedResult
Owner (if Required)
Name
Date
Signature
5)Check mechanical damage and sharp edges.
6) Check tray bending / corner is acceptable and will not cause stress to cable.
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 9 of 15
Form No. E-003 Cable Laying Inspection Report
Rev A Page 1 of 1 Job No.:
Inspection Type:
Check
cable
dressing
and fixing
Check no
damage to
the cable
Check
overall
layout /
route as
per
drawing
Check
bending
radius is
correct
Check
laying
pattern in
cable
trench /
cable tray
as per
drawing
NBL Project
Cable Laying Check Report
Subcon:
Item No.:
Report No.:
AC
CE
PT
ED
BY
:
Remarks:
Name
Signature
Owner (if Required)
Date
Sec. Contractor
FORM NO. E-003
Remarks
DWG No:
Area / Location:
Item Description:
Cable No.
Check
cable type
& size as
per
drawing
Check
cable
identificati
on and
cable tag
Check
segregatio
n between
power
cable,
instrument
cable,
LV&MV
cable as
per
drawing
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 10 of 15
Form No. E-004a Electrical Power Cable Testing Report
Rev A Page 1 of 1
Subcon:
R-Y Y-B B-R R-BK R-E Y-E B-E BK-E
Sec.
Name
Signature
Date
Continuity
(OK / FAIL)
Cable Size
(sqmm)
Cable No. / Drum No.
/ Core No
FORM NO. E-004a
Area / Location:
INSULATION TESTER
NBL Project
Item Description:
DWG No:
MULTIMETERTEST EQUIPMENT
MANUFACTURER
Report No.:
Job No.:
Electrical Power Cable Test Report
TYPE
SERIAL NO.
AC
CE
PT
ED
BY
:
R=Red, Y=Yellow, B=Blue, BK- Black, E=Earth
Remarks:
Sub-Contractor Contractor Owner (if Required)
Item No.:
Inspection Type:
Test
Voltage
(V)
Insulation Resistance Test Result (MΩ)
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 11 of 15
Form No. E-004b Instrument / Control CableTesting Report
Rev A Page 1 of 1
Continuity
(End to end)
(OK / FAIL)
Sec.
Name
Signature
Date
Sub-Contractor Contractor
NBL Project
FORM NO. E-004bInstrument / Control Cable Test Report
Report No.:
Job No.:
Area / Location:
Item Description:
Subcon:
Item. No:
DWG No:
TEST EQUIPMENT
Inspection Type:
MULTIMETERINSULATION TESTER
MANUFACTURER
TYPE
SERIAL NO.
Cable No.
Insulation Resistance Test Result (MΩ)Core
Number
Test
Voltage (V) Core - Core
(Lowest value)Core - Ground
Remarks:
R=Red, Y=Yellow, B=Blue, BK- Black, E=Earth
AC
CE
PT
ED
BY
: Owner (if Required)
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 12 of 15
Form No. E-005 MV Cable High Voltage Withstand Test Report
Rev A Page 1 of 1
Area / Location: Subcon:
Item Description: Item No.:
Inspection Type:
No.
No.
1
2
3
Phase Reading (GΩ) Phase Reading (GΩ) Reading (GΩ) Phase Reading (GΩ)
R-E R-E R-E
Y-E Y-E Y-E
B-E B-E B-E
Sec.
Name
Signature
DateAC
CE
PT
ED
BY
:
Remarks:
Test Record:
Cable Details:
Sub-Contractor Contractor
NBL Project
Final Leakage Current (µA)
I minute 3 minutes
Description Remarks
Normal working voltage
DWG No:
Phase Time Started
1. Cable Core Insulation Resistance Test at 5kV DC
Before After
Y-E
B-E
Phase
R-E
High potential voltage (DC)
Duration of Test
kV
kV
minutes
2. Cable Core High Voltage Test ( kV DC)
Between B, R&Y to Earth
Between Y, R&B to Earth
Between R, Y&B to Earth
Owner (if Required)
Between RYB to Earth
Report No.:
Job No.:
MV Cable High Voltage Withstand
Test Report
Size
FORM NO. E-005
Core
From
To:
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 13 of 15
Form No. E-006 Cable Termination Report
Rev A Page 1 of 1 Job No.:
Subcon:
Item No.:
Inspection Type:
FORM NO. E-006
Cable Termination Check Report
Report No.:
NBL Project
Area / Location:
Item Description:
DWG No:
Cable No. Remarks
Proper
terminal used
(correct size &
material)
Check
termination
lug/ferrule if
been properly
crimped
Check
cable
glanding
Check torque as
per size, material
and vendor
recommendation
Each core has
correct cable core
marker
HV/MV
termination kit
has been
correctly
installed on the
cable by
competence
cable jointer (N/A
for LV cable)
End to end
continuity check
has been
performed on each
core
DateAC
CE
PT
ED
BY
: Sec. Owner (if Required)
Name
Signature
ContractorSub-Contractor
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 14 of 15
Form No. E-007 Final Inspection Status for Cable
Project
Project No. Form No.
Contractor Rev.
Date Sheet
Code Description Code Description NOI Date NOI Date NOI Date Yes No
Final Inspection Status for Cable
Electrical Instrument
(Subsystem No.) 1 of 1
ScopeSystem Definition Sub-System Definition
Cable Tag Number DescriptionCable Laying Cable Testing Cable Termination
Completion
Status Remarks
NBL Project Pengerang Integrated Complex Johor, Malaysia Contractor Job No : 190196
ITP for Conduit, Tray, Cable (E&I) Works NBL-CN-O-P-80-0113
Rev A
Page 15 of 15
Form Punchlist
Project
Form No. Rev. A
System No.
Discipline :
Name Date Accept Reject
Punch List for
Final InspectionSheet : Page 1 of 1
Test Circuit No.:
Category:
“A” : To be done Before Final Inspection
“B” : To be done After Final Inspection
Type:
“EL” : Electrical Punch
“IN” : Instrument Punch
“A”: Architectural, “C”: Civil, “E”: Electrical, “F”: Fire and Gas, “T”:
Design Asbuilt, “G”: Grounding, “H”: HVAC, “I”: Instrument, “P”:
Piping, “PC”: Pre-Commissioning, “M”: Mechanical, “I”: Insulation, “S”:
Structure,“V”: Vendor
Punch No Item & Area Details Cate’y Disc. PhotoIssue (Raised) by Result
Remark