+ All Categories

jhpl

Date post: 29-May-2018
Category:
Upload: chauhanbrothers3423
View: 226 times
Download: 0 times
Share this document with a friend

of 80

Transcript
  • 8/9/2019 jhpl

    1/80

    2010

    Jagdishpur-Haldia Pipeline:Demand Estimation & TariffDeterminationGAIL (INDIA) Limited

    Ankit SethiUniversity of Petroleum and Energy Studies, Dehradun

    2010

  • 8/9/2019 jhpl

    2/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    2 | P a g

    Project Report Approval Sheet

    This is to certify that the project mentioned below, has been completed by Mr.

    Ankit Sethi under my guidance during the period w.e.f 1stJune 2010 to 31

    stJuly

    2010.

    1. Jagdishpur-Haldia Pipeline: Demand estimation & Tariff Determination

    2. Proposal for Bhatinda-Srinagar Pipeline

    He has submitted this project report towards partial fulfillment of curriculum ofMasters Degree of

    Business Administration in Oil and Gas, University of Petroleum and Energy Studies,Dehradun.

    To my best knowledge, the matter presented in the project has not been

    submitted anywhere else. The same is hereby approved.

    Rajesh Bagaria

    Senior Manager

    Gas Authority of India Limited (GAIL), Delhi

  • 8/9/2019 jhpl

    3/80

    3 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    Acknowledgement

    It gives me immense pleasure to be attached with Gas Authority of India Limited

    (GAIL), Delhi which has provided me a very unmatched training in my summer

    internship. I place special thanks to the Deputy General Manager Mr. G. S.

    Chouhan for his continuous support.

    I gratefully acknowledge my profound indebtedness towards my esteemed mentor

    Mr. Rajesh Bagaria Senior Manager, GAIL (India) Ltd for his valuable

    guidance, excellent supervision and constant encouragement during the entirecourse of work, without which the present work would have not been possible.

    A special thanks to Mr. Vivek. R. S. Neelam Senior Officer (pricing) and Mr.

    V. K. Duggal, Deputy General Manager ,Business Development BPCL

    Delhi for extending their support in the successful completion of my project.

    I also express sincere gratitude to the faculties, UPES Dehradun for providing

    pivotal study material. Last but not least, I would also like to thank the entire

    team of GAIL, for their constant support.

    .

    Thanking you

    Ankit Sethi

    University of Petroleum & Energy Studies

    Date: Dehradun, Uttrakhand

  • 8/9/2019 jhpl

    4/80

    4 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    CONTENTS

    Glossary of Terms . . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . . . . . . . . . . 6Executive Summary . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . . . . . . . . . . 7

    1. Overview of Indian Economy . . . . . . . . . . .. . . . . . . . . .9

    1. 1. Demand-Supply Outlook . . . .. . . . . . . . .10

    1. 2. Company Profile . . . . . . . . . . .. . . . . . . . 12

    2. Prioritization of Natural Gas . . . . . . . . . . . .

    . . . . . . . . . . .143. The Proposal . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . 17

    3. 1. Jagdishpur-Haldia Pipeline . .. . . . . . . . 17

    4. Jagdishpur-Haldia Pipeline. . . . . . . . . . . . . .. . . . . . . . . . .18

    4. 1. Basic Parameter. . . . . . . . . . .. . . . . . . . . 19

    4. 2. Gas Supply Scenario . . . . . . . .. . . . . . . . 20

    4.3. Project Schedule & CostEstimate . . . . . 22

    5. Gas Throughput for Transmission Tariffs-JHPL. . . . . . . . 23

    5. 1. Optimal Pipe Size . . . . . . . . . .. . . . . . . . 23

    5. 2. Proposed Pipeline System . . .. . . . . . . . 25

    6. Project Cost. . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . 28

    7. Project Financials . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . 34

    7. 1. Total Revenue. . . . . . . . . . . . .. . . . . . . .34

    7.2. Capital Expenditure . . . . . . . . .. . . . . . . . 34

    7. 3. Operating Expenditure . . . . .. . . . . . . . . 35

    7. 4. Methodology for Tariffcalculation . . . 36

  • 8/9/2019 jhpl

    5/80

    5 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    7. 5. Transportation Tariff. . . . . . .. . . . . . . . 37

    8. Means of Finance. . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . .40

    9. Basic Assumption. . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . .42

    10. Project Profitability. . . . . . . . . . . . . . . . . . .

    . . . . . . . . . . . 4411. SWOT Analysis. . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . . . . . . 51

