JESSICA Evaluation Study for Silesia
Katowice ul. Karłowicza 13
Tel: 32 730 2510, 32 730 2509, 32 730 2511
Fax: 32 730 2512, [email protected]
Developed for the European Investment
Bank
C i t y C o n s u l t i n g I n s t i t u t e
Page 2
Disclaimer
This report takes into account the particular instructions and requirements of our client. It is not
intended for and should not be relied upon by any third party and no responsibility is undertaken to
any third party.
This document has been produced with the financial assistance of the European Union. The views
expressed herein can in no way be taken to reflect the official opinion of the European Union.
City Consulting Institute Sp. z o.o.
C i t y C o n s u l t i n g I n s t i t u t e
Page 3
Table of Contents
1. Review of the market for urban regeneration projects in the Silesia region ................................ 14
1.1. Regeneration projects implemented in Silesia ...................................................................... 14
1.1.1. Financing sources of regeneration projects .................................................................. 14
1.1.2. Principles of financing regeneration projects ............................................................... 14
1.1.3. Formal conditions necessary to implement regeneration projects .............................. 16
1.1.4. Availability of resources for regeneration projects ....................................................... 18
1.1.5. Characteristics of the completed projects .................................................................... 19
1.1.6. Conclusions for JESSICA ................................................................................................. 26
1.2. Possibility of financing regeneration projects within ROP SL ................................................ 26
1.2.1. Project eligibility criteria ................................................................................................ 26
1.2.1.1. Formal conditions .................................................................................................. 26
1.2.1.2. Eligibility of costs ................................................................................................... 27
1.2.1.3. Beneficiaries .......................................................................................................... 29
1.2.2. Analysis of the existing lists of project selection criteria and indicators as regards their
relevance for JESSICA .................................................................................................................... 29
1.2.3. List of key potential projects to be implemented in the years 2010-2013 ................... 39
1.2.4. List of key projects financed after a restricted call of proposals ................................... 41
1.2.5. Conclusions for JESSICA ................................................................................................. 45
1.3. Analysis of strategic documents ............................................................................................ 45
1.3.1. Local Revitalisation Programmes .................................................................................. 45
1.3.2. Multi-annual Investment Plans ..................................................................................... 50
1.3.3. Conclusions for JESSICA ................................................................................................. 53
1.4. Identification and evaluation of specific potential JESSICA projects .................................... 55
1.4.1. Projects reported in a survey research ......................................................................... 55
1.4.2. Other potential projects ................................................................................................ 60
C i t y C o n s u l t i n g I n s t i t u t e
Page 4
1.4.3. Assessment of the interest of potential beneficiaries in a revolving financial instrument
60
1.5. SWOT analysis for JESSICA ..................................................................................................... 61
1.6. Conclusions for JESSICA ......................................................................................................... 63
2. Financial and social analysis for JESSICA implementation ........................................................... 64
2.1. Present financial instruments for urban regeneration projects ........................................... 64
2.2. Budgetary implications of JESSICA for the Silesia Managing Authority ................................ 74
2.2.1. Cash flow in case of the traditional donation system - variant 0 .................................. 75
2.2.2. Cash flow in case of JESSICA implementation – V1 – one UDF. .................................... 77
2.2.3. Cash flow in case of JESSICA implementation – V2 – 1 UDF created from the ROP and
investors (JST) funds. ..................................................................................................................... 83
2.2.4. Cash flow in case of JESSICA implementation – Variant 3 – HF, 2 UDFs from the ROP
and shareholders (JST, banks) funds. ............................................................................................ 89
2.2.5. Cash flow in case of JESSICA implementation – Variant 4 – 1 HF/EIB and >2 UDFs
created from the ROP and shareholders’ funds (JST, banks). ....................................................... 96
2.3. Non-budgetary effects of JESSICA implementation ............................................................ 104
2.4. PPP as a method of optimising the JESSICA implementation process. ............................... 105
2.5. Summary. Conclusions for JESSICA implementation. .......................................................... 112
3. Institutional analysis of JESSICA implementation. ...................................................................... 114
3.1. Description of potential market participants in JESSICA. .................................................... 114
3.1.1. Public administration................................................................................................... 114
3.1.2. Public institutions ........................................................................................................ 118
3.1.3. Financial sector institutions ......................................................................................... 122
3.1.4. Private sector ............................................................................................................... 126
3.2. Ability and willingness of the private and public sectors to support urban regeneration in
Silesia through JESSICA .................................................................................................................... 131
3.2.1 Conclusions: willingness to engage in JESSICA projects and institutional structure of the
Programme. ................................................................................................................................. 134
3.3. Analysis of institutional models of JESSICA operation ........................................................ 136
C i t y C o n s u l t i n g I n s t i t u t e
Page 5
3.3.1 Potential JESSICA organizational structures ................................................................ 136
3.3.2. Establishment of a Holding Fund ................................................................................. 139
3.3.2.1. Basic tasks of holding funds (HF) ......................................................................... 145
3.3.2.2. Benefits resulting from the HF establishment..................................................... 147
3.3.2.3. Entities that may potentially establish a HF ........................................................ 147
3.3.3. Establishment of Urban Development Funds ............................................................. 152
3.3.3.1. UDF business models ........................................................................................... 156
3.3.3.2. UDF operating as a credit – guarantee institution .............................................. 156
3.3.3.3. UDF operating as a capital investor ..................................................................... 157
3.3.4. HF/UDF model ............................................................................................................. 157
3.3.4.1. Advantages and disadvantages of the full model of JESSICA implementation. .. 158
3.3.5. One UDF model ........................................................................................................... 159
3.3.5.1. Conditions and advantages of the one UDF model ............................................. 159
3.3.5.2 Institutions that may establish one UDF ..................................................................... 160
3.3.6. Institutional model and project financing possibility .................................................. 162
3.3.6.1. One UDF model ................................................................................................... 162
3.3.6.2. HF and 2 UDFs model .......................................................................................... 162
3.3.6.3. HF and a greater number of UDFs ....................................................................... 162
3.3.6.4. EBI involvement and possibility of project financing ......................................... 163
3.3.7. Institutional model and participation ability ............................................................... 163
3.3.7.1. One UDF model ................................................................................................... 163
3.3.7.2. HF and 2 UDFs model .......................................................................................... 163
3.3.7.3. HF and a greater number of UDFs ....................................................................... 163
3.3.7.4. EBI and a possibility of other entities involvement ............................................. 163
3.3.8. Institutional model and PPP ........................................................................................ 164
3.3.8.1. One UDF model ................................................................................................... 164
3.3.8.2. HF and 2 UDFs model .......................................................................................... 164
3.3.8.3. HF and a greater number of UDFs ....................................................................... 164
C i t y C o n s u l t i n g I n s t i t u t e
Page 6
3.3.8.4. EBI involvement and PPP ..................................................................................... 164
3.4. Comparison and evaluation of different institutional models of JESSICA implementation 165
3.4.1. Analysis of advantages and disadvantages resulting from entrusting the EIB with the
HF function .................................................................................................................................. 169
3.4.2. Recommendations for the Śląskie Voivodship ............................................................ 170
3.4.2.1. Recommendations concerning the Holding Fund establishment ....................... 170
3.4.1.1. Recommendations concerning the number of UDFs .......................................... 171
3.4.1.2. Recommendation concerning organisational changes in time. .......................... 172
4. JESSICA implementation strategy in Silesia ................................................................................. 174
4.1. Recommendations on how JESSICA should be taken forward in Silesia in short-, medium-
and long-term perspective .............................................................................................................. 174
4.2. JESSICA implementation methodology ............................................................................... 175
4.3. Indicative timeline of the new structure implementation .................................................. 176
4.4. Potential risks for the Managing Authority ......................................................................... 177
4.4.1. Managing Authority’s financial obligations resulting from RPO SL ............................ 177
4.4.2. State aid and project sustainability issues .................................................................. 179
4.5. Recommendations............................................................................................................... 181
C i t y C o n s u l t i n g I n s t i t u t e
Page 7
Index of tables
Table: Financing sources of regeneration projects in Silesia until 2008. .............................................. 14
Table: Principles of financing regeneration projects ............................................................................. 14
Table: Formal conditions necessary to implement regeneration projects ........................................... 17
Table: Basic formal limitations influencing the adopted regeneration development directions ......... 18
Table: Availability of resources for regeneration projects .................................................................... 18
Table: Regeneration projects implemented in Silesia ........................................................................... 20
Table: Basic types of projects ................................................................................................................ 28
Table: Product and result indicators ..................................................................................................... 32
Table: Key potential regeneration projects (years 2010 – 2013) .......................................................... 39
Table: List of key projects financed after a restricted call of proposals ................................................ 42
Table: Strategic planning model ............................................................................................................ 47
Table: Budgeting in a self-government entity ....................................................................................... 52
Table: Analysis of selected projects ...................................................................................................... 58
Table: The EIB funds for regional development. ................................................................................... 67
Table: Maximum value of financial support from the Surcharge Fund. ............................................... 69
Table: Summary of the objective, value, crediting period and interest rate of TBS Programme loans.73
Table: Analysis assumptions – V0. ......................................................................................................... 75
Table: Cash flow for subsiding mechanisms of the ROP SL (in million PLN) ......................................... 75
Table: Financial flow for the subsiding mechanism of the ROP SL in PLN (V0). .................................... 76
Table: Analysis assumptions – V1. ......................................................................................................... 77
Table: Advantages and disadvantages of V1. ........................................................................................ 78
Table: Financial flows for variant 1 [million PLN] - V1. .......................................................................... 79
Table: Analysis assumptions– V2 .......................................................................................................... 83
Table: Advantages and disadvantages of V2. ........................................................................................ 84
Table: Financial flow for variant 2 [million PLN] – V2. .......................................................................... 85
Table: Analysis assumptions – V3. ......................................................................................................... 89
Table: Advantages and disadvantages of V3. ........................................................................................ 90
Table: Financial flow for Variant 3 [million PLN] – V3. .......................................................................... 91
Table: Analysis assumptions – V4. ......................................................................................................... 96
Table: Advantages and disadvantages of V4. ........................................................................................ 97
Table: Financial flow for Variant 4 (million PLN) - V4. ........................................................................... 99
Table: PPP objectives. .......................................................................................................................... 106
C i t y C o n s u l t i n g I n s t i t u t e
Page 8
Table: Conclusions for PPP implementation ....................................................................................... 109
Table: Critical factors of PPP from the JESSICA perspective. .............................................................. 110
Table: Opportunities for cooperation in PPP with JESSICA support. .................................................. 111
Table: Potential engagement of public administration units in JESSICA. ............................................ 114
Table: Potential engagement of public institutions into JESSICA. ....................................................... 118
Table: Engagement of the financial sector in JESSICA. ........................................................................ 122
Table: Analysis of ability and willingness to implement projects financed within the JESSICA frame.
............................................................................................................................................................. 132
Table: Units’ engagement on project level. ........................................................................................ 133
Table: Interest in engaging in JESSICA projects. .................................................................................. 134
Table: Model: HF (EIB) + UDF .............................................................................................................. 137
Table: Model HF + UDF ........................................................................................................................ 138
Table: Model UDF ................................................................................................................................ 138
Table: Choosing the HF operator in accordance with the Public Procurement Law. ......................... 144
Table: Entrusting HF management to the EIB. .................................................................................... 145
Table: The Upper Silesian Fund – advantages and disadvantages ...................................................... 147
Table: EIB – advantages and disadvantages ........................................................................................ 149
Table: Advantages and disadvantages of the full JESSICA implementation model. ........................... 158
Table: Comparative analysis of chosen organizational models. ......................................................... 165
Table: Comparative analysis of chosen organizational models – financial aspect.............................. 166
Table: Analysis of advantages and disadvantages of chosen organizational models. ........................ 167
Table: Organizational model with the HF involvement. ...................................................................... 172
Table: Recommendations for JESSICA ................................................................................................. 173
Table: Main problems that may be encountered throughout JESSICA implementation .................... 175
C i t y C o n s u l t i n g I n s t i t u t e
Page 9
List of Acronyms
BGK Bank Gospodarstwa Krajowego
CEB Council of Europe Development Bank
Consultant City Consulting Institute Sp. z o.o.
EC European Commission
EIB or Bank European Investment Bank
ERDF European Regional Development Fund
GZM Metropolitan Association of Upper Silesia (Górnośląski Związek Metropolitalny)
HF Holding Fund
IA Implementing Authority
IRDOP Integrated Regional Development Operational Programme (Polish: ZPORR)
IUDP Integrated Urban Development Plans / Programmes
JESSICA Joint European Support for Sustainable Investment in City Areas
JST Territorial self-government units
KFM, NHF Krajowy Fundusz Mieszkaniowy (National Housing Fund)
LRP Local Regeneration Plan / Programme
MA Managing Authority for a Regional Operational Programme
MIDF The Municipal Investment Development Fund
MRR Ministry of Regional Development
NBP National Bank of Poland
NFEPWM National Fund for Environmental Protection and Water Management
PPP Public-private partnership
Region Śląskie Voivodship
Report Report prepared according to the consultancy contract with EIB
ROP Regional Operational Programme
ROP SL Śląskie Regional Operational Programme
SDPSV Spatial Development Plan of the Silesian Voivodship
SF Surcharge Fund
TBS Towarzystwa Budownictwa Społecznego (Social Housing Societies)
The Study,
Project
Advisory project named ‘JESSICA Evaluation Study for Silesia.
UDF Urban Development Fund
UMSL Marshal Office of Śląskie Voivodship (regional government of Silesia)
C i t y C o n s u l t i n g I n s t i t u t e
Page 10
Introduction
The JESSICA Evaluation Study for Silesia has been contracted by the European Investment Bank and
developed by experts of City Consulting Institute Sp. z o.o.
The Study has been conducted with reference to regional conditions, in cooperation with all Silesian
self-governments.
The analysis has been possible thanks to the commitment of representatives of the Department of
Regional Development of the Marshal Office of the Śląskie Voivodship.
JESSICA is a chance for further dynamic development of the region. The possibility of financing
projects from revolving mechanisms is welcomed by self-government authorities as well as by
entrepreneurs. JESSICA may be also a chance for the development of public – private partnerships
and an initiative promoting interesting projects.
Mateusz Górka
Chairman of City Consulting Institute Sp. z o.o.
C i t y C o n s u l t i n g I n s t i t u t e
Page 11
Summary
Chapter Summary
Review of the
market for urban
regeneration
projects in the
Silesia Region
The market of regeneration projects in Silesia has been shaped primarily by
the guidelines of the Integrated Regional Development Operational
Programme. Beneficiaries (mostly communes) willing to apply for a grant,
adapted their projects and Local Revitalization Programmes to the guidelines.
In result, most projects were non-profit, limited to visual and functional
development of city centres, buildings or post-industrial areas.
The most interesting projects have been financed primarily from own
resources of the investors.
The present guidelines on regeneration are more liberal and most projects are
thus eligible. However, it is still obligatory to calculate the funding gap which
may in turn result in financing non-profit projects, similar to those
implemented within IRDOP.
In case of JESSICA, it is not obligatory to calculate the funding gap. Co-financed
projects may be thus much more interesting.
Present ROP SL guidelines concerning revitalization are coherent with JESSICA
regulations. There is thus no need to introduce any changes to eligibility
criteria, types of projects or product and result indicators.
Financial and social
analysis for
JESSICA
implementation
Financial and economic analysis of possible JESSICA implementation options
has been developed on the basis of the following criteria:
data from potential beneficiaries (possible engagement in JESSICA,
institutional analysis and financial conditions of participation in
UDFs);
ratio analysis resulting from a review of documents concerning
JESSICA elaborated so far.
In result of the analysis of possible variants of JESSICA implementation in
Silesia it should be stated that the optimum solution is to implement the
option: HF + >3 UDFs + shareholders (self-government entities, banks). Higher
number of UDFs results in the so called leverage effect, consisting in the ability
of encouraging public (self-government entities) and private (banks) sectors to
contribute shares to UDFs. Higher JESSICA resources will in turn result in the
C i t y C o n s u l t i n g I n s t i t u t e
Page 12
possibility of financing a greater number of projects and continuous increase
of the UDF value (e.g. by profit from interest rates).
Institutional
analysis of JESSICA
implementation
Institutional analysis has been elaborated with regard to the binding home
and Community law as well as interministerial arrangements concerning
financial mechanisms similar to JESSICA.
The analysis has taken into account all institutions whose participation in
JESSICA would be possible from the financial or institutional point of view.
The analysis has proven that taking into account the present institutional
conditions as well as the time remaining to the end of the programming
period 2007-2013, the only solution that may have considerable impact on
regional development is the model based on the institutional division of the
HF and the UDF. In order to minimise the risk for the Marshal Office, it is
recommended to base the HF on EIB structures.
After the year 2013, one should consider the purposefulness of further HF
operation or handing over its operation to a local entity.
JESSICA
implementation
strategy in Silesia
Efficient JESSICA implementation necessitates the following actions:
Establishment of a HF within EIB structures (no need to apply the
public procurement procedure, EIB experience, advantageous
financial conditions as well as experience of other countries prove that
this institutional solution is the best possible one).
Initial establishment of two UDFs (financial and investment ones).
Preparing potential beneficiaries in the following areas:
o information (knowledge on JESSICA is still very poor, a number
of trainings and information campaigns should be organised);
o technical (the most considerable problem seems to be the lack
of Integrated Urban Development Plans that are necessary in
order to apply the systemic approach to revitalization and
prove the impact of a particular project on other projects to
be implemented in the area. As JESSICA encourages public –
private partnership, it would seem necessary to implement
PPP Implementation Plans, facilitating the contracting
procedures).
Implementation of a JESSICA application system as well as control and
monitoring procedures.
C i t y C o n s u l t i n g I n s t i t u t e
Page 13
Conclusions Revolving financial mechanisms are welcomed by the market. Due to the
character of the EU granting system, most regeneration projects are of social,
non-profit character. There is a need on the market to implement projects
that may become local development factors in the area of revitalization.
Large number of potential JESSICA projects and advanced stages of technical
plans development are considered the major success factors. Problems
include legal issues and know-how of potential beneficiaries.
A cycle of trainings on JESSICA should be organised, Integrated Urban
Development Plans and PPP Implementation Plans should be developed in
order to implement the future JESSICA projects efficiently.
C i t y C o n s u l t i n g I n s t i t u t e
Page 14
1. Review of the market for urban regeneration projects in the Silesia
region
1.1. Regeneration projects implemented in Silesia
1.1.1. Financing sources of regeneration projects
The beginning of the regeneration process in Silesia is related with the possibility of applying for
European Union funds within the Integrated Regional Development Operational Programme in the
years 2004 – 2006r.
All previous efforts of local authorities in this respect had been standard investment actions resulting
from current needs or development programmes other than Local Revitalization Programmes.
Table: Financing sources of regeneration projects in Silesia until 2008.
1.1.2. Principles of financing regeneration projects
General principles of financing regeneration projects have been presented in the table below:
Table: Principles of financing regeneration projects
Grants Source General co-financing principles
IRDOP General principles of financing were the following:
75% - ERDF
10% - state budget
15% - own resources (including loans/credits)
EEA FM Two regeneration projects have been financed within the EEA FM in
grants
• IRDOP;
• ROP;
• EEA FM;
• ministry funds;
• voivodship contracts;
loans
• commercial banks;
• EIB;
own resources
• total financing;
• co-financing;
C i t y C o n s u l t i n g I n s t i t u t e
Page 15
Silesia:
Revitalization of the Old Castle Complex and the Habsburg
Park in Żywiec
Protection and conservation of written heritage of Cieszyn
General principles of financing were the following:
up to 85% - the Donor Countries
15% - own resources (including loans/credits)
ROP SL General principles of financing are the following:
85% - ERDF
15% - own resources (including loans/credits)
Due to the fact that the call of proposals has been witheld and
projects are selected only within the Subregional Development
Programmes of the ROP 2007 – 2013, their implementation has only
just started.
Other A number of projects have been financed from the resources
granted by regional or national authorities. Thermal efficiency and
water and sewage management projects have been co-financed
from the resources of the National and the Regional Environment
Protection Funds.
A few projects have been also co-financed within INTERREG 3A.
Loans Most projects have been co-financed by loans. This fact resulted from the following:
necessity of providing own resources [in case of refunding, loans ensured financial
liquidity of beneficiaries];
necessity of covering the difference between the sum applied for and the real
project cost [project evaluation periods were relatively long and during that time
exchange rate differences as well as price increase occurred];
Some beneficiaries financed regeneration projects by loans only [this solution was most
frequently applied by municipal companies or entrepreneurs implementing profitable
projects].
Own resources Financing projects partially from own resources took place in case of all projects co-
financed by the European Union. The share of own resources in case of projects co-
C i t y C o n s u l t i n g I n s t i t u t e
Page 16
financed by loans was determined by bank contract conditions. Projects implemented
solely from own resources occurred rarely. However, some local authorities decided to
choose this solution.
With regard to the above compilation, it should be stressed that most regeneration projects in Silesia
have been co-financed from the European Union resources [IRDOP]. Limitations resulting from the
IRDOP application guidelines have strongly influenced the character of the projects and defined
regeneration directions to be continued for many years.
1.1.3. Formal conditions necessary to implement regeneration projects
The beginning of the process of implementing regeneration projects in Silesia was undoubtedly
related with the possibility of applying for the resources from the Integrated Regional Development
Operational Programme (Polish acronym: ZPORR). According to the guidelines defined by the
Programme Complement to the Integrated Regional Development Operational Programme for the
years 2004 – 20061 and Revitalization Guidelines2 it was necessary to develop a Local Revitalization
Programme in order to meet the formal conditions of applying for EU resources. The general scope of
a Local Revitalization Programme was defined in an Appendix to IRDOP.
First Local Revitalization Programmes were developed mostly in order to meet the formal criteria.
These were frequently analyses based on minimum eligibility criteria, pointing only the projects to be
potentially co-financed. That in turn caused the present situation in which many representatives of
local governments see a Local Revitalization Programme as a strategic document of poor
functionality and not as an important spatial document determining the development of degraded
areas.
1 Programme Complement to the Integrated Regional Development Operational Programme for the years 2004 – 2006 (appendix to the
resolution of the Minister of Economy and Labour of 25 August 2004 on the adoption of Programme Complement to the Integrated Regional Development Operational Programme, Offical Gazzette No 200, item 2051)
2 Revitalization Guidelines, Principles, Procedures and Methods of Contemporary Revitalization Processes (Polish: Podręcznik Rewitalizacji, Zasady, procedury i metody działania współczesnych procesów rewitalizacji), 2003, GTZ Gesellschaft für Technische Zuzammenarbeit i Urząd Mieszkalnictwa i Rozwoju Miast, Warszawa.
C i t y C o n s u l t i n g I n s t i t u t e
Page 17
Table: Formal conditions necessary to implement regeneration projects
The above scheme of regeneration project implementation was characteristic to most Silesian
gminas applying for IRDOP grants.
Perceiving a Local Revitalization Programme as an appendix necessary to meet the formal criteria of
project evaluation processes results in development of Local Revitalization Plans in isolation from
urban development procedures. The document is thus called a development plan but the projects
included in it do not have to be coherent and integrated with each other in any way (apart from
location).
Application Form
Together with a feasibility study and other appendices (including LRP), an application form was the document enabling local government bodies to apply for an IRDOP grant.
Strategic documents
Development of strategic documents was primarily aimed at meeting the formal criteria. In many cases, local government bodies adapted their LRP to the contents of a technical plan and to feasibility
study analyses.
Technical plans, licences, permits
Technical plans and building permits were obligatory in order to apply for IRDOP grants; in result only those projects were financed that had been previously planned and included in the required strategies;
C i t y C o n s u l t i n g I n s t i t u t e
Page 18
Table: Basic formal limitations influencing the adopted regeneration development directions
1.1.4. Availability of resources for regeneration projects
Resources for regeneration projects implemented in Silesia have been and still are considerably
limited. It is only possible to implement projects in two basic forms, both having advantages and
disadvantages.
Table: Availability of resources for regeneration projects
•the area on which a particular project is to be implemented should be the property of the beneficiary; ownership
right
•project should by design be non-profitable;
•no possibility of implementing projects within PPP (legislative errors);
project profitability
•projects located only within administrative borders of cities;
•post-industrial areas;
•post-military areas; location
•little resources compared to demands;
•limited scope/value of a project aimed at increasing chances for a grant;
financial limitations
grant
• possibility of financing only 85% ofproject value from external resources;
• complicated procedure of applying,settling and monitoring projects;
• necessity of ensuring projectsustainability;
• necessity of monitoring the assumedindicators;
• necessity of participating in a call ofproposals [the value of applicationsfiled exceeds several times the value ofavailable resources];
own resources / loans
• possibility of financing any project;
• possibility of financing profitableprojects;
• simple system of financial settlement;
C i t y C o n s u l t i n g I n s t i t u t e
Page 19
Most projects implemented in Silesia have been co-financed from IRDOP grants. Only a few projects
that had not been selected during a call for proposals procedure were financed from other resources.
This fact proves that there are no efficient mechanisms developed to finance and co-finance
regeneration projects in Silesia.
1.1.5. Characteristics of the completed projects
The character of completed regeneration projects has been defined mostly by the following factors:
IRDOP regulations;
ROP SL regulations;
Information included in guidelines describing the principles of developing regeneration
programmes.
Silesian regeneration projects may be divided into three basic groups3:
3 The division is based on the number of projects implemented.
Innovative, designer projects, resulting from integrated strategies of actions leading to a certain aim
(economic, social, etc.)
Projects developed on the basis of IRDOP, ROP SL guidelines in order to
obtain the best possible essential evaluation results.
Investment projects not related with regeneration areas but coherent
with Local Revitalization Programmes.
Table: Regeneration projects implemented in Silesia
Location Project Beneficiary Financing source
Bielsko Biała
Bielsko-Biala Old Town Bielsko Biała
ERDF, state budget, own resources
Bieruo Repair and redevelopment of social infrastructure in Bierun, 15
Rynek Street.
Bieruo ERDF, state budget, own resources
Bieruo Construction of a footbridge on a fitness trail in Bieruo Bieruo ERDF, state budget, own resources
Bieruosko-Lędzioski poviat Adaptation of a building at 24 Ledzinska Street for Business and
NGO Incubator
Bieruosko-Lędzioski poviat ERDF, state budget, own resources
Bytom Adaptation of a building for the Silesian University of Technology
in Bytom
Bytom ERDF, state budget, own resources
Bytom Revitalization of the main building of the Municipal Library in
Bytom
Bytom ERDF, state budget, own resources
Bytom Revitalization of the Bytom Market Square Bytom Municipal budget including municipal bonds,
Fund for Silesia
Bytom Bytom Industrial Park Partnership agreement signed on 9 July
2004 between the Upper Silesian
Enterprise Transformation Agency Joint
Stock Company in Katowice, Bytom
Municipality, "Orzeł Biały" Joint Stock
Company, PUMECH-Orzeł Sp. z o.o. w
Bytomiu, and Mines Restructuring
Company. Project participants were
also: Partnership for Environment Fund,
and Association of Bytom Employers.
1.3 The Sectoral Operational Programme
"Improvement of the Competitiveness of
Enterprises
Bytom “Dolomity” Sports Valley “Dolomity” Sports Valley Project “Modernization of the company aimed at
improvement of service quality, introduction of
new services and increase of sales” was co-
financed (in 50%) from Phare 2002.
C i t y C o n s u l t i n g I n s t i t u t e
Page 21
Location Project Beneficiary Financing source
Project “Orderman – virtual orders” was co-
financed (in 50 %) from The Sectoral
Operational Programme "Improvement of the
Competitiveness of Enterprises”.
Project “Investment planning – swimming pools
in Dolomity Sports Valley” was co-financed (in 50
%) from The Sectoral Operational Programme
"Improvement of the Competitiveness of
Enterprises”.
Project “Development of technical plans of a ski
centre in Sosnowiec” was co-financed (in 50 %)
from The Sectoral Operational Programme
"Improvement of the Competitiveness of
Enterprises”.
Project „High service quality in Dolomity Sports
Valley” was co-financed (in 50%) from Phare
2003.
Bytom Revitalization of Jana III Sobieskiego Square in Bytom Bytom ERDF, state budget, own resources
Bytom Adaptation of a building for the Polish-Japanese Institute of
Information Technology in Bytom
Polish-Japanese Institute of
Information Technology
ERDF, state budget, own resources
Bytom Reconstruction of a nursing home in Bytom Nursing home city budget, National Disabled Persons
Rehabilitation Fund, Bytom Fund for
C i t y C o n s u l t i n g I n s t i t u t e
Page 22
Location Project Beneficiary Financing source
Environmental Protection and Water
Management
Bytom Development of a Professional Career Centre in Bytom Professional Career Centre City budget, Integrated program of alleviating
the restructuring effects in the mining industry.
Bytom Reconstruction of Świętochłowicka and Łagiewnicka Streets in
Bytom
Bytom City budget
Bytom Ringroad of the Upper Silesia Agglomeration Bytom ERDF, state budget, own resources
Chorzów Revitalization of Amelung industrial reservoirs in Chorzów Chorzów ERDF, state budget, own resources
Cieszyn Revitalization of a post-industrial building on 4 Wałowa Street in
Cieszyn for the purposes of a Social Education Centre
Cieszyn ERDF, state budget, own resources
Czechowice - Dziedzice Development of areas neighbouring with the Północ district in
Czechowice-Dziedzice
Czechowice - Dziedzice City budget, RPO SL
Czeladź Revitalization of the medieval Old Town in Czeladz – stage I
(infrastructure)
Czeladź 69,66% - ERDF, 10% - state budget
Częstochowa, Revitalization of the Jasna Góra Park in Częstochowa Częstochowa, ERDF, state budget, own resources
Częstochowa Reconstruction of Berka Joselewicza Street Częstochowa City budget
Częstochowa Reconstruction and development of a post-industrial building for
the purposes of a Modern Art Gallery
Zachęta Association City budget
Częstochowa Reconstruction and repair of the Exhibition Pavilion B and the
Museum of Mining on 7 Kamienic Street in Częstochowa
Museum of Częstochowa City budget
Częstochowa Repair, reconstruction and modernisation of a monumental
building on 24 Najświętszej Maryi Panny Avenue in Częstochowa
Częstochowa - ZGM TBS Sp. z o.o. City budget
Częstochowa Modernization and adaptation of a former House of Orthodox
Clergy called “Popówka” for the purposes of the Museum of
Pilgrimage
Museum of Częstochowa City budget
C i t y C o n s u l t i n g I n s t i t u t e
Page 23
Location Project Beneficiary Financing source
Gliwice Regeneration of the Castle of the Piasts – establishment of a
Centre of Cultural Information and Regional Education
Gliwice, Museum ERDF, state budget, own resources
Gliwice Regeneration of a post-industrial zone in Nowe Gliwice PHARE 2003, city budget
Gliwice Revitalization of the Radiostation Gliwice City budget
Gliwice Development of the cycle path network in Gliwice Gliwice City budget
Gliwice Thermal efficiency improvement of the Gliwice Music Theatre The Music Theatre City budget and the Regional Fund for
Environmental Protection and Water
Management
Jastrzębie Zdrój Modernization of buildings in the Zdrojowy Park for the purposes
of the University of Silesia
University of Silesia City budget
Jastrzębie Zdrój Modernization of buildings in the Zdrojowy Park for the purposes
of a library and reconstruction of a fountain in Jastrzębie Zdrój
Jastrzębie Zdrój, University of
Silesia
City budget
Jastrzębie Zdrój Adaptation of a hospital building for the purposes of the District
Court in Jastrzębie Zdrój
District Court in Jastrzębie Zdrój City budget
Jastrzębie Zdrój Modernization of a swimming pool on Witczaka Street in
Jastrzębie Zdrój
Jastrzębie Zdrój City budget
Katowice Adaptation of a post-military building on 17 Koszarowa Street for
the purposes of the Academy of Fine Arts in Katowice
Academy of Fine Arts in Katowice ERDF, state budget, own resources
Katowice International Congress Centre in Katowice Katowice RPO SL and city budget
Katowice New seat of the Museum of Silesia in Katowice Museum of Silesia in Katowice Voivodship government resources
Katowice The heart of Nikiszowiec. Revitalization of the Museum of
Katowice History building in Katowice
Museum of Katowice History ERDF and city budget
Katowice Szyb Wilson Gallery Szyb Wilson Gallery Own resources and grants from the city of
Katowice
Kłobuck Development of the Kłobuck Market Square and its surroundings Kłobuck ROP SL and city budget
C i t y C o n s u l t i n g I n s t i t u t e
Page 24
Location Project Beneficiary Financing source
Łaziska Górne Revitalization of the monumental City Hall in Łaziska Górne Łaziska Górne City budget and the Regional Fund for
Environmental Protection and Water
Management
Łaziska Górne Construction of a sports hall on Ogrodowa Street in Łaziska
Górne
Łaziska Górne Ministry of Sports and Tourism grant within the
Fund for Development of Physical Culture
Łaziska Górne Construction of a sports and recreation centre "Żabka" Łaziska Górne City budget, Integrated program of alleviating
the restructuring effects in the mining industry.
Marklowice, gmina Revitalization of a post-industrial area – Tropical Island – stage I Marklowice ERDF, state budget, own resources
Mierzęcice, gmina Modernization of the transport system and water and sewage
management on post-military areas
Mierzęcice ERDF, state budget, own resources
Mikołów Revitalization of a post-industrial area – construction of a
swimming pool and a communication system in Mikołów.
