+ All Categories
Home > Documents > J2007 - Construction Law Report

J2007 - Construction Law Report

Date post: 14-Apr-2018
Category:
Upload: pameswara
View: 220 times
Download: 0 times
Share this document with a friend

of 14

Transcript
  • 7/29/2019 J2007 - Construction Law Report

    1/14

    Robins Appleby & Taub LLP Suite 2600, 120 Adelaide Street West, Toronto, ON M5H 1T1 (416) 868-1080

    Time is money is an appropriate motto in

    the field of high-rise condominium projects.

    Yet, delays are an expected, although

    unfortunate, reality of such projects.

    Introduction

    The developer is at the projects centre, orchestrating the

    progress of the project and dealing with all others involved

    in the process including:

    unit purchasers;

    contractors;

    lenders;

    consultants, which may include architects,

    engineers and cost consultants;.

    the municipality; and

    Tarion.

    A developer is vulnerable to damage from delays because

    the project revenue is fixed early in the process by the sale

    price of the condominium units. Return on invested equity

    is always diminished by delays. Further, some project costs

    may be variable and sensitive to delays, such as financing

    costs, especially where there is a variable interest rate,

    and possibly construction costs, depending on whether

    the contracts are stipulated price or cost plus. When

    TIME IS MONEYThe Condominium Developers Guide to Delay Claims

    BY IRVING MARKSAND BARBARA GREEN

    ConstructionLaw Report

    KEEPING YOU INF ORMEDJULY 2007

  • 7/29/2019 J2007 - Construction Law Report

    2/14

    CONSTRUCTION LAW REPORTTime is MoneyThe Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 2 (416) 868-1080

    project costs are sensitive to delays, the developers ultimate

    return on investment is also sensitive to delay.

    In recent years, there has been little litigation driven by

    condominium unit purchasers on the basis of delay because

    of a strong market and rising prices. Although delay maycause these purchasers inconvenience, the delay often does

    not generate financial losses significant to justify a lawsuit.

    Even if a purchaser ultimately backs out of the deal, the

    developer can often sell the unit to a new purchaser for

    more money.

    While there has been an unprecedented run of rising prices,

    market conditions could easily change. If prices fall, even

    marginally, a delay could cause the developer to suffer

    significant losses. In the worst case scenario, all of the

    purchasers could terminate, leaving the developer to resell

    all of the units at lower prices. In those circumstances,

    the developer would want to hold the responsible parties

    accountable for the delay. This paper briefly addresses

    the remedies available to the developer, and the risks the

    developer faces as the target of delay lawsuits.

    Delay claims are frequently complicated, requiring an

    analysis of complex factual and legal arguments. The

    number of parties and different legal relationships between

    them often leads to multi-party litigation with numerous

    crossclaims, counterclaims and third party claims.

    The topic of delay claims is so broad that entire textbooks

    have been written on the subject. Given the scope of this

    topic, the purpose of this paper is to introduce some key

    concepts and issues which arise in delay claims from the

    perspective of the developer, as well as to provide some

    practical tips to protect the developer, even before the

    project encounters a delay.

    The paper addresses the following topics: Where delays can occur in a project:

    developer delays

    general contactor delays

    subcontractor delays

    consultant delays

    municipality delays

    lender delays

    Assessing damages in delay claims:

    notice requirements

    when is a party entitled to damages on

    the basis of delay?

    the categories of delay:

    excusable

    non-excusable

    compensable

    non-compensable

    damages arising from delay

    foreseeability

    additional construction costs

    loss of profits

    contract limitations

    supporting documents

    expert evidence

    mitigation of damages

    Review of some typical terms in construction con-

    tracts:

    exclusion clauses/disclaimers

    penalty claims vs. liquidated damages clauses

    time is of the essence clauses

    arbitration clauses

    implied terms

    Defences to delay claims, including:

    force majeure clauses

    concurrent delay

    exclusion clauses

    A checklist for success

  • 7/29/2019 J2007 - Construction Law Report

    3/14

    CONSTRUCTION LAW REPORT Time is Money The Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 3 (416) 868-1080

    Where Delays Arise in a Condominium Project

    and Who May be Liable

    Delays can occur at any time and at more than one stage

    of development and construction of a condominium project.

    A delay at one step often leads to delays at other steps

    because the steps are so inter-dependent. Typical stages ofsuch a project include:

    The developer purchases land suitable for the

    project.

    A concept or design for the project is developed.

    The developer obtains the necessary zoning

    and development approvals from the municipal

    authorities.

    Tarion registration.

    Unit pre-sales.

    The developer obtains project financing.

    The project is constructed.

    Unit purchasers take interim occupancy.

    The condominium is registered.

    Final closing.

    a) Delays Caused by the Developer

    The relationship between a condominium unit purchaserand the developer, both with respect to delays and more

    generally, is governed by the terms of the Agreement of

    Purchase and Sale. For new condominium units, the Ontario

    New Home Warranty Program Act also sets out a regime

    of permissible delays and limitations on the purchasers

    potential claims on the basis of delay.1

    A contractor is entitled to assume that the work will be

    completed in the time provided for in the contract, and to

    arrange other projects accordingly. Even if the contract

    does not provide a specific completion date, the developer

    must not do, or fail to do, anything to delay the contactor

    in carrying out the work. A developer who causes delay by,

    for example, directing work to be performed in a sequence

    different than originally planned, imposing testing beyond

    what is necessary, or interferes in some similar fashion,

    could be liable for interference.2 Other examples of delay

    caused by the developer include:

    excessive changes in requirements or design;

    defective or insufficient plans;

    the failure to obtain necessary work permits; and

    the failure to provide or approve drawings in a

    reasonable time.

