+ All Categories
Home > Documents > Jacking Aker

Jacking Aker

Date post: 28-Nov-2015
Category:
Upload: ibnuhary
View: 90 times
Download: 3 times
Share this document with a friend
32
Confidential © 2013 Aker Solutions Preferred partner A continuous hydraulic jacking system High Performance Turbine Installation Vessel (HPTIV) Bergen, 10th Sept. 2013 Roy Martin Edvardsen | Aker Solutions Product Responsible, Offshore Jacking Systems
Transcript
Page 1: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Preferred partner

A continuous hydraulic jacking system High Performance Turbine Installation Vessel (HPTIV)

Bergen, 10th Sept. 2013

Roy Martin Edvardsen | Aker Solutions

Product Responsible, Offshore Jacking Systems

Page 2: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 2 13 September 2013

1. Introduction

Link:

Aker Solutions has developed a new concept of a

Jacking System for a Jack-Up vessel for

installation of offshore wind turbines.

■ Using a combination of:

truss legs, and

■ hydraulic pin&hole.

■ A joint-venture agreement with Wartsila, as the

ship designer, a concept of a High Performance

Turbine Installation Vessel (HPTIV) is designed. Jack-Up Leg

Jack-Up Cylinders

Locking Bolt Unit

Main Deck

Tween Deck VESSEL

HULL

Page 3: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 3 13 September 2013

2. Success factors and advantage:

■ Truss legs is a more light weighted structure, compared to

■ tubular legs of similar strength for leg sizes approx. 6x6x6 and upwards, - and also easy scalable.

■ For smaller legs than approx. 6x6x6, tubular legs might be more optimal.

Tubular legs: Truss legs:

Page 4: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 4 13 September 2013

■ A hydraulic pin&hole system is very reliable, robust, and cost optimal

■ compared to a rack and pinion system, especially for frequent use of

the jacking system. The design is based on the experience from our

drilling technology

■ In this case we have chosen design criteria for jacking to be

280times/year). This is not the case for oil&gas rigs.

Hydraulic cylinders: Rack & Pinion:

Page 5: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 5 13 September, 2013

3. Jacking concept

3.1. Animation HPTIV Animation 2: 8of12 (new)

3.2. Cylinders:

Cylinder sequences : Total 12 cylinders pr leg

■ 4:12 System (Leg Handling, leg up/down)

■ Double speed is then possible compared to 8:12,

decreasing lifting capacity – but we need to lift

“only” the weight of legs.

■ 8:12 System (Jacking, vessel up/down)

2 levels, 2 or 4 cylinders lifting at each corner

■ 12:12 System (Parking)

Increasing system holding capacity with 50%

compared to lifting with 8:12 – giving 48/32*26 717 =

40 106 tons.

6

5

4

3

2

1

12

11

10

9

8

7

Page 6: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 6 13 September, 2013

3.3. 8:12 System info:

■ By using 8 of 12 cylinders at all times a greater

total lifting force of 33% is then available,

compared to for instance 6 of 12.

■ Cylinder info: ■ cylinder bore Ø550mm

■ rod diameter of Ø330mm

■ 250 bar working pressure

■ 345 bar design pressure

■ => 605tons lifting capacity pr cylinder.

■ => Total lifting capacity of 605x32 =19360 tons.

■ 345 bar is available as capacity for impact loads in

«opposite direction», =345/250*19360 = 26 717 tons,

■ Loads above 345 bar will bleed of with a PSV

(Pressure Safety valve) – protecting the hydraulic

cylinders from pressure above 345 bar.

Page 7: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 7 13 September, 2013

3.4. RPD: Rack Phase Differential

■ Measuring RPD, is a good indicator of

brace loading for slender truss legs.

■ The HPTIV is designed with a plated

structure in between the chords instead

of braces on the top part of the legs that

are never exposed to wave slamming –

eliminating any RPD issues.

Page 8: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 8 13 September, 2013

3.5. Footing:

Independent Spud can is chosen, instead of mat footings, having an

advantage to be used on several types of seabed's.

One spike in center of the spud can intended for rocky seabed, and a

large taper surface for medium dense sand (soft soil) around the spike.