Mikołów City budget, Integrated program of alleviating
the restructuring effects in the mining industry,
Ministry of Sports and Tourism grant
Mikołów Development of the Environment and Ecology Centre of the
Silesian Botanical Garden in Mikołów
Silesian Botanical Garden ROP SL and city budget
Upper Silesia Museum, Bytom Revitalization of buildings of the Upper Silesia Museum Upper Silesia Museum ERDF, state budget, own resources
Ożarowice Post-military area revitalization in Ożarowice – stage I:
Construction of Transportowa and Nowa Streets and a water
supply system
Ożarowice ERDF, state budget, own resources
Ożarowice Post-military area revitalization in Ożarowice - II stage: internal
roads, utilities, adaptation for business purposes
Ożarowice ERDF, state budget, own resources
Pszczyna Revitalization of the Pszczyna Old Town Pszczyna ERDF, state budget, own resources
Ruda Śląska Development of a trade – exhibition – cultural centre in Ruda
Śląska - Wirek
Ruda Śląska City budget, Integrated program of alleviating
the restructuring effects in the mining industry
Ruda Śląska Council housing in the city Ruda Śląska City budget
Ruda Śląska Adaptation of a building in Ruda Śląska for the purposes of the
Municipal Prevention Centre
Addiction Treatment Centre and
Municipal Prevention Centre
ERDF, state budget, own resources
Rybnik Renovation of a monumental tenement house on the Market Rybnik, Public Utilities Department ERDF, state budget, own resources
C i t y C o n s u l t i n g I n s t i t u t e
Page 25
Location Project Beneficiary Financing source
Square in Rybnik and its adaptation for business purposes
Rydułtowy Rydułtowy Cultural Centre Rydułtowy ROP SL, own resources
Siemianowice Śląskie Development of the Market Square Siemianowice Śląskie City budget
Siemianowice Śląskie Development of the “Siemion” sports centre Siemianowice Śląskie City budget
Siemianowice Śląskie Modernization of the “Michał” sports centre Siemianowice Śląskie, City Sports
and Leisure Centre
City budget, grant from the Fund for
Development of Physical Culture
Sławków Revitalization of the monumental Sławków city centre Sławków City budget
Sławków Revitalization of the monumental inn in Sławków Sławków Ministry of Culture, voivodship contract for the
year 2004, city budget
Sosnowiec Adaptation of a post-industrial building for the purposes of the
Silesian University of Technology
The Silesian University of
Technology
ERDF, state budget, own resources
Tarnogórski poviat Business Incubator – development in advantageous conditions Tarnogórski poviat, Inkubator
Przedsiębiorczości Sp. z o.o.
ERDF, state budget, own resources
Ustroo Revitalization of the Market Square in Ustroo Ustroo ERDF, state budget, own resources
Żywiec Renewal of the Żywiec Old Castle elevation Żywiec Marshal Office of Śląskie Voivodship, Ministry of
Culture, own resources
Żywiec Revitalization of the Old Castle Complex and the Habsburg Park
in Żywiec
Żywiec Financial Mechanism of the European Economic
Area Ministry of Culture, own resources
Żywiec Revitalization and development of the Old Castle complex and
the Habsburg Park in Żywiec
Żywiec ERDF, state budget, own resources
Żywiec Preservation of the Żywiec cultural heritage – cooperation
between the Żywiec library and Kysucka Kniznica in Cadcy.
Żywiec INTERREG IIIA Poland-Slovakia, own resources
1.1.6. Conclusions for JESSICA
1.2. Possibility of financing regeneration projects within ROP SL
1.2.1. Project eligibility criteria
1.2.1.1. Formal conditions
If IRDOP formal conditions set regeneration frames not only for Silesia but also for the whole
country, ROP SL guidelines are to a considerable extent based on local conditions.
From the formal point of view, application procedure in case of regeneration projects is similar to
IRDOP.
The key element is obviously the application form with several appendices, one of them being a Local
Revitalization Programme. The scope of LRPs is defined by separate guidelines.
•Due to the necessity of ensuring project eligibility and more importantly, smooth process of formal appraisal, beneficiaries avoided projects that did not directly result from the list of exemplary projects;
•Information on regeneration reached local governments shortly before the deadline for filing application forms. Several local authorities did not manage to prepare good projects on time.
The market of regenation projects that are innovative,
profitable and result from integrated municipal strategies
is very limited and requires considerable support.
•It is the guidelines that create the picture of Silesian regeneration. The basic aim of local government authorities is to win a grant. Only in case of failure, alternative solutions are considered, such as PPP, changes in technical drafts, combining the project with other projects implemented in the direct neighbourhood (also by other institutions).
The problem of regeneration is substantive and results
primarily from the guidelines of IRDOP and ROP. The present state of Silesian regeneration is
the reflection of formal requirements not urban
planning.
•The market expects a mechanism enabling application in long term perspective (revolving mechanism).
•The projects implemented should be profitable and related (logically and economically) with other actions implemented in the region.
The market expects financial mechanisms enabling
implementation of profitable projects.
C i t y C o n s u l t i n g I n s t i t u t e
Page 27
According to these guidelines, Local Revitalization Programmes do not introduce the notion of
“integrated municipal plans”. It is thus possible to apply for resources to finance projects that are not
systemically related. The guidelines do not also define detailed procedures of setting revitalization
areas, depending on factors such as:
degradation degree,
poverty,
unemployment,
development perspectives.
This approach means that on the one hand beneficiaries are free to choose regeneration projects
and the choice does not have to be limited by indicators excluding certain locations and on the other
that they can also develop LRP with no detailed analyses.
1.2.1.2. Eligibility of costs
The basic difference between IRDOP and ROP SL results from the eligibility criteria and the types of
projects that may be co-financed.
According to the Complement to ROP SL:
All project costs must be borne in accordance with the public procurement law.
All project costs must be documented by invoices issued by contractors or by other,
equivalent documents.
Only the expenses necessary to implement the project may be considered eligible.
Within measure 6.2, sub-measures 6.2.1. and 6.2.2 only the costs borne in accordance with
the National Eligibility Guidelines for Structural Funds and the Cohesion Fund implemented
in the years 2007 – 2013, defined in the regulation 1083/2006/WE and Eligibility Guidelines
for the ROP SL implemented in the years 2007 – 2013 (Appendix no 2 to the Śląskie Regional
Operational Programme 2007-2013) may be considered eligible.
C i t y C o n s u l t i n g I n s t i t u t e
Page 28
Table: Basic types of projects
Measure Types of projects
Measure 6.2. Revitalization of
degraded areas
Submeasure 6.2.1.
Revitalization of large
cities
Submeasure 6.2.2.
Revitalization of small
cities
1. Reconstruction and repair of post-industrial/post-military/post-
state farm environments, including their adaptation for business,
educational, tourism, social or cultural purposes, as well as
development of neighbouring areas, resulting in solving
economic or social problems in the revitalized area (except for
housing estates).
2. Development of municipal areas, including construction,
reconstruction and repair of buildings for business, educational,
tourism, social or cultural purposes, as well as development of
neighbouring areas, resulting in solving economic or social
problems in the revitalized area (except for housing estates).
3. Supplementation and repair of built-up areas, including infill
buildings, repair of occupied and unoccupied buildings and their
adaptation for business, educational, tourism, social or cultural
purposes, as well as development of neighbouring areas,
resulting in solving economic or social problems on the
revitalized area (except for housing estates).
4. Complex development of land for business purposes, except for
infrastructure for inhabitants.
5. Development of monitoring systems aimed at increasing safety
in public spaces.
6. Replacing asbestos elements of multi-family housing
developments with less harmful materials, only with asbestos
utilization4.
4 Housing projects have to be implemented in areas meeting any three criteria defined by indicators published in
the Guidelines of the Minister of Regional Development on housing projects, based on Article 474 of Regulation no
1828/2006
C i t y C o n s u l t i n g I n s t i t u t e
Page 29
1.2.1.3. Beneficiaries5
1. Territorial self-government units, their associations, societies.
2. Entities in which the majority of shares is owned by territorial self-government units or their
associations and societies.
3. Entities contracted by territorial self-government units in accordance with the public
procurement law.
4. Schools of higher education.
5. Churches and denominations and legal persons of churches and denominations.
6. Non-government organisations.
7. Public finance sector units with legal personality (not listed above)
8. Housing communities, social housing associations,
9. Partnerships of the entities mentioned in 1-8 represented by a leader.
10. Entities acting in accordance with the Law on public-private partnership.
1.2.2. Analysis of the existing lists of project selection criteria and indicators as
regards their relevance for JESSICA
Project selection criteria have been presented in the compilation below.
Project type 1. Reconstruction and repair of post-industrial/post-military/post-state farm
environments, including their adaptation for business, educational, tourism, social or cultural
purposes, as well as development of neighbouring areas, resulting in solving economic or social
problems in the revitalized area (except for housing estates).
Project type 2. Development of municipal areas, including construction, re construction and repair of
buildings for business, educational, tourism, social or cultural purposes, as well as development of
neighbouring areas, resulting in solving economic or social problems in the revitalized area (except
for housing estates).
Project type 3. Supplementation and repair of built-up areas, including infill buildings, repair of
occupied and unoccupied buildings and their adaptation for business, educational, tourism, social or
5 According to the Complement of the Regional Operational Programme of Śląskie Voivodship 2007-2013
C i t y C o n s u l t i n g I n s t i t u t e
Page 30
cultural purposes, as well as development of neighbouring areas, resulting in solving economic or
social problems on the revitalized area (except for housing estates).
No Criterion Weight
1. Number of project objectives – economic, social, cultural, tourist,
recreational, educational:
2 objectives other than the economic one - 1p.
economic - 2p.
economic and one other objective - 3p.
3 objectives and more – 4p.
4,0
2. Degree of implementation of LRP priorities. 2,0
3. Innovativeness of project solutions. 1,5
4. Project availability to general public. 1,5
5. Adjustment for the needs of the disabled. 1,0
Project type 4. Complex development of land for business purposes, except for infrastructure for
inhabitants.
No Criterion Weight
1. Availability of the investment area. 4,0
2. Degree of implementation of LRP priorities. 2,0
3. Project impact on the development of economic infrastructure. 3,0
4. Project location in the light of area investment attractiveness. 1,0
Project type 5. Development of monitoring systems aimed at increasing safety in public spaces.
No Criterion Weight
1. Functionality of the solutions applied. 5,0
2. Degree of implementation of LRP priorities. 2,5
3. Common initiatives (of different entities) aimed at complex protection of the
project area.
2,5
C i t y C o n s u l t i n g I n s t i t u t e
Page 31
Project type 6. Replacing asbestos elements of multi-family housing developments with less harmful
materials, only with asbestos utilization .
No Criterion Weight
1. Degree of urgency (assessment of the present state and possibility of safe usage
of asbestos elements).
4,5
2. Degree of implementation of LRP priorities. 2,0
3. Quantity of asbestos removed. 3,5
Table: Product and result indicators
Measure 6.2. Revitalization of degraded areas
Submeasure 6.2.1 Revitalization – large cities
1. Reconstruction and repair of post-industrial/post-military/post-state farm environments, including their adaptation for business, educational, tourism, social or cultural purposes, as well as development of neighbouring areas, resulting in solving economic or social problems in the revitalized area (except for housing estates).
Product N Number of post-industrial/post-military/post-state farm environments reconstructed for the purpose of at least two of the objectives Psc. Product N Area of post-industrial/post-military/post-state farm environments reconstructed for the purpose of at least two of the objectives m2
Product N Number of post-industrial/post-military/post-state farm environments reconstructed for business activity purposes psc. Product N Area of post-industrial/post-military/post-state farm environments reconstructed for business activity purposes m2
Product N Number of buildings with technical (including municipal) infrastructure reconstructed pcs.
Product N Area of buildings with technical (including municipal) infrastructure reconstructed m2
Product N Length of reconstructed technical (including municipal) infrastructure m
Product N Number of buildings adapted to the needs of the disabled pcs.
Result T Number of events organised with the use of project infrastructure pcs.
Result T Number of people using the buildings covered by the project people Result N Number of the disabled using the buildings covered by the project people Result N Number of buildings protected pcs.
Result N Area of reconstructed and regenerated public infrastructure m2
Result N Number of new service points in the revitalized area pcs.
Result N Usable area m2
Result N Area of developed grounds neighbouring with the buildings covered by the project m2
Result N Area of post-industrial/post-military/post-state farm environments reconstructed for the purpose of at least two of the objectives m2
Result T Number of new enterprises in the area covered by the project pcs.
Result T Regenerated area m2
2. Development of municipal areas, including construction, reconstruction and repair of buildings for business, educational, tourism, social or cultural purposes, as well as development of neighbouring areas, resulting in solving economic or social problems in the revitalized area (except for housing estates).
Product N Number of buildings restored for the purpose of at least 2 of the objectives pcs.
Product N Area of buildings restored for the purpose of at least 2 of the objectives m2
Product N Number of buildings constructed for the purpose of at least 2 of the objectives pcs.
Product N Area of buildings constructed for the purpose of at least 2 of the objectives m2
Product N Number of buildings reconstructed for the purpose of at least 2 of the objectives pcs.
Product N Area of buildings reconstructed for the purpose of at least 2 of the objectives m2
Product N Number of buildings reconstructed for business activity purposes pcs.
Product N Area of buildings reconstructed for business activity purposes m2
C i t y C o n s u l t i n g I n s t i t u t e
Page 33
Product N Number of buildings with technical (including municipal) infrastructure reconstructed pcs.
Product N Area of buildings with technical (including municipal) infrastructure reconstructed m2
Product N Length of reconstructed technical (including municipal) infrastructure m
Product N Usable area of the reconstructed buildings m2
Product N Green areas developed around the buildings covered by the project m2
Product N Small architecture area m2
Product N Number of small architecture elements pcs.
Product N Number of parking places pcs.
Product N Parking area m2
Product N Area of reconstructed and regenerated public infrastructure m2
Product N Length of internal roads built in the area covered by the project m
Product N Length of internal roads reconstructed/repaired in the area covered by the project m
Product N Number of road infrastructure elements built pcs.
Product N Number of road infrastructure elements reconstructed / repaired pcs.
Product N Number of buildings adapted to the needs of the disabled pcs.
Result T Number of events organised with the use of project infrastructure pcs.
Result N Number of buildings protected pcs.
Result N Usable area m2
Result N Number of new service points in the revitalized area pcs.
Result N Area of developed grounds neighbouring with the buildings covered by the project m2
Result N Area of regenerated public spaces that became available for the purpose of at least 2 of the objectives m2
Result N Area of grounds that became available in result of the project m2
Result T Number of people using the buildings covered by the project people Result N Number of the disabled using the buildings covered by the project people Result T Number of new enterprises in the area covered by the project pcs.
Result T Regenerated area m2
3. Supplementation and repair of built-up areas, including infill buildings, repair of occupied and unoccupied buildings and their adaptation for business, educational, tourism, social or cultural purposes, as well as development of neighbouring areas, resulting in solving economic or social problems on the revitalized area (except for housing estates). Product N Number of buildings restored for the purpose of at least 2 of the objectives pcs.
Product N Area of buildings restored for the purpose of at least 2 of the objectives m2
Product N Number of buildings reconstructed for the purpose of at least 2 of the objectives pcs.
Product N Area of buildings reconstructed for the purpose of at least 2 of the objectives m2
Product N Number of infill buildings developed for the purpose of at least 2 of the objectives pcs.
Product N Area infill buildings developed for the purpose of at least 2 of the objectives m2
Product N Number of buildings reconstructed for business activity purposes pcs.
Product N Area of buildings reconstructed for business activity purposes m2
C i t y C o n s u l t i n g I n s t i t u t e
Page 34
Product N Number of buildings with technical (including municipal) infrastructure reconstructed pcs.
Product N Area of buildings with technical (including municipal) infrastructure reconstructed m2
Product N Length of reconstructed technical (including municipal) infrastructure m
Product N Number of buildings adapted to the needs of the disabled pcs.
Result T Number of events organised with the use of project infrastructure pcs.
Result N Number of the disabled using the buildings covered by the project people
Result N Number of buildings protected pcs.
Result T Number of people using the buildings covered by the project people
Result N Usable area m2
Result N Number of new service points in the revitalized area pcs.
Result N Area of grounds that became available in result of the project m2
Result N Number of people using the developed / regenerated empty public spaces. people
Result T Number of new enterprises in the area covered by the project pcs.
Result T Regenerated area m2
4. Complex development of land for business purposes, except for infrastructure for inhabitants.
Product N Number of buildings constructed pcs.
Product N Area of buildings constructed m2
Product N Usable area in the buildings constructed m2
Product N Number of buildings reconstructed for business activity purposes pcs.
Product N Area of buildings reconstructed for business activity purposes m2
Product N Number of buildings with technical (including municipal) infrastructure reconstructed pcs.
Product N Area of buildings with technical (including municipal) infrastructure reconstructed m2
Product N Length of reconstructed technical (including municipal) infrastructure m
Product N Length of access roads built in the area covered by the project m
Product N Length of access roads reconstructed/repaired in the area covered by the project m
Product N Number of road infrastructure elements built pcs.
Product N Number of road infrastructure elements reconstructed / repaired pcs.
Product N Number of buildings adapted to the needs of the disabled pcs.
Result N Number of incubators established in result of the project pcs.
Result N Area of incubators established in result of the project m2
Result N Number of new service points in the revitalized area pcs.
Result T Regenerated area m2
Result N Usable area m2
Result N Area of grounds that became available in result of the project m2
Result T Number of new enterprises in the area covered by the project pcs.
5. Development of monitoring systems aimed at increasing safety in public spaces.
Product N Number of monitoring appliances installed pcs.
C i t y C o n s u l t i n g I n s t i t u t e
Page 35
Product N Area covered by the monitoring system m2
Product N Number of districts covered by the monitoring system pcs.
Product N Number of monitoring systems implemented pcs.
Result N Number of crimes in the city pcs.
Result N Number of people covered by the monitoring system people
Result N Crime detection rate %
Result N Number of offences / crimes recorded by the monitoring system pcs.
6. Replacing asbestos elements of multi-family housing developments with less harmful materials, only with asbestos utilization . Product N Number of buildings from which asbestos was removed pcs.
Product N Area of buildings from which asbestos was removed m2
Product N Area from which asbestos was removed m2
Result N Amount of asbestos containing materials removed Mg
Result T Number of people living in the regenerated buildings people
Measure 6.2. Revitalization of degraded areas
Submeasure 6.2.2. Revitalization – small cities
1. Reconstruction and repair of post-industrial/post-military/post-state farm environments, including their adaptation for business, educational, tourism, social or cultural purposes, as well as development of neighbouring areas, resulting in solving economic or social problems in the revitalized area (except for housing estates).
Product N Number of post-industrial/post-military/post-state farm environments reconstructed for the purpose of at least two of the objectives pcs.
Product N Area of post-industrial/post-military/post-state farm environments reconstructed for the purpose of at least two of the objectives m2
Product N Number of post-industrial/post-military/post-state farm environments reconstructed for business purposes pcs.
Product N Area of post-industrial/post-military/post-state farm environments reconstructed for business purposes m2
Product N Number of buildings with technical (including municipal) infrastructure reconstructed pcs.
Product N Area of buildings with technical (including municipal) infrastructure reconstructed m2
Product N Length of reconstructed technical (including municipal) infrastructure m
Product N Number of buildings adapted to the needs of the disabled pcs.
Result T Number of events organised with the use of project infrastructure pcs.
Result T Number of people using the buildings covered by the project people Result N Number of the disabled using the buildings covered by the project people Result N Number of buildings protected pcs.
Result N Area of reconstructed and regenerated public infrastructure m2
Result N Number of new service points in the revitalized area pcs.
C i t y C o n s u l t i n g I n s t i t u t e
Page 36
Result N Usable area m2
Result N Area of developed grounds neighbouring with the buildings covered by the project m2
Result N Area of post-industrial/post-military/post-state farm environments reconstructed for the purpose of at least two of the objectives m2
Result T Number of new enterprises in the area covered by the project pcs.
Result T Regenerated area m2
2. Development of municipal areas, including construction, re construction and repair of buildings for business, educational, tourism, social or cultural purposes, as well as development of neighbouring areas, resulting in solving economic or social problems in the revitalized area (except for housing estates). Product N Number of buildings restored for the purpose of at least 2 of the objectives pcs.
Product N Area of buildings restored for the purpose of at least 2 of the objectives m2
Product N Number of buildings constructed for the purpose of at least 2 of the objectives pcs.
Product N Area of buildings constructed for the purpose of at least 2 of the objectives m2
Product N Number of buildings reconstructed for the purpose of at least 2 of the objectives pcs.
Product N Area of buildings reconstructed for the purpose of at least 2 of the objectives m2
Product N Number of buildings reconstructed for business activity purposes pcs.
Product N Area of buildings reconstructed for business activity purposes m2
Product N Number of buildings with technical (including municipal) infrastructure reconstructed pcs.
Product N Area of buildings with technical (including municipal) infrastructure reconstructed m2
Product N Length of reconstructed technical (including municipal) infrastructure m
Product N Usable area of the reconstructed buildings m2
Product N Green areas developed around the buildings covered by the project m2
Product N Small architecture area m2
Product N Number of small architecture elements pcs.
Product N Number of parking places pcs.
Product N Parking area m2
Product N Area of reconstructed and regenerated public infrastructure m2
Product N Length of internal roads built in the area covered by the project m
Product N Length of internal roads reconstructed/repaired in the area covered by the project m
Product N Number of road infrastructure elements built pcs.
Product N Number of road infrastructure elements reconstructed / repaired pcs.
Product N Number of buildings adapted to the needs of the disabled pcs.
Result T Number of events organised with the use of project infrastructure pcs.
Result N Number of buildings protected pcs.
Result N Usable area m2
Result N Number of new service points in the revitalized area pcs.
Result N Area of developed grounds neighbouring with the buildings covered by the project m2
C i t y C o n s u l t i n g I n s t i t u t e
Page 37
Result N Area of regenerated empty public spaces that became available for the purpose of at least 2 of the objectives m2
Result N Area of grounds that became available in result of the project m2
Result T Number of people using the buildings covered by the project people Result N Number of the disabled using the buildings covered by the project people Result T Number of new enterprises in the area covered by the project pcs.
Result T Regenerated area m2
3. Supplementation and repair of built-up areas, including infill buildings, repair of occupied and unoccupied buildings and their adaptation for business, educational, tourism, social or cultural purposes, as well as development of neighbouring areas, resulting in solving economic or social problems on the revitalized area (except for housing estates).
Product N Number of buildings restored for the purpose of at least 2 of the objectives pcs.
Product N Area of buildings restored for the purpose of at least 2 of the objectives m2
Product N Number of buildings reconstructed for the purpose of at least 2 of the objectives pcs.
Product N Area of buildings reconstructed for the purpose of at least 2 of the objectives m2
Product N Number of infill buildings developed for the purpose of at least 2 of the objectives pcs.
Product N Area infill buildings developed for the purpose of at least 2 of the objectives m2
Product N Number of buildings reconstructed for business activity purposes pcs.
Product N Area of buildings reconstructed for business activity purposes m2
Product N Number of buildings with technical (including municipal) infrastructure reconstructed pcs.
Product N Area of buildings with technical (including municipal) infrastructure reconstructed m2
Product N Length of reconstructed technical (including municipal) infrastructure m
Product N Number of the disabled using the buildings covered by the project pcs.
Result T Number of events organised with the use of project infrastructure pcs.
Result N Number of buildings protected pcs.
Result T Number of people using the buildings covered by the project people Result N Number of the disabled using the buildings covered by the project people Result N Usable area m2 Result N Number of new service points in the revitalized area pcs.
Result N Area of grounds that became available in result of the project m2
Result N Number of people using the developed / regenerated empty public spaces. people
Result T Number of new enterprises in the area covered by the project pcs.
Result T Regenerated area m2
4. Complex development of land for business purposes, except for infrastructure for inhabitants.
Product N Number of buildings constructed pcs.
Product N Area of buildings constructed m2
Product N Usable area in the buildings constructed m2
Product N Number of buildings reconstructed for business activity purposes pcs.
C i t y C o n s u l t i n g I n s t i t u t e
Page 38
Product N Area of buildings reconstructed for business activity purposes m2
Product N Number of buildings with technical (including municipal) infrastructure reconstructed pcs.
Product N Area of buildings with technical (including municipal) infrastructure reconstructed m2
Product N Length of reconstructed technical (including municipal) infrastructure m
Product N Length of access roads built in the area covered by the project m
Product N Length of access roads reconstructed/repaired in the area covered by the project m
Product N Number of road infrastructure elements built pcs.
Product N Number of road infrastructure elements reconstructed / repaired pcs.
Product N Number of buildings adapted to the needs of the disabled pcs.
Result N Number of incubators established in result of the project pcs.
Result N Area of incubators established in result of the project m2
Result N Number of new service points in the revitalized area pcs.
Result N Usable area m2
Result N Area of grounds that became available in result of the project m2
Result T Number of new enterprises in the area covered by the project pcs.
Result T Revitalized area m2
5. Development of monitoring systems aimed at increasing safety in public spaces.
Product N Number of monitoring appliances installed pcs.
Product N Area covered by the monitoring system m2
Product N Number of districts covered by the monitoring system pcs.
Product N Number of monitoring systems implemented pcs.
Result N Number of crimes in the city pcs.
Result N Number of people covered by the monitoring system people
Result N Crime detection rate %
Result N Number of offences / crimes recorded by the monitoring system pcs.
6. Replacing asbestos elements of multi-family housing developments with less harmful materials, only with asbestos utilization .
Product N Number of buildings from which asbestos was removed pcs.
Product N Area of buildings from which asbestos was removed m2
Product N Area from which asbestos was removed m2
Result N Amount of asbestos containing materials removed Mg
Result T Number of people living in the regenerated buildings people
Project selection criteria are general and all refer to non-profitable projects. In case of JESSICA, it is
necessary to broaden the criteria by the following aspects:
Profitability / self-financing ability of projects [crucial in the light of the method of financing
projects within JESSICA]
Compatibility with an Integrated Municipal Development Plan [crucial in the light of
necessity to implement a systemic approach to urban regeneration]
The present list of product and result indicators is very complex and enables applicants to
characterise potential JESSICA projects. There is no need to introduce any changes as their
implementation would additionally lengthen the process of JESSICA implementation.
1.2.3. List of key potential projects to be implemented in the years 2010-20136
An analysis has been conducted of potential ROP SL projects. The projects (listed in the compilation
below) correspond to ROP SL guidelines on eligibility.
The general profile of the projects comprises actions in the following spheres:
revitalization of public spaces;
development and modernization of historical buildings and museums;
modernization of transport infrastructure.
The character of these projects is non-commercial. However, some of them, especially concerning
modernization of sports, cultural and post-industrial infrastructure could generate considerable
income.
Table: Key potential regeneration projects (years 2010 – 2013)
No City Project
1. BIELSKO – BIAŁA Revitalization of the Bielsko Old Town – “Visit and rest” – stage II.
2. BIELSKO - BIAŁA Revitalization of the Słowackiego Park in Bielsko-Biała.
3. BIELSKO-BIAŁA Revitalization of the Bielsko Old Town.
4. BIERUO Reconstruction of XVI century dyke on Chemików Street.
5. BIERUO Revitalization of the area of Paciorkowce in Bieruo Nowy for sports and
recreation purposes.
6. BIERUO Construction of an impounding reservoir in Bijasowice.
6 The list was developed on the basis of information supplied by self-government units in response to the request of
the Marshall Office of Śląskie Voivodship.
C i t y C o n s u l t i n g I n s t i t u t e
Page 40
7. BIERUO Development of new cycle paths.
8. BIERUO Development of the Łysina reservoir area in Bieruo Stary.
9. BIERUO New city monitoring system.
10. BIERUO Modernization of roads, pavements, power utilities and fibre networks within
the Old Town.
11. BIERUO Reconstruction and repair of a post-industrial building including its adaptation
for business, social and cultural purposes.
12. BIERUO Reconstruction and repair of the Jutrzenka Cinema and Theatre.
13. BIERUO Reconstruction and repair of the Gama Community Centre.
14. BIERUO Gallery and museum of the city of Bieruo.
15. BIERUO Reconstruction and adaptation of a sports hall in the Homer district.
16. BIERUO Revitalization of the area of a former crystal grinding workshop on Borowinowa
Street.
17. CIESZYN Monitoring system in the Cieszyn Down-Town.
18. CIESZYN Regeneration of the building on 7 Limanowskiego Street in Cieszyn –
construction of a public parking.
19. CIESZYN Regeneration of the building of the former border crossing by the Friendship
Bridge.
20. CZĘSTOCHOWA Modernization of the Wieluoski Square and Rocha Street
21. DĄBROWA GÓRNICZA Construction of a school and education centre with a sports centre for disabled
children and youth in Dąbrowa Górnicza: stage I – development of the area and
external utilities.
22. DĄBROWA GÓRNICZA Reconstruction of the monumental Zagłębie Culture Palace in Dąbrowa
Górnicza.
23. DĄBROWA GÓRNICZA Reconstruction of the DAMEL city stadium in Dąbrowa.
24. DĄBROWA GÓRNICZA New parking places and reconstruction of the communication system in the
Morcinek district of Dąbrowa Górnicza.
25. DĄBROWA GÓRNICZA New parking places and reconstruction of the communication system in the
Sikorskiego district in Dąbrowa Górnicza.
26. GLIWICE Development of the areas around the Radiostation.
27. GLIWICE Revitalization of the Radiostation – Gliwice.eu
28. GLIWICE Reconstruction and development of the stadium on Okrzei Street in Gliwice.
29. GLIWICE Reconstruction of the Municipal Theatre ruins.
30. GLIWICE Modernization of the “Forrest” swimming pool.
31. GLIWICE Development of the Rzeźniczy Square in Gliwice.
32. GLIWICE Modernization of the square on Narutowicza Street.
C i t y C o n s u l t i n g I n s t i t u t e
Page 41
33. ŁAZISKA GÓRNE Revitalization of fitness trails around the “Żabka” swimming pool in Łaziska
Górne.
34. MYSZKÓW Revitalization of the Myszków Market Square.
35. RUDA ŚLĄSKA Revitalization of the Kozioła Park.
36. RUDA ŚLĄSKA Revitalization of the historical centre of the Wirek district.
37. RUDA ŚLĄSKA Revitalization of the Sobieskiego Park.
38. RUDA ŚLĄSKA Revitalization of recreation grounds – development of the Achtelika Valley.
39. RUDA ŚLĄSKA Hill of New Ideas – revitalization of a park for sports and business purposes –
stage II.
40. RUDA ŚLĄSKA Development of green areas – Planty Kochłowickie.
41. RUDA ŚLĄSKA Renovation of St. Paul Church and a viewing tower in Ruda Śląska.
42. SIEWIERZ Reconstruction of the Market Square in Siewierz.
43. SIEWIERZ Complex conservation of the Siewierz castle – stage II.
44. SIEWIERZ Development of active tourism and recreation infrastructure “Pogoria Summer
and Water Sports Centre”. Cycle path from Kuźnica Warężyoska Reservoir to
Siewierz Castle ruins.
45. SIEWIERZ Development of the Siewierz Castle surroundings for recreation, tourism and
sports purposes.
46. SOSNOWIEC Reconstruction of the “MUZA” building in Sosnowiec as a chance to promote
culture.
47. SOSNOWIEC Adaptation of the Sielecki Castle.
48. SOSNOWIEC Reconstruction of Chemiczna Street.
49. SOSNOWIEC Revitalization of the monumental Schoen Park in Sosnowiec.
50. SOSNOWIEC Revitalization of the Three Caesars’ Triangle and adaptation of the Biała
Przemsza river for tourism and recreation purposes.
51. SOSNOWIEC Revitalization of the Rudna district – stage II.
52. STRUMIEO Revitalization of the monumental Strumieo Old Town.
53. ZAWIERCIE Development of the local cultural infrastructure by building a new seat of the
Zawiercie Municipal Library.
54. ZAWIERCIE Development of the local sports infrastructure by modernizing the Zawiercie
municipal swimming pool.
1.2.4. List of key projects financed after a restricted call of proposals
Table: List of key projects financed after a restricted call of proposals
No Measure/Sub-measure (no and name)
Project title Beneficiary (leader + partners)
Total project cost (PLN) Grant (PLN)
Western Subregion Development Programme 24 Sub-measure 6.2.1.