    Where some part of the construction must be carried out

    by or on behalf of the developer before the contractor can

    perform its work under the contract, any delay in the work

    amounts to a breach of contract for which the developer

    may be liable. However, if a contractor is delayed because

    other contractors have defaulted and the developer is

    not responsible for the delay, the developer will not be

    responsible for paying damages to the contractor arising

    from the delay unless the contract states that the developer

    must prevent such delays.3

    When the developer causes delay, it commonly grants an

    extension of time to the contractor to complete its work.

    If the contractor accepts the extension from the developer

    without claiming damages for the delay, this may amount to

    a waiver (or an acceptance) of the developers breach and

    may prevent the contractor from later claiming damages

    from the developer for delay.4

    b) Delays Caused by a Contractor

    A contractor who is responsible for delay in the completion

    of work will be in breach of its contractual obligations and

    may be liable to the developer for damages. A sufficient

    delay may also enable the developer to terminate the

    contract altogether.5 In addition to the contractors duty

    to perform the work pursuant to the terms of the contract,

    the contractor may have additional obligations under the

    contract, such as compliance with statutory rules and

    regulations and by-laws. If the contractor fails to fulfil these

    obligations, this constitutes a breach of contract.6 Other

    examples of delay caused by the contractor include:

    contractor management and performance

    problems;

    contractor management and performance

    problems;

    failure to properly staff the job;

  • 7/29/2019 J2007 - Construction Law Report

    4/14

    CONSTRUCTION LAW REPORTTime is MoneyThe Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 4 (416) 868-1080

    failure to order materials and equipment in a

    timely fashion; and

    the unavailability of labour, material or

    equipment.

    A contractor who incurs additional costs because of its

    own delay is not entitled to recover such costs from the

    developer.7

    If a contractor knows in advance that it will not be able to

    complete its work in a timely fashion, it may apply to the

    developer for an extension of time. If the developer grants

    the extension and the work is completed within the extended

    time period, the contractor will not be considered to have

    breached the contract. If the delay was solely the fault of

    the contractor, the developer is not required to grant an

    extension.8

    Standard form construction contracts have timelines

    that specifically address the issue of delay. For instance,

    General Condition 6.5 of the stipulated price contract in

    CCDC 2-1994 contains a specific delay section, attached

    as Appendix A.9

    c) Delays Caused by Subcontractors

    Delay caused by the subcontractors or the contractors

    suppliers is the contractors responsibility as far as the

    developer is concerned.10

    d) Delays Caused by Consultants

    If work performed by a consultant is not timely or is

    deficient, which leads to delay, the developer may have a

    claim in contract or professional negligence against the

    consultant. Examples of this are: design deficiencies, delay

    in approval of change work orders, and delays in payment

    certification.

    e) Delays by the Municipality

    Practically speaking, it may be difficult and expensive to

    successfully sue a municipality for causing development

    delays. However, Courts have held municipalities liable for

    delays in unique circumstances. An application can be made

    to Court under section 8 of the Building Code Act, 1992 to

    require issuance of a building permit or demolition permit.

    For instance, inAxelrod v. City of Toronto, the Court ordered

    a municipality to issue demolition permits to a developer

    after its refusal to do so without proper grounds.11

    Legal proceedings against a municipality will likely cause

    further delays given that the judicial process is frequentlyslow.

    f) Delays by the Lender

    The rights between a developer and its lender, typically

    a large financial institution, are governed by the lending

    commitment agreement between them. A developer may

    have limited contracting freedom with a lender as the

    lending agreements are frequently geared towards protecting

    the latters interests. Delays by a lender in making proper

    advances could result in a failure to pay contractors and

    the registration of construction liens. However, depending

    on the terms of the agreement, a developer may have a

    claim for breach of contract and damages for loss of profits

    in circumstances where the lender failed to abide by the

    terms of their agreement which results in project delays.

    For instance, in National Trust Co. v. Saks, the developer

    was successful in its claim against the lender for breach of

    contract when the latter wrongfully disregarded the terms of

    the loan agreement by demanding that the developer make

    cash equity injections to pay cost overruns.12

    Assessing Damages in Delay Claims

    The following section explores the topic of the computation

    of damages in delay claims and how notice provisions in

    the contract and the duty of the innocent party to mitigate

    its losses impact the claim. In addition, the significance of

    proper documents and expert evidence on delay claims is

    briefly reviewed.

    a) Notice Requirements: A Possible Precondition

    to a Damages Claim

    Construction contracts frequently require that a specific

    form of timely notice be given to the defaulting party as

    a precondition to preserving the innocent partys right to

    claim compensation for delay. It is essential that the notice

    requirements of a contract be strictly adhered to in order

  • 7/29/2019 J2007 - Construction Law Report

    5/14

    CONSTRUCTION LAW REPORT Time is Money The Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 5 (416) 868-1080

    to preserve the right to claim damages. Particulars must

    be given in a timely fashion so that the defaulting party is

    notified that a claim will be advanced against it for costs

    related to delays but has the opportunity to take protective

    measures.13

    b) When is a Party Entitled to Damages on the

    Basis of Delay?

    A delay can be categorized as excusable or non-

    excusable. To decide which category a delay falls into,

    the construction contract is reviewed first to determine

    whether it permits the delay and whether it provides for

    entitlement to compensation or an extension of time in the

    circumstances.