    12. Risk Analysis & Mitigation Strategies. . . . . .. . . . . . . . . . 52

    13. Sensitivity Analysis. . . . . . . . . . . . . . . . . . .. . . . . . . . . . . 53

    14. Conclusion and Recommendations. . . . . . . .. . . . . . . . . 54

    ANNEXURE-1: Envisaged MarketANNEXURE-2: Capacity Build Upin Phases

  • 8/9/2019 jhpl

    6/80

    6 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    Facts &Figures

    Table 1: Gas Scenario: Present & Future

    Table 2: Demand

    Outlook Table 3: Gas Supply

    sources Table 4: Demand supply

    gap Table 5: Basic

    Parameters Table 6: Gas Supply

    Scenario

    Table 7: Projected demand year wise

    Table 8: Project Schedule and CostEstimate

    Table 9: Proposed Pipeline System

    Table 10: Capital Outflow

    Table 11: Total Revenues

    Table 12: Transportation

    TariffTable 13: Means of

    Finance Table 14: Free cash Flow

    Table 15: Basic

    Assumptions Table 16: Profitability

    Analysis Table 17: Sensitivity

    Analysis

    Figure 1: Prioritization of Natural Gas

    Figure 2: JHPL Map

    Figure 3: Profit after Tax

  • 8/9/2019 jhpl

    7/80

    6 | P a g

    JAGDISHPUR-HALDIA PIPELINE: DEMAND ESTIMATION & TARIFF DETERMINATION 2010Glossary ofTerms

    Abbreviation Full Form

    CGD City Gas Distribution

    CNG Compressed Natural Gas

    CGS City Gas Station

    CV Calorific Value

    Capex Capital Expenditure

    DSCR Debt-Service Coverage Ratio

    EBIT Earnings Before Income and Tax

    FCI Fertilizer Corporation of India

    HOA Heads of Agreement

    HSD High Speed Diesel

    IDC Interest During Construction

    IRR Internal Rate of Return

    JHPL Jagdishpur-Haldia Pipeline

    LPG Liquefied Petroleum Gas

    LNG Liquefied Natural Gas

    MS Motor Spirit

    MTPA Metric Tons Per Annum

    MMTPA Million Metric Tons Per Annum

    MMSCMD Million Metric Standard Cubic Meters Per

    MoP&NG Ministry of Petroleum and Natural Gas

    MMBtu Million British Thermal Unit

    Opex Operating Expenditure

    PAT Profit After Tax

    PBT Profit Before Tax

    P&L Acc. Profit and Loss Account

    PNGRB Petroleum and Natural Gas Regulatory

    ROW Right of Way

    SAIL Steel Authority of India Limited

    WBPDC West Bengal Power Development

  • 8/9/2019 jhpl

    8/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    Source Available Gas Volume(MMS

    CMD2011-2012 2012-2013 2013-2014 2014-2015 2015-2016

    KG Basin 5.1 7.1 7.8 8.6 9.0Mahanadi 0 5 10 20 20Gas

    7 | P a g

    Jagdishpur-Haldia Pipeline

    GAIL (India) Limited, is India's flagship Natural Gas

    company, integrating all aspects of the Natural Gas value

    chain (including Exploration & Production, Processing,

    Transmission, Distribution and Marketing) and its relatedservices.

    Jagdishpur-Haldia pipeline (JHPL) project has been

    conceptualized to cater to the gas demand of consumers in

    the states of eastern Uttar Pradesh, Bihar, Jharkhand and

    West Bengal. The gas source for the pipeline has been

    considered KG Basin and ONGC Mahanadi Gas. This pipeline

    shall carry gas from ONGC Mahanadi and KG Basin through

    Reliances Kakinada- Basudevpur-Howrah pipeline. The

    pipeline will start from Haldia and terminate at Phulpur.

    Gas Supply Scenario

    Gas source envisaged & projected available gas volume on the Jagdishpur-

    Haldia pipeline system is given below:

    Executive Summary

    Total 5.1 12.1 17.8 28.6 29

    Projected gas demand year wise by Marketing is tabulated below:

    HoA Gas InMMSCMD

    2012-2013 2013- 2014- 2015- 2016- 2017-2018Total 8.15 15.78 18.18 20.58 22.99 24.00

    Pipeline system has been designed for meeting the gas demand in

    various sectors. Details are given below:

    a) Fertilizers (HFC Durgapur, FCI Sindri, HFC Barauni,

    FCI Gorakhpur & DIL Kanpur)

    b) Power (CESC Haldia, DPL Durgapur, WBPDC Bandel, WBPDC Katwa,WBPDC Sagardighi & Barh Power Plant)

    c) Industries (SAIL Durgapur, SAIL Bokaro & Petrochemical Plant

    Barauni).

    d) City Gas (Kolkata, Jamshedpur, Ranchi, Patna,

    Chapra, Siwan, Gopalganj, Betiah Varanasi &

    Allahabad).

  • 8/9/2019 jhpl

    9/80

    8 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    Gas Source for Jagdishpur-Haldia Pipeline would be available

    from KG Basin by Reliance, Mahanadi Basin by ONGC and KG

    Basin by Gujarat state

    Petroleum Corporation.

    As per the authorization, the capacity of this pipeline is 16

    MMSCMD (which is inclusive of 4 MMSCMD for common

    carrier), however based on

    prevailing gas demand and gas availability scenario, the

    design capacity for JHPL in first phase will be 16 MMSCMD

    which will be augmented in second phase from 16 to 32

    MMSCMD.

    As per the technical team the diameter of the pipeline isrecommended at

    36 for thisproject.

    ExecutiveSummary

  • 8/9/2019 jhpl

    10/80

    1. Overview of IndianEconomy

    Most agencies have projected Indias demand of natural gas to grow at a rate

    higher than other fuels such as oil and coal. The future demand for natural

    gas in India will be driven mainly by two factors:

    The need for new sources of energy to fuel economic growth

    and improve living conditions; and

    The desire to reduce the consumption of coal and liquid fuels and

    thus the level of pollution.

    These drivers are, however, subject to a number of constraints indetermining the actual

    level of gas demand: the price of gas and its competitiveness vis--vis

    other fuels and the rate at which the downstream market is

    developed in both power and non-power sectors.

    Many uncertainties will affect the future gas demand level, particularlywith respect to

    the cost of supply and Indias ability to create an integrated national

    transportation and distribution network. Competitiveness of natural gas

    against coal in power generation will also be a key determinant of gas-

    demand growth.

    Indias demand projections have been made at different points in time

    using different

    assumptions and for different periods. Summarizes the projections

    made by different agencies for the same milestone years over

    respective forecast period by adopting the process of interpolation andextrapolation.