Revitalization - "large cities" Modernization of a sports and entertainment arena
in Rybnik - Boguszowice Rybnik - Gmina 5 571 478,57 3 999 764,47
25 Sub-measure 6.2.1. Revitalization - "large cities"
Monitoring system in the City of Rybnik - Stage II Rybnik - Gmina 2 190 631,24 1 840 000,00
26 Sub-measure 6.2.2 Revitalization – “small cities”
Establishment of a "Culture and Entertainment Centre" in Rydułtowy
Rydułtowy - Gmina 11 045 000,00 6 160 000,00
27 Sub-measure 6.2.2 Revitalization – “small cities”
Social and cultural centre with exhibition areas Pietrowice Wielkie -Gmina
8 004 664,00 6 800 000,00
28 Sub-measure 6.2.2 Revitalization – “small cities”
Modernization of a sports and entertainment arena for the purpose of a cultural and educational centre
Czerwionka – Leszczyny - Gmina
13 508 816,00 11 480 000,00
29 Sub-measure 6.2.2 Revitalization – “small cities””
Development of public spaces for the purposes of a municipal open – air market in Czerwionka Leszczyny
Czerwionka – Leszczyny - Gmina
3 764 920,00 3 200 000,00
44085509,81
33479764,47
Southern Subregion Development Programme 39 Sub-measure 6.2.2
Revitalization – “small cities” Revitalization of degraded areas and development of technical infrastructure for the purposes of the Water
Sports and Recreation Centre
Bestwina - Gmina 2 600 000,00 2 200 000,00
40 Sub-measure 6.2.2 Revitalization – “small cities”
Time for Business – reconstruction of the railway station in Czechowice-Dziedzice
Czechowice-Dziedzice -Gmina
5 002 000,00 3 900 000,00
41 Sub-measure 6.2.2 Revitalization – “small cities”
Revitalization of degraded areas of the Silesia coal mine
Bielski - Poviat 2 488 556,00 1 900 000,00
42 Sub-measure 6.2.2 Revitalization – “small cities”
Revitalization of buildings of the former cement mill Goleszów - Gmina 1 416 517,60 1 204 000,00
43 Sub-measure 6.2.2 Revitalization – “small cities”
INTEGRATOR – Municipal Centre – repair of the monumental tenement house on 9 Mickiewicza
Street in Skoczów
Skoczów - Gmina 2 924 960,00 2 456 000,00
44 Sub-measure 6.2.2 Revitalization – “small cities”
Revitalization of the monumental Old Town in Strumieo
Strumieo - Gmina 2 967 040,00 2 516 000,00
45 Sub-measure 6.2.2 Revitalization – “small cities”
Revitalization of Great Houses – stage I Ustroo - City 2 230 701,68 1 896 000,00
46 Sub-measure 6.2.2 Revitalization – “small cities”
Development of the area neighbouring with the Północ district in Czechowice - Dziedzice
Czechowice – Dziedzice - Gmina
2 552 946,89 2 141 232,36
47 Sub-measure 6.2.2 Revitalization – “small cities”
Revitalization of areas neighbouring with the Castle Hill in Cieszyn – modernization and development of
Cieszyn - Gmina 1 548 120,00 1 101 600,00
C i t y C o n s u l t i n g I n s t i t u t e
Page 43
the public parking 48 Sub-measure 6.2.2
Revitalization – “small cities” Revitalization of the park in Łękawica Łękawica - Gmina 703 031,28 565 940,18
49 Sub-measure 6.2.2 Revitalization – “small cities”
Development of the quarry area in Glinka Ujsoły - Gmina 620 603,33 526 209,56
50 Sub-measure 6.2.2 Revitalization – “small cities”
Revitalization of post-industrial infrastructure for business, recreation and social purposes
Węgierska Górka -Gmina
990 712,71 805 059,89
26045189,49
21212041,99
Northern Subregion Development Programme 37 Measure 6.1 Enhancement of
regional growth centres Sports centre on Żużlowa Street in Częstochowa Częstochowa - City 70 000 000,00 29 520 000,00
38 Sub-measure 6.2.1. Revitalization - "large cities"
Reconstruction and repair of the Youth Community Centre in Częstochowa
Częstochowa - City 4 470 592,00 3 800 000,00
39 Sub-measure 6.2.1. Revitalization - "large cities"
Repair and adaptation of the former astronomical observatory for cultural and educational purposes in
Częstochowa
Częstochowa - City 2 646 153,85 1 720 000,00
40 Sub-measure 6.2.2 Revitalization – “small cities”
Business Activity Zone Poczesna - Gmina (project leader), partner gminas:
Kamienica Polska, Starcza, Konopiska
14 117 647,06 12 000 000,00
41 Sub-measure 6.2.2 Revitalization – “small cities”
Development of the Market Square in Kłobuck Kłobuck - Gmina 6 559 789,54 5 575 821,10
42 Sub-measure 6.2.2 Revitalization – “small cities”
Reconstruction of the Market Square in Krzepice as an element of the town revitalization programme –
stage I
Krzepice - Gmina 2 380 708,00 2 023 601,80
43 Sub-measure 6.2.2 Revitalization – “small cities”
Reconstruction of the Old Town and Jana Pawła II Square in Żarki
Żarki - Gmina 2 761 000,00 2 295 000,00
44 Sub-measure 6.2.2 Revitalization – “small cities”
Revitalization of the Market Square in Koziegłowy Koziegłowy - Gmina 1 936 025,88 1 622 400,00
45 Sub-measure 6.2.2 Revitalization – “small cities”
Myszków Business Initiative Centre in former factory buildings from the beginning of the XXth century;
Myszków, 12 Kościuszki Street
Myszków - Gmina 3 025 352,20 1 193 548,88
46 Sub-measure 6.2.2 Revitalization – “small cities”
Revitalization of areas degraded by excavation of moulding sand in the gmina of Niegowa for tourism
and recreation purposes
Niegowa - Gmina 783 070,92 665 610,28
47 Sub-measure 6.2.2 Revitalization – “small cities”
Revitalization of the Market Square in Myszków - Mrzygłód
Myszków - Gmina 3 285 590,21 651 507,28
41 965 929,66
31 547 489,34
C i t y C o n s u l t i n g I n s t i t u t e
Page 44
Central Subregion Development Programme 84 Sub-measure 6.2.1. Revitalization
- "large cities" Adaptation of a building for a Social Initiative
Centre in Chorzów Chorzów – Gmina with
poviat rights 1 729 411,78 1 470 000,00
85 Sub-measure 6.2.1. Revitalization - "large cities"
Adaptation of a building for a Social Initiative Centre in Bytom
Bytom - City 1 935 940,00 1 470 000,00
86 Sub-measure 6.2.1. Revitalization - "large cities"
Adaptation of a building for a Social Initiative Centre in Świętochłowice
Świętochłowice - City 3 526 419,77 1 353 985,95
87 Sub-measure 6.2.1. Revitalization - "large cities"
Adaptation of a building for a Social Initiative Centre in Ruda Śląska
Ruda Śląska - City 1 729 411,78 1 470 000,00
88 Sub-measure 6.2.1. Revitalization - "large cities"
Safe Mysłowice – city monitoring system Mysłowice - Municipality
1 684 490,60 1 200 000,00
Total 10 605 673,93
6 963 985,95
Total resources in all sub-regional programmes 122 702 302,9
93203281,8
C i t y C o n s u l t i n g I n s t i t u t e
Page 45
1.2.5. Conclusions for JESSICA
1.3. Analysis of strategic documents
1.3.1. Local Revitalisation Programmes
The objective of Local Revitalization Programmes is to elaborate social, economic and spatial
development directions for degraded urban areas, post-industrial and post-military areas. These documents
are parts of strategic planning actions, that is, actions undertaken by local self-government
authorities to plan for the future, define project stages and provide for financing resources. Effective
strategic planning may be characterised by the following features:
It helps self-government entities define common objectives acceptable by the society and achieve
them,
•Due to the necessity of ensuring project eligibility andmore importantly, smooth process of formal appraisal,beneficiaries avoided projects that did not directlyresult from the list of exemplary projects;
•Information on regeneration reached localgovernments shortly before the deadline for filingapplication forms. Several local authorities did notmanage to prepare good projects on time.
Formal requirements of ROP SL (Priority 6) correspond to
JESSICA implementation conditions
•It is the guidelines that created the picture of Silesianregeneration. The basic aim of local governmentauthorities is to win a grant. Only in case of failure,alternative solutions are considered such as PPP,changes in technical drafts, combining the project withother projects implemented in the directneighbourhood (also by other institutions).
Implementation of JESSICA will not necessitate any
changes to the list of product and result indicators
•The market expects a mechanism enabling applicationin long term perspective (revolving mechanism).
•The projects implemented should be profitable andrelated (logically and economically) with other actionsimplemented in the region.
In response to the revitalization market
demand, it is recommended to include rural communes strongly influenced by large cities on the list of potential
JESSICA beneficiaries
C i t y C o n s u l t i n g I n s t i t u t e
Page 46
It presents development aims and tasks to do as well as necessary resources and achievement
methods,
It focuses on feasible (not desirable) enterprises by real and true assessment of local resources,
chances and threats.
Effective strategic planning necessitates also financial planning actions such as Multi-annual
Investment Plans. It provides control and realism in the process of defining priorities and their
selection.
Strategic planning combines a large number of small projects (investment tasks) in order to
achieve wider economic objectives. Strategic planning enables authorities e.g. to:
avoid guesswork and accidental decisions,
organise preferences of the local society,
organise local problems and demands in order of precedence.
Analysis of LRPs adopted by particular city councils has proven that these documents are
multi-annual plans of economic, social and spatial actions covering the period of maximum 20 years.
All the activities are planned for the years 2007 – 2013, in correspondence with the ERDF
programming period.
C i t y C o n s u l t i n g I n s t i t u t e
Page 47
Table: Strategic planning model
Local Revitalization Programmes assume the necessity of update as new demands appear
and new development directions are defined. These Programmes are coherent with ROP SL or IRDOP
(in case of not updated programmes) guidelines. Revitalization projects concern not only technical
infrastructure but also improvement of local community life quality.
Local Revitalization Programmes enable gminas and their partners to apply for European
Union grants to finance their projects. Possibility of financing investments from external resources
enables gminas and other self-government entities to implement the projects defined by the
Policies, programmes, sectoral plans
Development strategy Spatial Development Plan
Multi-annual Investment Plan
Priorities
Annual budget
Investment expenditure Operating expenditure
ProjectProject Project Project
Local Revitalization Programme
C i t y C o n s u l t i n g I n s t i t u t e
Page 48
Programme. The major objective of a LRP is thus provision of coherence between all activities and
tasks concerning a particular revitalization area.
Revitalization projects defined by the LRPs analysed are primarily investments eligible for
financing from the resources of the Śląskie Regional Operational Programme within Priority VI
Sustainable urban development. In order to win a grant, it is necessary for a potential beneficiary to
present a Local Revitalization Programme including the project to be co-financed.
Local Revitalization Programmes include also key projects and investments covered by
Subregion Development Programmes. The key projects are:
1. Podium – a modern sports and entertainment arena in Gliwice.
2. New seat of the Museum of Silesia in Katowice.
3. Enhancement of the role of the Pilgrimage Centre by modernizing Najświętszej Maryi Panny
Avenue in Częstochowa.
4. Academic Information Centre and Library.
5. International Congress Centre in Katowice.
Investments defined by Local Revitalization Programmes are coherent with the types of
projects defined by the Detailed Description of ROP SL Priorities, that is:
Construction (including outward extension, upward extension and reconstruction), conversion
and repair of public buildings shaping the metropolitan image of the region.
Development and transformation of representative public areas characterised by high quality
urban solutions and supraregional importance.
Construction (including outward extension, upward extension and reconstruction), conversion
and repair of academic infrastructure.
Construction (including outward extension, upward extension and reconstruction), conversion
and repair of cultural, tourism, sport and recreation infrastructure of supraregional importance, in
which international meetings, congresses, fair, exhibitions, sports and entertainment events may be
organised.
Construction (including outward extension, upward extension and reconstruction) and
conversion of strategic public transport infrastructure (excluding means of transportation).
Establishment and development of economic activity zones, especially on post-industrial areas.
Reconstruction and repair of post-industrial/post-military/post-state farm environments,
including their adaptation for business, educational, tourism, social or cultural purposes, as well
as development of neighbouring areas, resulting in solving economic or social problems in the
revitalized area (except for housing estates).
C i t y C o n s u l t i n g I n s t i t u t e
Page 49
Development of municipal areas, including construction, reconstruction and repair of buildings
for business, educational, tourism, social or cultural purposes, as well as development of
neighbouring areas, resulting in solving economic or social problems in the revitalized area
(except for housing estates).
Supplementation and repair of built-up areas, including infill buildings, repair of occupied and
unoccupied buildings and their adaptation for business, educational, tourism, social or cultural
purposes, as well as development of neighbouring areas, resulting in solving economic or social
problems on the revitalized area (except for housing estates).
Complex development of land for business purposes, except for infrastructure for inhabitants.
Development of monitoring systems aimed at increasing safety in public spaces.
Replacing asbestos elements of multi-family housing developments with less harmful materials,
only with asbestos utilization.
The Local Revitalization Programmes analysed have to be updated due to the following
reasons:
LRPs have not been updated since the last call for proposals of the EU programming
period 2004 – 2006 or since selected projects have been included in particular
subregional development programmes of Śląskie Voivodship within ROP SL 2007 –
2013,
There has still been no call for proposals announced in the present programming
period as the call has been withheld until further notice.
Introduction of new projects or modification of the already included ones in the
course of the update process before the call for proposals.
LRPs are usually updated after application documents had been prepared or after the planned
deadline of applying within subregional development programmes had been announced.
There is also a necessity to ensure coherence between multi-annual investment plans and local
revitalization programmes of a particular self-government entity. Due to the new request of the ROP
MA, it is obligatory to ensure financial resources for a particular project only when a co-financing
contract is to be signed. There may be thus postponements of multi-annual plan completion dates
(new project titles, costs, financing sources and time-tables).
C i t y C o n s u l t i n g I n s t i t u t e
Page 50
1.3.2. Multi-annual Investment Plans
Certain competences of self-government entities to earn profit and bear expenses have
considerable impact on the level, directions and types of investments.
Public investments of self-government entities may be divided according to the following
scheme:
social infrastructure (e.g. schools, community centres, social security centres, hospitals, out-
patient clinics, etc.),
technical infrastructure (e.g. roads, heat, water and waste water systems, sewage treatment
plants, dumps, city transport).
Investments in infrastructure contribute to improvement of life quality and business activity
conditions. They may also have positive impact on the job market. One should also remember that
investments in infrastructure (including revitalization projects) result in greater attractiveness of a
particular area than investments in social infrastructure.
Investment policy of self-government entities implements the objectives of social and
economic policies and influences the investment attractiveness of a particular entity. Investment
policy is a type of expenditure policy and is combined with profit policy by defining possible sources
of financing public investment and debt service. Investment policy of a self-government entity is a
conscious and purposeful choice of:
projects to be implemented in accordance with certain previously defined criteria – new,
continued, modernization, material, financial projects (including the definition of investment
potential of the particular entity);
methods and sources of financing investment (grants, e.g. from the European Union as well as
credits and loans), reflected in the development strategy, revitalization programme and multi-annual
investment plan.
A multi-annual investment plan of a self-government body comprises a compilation of
investment projects to be implemented in the next few years. It is developed in result of strategic
choice of investment directions in a long-term perspective and its aim is social and economic growth.
The bases for multi-annual investment plans are medium-term and long-term budget
projections, taking into account the maximum debt level and the costs of debt service. These
projections are the basic tool, integrating profit with expenditure.
C i t y C o n s u l t i n g I n s t i t u t e
Page 51
According to statutory regulations, the primary objectives of long-term investment policies
are the following:
improvement of road infrastructure, public transport – projects aimed at higher transport
quality,
improvement of living conditions, e.g. by providing connection to the waste water system,
revitalization of historical and monumental buildings,
revitalization and activisation of degraded urban areas, degraded post-industrial, post-
military and post-mining areas,
construction or modernization of buildings aimed at the development of sports, tourism and
recreation,
providing conditions for entrepreneurship development,
providing conditions for housing development,
improvement of technical conditions of public buildings.
C i t y C o n s u l t i n g I n s t i t u t e
Page 52
Table: Budgeting in a self-government entity
The key assumptions and directions of investment policies of self-government entities are the
following:
ensuring compatibility with social and economic development conditions of self-government
entities, defined in strategic and urban planning documents,
ensuring continuation of the already began projects and the ones planned for the analysed
period, including key social and economic tasks,
assuming the estimated expenses on the basis of the present and the long-term budget
projections as well as macro-economic indicators,
assuming the expenses planned for the initial years on the basis of tender procedures, signed
contracts or cost estimates,
adaptation of the projects to operational programmes for the years 2007 – 2013, financed by the
EU (chance for a grant),
Budget assumptions
Present financial
situation of the entity
Major tasks
Investment projects
Forecast of macro-
economic indicators
Profit policy
Grants
Main threats
Initial assumption of budget
values
C i t y C o n s u l t i n g I n s t i t u t e
Page 53
introducing projects in case of which the Council of the particular entity has already undertaken
financial obligations,
maintaining indicators of debt and debt service on a reasonable level, not exceeding the statutory
limits (Law on public finance).
Limitations concerning debt levels for self-government entities are the following:
the total sum of instalments to be paid in the particular year as well as potential payoff of sums
resulting from guarantees granted by a self-government entity, together with due interest from
credits and loans, due interest, discount and redemption of securities issued by the entity must not
exceed 15% of the income planned for the particular budget year,
in case the relation of the total sum of the public debt and amounts due from sureties and
guarantees granted by public finance sector entities to the GDP exceeds 55%, the total sum of debt
and debt service increased by potential liabilities resulting from guarantees of a self-government
entity must not exceed 12% of the income planned for the particular budget year, unless these
liabilities had been incurred before the day this relation was published.
There are also certain limitations concerning the debt level of self-government entities:
the total debt of a self-government entity at the end of a budget year must not exceed 60% of
actual revenues of this entity in that particular year.
throughout a budget year, the total debt of a self-government entity at the end of each quarter
must not exceed 60% of planned revenues of this entity in that particular year.
1.3.3. Conclusions for JESSICA
In order to formulate the directions of investment policy, being the basis for a Multi-annual
Investment Plan, self-government entities:
- define project selection criteria, e.g. in accordance with its long-term objectives defined in
strategic documents such as development strategies or revitalization programmes,
- define own business potential and economic situation, as well as financial, economic and
technological feasibility of projects,
- choose the cheapest methods of financing, adequate to the investment type as well as
present and anticipated financial situation,
- formulate and then update a Multi-annual Investment Plan at least once a year, in
accordance with the investment policy,
- adapt multi-annual plans to annual budgets, introducing modifications caused by
demographic, financial or economic factors;
Multi-annual Investment Plans include:
C i t y C o n s u l t i n g I n s t i t u t e
Page 54
- principal assumptions, including those on the document update,
- projection of revenues and expenditures for the period covered by the plan as well as debt
and debt service ratios,
- general characteristics, including the structure of investment expenditures, new and
continued projects,
- material and financial plan, divided into groups, e.g. roads, revitalization, health care,
education, etc. The plan includes each project title, implementation period, total cost in
particular years as well as sources of financing;
Multi-annual Investment Plans include mostly projects aimed at social and economic
development (transport, investment attractiveness, sports, recreation, life quality and public
safety);
as investment is one of the primary public functions of self-governments, influencing the life
quality of inhabitants, resources devoted to investment are higher from year to year;
financial engineering of degraded areas regeneration projects comprises primarily resources
from ROP SL (Priority VI) and own contribution;
most projects included in the investment plans analysed are not coherent with the ones
included in Local Revitalization Programmes; this situation results from the following
reasons:
o LRPs have not been updated since the last call for proposals of the EU programming
period 2004 – 2006 or since selected projects have been included in particular
subregional development programmes of Śląskie Voivodship within ROP SL 2007 –
2013,
o There has still been no call for proposals announced in the present programming
period as the call has been withheld until further notice.
o Introduction of new projects or modification of the already included ones in the
course of the update process before the call for proposals.
Multi-annual Investment Plans and Local Revitalization Programmes have to be updated in
order to introduce potential urban regeneration projects to be co-financed from the
resources of ROP SL. Projects should be verified with regard to their scope, timetable and
cost. Moreover, new projects should be added to strategic documents in response to social
demands and needs.
C i t y C o n s u l t i n g I n s t i t u t e
Page 55
1.4. Identification and evaluation of specific potential JESSICA projects
1.4.1. Projects reported in a survey research
The present list of potential JESSICA projects is very comprehensive. The value of the projects may
exceed 150 mln EUR. The list has been developed on the basis of a survey research, conducted by
City Consulting Institute Sp. z o.o. and the Marshal Office in Katowice, as well as on the basis of
personal meetings of the Consultant representatives with members of local governments.
No City Project
1. BIELSKO – BIAŁA
Construction of a City Stadium on Rychlinskiego Street in Bielsko
– Biala.
2. BLACHOWNIA New Blachownia market.
3. BLACHOWNIA Repair of two business premises owned by the gmina of
Blachownia
4. BLACHOWNIA Revitalization of recreation areas around the Blachownia water
reservoir; a harbour and a yacht club.
5. CHORZÓW
Adaptation of a monumental municipal slaughterhouse for the
purpose of a business centre.
6. CHORZÓW Modernisation of a post-industrial shaft on Siemianowicka
Street.
7. CHORZÓW Construction of indoor tennis courts.
8. CHORZÓW Reconstruction of commercial pavilions and a local community
centre.
9. CHORZÓW Modernisation of the building of the Silesian College of
Computer Studies.
10. CHORZÓW Regeneration of a building of The Poznan School of Banking,
Faculty in Chorzow (66 Wandy Street).
11. CHORZÓW Regeneration of a building of The Poznan School of Banking,
Faculty in Chorzow (29 Sportowa Street).
12. CHYBIE
Regeneration of post-industrial areas in Chybie (Kuchenna and
Polna Street).
13. CIESZYN
Regeneration of the municipal market on Katowicka Street.
14. CIESZYN
Regeneration of the Cieszyn Venice area.
C i t y C o n s u l t i n g I n s t i t u t e
Page 56
15. CZELADŹ
Reconstruction and development of buildings for commercial
purposes (Rynek 26/28).
16. CZELADŹ Reconstruction and development of a building (Rynek 22) for
the purpose of a business centre.
17. CZELADŹ Reconstruction of a monumental pithead building for the
purpose of a training and cultural centre.
18. CZELADŹ Construction of commercial pavilions within the medieval Old
Town in Czeladz.
19. CZELADŹ Reconstruction of a monumental building of the “Elektrownia”
Modern Art Gallery.
20. CZERNICHÓW
Regeneration of the “Flamingo” Centre in Miedzybrodzie
Zywieckie.
21. CZĘSTOCHOWA Development of a recreation centre in Lisiniec.
22. CZĘSTOCHOWA Reconstruction of a tenement building on 44 Wolności Street.
23. CZĘSTOCHOWA Construction of a building on Śląska and Waszyngtona Streets
for service and hospitality purposes.
24. DĄBROWA GÓRNICZA Regeneration of Dabrowa Gornicza down-town – development
of post-industrial areas of the Defum factory.
25. DĄBROWA GÓRNICZA Regeneration of Dabrowa Gornicza down-town –development
of public space in the neighbourhood of the railway station.
26. DĄBROWA GÓRNICZA Regeneration of post-industrial buildings of the “Paryz” mine in
Dabrowa Gornicza.
27. DĄBROWA GÓRNICZA Regeneration of post-industrial areas of the “Paryz” mine in
Dabrowa Gornicza (Jadwiga heap).
28. GLIWICE
Development of investment grounds – Science and Technology
Park.
29. GORZYCE
Development of a Recreation Centre “Olza “.
30. JAWORZNO Construction of a multi-storey car park with commercial
premises in Jaworzno city centre.
31. KATOWICE Regeneration of Pawla, Wodna and Gornicza Streets in
Katowice.
C i t y C o n s u l t i n g I n s t i t u t e
Page 57
32. KATOWICE Regeneration of Mariacka and Dworcowa Streets in Katowice.
33. KŁOBUCK Reconstruction of the municipal open-air market.
34. KŁOBUCK Adaptation of a palace to a conference centre and revitalization
of the palace park in Kłobuck.
35. KŁOBUCK Development of the swimming pool area in the Sports and
Recreation Centre in Kłobuck.
36. LUBLINIEC Construction of a swimming pool in Lubliniec.
37. MIASTECZKO ŚLĄSKIE Adaptation of areas neighbouring the Zinc Mill in Miasteczko
Slaskie for business purposes.
38. OGRODZIENIEC
“Krępa” Recreation Centre in Ogrodzieniec.
39. POWIAT BĘDZIOSKI
Regeneration of Rogoznik and adaptation for the purpose of a
water sports centre.
40. RUDA ŚLĄSKA
Commercial Centre on Janasa Street.
41. SŁAWKÓW
Regeneration of the monumental centre of Slawkow – stage I –
commercial buildings.
42. ZAWIERCIE Cristal Valley – regeneration of post-industrial areas.
43. ZAWIERCIE Development of degraded urban areas surrounding the railway
station in Zawiercie.
The above projects have been analysed by the Consultant with regard to the following issues:
profitability (income generation capacity defined on the basis of a study of the documents
supplied by potential beneficiaries as well as personal meetings);
location (attractive location of the project);
stage of document preparation (technical plans, concepts, drafts, feasibility studies).
On the basis of the analyses conducted it may be stated that all projects are profitable or combine
the open access with commercial development.
Some projects are perfectly located (e.g. Development of a recreation centre in Lisiniec – 200 metres
from the Jasna Gora Sanctuary) that will be directly translated to their attractiveness.
The projects are consistent with urban planning documents, most of them have ready functional –
utility programmes and technical plans.
C i t y C o n s u l t i n g I n s t i t u t e
Page 58
On the basis of the above analysis one may state that as far as project maturity and readiness for
implementation are concerned, potential JESSICA beneficiaries are ready for the initiative
implementation.
Table: Analysis of selected projects7
No City Project
1. CZELADŹ Element Description
Project title Construction of commercial pavilions within the medieval Old Town in Czeladz.
Short description
The project concerns developing an area situated in the historical and monumental centre of Czeladź. It consists in building a complex of historically styled commercial pavilions within the medieval Old Town (together with water and sewage systems and transport infrastructure). 39 commercial premises located in a few pavilions with arcades will be constructed. The project location is very advantageous – in direct neighbourhood of the Market Square and the National Road no 94 from Wrocław to Kraków.
Project value Project value: 8.454.759 PLN The resources have been provided in the Multi-annual Investment Plan. Project timetable: 2010-2011.
Compatibility with the LRP
The project is compatible with the LRP and other strategic documents. The Local Revitalization Plan of the City of Czeladź was approved by the resolution LVI / 765 / 2005 of 21 July 2005. The Plan will be updated after the issue of state aid in regeneration projects will will have been regulated by appropriate laws (as it influences the financial engineering of projects) and after the Environmental Impact Assessment procedures will have been completed. The project is complementary with regeneration actions undertaken in the years 2006-2007 in the neighbouring areas: the project consisting in revitalization of the urban area and complete technical infrastructure supply of 10 streets and the Market Square was supported by an IRDOP grant.
PPP The project does not directly necessitate a contribution of a private partner. However, there are private parties interested in it:
7 The above compilation has been developed for all projects mentioned in the present Study. The above examples are to prove
the great diversity of actions to be undertaken and stages of preparation of particular beneficiaries.
C i t y C o n s u l t i n g I n s t i t u t e
Page 59
No City Project
private entities willing to create a commercial network in cities
association of merchants (capital contribution)
ENION S.A. (Turon Group) building its own power supply network will be a project partner. Technical conditions have been already agreed. Another project partners is ZIK Sp.o.o. – a company managing the municipal water and sewage system.
Technical documentation
The project has:
complete technical plans,
all necessary opinions and agreements,
building permission for public purpose investment,
decision on environmental conditions of approval of an undertaking,
building permit,
technical graphs,
cost estimates, bill of quantities, Specification for Work Accomplishment and Acceptance
2. CZĘSTOCHOWA Element Description
Project title Development of a recreation centre in Lisiniec. Short description
Development of an urban area (about 40 ha), situated in the neighbourhood of the city centre and the Jasna Góra Sanctuary. Planned usable area – 11.000m2. Functional programme:
high quality aquapark
wellness & Spa
sport & fitness
entertainment facilities Total water area – 1590 m2
Project value 127.000.000 PLN Compatibility with the LRP
The project has been included in the Municipal Revitalization Programme (updated in 2008).
PPP The project is anticipated to be implemented within PPP.
Technical documentation
Functional – utility programme.
3. JAWORZNO Element Description
Project title Construction of a multi-storey car park with commercial premises in Jaworzno city centre.
Short description
The aim of the project is to: - provide parking places in the city centre (in the neighbourhood of the Old Town Market), - development of one of the key city districts for
C i t y C o n s u l t i n g I n s t i t u t e
Page 60
No City Project
the purposes of a pedestrian zone; construction of a fine arts square between the library and the museum; - combination of parking and service functions. The project product will be a four-storey building with 282 parking places (total area of 9 490 m2). The ground floor will be devoted to service points.
Project value Estimated project value: 13 895 000 PLN No resources have been provided for the project in the Multi-annual Investment Plan as the city still searches for additional sources of financing.
Compatibility with the LRP
The project is compatible with the Local Revitalization Programme and is located in a revitalization area. It is also compatible with the objectives of measure 6.2.1 Revitalization of big cities of the ROP SL 2007-2013.
PPP Possibility of establishing PPP. Technical documentation
Spatial conception of a multi-storey car park (developed in 2009).
1.4.2. Other potential projects
The list of potential JESSICA projects will be successively broadened, depending on the following
factors:
information and methods of reaching potential beneficiaries;
implementation of public-private partnerships;
JESSICA operation and opinions on the mechanism;
1.4.3. Assessment of the interest of potential beneficiaries in a revolving financial
instrument
In the course of work leading to the development of the Report, a survey research has been
conducted and several meetings between City Consulting Institute Sp. z o.o. experts with
representatives of local government authorities have been organised.
Interest of potential beneficiaries may be estimated on the basis of the following factors:
list of potential projects;
interest in the financing method (including potential institutional solutions);
information transferred from Municipal Offices to their budget entities.
C i t y C o n s u l t i n g I n s t i t u t e
Page 61
1.5. SWOT analysis for JESSICA
The SWOT analysis has been developed on the basis of regional conditions concerning urban
regeneration projects.
Possibility of financing projects
STRENGTHS WEAKNESSES
large number of wide-range projects that are already prepared or implemented,
continuity in financing regeneration projects,
greater scope of project effect achieved thanks to implementation of integrated projects, characterised by wider scope and value, also commercial and generating considerable profit ,
participation of the private sector in project financing,
fast payment schedule and availability of resources as well as possibility of quick use of resources,
wide range of financial products (loans, credits, capital contribution, guarantees),
a revolving mechanism opening a long-term possibility of financing
relatively little resources,
necessity of searching for additional sources of financing the mechanism in order to develop it,
lack of experience with financial mechanisms aimed at urban development,
little knowledge on JESSICA among potential beneficiaries,
lack of Integrated Urban Development Plans; Local Revitalization Programmes comprise projects that are not systemically related,
unpreparedness of local governments to conclude PPP contracts,
List of potential projects
•over 150 projects have been reported, out of which 43 may be directly placed in the JESSICA context;
•preliminary list of projects has been prepared;
Financing method
•local governemtns search for attractive methods of financing their projects, including revolving mechanisms enabling them to obtain resources in the most advantageous moment of a particular project implementation;
•local governements prove considerable interest in participation in UDFs
Information on JESSICA
•information on JESSICA is still very poor;
•main principles of JESSICA operation have been presented during the meetings between the Consultant and local government representatives;
•some local governement entities informed their budget entities and other potential beneficiaries on the chance offered by JESSICA.
C i t y C o n s u l t i n g I n s t i t u t e
Page 62
OPPORTUNITIES THREATS
possibility to implement competitive, revolving financial mechanisms,
greater allocation of resources achieved thanks to participation of numerous institutions and partners in JESSICA,
interest rate rebates,
mild monetary policy of the state,
failure to meet the funding gap criteria,
readiness of self-governments and financial institutions to finance regeneration projects,
implementation of PPP projects, financed from private resources,
higher interest rates on credits and loans,
strict monetary policy of the state,
other competitive financial mechanisms,
difficult situation on the credit market and restrictions introduced by banks,
engagement of self-governments in projects that are not related with revitalization,
high debt and debt service ratios of local government entities,
passive attitude of public entities towards projects implemented within PPP,
C i t y C o n s u l t i n g I n s t i t u t e
Page 63
1.6. Conclusions for JESSICA
•beneficiaries prepare projects on the basis of guidelines that will enable them to apply for EU grants;
•formal requirements, eligibility criteria and lists of potential beneficiaries correspond to JESSICA regulations;
•there is no need to introduce any key changes to ROP SL in the process of JESSICA implementation;
The market of regeneration projects in Silesia has been
to a considerable extent shaped by the formal
requirements of IRDOP and ROP SL
•Beneficiaries mostly apply for grants, what results in the development of non-profit projects, whose maintenance in long perspective becomes a burden for local governments;
•Revolving mechanisms offer a possibility of better planning and searching for project partners;
There is a necessity to implement revolving financial mechanisms
•as there are no trainings on JESSICA, knowledge of self-government representatives on the initiative is very poor;
There is no system of information and trainings on
JESSICA
•most regeneration projects do not result from systemic solutions;
•LRPs are developed in order to adapt the document to potential projects;
•mechanisms should be introduced in order to necessitate complex urban planning;
Application procedure based on Integrated Urban
Development Plans should be considered
•in case of JESSICA projects it is necessary to evaluate their profitability and possibility of self-financing
Project profitability should be added to the evaluation
criteria
C i t y C o n s u l t i n g I n s t i t u t e
Page 64
2. Financial and social analysis for JESSICA implementation 8
2.1. Present financial instruments for urban regeneration projects
Currently there are no funds created from public resources and specialised in financing complex
regeneration projects in Silesia. Most revitalization projects are financed externally, primarily by
bank loans. Nevertheless, bank credits are available only for th entities meeting specific criteria and
requirements. This option is also strongly dependent on the situation on the financial market,
including interest rate strategy of national banks.
The main financial resources for regeneration projects in the Śląskie Voivodship are:
Internal funds of territorial self-government and other public institutions,
European Union funds,
European Investment Bank (EIB) funds,
Commercial banks’ funds,
Private equity (for commercial projects)
Financial resources obtained for renovation projects are often related to operational plans or funds,
e.g. to regional development. Each individual financial instrument used in Silesia is described below.
The Śląskie Regional Operational Programme (ROP SL) for 2007 – 2013
The main European Union financial source for Silesian regeneration projects is the European Regional
Development Fund (ERDF), within the Śląskie Regional Operational Programme for 2007-2013 –
Priority VI. Sustainable urban development.
Priority VI supports projects related to reinforcing regional development centres and regeneration of
degraded areas. This support includes ventures associated with the development of metropolitan
functions (including projects concerning characteristic objects or representative areas) located in big
cities of the Silesian agglomeration. As part of the local development centres’ strengthening plan, 20
million PLN was granted to support projects implemented in city agglomerations defined in the
Spatial Development Plan of the Silesian Voivodship (19 urban districts/cities, combined into 4 city
agglomerations).
8 The level of potential contribution of particular shareholders has been defined on the basis of the development
perspective of the potential JESSICA projects. In the Consultant’s opinion, the engagement of particular shareholders may be even higher than the one adopted foe analysis purposes. Due to the fact that the potential JESSICA projects are well prepared and correspond to regional development strategies, it was assumed the EIB may also be interested in financing them.
C i t y C o n s u l t i n g I n s t i t u t e
Page 65
Revitalization of post-state farm environments, post-industrial and post-military degraded areas puts
emphasis on restoring public space order. These projects concern development of urban areas,
infilling the existing buildings, providing investment areas with access to the domestic and
international road network. Apart from the full scope of revitalization activities for degraded areas,
additional housing investments are planned, dedicated to remove asbestos from existing buildings.
All degraded areas regeneration projects have to result from Local Revitalization Programmes.
Projects putting emphasis on economical recovery, development of new forms of economic activity
or creating new jobs, are prioritized.
Regeneration activities have been divided for government units with various population potential.
Maximum grant amounts to 85% of the total eligible cost of investment.
Currently, projects to be financed are chosen in a competition within Subregional Development
Programmes or from the indicative list of key projects. The ERDF’s total financial pool for Priority VI is
312,8 million PLN. The resources devoted to the key projects amount to 153,85 mln PLN. 47,29 mln
PLN was devoted to subregional projects and 111,66 mln PLN to the contest ones.
Actions complementary to regeneration measures distinguished in ROP SL are the following:
Priority I: Technical research and development (R&D), innovation and entrepreneurship,
Measure 1.3. Technology and innovation transfer.
Priority II: Knowledge society, Measure 2.1 Knowledge society infrastructure; Measure 2.2.
Development of public e-services.
Priority III: Tourism, Measure 3.2. Tourism-related infrastructure. 3.3 Tourism information
systems, 3.4. Tourism promotion.
Priority IV: Culture, Measure 4.1. Culture infrastructure, 4.2. Culture information systems,
4.3. Culture promotion.
Priority V: Environment, Measure 5.3. Quality air and renewable energy sources.
Priority VII: Transport, Measure 7.1. Modernization and development of transport system,
7.2. Public transport.
Priority VII: Educational infrastructure, Measure 8.1. Higher education infrastructure.