    An excusable delay is a delay for which the claimant

    is entitled to an extension in the contract time, or

    compensation for the delay, or both. If there is entitlement

    to compensation, as well as an extension in the contract

    time, the delay is a compensable excusable delay. If the

    claimant is only entitled to an extension of the contract time,

    the delay is a non-compensable excusable delay. Delays

    not caused by a party, such as acts of G-d, severe weather,

    and natural disasters such as floods or fires, are generally

    considered non-compensable excusable delays. When such

    delays occur, the developer typically is required to give the

    contractor an extension of time to perform the contract,

    but this does not permit the developer to make any claim

    for additional costs arising out of the delay, or to terminate

    the contract on that basis. A non-excusable delay is one

    for which the party is entitled to neither an extension in the

    contract time nor any monetary compensation.14

    The usual remedy sought by a party to a building contract

    is damages for breach of the contract. A claim for breach

    of contract may only be made against the party with whom

    the contract was made. If the breach is of such a naturethat there is a repudiation of the contract (ie: the breach

    goes to the root of the contract or there is a substantial

    failure of performance or the breaching party has indicated

    its intention to no longer be bound by the contract), the

    innocent (ie: non-breaching) party may elect to accept the

    repudiation and treat the contract as terminated by the

    breach. In these circumstances, the innocent party may

    recover damages for breach of contract, and the breaching

    party is excused from any further performance under the

    contract. The developer may terminate the contract and

    retain other forces to complete the contractors work.15

    However, if the innocent party does not accept the repudiation,

    the breaching party is not excused from further performance,

    and the innocent party can still claim damages for the

    breach of contract.16 Whether in any given circumstances

    the breach is sufficiently fundamental so as to amount to a

    repudiation is in each case a question to be determined in

    light of the particular terms of that contract.17

    c) Damages Arising From Delay

    In order to recover damages, the innocent party must be

    able to establish that there has been a breach of duty or

    contract, that it suffered a loss, and that the loss is a result

    of the breach of contract or negligence. The purpose of

    awarding damages is to put the injured party, as far as

    money can accomplish this, into the same position as if the

    innocent partys rights had not been violated.

    Typical heads of damage for a delay claim made by a

    developer include:

    additional construction costs

    overhead and carrying costs, such as interest andproperty tax during the period of delay

    liquidated damages (depending on the terms of

    the contract)

    diminution of value of the project

    loss of profits

    i) Foreseeability

    Even if a delay amounts to a breach of contract, not all

    damages are necessarily recoverable. Damages are only

    recoverable if they arise naturally from the breach or, in

    some circumstances, if they could reasonably have been

    within the contemplation of the parties when they entered

    into the contract. All other damages will be considered too

    remote. For instance, if a developer requires a building to be

    completed by a certain date, and its purpose is to generate

    income, a contractor who fails to complete its work in time

  • 7/29/2019 J2007 - Construction Law Report

    6/14

    CONSTRUCTION LAW REPORTTime is MoneyThe Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 6 (416) 868-1080

    will be liable to the developer for damages for loss of profits

    only if the contractor actually knew that the building was

    required for such purpose, or if that purpose was reasonably

    within the parties contemplation.18

    ii) Additional Construction CostsSince the purpose of a damages award is to grant full

    compensation, but not a windfall, if the developer is the

    innocent party, the cost of completing or correcting the work

    over and above the contract price is the proper measure

    of damages in many cases, especially when the contractor

    failed to perform the work. It is usually more expensive

    to call in another contractor during the course of work to

    complete it, and such additional costs must be paid by the

    defaulting contractor if the developer reasonably incurred

    such costs. In other cases, the proper measure of damagesis based on the loss in the value of the land.19

    iii) Loss of Profits

    Where a contractor can prove that it suffered a loss as a

    result of the developers breach, the measure of damages is

    the net loss occasioned by the breach.20 Where a contractor

    can establish that it has lost profit as a result of the owners

    breach of contract, it will be entitled to recover lost profit as

    damages.21 A contractor is also entitled to claim damages

    for idle equipment and for office overheads as a result of

    the delay. Further, if the scope of the contractors work

    is significantly changed by the owner during construction,

    the contractor will be entitled to the increased costs as

    damages.22

    Loss of profit claims are complex and usually involve an

    analysis of actual profits as against budgeted or projected

    profits. The question is how much profit would have been

    realized but for the delay. The analysis usually includes

    a discount for the risk that the projections might not have

    been achieved even if there were no delays.

    iv) Contract Limitations

    Many contract clauses provide that if there is a delay,

    recoverable damage will be computed in accordance with a

    particular formula or only using specified heads of recovery.

    In Goodfellows Trucking Ltd. v. New Brunswick, the Court

    ordered damages to be paid pursuant to the method selected

    by the parties and set out in the contract.23

    d) Supporting Documents

    Supporting documents are critical in proving that there

    was a delay, that it was caused by the Defendant, that thePlaintiff suffered compensable damages as a result of the

    delay, and that a particular measure of damages is proper

    in the circumstances.

    The following are suggestions of steps and documents

    that should be maintained throughout the course of the

    project:

    The developer should have a well-established

    project schedule and maintain accurate and

    timely records of all delays, as they occur, and

    how the delay impacted upon the project. This

    will assist the developer to corroborate any

    consequential losses resulting from the delay.

    Immediately put the responsible parties on

    notice of the need to comply with a specific

    deadline and that they will be held responsible

    for any delay.

    Keep clear and accurate records of all contracts

    related to the project.

    Maintain detailed accounting records since the

    losses will be financial.

    All staff involved in the construction project

    should keep detailed records of daily events

    during the course of construction.