    Gas Scenario: Present & Future

    ( i n b i ll i on s o f c ub i c f e e t)

    3000

    2500

    2000

    1500

    1000

    500

    0

    2010

    2030Source: Infraline.Com

    Domestic Production

    Net Imports

  • 8/9/2019 jhpl

    11/80

    2009-10

    2010-11

    2011-12

    ONGC + OIL (A) 55.69 54.67 51.08

    Pvt./ JVs (As Per DGH) (B) 60.28 58.42 57.22

    Projected Domestic Supply 115.97 113.09 108.30

    Additional Gas Anticipated 74 84 94

    Total Projected SupplyScenario 1 (A+B)

    115.97 113.09 108.30

    1. 1. Demand Outlook

    Sector 2009-2010 2010-2011 2011-2012

    Power 100 11 12Fertilizer 52 79 79

    City gas 14 15 16Industrial 17 18 20Petrochemicals/ refineries/ others/internal

    29 31 33

    Sponge iron/ steel 7 7 8Total 219 26 28

    1. 1. 1. Gas Supply Sources

    Sources

    Total Projected SupplyScenario 2 (A+B+C)

    189.97 197.09 202.30

    The estimated gap between domestic gas production and supply is mainly on

    account of internal use by the producers themselves, technical flaring and gas

    shrinkages.

    Looking at the overall demand projections and even the most optimistic scenario of

    expected domestic supplies, it is very clear that there would be a supply

    shortfall. Therefore, there is a need to step up imports in the coming 5 years.

    There is already an import of LNG to the tune of 18 MMSCMD by PLL at Dahej. Thisis being supported by the commencement of LNG supply from the Hazira Terminal

    of Shell which is, however, yet to stabilize. To augment the shortfall, the country

    is already pursuing imports, both through the LNG route and the transnational

    pipeline route.

    Source:Infrraline.com

  • 8/9/2019 jhpl

    12/80

    09-10 10-11 11-12

    Dahej 7.5 10.00 10.00

    Hazira 2.50 2.50 2.50

    Dabhol 5.00 5.00 5.00

    Kochi - 2.50 5.00

    Mangalore - - 1.25

    Total LNG Supply (MMTPA) 15.00 20.00 23.75

    09-10 10-11 11-12

    Projected DomesticSupply (ONGC

    115.97 113.09 108.30

    Additional anticipated 74 84 94

    LNG (C) 52.50 70.00 83.12

    LNG/Supplies through Transnational Pipelines

    LNG Supply Source

    Total LNG Supply (MMSCMD) 52.50 70.00 83.12

    1. 1. 2. Demand Supply Gap for Natural Gas

    Gap would increase steadily to 91.13 MMSCMD by 2011-12 in Scenario

    I, whereas under Scenario II, the gap would by and large be bridged from

    2009-10 onwards and there is expected to be a demandsupply balance

    during the last 3 years of the XI Plan period. The overall demandsupply

    balance is presented below:

    Supply

    Total Supply (A+C) 168.47 183.09 191.42

    Total Supply (A+B+C) 242.47 267.09 285.42

    Demand (MMSCMD) 225.52 262.07 279.43

    Demand Supply Gap I 57.05 78.97 88.03

    Demand Supply Gap II -16.95 -5.03 -5.97

    Source: Infraline.com

  • 8/9/2019 jhpl

    13/80

    1. 2. Company Profile

    GAIL (India) Limited, is India's flagship Natural Gas company, integrating allaspects of the Natural Gas value chain (including Exploration & Production,Processing, Transmission, Distribution and Marketing) and its related services. In arapidly changing scenario, we are spearheading the move to a new era of clean

    fuel industrialization, creating a quadrilateral of green energy corridors thatconnect major consumption centers in India with major gas fields, LNG terminalsand other cross border gas sourcing points. GAIL is also expanding its business tobecome a player in the International Market.

    Incorporated 16th

    August ,1984

    Turnover (2009-10) Rs. 24,996 Crore

    Net Profit (2009-10) Rs. 3,140 Crore

    Employees 3,480

    Market Shares 78% Market Share in Natural Gas Transmission70% Market share in Natural Gas Marketing

    Today, GAIL's Business Portfolio includes:

    7,700 km of Natural Gas high pressure trunk pipeline with a capacity tocarry 157 MMSCMD of natural gas across the country7 LPG Gas Processing Units to produce 1.2 MMTPA of LPG and other liquidhydrocarbonsNorth India's only gas based integrated Petrochemical complex at Patawith a capacity of producing 4,10,000 TPA of Polymers

    1,922 km of LPG Transmission pipeline network with a capacity to transport 3.8MMTPA of LPG27 oil and gas Exploration blocks and 3 Coal Bed Methane Blocks13,000 km of OFC network offering highly dependable bandwidth for telecomservice providers Joint venture companies in Delhi, Mumbai, Hyderabad,Kanpur, Agra, Lucknow, Bhopal, Agartala and Pune, for supplying PipedNatural Gas (PNG) to households and commercial users, and CompressedNatural Gas (CNG) to the transport sectorParticipating stake in the Dahej LNG Terminal and the upcoming Kochi LNGTerminal in Kerala GAIL has been entrusted with the responsibility of revivingthe LNG terminal at Dabhol as well as sourcing LNG GAIL Gas Limited, a wholly owned subsidiary of GAIL (India) Limited, was

    incorporated on May27, 2008 for the smooth implementation of City Gas Distribution (CGD)projects. GAIL GasLimited is a limited company under the Companies Act, 1956.

    Established presence in the CNG and City Gas sectors in Egypt throughequity participation in three Egyptian companies: Fayum Gas Company SAE,Shell CNG SAE and National Gas Company SAE.