Priority IX: Health care and recreation, Measure 9.3. Local sport infrastructure.
Operational Programmes for the years 2007 – 2013
Renovation ventures may be also realized together with other operational programmes, e.g.:
Rural Development Programme for 2007 – 2013.
Priority axis III. Quality of life in rural areas and differentiation of rural economy.
C i t y C o n s u l t i n g I n s t i t u t e
Page 66
Infrastructure and Environment Operational Programme.
Priority axis XI. Culture and cultural heritage.
Priority axis XIII. Higher education infrastructure.
Priority axis VII. Environment friendly transport.
Human Capital Operational Programme for 2007 - 2013
Priority I. Employment and social integration, Priority VII. Social integration promotion.
Innovative Economy Operational Programme for 2007 - 2013
Priority axis VI. Polish economy on the international market in 2007-2013.
Operational Programme: Trans-border Cooperation – Republic of Poland – Slovak Republic –
2007 – 2013 and Operational Programme: Trans-border cooperation Czech Republic –
Republic of Poland - 2007 – 2013.
A loan from the European Investment Bank for financing regional development – granted with the
BGK support.
The loan for regional development in the BGK can be granted to the following entities:
Territorial self-government units (Polish acronym - JST): municipalities, associations of
municipalities, districts and voivodships,
JST subsidiaries and budget entities,
Other units, if the credited project aims at regional development.
The condition to receive the loan is to dedicate it for:
Co-financing projects supported by structural funds of the EU,
Co-financing projects according to the regional development strategy (without the EU
support),
The loan can embrace various economy sectors. The objectives of the loan may include:
environment protection, infrastructure, knowledge economy development, education and health.
C i t y C o n s u l t i n g I n s t i t u t e
Page 67
Table: The EIB funds for regional development.
Sector The bank loan object
Environment
protection
Drinking water supply and distribution
Waste water and sewerage,
Environment protection equipment,
Reduction of noise and vibration,
Collection, transport and recycling of waste,
Renovation of protected monuments and buildings,
Regeneration of urban constructions,
Other activities related to environment protection.
Infrastructure
Transportation (roads, rails, ports and airports),
Telecommunication (e.g. telecommunication network),
Industrial parks and zones,
Tourist infrastructure,
Sport, recreation and cultural objects.
Knowledge
Economy
Development
Human capital and society’s qualification in line with the concept
of lifelong learning, access to high quality information and
communication technology infrastructure,
Education, commercial and administrative processes within the
following areas: higher education, university research, media,
logistic/mail processes, e-business, e-government,
Innovative products and processes/services supporting long-term
competitiveness of the economy.
Education
Educational infrastructure and auxiliary facilities (e.g. student
accommodation, sport facilities),
Education equipment and teaching tools (e.g. textbooks),
Curricula, teacher training programmes etc.,
Vocational training and lifelong learning programmes in education,
Research components in higher education (e.g. science parks),
E-learning and open universities,
Development and knowledge dissemination via the media.
Health
Buildings and equipment at all heath care levels, including primary
health care, clinics, hospitals, hospices, psychiatric care,
C i t y C o n s u l t i n g I n s t i t u t e
Page 68
Investment in research and development (education centres,
equipment, hardware and software for staff training, laboratories,
diagnostic centres),
Centres and programmes for public health and preventive care,
Infrastructure and programmes for preventive and social healthcare
including: social support, nursery, care for the disabled etc.
Veterinary projects.
EIB funds can cover up to 50% of total project costs. In case of projects supported by other EU funds
or loans, the total EU support can cover maximum 90% of the total cost.
The minimum and maximum cost of a project in case of this financing method is 40 thousand and 25
million EUR respectively. The total cost of the loan granted cannot exceed 12.5 million EUR.
A bank loan is granted in Polish zlotys for minimum of 4 and maximum of 5 years. The grace period
for repayment is up to 5 years. Interest rate of loans is variable and covers:
Variable basis rate, settled by the EIB every 3 months,
Fixed margin for the BGK.
The Bank charges also commission for granting a credit.
Examples of regeneration projects co-financed by the EIB in Silesia are the following:
City of Częstochowa: Reconstruction of the areas surrounding Najświętszej Maryi Panny
Avenues, project value: 12.370.000 PLN, EIB resources: 7.865.250 PLN
City of Częstochowa: Development of the amphitheatre by the Niemena Promenade for
recreation purposes, project value: 5.300.000 PLN, EIB resources: 780.000 PLN,
City of Katowice: Reconstruction of the Katowice Down Town, project value: 120.742.701
PLN, EIB resources: 4.512.000 PLN,
City of Katowice: Reconstruction of the communication system around the Jantor ice rink,
project value: 9.633.039 PLN, EIB resources: 1.144.000 PLN,
City of Katowice: Rawa Boulvars, project value: 20.127.272 PLN, EIB resources: 6.787.699
PLN.
Domestic funds
Funds for regeneration projects can also come from the following financial investment instruments:
Social housing support programme from the Surcharge Fund;
The Municipal Investment Development Fund;
C i t y C o n s u l t i n g I n s t i t u t e
Page 69
The Thermomodernization Fund;
The TBS Programme (Polish: TBS - Towarzystwo Budownictwa Społecznego - Social Housing
Society)
The National Fund for Environmental Protection and Water Management
The financial instruments mentioned above (except for the NFEPWM) are established, assigned or
transferred on the basis of separate Acts to be realized by the BGK. The Bank plays a special and
important role in the Polish banking system: it finances and supports housing development,
expansion of small and medium sized companies and local government operations. The BGK, as a
state financial institution of high credibility, specializes in serving the public finance sector.
Governmental programme of financial support from the Surcharge Fund devoted to social housing,
sheltered housing, flophouses and lodging houses for the homeless.
The Surcharge Fund supports the following projects:
Construction of a building, including extension of an existing property owned by the investor
or in their perpetual usufruct;
Renovation and rebuilding of a property or its part (owned by the investor and fit for human
habitation);
Change in the way of using a property or its part (owned by the investor and requiring
renovation or rebuilding);
Purchase of a housing property or a building;
Purchase of a housing property or a building and its renovation;
Covering a part of costs of a TBS project – building a housing property by the Social Housing
Society.
Table: Maximum value of financial support from the Surcharge Fund.
Venture Social housing
Sheltered housing
Flophouses and lodging houses for
the homeless
Council housing
Investor Type of investment
Municipality
Munici-pality, county
Municipality, association of
municipalities, public benefit organization
Municipality
Construction work, including extension or superstructure
30% 30% 40% 30%
Renovation and rebuilding of a property or its part
40% 40% 50% 40%
Changing the way of using a property or its part
40% 40% 50% 40%
C i t y C o n s u l t i n g I n s t i t u t e
Page 70
Purchase of a housing property or a building
30% 30% -- 30%
Purchase of a housing property or a building and its renovation
30% 30% -- 30%
Housing property built
by TBS
Construction work, including extension and superstructure
40%2 40% -- 40%
Renovation or rebuilding
50%2 50% -- 50%
Changing the way of using a property
50%2 50% -- 50%
The Municipal Investment Development Fund
The Municipal Investment Development Fund was established by the BGK on 1 January 2004 on the
basis of the Act of 12 December 2003. The MIDF grants preferential loans to municipalities and their
associations for the purpose of preparation of the documents necessary for municipal investment
projects, to be co-financed by EU funds. The loan can be spent on a feasibility study, a cost and
benefit analysis and other project documents, including analyses, expertises or studies necessary for
the venture.
The municipalities applying for a MIDF loan may choose procurement by a single-source procedure
instead of organizing a tender open to other banks.
The loan amount cannot exceed 500 000 PLN per one project and 80% of the net budgeted costs. The
credit can be transferred at once or in instalments. In order to get the money off, 20% of the net cost
of technical plans has to come from own resources.
The crediting period cannot be longer than 36 months. Nevertheless, the BGK can extend it by up to
18 months of grace period. The interest rate for the loan is calculated as 0.5 of bill of exchange
rediscount rate accepted by the National Bank of Poland as a rediscount.
The BGK charges interest - 1% of the loan amount. The credit and interest payback is made on a
monthly or quarterly basis.
The Thermomodernization Fund;
The basic goal of the Thermomodernization Fund is to support investments in thermomodernization,
renovation projects and rebuilding of single-family houses, financed jointly with the loans from
commercial banks. This support is called accordingly: “thermomodernization bonus”, “renovation
C i t y C o n s u l t i n g I n s t i t u t e
Page 71
bonus” and “compensation bonus”, and is accounted as a part of repayment of a bank loan taken for
the particular project.
The thermomodernization bonus can be requested by an owner or administrator of:
a residential building,
multi-apartment residential buildings,
public buildings owned by local self-government units and used for public functions,
a local heating network,
local heat emitters.
The bonus cannot be granted to budgetary units or entities.
The thermomodernization bonus can be granted to investments in thermomodernization, if the goal
of the venture is:
Reduction of energy consumption necessary for air and water heating in residential
buildings, multi-apartment residential buildings and buildings owned by territorial self-
government units, used for public functions,
Minimizing costs of acquiring heat, delivered to the above mentioned buildings via
a technical connection to a centralized heat source created as a result of liquidation of local
heat sources,
Decrease of initial energy losses in local heating networks and connected local heat sources,
Partial or total replacement of existing energy sources for renewable energy or application
of high-efficiency cogeneration with obligatory savings in energy consumption, regulated by
an adequate act.
In order for a project to be considered eligible, an internal energy audit has to be presented and
positively verified by the BGK.
From 19 March 2009, the value of the thermomodernization bonus has been equal to 20% of the
granted credit (no more than 16% of the total project cost and double expected annual savings on
energy costs, evaluated on the basis of the energy audit).
BGK investment loans for territorial self-government units.
This loan may be spent on the following tasks:
financing the planned deficit in the JST’s budget,
paying off debt obligations resulting from issued securities as well as incurred loans and
credits,
C i t y C o n s u l t i n g I n s t i t u t e
Page 72
re-financing expenses borne in the particular budgetary year, in which the self-government
unit was applying for a BGK loan,
funding other ventures and expenses.
The investment loan can be paid at once or as a non-renewable credit line, paid in tranches.
The bank can finance up to 100% of venture costs. The maximum payback period is 10 years, but the
bank can decide to grant the investment credit for a longer period (if it is in line with the
Specification of Essential Terms of a Contract) or agree on grace period for credit and interest
repayment.
In order to receive an investment loan, a potential borrower has to:
provide legal protection of the loan repayment,
have a sufficient credit rating,
prove his own contribution to the credited project, if applicable.
The interest rate is based on fixed market rates and the bank’s profit margin is set up individually.
The Social Housing Society (TBS) Programme
In accordance with the Act of 2 April 2009, the BGK is obliged to undertake tasks resulting from the
state housing and housing development policy (including rental building).
The main aim of the TBS Programme is to increase the availability of apartments for people whose
income does not enable them to satisfy their housing needs on the market. The main tool to achieve
this objective is a preferential loan for:
Social Housing Societies (TBS) and housing cooperatives for building and adapting
apartments for rent;
Housing cooperatives for building new flats to be inhabited on the basis of cooperative
housing tenancy law;
Municipalities for building technical infrastructure auxillary to housing estates.
TBSs as well as housing cooperatives are non-profit organizations; their statuary goal is to satisfy
housing needs of a society. Apartments financed by loans from the TBS Programme can be rented to
families/individuals, who do not have legal rights to any other living premises and have limited
income per capita. Implementation of the social programme for rental housing is supported by
territorial self-government units.
The programme in its current shape will be relevant for all applications sent before 30 September
2009.
C i t y C o n s u l t i n g I n s t i t u t e
Page 73
Table: Summary of the objective, value, crediting period and interest rate of TBS Programme loans.
The National Fund for Environmental Protection and Water Management (NFEPWM)
The National Fund for Environmental Protection and Water Management (NFEPWM) is the biggest
institution implementing the National Environmental Policy. The NFEPWM finances investments in
environment protection and water management in the areas important from the perspective of
accommodating to the European Union regulations and norms. The objective of the NFEPWM is to
financially support ecological investments of nationwide and cross-regional importance as well as
local projects, important from the environment protection perspective.
Distribution of financial resources within the NFRPWM is organized in the following areas:
air protection,
water protection and water management,
protection of the Earth surface,
nature, landscape and forestry preservation,
geology and mining,
ecological education,
the State Environmental Monitoring,
multidisciplinary programmes,
extraordinary environmental threats,
expertises and research.
There are three funding forms available in case of the NFRPWM:
•Building or adapting apartments for rent with low rentals or assuring cooperative housing tenancy rights
Objective of the loan
•Max. 70% of costsValue
•Approx. 35 years, depending on the rediscount rate in the NBP and inflation for construction and assembly production.
Crediting period
•Variable, set as an effective rate - 50% of rediscount rate in NBP, not less than 3.5% (current interest rate for all new loan contracts is 3.5%, same for existing contracts if they were negotiated, 4.5% for all the remaining contracts signed before 6 May 2004.
Interest rate
C i t y C o n s u l t i n g I n s t i t u t e
Page 74
loan (granted by the NFRPWM, loans or credit lines granted by other banks but from the
NFRPWM’s resources, project co-financing from both NFRPWM and bank resources),
subsidy (investment and non-investment subsidies, surcharges to bank loans, amortization)
capital financing (taking over company’s stocks or shares in order to reach ecological
effects).
2.2. Budgetary implications of JESSICA for the Silesia Managing
Authority
In order to define the budgetary and financial effects of the JESSICA initiative, a cash flow forecast
was prepared for the following options:
Variant zero – V0 - without implementing the JESSICA initiative, with the subsiding mechanism
of the Śląskie Regional Operational Programme for 2007-2013, as the sole funding source.
Variants including the JESSICA initiative:
V1 – establishment of 1 Urban Development Fund (UDF) from the ROP SL funds,
V2 – establishment of 1 UDF from the ROP SL and shareholders’ funds (e.g. local self-
government units),
V3 – establishment of a Holding Fund (HF) and 2 UDFs from the ROP SL and stakeholders’
funds, e.g. local self-government units and banks,
V4 – establishment of a HF managed by the EIB and >2 UDFs from the ROP SL and
shareholders’ funds (e.g. local self-government units and banks)
For the purpose of this study, the initial value of resources available from the ROP SL for
regeneration projects (within Priority VI) was estimated to be the same in all considered options,
both in case of the granting system and in case of JESSICA. The projected cash flow was prepared in
PLN. A fixed exchange rate 1 EUR = 4 PLN was assumed for the analysis purposes.
The analysis time horizon (years: 2010-2022) has been adopted for the period needed to establish
JESSICA managing structures, develop implementation procedures, select first projects to be
implemented, and the 10 year period of payoff of loans/credits, in order to show the financial
leverage effect and the revolving mechanism.
C i t y C o n s u l t i n g I n s t i t u t e
Page 75
2.2.1. Cash flow in case of the traditional donation system - variant 0
Table: Analysis assumptions – V0.
Time horizon Years: 2010-2022
From 2010 – spending the first money from the ROP SL, Priority VI.
2015 – end of the spending period, e.g. according to the n+2 rule (binding
in case of EU funds).
Financial sources European Regional Development Fund – Śląskie Regional Operational
Programme for 2007-2013, Priority VI. Sustainable urban development.
Funding pool – initial
value
40 million EUR = 160 million PLN
Income tax Subsidies are income tax free for legal persons (in accordance with the
binding law).
Table: Cash flow for subsiding mechanisms of the ROP SL (in million PLN)
0,00
20,00
40,00
60,00
80,00
100,00
120,00
140,00
160,00
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
End of year balance Inflows Outflows - subsidy use
C i t y C o n s u l t i n g I n s t i t u t e
Page 76
Table: Financial flow for the subsiding mechanism of the ROP SL in PLN (V0).
Item Years
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
End of year balance 140,00 95,00 50,00 20,00 5,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
Inflows 160,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
Outflows –subsidy use 20,00 45,00 45,00 30,00 15,00 5,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
C i t y C o n s u l t i n g I n s t i t u t e
Page 77
2.2.2. Cash flow in case of JESSICA implementation – V1 – one UDF.
This variant assumes establishment of 1 UDF, for which the start-up capital would come from the
Śląskie ROP for 2007-2013 funds only.
Table: Analysis assumptions – V1.
Time horizon Years: 2010-2022
Signing the contract for establishing and managing the UDF - end of 1st
half of 2010.
Number of UDFs – 1.
2nd half of 2010 – transfer of funds to the UDF, arranging selection
procedures, project preparation.
2011 – implementation of the first projects.
Financial sources ERDF – Śląskie ROP, Priority VI. Sustainable Urban Development
Funding pool – initial
value
40 million EUR = 160 million PLN
Financial income Income from bank deposit interests: 3% per year.
Income from the granted loans: 4% per year.
Operational costs Management cost: maximum 3% per year of the registered capital (ROP SL
resources).
Income tax Taxation of income on interest rate deposits and accounts: 19%
Taxation of income from granted loans 19%
Average payback
period
20 years
Grace period 2 years
Granted loan
commission
None
Investing unused UDF
capital
Fund relocation for new ventures of minimum 30 million PLN.
C i t y C o n s u l t i n g I n s t i t u t e
Page 78
Table: Advantages and disadvantages of V1.
Disadvantages Advantages
High organisational costs of the MA related with
setting up organizational structures, guidelines
for JESSICA management (personal costs, external
expertise, equipment etc.).
Low costs of program management during
JESSICA implementation, primarily connected
with simple organizational structure and low
demand for highly qualified human resources.
Impossibility to obtain the financial leverage
effect. Low potential for finding shareholders due
to low impact on the market and competitive
mechanisms of financial and capital markets.
Clear and standardized operation methods.
Insufficient MA experience or its complete lack in
implementation of similar projects (financial
mechanisms). Additional costs for expertise
outsourcing or employing consultants.
Possibility of delay in JESSICA implementation,
and even in the development of procedures.
Few years of standstill on loans, due to allocation
of all available resources, 2 years of grace period
and the loan payoff period.
C i t y C o n s u l t i n g I n s t i t u t e
Page 79
Table: Financial flows for variant 1 [million PLN] - V1.
Details Arranging UDF
Use of EU funds Long term operational plans
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Year-end balance of UDF funds
159,54 159,59 160,53 161,90 163,36 164,02 164,86 165,91 168,25 170,02 172,01 175,22 177,97
161,94 4,85 5,74 6,17 6,25 5,46 5,64 5,85 7,14 6,57 6,79 8,01 7,55
In-flow 160,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
Fund transfer from the Managing Authority
1,94 4,85 5,74 6,17 6,25 5,46 5,64 5,85 7,14 6,57 6,79 8,01 7,55
Net financial income from interest on deposits and loans
2,40 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80
2,40 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80
Out-flow 1,94 4,85 5,74 6,17 6,25 5,46 5,64 5,85 7,14 6,57 6,79 8,01 7,55
Management fee 0,00 1,20 3,20 5,20 6,72 6,72 6,72 6,72 8,04 8,04 8,04 9,24 9,24
0,00 0,23 0,61 0,99 1,28 1,28 1,28 1,28 1,53 1,53 1,53 1,76 1,76
Financial income 0,00 0,97 2,59 4,21 5,44 5,44 5,44 5,44 6,51 6,51 6,51 7,48 7,48
2,40 4,79 3,89 2,42 1,00 0,03 0,24 0,51 0,77 0,08 0,34 0,65 0,08
Income from interest on loans (gross)
0,46 0,91 0,74 0,46 0,19 0,00 0,05 0,10 0,15 0,01 0,06 0,12 0,02
Tax for interest related income 1,94 3,88 3,15 1,96 0,81 0,02 0,19 0,41 0,63 0,06 0,27 0,52 0,07
Income from interests on loans (after taxation)
3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00%
Income from interests on bank deposits (gross)
3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00%
Tax for interest related income 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00%
Income from interests on deposits (after taxation)
19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00%
20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00
C i t y C o n s u l t i n g I n s t i t u t e
Page 80
Important values: 0,00 30,00 50,00 50,00 38,00 0,00 0,00 0,00 33,00 0,00 0,00 30,00 0,00
UDF management costs - % 0,00 30,00 80,00 130,00 168,00 168,00 168,00 168,00 201,00 201,00 201,00 231,00 231,00
Deposit interest rate 0,00 0,00 0,00 1,50 4,00 6,43 8,13 7,80 7,40 7,01 8,29 7,94 7,52
Loan interest rate 0,00 30,00 80,00 128,50 162,50 156,08 147,95 140,15 165,75 158,74 150,45 172,52 164,99
Tax on credit and deposit related income
159,54 129,59 80,53 33,40 0,86 7,95 16,91 25,77 2,50 11,28 21,56 2,70 12,97
C i t y C o n s u l t i n g I n s t i t u t e
Page 81
160
0 0 0 0 0 0 0 0 0 0 0 0
160
Authorised share capital 2010-2022 (million PLN)
kapitał przekazany przez IZ (środki RPO)
150,00155,00160,00165,00170,00
175,00
180,00
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
UDF funds balance at the end of each year [million PLN]
Capital transfered by the MA (ROP funds)
C i t y C o n s u l t i n g I n s t i t u t e
Page 82
0,00
50,00
100,00
150,00
200,00
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Unused capital of UDFat the end of each year [million PLN]
0,00
20,00
40,00
60,00
80,00
100,00
120,00
140,00
160,00
180,00
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
UDF operations
pożyczki udzielone w danym roku spłaty pożyczek saldo udzielonych pożyczekLoans Balance of loans Credit payback
C i t y C o n s u l t i n g I n s t i t u t e
Page 83
2.2.3. Cash flow in case of JESSICA implementation – V2 – 1 UDF created from the ROP
and investors (JST) funds.
This variant assumes that there is 1 UDF established, with the initial capital created from the
Śląskie ROP funds and shareholders’ funds (JST)
Table: Analysis assumptions– V2
Time horizon Years: 2010-2022
Signing the contract for establishing and managing the UDF – end of
1 half of 2010.
Number of UDFs – 1.
2 half of 2010 – ROP funds transfer to the UDF, arranging selection
and realization procedures, project preparation.
2011-2012 – transfer of shareholders’ funds to the UDF.
2011 – implementation of the first projects.
Financial sources European Regional Development Fund – Śląskie ROP 2007-2013 –
Priority VI. Sustainable urban development.
Shareholders commitment – territorial self-government units (JST).
Funding pool – initial value ROP: 40 million EUR = 160 million PLN
JST: 24 million PLN
Financial income Income from bank deposits: 3% per year.
Income from bank loans: 4% per year.
Operational costs Management cost: maximum 3% per year of the registered capital
(ROP SL resources).
Income tax Taxation of income on interest rate deposits and accounts: 19%
Taxation of income from granted loans: 19%
Average payback period 20 years
Grace period 2 years
Granted loan commission None
Investing unused UDF capital Fund relocation for new ventures of 30 million PLN.
C i t y C o n s u l t i n g I n s t i t u t e
Page 84
Table: Advantages and disadvantages of V2.
Disadvantages Advantages
High organisational costs of the MA connected with setting
up organizational structures, guidelines for JESSICA
management (personal costs, external expertise,
equipment etc.).
Low costs of management, primarily
resulting from simple organizational
structure and low demand for highly
qualified human resources.
Low possibility of obtaining the financial leverage effect.
Few years delay in the process of contributing capital by
potential shareholders, due to lack of strong impact and
competitive mechanisms on capital and investment
markets.
Clear and standardized operation
methods.
Insufficient MA experience or its complete lack in
implementation of similar projects (financial mechanisms).
Additional costs for expertise outsourcing or employing
experts.
Possibility of delay in JESSICA realization, even in the
development of procedures.
As it would be one of many loan funds, potential
shareholders (cities) would prove little interest in it.
Few years of standstill on loans, due to allocation of all
available resources, 2 years of grace period and the loan
payoff period.
C i t y C o n s u l t i n g I n s t i t u t e
Page 85
Table: Financial flow for variant 2 [million PLN] – V2.
Details Arranging UDF Use of EU funds Long term operational plans
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Year-end balance of UDF funds 157,60 153,77 151,89 159,95 160,01 160,30 177,33 178,36 179,86 180,89 182,89 184,90 186,90
160,00 0,97 2,92 12,86 5,18 5,41 22,15 6,79 7,25 6,79 7,76 7,76 7,95
In-flow 160,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
Capital granted by the MA 8,00 16,00
Capital granted by other shareholders (including cities)
0,00 0,97 2,92 4,86 5,18 5,41 6,15 6,79 7,25 6,79 7,76 7,76 7,95
Net financial income from interest on deposits and loans
2,40 4,80 4,80 4,80 5,12 5,12 5,12 5,76 5,76 5,76 5,76 5,76 5,94
2,40 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80
Out-flow 0,00 0,00 0,00 0,00 0,32 0,32 0,32 0,96 0,96 0,96 0,96 0,96 1,14
Management fee 0,00 0,97 2,92 4,86 5,18 5,41 6,15 6,79 7,25 6,79 7,76 7,76 7,95
Profit commission from loan’s interests – for shareholders
0,00 1,20 3,60 6,00 6,00 6,00 7,20 7,20 7,20 7,20 8,40 8,40 8,40
Financial income 0,00 0,23 0,68 1,14 1,14 1,14 1,37 1,37 1,37 1,37 1,60 1,60 1,60
Income from interest on loans (gross, ROP capital) 0,00 0,97 2,92 4,86 4,86 4,86 5,83 5,83 5,83 5,83 6,80 6,80 6,80
Tax for interest related income 0,00 0,00 0,00 0,00 0,32 0,32 0,32 0,96 0,96 0,96 0,96 0,96 1,14
Income from loans (after taxation)
Income from interest on loans (gross, shareholders capital)
0,00 0,00 0,00 0,00 0,00 0,24 0,00 0,00 0,48 0,00 0,00 0,00 0,00
Income from interests on bank deposits (gross) 0,00 0,00 0,00 0,00 0,00 0,01 0,00 0,00 0,02 0,00 0,00 0,00 0,00
Tax for interest related income 0,00 0,00 0,00 0,00 0,00 0,23 0,00 0,00 0,46 0,00 0,00 0,00 0,00
Income from interests on deposits (after taxation)
Important values: 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00%
UDF management costs - % 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00%
Deposit interest rate 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00%
Loan interest rate (ROP) 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00%
C i t y C o n s u l t i n g I n s t i t u t e
Page 86
Loan interest rate (shareholders) 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00%
Tax on the credit and deposit related income 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00
The payback period (years) 0,00 30,00 60,00 60,00 8,00 0,00 30,00 16,00 0,00 0,00 30,00 0,00 4,56
Loans granted YTD 0,00 30,00 60,00 60,00 30,00 30,00
Loans YTD (ROP capital) 8,00 16,00 4,56
Loans YTD (shareholders capital) 0,00 30,00 90,00 150,00 158,00 158,00 188,00 204,00 204,00 204,00 234,00 234,00 238,56
Loans – total 0,00 30,00 90,00 150,00 150,00 150,00 180,00 180,00 180,00 180,00 210,00 210,00 210,00
Loans total (ROP capital) 0,00 0,00 0,00 0,00 8,00 8,00 8,00 24,00 24,00 24,00 24,00 24,00 28,56
Loans total (shareholders capital) 0,00 0,00 0,00 1,50 4,50 7,43 7,60 7,23 8,35 8,79 8,37 7,93 9,01
Credit payback 0,00 0,00 0,00 1,50 4,50 7,43 7,20 6,83 7,97 7,63 7,23 6,85 7,99
Loans (ROP capital) 0,00 0,00 0,00 0,00 0,00 0,00 0,40 0,40 0,38 1,16 1,14 1,08 1,03
Loans (shareholders capital) 0,00 30,00 90,00 148,50 152,00 144,58 166,98 175,75 167,40 158,61 180,24 172,31 167,86
Granted loans balance 0,00 30,00 90,00 148,50 144,00 136,58 159,38 152,55 144,58 136,95 159,72 152,87 144,89
Loans (ROP capital) 0,00 0,00 0,00 0,00 8,00 8,00 7,60 23,20 22,82 21,66 20,52 19,44 22,97
Loans (shareholders capital) 157,60 123,77 61,89 11,45 8,01 15,72 10,36 2,62 12,46 22,28 2,65 12,59 19,04
C i t y C o n s u l t i n g I n s t i t u t e
Page 87
160
0 0 0 0 0 0 0 0 0 0 0 0
160
0 0 08
0 0
16
0 0 0 0 0 0
24
Authorised share capital 2010-2022 [million PLN]
kapitał przekazany przez IZ (środki RPO)
kapitał przekazany przez pozostałych udziałowców (w tym miasta)
0,00
50,00
100,00
150,00
200,00
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
UDF funds balance – at the end of each year [million PLN]
Capital transferred by the MA (ROP)
funds)
Capital transferred by other shareholders (including cities)
C i t y C o n s u l t i n g I n s t i t u t e
Page 88
0,00
50,00
100,00
150,00
200,00
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Unused capital of UDF – at the end of each year [million PLN]
0,00
20,00
40,00
60,00
80,00
100,00
120,00
140,00
160,00
180,00
200,00
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
UDF operations
pożyczki i kredyty udzielone w danym roku spłaty pożyczek i kredytów ogółem
saldo udzielonych pożyczek i kredytów
Loans granted per year
Balance of loans granted
Credit payback - total
C i t y C o n s u l t i n g I n s t i t u t e
Page 89
2.2.4. Cash flow in case of JESSICA implementation – Variant 3 – HF, 2 UDFs from the ROP
and shareholders (JST, banks) funds.
This variant assumes that will be 2 UDFs and 1 HF established, with the initial capital composed of
the Śląskie Regional Operational Programme 2007-2013 funds and shareholders’ (JST and banks)
funds.
Table: Analysis assumptions – V3.
Time horizon Years: 2010-2022
Public procurement procedure, signing the contract for establishing and
managing the HF – end of 2009.
1 half of 2010 – transfer of funds to the HF.
Choice of UDFs – end of 1 half of 2010.
Number of UDFs – 2.
2 half of 2010 – transfer of funds to UDFs, arranging selection and
realization procedures, project preparation.
2011 – implementation of the first projects.
Financial sources European Regional Development Fund – the Śląskie ROP 2007-2013 –
Priority VI. Sustainable urban development.
Shareholders commitment – territorial self-government units (JST, banks)
Funding pool – initial
value
ROP: 40 million EUR = 160 million PLN
JST: 24 million PLN
Banks: 48 million PLN
Financial income Income from bank deposits: 3% per year.
Income from loans: 4% per year.
Operational costs Management cost:
HF: maximum 2% of the authorised capital (ROP funds) – per year.
UDF: maximum 3% of the authorised capital (ROP funds) – per year.
C i t y C o n s u l t i n g I n s t i t u t e
Page 90
Income tax Taxation of income on interest rate deposits and accounts: 19%
Taxation of income from granted loans: 19%
Average payback
period
20 years
Grace period 2 years
Granted loan
commission
None
Investing unused UDF
capital
Fund relocation for new ventures of min. 30 million EUR.
Table: Advantages and disadvantages of V3.
Disadvantages Advantages
Costs connected with HF
operation, comprising a share
of the initial capital (ROP
funds)
Low costs for the MA, resulting from the fact that the MA would
not be responsible for managing the funds from operational
programs and investing them in particular UDFs. The HF would take
over all the responsibilities of a managing authority.
More complex mechanisms in
case of the investment UDF.
Possibility of accommodating financial instruments to a project.
Necessity to individualize
procedures, including finance
and accounting.
Possibility of obtaining the financial leverage effect. From the
public finance sector’s point of view, not only income from the
invested funds is important. Professional management of ROP
funds is considered a key objective of the HF operation.
Necessity to employ highly
qualified stuff, leading to cost
increase.
Possibility of involvement of other financial institutions, including
banks and other shareholders (e.g. cities).
Possibility of relocation of resources for new ventures after paying
off all loans, achieved thanks to the shares of self-government
entities and banks.
C i t y C o n s u l t i n g I n s t i t u t e
Page 91
Table: Financial flow for Variant 3 [million PLN] – V3.