    Photos and video footage showing the status of

    a construction project on any given day are often

    helpful in proving delay claims, as well as logs

    and journals which recorded details of events

    that transpired on site.

    Keep all correspondence, as well as written notes

    of discussions.

    Any problems related to delays in the

    construction schedule should be addressed during

  • 7/29/2019 J2007 - Construction Law Report

    7/14

    CONSTRUCTION LAW REPORT Time is Money The Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 7 (416) 868-1080

    meetings. Minutes of those meetings should be

    circulated to attendees for approval.24

    e) Expert Evidence

    In order to establish a claim for delay of any significant size,

    expert evidence will be necessary. It is strongly recommended

    that the expert be retained in the early stages of litigation

    so that the expert can assist in the preparation of pleadings,

    assist with the discovery process, assist counsel to prepare

    the case for trial, and appear as a witness at trial.

    At trial, experts are permitted to give evidence of the proper

    method to be adopted in assessing a delay claim as a matter

    of industry practice, and testify as to any exceptions to

    that method which should be made in the case. The expert

    may also express an opinion about the type of effect that is

    generally caused by the delay of one branch of a construction

    project upon other branches of the project. The expert can

    also provide factual evidence about construction techniques

    and practice.25 Expert accounting evidence will also be

    required to establish a loss of profit claim.

    f) Mitigation of Damages

    In the case of a breach of contract, the innocent party

    is required to mitigate (minimize) its damages by taking

    reasonable steps to protect itself from further loss. In other

    words, the innocent party must behave in a reasonablemanner with a view to ensuring that its damages resulting

    from the breach are as minimal as possible, which includes

    seeking the most economical and efficient way of making up

    for a delay. It may also include the least expensive method

    of returning the innocent party to the same position. For

    instance, the developer must attempt to replace a contract

    as quickly as possible where a contractor has failed to

    complete. The onus is on the party asserting that the

    innocent party has not mitigated its damages to prove that

    it did not do so.26

    The innocent partys failure to mitigatecould significantly reduce the damages ultimately awarded

    to it by the court.27

    Tips and Traps of Common Construction

    Contract Clauses: Strategies for Examining

    Contractual Terms

    The terms of the contract have clear implications on delay

    claims. For instance, what does the contract say about

    delivery dates? Are the dates firm? Does the contract maketime of the essence? Set out below is a brief analysis

    and practical tips regarding some common construction

    contract terms, including: exclusion clauses, penalty and

    liquidated damages clauses, time is of the essence

    provisions, arbitration clauses, as well as the effect of

    implied contractual terms.

    a) Exclusion Clauses/Disclaimers

    Construction contracts frequently contain clauses which

    attempt to limit or exclude a partys liability if certain eventsoccur. Often, a developer includes such a provision stating

    that in no, or only limited, circumstances will it be liable to

    the contractor. If a developer seeks to exclude its liability for

    delay in respect of its own breaches of contract, it may do

    so but it is mandatory that the disclaimer expressly provides

    that it includes the developers own breach of contract.

    Language such as the developer shall in no circumstances

    be responsible to the contractor for damages resulting from

    the delay of the contractors work operations has been

    found to be insufficient because it fails to include in express

    language the situation where the developer has breached its

    contractual obligations.28

    By contrast, in Perini Pacific Ltd. v. Greater Vancouver

    Sewerage & Drainage District (No. 2), the Supreme Court

    of Canada held that the addition of the more specific phrase:

    whether or not such delay may have resulted from anything

    done or not done by [the developer] under the contract was

    an effective exclusion clause as this was exactly the kind of

    loss which precluded the claim according to the language

    of the contract.29

    Because exclusion clauses and disclaimers are strictly

    construed, it is necessary that clear and unambiguous

    language be used. If there is ambiguity, an exclusion

    clause will be read strictly against the party for whose

    benefit it was inserted. Therefore, the best tool to attack an

    exclusion clause is to have it strictly construed against the

  • 7/29/2019 J2007 - Construction Law Report

    8/14

    CONSTRUCTION LAW REPORTTime is MoneyThe Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 8 (416) 868-1080

    interest of the party who put it forward, on the grounds of

    ambiguity.30

    There is no rule that necessarily invalidates an exclusion

    clause in the event of a fundamental breach or other type

    of breach of contract.

    31

    In deciding whether to enforcean exclusion clause in the face of a fundamental breach

    of contract, the court will decide whether doing so would

    be unconscionable or so unreasonable that the parties

    could not have intended this result. Unconscionability

    usually arises in situations where there is a vast disparity

    of contractual bargaining power between two parties to

    the contract so that the imposition of the disclaimer was

    essentially forced upon a party (usually the contractor) with

    no real commercial choice but to accept the term. Where

    there is equality of bargaining power, the courts will usually

    give effect to the bargain.32

    b) Penalty Clauses vs. Liquidated Damages

    Clauses

    Construction contracts sometimes contain clauses which

    provide for the payment of a stipulated sum of money per day

    for any delays in completing the work beyond the completion

    date in the contract. Such clauses may be characterized as

    either a liquidated damages clause or a penalty clause.