Page 9: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 9 13 September 2013

3.6. LBU detail:

A specially designed Locking Bolt Unit is designed for

the purpose.

The LBU is transferring the forces between the LEG and

the GUIDING TOWER.

Page 10: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 10 13 September, 2013

3.7. Chord cross section:

T=140mm

T=100mm

Page 11: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 11 13 September, 2013

4. HPU : Hydraulic Power Unit

Integrated HPU and hydraulic piping:

■ HPU’s at each leg, no piping in hull

■ 2 HPU’s pr leg is chosen, totally 8.

■ Guiding tower unit to be installed and tested before

installation at yard, reducing fabrication time.

■ One HP system (for working cylinders), and one LP

system (for returning cylinders) + drain line to tank.

■ Main components:

Motor

Oil Tank

Oil cooler

Piping Manifold

Pumps

Control System Cabinet

Page 12: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 12 13 September, 2013

4.1. Simplified calculation of HPU Power:

Lifting speed: 1.0m/min = 16.67mm/s

Energy = Work / Time = ( Force x Length) / Time

Energy [W] = Force [N] x Speed [m/s], P = F x v

Total HP HPU Power needed:

(incl efficiency 0.6=energy loss in pumps,piping,valves,friction)

P TOT=(19360*1000*10)/0.6x1.0/60)=5.38MW HP Power each leg (2HPU’s):1.34MW (670kW pr HPU)

Assuming 10% LP Power, increasing total

consumption to 1.5 MW pr leg, or 0.75 MW pr HPU, or

375 kW pr motor. If working pressure is increased above working pressure of 250 bar to

achieve extra lifting capacity, then the hydraulic flow (and jacking speed)

needs to be reduced similar.

Energy [W] = Pressure * Flow

Page 13: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 13 13 September, 2013

4.2. Hydraulic calc. of HPU’s:

Energy = Pressure x Flow, Energy [W] = Pressure [Pa] x Flow [m3/s]

Flow = Speed x Area, Q= v [m/min] x A [m2]

Q in-Lifting =8*Q jacking1.0-piston+4*Q return3.0-rod=8*237+4*456=1896(HP)+1824(LP)=3720l/min. pr. leg

Energy = P/10[bar] x Q*1000/60 [l/min]

Energy HP = 250/10 x (4legs*1896)*1000/60 =3.16 MW

Energy LP = 50/10 x (4legs*1824)*1000/60 =0.62 MW (LP-flow=3xHP-flow) Energy HP+LP = 3.16 + 0.62 = 3.78 MW for the total vessel

Total HPU Power pr. vessel = 5.2 MW pr. Vessel (incl efficiency HP=70%, LP=90%)

Energy VESSEL = 3.16/0.7 + 0.62/0.9 = 4.51+0.69= 5.2 MW Energy LEG = 5.2 / 4 = 1.3 MW pr leg

Energy HPU = 1.3 / 2 = 0.65 MW = 650 kW pr leg

With 2 engines for HPU,

325kW pr motor.

Hydraulic flow diagram,

Cylinders of Test Model 1:6:

Page 14: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 14 13 September, 2013

4.3. Guiding tower:

■ LBU at each chord, pinned to guiding

tower and

■ guided towards leg chords, removing

horizontal forces between guide tower

and legs.

■ Only VERTICAL forces are therefore

taken by hydraulic cylinders and guiding

tower.

Page 15: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 15 13 September, 2013

4.4. Guiding tower support structure:

■ Guiding tower are boxed in with a plated

guide tower support structure, taking all

■ HORISONTAL forces at upper and lower

guide points.

■ 2 purposes, weather shield AND strength

Page 16: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 16 13 September, 2013

5. Maintenance:

Guide support structure will be equipped

with suitable openings to be able to

replace cylinders and HPU pumps/motors

within 24hours.

Page 17: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 17 13 September, 2013

6. Video film and Test Model 1:6

Link

Page 18: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 18 13 September, 2013

7. Hydraulic & Control system

Test Model HMI:

A servo valve controls the

hydraulic flow from the HPU to

each side of a pair of jacking

cylinders, (handling 1 LBU).