Details Arranging UDF Use of EU funds Long term operational plans
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Year-end balance of HF funds 0,00
160,34
In-flow 160,00
Authorised share capital contribution 0,34
160,34
Operational income 160,34
0,00
Outflows 0,00
Capital transfer to UDF
Other 2,40
Operational loss (negative value) 0,46
1,94
Operating activities 1,60
Income from interest on deposits (gross) 159,89 208,92 227,63 245,46 270,44 279,84 289,15 291,82 293,86 296,25 299,99 303,40 307,91
Tax for interest related income 162,29 53,83 25,43 25,43 33,46 19,08 19,31 12,98 12,37 12,71 14,06 13,73 16,41
160,34
Income from bank deposits (after taxation) 8,00 8,00 8,00
Management fee (3%) 16,00 16,00 16,00
48,00
Year-end balance of UDF funds 1,95 5,83 9,43 9,43 9,46 11,08 11,31 12,98 12,37 12,71 14,06 13,73 16,41
2,40 4,80 6,72 7,60 8,48 9,68 10,00 10,32 10,32 10,32 10,32 10,32 11,90
In-flow 2,40 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80
Funds transferred from HF 0,00 0,00 0,00 0,88 1,76 2,64 2,64 2,64 2,64 2,64 2,64 2,64 3,37
Funds transferred by other shareholders (including cities)
0,00 0,00 0,00 0,00 0,00 0,32 0,64 0,96 0,96 0,96 0,96 0,96 1,14
C i t y C o n s u l t i n g I n s t i t u t e
Page 92
Funds transferred by commercial banks 0,00 0,00 1,92 1,92 1,92 1,92 1,92 1,92 1,92 1,92 1,92 1,92 2,59
Funds transferred by EIB 1,95 5,83 9,43 9,43 9,46 11,08 11,31 12,98 12,37 12,71 14,06 13,73 16,41
Operational income net with interests on loans and deposits
0,00 2,40 4,80 6,40 6,40 6,40 6,40 7,68 7,68 7,68 8,88 8,88 9,78
0,00 0,46 0,91 1,22 1,22 1,22 1,22 1,46 1,46 1,46 1,69 1,69 1,86
Out-flow 0,00 1,94 3,89 5,18 5,18 5,18 5,18 6,22 6,22 6,22 7,19 7,19 7,92
Management cost 0,00 0,00 0,00 0,88 1,76 2,64 2,64 2,64 2,64 2,64 2,64 2,64 3,37
Profit payout for moneylender – from interests on bank loans
0,00 0,00 0,00 0,00 0,00 0,32 0,64 0,96 0,96 0,96 0,96 0,96 1,14
Profit payout for shareholders – from income on interests
0,00 0,00 1,92 1,92 1,92 1,92 1,92 1,92 1,92 1,92 1,92 1,92 2,59
Profit payout for EIB – from income on interests 2,41 4,80 4,47 1,79 0,73 1,26 1,15 1,53 0,77 1,19 1,66 1,26 1,72
0,46 0,91 0,85 0,34 0,14 0,24 0,22 0,29 0,15 0,23 0,32 0,24 0,33
Operational income 1,95 3,89 3,62 1,45 0,59 1,02 0,93 1,24 0,63 0,97 1,35 1,02 1,39
Income from interest on loans (gross, ROP capital)
Tax from interest related income 2,00%
Income from bank loans (after taxation) 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00%
Income from interest on loans (gross) 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00%
Income from interest on loans (shareholders capital)
4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00%
Income from interest on loans (EIB capital) 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00%
Income from interests on bank deposits (gross) 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50%
Tax for interest related income 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00%
Income from interests on bank deposit (after taxation)
19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00%
20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00
Important values: 0,00 60,00 108,00 56,00 16,00 24,00 8,00 40,00 0,00 0,00 30,00 0,00 56,97
Management cost of the HF 0,00 60,00 60,00 40,00 0,00 0,00 0,00 32,00 0,00 0,00 30,00 0,00 22,38
UDF management costs - % 0,00 0,00 0,00 0,00 0,00 8,00 8,00 8,00 0,00 0,00 0,00 0,00 4,60
Deposit interest rate 0,00 0,00 0,00 16,00 16,00 16,00 0,00 0,00 0,00 0,00 0,00 0,00 13,19
Loan interest rate (ROP) 0,00 0,00 48,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 16,80
Loan interest rate (shareholders) 0,00 60,00 168,00 224,00 240,00 264,00 272,00 312,00 312,00 312,00 342,00 342,00 398,97
Commercial loan interest rate (1,5%+WIBOR) 0,00 60,00 120,00 160,00 160,00 160,00 160,00 192,00 192,00 192,00 222,00 222,00 244,38
EIB loan interest rate 0,00 0,00 0,00 0,00 0,00 8,00 16,00 24,00 24,00 24,00 24,00 24,00 28,60
C i t y C o n s u l t i n g I n s t i t u t e
Page 93
Tax from credits, loans and deposits’ income 0,00 0,00 0,00 16,00 32,00 48,00 48,00 48,00 48,00 48,00 48,00 48,00 61,19
Payback period for loans and credits [years] 0,00 0,00 48,00 48,00 48,00 48,00 48,00 48,00 48,00 48,00 48,00 48,00 64,80
Loans and credits granted YTD 0,00 0,00 0,00 3,00 8,40 11,05 11,43 12,08 11,91 13,30 12,71 12,04 12,91
Loans YTD (ROP capital) 0,00 0,00 0,00 3,00 6,00 7,85 7,55 7,16 6,78 8,02 7,68 7,28 8,40
Loans YTD (shareholders capital) 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,40 0,80 1,18 1,14 1,08 1,02
Loans YTD (commercial banks) 0,00 0,00 0,00 0,00 0,00 0,80 1,60 2,36 2,28 2,16 2,05 1,94 1,84
Loans YTD (EIB capital) 0,00 0,00 0,00 0,00 2,40 2,40 2,28 2,16 2,05 1,94 1,84 1,74 1,65
Loans and credits granted total 0,00 60,00 168,00 221,00 228,60 241,55 238,12 266,04 254,14 240,83 258,13 246,09 290,15
Loans total (ROP capital) 0,00 60,00 120,00 157,00 151,00 143,15 135,60 160,44 153,66 145,64 167,96 160,68 174,66
Loans total (shareholders capital) 0,00 0,00 0,00 0,00 0,00 8,00 16,00 23,60 22,80 21,62 20,48 19,40 22,98
Loans total (commercial banks) 0,00 0,00 0,00 16,00 32,00 47,20 45,60 43,24 40,96 38,80 36,75 34,81 46,16
Loans total (EIB funds) 0,00 0,00 48,00 48,00 45,60 43,20 40,92 38,76 36,71 34,78 32,94 31,20 46,35
Credit payback 159,89 148,92 59,63 24,46 41,84 38,29 51,03 25,77 39,73 55,41 41,86 57,31 17,76
C i t y C o n s u l t i n g I n s t i t u t e
Page 94
160,56
0 0 0 0 0 0 0 0 0 0 0 0
160,56
0 0 0 016 16
320 0 0 0 0 0
64
0 032 32
64
0 0 0 0 0 0 0 0
128160
0 0 0 0 0 0 0 0 0 0 0 0
160
Authorised share capital 2010-2022 [million PLN ]
kapitał przekazany przez HF (środki RPO)
kapitał przekazany przez pozostałych udziałowców (w tym miasta)
0,00
200,00
400,00
600,00
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
UDF funds balance – at the end of each year [million PLN]
Capital transferred by the MA (ROP)
funds)
Capital transferred by other shareholders (including cities)
C i t y C o n s u l t i n g I n s t i t u t e
Page 95
0,00
50,00
100,00
150,00
200,00
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Unused capital of UDF – at the end of each year [million PLN]
0,00
100,00
200,00
300,00
400,00
500,00
600,00
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
UDF operations
pożyczki i kredyty udzielone w danym roku spłaty pożyczek i kredytów ogółem
saldo udzielonych pożyczek i kredytów
Loans granted per year
Balance of loans granted
Credit payback - total
C i t y C o n s u l t i n g I n s t i t u t e
Page 96
2.2.5. Cash flow in case of JESSICA implementation – Variant 4 – 1 HF/EIB and >2 UDFs
created from the ROP and shareholders’ funds (JST, banks).
This variant assumes the establishment of 1 HF managed by the EIB and >2 UDFs, whose initial
capital would be composed of the Śląskie ROP 2007-2013 and shareholders’ funds (JST, banks).
Table: Analysis assumptions – V4.
Time horizon Years: 2010-2022
Signing the contract for establishing and managing the HF – end of 1
half of 2010.
1 half of 2010 – fund transfer to the HF managed by the EIB.
Choice of UDFs– by the end of 1 half of 2010.
Number of UDFs – >2.
2 half of 2010 – ROP funds transfer to each UDF, arranging selection
and realization procedures, project preparation.
2011 – implementation of first projects
First UDFs would be established from the resources of the ROP SL. In
a later perspective, the new UDFs would be financed from the
shareholders’ resources (e.g. JST).
Financial sources European Regional Development Fund – the Śląskie ROP 2007-2013
– Priority VI. Sustainable urban development.
Shareholders commitment – territorial self-government units and
banks.
Funding pool – initial value ROP: 40 million EUR = 160 million PLN
JST: 64 million PLN
EIB: 160 million PLN
Commercial banks: 128 million PLN
C i t y C o n s u l t i n g I n s t i t u t e
Page 97
Financial income Income from deposits in the EIB: 2,7% per year.
Income from bank deposits: 3% per year.
Income from loans given: 4% per year.
Operational costs Management fee:
HF: maximum 2% from the authorized capital (ROP funds) – per year
UDF: maximum 3% from the authorized capital (ROP funds) – per
year.
Income tax Taxation of income on interest rate - deposits and accounts: 19%
Taxation of income from granted loans: 19%.
On an EIB account – 0%
Average payback period 20 years
Grace period 2 years
Granted loan commission None
Investing unused UDF
capital
Fund relocation for new ventures of minimum 30 million EUR.
Table: Advantages and disadvantages of V4.
Disadvantages Advantages
Costs connected with HF
operation, comprising a
share of the initial capital
(ROP SL funds).
Low costs for the MA, resulting from the fact that the MA would not
be responsible for managing the funds from operational programs
and investing them in particular UDFs. The HF would take over all the
responsibilities of a managing authority.
There is also an option to pass management costs to territorial self-
government entities of lower level.
Risk of too high institutional
fragmentation.
Possibility of fitting financial instruments to the project and local
requirements. High knowledge transfer between the HF managed by
the EIB and the UDFs.
C i t y C o n s u l t i n g I n s t i t u t e
Page 98
Necessity to individualize
procedures, including
finance and accounting.
Possibility of obtaining the financial leverage effect. From the public
finance sector’s point of view, not only income from the invested
funds is important. Professional management of the ROP funds is
considered a key objective of the HF operation. The EIB prestige as a
HF adds to the great experience in JESSICA implementation.
Necessary individualization
of procedures.
In accordance with the Roman Treaty, there will be no need to
perform a public procurement procedure for the HF, if the EIB
decides to take over this function.
Necessity to employ highly
qualified stuff, which leads
to increase of costs.
The EIB acting as a HF has the highest possible credit rating (AAA) on
the financial market. Thanks to this fact, the EIB may gather high
capital on favourable conditions. As the EIB is a non-profit oriented
bank, conditions for loan granting are also favourable.
Ability to create good practice database and transfer of experience to
self-government units.
High potential of finding new partners and financing sources.
Possibility to win over other financial institutions, including the EIB,
commercial banks, other shareholders (e.g. cities).
The highest flexibility of this financial model.
Potential diversification of projects.
Due to a great variety of available tools, it would be possible to
achieve the highest value added effect in realizing Integrated
Programs.
Possibility of frequent relocation of financial resources to other
projects (after paying back the previously granted loans), achieved
thanks to the contribution of JST, commercial banks and the EIB.
Implementation of PPP projects.
C i t y C o n s u l t i n g I n s t i t u t e
Page 99
Table: Financial flow for Variant 4 (million PLN) - V4.
Details Arranging HF and UDF
Use of EU funds Long term operational plans
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Year-end balance of HF funds 0,00 160,56
In-flow 160,00
Authorised share capital contribution 0,56
Operational income 160,56
Out-flow 160,56
Capital transfer to UDF 0,00
Other 0,00
Operational loss (negative value)
Operating activities 2,16
Income from interests on deposits (gross) 0,00
Tax for interest related income 2,16
1,60
Income from bank deposits (after taxation)
Management fee (3%) 322,05 327,02 363,14 398,52 480,18 499,34 534,48 537,75 540,84 544,93 548,84 553,42 559,96
324,45 12,17 45,72 48,34 96,38 38,04 54,66 24,07 25,15 26,15 25,97 26,65 32,05
Year-end balance of UDF funds 160,56
16,00 16,00 32,00
In-flow 32,00 32,00 64,00
Funds transferred from HF to UDF 160,00
Funds transferred by other shareholders 3,89 12,17 13,72 16,34 16,38 22,04 22,66 24,07 25,15 26,15 25,97 26,65 32,05
Funds transferred by commercial banks 2,40 7,20 9,60 12,96 14,72 18,88 19,52 20,80 22,06 22,06 22,06 22,06 25,52
Funds transferred by the EIB 2,40 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80 4,80
Operational income net from interests on loans and deposits
0,00 0,00 0,00 1,76 3,52 7,04 7,04 7,04 7,04 7,04 7,04 7,04 8,90
C i t y C o n s u l t i n g I n s t i t u t e
Page 100
0,00 0,00 0,00 0,00 0,00 0,64 1,28 2,56 2,56 2,56 2,56 2,56 3,02
Out-flow 0,00 2,40 4,80 6,40 6,40 6,40 6,40 6,40 7,66 7,66 7,66 7,66 8,79
Management cost 3,89 12,17 13,72 16,34 16,38 22,04 22,66 24,07 25,15 26,15 25,97 26,65 32,05
Profit payout for moneylender –interests on loans
0,00 2,40 4,80 6,40 6,40 6,40 7,68 7,68 7,68 9,08 9,08 9,08 10,62
Profit payout for shareholders –from income on interests
0,00 0,46 0,91 1,22 1,22 1,22 1,46 1,46 1,46 1,73 1,73 1,73 2,02
Profit payout for the EIB –from income on interests
0,00 1,94 3,89 5,18 5,18 5,18 6,22 6,22 6,22 7,35 7,35 7,35 8,60
0,00 0,00 0,00 1,76 3,52 7,04 7,04 7,04 7,04 7,04 7,04 7,04 8,90
Operational income 0,00 0,00 0,00 0,00 0,00 0,64 1,28 2,56 2,56 2,56 2,56 2,56 3,02
Income from interest on loans (gross, ROP capital)
0,00 2,40 4,80 6,40 6,40 6,40 6,40 6,40 7,66 7,66 7,66 7,66 8,79
Tax for interest related income 4,81 9,66 6,21 3,69 1,58 3,43 2,12 2,28 2,06 1,90 1,67 2,51 3,38
Income from bank loans (after taxation) 0,91 1,84 1,18 0,70 0,30 0,65 0,40 0,43 0,39 0,36 0,32 0,48 0,64
Income from interest on loans (gross) 3,89 7,83 5,03 2,99 1,28 2,77 1,72 1,85 1,67 1,54 1,36 2,03 2,74
Income from interest on loans (shareholders capital)
Income from interest on loans (EIB capital) 2,00%
Income from interests on bank deposits (gross) 2,70%
Tax for interest related income 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00%
Income from interests on deposits (after taxation)
3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00% 3,00%
4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00%
Important values: 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00%
HF management costs - % 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50% 5,50%
Deposit interest rate in HF 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00% 4,00%
UDF management costs - % 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00% 19,00%
Deposit interest rate in UDF 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00
Loan interest rate (ROP) 0,00 120,00 120,00 112,00 32,00 80,00 48,00 32,00 31,56 35,00 0,00 0,00 112,05
Loan interest rate (shareholders) 0,00 60,00 60,00 40,00 0,00 0,00 32,00 0,00 0,00 35,00 0,00 0,00 38,38
Commercial loan interest rate (1,5%+WIBOR) 0,00 0,00 0,00 0,00 0,00 16,00 16,00 32,00 0,00 0,00 0,00 0,00 11,56
EIB loan interest rate 0,00 0,00 0,00 32,00 32,00 64,00 0,00 0,00 0,00 0,00 0,00 0,00 33,90
Tax from credits, loans and deposits’ income 0,00 60,00 60,00 40,00 0,00 0,00 0,00 0,00 31,56 0,00 0,00 0,00 28,20
C i t y C o n s u l t i n g I n s t i t u t e
Page 101
Payback period for loans and credits [years] 0,00 120,00 240,00 352,00 384,00 464,00 512,00 544,00 575,56 610,56 610,56 610,56 722,61
Loans and credits granted YTD 0,00 60,00 120,00 160,00 160,00 160,00 192,00 192,00 192,00 227,00 227,00 227,00 265,38
Loans YTD (ROP capital) 0,00 0,00 0,00 0,00 0,00 16,00 32,00 64,00 64,00 64,00 64,00 64,00 75,56
Loans YTD (shareholders capital) 0,00 0,00 0,00 32,00 64,00 128,00 128,00 128,00 128,00 128,00 128,00 128,00 161,90
Loans YTD (commercial banks) 0,00 60,00 120,00 160,00 160,00 160,00 160,00 160,00 191,56 191,56 191,56 191,56 219,76
Loans YTD (EIB) 0,00 0,00 0,00 6,00 12,00 17,30 18,30 21,44 22,92 23,45 23,88 24,46 23,26
Loans and credit granted total 0,00 0,00 0,00 3,00 6,00 7,85 7,55 7,16 8,38 8,02 7,60 8,95 8,57
Loans total (ROP capital) 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,80 1,60 3,16 3,08 2,92 2,77
Loans total (shareholders capital) 0,00 0,00 0,00 0,00 0,00 1,60 3,20 6,32 6,16 5,84 5,54 5,24 4,97
Loans total (commercial banks) 0,00 0,00 0,00 3,00 6,00 7,85 7,55 7,16 6,78 6,42 7,66 7,34 6,96
Loans total (EIB) 0,00 120,00 240,00 346,00 366,00 428,70 458,40 468,97 477,60 489,15 465,27 440,82 529,60
Credit payback 0,00 60,00 120,00 157,00 151,00 143,15 167,60 160,44 152,06 179,04 171,44 162,49 192,29
Loans (ROP capital) 0,00 0,00 0,00 0,00 0,00 16,00 32,00 63,20 61,60 58,44 55,36 52,44 61,23
Loans (shareholders capital) 0,00 0,00 0,00 32,00 64,00 126,40 123,20 116,88 110,72 104,88 99,34 94,10 123,03
Loans (commercial banks) 0,00 60,00 120,00 157,00 151,00 143,15 135,60 128,44 153,22 146,80 139,14 131,80 153,04
Loans (EIB) 322,05 207,02 123,14 52,52 114,18 70,64 76,08 68,78 63,24 55,77 83,56 112,61 30,36
C i t y C o n s u l t i n g I n s t i t u t e
Page 102
160,56
0 0 0 0 0 0 0 0 0 0 0 0
160,56
0 0 0 0
16 16
32
0 0 0 0 0 0
64
0 0
32 32
64
0 0 0 0 0 0 0 0
128
160
0 0 0 0 0 0 0 0 0 0 0 0
160
Authorized share capital 2010-2022 [million PLN]
capital transferred by the HF (ROP resources)
capital transferred by other shareholders (including cities)capital transferred by commercial banks
capital transferred by the EIB
0,00
100,00
200,00
300,00
400,00
500,00
600,00
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
UDF funds balance – at the end of each year [million PLN]
C i t y C o n s u l t i n g I n s t i t u t e
Page 103
0,00
100,00
200,00
300,00
400,00
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Unused capital of UDF – at the end of each year [million PLN]
0,00
100,00
200,00
300,00
400,00
500,00
600,00
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
UDF operation
loans granted per year credit payback - total balance of loans granted
C i t y C o n s u l t i n g I n s t i t u t e
Page 104
2.3. Non-budgetary effects of JESSICA implementation
The main effects of JESSCA implementation include:
Fund management effectiveness. In the JESSICA mechanism, management functions are
outsourced to an external institution, which is responsible for the development of
guidelines, document templates, potential projects evaluation and selection, funding
ventures, etc.
Optimization of selection processes and mechanisms, as well as project implementation by
applying objective and independent selection criteria, HF/UDF establishment, organizational
structure, standardized application documentation, substance and financial services for
projects.
High quality of projects – achieved in result of engagement of renewable resources, complex
preparatory analyses, role of crediting institutions in financing ventures, involvement of
private partners within PPP frames.
Increase of allocation achieved thanks to the engagement of a greater number of
institutions and other partners in projects financed within JESSICA.
Greater project impact achieved thanks to the implementation of integrated projects of
greater scope and value, as well as commercial and profitable ones. In the traditional
granting system, the grant rate depended on the net income generated by a particular
project, calculated as the so called “funding gap”.
Opportunity to re-invest the income generated by the financial instruments operating within
JESSICA in new regeneration projects. Funds transferred to UDFs for investment are
revolving and can be re-invested in several ventures. As the allocation of EU funds is limited,
only JESSICA may enable potential beneficiaries to prolong the period in which ROP funds
have to be consumed and at the same time to maintain continuity of regeneration projects
financing.
Positive non-budgetary effects argue for JESSICA implementation in Silesia. The mechanism
implementation will lead to: increase of quality and effectiveness of project preparation and
realization processes as well as their positive influence on socio-economic and spatial development
of the region.
C i t y C o n s u l t i n g I n s t i t u t e
Page 105
2.4. PPP as a method of optimising the JESSICA implementation
process.
Public-Private Partnership is a form of long-term cooperation of private and public sectors in projects
aiming at implementing public tasks. The objective of this cooperation is to achieve reciprocal
benefits, including both social and commercial advantages. In case of profit-oriented ventures, which
are implemented with the support of a revolving financial instrument, such a partnership of public
and private entities offers a high development potential.
Wide application of PPP can contribute to significant savings, as costs of investment and public utility
service may be reduced. In Great Britain, where PPP projects account for approx. 11% of all public
sector’s investments, the benefits of PPP implementation are evaluated between 10-20%.
The principles of public and private cooperation have been defined in the Private-Public Partnership
Law, which was enacted by the Sejm of the Republic of Poland (Lower Chamber of the Polish
Parliament) on 21 November 2008. Currently, the bill is in the Senate.
According to this Law, the subject of PPP is common undertaking of an activity, based on task and
risk division between private and public partners.
Public Partner
•According to the PPP Law, a publicpartner is any entity operating in thepublic finance sector (according to theLaw on public finances) or any legalperson established by these entities inorder to satisfy common needs anddemands.
Private Partner
•Accoding to the Law, a private partner isany “enterpreneur or foreignentrepreneur “.
C i t y C o n s u l t i n g I n s t i t u t e
Page 106
Table: PPP objectives.
Objectives of projects
Construction or renovation of a building.
Services.
Performing a work, including installation of devices which increase the value or utility of a building.
Other services related to maintenance or management of assets, used to implement a PPP
investment or related to it.
The legislator purposefully did not restrict the list of activities, which can be the subject of a PPP
venture. It allows flexibility in choosing projects for realization and precise description of the
investment in a PPP contract. Nevertheless, apart from the Law mentioned above, the civil law
provisions apply.
Once the partnership contract period ends, the subject of partnership (e.g. road, building, hospital,
installations etc.) is transferred to the public partner. The PPP Law obligates also both parties to
transfer the ownership of any other assets to the public partner (e.g. land which was used for the
venture). Nevertheless, parties can agree otherwise in the partnership contract. In the contract,
parties can for example agree to hand over the assets different to the subject of the venture to a self-
government legal person or company, which is established for this purpose by the public partner. The
private partner has a pre-emption right to buy the subject of partnership in the project duration
period or after the end of the investment, if it was assumed to be transferable. This regulation
assures project continuity, also after its completion.
An average PPP project may be divided into 4 stages:
Table: PPP project stages
Stage I
Before a PPP investment is prepared, it should be preceded by a preparation stage, when it is:
identified, analyzed in terms of feasibility and organizational structure. During this stage, the
originator should collect as much information about the project as possible. At this stage, detailed
definition of the parties to be involved in the project should be developed, as well as a list of other
project recognition
evaluation and preparation
tender realization
C i t y C o n s u l t i n g I n s t i t u t e
Page 107
entities engaged in this investment. Further on, socio-economic impact of a project has to be
identified, together with its costs and benefits. The next step is to evaluate the real ability to finance
the project by a public unit and its financial influence on other public entities. In the end, all potential
sources of funding the project should be compared.
Stage II
During this stage, it has to be examined whether the project fits into the definition of PPP projects
and may be contracted as a partnership. It should be primarily evaluated if adapting the PPP
approach will be more beneficial, than any other financial option available for public projects.
Besides, it should be appraised, whether it can be attractive for the private sector. The rate of return
for all financial flows of this project should be calculated. Shall the analysis reveal that the PPP
method can be applied for the particular venture, advantages and disadvantages of various PPP
models have to be considered, in order to choose the optimum one. In this stage, it is advised to
analyze the experience of entities that have already implemented PPP projects within the same
functional area.
Stage III
The tender stage is very detailed, concentrated on creating the partnership structure and choosing
the best private partner. The result of this stage is a complex network of potential solutions, which is
later on structured into a PPP contract. This contract includes all technical, legal and financial
regulations. It should be stressed that active and well structured partnership cooperation together
with a clear hierarchy of own objectives, clear risk division and structure of obligations lead to best
effects of a PPP venture.
Stage IV
Realization consists in implementation of the PPP according to all the assumptions and schedules
specified in the previous stages. Project success strongly depends on PPP contract provisions. The key
principle of successful realization is the win-win rule, which assumes that successful partnership is a
partnership in which risks and tasks are divided optimally and every party is responsible for the
activities they are expert in. Therefore, both parties can benefit from realizing the venture objectives.
Realization of investments in the PPP model brings benefits and profits to all parties. Moreover,
benefit in this case is not only material but also mediagenic.
C i t y C o n s u l t i n g I n s t i t u t e
Page 108
Benefits for the public party
The private partner engagement into the project enables the public party to reduce the
costs and helps balance the entity’s budget.
The private capital significantly reduces the risk of stopping construction work due to
shortage of financial resources and increases the probability of infrastructure’s quality
improvement.
Involvement of a private entity means the application of newer technologies and know how.
More efficient management of the investment and human resources shortens the
implementation time and therefore reduces costs.
The role of political impact exerted on the investment and other economic decisions may be
reduced by engaging private companies.
Benefits for the private party
Possibility to invest in a project with an attractive rate of return.
Access to projects which could be previously implemented only by the public sector.
Cooperation with a public sector entity, ensuring new experience, knowledge and skills that
may be further used in other ventures (learning curve).
On the top of the above benefits, involvement in a public project of media’s interest may be
a strong PR element and good promotion for a company.
C i t y C o n s u l t i n g I n s t i t u t e
Page 109
Table: Conclusions for PPP implementation
Stream of capital, which can be used for investment in the public sector, achieved thanks to the involvement ofthe private sector. The PPP system faciliates implementation of projects with limited access to public funds as itoffers a possibility to obtain capital from the private sector for public investments. This is very important, as itencourages public entities to apply for structural EU funds.
Spreading knowledge and experience of the private sector and increasing the effectiveness and quality of publicworks.
Sharing the risk related to the venture – in PPP the greatest risk is carried by the party with the biggest potential tosuccessfully manage it with available resources. The goal is to share the risk in the optimum manner to maximisethe added value (not to minimize it for partners).
Higher effectiveness in consuming available resources and higher service level – as previous experience shows,most activities related to a project can be performed more efficiently within PPP, because of managementdiscipline and the private sector experience. Moreover, the service level within PPP is often much higher than incase of traditional investments. This is related to better organization, supervision, implementation of innovativesolutions and motivation to reduce costs. It is also important that this motivation results from both private sectorinterest (concentrated on profits) and public supervision (concentrated on PPP contract provisions related to:breaching the contract by the private partner by not following the agreed standards and quality of servicesprovided).
Ability to generate additional profit for third parties, which also reduces the demand for public funds for otherinvestments.
Ensuring the optimum project management, with limited total cost – transferring part of project risk to a privatepartner encourages him to search for the optimum management method and therefore optimizes the process ofspending the available financial resources. At the same time, the total project cost may be reduced. However,decrease of the total cost cannot result in lower quality of services or other standards provided for in the PPPcontract, as the revenue of the private partner depends on the fulfilment of contract conditions.
Greater supervisory role of the public sector – As responsibility for the project is transferred to the privatepartner, the public party can concentrate on its regulatory functions, planning and monitoring of theimplementation process (although the responsibility to provide public services stays with the public entity).Besides, public services become more competitive and market oriented, which helps maximise the return oninvestment.
Keeping the right proportions while agreeing on a hierarchy of objectives for both public and private partners aswell as the scope of responsibilities. This should result from a clearly defined share of risk and obligations and leadto maximization of benefits and effectiveness of the project.
C i t y C o n s u l t i n g I n s t i t u t e
Page 110
In case of the JESSICA initiative, Public-Private Partnership is a necessary element, unavoidable and
beneficial, although there are some critical points, which should be considered in the initial phase of
application verification.
Table: Critical factors of PPP from the JESSICA perspective.
•The PPP Law was initially introduced in 2005, butdue to a large number of errors and lack ofrelevant decrees, it was defective. Applying thisLaw without reference to other acts could be (andoften was) considered a crime.
•Due to numerous problems with PPP, self-government entities are afraid to establish such apartnership. Therefore PPP contracts are oftenvery unfavourable to private partners.
Legal problems with PPP implementation
•The PPP Law in its correct form has been bindingsince 2009. Therefore, there are no practicalexamples of partnership projects implementation.
•There are only few experts in developing contractsand implementing PPP to optimize investmentresults.
Lack of knowledge and experts
•PPP implementation in self-government unitsshould be preceded by a detailed analysis ofbudgetary needs and opportunities.
•Local governments should introduce clearschemes of PPP implementation consisting in thedevelopment of PPP Implementation Plans, whichwould describe the key investment areas, contractparticipation opportunities and PPP models forindividual ventures.
Lack of conditions for PPP implementation strategy in
self-government units
•There is a need to adopt a standardized analyticalmodel to enable unambiguous evaluation ofprofitability of each investment within a PPPmodel, which can be implemented within theJESSICA initiative.
Lack of conditions for evaluation of PPP economic
perspectives.
C i t y C o n s u l t i n g I n s t i t u t e
Page 111
The analysis of opportunities connected with JESSICA and PPP gives optimistic results. It should be
stressed, that PPP is a new solution. Due to the fact that long time has been spent on preparing legal
acts and faulty Law was adopted in the end, the new Law has a low acceptance level among most
self-government entities.
On the other hand, local authorities expect the possibility to implement projects within PPP, as it is
the only way to cure the current investment policy and implement profitable projects.
JESSICA has a chance to become a natural incentive for public entities and private investors to
establish partnerships and jointly implement interesting and profitable investments.
In result of JESSICA implementation, Silesia may take the chance of developing advantageous
conditions for investments, from legal, economic as well as financial perspectives (implementation of
a new, revolving mechanism to support investment).
Table: Opportunities for cooperation in PPP with JESSICA support.
JESSICA + PPP
business units
self-government
units
C i t y C o n s u l t i n g I n s t i t u t e
Page 112
2.5. Summary. Conclusions for JESSICA implementation.
A comparative analysis was performed for Variant 0 (representing the traditional granting
mechanism of ROP SL funds) and Variants 1-4 (related to JESSICA implementation). The general
conclusions have been summarized below.
Funds granted to JESSICA projects are returnable, contrary to those coming from the subsiding
mechanism of the ROP SL. This fact enables the development of a long-term financial mechanism for
regeneration projects.
One of the main short-term financial benefits of JESSICA is the option to withdraw the full ROP
subsidy at once. Unused funds (e.g. not yet transferred or left after loan payback) may stay as a bank
deposit and generate additional income from interest. This income should cover at least part of the
management fees.
In comparison to the traditional system, JESSICA’s effects are the following:
The financial capital is revolving, therefore the total funds are not decreasing.
The value of funds transferred for project implementation will be relatively increasing, in
comparison to the traditional mechanism. This will result from re-investment of available
funds coming back to the UDFs as a loan payback. The financial assets will be increased by
interests from loans granted for projects and from bank deposits.
The analysis of 4 variants of JESSICA implementation in Silesia revealed that Variant 4 (HF + >2
UDFs + other shareholders – JSTs, banks) is the optimum one. Establishment of a higher number of
UDFs will result in the leverage effect, which means that the solution will offer a higher potential
for public (JST) and private (banks) sector units to engage their funds in UDFs. Increase of financial
resources within JESSICA means in turn that more projects will be implemented and the UDF value
will increase (e.g. financial income on interests).
Thanks to the implementation of the above variant, an expert institution implementing the JESSICA
initiative will be established. This will result in the following advantages:
• Low costs for the MA, resulting from the fact that the MA would not be responsible for
managing the funds from operational programs and investing them in particular UDFs. The
HF would take over all the responsibilities of a managing authority.
• In accordance with the Roman Treaty, there will be no need to perform a public
procurement procedure for the HF, if the EIB decides to take over this function.
C i t y C o n s u l t i n g I n s t i t u t e
Page 113
• Possibility of fitting financial instruments to the project and local requirements. High
knowledge transfer between the HF managed by the EIB and the UDFs.
• Possibility of obtaining the financial leverage effect.
• Ability to create good practice database and support transfer of experience to self-
government units.
• High potential of finding new partners and financial sources.
• Possibility to win over other financial institutions, including the EIB, commercial banks,
other shareholders (e.g. cities).
• Potential diversification of projects.
• Due to a great variety of available tools, it would be possible to achieve the highest value
added effect in realizing Integrated Programs.
• Possibility of frequent relocation of financial resources to other projects (after paying back
the previously granted loans), achieved thanks to the contribution of JST, commercial banks
and the EIB.
• Implementation of PPP projects.
Possibility of obtaining the financial leverage effect.
From the public finance sector’s point of view, not only income from the invested funds is important.
Professional management of the ROP funds is considered a key objective of the HF operation. The EIB
prestige as a HF adds to the great experience in JESSICA implementation.
The EIB acting as a HF has the highest possible credit rating (AAA) on the financial market.
Thanks to this fact, the EIB may gather high capital on favourable conditions. As the EIB is a non-
profit oriented bank, conditions for loan granting are also favourable.
C i t y C o n s u l t i n g I n s t i t u t e
Page 114
3. Institutional analysis of JESSICA implementation.
3.1. Description of potential market participants in JESSICA.
3.1.1. Public administration.
The parties that may potentially be interested in the JESSICA initiative include: central government
administration, voivodeship (region), poviat (county) and gmina (commune) self-government entities
as well as the Metropolitan Association of Upper Silesia.
Areas where JESSICA implementation is possible and desirable have been summarized in the table
below.
Table: Potential engagement of public administration units in JESSICA.
Unit Potential involvement in JESSICA
Central
government
units: regional
offices of central
institutions,
Voivodeship
Office
Central administration is the owner of companies and properties which need
transformation and regeneration. It is interested in contributing a part of its
assets for the purpose of their revitalization.
The State Treasury owns post-industrial and degraded areas (waste dumps,
post- exploitation areas, contaminated land) and post-industrial objects of high
historical value. The State Treasury is also the owner of companies currently
undergoing restructuring processes, being in possession of non-productive
property situated in revitalization areas.
Self- government
voivodeship
entities
Voivodeship self-government plays the role of the ROP Managing Authority and
is the entity responsible for taking decisions on strategy, development
directions and effectiveness of the JESSICA mechanism. JESSICA is an efficient
tool that may be applied in the process of implementing Priority 6 of the ROP
SL. Moreover, voivodeship self-government owns properties situated in urban
areas and other entities that may participate in PPP processes. JESSICA funds
may be applied in the planned PPP investments in the Voivodship Park of
Culture and Recreation or in health care transformation (additional analyses
would be required).
C i t y C o n s u l t i n g I n s t i t u t e
Page 115
Poviat self-
government
entities
Poviat self-government entities are interested in two aspects of the initiative.
Firstly, poviat authorities in country districts would like to support smaller cities
in creating effective financial mechanisms that would enable them to
implement large investments in poviats. Secondly, self-government entities of
both country and township districts may benefit from the initiative
implementation in the areas of healthcare, upper-secondary education and
road infrastructure. PPP initiatives in the sphere of development or renovation
of hospitals and their auxilliary buildings, schools and health care restructuring
processes are particularly interesting. These processes are still in initial phases,
therefore JESSICA could be crucial for their success.
Gmina self-
government
entities
Gmina self-government entities prove considerable interest in JESSICA
implementation. These entities implement urban regeneration projects and
initiate investment processes as well as engage in partnerships aimed at
revitalization of degraded or urban areas. Most self-government entities have
and implement Local Revitalization Programmes. Nevertheless, there is no legal
solution offering support as far as project financing is concerned. The only
financial source is own budget and subsidies from the IRDOP or the ROP SL.