    Penalty clauses are void and unenforceable because a partycannot legally provide in a contract for the payment of a

    penalty.33 For example, a late payment clause of $1,500.00

    per day in a contract worth $59,000.00 to install new

    foundations and pillars and to replace 13 existing buildings

    on new structures was held to bear no relation to reality,

    nor was it a genuine attempt to make a pre-estimate of the

    damages likely to occur. It was therefore held to be a penalty

    clause and void.34

    Parties to a contract are, however, permitted to provide

    for a pre-estimate of damages which are likely to arise

    in certain circumstances and to agree on the payment of

    liquidated damages in such circumstances. In order for a

    liquidated damages clause to be considered valid, it must

    provide for payments which bear a relation to reality and

    must be a genuine attempt to make a pre-estimate of the

    damages which are likely to occur. The amount should not

    be excessive. Otherwise, the Court will view this as a penalty

    clause. Further, the developer will likely have to prove that

    it suffered actual damages in the amount of the claimed

    liquidated damages.35

    Liquidated damages provisions for delay in completion are

    inapplicable if the contractor never started the work underthe contract, as they apply only once work has begun.36

    c) Time is of the Essence Provisions

    Where a construction contract makes time of the essence,

    the breach of an obligation calling for performance at a

    specified time may amount to a breach of an essential

    element of the contract which can be treated by the innocent

    party as discharging the agreement and relieving against

    performance by the innocent party.37 In contracts where

    time is of the essence, even a 10-minute delay has been

    held to be a breach of this term.38Therefore, when a time is

    of the essence clause exists in a contract, strict compliance

    with time limits is imperative. Therefore, when a time is of

    the essence clause exists in a contract, strict compliance

    with time limits is imperative.

    d) Arbitration Clauses

    Construction contracts often contain arbitration clauses,

    such as the one set out in General Condition 8.2 of the CCDC

    Stipulated Price Contract, attached as Appendix A. It is

    strongly recommended that all contracts in a given project

    be consistent with respect to arbitration provisions. Either

    all project contracts should contain an arbitration clause, or

    none should have this clause. This consistency may prevent

    procedural problems and a multiplicity of proceedings given

    that section 7(1) of the Arbitration Act, 1991 provides that

    a court proceeding must be stayed in favour of arbitration

    when there is an agreement to arbitrate.

    Further, any arbitration clause contained in the construction

    contracts should specifically exclude arbitration where adeveloper has been sued and wishes to commence third

    party proceedings. Otherwise, the main action could proceed

    in court while the third party claim proceeds by arbitration,

    resulting in a multiplicity of proceedings and potentially

    inconsistent results.

    However, these concerns are not usually an issue when

    a developer has entered into a General Contract with a

  • 7/29/2019 J2007 - Construction Law Report

    9/14

    CONSTRUCTION LAW REPORT Time is Money The Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 9 (416) 868-1080

    general contractor. In this situation, the developer has no

    direct relationship with the subcontractors so any delay

    claims would be governed solely by the contract between

    the developer and the general contractor (and the developer

    would not need to bring claims against the subcontractors

    for delay).

    The prevalence of arbitration in construction cases (and

    other commercial cases) has lead to a dearth of recent

    reported court cases on these issues. While this may benefit

    the immediate parties (lower costs, speed and privacy), it

    deprives subsequent parties and their lawyers the benefit

    of guidance from decided case law.

    e) Implied Terms

    Since it is almost impossible to foresee all situations that

    may arise during the course of construction to provide for

    all of them in the contract, the court will sometimes have

    to imply a term to address a situation when the parties did

    not deal with it expressly.

    In the absence of an express provision in a contract, it is an

    implied term of a construction contract that the developer

    will do everything reasonable to allow the contractor to

    complete its work, such as making timely payments and

    refraining from interfering with the contractors work which

    may result in delay in its completion.39

    Defences to Delay Claims

    Depending on the circumstances, there may be some

    available grounds to reduce or eliminate a delay claim. Set

    out below is a brief analysis of some common defences:

    force majeure clauses, concurrent delay as a defence,

    and disclaimer clauses.

    a) Force Majeure ClausesFrustration of a contract occurs when its performance

    becomes impossible due to a supervening event caused by

    neither party, and not within their contemplation. Many

    condominium construction contracts contain a force

    majeure clause to address these situations. Section 6.5.2 of

    the CCDC-2 1994, set out in Appendix A, is an example

    of such a clause. If the event occurred without the clause

    in the contract, the contract would be frustrated and the

    parties no longer bound to perform their future contractual

    obligations.

    In order to rely on a force majeure clause as a defence

    to a delay claim, the circumstance which occurred should

    not have been foreseen and could not have been prevented.

    Strict compliance with the notice provisions set out in

    the contract has been held to be a condition precedent to

    invoking a force majeure clause.40

    b) Concurrent Delay

    Concurrent delay occurs when two or more causes of delay

    operate at the same time. If different parties are responsible

    for different concurrent delays, the court will generally

    assign a percentage of fault to each responsible party. A

    court will do the best it can to apportion responsibility on

    an estimated basis, on the basis of expert evidence. If the

    court cannot decide how to apportion the fault, an equal

    percentage of the blame will be assigned to each party.41

    Concurrent delay is frequently used as a defence to a delay

    claim. If a party can successfully assert a concurrent delay

    so that the court apportions the concurrent delay, the party

    might be able to reduce such a claim by the percentage of

    concurrent delay for which the claimant is responsible. Forinstance, in Alberta Engineering Co. v. Blow, the contractor

    brought an action for the balance of the contract owing. The

    owner counterclaimed for delay on the basis that the project

    was delivered several months after the agreed completion

    date and the owner lost rental income as a result. The

    contractor asserted that the owner was responsible for some

    concurrent delay. The court attributed over a quarter of the

    concurrent delay to the owner, thereby reducing the owners

    claim for rent.42

    Further, if a party can prove that an excusable but non-

    compensable delay ran concurrently with the compensable

    delay, the party can try to entirely defeat the delay claim

    on the grounds that the non-compensable delay overrides

    the compensable delay such that only an extension of time

    is permitted.43

  • 7/29/2019 J2007 - Construction Law Report

    10/14

    CONSTRUCTION LAW REPORTTime is MoneyThe Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 10 (416) 868-1080

    Proving a concurrent delay may reduce or defeat the delay

    claim even when the defending party is not asserting a delay

    claim itself.44

    c) Exclusion Clauses

    Exclusion clauses, also known as disclaimers, are a possibledefence to a delay claim, as set out above.