    Stake in China Gas Holding to explore opportunities in the CNG sector inmainland China

  • 8/9/2019 jhpl

    14/80

    Leaders in Gas

    Since inception, GAIL has been the undisputed leader in the marketing,transmission and distribution of Natural Gas in India. As India's leadingNatural Gas Major, it has been instrumental in the development of theNatural Gas market in the country. Today, Natural Gas accounts for about8% of the total primary commercial energy consumption in India.Consumption has grown significantly during the past two decades. In fact,in the 1990s, thedemand for Natural Gas far outstripped its domestic production, leading togas import initiatives and the subsequent development of LNG importprojects at suitable coastal locations inWestern and Southern India.

    Currently, GAIL sells over 70% (excluding internal usage) of Natural Gas in thecountry. Of this,

    41% is to the power sector and 30% to the fertilizer sector.* Totally, theysupply 60 MMSCMD of Natural Gas from domestic sources to customersacross India basis long-term Gas Sales Agreements. These customers rangefrom the smallest of companies to mega power and fertilizer plants. Theyhave adopted a Gas Management System to handle multiple sources ofsupply and delivery of gas in a co-mingled form and provide a seamlessinterface between shippers, customers, transporters and suppliers. They arepresent in 11 states, i.e., Gujarat, Rajasthan, Madhya Pradesh, Delhi,Haryana, Uttar Pradesh, Maharashtra, Tamil Nadu, Andhra Pradesh, Assam,and Tripura.

    Actively pursuing opportunities in inter-regional gas trade both in the form ofPipeline gas and

    LNG.

  • 8/9/2019 jhpl

    15/80

    2. PRIORITIZATION OF

    NATURAL GAS FERTILIZER

    Food security as urea consist of 60% of fertilizer inputs and India must

    improve the yield per acre as there is no further scope left forincreasing the crop acreage . Natural gas is considerably cheaper than

    naphtha and domestic gas should be first used in existing fertilizer

    units, thereafter feed the requirement of expansion and new capacity addition.

    400

    200

    0

    Projected Gas Demand for FertilizerSector

    2007-08 2008-09 2009-10 2010-11 2011-12

    Urea Production Capacity (Lakh tones) Gas Demand (MMSCMD)

    POWER

    Most versatile form of energy: best in terms of application, pollution free

    and impact the population at large. Power for all goals is to be achievedand so in the additional power requirement to be created to sustain GDP

    growth. Domestic coal, although available is large reserves, but cannot

    meet this goal due to low calorific value, ash disposal, environmental

    infrastructural constraints, land requirement etc. Imported coal is

    constrained by limited port infrastructure and limitations of the existing

    cross country transportation by rail (road is not feasible) .Nuclear power

    has long gestation and fuel linkage issue. Hydel again has serious

    environment, silting, social cost, seismic and long gestation period issue.

    150

    Gas Demand Projections inpower sector(MMSCM

    D)

    100

    50 Gas Demand

  • 8/9/2019 jhpl

    16/80

    0

    2007-08 2008-09 2009-10 2010-11 2011-12

  • 8/9/2019 jhpl

    17/80

    Renewable do hold the promise but is not economic and base load power

    requirement can hardly be met. Petroleum products (FO & Naphtha) can be

    an important source for generating power, yet the economic and high crude

    oil prices volatilities adversely affected the power economic. So, domestic

    natural gas should next best be used for creating of CCGT plant to meet the

    additional power requirements. Further, the CCGT economic compares mostfavorable

    options with power generation based on other fossil fuels.

    INDUSTRIES

    Purely on economic consideration, next best use of domestic gas is in

    industries refineries, steel plant petrochemical units, small medium

    enterprises etc as the alternative fuel ( FO , HSD , LDO & LSHS ) are

    expensive and are not environmentally friendly . Further, coal meeting the

    fuel

    requirement of steel plant has serious environmental issues.

    Gas Demand inPetrochemicals/Refineries and InternalConsumption

    GasDemand

    23.71 25.37 27.14 29.0431.07

    33.25

    2006-07 2007-08 2008-09 2009-20102010-11 2011-12

    Gas Demand in sponge iron/steel sector

    GasDemand

  • 8/9/2019 jhpl

    18/80

    6 6.426.87

    7.35

    7.86

    2007-08 2008-09 2009-10 2010-11 2011-12

  • 8/9/2019 jhpl

    19/80

    CITY GAS DISTRIBUTION (CGD)

    Surplus domestic gas , if any could be used in CGD network for meeting

    small industrial / commercial fuel requirements and if possible , replace LPGby piped natural gas ( LPG should go rural ). CNG may be environmentally

    friendly , the solution for replacement of transportation fuels ( MS / HSD )

    should hardly be by CNG- certainly not as economical as perceived to be as

    the indirect costs in terms of conversion have to be factored in andcomparison should not

    with an already skewed pricing of MS / HSD , but with their economic cost

    of production . The best solution should be to use natural gas for

    generating additional power requirements for feeding mass rapid

    transportation system (MRTS) TO decrease avoidable per capital energy

    consumption through cars and personal vehicle.

    Gas Demand in city gas distribution sector

    Gas Demand

    11 12.0812.93

    13.83

    14.8 15.83

    2006-07 2007-08 2008-09 2009-10 2010-11 2011-12

  • 8/9/2019 jhpl

    20/80

    Source: oil & gasjournal

  • 8/9/2019 jhpl

    21/80

    3. Proposal: Jagdishpur-Haldia Pipeline

    Source: GAIL (INDIA) Ltd

  • 8/9/2019 jhpl

    22/80

    4. Jagdishpur-Haldia Pipeline

    GAIL has already received the authorization in July, 2009 from MoP&NG for

    laying Jagdishpur-Haldia pipeline. The authorized capacity for the above pipeline

    is 16 MMSCMD including 4.0 MMSCMD as common carrier.