There are also other funds available, but their impact is rather minor: EEA
financial mechanism or funds related to environment protection and domestic
loans. Most of these programmes / funds support non-profit projects.
Therefore, there are no funds able to generate income or added value.
Moreover, the market is lacking resources and legal regulations concerning PPP.
All these factors result in weak financial leverage effects in the sphere of
regeneration projects.
Most revitalization projects are financed from communal budgets. In the light of
the present crisis and decrease of income, even high potential projects may not
be started.
Seeing the possibility of financing the JESSICA projects outside own budget and
engaging private partners in the process, gminas have proven considerable
interest in the mechanism.
Some gminas have even declared their ability to contribute own resources in
order to reinforce the capital of local UDFs. Gmina self-governments own
properties situated in urban areas and other entities that may participate in PPP
processes. This approach guarantees the establishment of strong regional
C i t y C o n s u l t i n g I n s t i t u t e
Page 116
financial institutions.
Metropolitan
Association of
Upper Silesia -
GZM
The special character of the most urbanized region in Poland was the reason to
establish the Metropolitan Association of Upper Silesia (Polish acronym: GZM).
The main objective of GZM is to create a dynamically developing metropolitan
center, which will be able to effectively compete with other metropolitan
centers in Poland and in Europe.
Other GZM’s objectives are:
- Harmonized development of the whole metropolis, achieved through
the best allocation of member cities’ potential with respect to their
autonomy and individual character.
- Arising pride of being parts of a great city mechanism in the metropolis
inhabitants and assuring that the metropolis potential is available for all
of them.
- Encouraging inhabitants and visitors to discover the metropolis, to
settle and work there.
- Building and popularizing a belief in comprehensive opportunities to
choose a career, life style, encouraging young, well-educated people to
move to and work in the metropolis.
- Promoting, in and outside the country, all advantages of the metropolis:
economical, cultural, touristic and environmental.
Members of GZM:
Bytom Chorzów Gliwice Dąbrowa Górnicza Jaworzno Katowice Mysłowice Piekary Śląskie Ruda Śląska Siemianowice Śląskie Sosnowiec Świętochłowice Tychy Zabrze According to the Associations’ status, it is a municipal association realizing the
following tasks:
- Defining the common development strategy for member cities,
according to the Law on planning and spatial development. The strategy
C i t y C o n s u l t i n g I n s t i t u t e
Page 117
should be taken into account in studies of land use conditions and
directions of particular cities.
- Realization of the tasks included in the common development strategy,
transferred by member cities to the Association on the basis of relevant
agreements.
- Acquisition of financial resources from domestic and international
funds.
- Managing roads handed over to the Association by member
communities on the basis of relevant agreements.
- Development of applications for public funds from the EU budget to co-
finance statutory tasks.
- Labour market activation in member cities, achieved through gathering
and managing financial resources as well as through supporting projects
innovative to economy, increasing competitiveness between member
cities. The scope of these activities is based on relevant agreements.
- Development of analyses and reports on current scarce professions,
assessing the labour market and supporting public education, especially
targeted at educating students in scarce professions. The scope of
these activities is based on relevant agreements.
- Issuing opinions on legislation and decision making processes (national
and regional) in the areas of the Association interest.
- Cooperation with territorial self-government units, including local and
regional communities of other countries and government
administration bodies.
Currently, the Association is responsible for preparation and implementation of
a programme of waste development through thermal processing.
Many urban regeneration tasks of the Upper Silesia Metropolis have to be
implemented by two or more neighbouring cities due to their geographical
location. Therefore, the Association may be a natural partner in the process of
implementing integrated urban projects on this territory.
C i t y C o n s u l t i n g I n s t i t u t e
Page 118
3.1.2. Public institutions
Among the entities interested in JESSICA, there are also public institutions like: Local Development
Agencies, The Regional Fund for Environmental Protection, The Capital Group of the Upper Silesia
Fund (The Upper Silesian Fund, The Center of Regional Projects, The Upper Silesian Regional
Development Agency), The Upper Silesian Business Transformation Agency, TF Silesia and
universities.
Summary of potential engagement areas has been presented in the table below.
Table: Potential engagement of public institutions into JESSICA.
Unit Potential engagement in JESSICA
Local
Development
Agencies
Agencies operating in the region have a broad knowledge on the local economy
and its potential. They operate in the area where business and self-government
meet, what gives them a possibility to participate or to counsel in PPP
processes. Agencies show interest in advising, consulting and training in JESSICA
projects development. Agencies can be also used as local consultation points for
this mechanism.
Regional Fund
for
Environmental
Protection
RFfEP has at its disposal funds dedicated to regeneration of degraded and post-
industrial areas. It supports communes in this respect. The Fund can co-finance
Integrated Programmes of Urban Development as it may grant loans for those
elements of programmes that do not generate income, but reinforce the overall
project effect.
In case of regeneration of degraded post-industrial areas, the RFfEP may be the
key to effective financial engineering of projects.
Capital Group of
the Upper
Silesian Fund
(The Upper
Silesian Fund,
The Center of
Regional
Projects, The
Upper Silesian
Regional
The Upper Silesian Fund is an entity owned in 100% by territorial self-
government units of Śląskie Voivodeship. The company was established in 1995
on the basis of the so called regional contract. Its scope of activity includes:
- Purchase of property and movable assets in order to use them for
business purposes or dispose,
- Attracting external capital to invest on the Śląskie Voivodeship territory,
- Cooperation with domestic, foreign and international institutions aimed
at implementation of the Company’s objectives,
C i t y C o n s u l t i n g I n s t i t u t e
Page 119
Development
Agency)
- Administration and management of funds for regeneration and
development projects.
The entity has considerable experience in implementing projects that may be
co-financed within the JESSICA frame. This experience has been gained thanks
to the Department of Communal Investment Development. The Department
aims at:
1. Organizing issuance and sales of securities issued by gminas, gmina
associations and other communal entities on the market.
2. Investing the Fund’s resources in communal entities.
3. Capitalization of the Fund’s property, e.g. through shares in developer
companies.
4. Provision of consulting services in the following areas:
- Financing communal investments with the use of not-budgetary
commercial financial sources;
- Impact of the commune’s budget deficit on its financial credibility in 10
year periods;
- Assessing the effectiveness of communal investment projects;
- Planning and acquisition of financial resources for the purpose of
covering current communal demands (use of different financial
instruments).
5. Implementing financial instruments in gminas.
6. Organizing training sessions with territorial self-government units,
primarily on public finance management.
There is also an Aid Programme Department within the structure of the Upper
Silesian Fund, crediting projects from public funds (including funds from the
European Union). The capital group comprises:
- Silesia Regional Guarantee Fund Ltd. (Polish: Śląski Regionalny Fundusz
Poręczeniowy Sp. z o.o.) – providing guarantees thanks to e.g. the EU
funds,
- Upper Silesian Investment Funds, joint-stock company (Polish:
C i t y C o n s u l t i n g I n s t i t u t e
Page 120
Górnośląskie Towarzystwo Funduszy Inwestycyjnych S.A.),
- Upper Silesian Restructuring Fund, joint-stock company (Currently: the
Silesia Capital Fund SA).
Yet another Fund is currently being established. It will be co-financed from
European Union funds in partnership with a subsidiary company of Bank
Gospodarstwa Krajowego and private capital.
In the Upper Silesian Fund group, there is also a company established in order
to cooperate with local authorities in the sphere of construction and spatial
development (CPR Investor) and a company advising small and medium sized
companies, which was in the past a Regional Financing Institution (GARR).
Thanks to their experience, these companies may (in cooperation with the
Fund) establish new subsidiary companies to play the functions of UDFs.
CPR Investor SA staff is highly qualified in urban regeneration and PPP projects.
The company owns the Social Housing Association that may be a very active
player on the regeneration market. The comapny manages post-industrial areas
owned by the Upper Silesian Fund (Fundusz Górnośląski S.A.) and develops their
revitalization strategies. CPR can act as an operator of the Real Estate
Development Fund, regenerating post-industrial areas. On the basis of the
above information, it should be stressed that the Upper Silesian Fund (Fundusz
Górnośląski S.A.) is a unique institution in Upper Silesia, with no equivalent in
terms of experience (best practices), human resources, relevant tools and know-
how. The added value is the experience in cooperation with self-government
entities (being its shareholders at the same time) and private capital (in public-
private partnership).
The Upper Silesian Fund has established a Regional Loan Fund for small and
medium-sized enterprises, assisting entrepreneurs in the process of applying for
EU grants. Support is also granted to people starting up their own business
acitivity, graduates and the unemployed.
Moreover, the Upper Silesian Fund has also created a regional venture capital
fund aiming at innovative project and environment protection ventures. Its
subsidiary – CPR Inwestor S.A. ,together with the local self-governement entity
have established a regional Social Housing Association (TBS) to implement
C i t y C o n s u l t i n g I n s t i t u t e
Page 121
regeneration projects.
The Upper Silesian Fund is interested in creating two UDFs: loan and guarantee
fund and investment fund for regeneration projects. Basing on its experience,
the Fund has expressed the opinion that combining both functions within one
UDF would not be effective. All banks differentiate these two types of activities,
creating separate loan, mortgage or investment banks within one banking
group. Due to the fact, the Upper Silesian Fund declares the establishment of
two separate UDFs within its structures.
The Upper
Silesian Business
Transformation
Agency (Polish:
GAPP S.A.)
GAPP S.A. is a State Treasury Company. The goal of this firm is to break or
mitigate barriers in structural and ownership transformation processes in
companies, leading to development and growth of the region. One of the
company’s priorities is to support competitiveness and growth of small and
medium-sized companies. The company is also engaged in transformation and
management of degraded and post-industrial areas. It declares the will to create
a platform for transformation processes in degraded areas. It would like to
implement regeneration projects and play the role of an advisor in developing
post-industrial areas.
TF Silesia This institution was established to support transformation of companies in the
region. Due to the fact that most of them are located in attractive areas but
posess de-capitalized assets, TF Silesia may be interested in using JESSICA to
bring in assets to urban projects.
Universities Local universities have a great potential and knowledge on the conditions of
post-industrial heritage. Due to the fact, they are interested in supporting
intellectually the initative through research, own regeneration projects,
knowledge sharing and qualification improvement.
C i t y C o n s u l t i n g I n s t i t u t e
Page 122
3.1.3. Financial sector institutions
There are financial institutions interested in engaging in the JESSICA initiative. These are commercial
banks, BGK, CEB, EBRD and EIF.
Table: Engagement of the financial sector in JESSICA.
Unit Potential engagement in JESSICA
Commercial
banks
Despite of a large number of banks operating on the Polish market, only
communal investment and mortgage banks have shown interest in the
initiative. Due to limited confidence of banks in developer investment
(information valid for August 2009), a majority of them declare their will to
participate, without providing the scope of cooperation they would be
interested in. In general, commercial banks are interested in financing particular
projects that self-government units are involved in. Banks do not have any
experience in managing UDFs and HFs and due to specific requirements of
banking legislation, they are not interested in it.
PKO BP –interested in financing regeneration investments up to 10 million PLN.
It could potentially support bigger investments, after individual negotiations.
The bank prefers financing investments of self-government units.
DEPFA BANK –oriented on cooperation with the public sector, regeneration and
restructuring ventures, PPP. Its experience and cooperation with the EIB in
Silesia opens the possibility of cooperation in implementing the JESSICA
mechanism and PPP. The Bank would involve in investments over 5 million PLN.
ING Bank Śląski – interested in financing projects of self-government entities,
mostly by issuing bonds. Due to its special connection with region, the bank is
interested mostly in Silesian regeneration projects.
Dexia Kommunalkredit Bank – specialized in supporting public and communal
sectors. The Bank is also keen on financing long term public projects, realized as
PPP (long crediting period, up to 20 years). The bank offers also negotiations on
the grace period and pay-back structures fitting the character of the
investment. Funds in various currencies. Issue of bonds. Involvement in
restructuring processes.
DnB NORD – the Banks’ offer includes full service for territorial self-government
C i t y C o n s u l t i n g I n s t i t u t e
Page 123
units. The bank finances even the most complicated investment projects,
implemented directly by self-government units or in cooperation with private
partners. It has a great experience in financing housing regeneration,
restructuring of health care institutions and construction of technology parks. It
offers European loans for financing ineligible costs of projects and bridge loans.
Commercial banks are not interested in managing the HF and UDFs or financing
specific projects. Nevertheless, their experience and openness for PPP projects
and public sector restructuring are very important.
BGK BGK, as a state-owned financial institution of high credibility, specializes in
serving the public finance sector. It provides economically and operationally
effective support for socio-economic state programmes and self-government
programmes for regional development. It ensures modern and high quality
offers and good relationship with customers by flexible approach towards their
needs. The mission of BGK is to provide high performance and cost-effective
realization of activities contracted by the state, supplemented by development
of an attractive offer of self-operation for chosen segments of the market,
where the bank can use its natural advantages. The bank’s offer includes:
Long-term loans
- Investment loans;
- Loans for financing EU projects;
- Loans granted by the EIB;
- Loans granted by the EIB with the European Commission grants.
Securities and guarantees
Bonds
- Issue of bonds;
- Consulting services for self-government bodies.
State programmes
- Pre-financing;
- Social housing support programme from the Surcharge Fund;
- Energy Effectiveness Programme – Global Environment Facility.
Special Purpose Funds
Thermomodernization Fund
Communal Investment Development Fund
C i t y C o n s u l t i n g I n s t i t u t e
Page 124
Credit Guarantee Fund
European Union Package
CEB CEB was established in 1955. It is the Europe’s oldest financial institution and
Poland is one of its shareholders. The bank is a financial institution of the
Council of Europe, which provides loans for the member states. CEB offers
credits for 50% of the total net cost of an investment or a project.
CEB can finance self-government investment for very long crediting periods and
on very convenient conditions. The bank is also experienced in projects run
jointly with the EIB.
The bank can also co-finance regeneration projects in the sphere of social
housing, health care, education and environment protection. The possibility to
finance construction and modernization of hospitals and educational buildings
seems particularly interesting in revitalization projects. Besides, in case of
integrated renovation projects, the bank can finance some non-profit
components without interest and with minimum bank’s margin.
The bank is not a contractor in terms of the public procurement Law. The
European legislation and the Polish Public Procurement Law (Art. 4 point 1a) of
29 January 2004 as amended, refer to financing with the support from
international organizations, to which the public procurement Law does not
apply. Moreover, in case of the CEB, each application for funding is formally
presented to the Administrative Board of the Bank after it had been agreed with
the Ministry of Finance. Credits offered by the CEB are more favourable than
the ones offered by commercial domestic banks. The bank can cover up to 50%
of the total investment costs, regardless of other funding sources. This
favourable offer includes: low cost of money (no interest), long crediting and
payback period, freedom of choosing the investment type, flexible structure
(option to use various currencies, formulas for interest rates calculation and
characteristics of payback) together with the ability to apply special procedures
for international organizations (in relation to granted credits, according to the
public procurement Law).
The bank is not interested in taking over the functions of the HF and UDFs.
European Bank The EBRD bank has strongly supported the Polish transformation in 1990s.
C i t y C o n s u l t i n g I n s t i t u t e
Page 125
for
Reconstruction
and
Development
(EBRD)
Currently, the bank considers its strategy for Poland in 3 areas of potential
engagement:
private sector;
financial sector;
infrastructure and environment.
It is particularly interested in the possibility of engaging in the private sector
transformation, private equity funds and venture capital. The bank will use its
experience in financing projects within the public-private partnership, especially
in the communal and transport sector.
Cooperation with the EBRD can lead to active cooperation on a project, as well
as on a UDF level, where the UDF invests capital in restructuring and
regeneration of urban areas. The bank shows no interest in direct management
of the HF and UDFs.
EIF - European
Investment Fund
The European Investment Fund was created in 1994 to support small and
medium sized companies. Its main shareholder is the European Investment
Bank. Together with the EIF, the bank forms the EIB Group. The EIF provides
high risk capital for small and medium sized companies, especially for the young
and technology oriented. It provides guarantees for loans granted by the EIB.
The EIF does not provide direct loans or subsidies, neither invests directly
in companies. It acts through its middlemen: banks and other financial
institutions. It uses its own funds or resources provided by the EIB or the EU.
The EIF is an institution responsible for implementation of the JEREMIE initiative
in Poland. The JEREMIE initiative aims at supporting companies. There are
potential benefits for JESSICA deriving from cooperation with the EIF, especially
if one of the elements of a PPP regeneration project is reinforcing
competitiveness of companies.
C i t y C o n s u l t i n g I n s t i t u t e
Page 126
3.1.4. Private sector
Among private institutions interested in JESSICA implementation, there are mainly municipal
companies, State Treasury companies, restructuring companies, medical centres, developers,
institutions supporting regeneration processes and other investors.
Table: Potential engagement of the private sector institutions in JESSICA.
Unit Potential engagement in JESSICA
Municipal
enterprises and
the State
Treasury
companies
Municipal enterprises may play a key role in the process of implementing
projects within JESSICA.
The existing companies concentrate on municipal services, housing and
environment protection. They posses or manage huge assets, located mostly in
regeneration areas. The scope of their interest may include regeneration of
particular areas, objects in PPP or restructuring of whole segments of their
activity in revitalized areas. The main types of companies are:
Water supply companies;
Housing companies;
Heat power companies.
Municipal enterprises have significant experience in the sphere of regeneration,
e.g. heating infrastructure programmes for regenerated districts (realized with
the Heat Power Company support), infrastructural programs within PPP (water
supply and sewage management).
Other units engaged in JESSICA may be municipal special purpose companies,
established in order to implement particular regeneration projects within
JESSICA or PPP. Setting up such a company is the most clear and transparent
form of running a regeneration investment, and at the same time the most
understandable by the commercial finance sector.
Municipal special purpose companies will be therefore interested in managing
projects, applying for financial resources but also in coordinating integrated
programs comprising a few projects. Municipal special purpose companies may
be established by an association of municipalities interested in the
establishment of local UDFs.
C i t y C o n s u l t i n g I n s t i t u t e
Page 127
Currently, municipalities of the northern sub-region are interested in
establishing their own UDF as a partnership or investment fund.
State Treasury Companies - most of these companies are currently undergoing
restructuring processes leading to privatization or reorganization of their
operation. They possess huge non-productive assets. Most of them are located
in areas under regeneration (or potential regeneration zones) and they are
often the most interesting architectural objects in the centres of Silesian cities.
These are also potentially interesting investment areas, unfortunately
demanding great outlays for revitalization.
Examples may include Kompania Węglowa S.A. (coal mining company) –
managing mining industry assets or the already presented TF Silesia.
These companies might be interested in running regeneration processes and
contributing land for regeneration ventures together with municipalities.
Decisions on these contributions would be made on a ministerial level. In order
to receive positive results, it would be necessary to prepare a common project
(e.g. Real Estate Development Fund) together with the Ministry of Economy and
the Ministry of Treasury.
Restructuring
companies
Restructuring companies are very specific enterprises, created for the purpose
of managing non-productive post-industrial assets. These are mainly properties,
which in spite of their location require so significant investment in regeneration
that no one wanted to buy them on the commercial market. These properties
might be contributed to regeneration projects.
Spółka Restrukturyzacji Kopalo S. A. (Mines Restructuring Company) may be an
example here as it owns properties in the following cities: Katowice, Bytom,
Sosnowiec, Jaworzno and Zabrze.
Decisions on these contributions would be made on a ministerial level. In order
to receive positive results, it would be necessary to prepare a common project
(e.g. Real Estate Development Fund) together with the Ministry of Economy and
the Ministry of Treasury.
Medical entities The JESSICA initiative does not concentrate on restructuring the public health
care. Most buildings requiring resources for regeneration and restructuring are
located in city centers. Major private companies as well as public health care
C i t y C o n s u l t i n g I n s t i t u t e
Page 128
sector employees are interested in restructuring these institutions.
Restructuring in this case means economically justified expenditure on tangible
and intangible assets. Poviats have shown considerable interest in these
projects as they own most hospitals. It is also possible to combine private and
institutional financing (e.g. by the CEB, the EIB or the JESSCA initiative). The role
of JESSICA is to support PPP ventures implemented by self-government units in
order to show profits.
Developers The main problem that developers face is the lack of well located investment
areas. Therefore, they are natural partners for regeneration projects bringing
back to life degraded and post-industrial areas. Another area of their interest is
adaptation of post-industrial and de-capitalized objects, located in city centers,
for the purpose of new functions oriented on development of the center.
Developers could participate in the process of JESSICA implementation in the
following ways:
participation in property development companies or directly in UDFs.
They could support financially ventures connected with property
development. They could also manage the process of restructuring
objects and land as well as engage their own funds.
extensive cooperation - a developer becomes the owner of the land,
initially prepared for regeneration projects. Cooperation between
developers and self-government units starts already in the planning
phase. The effect of this cooperation is market oriented management of
the regeneration process, which guarantees success.
If more than one investor or developer is to be involved in PPP, it is crucial for
local authorities to recognize what are the actual needs of investors already in
the preparatory phase. Good examples may be German companies, like LEG
(Landesentwicklungsgesellschaft). It is also crucial to use proper tools (e.g.
Charrette workshops) in the process of developing complex investment
projects. These objective tools should be preferred by implementing complex
PPP projects based on the JESSICA mechanism.
Investors The main groups of investors indentified in this report are:
International holdings interested in cooperation in the communal
services sector, and therefore also in regeneration of infrastructure in
C i t y C o n s u l t i n g I n s t i t u t e
Page 129
degraded city centers (e.g. Veolia, Suez, RWE, Remondis, etc.). These
companies have considerable budgets and have initially declared their
potential engagement in JESSICA projects.
International and domestic companies offering complex regeneration
of cities and other areas (e.g. BIG-STÄDTEBAU GRUPPE) are willing to
engage in integrated, complex regeneration processes and urban
development of cities. These companies may also be shareholders of
various projects and develop financial engineering models for entire
processes. They are interested in operating a capital UDF, but not in
running the HF. They also emphasize that they would like to cooperate
with the EIB or other European institutions during the process (e.g. in
the HF). In their opinion, this solution would assure greater flexibility of
financial engineering models in case of complex regeneration projects
financed from other EU resources.
Domestic and international companies interested in restructuring
particular properties or companies that own properties situated in
regeneration areas (e.g. TUP SA, Szpitale Polskie SA). These companies
are experienced in regeneration processes, e.g. TUP SA has
implemented regeneration projects in Poznan and is currently
progressing with similar projects in Silesia. These companies are not
interested in managing the HF or a UDF but would like to act as project
operators, supporting local authorities. They have their own capital and
may be active players in PPP processes.
Supporting
institutions
Regeneration Forum Association
The Regeneration Forum is the most active unit in Poland and Silesia in terms of
regeneration knowledge. The association is represented in Silesia by a few
experts, experienced in developing regeneration programs as well as
implementation and management of regeneration projects.
The Regeneration Forum cooperates on a daily basis with the Ministry of
Infrastructure and the Ministry of Regional Development as well as the BGK.
The Forum advises self-government units and has published numerous papers
on regeneration. Forum experts have for several years cooperated with
European institutions: the EIB and the EBRD. Several Forum experts have been
C i t y C o n s u l t i n g I n s t i t u t e
Page 130
European experts in countries from outside the Union (e.g. Georgia or the
Balkans). The Forum cooperates closely with regions such as: North Westphalia,
Nord-Pas-de-Calais, Burgundy, Mecklenburg-Vorpommern, Brandenburg.
The Forum declares its support for self-government units, UDFs and assistance
in developing Integrated Development Plans for cities as well as assistance in
project implementation processes.
This institution has created a regeneration best practice database and possesses
the know how in regeneration management.
The Forum is not interested in institutional participation in the HF and UDFs but
may provide experts to support the above institutions with their knowledge.
Silesian Association of Municipalities and Poviats
The Association mission is to serve the local society and self-government units
of Śląskie Voivodeship. The SAMP has 114 member municipalities (including 19
cities with poviat rights) and 11 poviats. The spatial scope of its operation
covers the area inhabited by over 4 million people. All activities and initiatives
undertaken by the association aim at integration of the region and popularizing
the best practices in terms of local development. The idea of the Silesian
Association of Municipalities and Poviats is based on cooperation with other
organizations, both national and international, which can jointly realize
ventures leading to stimulation of regional development.
The main areas of SAMP interests are:
- shaping the common policy of local self-government units;
- representing local authorities;
- informing and training municipalities and poviats in European Union
procedures and programmes;
- urban policies;
- initiatives for economic development of municipalities, poviats and
their promotion;
- implementation of the “Rural Area Development Programme in
Municipalities and Poviats of Śląskie Voivodeship”;
C i t y C o n s u l t i n g I n s t i t u t e
Page 131
- informational and educational actions aimed at municipalities and
poviats.
The SAMP is also engaging in regeneration actions, supporting its members in
these processes. The Association may play an advisory role in JESSICA projects.
3.2. Ability and willingness of the private and public sectors to support
urban regeneration in Silesia through JESSICA
The interest of the public and private sectors as well as their ability to engage in projects
implemented within the JESSICA initiative have been analyzed and summarized below. The
comparison has been performed according to the particular unit’s interest in financial and strategic
management of regeneration projects, consultant role, capital or material commitment. Moreover,
the table below summarizes the interest of various institutions in managing projects or independent
project implementation, financing, capital or material commitment, partnership commitment based
on PPP. The table defines also the beneficiaries of credit-guarantee support. Preferred solutions are
marked as “++”.
C i t y C o n s u l t i n g I n s t i t u t e
Page 132
Table: Analysis of ability and willingness to implement projects financed within the JESSICA frame.
-- Impossible or unit not interested, - Difficult or not beneficial, +/- Possible, few benefits, + Unit interested, possible solution, ++ Unit very interested, prefered solution.
Unit Financial
management
Strategic
Management
Consulting
and control
Financing Capital
Commitment
Material
Commitment
Central administration -- -- + + - ++
Voivodeship administration - ++ ++ + ++ +
Poviats -- -- +/- -- -- +
Municipalities -- ++ ++ + + ++
Development agencies +/- ++ ++ - - +/-
Special purpose funds (environment, restructuring) - - + + + ++
The Upper Silesian Fund +/- ++ ++ + ++ ++
Commercial banks + - +/- ++ + --
International financial institutions ++ + +/- ++ + -
EIB ++ ++ ++ ++ ++ --
TFI + +/- +/- - + -
BGK + - +/- ++ + --
Polish and international public utility companies (i.e. municipal companies,
health care)
- - - - - +/-
Developers, other institutions investing in real estates (FIN) -- - - - - -
Polish and foreign entities managing regeneration processes + ++ ++ - - -
Institutions supporting regeneration and development of cities. -- +/- + - - -
C i t y C o n s u l t i n g I n s t i t u t e
Page 133
Table: Units’ engagement on project level.
Unit Project
management
Independent
project
realization
Financing
projects
Capital or
material
commitment
Capital
partnership
(PPP)
commitment
Assignee of
credit or
guarantee
support
Central administration - - - + - --
Voivodeship administration + + ++ + + +/-
Poviats + + ++ + + +/-
Municipalities + + ++ + + +/-
Development agencies + + - +/- +/- +/-
Special purpose funds (environment, restructuring) - - ++ +/- +/- -
The Upper Silesian Fund ++ ++ ++ ++ ++ -
Commercial banks - - ++ + - -
International financial institutions - - ++ + + -
EIB - +/- + ++ + -
TFI - - ++ + - --
BGK + ++ - + + +
Polish and international public utility companies (i.e. municipal companies,
health care)
+ + + + ++ +
Developers, other institutions investing in real estates (FIN) ++ + - - ++ +
Polish and foreign entities managing regeneration processes + +/- - - - +
-- Impossible or unit not interested, - Difficult or not beneficial, +/- Possible, few benefits, + Unit interested, possible solution, ++ Unit very interested, prefered solution.
C i t y C o n s u l t i n g I n s t i t u t e
Page 134
3.2.1 Conclusions: willingness to engage in JESSICA projects and institutional structure of
the Programme.
Table: Interest in engaging in JESSICA projects.
Interest identified Experience of the entity
Institutions
interested in the
establishment of
a HF
Except for the EIB, none of the
units interested in the JESSICA
initiative has shown willingness
to establish a HF. None of the
European institutions, which
could establish a HF without the
time consuming public
procumrement procedure, has
shown interest in it.
The EIB is the only European entity
experienced in creating and managing a HF
within the JESSICA initiative. The EIB is ready
to take over the HF creator role for indefinite
time or for the initial period only (e.g. until
2013). After this time, this function may be
taken over by e.g. The Upper Silesian Fund or
by another institution which will in the
meantime gain necessary experience with the
EIB support.
It is also possible to liquidate the HF after this
time.
Institutions
interested in
formation or co-
formation of
UDFs.
The Upper Silesian Fund
together with the companies
from its capital group is
interested in creating two UDFs
as separate financial
mechanisms. The Fund can also
manage a UDF established by
other units.
Gminas of the northern
subregion have shown interest
in forming a UDF and
contributing their own funds in
order to create an important
institution financing
regeneration of this subregion.
Experience of the Upper Silesian Fund covers
all aspects related with UDF management in
the JESSICA initiative. The Fund has broad
experience in self-government financing,
financial engineering, as well as
transformation of degraded areas. It is a
unique institution in the entire country, which
can solely perform activities related to finance
and regeneration processes management.
Experience of northern subregion gminas is
mainly based on long-term cooperation of the
city of Czestochowa with the EIB and common
regeneration projects. The city employs
a group of experienced experts, who run
financial accounting of EU and EIB funds. The
experts manage complex investment projects
C i t y C o n s u l t i n g I n s t i t u t e
Page 135
and have considerable knowledge on
integrated regeneration processes.
Institutions
interested in
content-related
support on
a programme,
fund or project
level
Regeneration Forum,
GAPP
The RF and GAPP experience has been
described in the previous chapter. These
institutions have a broad knowledge on
regeneration and transformation. They have
cooperated with Śląskie Voivodeship for
years. Therefore it is recommended to involve
them as experts in the content-related work.
Institutions
interested in
capital
commitment to
UDFs
Gminas.
Banks declare that in the future
they may financially support
UDFs, but currently the banking
law does not allow them to
participate in such projects.
Financial commitment from gminas may at
the beginning be the main source of financial
leverage in JESSICA. The binding law allows
them to establish companies dedicated to
urban development.
Besides, engagement of gminas gives the
possibility to create solid regional financial
institutions aimed at urban development.
Institutions
interested in
managing
complex
sustainable
projects for
urban
development
Subjects managing regeneration
processes – e.g. BIG STADTBAU.
They are mainly interested in
complex urban projects.
Experience gained in various European
regeneration projects.
Institutions
interested in
capital
commitment.
Gminas;
Private investors;
International companies;
Interest and experience of these companies is
very important and may lead to the second
step of the JESSICA financial leverage.
Institutions
interested in
managing
Gminas;
International companies;
Public utility companies;
Engagement of these institutions will result
from the Law on public procurement,
concessions and on PPP.
C i t y C o n s u l t i n g I n s t i t u t e
Page 136
projects Private companies;
Developers.
Institutions
interested in
financing
projects or
managing UDF
funds.
Investment funds;
BGK;
Commercial banks;
International financial
institutions;
TFI experience in closed investment funds
may be very helpful in the process of creating
an investment UDF. Moreover, formation of
such a fund by gminas can reduce operational
costs of the UDF and help in finding additional
financial resources on the market.
The BGK should also be an important partner,
involved in the JESSICA implementation
process from the beginning.
International financial institutions’ experience
will be useful in planning big, integrated
urban projects, after forming the UDFs.
3.3. Analysis of institutional models of JESSICA operation
3.3.1 Potential JESSICA organizational structures
Full organizational structure of the JESSICA initiative comprises the establishment of one Holding
Fund (HF) and Urban Development Funds (UDFs). The HF is not an obligatory element, but an
authority of the regions, giving various possibilities for more effective management of the
mechanism and receiving higher level of financial leverage. The JESSICA initiative is flexible and
basing on local conditions and European experience it can be easily adapted to the needs of Śląskie
Voivodeship.
C i t y C o n s u l t i n g I n s t i t u t e
Page 137
Table: Model: HF (EIB) + UDF
According to the above model, the HF will be established within the EIB structure. From the
Managing Authority perspective, this solution offers real financial benefits, resulting from the
reduction of technical support costs. The costs of establishing the HF within the EIB structures are
lower than the interest rate on the sum contributed to the HF.
Within this structure, it is possible to create more UDFs, according to real needs of the region.
The above model applies to most cases and is the only one guaranteeing quick and smooth
disbursement of financial resources for investment projects.
Managing Authority
Holding Fund [HF]
Created by EIB, technical support of EIB
Urban Development Fund
[UDF]
Urban Development Fund
[UDF]
Urban Development Fund
[UDF]
formal procedure of choosing entities managing the UDFs
C i t y C o n s u l t i n g I n s t i t u t e
Page 138
Table: Model HF + UDF
The above structure is similar to the first one, but the HF role is given to an external institution, in
accordance with the public procurement law.
Implementation of this structure offers the possibility of creating more UDFs, but may be time
consuming due the lack of knowledge and experience of the entity establishing the HF. Insufficient
experience in managing revolving instruments may be a critical factor here.
Table: Model UDF
Managing Authority
Holding Fund [HF]
Procedures of choosing the entity managing the HF
Urban Development Fund
[UDF]
Urban Development Fund
[UDF]
Urban Development Fund
[UDF]
Formal procedure of choosing the entities managing UDFs
EIB technical support (optional)
Managing Authority
Urban Development
Fund [UDF]
Urban Development
Fund [UDF]
Formal procedure of choosing the entities managing the UDFs
EIB technical support (optional)
C i t y C o n s u l t i n g I n s t i t u t e
Page 139
The above model is seems to be the simplest one. Nevertheless, due to the need of adapting UDFs to
the character of projects and disbursement procedures, developing contracts and contacting EU
institutions, it is highly probable that the UDF (or UDFs) will have to build complicated internal
structures. As the Managing Authority is obliged to perform independent internal controls, it will
have to copy the UDF structure and take over many of the Fund’s responsibilities.
In practice, this model has been adopted only in few German lands, but administrative problems
formally connected to its functionality did not allow spending any financial resources so far. In these
lands, UDF management is performed by regional banks. This solution results in the focus on financial
engineering, instead of the key objectives of JESSICA. In result, these institutions still do not fully
understand the needs and conditions of JESSICA. Basing on the German example it should be stated
that this model is difficult to implement and may paralyze regional development.