    Conclusion and Checklist for Success

    Preparation in advance is the key to a successful delay claim

    and will assist in the defence of any such claim. Below is

    a short checklist to assist the developer to prepare itself.

    These steps are summarized in greater detail above, and

    should be considered and, where applicable, undertaken

    from the outset of the project and on an on-going basis

    throughout the project:

    take care in the review and co-ordination of all

    project contracts;

    establish and maintain a project schedule;

    maintain records of construction progress;

    maintain proper accounting records;

    comply with all contractual notice provisions;

    act reasonably to mitigate losses; and

    be prepared to devote the time, attention and

    money necessary to win. Litigation is expensive

    and it may end up becoming the developers next

    project!

    APPENDIX A

    GC 6.5 DELAYS

    6.5.1 If the Contractor is delayed in the performance of

    the Work by an action or omission of the Owner,

    Consultant, or anyone employed or engaged by them

    directly or indirectly, contrary to the provisions of

    the Contract Documents, then the Contract Time

    shall be extended for such reasonable time as the

    Consultant may recommend in consultation with

    the Contractor. The Contractor shall be reimbursed

    by the Owner for reasonable costs incurred by the

    Contractor as the result of such delay.

    6.5.2 If the Contractor is delayed in the performance of

    the Work by a stop work order issued by a court

    or other public authority and providing that suchorder was not issued as the result of an act or

    fault of the Contractor or any person employed or

    engaged by the Contractor directly or indirectly,

    then the Contract Time shall be extended for such

    reasonable time as the Consultant may recommend

    in consultation with the Contractor. The Contractor

    shall be reimbursed by the Owner for reasonable

    costs incurred by the Contractor as the result of

    such delay.

    6.5.3 If the Contractor is delayed in the performance

    of the Work by labour disputes, strikes, lock-outs

    (including lock-outs decreed or recommended for its

    members by a recognized contractors association,

    of which the Contractor is a member or to which the

    Contractor is otherwise bound), fire, unusual delay

    by common carriers or unavoidable casualties, or

    without limit to any of the foregoing, by a cause

    beyond the Contractors control, then the Contract

    Time shall be extended for such reasonable time

    as the Consultant may recommend in consultation

    with the Contractor. The extension of time shall not

    be less than the time lost as the result of the event

    causing the delay, unless the Contractor agrees

    to a shorter extension. The Contractor shall not

    be entitled to payment for costs incurred by such

  • 7/29/2019 J2007 - Construction Law Report

    11/14

    CONSTRUCTION LAW REPORT Time is Money The Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 11 (416) 868-1080

    delays unless such delays result from actions by

    the Owner.

    6.5.4 No extension shall be made for delay unless notice in

    writing of claim is given to the Consultant not later

    than 10 Working Days after the commencement

    of delay, providing however, that in the case of a

    continuing cause of delay only one notice of claim

    shall be necessary.

    6.5.5 If no schedule is made under paragraph 2.2.9 of

    GC 2.2 - ROLE OF THE CONSULTANT [ie: the

    Consultant will furnish Supplemental Instructions

    to the Contractor with reasonable promptness or

    in accordance with a schedule agreed to by the

    Consultant and the Contractor], no claim for delay

    shall be allowed because of failure of the Consultant

    to furnish instructions until 10 Working Days after

    demand for such instructions has been made and

    not then, unless the claim is reasonable.]

    GC 8.2 NEGOTIATION, MEDIATION, AND

    ARBITRATION

    8.2.1 In accordance with the latest edition of the Rules

    for Mediation of CCDC 2 Construction Disputes,

    the parties shall appoint a Project Mediator

    .1 within 30 days after the Contract was

    awarded, or

    .2 if the parties neglected to make an appoint-

    ment within the 30 day period, within 15

    days after either party by notice in writing

    requests that the Project Mediator be ap-

    pointed.

    8.2.2 A party shall be conclusively deemed to have

    accepted a finding of the Consultant under GC

    2.2 - ROLE OF THE CONSULTANT and to have

    expressly waived and released the other party from

    any claims in respect of the particular matter dealt

    with in that finding unless, within 15 Working Days

    after receipt of that finding, the party sends a

    notice in writing of dispute to the other party and

    to the Consultant, which contains the particulars

    of the matter in dispute and the relevant provisions

    of the Contract Documents. The responding party

    shall send a notice in writing of reply to the dispute

    within 10 Working Days after receipt of the notice

    of dispute setting out particulars of this response

    and any relevant provisions of the ContractDocuments.

    8.2.3 The parties shall make all reasonable efforts to

    resolve their dispute by amicable negotiations and

    agree to provide, without prejudice, frank, candid

    and timely disclosure of relevant facts, information,

    and documents to facilitate these negotiations.

    8.2.4 After a period of 10 Working Days following

    receipt of a responding partys notice in writing

    of reply under paragraph 8.2.2, the parties shall

    request the Project Mediator to assist the parties

    to reach agreement on any unresolved dispute.

    The mediated negotiations shall be conducted in

    accordance with the latest edition of the Rules for

    Mediation of CCDC 2 Construction Disputes.