A pair of locking bolt cylinders is

locking the LBU to the leg with

locking bolts.

The servo valve is controlled by a

servo controller integrated in a

Siemens PLC. (Siemens SIMATIC

Step 7 programming software).

The HMI runs on a Siemens

SIMATIC WinCC Flexible

platform on a panel PC with touch

screen.

Page 19: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 19 13 September, 2013

Virtual Master curve: (Simplified)

3 LBU*s are «slaves», following a virtual master

time curve, by position. All 3 LBU’s is moved in

vertical direction by 2 hydraulic cylinders.

One LBU is pushing (stroking out) 0%-50% stroke,

Second LBU is pushing (stroking out) 50%-100%,

Third LBU is pulling (stroking in) 100%-0%.

Page 20: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 20 13 September, 2013

Main Regulating Parameters:

Input parameters are cylinder

pressure (force) and cylinder

absolute position (stroke).

Proximity switches:

Proximity switches reading physical

vertical location of holes in the legs

(when to insert the locking bolt),

and prox’es reading physical

horizontal location if the locking bolt

is inserted in the leg or not (in/out).

Page 21: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 21 13 September, 2013

Full size vessel, HPTIV

Control center:

• The central Jacking HMI and PLC is located at

the bridge.

• Each leg shall have a setup with also local panels

and PLC on each leg

• A challenge for our system is to handle the

variable direction of load at touch down, when

vessel is going afloat, and cylinders switching

between pull and push !

Redundancy:

Redundancy of E&I hardware and signals will also

be an important part of the setup, having safety as

top priority when doing detailed control system

development for full size vessel with 4 legs.

Control Center

Page 22: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 22 13 September, 2013

8. HIL-simulation (Hardware-in-the-Loop)

- Real time simulation is used to reduce cost

and failure related to testing of our Jacking

system. We can vary the system algorithm

and easily test the system response with

different parameters – tuning the system to

meet function requirements.

- With Sim-X software we have built a

virtual physical model of the test model

size 1:6, controlled by the PLC developed

for the purpose.

- In workshop we are verifying our virtual

Sim-X model, in order to scale the virtual

system up to a full size HPTIV vessel !

Hydraulic jacking

Cylinders corner1:

Low Pressure

pump:

Locking

Bolt unit1:

Page 23: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 23 13 September, 2013

9. Operation criteria

■ 1 meter/min jacking speed might not be that important -

because pre-loading is a large portion of the total jacking time. ■ Power consumption is proportional to jacking weight & speed, and must be evaluated up against vessel

- case by case.

■ Hs (Sign. Wave Height) and Tp (Time Period) at specific location (Depth max

50m), defining percentage 1-year operation criteria is more interesting.

■ The HPTIV is designed to operate and install wind turbines in Hs=5, and

if needed, jacking further up to Survival position (18m air gap) in Hs=6,

instead of going to safe location (meaning jacking down and going afloat in Hs=2.5)

that would reduce the operating weather window.

Approx. 70%

Page 24: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 24 13 September, 2013

10. Global strength analysis

Design conditions: Basic code used is DNV-OS-J301

■ Installation condition (Hs=2.5, Tp max 7sec)

■ Operation condition (Hs=5)

■ Transit condition (Hs=6.5)

■ Survival condition (Hs=10)

Design software:

■ SESAM for package for all linear analyses

■ GTSTRUDL/SELOS for Non-linear dynamic installation analysis

■ TOWER for Time history dynamic analysis based on irregular and random sea

Page 25: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 25 13 September 2013

10.1 Survival

Plated field in top of legs requires the

vessel to be jacked up to maximum height

to withstand a SURVIVAL condition.

Self frequency of the system is approx. 8s,

and should preferably be outside 70%

operations of scatter diagram

For Hs= 2.5 Max Tp=7sec

Page 26: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 26 13 September 2013

10.2 Installation

DNV-RP-C104 is basis, But GTSTRUDL/SELOS is used for Non-linear dynamic

installation analysis, resulting in a more realistic approach

to the impact loads – and not that conservative.