3.3.2. Establishment of a Holding Fund
The Council Regulation (EC) no 1083/2006 lays down general provisions on the European Regional
Development Fund, the European Social Fund and the Cohesion Fund. These funds aim primarily at
sustainable development of urban areas. Implementation details have been defined in the
Commission Regulation (EC) no 1828/2006. The Regulation sets out in detail the conditions which
financial engineering instruments should fulfil to be funded under an operational programme.
According to the preamble to the Commission (EC) Regulation 1828/2006:
„contributions to financial engineering instruments from the operational programme and other public
sources, as well as the investments made by financial engineering instruments in individual
enterprises, are subject to the rules on State aid including the Community Guidelines on State aid to
promote risk capital investments in small and mediumsized enterprises”.
The main tool to support sustainable development of urban areas is the EU support (including
financial aid). Joint European Support for Sustainable Investment in City Areas Programme (JESSICA)
is an innovative and very effective financial instrument aimed at regeneration, renovation and
development of urban areas. It enables its beneficiaries to combine funds from various sources into
one financial stream and use them to finance projects supporting regeneration and further
development of city areas. The sources may include e.g. capital contributions, loans, guarantees,
private-public partnership and other financial tools.
C i t y C o n s u l t i n g I n s t i t u t e
Page 140
The key role in JESSICA is played by the Holding Fund (HF) and the Urban Development Fund(-s)
(UDF).
According to the European Union assumptions, the start up capital for these Funds will come from EU
structural funds, distributed within Regional Operational Programmes. Therefore, the initial capital
will be contributed from public funds, which according to Article 78, paragraph 6 of the Council
Regulation (EC) no 1083/2006 are considered eligible costs.
Implementation of the JESSCIA initiative and establishment of HFs and UDFs in particular EU member
countries, requires investigation of country specific legislation. It applies also to the following issues:
- legal form of the HF and the UDF, acceptable by country specific legislation;
- procedures of choosing the HF operator and establishing the UDF;
- participation principles for self-government entities and private companies;
- legal conditions resulting from the regional development policy;
- possibility to include PPP in sustainable development of urban areas.
In EU legislation, the problem of the Fund’s legal form is considered in article 43 paragraph 3 of the
Commission Regulation (EC) no 1828/2006, which says that:
„Financial engineering instruments, including holding funds, shall be set up as independent
legal entities governed by agreements between the co-financing partners or shareholders or
as a separate block of finance within a financial institution.
Where the financial engineering instrument is established within a financial institution, it
shall be set up as a separate block of finance, subject to specific implementation rules within
the financial institution, stipulating, in particular, that separate accounts are kept which
distinguish the new resources invested in the financial engineering instrument, including
those contributed by the operational programme, from those initially available in the
institution.”
Therefore, the Commission does not choose only one, specific legal form of the HF and the UDF. It
says unambiguously that it should be an independent legal person or a financial entity allocated
within a financial institution. It means that according to the Polish law, the HF and the UDF may take
one of the following forms:
- company (joint stock or limited liability company, including private-public partnership
participation);
C i t y C o n s u l t i n g I n s t i t u t e
Page 141
- investment fund managed by an entity selected for this purpose, e.g. Investment Fund
Associations (TFI) or the European Investment Bank (EIB).
Each of these legal entities assures that theHF and UDFs have the legal capacity to:
- sign contracts;
- contribute to capital;
- grant loans and guarantees.
Establishment of the HF is optional. According to the Council Regulation (EC) No 1083.2006 Art. 44, in
order to implement an operational programme, each EU member state may use financial engineering
instruments, including Urban Development Funds and/or optionally – a Holding Fund.
Nevertheless, taking into account that Poland does not have any experience in implementing JESSICA
and all procedures have to be created from scratch, there is strong rationale behind creating the HF.
The potential benefits of this solution result mainly from the fact that the HF takes over a significant
part of the administration from the Managing Authority (in this case a regional self-government
entity). One should consider both the overall HF management and development (according to Article
43 of the EC Regulation No 1828/2006) of the Operational Plan of actions covering also financial
engineering instruments. The Operational Plan should include a number of key elements mentioned
in the Regulation and consider the methods, criteria, rules and conditions for financing city projects.
The Holding Fund takes over also the responsibility to choose the UDF operator(-s) by means of a
competition.
According to Article 44 of the Council Regulation (EC) no 1083/2006, as part of an operational
programme, the structural funds may finance expenditure in respect of an operation comprising
contributions to support financial engineering instruments for enterprises, primarily small and
medium-sized ones, such as venture capital funds, guarantee funds and loan funds, urban
development funds, that is funds investing in public-private partnerships and other projects included
in an integrated plan for sustainable urban development.
When such operations are organised through holding funds, that is funds set up to invest in several
venture capital funds, guarantee funds, loan funds and urban development funds, the Member State
or the managing authority shall implement them through one or more of the following forms:
(a) the award of a public contract in accordance with applicable public procurement
law;
C i t y C o n s u l t i n g I n s t i t u t e
Page 142
(b) in other cases, where the agreement is not a public service contract within the
meaning of public procurement law, the award of a grant, defined for this purpose as
a direct financial contribution by way of a donation:
o to the EIB or to the EIF; or
o to a financial institution without a call for proposal, if this is pursuant
to a national law compatible with the Treaty.
It has to be stressed, that Council Regulation (EC) No 1083/2006 states, that structural funds within
an operational programme may be spent to support financial engineering instruments. At the same
time, the regulation emphasizes that in case this operation is organized through holding funds, a
member country or a managing authority disburses these resources by applying public procurement
procedures.
This regulation allows skipping the procedure in case the contract for services is realized through a
subsidy granted in the form of a direct contribution or donation. The legislator stresses that
disregarding the public procurement procedure is only possible if a financial instrument (assignee)
receives a grant within an operational programme. This form is acceptable for the EIB, the EIF and
financial institutions.
In the Polish legislation, the problem of awarding public contracts from public funds (e.g. structural
funds) is regulated by the Law of 29 January 2004 –Public Procurement Law. The Law does not apply
only in cases described in Article 4. Point 7 of this Article states that this regulation does not apply to
subsidies from public funds awarded on the basis of laws and acts.
There is no unambiguous, direct regulation, excluding the necessity of applying the public
procurement procedure in the process of distributing resources from operational programmes to
holding funds. As far as the EU legislation is concerned, Article 44 of Council Regulation No
1083/2006 regulates this issue unequivocally, as cited above.
Polish legal regulations defining the mechanism of supporting beneficiaries with public funds to
implement projects co-financed from structural funds have been included in the Act of 30 June 2005
on public finances and the Act of 6 December 2006 on the principles of development policy.
Unfortunately, it is impossible to find in these Acts as unequivocal regulations as in case of Article 44
of the Council Regulation (EC) 1083/2006.
C i t y C o n s u l t i n g I n s t i t u t e
Page 143
Taking into account the significant interest in financial engineering instruments in Poland, the
Chairman of Public Procurement Office in his letter of 2 February 2009 No OZP/DP/0/2151/1305/09
presented the interpretation of the current legislation in this subject. He affirmed among others that:
according to the provisions of Art.106, paragraph 2, point 3a of the Act of 30 June 2005 on public
finances, there are development subsidies granted for programs, projects and financial assignments
supported by structural funds and the Cohesion Fund (Art. 5, paragraph 3, point 2). Therefore,
according to Art. 4, point 7 of the Public Procurement Law, while granting development subsidies
based on the Act of 30 June 2005 on public finances, provisions of the Public Procurement Law do
not apply. In this respect it should be assumed that financial resources awarded to beneficiaries
within operational programmes as development subsidies (as in Act of 6 December 2006 on the
development policy) are excluded from the obligation to follow the procedures of public
procurement (Art. 4, Point 7 of the Public Procurement Law)
The cited act states also, that according to the Paying Authority Department in the Ministry of
Finance (letter of 13 January 2009, No OP 3/063/22/LRE/09/09/14381) funds granted on the basis of
Art. 44 of the Council Regulation (EC) No 1083/2006 are in line with the definition of a development
subsidy defined in Art. 106, paragraph 2, point 3 of the Act of 30 June 2005 on public finances. The
content of this article argues for this, as it states that grants are state budget expenses, which may be
supported by the article stating that subsidies are state budget expenses dedicated for programmes,
projects and financial assignments supported from structural funds. Transferring financial resources
within a holding fund may be therefore performed according to the Act of 30 June 2005 on public
finances.
According to Art. 27, paragraph 1, point 3 of the Act on development policy, projects may be
financed within an operational programme after a competition organised in accordance with the
criteria defined by the Monitoring Committee. Therefore, in accordance with Art 29-31 of the Act on
development policy, the procedure leading to the selection of the beneficiary (in this case a holding
fund) is open and transparent.
At the same time, according to the opinion of the Paying Authority Department in the Ministry of
Finance, funds granted on the basis on Art. 44 of the Council Regulation (EC) No 1083/2006 are in
line with the definition of a development subsidy defined in Art 4, point 7 of the Public Procurement
Law. It should be thus assumed that transferring financial sources to a holding fund within an
operational programme can be arranged on the basis of Art. 28, paragraph 1, point 3 of the Act on
development policy and Art. 106, paragraph 2, point 3a of the Act of 30 June 2005 on public finances.
C i t y C o n s u l t i n g I n s t i t u t e
Page 144
In this case – according the to the quoted interpretation of the Chairman of the Public
Procurement Office – the Act “Public Procurement Law” by exclusion (Art. 4, point 7) will not be
applicable for the procedure of choosing the holding fund, mentioned in Art. 44 of Council
Regulation (EC) No 1083/2006.
However, the consultant would like to emphasize that according to the common law doctrine,
interpretation of current legal norms does not constitute the binding law.
The decision on the discussed issue has to be made by the Managing Authority (in this case the
Voivodeship Management Board) on its own responsibility. Special attention should be given to
maintaining full transparency while choosing the mechanism of granting the right to run the Holding
Fund.
In the consultant’s opinion, only entrusting the EIB with the task of establishing and managing the HF
or alternatively following the full procedure described in the Act on public procurement (as well as
Art. 44 of the Council Regulation) would assure full transparency and chance to work out significant
added value, e.g. additional income from deposits in commercial banks. According to the analyses
conducted, it would be only possible, if the EIB was appointed as the holding fund operator. In the
consultant’s opinion, in case the Voivodeship Board of Management prefers applying the
competition procedure leading to the appointment of a holding fund operator, it has to be absolutely
sure that:
it will be able to run the competition, keeping open and transparent procedures;
the Holding Fund operator will be the best one in all aspects – content-related, social, and
financial.
Table: Choosing the HF operator in accordance with the Public Procurement Law.
Disadvantages Advantages
Time consuming tender procedures (risk of high number of offers, cancellations, protests);
Shortage of institutions experienced in managing HFs in Poland;
High risk of offering HF management to an entity, which will need content-related support from the Managing Authority (via EIB);
Need to follow the provisions of the Public Procurement Law in the process of signing financing contracts with UDFs;
Significant delay in the UDF establishment process.
Additional mechanism mobilizing entities operating on the Polish fund management market to better understand and implement the financial instruments within JESSICA.
C i t y C o n s u l t i n g I n s t i t u t e
Page 145
Table: Entrusting HF management to the EIB.
Disadvantages Advantages
None Significant acceleration of procedures leading to signing the contract for Holding
Fund management, and thereby acceleration of the UDF creation process;
Great substantive knowledge of the EIB on the implementation process of the
JESSICA initiative, enriched by the experience in implementing similar projects in
other member countries;
Guarantee that the EIB will prepare professional documentation, concerning
especially the Operational Plan and the contest for the best UDF offer;
Signing financing contracts with UDFs on the basis of transparent selection
procedures resulting from internal EIB regulations (no public procurement
procedures).
3.3.2.1. Basic tasks of holding funds (HF)
The main tasks of holding funds include:
taking over the majority of administrative work related with UDF establishment and
project monitoring from the Managing Authority;
consultancy on choosing the best UDFs;
implementation of the Investment and Planning Strategy;
implementation of all actions, including identification and consultancy by the process
of selecting the UDFs that may receive funds from the JESSICA Holding Fund;
evaluation of business plans presented by UDFs (in line with the Investment and
Planning Strategy) and advising the Investment Council on potential options;
negotiating Operational Contracts with UDFs and signing Operational Contracts for
the JESSICA Holding Fund, when the key Operational Contracts are accepted by the
Investment Council.
monitoring and control of operations, according to the conditions of particular
Operational Agreements and the Contract;
C i t y C o n s u l t i n g I n s t i t u t e
Page 146
presenting to the Investment Council a report on every operation progress; the
reports shall include information on financial inputs from UDFs to city projects as
well as information on irregularities reported by UDFs;
collecting and handing over to the Managing Authority all information received from
UDFs concerning UDF investments in city projects, so that the MA would be able to
follow all the binding home and EU regulations on state aid, considering that the MA
will be the only party responsible for monitoring the compliance with EU regulations
on state aid and informing the Commission or other relevant domestic institutions
responsible for state aid;
undertaking (to a sensible extent) informational and promotional actions on the
JESSICA initiative and related operations, organizing and/or participating in
conferences and seminars;
managing JESSICA finances, according to the Financial Guidelines;
under the Investment Council consent, the HF will also extemporaneously implement
additional tasks leading to more efficient and effective implementation of JESSICA
activities, like:
o providing (to a sensible extent) help in preparing documentation necessary
for the MA to follow the EU regulations on state aid and/or information on
big projects, their notification, with the reservation that the Managing
Authority is the only party responsible for notifying all operations to the
Commission, if the EU legislation requires such a notification;
o providing (to a sensible extent) support in interpretation of EU regulations
concerning financial engineering and in particular the eligibility of costs;
o providing (to a sensible extent) help in choosing and/or putting the finishing
touches on the integrated plans for permanent and sustainable development
of urban areas and city projects;
o ensuring training for middlemen and other key partners, in order to support
further development of the JESSICA initiative and the public-private
partnership in the urban sector.
C i t y C o n s u l t i n g I n s t i t u t e
Page 147
3.3.2.2. Benefits resulting from the HF establishment
Benefits resulting from the HF establishment include:
Significant acceleration of absorption of structural funds (due to the fact that on the
basis of the Council Regulation (EC) No 1083/2006 Art. 78, paragraph 6, contribution to a
HF is considered eligible cost);
Possibility to gain higher income from investing the Fund’s resources;
Simplification and acceleration of procedures in case the HF was established within the
EIB structures (the solution does not necessitate competition procedures);
Possibility of implementing a greater number of financial tools through the
establishment of separate credit-guarantee and capital UDFs;
Possibility of engaging self-government units and the banking sector, which should result
in better financial leverage effect achieved thanks to creating smaller UDFs for sub-
regions and contributing self-government capital for this purpose.
3.3.2.3. Entities that may potentially establish a HF
Table: The Upper Silesian Fund – advantages and disadvantages
Important to function Disadvantages Advantages
Speed of implementation Selection by means of a
competition.
Selection possibility Necessity to organize a
competition.
Experience in implementing
JESSICA
None.
Experience in managing EU
funds
Great experience in managing
loan instruments.
Experience in managing
financial engineering
instruments
Great experience. Various
financial tools.
Ability to assess feasibility Great experience.
C i t y C o n s u l t i n g I n s t i t u t e
Page 148
Important to function Disadvantages Advantages
studies, business plans,
investment strategies.
Experience in regeneration
processes
Little experience -
transformation processes only.
Experience in developing
Integrated Urban Development
Programmes
None.
Experience in managing
regeneration processes
Through its subsidiary – CPR
Investor
Experience in negotiations with
European institutions
Little.
Experience in PPP None.
Knowledge on the needs of
local self-government entities
Extensive.
Experience in leading complex
investment projects.
Little experience in
infrastructural and real estate
investments.
Experience in capital
investments.
Knowledge of local companies’
needs.
Extensive.
Ability to negotiate
interpretations of regulations
related to JESSICA directly with
the European Commission.
None.
Possibility of finding additional
partners to finance projects.
European institutions
Average.
Possibility of finding additional
partners to finance projects.
Banks and Polish institutions
Great knowledge on the
financial market.
Impact of the regional self-
government on the
institution’s operation.
Capital impact - as a
shareholders meeting.
Via the Programme Council,
capital impact - as the
shareholders meeting,
supervision as the MA.
C i t y C o n s u l t i n g I n s t i t u t e
Page 149
Table: EIB – advantages and disadvantages
Important to function Disadvantages Advantages
Speed of implementation Almost immediate
implementation and
disbursement. The mechanism
has been tested in other
regions.
Selection possibility No necessity to organise a
competition.
Experience in implementing
JESSICA
Institution responsible for the
initiative implementation in the
EU.
Experience in managing EU
funds
Multifaceted experience in
managing funds.
Experience in managing
financial engineering
instruments
Great experience. Various
financial tools.
Ability to asses feasibility
studies, business plans,
investment strategies.
Great experience.
Experience in regeneration
processes
Experience in the
implementation of
regeneration strategies in EU
member states. Possibility of
implementing the experience of
other countries.
Experience in developing
Integrated Urban Development
Programmes
Consulting the processes of
developing IUDPs in other
European countries.
Experience in managing
regeneration processes
Little experience in direct
project management.
Experience in financing big
regeneration projects in Europe
Experience in negotiations with
European institutions
Great experience.
C i t y C o n s u l t i n g I n s t i t u t e
Page 150
Important to function Disadvantages Advantages
Experience in PPP Considerable experience in
developing projects and
financial engineering with EU
funds.
Very important in the initial
phase – the EIB as the high
credibility institution for PPP.
Knowledge on the needs of
local self-government entities
Little knowledge on the needs
of small cities.
Considerable experience in
cooperation with bigger cities
of the region.
Experience in leading complex
investment projects.
The main objective of the bank
is to involve in big investment
projects.
Knowledge of local companies’
needs.
Little knowledge on the market.
Ability to negotiate
interpretations of regulations
related to JESSICA directly with
the European Commission.
Considerable experience,
enabling receiving
interpretations in short time.
Very important element in the
initial phase of the mechanism
implementation.
Possibility of finding additional
partners to finance projects.
European institutions
Cooperation with other EU
institutions in many projects.
Possibility of finding additional
partners to finance projects.
Banks and Polish institutions
Extensive knowledge of the
domestic and international
financial markets. High
credibility of the EIB.
Impact of the regional self-
government on the
institution’s operation.
Via the Programme Council.
Supervision as the MA.
C i t y C o n s u l t i n g I n s t i t u t e
Page 151
Due to the fact that the only institution interested in establishing the HF is the EIB, other options
engaging other financial institutions have not been analyzed. Basing on previous analyses, the Upper
Silesian Fund can be also considered as a potential HF.
The following conclusions may be drawn on the basis of the above considerations:
In the first stage of the mechanism operation, the HF establishment should be entrusted to the
EIB (if the MA decides to establish a HF). The solution guarantees the application of well known
legal mechanisms and quick absorption of EU funds;
Initially (in period 2010-2013), the best practices database of JESSICA will be created and in this
period cooperation with the EIB is the most important and beneficial. The few months period for
interpretation of the Polish law may be significantly shortened. Basing on the experience
resulting from the implementation of Cohesion Fund projects, it may be stated that participation
of a European bank in an investment may accelerate the decision making process by up to 1 year.
Due to the fact that the investment cycle for regeneration projects lasts approximately for 5
years (profit-oriented investments eligible for JESSICA have not been prepared by self-
governments in detail), a possibility to shorten the procedure is one of the key issues.
PPP – implementation of PPP in Poland has for years faced many problems. Introduction of new
legislation in this area at the beginning of this year has slightly improved the situation. Still, the
ventures undertaken as partnership are saddled with high political risk. Involvement of an
institution like the EIB will be a strong argument for PPP implementation;
Term in office. In case of rigorous time frame for JESSICA implementation, in the initial phase the
risk connected with different people coming to power after the end of each term in office should
be eliminated. The possibility of supervision over the Upper Silesian Fund acting as the HF is both
an advantage and a disadvantage. As a result of election, the authorities of subsidiaries change.
Unfortunately, the change very often leads to interruptions in regular work and reluctance to
make decisions in the period few months before and after the election. Despite of the best
intentions of authorities of all levels to reduce this phenomenon, it is common all over the world.
In this case, it is another prerequisite for appointing the EIB as the HF in the initial phase;
Another positive effect of choosing the EIB is knowledge transfer to the institutions managing the
UDFs. In result, in further phase of JESSICA operation, the HF function can be taken over by
another organization (e.g. the Upper Silesian Fund);
C i t y C o n s u l t i n g I n s t i t u t e
Page 152
After 3-4 years, if the number of UDFs is small and self-government entities (associations of
cities) take over all HF activities, the HF might be liquidated. It may lead to a certain increase of
MA administration, but this model may be effective from the economic perspective;
3.3.3. Establishment of Urban Development Funds
The key role of UDFs in JESSICA results from the principal aims of these funds. These are: strong and
effective stimulation of regeneration and further development of urban areas in particular EU
member countries. They should considerably contribute to:
improvement of competitiveness and attractiveness of cities for their citizens, students,
scientists and investors;
optimization in absorption of the capital devoted to urban development, including in
particular post-industrial and post-military areas;
creation of stimuli for efficient management of financial resources available for various
entities, including private units and spending them for the purpose of project
implementation within regeneration processes.
Implementation of the above objectives will be executed by innovative UDF products, like:
granting loans;
acquiring shares in companies providing public services;
granting guarantees for subjects financing projects, including private entities.
According to Art. 43. of the Commission Regulation (EC) No 1828/2006, the decision to establish
Urban Development Funds, their number, objectives and methods of operation belongs to the
Managing Authority. The MA should also decide on the legal form of UDFs. The cited provisions of
the Commission Regulation indicate the key MA role, in particular through the obligation to prepare
the Operational Plan and Financing Contracts.
The decision of the MA concerning the number of UDFs should be preceded by an analysis revealing
the number of potential projects eligible for this type of financing in each city and also the interest in
JESSICA declared by cities of the region. Due to the fact, that in the initial phase UDFs will have
limited financial funds granted from Regional Operational Programmes, it seems reasonable to
reduce the number of UDFs to the essential minimum resulting from the direct initiative of particular
cities.
It is possible to create one big UDF for the entire region. The main advantage of this solution is the
possibility to create one central project database, which will diversify the risk related to the selection
C i t y C o n s u l t i n g I n s t i t u t e
Page 153
process of projects in terms of their socio-economic importance and profitability. Another advantage
of this solution is the reduction of costs related with effective management of the Fund. However,
the main disadvantage of this solution is the impossibility to define the Fund’s specialization and to
target its geographical range to a specific region and its needs.
Another solution is to create 3-4 UDFs in the Region. Nevertheless, the initiative in this respect
should come from particular self-government entities. Considering the great engagement of Silesia in
the process of creating advantageous conditions for effective absorption of EU funds and great
regeneration needs in both big and smaller cities, it should be stressed that this solution will have a
positive impact on the interest of local self-government authorities and other entities being potential
shareholders of the Fund aiming at financing ventures that are important from their point of view.
The only shortcoming of this solution in the initial phase of the UDF existence would be dispersal of
funds granted from the ROP and dedicated to the UDFs. Nevertheless, the main strength is the ease
of accumulating experiences in the initial phase of JESSCIA implementation as well as lower risk of
directing significant resources for a project which will not result in any added value.
As it was shown in point 3.3.1., the problem of the legal form of UDFs in the EU legislation has been
regulated in Art. 43, paragraph 4 of the Commission Regulation (EC) No 1828/2006, which does not
restrict or recommend one specific legal solution. It states unambiguously that it should be “an
independent legal person” or “a financial entity allocated within a financial institution”. It means
that in Polish legal conditions, UDFs may take two forms:
company (joint stock or limited liability company, including private-public partnership
participation);
investment fund managed by an entity selected for this purpose, e.g. Investment Fund
Associations (TFI) or the European Investment Bank (EIB).
Each of these legal entities assures that the HF and UDFs have the legal capacity to:
sign contracts;
contribute to capital;
grant loans and guarantees.
It has to be emphasized that in each of these legal forms, partners of different legal status may be
engaged:
C i t y C o n s u l t i n g I n s t i t u t e
Page 154
Self-government units and legal persons established by self-government entities to
implement public tasks;
Banks;
Agencies;
Private units (on the basis of the Public-Private Partnership Law)
Other financial institutions.
It means that there is a number of possibilities to establish an UDF operating as “as independent
legal entities governed by agreements between the co-financing partners or shareholders” (Art.43,
paragraph 3 of the Commission Regulation (EC) No 1828/2006).
These may include the following:
Limited company created by one self-government entity (as a subsidiary with 100% of
shares owned by the self-government) or by several self-government entities with equal
amount of shares and votes;
Limited company, whose shareholders may include: self-government entities, banks,
agencies, already existing nationwide or regional Funds or private partners;
Limited company created on the basis of the Public-Private Partnership Act. The new PPP
Act does not obligate the public partner to choose a particular cooperation mode. Self-
government entities may choose from among various options resulting from the Act,
including setting-up a subsidiary or applying the concession model for construction works or
services;
UDF created in cooperation with an already existing Regional Fund (e.g. the Upper Silesian
Fund established by Silesian self-government entities).
Participation in funds means in this case also profit sharing.
Territorial self-government units can establish and join companies without any restrictions.
Nevertheless, the Report cannot omit certain restrictions resulting from the legal status of poviats
and voivodeships. . These restrictions result from the currently binding Municipal Services Law (Art.
10), the Act on poviat self-government (Art. 6) and the Act on voivodeship self-government (Art. 13).
These Acts narrow the scope of activities of the companies established with poviat’s involvement to
public tasks, and in case of voivodeship self-government – to public tasks and promotional actions,
education and editorial activities leading to regional development. On the other hand, UDFs (in
accordance with the Commission Regulation (EC) No 1828/2006) may grant loans, guarantees, as
well as invest in projects, whose scope may exceed the scope of public tasks of territorial self-
C i t y C o n s u l t i n g I n s t i t u t e
Page 155
government. It means that only gminas would be able to independently establish UDFs, whereas
other local self-government units could participate in the UDFs being joint stock or limited liability
companies, established in cooperation with other units.
There are similar conditions and restrictions regarding territorial self-government engagement in
investment funds in the Polish legislation.
It should be emphasized that thanks to current actions undertaken by the Polish central government,
whose aim is to provide favourable conditions for the development of small and medium sized
companies, the restrictions described above will soon disappear.
On 24 August 2009, the Polish government approved a draft of an Act introducing changes to the
Acts on municipal services, poviat and voivodeship self-government. The draft changes radically
the content of the above cited articles, by widening the list of territorial self-governments which can
act outside the public services sector (poviats and voivodeships are to be added to the list). A draft of
these changes was directed to the Sejm already in September 2009.
The impulse for the Ministry of Economy to work on an amendment of these Acts was the document
entitled “Directions for Development of Credit and Guarantee Funds for Small and Medium Sized
Companies in the Years 2009-2013” that had been previously accepted by the Council of Ministers.
According to this document, self-governments of voivodeship and poviats will play the key role in the
process of shaping conditions for the development of small and medium sized companies in the
years 2009-2013. In the Council’s opinion, this objective will be reached by allowing self-
governments to create or participate in limited companies whose operation concentrates on granting
credits, guarantees or securities in order to support the entrepreneurship.
It has to be underlined, that on the basis of the above cited EU legislation, holding funds and UDFs
could theoretically take the form of state and self-government special purpose funds. However,
according to the Polish legislation this solution would necessitate the Sejm to pass a law on the
establishment of these Funds first.
To summarize, in the current legal situation, there are no obstacles to establish UDFs. It seems thus
most reasonable to create UDFs in the form of limited companies or within public-private
partnership.
C i t y C o n s u l t i n g I n s t i t u t e
Page 156
3.3.3.1. UDF business models
An analysis of EC guidelines on the initiative implementation proves that UDFs are not institutions
managing investment projects but institutions financing such projects. Taking into account economic
effectiveness and the objective to create a long term financial tool to support regeneration
processes, one may distinguish two separate business models:
loan model (money lender);
capital model (capital investor).
Each model requires specific approach and set of tools. On the example of banking institutions it can
be assumed that crediting and investment banking should be separated.
The loan approach is the easier one, related with lower risks, based on the passive UDF approach
towards projects. However, this model gives significantly lower return rates and results in a burden
of securing projects. In case of projects implemented by self-governments (self-government
subsidiaries), the necessity to issue guarantees may result in a negative decision on project
implementation.
The investment approach requires much deeper analysis of business risks. This model requires also
much broader knowledge on regeneration mechanisms from UDFs. On the other hand, it gives much
higher return rates on capital and results in a possibility to develop the UDF. From the perspective of
PPP projects, the investment model increases the projects’ credibility in the eyes of a society.
In case of gminas’ capital contribution to UDFs and in case of PPP projects, none of the above models
can function as a financial pool within an existing financial institution.
3.3.3.2. UDF operating as a credit – guarantee institution
Required skills:
the ability to judge an organization with regard to income generation ability and ability to
discharge liabilities;
the ability to judge the level of securities;
the ability to evaluate an investment project with regard to market risk and ability to
discharge liabilities;
the ability to evaluate the project impact on the integrated effect of urban development,
including the value of land.
C i t y C o n s u l t i n g I n s t i t u t e
Page 157
3.3.3.3. UDF operating as a capital investor
Required skills:
the ability to judge organisations being shareholders with regard to their abilities,
experience and business credibility;
the ability to evaluate the market and credibility of business plan provisions. Expertise in
judging market research and analyses;
the ability to evaluate an investment project with regard to market risk and ability to
discharge liabilities;
the ability to evaluate the project impact on the integrated effect of urban development,
including the value of land.
3.3.4. HF/UDF model
Full model of JESSICA operation.
The above model is the optimum one in terms of functionality and technical aspects. An important
issue influencing the financial leverage level in this model will be separation of the loan and
investment UDFs as well as the UDF established by cities (one or few).
Marshal Office of ŚląskieVoivodeship
HF
UDF - loans
UDF - capital
UDF - cities (optional)
C i t y C o n s u l t i n g I n s t i t u t e
Page 158
3.3.4.1. Advantages and disadvantages of the full model of JESSICA
implementation.
Śląskie Voivodeship is the biggest urbanized region in Poland. The result is the greatest diversity and
amount of regeneration projects and programmes. In order to manage them effectively, it is
necessary to involve in the process a regional institution that could provide administrative, financial
and content-related support. This institution should be responsible for supervision, training, advising
and control.
In Śląskie Voivodeship there are 4 strong sub-regions;
As the result of the mechanism implementation in the Wielkopolska region, an initiative to
create own UDFs has appeared in some cities;
Operational costs of a HF are not higher than 2%, so if the initiative budget is assumed for
approx. € 40 M, it would be around € 800 000 per year. The costs of establishing an entity
that would serve one UDF and a few big projects may be significantly lower. The costs of
establishing an entity that would serve two or more UDFs granting greater amounts of loans
may exceed the 2% value;
In order to choose an institution that would establish the HF (other than the EIB), it is
necessary to organize a competition procedure which may be time consuming;
In case a greater number of UDFs is established, the control over them without the HF
support will be very difficult and could lead to the increase of the MA costs;
Creation of more than one UDF will result in a strong financial leverage effect, through
financial contribution of gminas and other organizations. It is thus a chance to create an
important financial institution to manage regeneration processes.
Table: Advantages and disadvantages of the full JESSICA implementation model.
Advantages Disadvantages
No need to extend the administration within the
MA.
Higher direct costs.
Possibility to obtain higher profits from investing
the Fund’s resources.
Small possibility of financial leverage on the HF
level.
Possibility to establish UDFs specializing in loans,
capital investments and particular cities. Greater
If the HF establishment is not entrusted to the
EIB, it will be necessary to prolong the process
C i t y C o n s u l t i n g I n s t i t u t e
Page 159
effectiveness and flexibility of operation. by organizing competitions leading to the choice
of HF and UDF operators.
A strong financial leverage effect will appear
with higher number of UDFs.
In the long-term perspective, after gaining some
experience and independence by UDFs and after
clear interpretation of legislation is available, the
HF should be liquidated.
High interest of gminas in creating UDFs, if
content-related support from the HF is available.
An entity that may undertake integrated actions
towards law interpretation. Especially
advantageous, if the HF is operated by the EIB.
3.3.5. One UDF model
3.3.5.1. Conditions and advantages of the one UDF model
This model is economically justified in case of a region implementing only few homogeneous projects
in terms of business-economical models of the venture. The basic advantage of this model is the lack
of HF management costs. However, only some HF responsibilities can be taken over by the UDF,
whereas the rest will stay with the MA, which will also generate some additional costs and increase
the MA responsibility.
In case of choosing the operational model based on one UDF, the choice of institution managing
UDFs should be conducted by means of a competition. However, on the MA level, it would be
necessary to create a separate department to analyze all the procedures from the banking,
economical and ROP requirements perspective. Due to the fact that UDFs are to be profit oriented,
the MA will have to judge the economic effectiveness of each project and credit worthiness of the
beneficiaries (not gminas!).
It would be problematic to conduct the UDF activities in both crediting and investment areas. All
market institutions separate these two types of operations. Therefore, in case of choosing the model
based on one UDF, the MA should reduce the JESSICA character to only one operational form.
The choice of the model based on one UDF is reasonable in case of smaller entities and in case of
implementing only few projects, e.g. crediting.
C i t y C o n s u l t i n g I n s t i t u t e
Page 160
In case of one complex UDF, costs of its operation may even exceed the total costs of HF creation, as
it would be necessary to build control and decision making structures within the MA. The experience
of existing regional credit funds concentrating on small loans for many assignees reveals that they
are also generating high operational costs, exceeding the level acceptable for UDFs - 3%.
In addition, due to the lower interest of self-government entities to contribute capital to a central
institution, the financial leverage in this model would be reduced to a minimum.
3.3.5.2 Institutions that may establish one UDF
Institution Conditions
Local financial
institution, e.g. the
Upper Silesian Fund,
local Investment
Fund
No experience in JESSICA procedures;
Experience in finance and credit funds management;
Little experience in managing investment processes;
Extensive knowledge on local market conditions;
Possibility to receive little self-government support.
Due to the little experience in the mechanism operation, the Upper Silesian
Fund is interested in the creation of a second level UDF (with a separate HF
institution).
Local institution
dealing with
regeneration,
restructuring, etc.
E.g. GAPP,
Regeneration
Forum,
Development
Agencies.