    8.2.5 If the dispute has not been resolved within 10

    Working Days after the Project Mediator was

    requested under paragraph 8.2.4 or within such

    further period agreed by the parties, the Project

    Mediator shall terminate the mediated negotiations

    by giving notice in writing to both parties.

    8.2.6 By giving a notice in writing to the other party,

    not later than 10 Working Days after the date

    of termination of the mediated negotiations under

    paragraph 8.2.5, either party may refer the dispute

    to be finally resolved by arbitration under the latest

    edition of the Rules for Arbitration of CCDC 2

    Construction Disputes. The arbitration shall be

    conducted in the jurisdiction of the Place of the

    Work.

    8.2.7 On expiration of the 10 Working Days, the

    arbitration agreement under paragraph 8.2.6 is not

    binding on the parties and, if a notice is not given

    under paragraph 8.2.6 within the required time,

    the parties may refer the unresolved dispute to the

  • 7/29/2019 J2007 - Construction Law Report

    12/14

    CONSTRUCTION LAW REPORTTime is MoneyThe Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 12 (416) 868-1080

    courts or to any other form of dispute resolution,

    including arbitration, which they have agreed to

    use.

    8.2.8 If neither party requires by notice in writing given

    within 10Working Days

    of the date of noticerequesting arbitration in paragraph 8.2.6 that

    a dispute be arbitrated immediately, all disputes

    referred to arbitration as provided in paragraph

    8.2.6 shall be

    .1 held in abeyance until

    (1) Substantial Performance of the Work,

    (2) the Contract has been terminated, or

    (3) the Contractor has abandoned the Work,

    whichever is earlier, and

    .2 consolidated into a single arbitration under

    the rules governing the arbitration under

    paragraph 8.2.6.

    Endnotes

    1. Ontario New Home Warranty Program Act, R.S.O.

    1990, c. O.31

    2. Immanuel Goldsmith and Thomas G. Heintzman,

    Goldsmith on Canadian Building Contracts, 4th

    (Toronto: Thomson Carswell, 1988) at 5-9

    3. Ibid.

    4. Esposito, Anna M. and Maria Tassou, Overview of

    Construction Delay Claims and Delay Damages in

    Construction Delay Claim: Following the Critical Path,

    Ontario Bar Association, Continuing Legal Education

    [CLE Program] (2006: Toronto, Ontario) at 3.

    5. Anderson Industrial Doors Ltd. v. Genstar Construction

    Ltd. [1985] CarswellBC 768 (B.C.S.C.)

    Supra, note 2 at 5-16

    6. Supra, note 2 at 5-18

    7. Josyln & Olsen Contractors Ltd. v. Bouey [1976]

    CarswellAlta 21 (A.C.A.)

    8. Supra, note 4 at 4

    9. CCDC stands for Canadian Construction Documents

    Committee, which is a joint committee comprised of

    owners and representatives of various institutes. The

    italicized terms are defined terms in the contract.

    10. Supra, note 2 at 5-17

    11. [1984] CarswellOnt 519 (Div. Ct.); (1984) 13 D.L.R.

    (4th) 634 (H.C.J.); varied at [1985] O.J. No. 2664

    (H.C.J.)

    12. [1998] CarswellOnt 2554 (O.C.A.)

    13. Supra, note 4 at 9

    W.J. Kenny, Cook Duke Cox (Edmonton-Calgary), Delay

    Claims at 37(source unknown)

    For further reading on the issue of the importance

    of timely notice on such claims, please see: Esposito,

    Anna M. and Maria Tassou, Overview of Construction

    Delay Claims and Delay Damages in Construction

    Delay Claim: Following the Critical Path, Ontario

    Bar Association, Continuing Legal Education [CLE

    Program] (2006: Toronto, Ontario) at 9 to 12.

  • 7/29/2019 J2007 - Construction Law Report

    13/14

    CONSTRUCTION LAW REPORT Time is Money The Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 13 (416) 868-1080

    14. Supra, note 4 at 2 and 3

    15. Torbray (Town Council) v. Metro Enrg. & Const. Ltd.

    (1980) 30 Nfld. & P.E.I.E. 298 (Nfld. T.D.)

    16. Supra, note 2 at 6-3 and 6-4

    17. Ibid, at 6-5

    18. Smith v. Tennant (1890), 20 O.R. 180

    Can. Foundry Co. v. Edmonton Portland Cement Co.

    (1918) CarswellAlta 157

    (P.C.).

    19. Supra, note 2 at 6-9 and 6-10

    20. Pendivic Contracting Co. v. International Nickel Co.

    [1975] CarswellOnt 299 (S.C.C.)

    21. Lowe v. Robb Engineering Co. [1905] CarswellNS 11(N.S.S.C.)

    22. Shore & Horowitz Construction Co. & Franki of

    Canada Ltd. [1964] CarswellOnt 70 (S.C.C.)

    23. [2003] CarswellNB 587 (N.B.Q.B.); affd at [2005]

    CarswellNB 411 (N.B.C.A.)

    24. Supra, note 4 at 12 and 13

    25. Cogar Estate v. Central Mountain Air Services Ltd.

    [1992] CarswellBC 305 (B.C.C.A.)

    26. W.J. Kenny, Cook Duke Cox (Edmonton-Calgary),

    Delay Claims at 41 (source unknown)

    27. Some cases which address the duty to mitigate and the

    effect of mitigation on a claim for damages are: Rice

    v. Sockett [1913] CarswellOnt 425 (O.C.A.); Sault

    Ste. Marie (City) v. Proctor & Redfern Ltd. [1986]

    CarswellOnt 785 (H.C.J.); and Westland Investment

    Corp. v. Carswell Collins Ltd. [1996] CarswellAlta 29

    (Alta Q.B.).