Page 27: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 27 13 September, 2013

11. Strengths & weakness (pro’s & con’s)

PRO’s:

■ Reliable and Robust system for frequent jacking (280times/year)

■ Cost optimal and easy scalable for truss legs 6x6x6m-18x18x18m

■ Fabrication friendly, HPU to be fabricated and tested before yard.

■ Operational friendly, to withstand rough weather conditions.

■ Maintenance friendly (24h time limit for critical parts)

■ No fixation system needed

■ Aker Solutions Drilling expertise and mindset in delivery

CON’s:

■ No previous vessels (except one in late 70’s, but no info is available)

delivered with this type of combination.

■ A conservative mindset (=R&P) regarding the choice of jacking system

Page 28: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 28 13 September, 2013

12. Where are we, and what to do ahead ?

Status of technical solution:

We have established the concept for the mechanical design and

developed a master/slave control philosophy (sequence 8:12) for the

hydraulic system, and executed preliminary tests in workshop of the

same.

Planned work ahead:

More tests are necessary to log and verify the test model up against our

Sim-X simulation , to be able to scale the system doing simulations for

a full size vessel and manipulating the system for worst case scenarios.

This is planned finished by end of Q4 2013

Page 29: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 29 13 September 2013

13. Separated Installation and Supply

■ A new concept in addition to HPTIV is developed.

■ J-LASH is one Installation vessel, with several Barges and Tug

boats, for independent Supply of foundation structure, monopiles,

and wind turbines, severe reducing downtime for installation.

Page 30: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 30 13 September, 2013

14. Marked and planned activities in 2014:

The need of installation vessels is varying a lot and is up to clients !

We need a cooperation with a serious player or client, to continue

further into a basic/detail phase for a specific vessel ?

2013 GL Gerrard Hassan 2012 Douglas Westwood

Indicated 10 – 15 new

installation vessel / year Indicated Overcapacity until

2018 ?

Page 31: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Offshore Jacking Systems

OJS Slide 31 13 September, 2013

Thank you !

Page 32: Jacking Aker

Confidential © 2013 Aker Solutions Preferred partner

Copyright and disclaimer

Copyright Copyright of all published material including photographs, drawings and images in this document remains vested in Aker Solutions and

third party contributors as appropriate. Accordingly, neither the whole nor any part of this document shall be reproduced in any form nor

used in any manner without express prior permission and applicable acknowledgements. No trademark, copyright or other notice shall

be altered or removed from any reproduction.

Disclaimer This Presentation includes and is based, inter alia, on forward-looking information and statements that are subject to risks and

uncertainties that could cause actual results to differ. These statements and this Presentation are based on current expectations,

estimates and projections about global economic conditions, the economic conditions of the regions and industries that are major

markets for Aker Solutions ASA and Aker Solutions ASA’s (including subsidiaries and affiliates) lines of business. These expectations,

estimates and projections are generally identifiable by statements containing words such as “expects”, “believes”, “estimates” or similar

expressions. Important factors that could cause actual results to differ materially from those expectations include, among others,

economic and market conditions in the geographic areas and industries that are or will be major markets for Aker Solutions’ businesses,

oil prices, market acceptance of new products and services, changes in governmental regulations, interest rates, fluctuations in currency

exchange rates and such other factors as may be discussed from time to time in the Presentation. Although Aker Solutions ASA believes

that its expectations and the Presentation are based upon reasonable assumptions, it can give no assurance that those expectations will

be achieved or that the actual results will be as set out in the Presentation. Aker Solutions ASA is making no representation or warranty,

expressed or implied, as to the accuracy, reliability or completeness of the Presentation, and neither Aker Solutions ASA nor any of its

directors, officers or employees will have any liability to you or any other persons resulting from your use.

Aker Solutions consists of many legally independent entities, constituting their own separate identities. Aker Solutions is used as the

common brand or trade mark for most of these entities. In this presentation we may sometimes use “Aker Solutions”, “we” or “us” when

we refer to Aker Solutions companies in general or where no useful purpose is served by identifying any particular Aker Solutions

company.

OJS Slide 32 13 September, 2013


Recommended