+ All Categories
Home > Documents > Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no...

Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no...

Date post: 17-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
23
Japan - Renewed Opportunities Kasumi Yasukawa Kasumi Yasukawa National Institute of Advanced Industrial Science and Technology National Institute of Advanced Industrial Science and Technology (AIST) (AIST) GRC 2014, 29 September 2014
Transcript
Page 1: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

Japan - Renewed Opportunities

Kasumi YasukawaKasumi YasukawaNational Institute of Advanced Industrial Science and TechnologyNational Institute of Advanced Industrial Science and Technology

(AIST)(AIST)

GRC 2014, 29 September 2014

Page 2: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

Contents1. Before the nuclear accident in 20111. Before the nuclear accident in 2011••Geothermal Power PlantsGeothermal Power Plants in Japanin Japan••Geothermal PotentialGeothermal Potential in Japanin Japan••The reasons why there was no new GPP in Japan The reasons why there was no new GPP in Japan

2. Renewed opportunities2. Renewed opportunities••National ParksNational Parks••Hot SpringsHot Springs••CostsCosts••New DevelopmentsNew Developments

3. Summary3. Summary

2

Page 3: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

1. Before the nuclear accident in 20111. Before the nuclear accident in 2011-- Why there was no geothermal development? Why there was no geothermal development? --

3

Before the nuclear accident in 2011

Page 4: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

Ogiri1996-30MW

Otake 1967- 12.5MW

Kirishima Kokusai Htl 1996- 0.1MW

Takigami 1996- 25MW

Suginoi 1981- 3MW

Kuju 1998- 0.9MW

Geothermal Power PlantsGeothermal Power Plants in Japanin Japan17 geothermal power plants with 19 units (2000-2012)

HatchobaruHatchobaruⅠⅠ.1977.1977-- 55MW55MWⅡⅡ.2000.2000-- 55MW55MWBinary 2MWBinary 2MW 4

Yamagawa Yamagawa 1995.3 30MW1995.3 30MW

Mori GPP1982- 25MWOnuma GPP

1974- 9.5MW

Sumikawa1995- 50MW

Matsukawa GPPMatsukawa GPP19661966-- 23.5MW23.5MW

Kakkonda GPPⅠ.1978- 50MWⅡ.1996- 30MW

Onikobe GPP1975.3-12.5MW

YanaizuYanaizu--NishiyamaNishiyama19951995-- 65MW65MWHachijojima GPP

1999- 3.3MW

Uenotai1994- 28.8MW

1 MW≦

10MW≦

< 1MW

Before the nuclear accident in 2011

Page 5: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

Japan is the world’s 3rd largest geothermal potential country,

Country No. of active volcanoes

Geothermal potential (MWe)

Geothermal Power generation on 2010 (GWeh)

USA 160 30,000 16,603 Indonesia 146 27,790 9,600 Japan 119 23,470 3,064 Philippines 47 6,000 10,311 Mexico 39 6,000 7,047 Iceland 33 5,800 4,597

New Zealand 20 3,650 4,055

Italy 13 3,270 5,520

Number of active volcanoes & geothermal energy potential (Muraoka et al., 2008)

Geothermal potential in Japan Geothermal potential in Japan

but its power generation is merely No. 8 in the world……Why? Why?

Geothermal potential in this table is an estimated value from heat energy stored at a depth of geological basement or shallower.

5

Before the nuclear accident in 2011

Page 6: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

0

2'000

4'000

6'000

8'000

10'000

12'000

14'000

1946

1948

1950

1952

1954

1956

1958

1960

1962

1964

1966

1968

1970

1972

1974

1976

1978

1980

1982

1984

1986

1988

1990

1992

1994

1996

1998

2000

2002

2004

2006

2008

Year

Inst

alle

d C

umul

ativ

e C

apac

ity (M

W)

Geothermal power capacity of the worldBertani (2010)

800

600

400

200

(10M

W)

Geothermal power in Japan

6

Before the nuclear accident in 2011

The world’s geothermal power capacity is increasing constantly.