    28. Westcounty Construction Ltd. v. Nova Scotia [1985]CarswellNS 124 (N.S.T.D.)

    D.J. Lowe (1980) Ltd. v. Nova Scotia (Attorney

    General) [1993] CarswellNS 152

    Mueller, Warren H.O. Contractual Exclusion and

    Limitation of Delay Claims 47 C.L.R. (3d) 5 (2005)

    at 4 and 22 (note: page references are to ecarswell).

    For a lengthier discussion on this topic, please see this

    article at pages 3 and 4 (ecarswell).

    29. [1967] CarswellBC 187 (S.C.C.)

    30. W.J. Kenny, Cook Duke Cox (Edmonton-Calgary),

    Delay Claimsat 32 (source unknown)

    31. A fundamental breach can be defined as a breach going

    to the root of the contract, or one based on performance

    that is totally different from that which the contract

    contemplated.

    32. Syncrude Canada Ltd. v. Hunter Engineering Co.

    [1989] CarswellBC 37 (S.C.C.)

    W.J. Kenny, Cook Duke Cox (Edmonton-Calgary),

    Delay Claims at 32 (source unknown).

    Some other cases that have considered the effectof exclusion clauses in the context of construction

    delay claims are: Alden Contracting Ltd. v. Newman

    Bros. Ltd. [1997] CarswellOnt 3734 (Gen. Div.) and

    Summitville Consolidated Mining Co. v. Klohn Leonoff

    [1989] CarswellBC 697 (B.C.S.C.). For further reading

    on the topic of exclusion clauses, please see: Mueller,

    Warren H.O. Contractual Exclusion and Limitation

    of Delay Claims 47 C.L.R. (3d) 5 (2005).

    33. Covert v. Janzen (No. 2) [1908] CarswellSask 128

    (S.C.A.)

    Macdonald v. Northwest Biscuit Co. [1924]

    CarswellAlta 84 (A.C.A.)

    34. H.A.R. Construction Ltd. v. DeMerchant Construction

    [1989] CarswellNB 68 (N.B.Q.B.)

    35. Calgary v. Janse-Mitchell Const. Co. [1919]

    CarswellAlta 156 (S.C.C.)

    36. Lembke v. Chin Wing [1912] CarswellBC 208

    (B.C.S.C.)

    37. 1473587 Ontario Inc. v. Jackson [2005] CarswellOnt

    712 (S.C.J.); affd at [2005] CarswellOnt 3282

    (C.A.)

    38. Union Eagle Ltd. v. Golden Achievement Ltd., [1997]

    A.C. 514 (Hong Kong P.C.), referred to with approval in

    1473587 Ontario Inc. v. Jackson [2005] CarswellOnt

    712 (S.C.J.) and in Harris v. McNeeley (1998) 21

  • 7/29/2019 J2007 - Construction Law Report

    14/14

    CONSTRUCTION LAW REPORTTime is MoneyThe Condominium Developers Guide to Delay Claims JULY 2007

    Robins Appleby & Taub LLP 14 (416) 868-1080

    R.P.R. (3d) 291; affd at (2000) 47, O.R. (3d) 161

    (O.C.A.)

    39. W.J. Crowe Ltd. v. Pigott Construction Ltd. [1963]

    CarswellOnt 64 (S.C.C.)

    Smith v. Johnson Brothers Co. [1953] CarswellOnt

    100 (H.C.J.)

    W.A. Stephenson Construction (Western) Ltd. v. Metro

    Canada Ltd. [1987] CarswellBC 675 (B.C.S.C.)

    Supra, note 4 at 4 and 5.

    40. Some cases which have considered the effect of a force

    majeure clause are: Perini Pacific Ltd. v. Greater

    Vancouver Sewerage & Drainage District [1966]

    CarswellBC 182 (B.C.C.A.), affd at [1967] S.C.R. 189

    (S.C.C.) and World Land Ltd. v. Daon Development

    Corp. [1982] CarswellAlta 131.

    Supra, note 2 at 1-66.

    Supra, note 4 at 5 - 7.

    41. Korban Inc. v. Pigott Construction Ltd. [1993]

    CarswellOnt 825 (Gen. Div.)

    Supra, note 4 at 15

    For further reading on the subject of concurrent delay,

    please see: Grenier, Glenn. Evaluating Concurrent

    Delay - Unscrambling the Egg. 53 C.L.R. (3d) 46(2006).

    42. [1914] CarswellAlta 165 (Alta T.D.)

    Grenier, Glenn. Evaluating Concurrent Delay -

    Unscrambling the Egg. 53 C.L.R. (3d) 46 (2006) at

    8.

    43. Grenier, Glenn. Evaluating Concurrent Delay -

    Unscrambling the Egg. 53 C.L.R. (3d) 46 (2006) at

    8.

    44. Ibid, at 11

    provides expertise in all areas of business law

    including commercial real estate, municipal

    and property tax assessment, banking and

    insolvency law, tax law and estate planning,

    commercial litigation and corporate law.

    Irving Marks is the senior partner of

    thelitigation group. Irving has extensive

    experience in all aspects of business litigation

    in the superior and appellate courts.

    Barbara Green is a senior associate in the

    litigation group, focusing on commercial

    litigation with an emphasis on real property

    disputes, commercial leasing, condominium

    litigation, banking litigation and corporate

    disputes.


Recommended