No experience in JESSICA procedures;
Experience in finance and credit funds management;
Little experience in managing investment processes;
Extensive knowledge on local market conditions;
Possibility to receive little self-government support.
Due to the little experience in the mechanism operation and the obligation
to build financial engineering tools from scratch, these institutions are not
ready to implement JESSICA in the region. They may take part in a second
level UDF, with the HF support in terms of procedures as well as finance and
risk management.
Banking institutions
- national or
international
No experience in JESSICA procedures;
Some German regional banks have little experience in the initiative
implementation in Germany. However, an analysis of the German
case proves that bank concentration on financial engineering is
disadvantageous to the initiative and results in the impossibility to
C i t y C o n s u l t i n g I n s t i t u t e
Page 161
start the mechanism and spend resources for the projects. Presently,
there is a discussion in those lands organized on the possibility to
withdraw from this model and to shift to the HF/UDF model, applied
in other EU countries.
Experience in managing finances and credits;
Great experience in risk management;
Little experience in direct management of investment processes;
Lack of knowledge on local conditions;
No experience in regeneration processes;
Impossibility to get any self-government support.
Banks have very little experience in creating JESSICA mechanisms and
managing regeneration processes. Entrusting the role of one UDF to banks
carries the great risk of wasting the chance that JESSICA offers in
regeneration processes and local self-government activation.
Banks have a great role to play as:
institutions co-financing projects;
institutions managing the finance – related tasks of UDFs established
by gminas (If gminas decide to create their own UDFs, with banks’
support only content-related issues will have to be controlled by
them);
CONCLUSIONS:
Currently, there is no institution which could create the JESSICA model based on one central UDF.
The choice of such a model will necessitate a great amount of preparatory work on the regional
administration side. Further control of project implementation and financial policies will also be
the responsibility of the Marshal Office.
The one UDF model requires the founding entity to be a financial institution, able to manage
regeneration processes on the local scale.
The choice of any of the above mentioned entities will be related to risk - higher than potential
benefits.
C i t y C o n s u l t i n g I n s t i t u t e
Page 162
This choice is also related with the risk of not spending the resources available until 2015, due to
the necessity of working out all the procedures, preparing projects and implementing them, with
limited experience of the people engaged in the process.
Another risk of this model is the fact that in order to simplify all the operations, the institution
responsible for UDF establishment will decide on the crediting character of the mechanism. In
result, interest in the application of the mechanism in regeneration processes will be considerably
smaller and the impact of JESSICA on PPP will be marginal.
Currently, the Consultant suggests choosing the HF model and creating two or more UDFs. After
the implementation period, liquidation of the HF and direct supervision of UDFs by the Marshal
Office may be considered. After the implementation period, the HF interest may be reduced, to be
fully covered from the UDF profits.
3.3.6. Institutional model and project financing possibility
3.3.6.1. One UDF model
In case of choosing this model, the UDF should be created as a crediting and guarantee institution.
The value of projects should exceed 2 000 000 €. In case of crediting smaller projects, UDF costs
(application evaluation, consulting point’s maintenance, training, financial services, administration)
may exceed the 3% limit. In most projects, it has to be assumed that projects with high level of
security will be preferred (e.g. with gmina guarantees).
3.3.6.2. HF and 2 UDFs model
This model gives the possibility to create two financial institutions, specialized in different tools of
financial engineering. The establishment of the investment UDF gives the possibility to manage more
complicated investment processes and receive securities in a form other than liabilities of self-
government budgets. The business models of the finaced projects should be rather simple. Projects
whose profitability will depend on special local conditions, difficult to be measured and evaluated by
a central UDF will encounter difficulties in receiving the financing decision.
3.3.6.3. HF and a greater number of UDFs
This model offers the greatest flexibility in financing projects. Apart from the advantages mentioned
above, within this solution it is easier to finance projects of sub-regional character. This model
requires close cooperation with the HF, which can play the role of a supplier of financial evaluation
tools for smaller UDFs. Without this support, running small UDFs may be too expensive.
C i t y C o n s u l t i n g I n s t i t u t e
Page 163
It seems reasonable to establish one bigger loan UDF and some more investment UDFs. In case of
small UDFs, the investment form will bring better return on capital and will help increase their
potency.
3.3.6.4. EBI involvement and possibility of project financing
The EIB involvement as the HF is crucial for project financing as the Bank has ready business tools
that may be offered to UDFs. In addition, many projects will necessitate financial engineering, based
on additional financing sources. Here the possibility to obtain some funds from other EU institutions
is invaluable. The EIB declares at the same time that it can provide additional support from own
funds, which should considerably increase the financial leverage.
3.3.7. Institutional model and participation ability
3.3.7.1. One UDF model
No institution has shown any interest in participation in this central institution. Both gminas and
banks do not declare interest in the support on one UDF level. Participation is only possible on a
project level.
3.3.7.2. HF and 2 UDFs model
External entities show interest in participation within this model. Initially, this interest in related to
the possibility of engaging in an investment UDF, operating as a venture capital fund. Greater
involvement is possible on a project level.
3.3.7.3. HF and a greater number of UDFs
As in case of the above model, also here some initial interest in the investment UDF fund may be
noticed. In addition, there is a clear declaration of gminas to contribute capital to smaller sub-
regional UDFs. Self-government units and companies declare contribution in-kind (in form of real
estates) to UDFs. Also institutions engaged in regeneration of post-industrial areas (GAPP, CPR) are
interested in this operational form.
3.3.7.4. EBI and a possibility of other entities involvement
The EIB involvement improves the credibility of all actions, especially in the sphere of PPP. It may be
thus a strong argument for other entities to participate in the project.
C i t y C o n s u l t i n g I n s t i t u t e
Page 164
3.3.8. Institutional model and PPP
3.3.8.1. One UDF model
In the one UDF model, the role of this institution will consist mostly in financial support of a private
partner, in case the difference between commercial and preferential financing offered by the UDF
decides on project profitability. In practice, financing PPP in this model is improbable.
3.3.8.2. HF and 2 UDFs model
PPP is highly possible within this model. UDFs may contribute capital to ventures; they may be
originators of spatial development projects. In this model, the investment UDF can play the role of a
real estate development company.
3.3.8.3. HF and a greater number of UDFs
This model offers the possibility to separate a fund, which will be directed at real estate development
in particular gmina associations. This model increases the probability of engagement of gminas into
PPP and managing projects with great UDF support. The existence of a HF may reduce the costs of
project management thanks to common, transparent procedures for all UDFs.
3.3.8.4. EBI involvement and PPP
In recent years, despite of the new legal solutions, PPP has encountered several implementation
problems in Poland. It is large cities that are most interested in this form of cooperation. However,
these projects wait for years to be implemented and are often used in the political game.
Unfortunately, PPP is still the word synonymous to unclean business.
The main PPP failure reasons are:
Inability to understand partner’s needs (both private and public);
Inability to create proper business models;
Problems with finding a partner interested in the investment;
Wrong project assumptions, not reflected in the market needs.
Lack of single interpretation of laws jeopardizing the institution implementing PPP for legal
risks.
The PPP contracts are signed for long periods of time and sole project preparation and
implementation last for 5 and more years.
C i t y C o n s u l t i n g I n s t i t u t e
Page 165
Self-government entities intentionally avoid this risk, despite of obvious advantages resulting from
PPP or even impossibility to realize some ventures in a different formula.
The EIB role can be crucial in this case. It is the key issue not only for projects, but also for PPP
implementation throughout the whole region, also outside the JESSICA initiative.
EIB, which has already worked out some legal and business procedures is able to
implement projects in much shorter time;
by shortening the time necessary to receive some binding interpretation of EU
legislation, the EIB can accelerate project implementation even by 2 years (for two years
it was impossible to receive an opinion concerning PPP assets produced with the
Cohesion Fund support, whereas a similar interpretation was issued by the European
Commission in 14 days on request of a European institution);
EIB provides political security of self-government authorities. Engagement of a European
institution as the coordinator of a PPP project reinforces the credibility of the process.
Being experienced in financing PPP projects, the EIB may also facilitate the process of
finding private partners from EU countries.
3.4. Comparison and evaluation of different institutional models of
JESSICA implementation
The most probable organizational models have been chosen for the analysis: one UDF model, HF with
two UDFs (credit-guarantee and capital) and HF and more UDFs - opening the possibility to create
UDFs to gminas and their associations.
Table: Comparative analysis of chosen organizational models.
UDF HF + 2 UDF HF + >2 UDF
Time for absorption of funds +/- ++ (EBI)
+/-
++ (EBI)
+/-
Time for project implementation +/- + (EBI)
-
+ (EBI)
-
Flexibility and change opportunities -- + ++
Fitting financial tools to particular needs - + ++
Management costs + - -
C i t y C o n s u l t i n g I n s t i t u t e
Page 166
-- very unfavourable, - unfavourable, +/- neutral, + favourable, ++ very beneficial
Table: Comparative analysis of chosen organizational models – financial aspect.
Values UDF HF + 2 UDF HF + >2UDF
Capital transferred to UDF – total (mln PLN) 184,00 280,34 512,56
ROP SL 160,00 160,34 160,56
Shareholders – cities (in mln PLN) 24,00 24,00 64,00
Commercial banks 0 48,00 128,00
EIB 0 48,00 160,00
Capital transferred to UDF as % of ROP
contribution
13,04% 42,80% 68,67%
Shareholders – cities in % 13,04% 8,56% 12,49%
Commercial banks 0,00% 17,12% 24,97%
EIB 0,00% 17,12% 31,22%
Balance of UDF(-s) funds at the end of 2022
(last year)
186,90 307,91 559,96
Value of granted loans and credits in PLN 238,56 398,97 722,61
Direct costs of the MA - + +
Financial leverage -- +/- ++
Knowledge potential - ++ (EBI)
+/-
++ (EBI)
+/-
Investment diversification - + ++
Financial risk minimization - +/- +
Project impact on regeneration effectiveness +/- +/- +
Possibility to implement big integrated projects + ++ +/-
Possibility to implement PPP projects +/- + +
Possibility to implement low-budget elements
of integrated projects
+/- +/- ++
C i t y C o n s u l t i n g I n s t i t u t e
Page 167
Table: Analysis of advantages and disadvantages of chosen organizational models.
Model Description
UDF Disadvantages Advantages
High organizational costs for the MA Initially, lower costs of program
operation, assuming that there is no
technical support necessary (the UDF is
created by an entity having knowledge
on revolving instruments).
Little institutional flexibility Simple business and organizational
structure.
Small possibility of obtaining the
financial leverage effect (limited
interest of gminas and commercial
banks)
Clear and recurrent schemes of
operation.
One of many credit funds Allocating all resources to the loan fund
will result in the establishment of a
financial instrument that is well known
to self-government authorities.
Low educational value Little demand for highly educated staff.
HF + 2 UDF Disadvantages Advantages
Costs resulting from the HF operation (if
established by an institution other than
the EIB).
Low operational costs for the MA. No
necessity to employ competent staff
resulting from the HF managed by
another institution (e.g. EIB).
Difficult mechanisms in the investment
UDF.
Possibility to adapt financial tools to
projects.
Necessity of greater individualization of
procedures.
Possibility to obtain the financial
leverage effect.
Possibility to support gminas in terms of
content-related issues.
Possibility to find additional financial
institutions.
Low HF operational costs (only if the HF
C i t y C o n s u l t i n g I n s t i t u t e
Page 168
is established by the EIB, the operational
costs will be compensated by income
from interest on invested capital and
value of technical support).
HF + >2
UDFs
Disadvantages Advantages
Costs resulting from the HF operation (if
established by an institution other than
the EIB).
Low operational costs for the MA,
possible takeover of some costs by self-
government entities of lower level.
Possibility of strong institutional
fragmentation
Possibility to adapt financial tools to
projects and local conditions.
Considerable knowledge transfer.
Difficult mechanisms in the investment
UDFs
High possibility to obtain the financial
leverage effect.
Necessity of greater individualization of
procedures
Possibility to create a best practices
database and content-related support of
self-government entities.
High possibility to find additional
partners and financial sources.
The greatest flexibility of the model.
Possibility of great diversification of the
model.
Thanks to the variety of tools, it will be
possible to obtain the added value effect
in implementing Integrated Programmes
Low HF operational costs (only if the HF
is established by the EIB, the operational
costs will be compensated by income
from interest on invested capital and
value of technical support).
C i t y C o n s u l t i n g I n s t i t u t e
Page 169
3.4.1. Analysis of advantages and disadvantages resulting from entrusting the EIB
with the HF function
Entrusting the HF management to the European Investment Bank having the biggest
knowledge on the JESSICA mechanism would be the fastest possible option, as no
competition procedure would have to be organized. In this case, all funds could be
transferred directly after completing negotiations of the management contract between
the Marshal Office and the EIB.
EIB offers professional support for newly opened institutions and the MA. The value and
quality of technical support is in this case an added value that is not offered by other
entities (the cost of the EIB technical support is estimated as € 200 000 / quarter)9.
The solution enables faster disbursement of ROP SL funds.
As an EU institution, the EIB is able to obtain direct legal interpretations and explanations
from the European Commission, which can be crucial for new projects. The EIB may act
as a middleman between the Marshal Office, central administration and the European
Commission.
Educational actions of the EIB aimed at UDFs and other entities implementing projects
are based on unique experience.
EIB involvement in PPP ventures increases their credibility and assures positive social
perception. At the same time, it offers a possibility of significant economic
development of the region.
The solution introduces a strong partner in the area of finance management to the
region.
The solution facilitates JESSICA implementation, thanks to the possibility of using
procedures developed by the EIB and tested for many years of the bank’s operation.
It provides direct contact with the European Commission and other institutions
responsible for developing and interpreting law for the JESSICA initiative.
9 Assessed on the basis of average prices of consulting services provided by experts, in the scope
necessary for HF operation (legal and economical services, translations, negotiations, development of contracts).
C i t y C o n s u l t i n g I n s t i t u t e
Page 170
3.4.2. Recommendations for the Śląskie Voivodship
3.4.2.1. Recommendations concerning the Holding Fund establishment
In the light of the above analyses, the Consultant recommends the establishment of a HF for the
period 2009-2013 and offering HF tasks to the EIB.
The analysis reveals, that the choice of the simplified model (one UDF), in case of a region with
such complex urban functions, consisting of four not fully integrated regions, will not guarantee
reaching all the assumed effects. With the planned amount of money to spend (of approx. 40 € M),
with no financial leverage effect, operation based on one UDF only will not have a considerable
impact on the regeneration process and integrated development of urban areas. In practice, a Fund
with no leverage will be disfunctional and expensive, as it will require building competent structures
within the UDF and the MA. In case of delays of disbursement procedures (delays will occur due to
the necessity of the UDF to acquire the knowledge required to launch the financial mechanism),
the region may lose the chance for dynamic development of PPP, connected to new financial
possibilities.
Entrusting HF tasks to the EIB will enable specification of all legal interpretations concerning UDF
operation and benefiting from the bank’s know-how at the same time.
In case of choosing an institution other than the EIB, the Consultant recommends the establishment
of only one UDF in the initial phase, due to the significant acceleration of disimbursement of funds.
However, this choice will cause significant constrains for the JESSICA mechanism implementation.
CONCLUSIONS – separation of tasks between two different entities is the most effective solution
for regional development.
The Holding Fund will be responsible for:
implementation of the initiative;
preparation of self-government entities;
training sessions;
supervision of financial engineering;
development of procedures;
database of best practices.
The UDF should be responsible for:
choice of projects exerting the greatest impact on regional development and regeneration;
analysis of local needs;
C i t y C o n s u l t i n g I n s t i t u t e
Page 171
provision of support for the beneficiaries.
The UDF should be also responsible for the choice of projects to be implemented. The HF would
only choose projects with regard to their profitability.
As the German example shows, combining these two functions (as in case of the one UDF model)
results in concentration on financial instruments only. The influence of project implementation on
regional sustainable development is neglected. This model will result also in the lack of self-
government interest in this initiative and treating it only as yet another place to receive a loan.
Adopting this business model will affect implementation of small, not necessarily effective projects
and stop PPP.
In the Consultant’s opinion, despite of the revolving character of the instrument, the one UDF model
will not be more effective on this stage of experience than the current subsiding model. Moreover, it
will increase the number of risks connected to disbursement of funds. Therefore, the model of one
UDF managed by a financial institution should be dismissed on the basis of past experience and the
Consultant’s opinion.
Considering the current stage of institutional preparation and little time left to the end of the
2007-2013 perspective, in the Consultant’s opinion the only solution that may significantly
influence regional development is the model based on responsibility split between HD and UDF
institutions. In order to significantly reduce potential risks for the Marshal Office, the Consultant
recommends basing the HF on the EIB structure.
After 2013, further existence of the HF as well as potential takeover of HF functions by some local
entity should be reconsidered.
3.4.1.1. Recommendations concerning the number of UDFs
Taking into account the fact that Silesia is the most urbanized region in the country, and that it
already has institutions like the Upper Silesian Fund (experienced in managing crediting-guarantee
and investment activities for self-governments), the Consultant recommends the choice of the full
JESSICA model.
Initially, two UDFs should be created in accordance with the current EIB procedures, based on the
Upper Silesian Fund that is institutionally ready for this solution. Each fund should concentrate on
different financial engineering tools.
C i t y C o n s u l t i n g I n s t i t u t e
Page 172
In the initial phase, the actual interest of cities (or their associations) in the engagement of capital in
own UDFs has to be unambiguously identified. In case such an option is confirmed, one should
consider establishing additional UDFs. Due to the threat of organizational fragmentation, it would be
reasonable to reduce the number of city UDFs to 2-5. Investment UDFs should be preferred as they
may work out better capital payoff by concentrating on the implementation of Integrated
Programmes.
3.4.1.2. Recommendation concerning organisational changes in time.
After 2013 (or earlier, in case of any prerequisites for change), the following elements should be
analysed:
rationale of further HF operation;
possibility of transferring the HF role to a local institution;
possibility of particular UDFs operation, potential changes in their operation, including
mergers, ownership structural changes, privatization etc.
Full analysis should be obligatorily prepared after using all the resources provided for project support
in the programme. After this period, the following elements defined by the Marshal Office may
change: guidelines on priorities and eligibility of costs.
Table: Organizational model with the HF involvement.
MA
Śląskie Voivodeship
HF (EIB)
UDF
crediting
project
project
UDF
capital
project
project
UDF
crediting
project
project
UDF
capital
project
project
C i t y C o n s u l t i n g I n s t i t u t e
Page 173
Table: Recommendations for JESSICA
•Regional institutions are unpreparedfor independent implementation offinancial revolving instruments - thereis a need of both technical andcontent-related support.
•Takeover of HF funtions by a regionalinstituion will be possible not earlierthan in the third year of themechanism operation.
•The time neccessary for themechanism implementation and thespeed of disbursement of funds willbe crucial in terms of regionaldevelopment.
•A chance resulting from the effectivemechanism implementation is thedevelopment of PPP in the ŚląskieVoivodeship, which will lead tonumerous interesting investmentprojects.
Entrusting the HF establishment to
the EIB is the best solution,
considering the speed and
effectiveness of the mechanism implementation
as well as the best stimulus of
regional development.
•The greater number of UDFs will enablebetter response to local needs. Accordingto the assumptions from the initial stageof this JESSICA implementation study, theself-government involvement in UDFs willdepend on the number of Funds.
•There is a need to create crediting and investment UDFs resulting from the analysis of potential JESSICA projects. This solution will have the greatest impact on regional development.
•The number of UDFs will directly translate to the financial leverage effect. On the basis of the initial analysis it can be stated that the difference in the leverage between the 1 UDF and the HF + >2 UDFs options will be at least 484 million PLN. Having this in mind, there is no rational justification for the 1 UDF model.
Greater number of UDFs and their
differentation will lead to an
increase of financial
engagement of gminas and other
entities (including
commercial banks)
C i t y C o n s u l t i n g I n s t i t u t e
Page 174
4. JESSICA implementation strategy in Silesia
4.1. Recommendations on how JESSICA should be taken forward in Silesia
in short-, medium- and long-term perspective
•Appointing the EIB as the institution within which theHolding Fund will be established [thanks to this solution itwill be possible to transfer the resources fast, avoidlenghty public procurement procedures and assurecorrect JESSICA implementation].
•Start of promotional actions, aimed at disseminatingknowledge on the mechanism as well as on PPP.
•Arising interest of regional institutions and self-governemnt entities in participation in UDFs (with capitalor substance).
short-term perspective
•Analysis of the system operation, adopting proceduresaiming at optimization of the number of UDFs andhanding the HF to a regional institution.
•Assessment of the engagement of potential beneficiariesin JESSICA.
mid-term perspective
•Actions aimed at increasing the financial leverage within particular UDFs.
•Increasing the number of UDFs with regard to geographical and sectoral division.
long-term perspective
C i t y C o n s u l t i n g I n s t i t u t e
Page 175
4.2. JESSICA implementation methodology
The mechanism implementation methodology comprises actions whose timetable has been
presented in chapter 4.3.
Actions concerning decision making processes in the Managing Authority, the HF and UDFs will be
crucial for the mechanism implementation.
Table: Main problems that may be encountered throughout JESSICA implementation
Problem area Scope of remedial actions
Substantive knowledge of the
institutions that may be
responsible for the
mechanism implementation
Presently, there is no regional financial institution that
would have substantial knowledge and experience in
management and implementation of revolving
mechanisms; due to the fact, cooperation with the EIB
seems the best solution as far as establishment of the
HF and UDFs is concerned.
There is a need to obtain technical support offered by
the EIB in order to optimise the mechanism
implementation and speed up the disimbursement
procedures.
Promotion and dissemination
of knowledge on JESSICA
The mechanism is very little known and requires
promotion. Information and promotional campaigns
should be organised as soon as possible.
Information and promotional actions should be aimed
both at potential beneficiaries and at potential UDF
participants. The JESSICA added value is the possibility
of a very high level of financial leverage.
Technical and factual
knowledge of potential
beneficiaries
Potential beneficiaries are very well prepared as far as
technical plans are concerned. This means that in case
of fast mechanism implementation, it will be possible
to spend the resources fast and achieve first results
and effects.
Beneficiaries are unprepared as far as the
conceptual/substantive sphere is concerned. There are
no Integrated Urban Development Plans, there is little
C i t y C o n s u l t i n g I n s t i t u t e
Page 176
knowledge on PPP as there are no PPP Implementation
Plans that would enable fair evaluation of transparency
and complexity of the procedures applied. A system of
trainings should be organised in order to disseminate
knowledge on the JESSICA initiative as well as on PPP,
IUDP, etc.
4.3. Indicative timeline of the new structure implementation
The scheme below presents an indicative timetable of the mechanism implementation.
IV quarter of 2009 - contract with the EIB to establish and manage a HF
I quarter of 2010 - transfer of resources to the HF /EIB
II quarter of 2010 - selection of UDF
III quarter of 2010 - transfer of resources to UDFs, development of project selection and implementation procedures
IV quarter of 2010 - development of projects
I - II quarter of 2011 - selection of projects to be supported
JESSICA implementation
C i t y C o n s u l t i n g I n s t i t u t e
Page 177
4.4. Potential risks for the Managing Authority
4.4.1. Managing Authority’s financial obligations resulting from RPO SL
Risk Probability Recommendations
Failure to meet eligibility
criteria defined by the
ROP SL
Little Instructions on project implementation and
disimbursement procedures should be developed
on the basis of the presently binding eligibility
criteria.
Cost eligibility criteria have been defined in the
Council Regulation (EC) No 1083/2006 of 11 July
2006 laying down general provisions on the
European Regional Development Fund, the
European Social Fund and the Cohesion Fund and
repealing Regulation (EC) No 1260/1999,
Regulation (EC) No 1080/2006 of the European
Parliament and of the Council of 5 July 2006 on the
European Regional Development Fund and
repealing Regulation (EC) No 1783/1999,
Commission Regulation (EC) No 1828/2006 of 8
December 2006 setting out rules for the
implementation of Council Regulation (EC) No
1083/2006 laying down general provisions on the
European Regional Development Fund, the
European Social Fund and the Cohesion Fund as
well as Regulation (EC) No 1080/2006 of the
European Parliament and of the Council on the
European Regional Development Fund, national
eligibility quidelines for structural funds and the
Cohesion Fund in the programming period 2007-
2013 issued by the Minister of Regional
Developement on 30 July 2007.
The scope of eligible expenses has been defined in
detail by the MA of ROP SL in the Eligibility
C i t y C o n s u l t i n g I n s t i t u t e
Page 178
Guidelines within the Śląskie Regional Operational
Programme for the years 2007 – 2013.
Lack of control systems Medium Development of guidelines and exemplary
contracts with UDFs concerning disbursement of
ROP resources, including guidelines on settlement
and monitoring procedures.
Introduction of a control system of the MA over
the UDFs.
Maintenance of the n+2
rule
Medium Development of guidelines obliging beneficiaries to
implement projects in accordance with the n+2
principle.
Irregularities in the use of
resources
Little Development of guidelines based on the presently
binding Guidelines on the procedures applied in
case of irregularities in the use of resources
granted from the structural funds or the Cohesion
Fund in the programming period 2007-2013.
Failure to apply the public
procurement law
Little Introduction of declarations binding the
beneficiaries to apply the public procurement law.
A beneficiary pledges to apply the law of 29
January 2004 Public Procurement Law (Official
Gazzette 2007 No 223, item 1655 as amended). In
case of beneficiaries operating out of the public
finance sector that are not bound to apply the
Public Procurement Law, a declaration is required
to apply the Guidelines of the Managing Authority
of the ROP SL on awarding contracts in case of
projects co-financed from ROP SL resources.
No disbursement of
resources until 2015 (in
case of the option with 1
UDF or the HF established
by an entity other than
the EIB)
Very high The risk of delays resulting from the lack of
administrative procedures and competence of both
the institutions that might possibly establish the HF
and UDFs and the beneficiaries. Due to the fact
that the time needed to implement regeneration
projects is very long, there is a great risk that they
will not be completed before the year 2015. The
C i t y C o n s u l t i n g I n s t i t u t e
Page 179
risk is especially high in case of establishing only
one UDF, not based on the EIB structures. Basing
on the German experience one may state, that
although our neighbours had begun their actions
earlier, they did not manage to spend their
resources, as they based their structures on
completely unprepared financial institutions.
Delays will result from the necessity of developing
structures ready to implement the initiative. The
German experience proves that choosing the
option of 1 UDF paralyses disbursement
procedures within JESSICA.
Basing on British, Lithuanian as well as Polish
experience one may state that initially (in 3 – 5
years perspective) it is absolutely necessary to
engage the EIB in the process of establishing the
HF and applying for technical assistance in efficient
JESSICA implementation. Additional advantage of
this solution is minimised responsibility of the
regional self-government for timely disbursement
of all the resources.
4.4.2. State aid and project sustainability issues
Risk area Risk description
State aid The opinion on state aid issues has been issued by the Ministry of Regional
Development10
Referring to present legal conditions one should state that the notion of state aid
has not been defined in detail in European Union documents. However, on the
basis of Article 87 paragraph 1 of the Treaty establishing the European Community
one may conclude that state aid is the support granted to a company in case the
following conditions are fulfilled at the same time:
the aid is granted by the state and comes from public resources,
10http://www.mrr.gov.pl/fundusze/pomoc_publiczna/czym_jest_pomoc_publiczna/strony/pomocpubliczna.aspx
C i t y C o n s u l t i n g I n s t i t u t e
Page 180
the aid is granted on more favourable conditions than the market ones,
the character of the aid is selective (it gives preference to a particular
company or companies or production of certain goods),
it may restrict or restricts competition and has impact on trade exchange
between EU Member States.
In order for support not to be considered state aid, the above conditions have to
appear simultaneously. In case any of the above conditions does not appear, the
support cannot be considered state aid.
The body responsible for issuing opinions on aid projects, notifying them to the
European Commission, respresenting the Polish government in disputes with the
Commission or European courts as well as monitoring state aid granted to Polish
institutions is The President of the Office of Competition and Consumer Protection
(OCCP). It is also the President’s competence to answer questions concerning
interpretation of the state aid law asked by entities granting the aid and potential
beneficiaries.
As JESSICA will function within structural funds (public resources), the issue of state
aid should be considered. The key question in this respect is whether on particular
stages of JESSICA implementation and operation certain entities will be preferred
over the others. Such preference would have impact on EU trade and result in
competition restrictions. The issue will primarily concern the relations between the
Managing Authority and the HF or UDF(-s) as well as between the HF and the UDF(-
s), setting the HF and UDF remuneration, UDF support granted to particular
projects or public entities investing in the UDF or the HF, managing private
resources. In case the support granted within JESSICA was considered state aid, its
beneficiary would be obliged to return it. It should be stressed that not all support
granted within JESSICA will be automatically considered state aid. If all the
entities engaged operate in accordance with market principles and if JESSICA
resources are also transferred according to market principles, there will be no
risk of prohibited state aid.
Project
sustainability
One of the main areas of regeneration activities in Silesia is development of post-
industrial and degraded areas and revival of their economic functions. In spite of
great effectiveness of these actions, their implementation in Silesia may be
C i t y C o n s u l t i n g I n s t i t u t e
Page 181
threatened by the fact that interpretation of project sustainability in such cases
remains unclear. These areas should be purchased by entrepreneurs willing to
start-up their business. However, due to sustainability issues, they may only be
leased. This fact has adverse impact on the interest of potential investors.
Minimising this risk is only possible in two cases:
positive opinion of the European Commission on the possibility of selling
the grounds. The key role may be played by the EIB, which may request the
European Commission to present a clear interpretation of this legal
problem in case of the JESSICA initiative.
change of law by the governement, introduction of urban development law
and procurement of the agreement of the European Commission to treat
this instrument on a par with lease.
4.5. Recommendations
In order to plan disimbursement of JESSICA resources properly and use them effectively, it should be
necessary for potential Beneficiaries to prepare the following documents:
Document Scope
Simple
application
form
Simplified application form should be a document whose aim is to present
general, concise information on a particular project. The application form should
include results of detailed analyses conducted and presented in the project
feasibility study, profitability analysis, etc.
Feasibility study
Project feasibility study is a document whose main aim is to prove the rationale of
a particular project and to state whether it is technically, strategically, financially
and economically feasible. A feasibility study should among others include the
following analyses: social and economic analysis, spatial analysys, project
background, economic, social, legal and environmental aspects of the project
implementation, intervention logic (aims, products, results), technical analysis,
environmental analysis, financial, economic, sensitivity and risk analyses. Product
effectiveness is primarily measured by indicators such as rate of return,
profitability ratios, PI, NPV, IRR, DGC.
Integrated
Urban
Integrated Urban Development Plan is developed, adopted and coordinated by a
C i t y C o n s u l t i n g I n s t i t u t e
Page 182
Development
Plan
local government as a long-term programme of actions in the sphere of public
space, utilities, society and economy. The aim of the document should be
sustainable development of a particular area or managing it out of crisis and
creating conditions for future development.
The plan should comprise: spatial, social and economic analyses of a city/town,
identification of problems and barriers of development, assumptions, objectives
and timetable of the plan, definition of projects to be undertaken, expected
indicators, implementation and monitoring system, environment impact analysis.
The plan should also include an analysis of planned spatial, social and economic
effects of each project.
Local
Revitalization
Programme
Projects included in the integrated plan have to result from the Local
Revitalization Programme – a planning document adopted by a
City/Town/Commune Council and defining degraded areas to be regenerated.
Multi-annual
Financial Plan
It is recommended for potential JESSICA projects to result directly also from Multi-
annual Financial Plans, developed by particular self-government entities.
A Multi-annual Financial Plan is a tool of rational management of public resources,
taking into account the following: macroeconomic ratios (GDP, average annual
inflation), forecast of interest rates (WIBOR 1M, WIBOR 3M, interest rate s of
commercial credits), forecast of income and expenditure, debt level and
anticipated income and expenditure in the following years.
A Multi-annual Financial Plan defines in detail:
level of possible budget income,
rational level of current expenditures ensuring implementation of all
statutory tasks,
gross available funds (operating surplus) to finance debt service and
planned investment,
net available funds that is the so called financial potential of a self-
government entity (resources to finance investment projects),
setting the maximum debt level of a self-government entity without
losing financial liquidity,
possibility of receiving an EU grant (provision of own contribution),
A Multi-annual Financial Plan facilitates rational implementation of projects
included in strategic documents of a particular self-government entity, defining
C i t y C o n s u l t i n g I n s t i t u t e
Page 183
the sources of their financing in subsequent years at the same time providing
resources to finance the statutory tasks of a beneficiary. A Multi-annual Financial
Plan defines the level of resources that may be spent on investment and non-
ivestment projects (what distinguishes it from the Multi-annual Investment Plan)
without affecting the financial safety of the investor (debt and debt service ratios).
In case of projects implemented within PPP, the following additional documents will be required:
Project
profitability
analysis
The aim of a project profitability analysis is to prove whether a particular project
implemented within PPP is effective. The analysis takes into account all expenses
that have to be borne and all income that may be drawn in result of a project,
taking into account alternative investment variants. This information is very
important for potential investors or institutions interested in co-financing the
project.
Project profitability analysis should comprise the following: project description,
forecast of investment outlays, concise social, economic and spatial analyses of
the project background, macroeconomic analysis (economic trends, law,
concessions, interest rates, exchange rates), financial analysis, including forecast
of potential income, structure of costs, cost volatility, decision making accounting
of costs and results, sunk, alternative and calculating costs as well as their impact
on project profitability, forecast of working capital, analysis of financial reports,
analysis of alternative project variants and potential financing sources, economic
analysis- cost benefit analysis, sensitivity analysis, including variance to budget,
risk analysis.
Product effectiveness is primarily measured by indicators such as rate of return,
profitability ratios, PI, NPV, IRR, DGC. These ratios are verified with regard to
requirements of different entities and institutions potentially interested in co-
financing a particular project.
Analysis of
investment
variants
Analysis of investment variants is directly connected with project profitability
analysis. The aim of the analysis is to choose the optimum solution from among
several possible options. In order to conduct the analysis, a number of financial
and economic ratios are examined.
PPP
Implementation
In case of self-government entities, one of the key documents, offering the
possibility of analysing the perspectives of PPP development (cooperation
C i t y C o n s u l t i n g I n s t i t u t e
Page 184
Plan conditions, areas, participation possibilities) is a PPP Implementation Plan.
Development of such a document may be beneficial both for potential investors
and for project success.
Principles defined in the PPP Implementation Plan will considerably shorten the
time needed to prepare PPP agreements what will in turn accelerate the process
of investment implementation.