    Jagdishpur-Haldia pipeline (JHPL) project has been conceptualized to cater to the

    gas demand of consumers in the states of eastern Uttar Pradesh, Bihar, Jharkhand

    and West Bengal. The gas source for the pipeline has been considered KG Basin

    and ONGC Mahanadi Gas. This pipeline shall carry gas from ONGC Mahanadi and

    KG Basin through Reliances Kakinada-Basudevpur-Howrah pipeline. The pipeline

    will start from Haldia and terminate at Phulpur.

    JHPL will originate from Haldia and will terminate at IFFCO; Phulpur. The gas

    demand of IFFCO Phulpur will be met through JHPL. This will optimize the rout for

    JHPL and enhance the capacity of existing Auraiya-Jagdishpur section by utilizing

    Phulpur-Thulendi-Jagdishpur pipeline section for transportation of gas in reverse

    flow in future.

    The demand assessed for the above pipeline is 32 MMSCMD. The gas availability fromgas supply source

    as indicated above will be about 30 MMSCMD and gas volume will be build up in

    phases. Based on the above, it is proposed to implement the above pipeline in

    phases based on availability of gas from source and gas sourcing tie-up. The design

    capacity for JHPL in first phase is 16 MMSCMD and which will be augmented in

    second phase from 16 to 32 MMSCMD.

    Detail of phases are as follows:

    Phase-1: (1860 km)

    Laying Haldia to Phulpur pipeline with spur lines/feeder lines to CGS Kolkata, HFC

    Durgapur, WBDPC Sagardighi, CGS Jamshedpur, FCI Sindri, CGS Ranchi, HFC

    Barauni, Power Plant Barh, CGS Patna, CGS Chapra, CGS Siwan, CGS Gopalganj,

    CGS Betiah, Power Plant Betiah, CGS Varanasi, and FCI Gorakhpur; CGS

    Allahabad.

    Phase-2: (190 km)

    Installation of Compressor at Haldia with spur lines to CSES Haldia, WBPDC

    Bandel, WBPDC Katwa, DPL Durgapur, SAIL Durgapur, and SAIL Bokaro &

    Petrochemical Plant Barauni.

    The design capacity of Haldia to Jagdishpur section in first phase is 16 MMSCMD.

    The design pressure of pipeline is 99.93 Kg/cm^2g (98 barg) and arrival pressure of

    gas at Haldia has been considered 70 kg/cm^2g initially and no gas compression

    facility has been considered at Haldia in first phase. Hydraulic study for Haldia-

    Phulpur section has carried out In-House and the optimized size for trunk line is

    found

  • 8/9/2019 jhpl

    23/80

    to be 36 diameter.

    The capacity of Haldia to Phulpur pipeline in second phase will be augmented from

    16 to 32 MSCMD by installing compressor at Haldia and no intermediate

    compressor has been envisaged in Haldia-Phulpur section. The gas will be boosted

    from 54 kg/cm^2g to 98 Barg (99.93 Kg/cm^2g) at Haldia compressor station.

  • 8/9/2019 jhpl

    24/80

    The pipeline is designed for 32 MMSCMD, for

    transportation & supply of gas at major demand

    centers enroute pipeline from Haldia to Jagdishpur.

    No spur lines are considered, only tap-off

    point have been considered at major demand

    centers enroute

    4. 1. BasicParameters

    Jagdishpur-Haldia pipeline. Arrival pressure of gas considered is 54-55 kg/cm^2g.

    The pipeline diameter is 30 with length of 876 km. Compressor is also envisaged

    at Jagdishpur for boosting pressure from 54 to 92 kg/cm^2g. Design pressure of

    pipeline is 92 kg/cm^2g and has the provision for reverse flow including

    augmentation of capacity in future by installing intermediate compressors on

    availability of

    more gas atJagdishpur

    S.No Parameters Detail

    1 Length-Trunk Line 800 km2 Trunk Line- Pipe Size 36

    3 Name of States covered Uttar Pradesh, Bihar, Jharkhand, West Bengal

    4 Products to be Re-gasified LNG, Natural gas

    5 Delivery Pressure at 53 kg/cm^2g

    6 Delivery Pressure at 45 kg/cm^2g

    7 Economic Life 25 years

    8 Benefits 1. No intermediate compressor2. Future capacity augmentation after installingintermediate compressor, if required.3. Can meet the gas requirement of Jagdishpur

    customers.4. Reversal Flow allowed.5. Low Operating cost as compared to other optionsexplored for pipelines.

    Source: GAIL (India) Ltd

    The gas source for Jagdishpur-Haldia pipeline has been considered as KG Basin by

    Reliance, Mahanadi by ONGC & KG Basin by GSPC. It is envisaged that this pipeline

    will originate from Haldia and terminate at IFFCO, Phulpur. The gas demand of

    IFFCO Phulpur will be met through JHPL. This connectivity will optimize the route for

    Jagdishpur-Haldia pipeline and enhance in capacity of existing Auraiya-Jagdishpur

    section and also effective utilization of Phulpur-Thulendi-Jagdishpur pipeline sectionin reverse flow mode in future.