But no new GPP in Japan this century.WHY?WHY?

Page 7: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

All these strong points are common with nuclear power.Therefore, under the federal policy pushing nuclear power, lows and regulations which limits geothermal development had not been improved.

Low CO2 emissionHydro (11), Geothermal (13), Nuclear (20), Wind (24), PV (38), LNG (474, 599), Oil (738), Coal (943) g-CO2/kWh (CRIEPI, 2010)

Low COLow CO22 emissionemissionHydro (11), Geothermal (13), Nuclear (20), Wind (24), PV (38), LNG (474, 599), Oil (738), Coal (943) g-CO2/kWh (CRIEPI, 2010)

Stable power & High capacity factorNot depending on weather

Stable power & High capacity factorStable power & High capacity factorNot depending on weather

High energy return (generated power/used energy)Hydro (50), Geothermal(31), Nuclear (24), Oil(21) , Coal (17)

High energy return High energy return (generated power/used energy)(generated power/used energy)Hydro (50), Geothermal(31), Nuclear (24), Oil(21) , Coal (17)

Strong points of geothermal powerStrong points of geothermal power

The reasons why there was no new GPP in Japan The reasons why there was no new GPP in Japan

7

Before the nuclear accident in 2011

Page 8: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

3. CostThermal and nuclear power have been considered more cost effectiveso that GPP has not been attractive for electric power suppliers.

1. National Parks (no drillings, no researches)80% of the geothermal energy in Japan exist inside national parks where no exploitation has been allowed. Even scientific survey has been limited.

2. Hot springsSome hot spring owners make strong campaign against geothermal development in afraid of degradation of the springs (amount, quality).

How these things have been improved after the nuclear accident in 2011?

8

Before the nuclear accident in 2011

The reasons why there was no new GPP in Japan The reasons why there was no new GPP in Japan

Page 9: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

2. Renewed Opportunities2. Renewed Opportunities-- Recent movement after 3.11, 2011Recent movement after 3.11, 2011

9

Renewed Opportunities

Page 10: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

1. National ParksThe cabinet decided to mitigate restrictions on geothermal development in national parks, as a low CO2 emission energy source (June, 2010). Ministry of Environment (MOE) changed ordinance on national park in 2012.

Ordinance of the Ministry of the Environment1) Special Protection zone and Class 1 Special zone (SP and S1)The development is not admitted but the gravity or MT survey will be admitted,

which covers wide area. A deviated well drilling is not admitted.2) Class 2 and 3 Special zones (S2 and S3)The development is basically not admitted. Only deviated well drilling from

outside will be admitted if there is no effect on the surface. (November 2011)

The development is basically not admitted but it may be allowed if environmental consideration is well treated. (March 2012)

10

Renewed Opportunities

Page 11: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

Never enter!Never enter!(Even survey is prohibited)(Even survey is prohibited)

Surface Surface survey and survey and

small small scale scale

developmedevelopment may be nt may be allowedallowed

Special Protection zones

Class 1 Special zones

Class 2 Special zones

Class 3 Special zones

Ordinary Zones

Outside parks

11

Renewed Opportunities

1. National Parks It has been…

Page 12: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

Special Protection zones

Class 1 Special zones

Class 2 Special zones

Class 3 Special zones

Ordinary Zones

Outside parks

Surface Surface survey survey

may be may be allowedallowed

Small scale Small scale development development may be may be allowedallowed

Higher protection

12

DevelopDevelop--ment ment allowedallowed

Renewed Opportunities

1. National Parks Since March 2012 if enough environmental consideration is made,

Page 13: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

2. Hot springsThe only social problem that cannot be solved by laws and regulation. But...

The Ministry of Environment (MoE) made a new guideline on permission of geothermal drilling in March 2012, to be referred by local (prefecture) government, in order to avoid delay in giving permission.