    GAIL has signed MoU for formation of JV with ONGC and MoU for Joint Corporation

    with RIL for natural gas transmission available from ONGC Mahanadi and Reliance

    gas from KG Basin respectively. The availability of gas from KG Basin by Reliance,

    Mahanadi by ONGC and KG Basin by GSPC will be from

    2012 onwards at Haldia and the total volume of gas available is expected in the

  • 8/9/2019 jhpl

    25/80

    range of 30 MMSCMD. The gas supply & laying of pipeline from Kakinada to Haldia

    will be executed by Reliance and MoP&NG has given its authorization for the same

    to Reliance.

  • 8/9/2019 jhpl

    26/80

    4. 2. Gas Supply Scenario

    Gas source envisaged & projected available gas volume on the Jagdishpur-Haldiapipeline system is

    given below:

    Source Available Gas Volume(MMSCMD)2011-2012 2012-2013 2013-2014 2014-2015 2015-2016

    KG Basin 5.1 7.1 7.8 8.6 9.0Mahanadi Gas 0 5 10 20 20Total 5.1 12.1 17.8 28.6 29

    Availability of gas from KB basin and Mahanadi

    Gas from KG Basin

    GAIL has signed MoU on15.03.2007 for formation of JV with RIL for natural gas

    transmission available from KG Basin. RIL has already been receivedauthorization for laying pipeline in Kakinada- Basudevpur-Howrah section. RILs

    production from KG Basin D6 block has been started and gas is being produced

    in phases, initially 40 MMSCMD which may go up to 80 MMSCMD. This will be

    used as a feeder line for supplying Reliances KG Basin gas from Kakinada to

    Haldia. About 9.0 MMSCMD gas is expected at Haldia which will flow in Haldia-

    Phulpur section to cater to the gas demand of some of the consumer enroute

    Haldia-Phulpur pipeline.

    Gas from ONGC Mahanadi

    GAIL has signed MoU on 24.07.2007 for formation of JV with ONGC for natural

    gas transmission available from ONGC Mahanadi. As per the information

    gathered the availability of gas from ONGC Mahanadi will be from 2011-2012

    onwards. Gas production from Mahanadi Basin is expected to be

    20 MMSCMD and will flow through Haldia-Phulpur section to meet the gas demandin the states of

    West Bengal, Jharkhand, Bihar & Uttar Pradesh pertaining to fertilizer, power,commercial, industrial

    & city gas enroute Haldia-Phulpur pipeline.

    Customer Tie-Up

    GAIL has entered into HoA(s) for gas volume of about 30 MMSCMD enroute Haldia-

    Phulpur pipelines which is about 93.75% of the pipeline design capacity. List of

    HoA(s) is placed below. GAIL has signed MoU on 30.01.2009 with Indian Farmers

    Fertilizers Corporation Limited (IFFCO) for jointly pursuing for setting up gas based

    power plant at Betiah.

  • 8/9/2019 jhpl

    27/80

    About five fertilizer plants (HFC Durgapur, FCI Sindri, HFC Barauni, FCI Gorakhpur

    and IFFCO Phulpur) are falling enroute Haldia-Phulpur pipeline. Availability of about

    9.0 MMSCMD Reliances KG Basin gas can

    be distributed to fertilizer plants enroute HPPL.

  • 8/9/2019 jhpl

    28/80

    Projected gas demand year wise by Marketing is tabulated below:

    HoA(s)sign Gas In(MMSCM

    2012-2013 2013-2014 2014- 2015- 2016- 2017-Total 8.15 15.78 18.18 20.58 22.99 24.00

    Projected demand yearwise

  • 8/9/2019 jhpl

    29/80

    4. 3. Project Schedule and Cost Estimate

    The detailed project schedule of completion of total pipeline system is 42 months fromthe date of

    approval of the project (36 months from the date of notification).

    S.No. Description of Pipeline system Estimated Cost Rs Cr Completiondate

    /Commissioning

    Phase-1:16MMSCMD

    As perDFR(excluding IDC &MarginMoney forWC)

    As perFinancialappraisal(including IDC &Margin Moneyfor WC)

    date

    1.0 Laying of pipelinefrom Haldia to

    Phulpur along withspur lines /feederlines to Kolkata, HFCDurgapur, WBDPCSagardighi, CGSJamshedpur, FCISindri, CGS Ranchi,HFC Barauni, PowerPlant Barh, CGSPatna, CGS Chapra,CGS Siwan, CGSGopalganj, CGS

    Betiah, Power PlantBetiah, CGSVaranasi, FCIGorakhpur & CGSAllahabad.

    6163.84 6625.32 Dec,2011

    /

    March,20

    11

    Phase-2: Capacity 16 to32 MMSCMD

    2.0 Installation of compressor atHaldia along with

    spur lines to CSESHaldia, WBDPCBandel, WBDPCKatwa, DPLDurgapur, SAILBokaro &Petrochemical PlantBarauni

    909.42 970.86Sept,2012

    Dec,2013

    Total 7073.26 7596.18

  • 8/9/2019 jhpl

    30/80

    The cost estimate for total project (Phase-1 +Phase-2) is Rs 7596.18 Cr (including

    IDC and Margin Money for Working Capital) including Foreign Exchange component

    of Rs 700 Crs.

  • 8/9/2019 jhpl

    31/80

    23 | P a g

    JAGDISHPUR-HALDIA PIPELINE: DEMAND ESTIMATION & TARIFF DETERMINATION 20105. Gas Throughput for Transmission Tariff-JHPL

    5. 1. OPTIMAL PIPE SIZE:

    In order to select an optimal size of a pipeline GAIL can look into three main

    possibilities mentioned below:-

    Option-1:-36 pipeline with compressor station at Haldia, & with followingconfiguration:-

    No intermediate compressor

    Delivery pressure at Phulpuris 53kg/cm^2g

    It can meet the requirement of Jagdishpur

    Customers. Delivery pressure of Gas at

    Jagdishpur 45kg/cm^2g.