Procedure for permission shown in the guideline

yes no

May geothermal development affect on shallow hot spring aquifer?

No information on their relation

Model exists on their relation

Monitoring data on their relation

Judgment by basic geo-scientific info.

Judgment based on the Model

Judgment based on Monitoring data

Existing information on relation between Geothermal Reservoir and hot spring

13

Renewed Opportunities

Page 14: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

3. CostThe Energy Agency of METI supports domestic geothermal businesses by :

●Financial support1.Drilling•Government’s support for geothermal drilling was to be abolished in FY2011. But after the big earthquake, government increased the budget from ~USD 15 to 90 million in FY2012. It covers up to 50 % of exploration well drilling costs.2. Public Acceptance•New budget for PA covers 100 % of PA activities by private sectors.3. RD&D (EGS, etc.)

●Feed in Tarif (FIT)FIT law for geothermal power was enacted and price is fixed in 2012.1.15 MW or bigger: 27.3 yen/kWh for 15 years 2. Smaller than 15 MW: 42 yen/kWh for 15 years.

Geothermal projects get double financial incentives from the government (drilling support and FIT).

14

Renewed Opportunities

Page 15: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

4. New developments

Private sectors (Industries)• Japan Geothermal Association (JGA) was established in Dec. 2012.

It consists of 49 companies and 3 organizations (dated May 2013), including metal developers, oil and gas developers, power supplier, trading companies, construction companies, turbine makers, plantmakers, geothermal consultants, drillings companies, and banks.

• Kawasaki Heavy Industry, KOBELCO, IHI, etc., began production of50-100 kW generator for small binary plants. Many local groups (municipal or hotel owners) show interests in such small GPP.

• Currently 44 or more exploration and/or development projects arerun by geothermal developers and local groups (see next page).

15

Renewed Opportunities

Page 16: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

Current projects (Explorations, evaluations and installations)

16

Map made by JGA

Activity Index

• 19 prospects over 10MW• 7 prospects 1MW-10MW• 18 prospects less than 1MW

(as of July 2014)

Higher number indicates higher subsurface temperature (expected).

Preceding projects (began before 2011)•TOHGEC group began exploration drilling in 2013 in Hachimantai, aiming at 10 MW GPP.•Yuzawa-Chinetsu Co. Ltd. (J-Power, MMC and Mitsubishi Gas) began environmental assessment in Wasabizawa geothermal field, aiming at 42 MW GPP in 2020.

Renewed Opportunities

4. New developments

Page 17: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

Higher number indicates higher subsurface temperature (expected).

Present geothermal power stations

17

Activity Index

• 12 areas, 14 units 10MW or bigger

• 3 + 1 units 1MW-10MW• 9 units less than 1MW

(6 are installed in 2014 and Abo Tunnel was in 2013)as of July 2014

Mori 25MW

Onuma 9.5MW

Sumikawa 50MWMatsukawa

23.5MW

Kakkonda50+30MW

Yanaizu-Nishiyama 65MW

Hachijojima 3.3MW

Uenotai 28.8MW

Yamagawa 30MW

Ogiri 30MW

Otake 12.5MW

Kirishima Kokusai Htl 0.1MW

Takigami 25MW

Suginoi 3MW

Kuju 0.9MWHatchobaru 55+55+2MW

Shichimi Spring 0.02MW

Abo Tunnel 0.003MWYumura Spring 0.03MW

Beppu Spring 0.5MWGoto-en 0.09MW

Hagenoyu 2MWOguni Matsuya 0.06 MW

LEGEND

(map made by JGA)

1 MW≦

10MW≦

< 1MW

Onikobe12.5MW

Ongoing projects•Some of these small plants have plans to enlarge capacity.•Abo Tunnel will have additional 2MW in 2015.•Goto-en will have additional 0.05MW by 2015.

Renewed Opportunities

4. New developments

Page 18: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

3. Summary• Renewable preference after the nuclear power plant accident

in March 2011 pushed Japanese government to support geothermal development.