    Benefits/Limitation:-

    No Intermediate Compressor

    Future capacity augmentation after installing intermediate

    compressor, if required. Can meet the gas requirement of

    Jagdishpur customers.

    Reversal flow

    Low Operating cost

    Lowest Transport Tariff

    Option-2:-30 pipeline with compressor station at Haldia and with

    Two intermediate compressor stations at 106 km

    and 206 km. Delivery pressure at Phulpur is78kg/cm^2g.

    It can meet the requirement of 2.0MMSCMD gas flow of Indo Gulf FertilizersJagdishpur.

    Benefits/Limitation:-

    Two intermediate compressors, one at chainage of 106 km and second at

    chainage of 226 km. Can meet the requirement of Jagdishpur customers.

    Reversal Flow.

    Highest operating

    cost. HighestTransport Tariff.

    Option-3:-36 & 30pipeline

    36 pipeline up to Durgapur tap-off.

    One intermediate compressor at chainage

  • 8/9/2019 jhpl

    32/80

    24 | P a g

    of 351km. Delivery pressure at Phulpur is

    86kg/cm^2g.

  • 8/9/2019 jhpl

    33/80

    24 | P a g

    JAGDISHPUR-HALDIA PIPELINE: DEMAND ESTIMATION & TARIFF DETERMINATION

    2010

    Benefits/Limitation:-

    One intermediate compressor at chainage

    of 351 km. No reversal flow.

    High Operating cost.

    Transport tariff slightly higher compare to Option-1.

    Considering on technical analysis and above mentioned details, 36 pipeline size

    under option-1 was selected as optimal pipeline size for transportation of gas from

    Haldia to Jagdishpur, it is also having potential for further augmenting the capacity

    of pipeline in future on availability of more gas at Haldia.

    30 pipeline size is limited to capacity up to 30 MMSCMD with two compressors.

    The operating cost will also be higher in this case due to boosting of pressure of

    gas at two locations.

  • 8/9/2019 jhpl

    34/80

    25 | P a g

    JAGDISHPUR-HALDIA PIPELINE: DEMAND ESTIMATION & TARIFF DETERMINATION

    2010 5. 2. Proposed Pipeline System

    Pipeline system has been designed for meeting the gas demand in various

    sectors. Details are given below:

    e) Fertilizers (HFC Durgapur, FCI Sindri, HFC Barauni, FCI Gorakhpur & DILKanpur)

    f) Power (CESC Haldia, DPL Durgapur, WBPDC Bandel, WBPDC Katwa, WBPDCSagardighi & Barh

    Power Plant)

    g) Industries (SAIL Durgapur, SAIL Bokaro & Petrochemical Plant Barauni).

    h) City Gas (Kolkata, Jamshedpur, Ranchi, Patna, Chapra, Siwan,

    Gopalganj, Betiah Varanasi & Allahabad).

    Phase-1:-

    Installation of 36, 800 km trunk line from Haldia to Phulpur.

    Installation of dispatch terminal at Haldia for transportation and supply of gasto customers

    enroute Haldia-Phulpur.

    Installation of spur lines / feeder lines.

    a) 18, 70 km feeder line from Kolkata Tap-off (CH-40 km) to CGS Kolkata.

    b) 30, 60 km spur line from Durgapur Tap-off (CH-226 km) to HFC Durgapur.

    c) 24, 125 km spur line from Sagardighi Tap-off (HFC Durgapur) to

    WBPDC Sagardighi. d) 12, 100 km feeder line from Jamshedpur Tap-

    off (CH-226 km) to CGS Jamshedpur. e) 12, 25 km spur line from

    Sindri Tap-off (CH-286 km) to FCI Sindri.

    f) 12, 90 km feeder line from Ranchi Tap-off (CH-335 km) to CGS Ranchi.

    g) 24, 60 km spur lines from Barauni Tap-off (CH-435 km near GAYA) to

    CGS Patna Tap-off. h) 18, 70 km spur lines from CGS Patna Tap-off HFCBarauni.

    i) 18, 70 km spur lines from Barh Tap-off (at 20 km up stream of 18 spurline to HFC Barauni)

    to Barh Power Plant.

    j) 18, 60 km feeder line from Patna Tap-off (at CH-60 km in 24 spur line toHFC Barauni) to

    CGS Patna.

    k) 18, 65 km feeder line from Tap-off (CGS Patna) to

    CGS Chapra. l) 18, 65 km feeder line from Tap-off

    (CGS Chapra) to CGS Siwan.m) 18, 30 km feeder line from Tap-off (CGS Chapra) to CGS Gopalganj.

    n) 18, 35 km feeder line from Tap-off (CGS Gopalganj) to Power Plant

    Betiah and CGS Betiah. o) 12, 25 km feeder line from Varanasi tap-off

    (CH-685 km) to CGS Varanasi.

    p) 18, 140 km spur line from Gorakhpur Tap-off (CH-735 km) to FCIGorakhpur.

    q) 12, 40 km feeder line from Allahabad Tap-off (CH-770 km) to CGSAllahabad.

  • 8/9/2019 jhpl

    35/80

    26 | P a g

    Installation of Receiving Terminals (RTs)/Dispatch Terminals (DTs) at customer siteand also include City

    Gate Station for city gas.