• Financial incentives for geothermal developments, drilling support and FIT system are given by METI.

• New RD&D has begun supported mainly by METI (also by MOE and Reconstruction Agency).

• MOE released constrains for national parks. MOE made a new guideline on giving geothermal drilling permission to speed-up the process.

• Industries have moved forward to accelerate domestic geothermal developments. Currently 44 or more exploration and/or development projects are running.

18

Summary

Page 19: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

Geothermal study by AIST

• National Institute of Advanced Industrial Science and Technology (AIST) opened Fukushima Renewable Energy Institute (FREA) in April 2014.

• Geothermal studies by AIST, which used be done by geo-scientific units, would be mainly conducted in FREA.

19

Shallow Geothermal and Hydrogeology Team (SGHT)

Shallow Geothermal Shallow Geothermal and Hydrogeology and Hydrogeology Team (SGHT)Team (SGHT)

Hydrogen Energy Carrier Team

Renewable Energy Research Center (RERC)

Renewable Energy Renewable Energy Research Center (RERC)Research Center (RERC)

Fukushima Renewable Energy Institute AIST (FREA)Fukushima Renewable Energy Institute AIST (FREA)Fukushima Renewable Energy Institute AIST (FREA)

Solar Cell Technology Team

Wind Power Team

Energy Integration Team

Administration offices

Administration offices Universities

Institutes

Industries

Overseas

Universities

Institutes

Industries

Overseas

Collaboration

Other organizationsOther organizations

Geothermal Energy Team (GET)

Geothermal Geothermal Energy Energy Team Team (GET)(GET)

Renewed Opportunities

Page 20: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

Major projects by Geothermal Energy Team in FREA

BUDGET for FY2014 (April 2014- March 2015)*JOGMEC Project (Sponsored by METI)

AE monitoring in Yanaizu-Nishiyama (AE Mapping, Risk evaluation), ~USD 100,000*Japan-US collaboration project (Sponsored by METI)

Development of decision tree for hydro-fracturing process, ~USD 720,000* ERIA project (Sponsored by METI)

Sustainability Assessment of Utilizing Conventional and New-Type Geothermal Resources in East Asia, USD 65,000

* Local FS (Sponsored by Reconstruction Agency) 1-year projects to support FS by local firms in

area struck (Fukushima, Miyagi and Iwate prefectures), Max ~USD 300,000.

4 projects are currently conducted by Geothermal Energy Team.

Renewed Opportunities

5. Geothermal study by AIST

Page 21: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

Reference

21Map by JGA

Activity Index by Hayashi (1982)

Updated by Muraoka et al. (2008)

Activity Index

• What is Activity Index?

Higher number indicates higher subsurface temperature (expected).

Page 22: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

““Harmonious utilization of geothermal Harmonious utilization of geothermal energy with hot spring resourcesenergy with hot spring resources””- to avoid conflicts between hot spring owners and

geothermal developers -AIST had conducted a 3-year research project from FY2010 sponsored by MoE, consists of modeling, monitoring, and data integration for a whole subsurface system including hot spring aquifer.

22

Renewed Opportunities

2. Hot springs

Page 23: Japan - Renewed Opportunitiesgeothermal.org/Annual_Meeting/PDFs/Japan.pdf1. National Parks (no drillings, no researches) 80% of the geothermal energy in Japan exist inside national

A Kalina cycle enables power generation by ~85 C water. GERD and AIST have been conducting a demonstration project in Niigata sponsored by MoE.Many hot spring owners have interest in such small plants for their own use.

Hot spring source

To spa (bath)

To power line

Heat exchanger

turbineCooling tower

condenser

23

Low temperature binary systemLow temperature binary system

For utilizing local energy and reducing “geothermal allergy”of hot spring owners,

““Hot spring power plantHot spring power plant”” projectproject

Renewed Opportunities

2. Hot springs


Recommended