    Phase-1:(1860 km)Laying Haldia to Phulpur pipeline with spur lines/feeder lines to CGS Kolkata, HFCDurgapur, WBDPC

    Sagardighi, CGS Jamshedpur, FCI Sindri, CGS Ranchi, HFC Barauni, Power PlantBarh, CGS Patna, CGS Chapra, CGS Siwan, CGS Gopalganj, CGS Betiah, CGSVaranasi, FCI Gorakhpur & CGS Allahabad.

  • 8/9/2019 jhpl

    36/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    27 | P a g

    Phase-I: (1860 km)

    Part-I A: (1410 km)

    Description of Pipeline System in First Phase Pipeline Configuration Demand(MMSCMCD)

    Part-I: (1410 km)

    Trunk Line

    Haldia Phulpur 36", 800 km 16Spur lines/Feederlines

    HFC Durgapur 30", 60 km 2.11

    FCI Sindri 12", 25 km 2.11

    CGS Patna tap-off 24", 60 km 0.25

    HFC Barauni 18", 70km 2.11

    Barh Power Plant 12", 25 km 0.50

    Patna City Gas 18", 60 km 0.25

    Chapra City Gas 18", 40 km 0.20

    Siwan City Gas 18", 65 km 0.10

    Gopalganj City Gas 18", 30 km 0.10

    City Gas & Power Plant at Betiah 18", 35 km 0.10 + 1.50

    FCI Gorakhpur 18", 140 km 2.11

    IFFCO, Phulpur Connectivity in existing 1.60system

    Note: The present IFFCO, Phulpur supply may be, swapped with new gasdemand pertaining to Auraiya-Jagdishpur Pipeline, such as DIL, Kanpur (1.9),SIOE (1.2) etc.)

    Part-IB: (450 km)

    Description of Pipeline System in First Phase Pipeline Configuration Demand(MMSCMD)

    Part-II: (450 km)

    Spur lines/Feeder lines

    Kolkata City Gas 18", 70 km 0.50

    WBDPC Sagardighi 24", 125 km 2.20

    Jamshedpur City Gas 12", 100km 1.00

    Ranchi City Gas 12", 90 km 0.20

    Varanasi City Gas 12", 25 km 0.50

    Allahabad City Gas 12", 40 km 0.25

    Total 17.69

    Phase-II: (190 km)

    Phase-2:-

    Installation of compressors at Haldia for boosting pressure from 54

    kg/cm^2g to 98 barg (99.93 kg/cm^2g).

  • 8/9/2019 jhpl

    37/80

    28 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    Installation of spur lines / feeder lines.

    a) 18, 15 km spur line Tap-off toCSES Haldia.

    b) 18, 85 km spur line from Tap-off (CH-40 km) to

    WBPDC Bandel.c) 18, 55 km spur line Tap-off (WBPDC Sagardighi) to

    WBPDC Katwa. d) 12, 5 km spur line from Tap-off

    (HFC Durgapur) to SAIL Durgapur. e) 12, 10 km spur

    line Bokaro Tap-off (CH-335 km) to SAIL Bokaro

    f) 12, 15 km spur line from Barauni Tap-off (HFC Barauni) toPetrochemical Plant Barauni.

    Installation of Receiving Terminals (RTs) / Dispatch Terminals (DTs)

    Description of Pipeline System in Second Phase Pipeline Configuration Demand(MMSCMD)

    Haldia-Phulpur section Compressors

    Installation of Compressor at Haldia

    Spur lines/Feeder lines

    CSES, Haldia 24", 15 km 4.2*

    Kolkata City Gas Covered in PH-I 1.50

    WBPDC Bandel 18". 55 km 2.00

    WBDPC Katwa 18", 85 km 2.00

    Durgapur Projects Ltd. 18", 5.0 km 4.50

    SAIL Durgapur & Durgapur City Gas 12", 5.0 km 1.45

    SAIL Bokaro 12", 10 km 1.07

    Petrochemical Plant Barauni 12", 15 km 1.00

    Varanasi City Gas Covered in PH-I, Part-II 0.50

    Allahabad City Gas Covered in PH-I, Part-II 0.25

    Total 18.47

  • 8/9/2019 jhpl

    38/80

    29 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    Source: GAIL (India) Ltd

  • 8/9/2019 jhpl

    39/80

    28 | P a g

    JAGDISHPUR-HALDIA PIPELINE: DEMAND ESTIMATION & TARIFF DETERMINATION 20106. PROJECTCOST

    The financial appraisal of pipeline along with their spur/feeder lines has been

    carried out along with tariff calculations as per PNGRB tariff regulations

    guidelines. Details of methodology followed forarriving for Jagdishpur-Haldia pipeline along with spur lines as per PNGRB guidelinesare given below.

    JHPL tariff has been determined considering a reasonable rate of

    return on normative level of capital employed plus a normative

    level of operating expenses in natural gas pipeline.

    The rate of return on capital employed has been considered as 12%

    (post- tax) andpre-tax return on capital employed has been computed by

    grossing up 12% which works out to 18.18%.

    The total capital employed includes working capital (equal to 30 daysof operating

    costs and 18 days of receivables) which has been considered forcalculating tariff.

    Levelized tariff has been calculated for Main Trunk Line and Spur

    Lines up to 50 Kms range of Main Line (put together) and thus

    corresponding capital cost, operating cost, receivables and working

    capital have been considered together for arriving at the Levelized

    tariff.

    The capacity utilization has been assumed as60%,70%,80%,90%,100% in

    1st,2

    nd,3

    rd,4

    th& % 5

    thyear of operations and thereafter respectively.

    The economic life of the project has been considered as 25 years

    of operations in case of first phase.

    The levelized tariff has been arrived based on the Discounted cashFlow(DCF)

    methodology equating the inflows from the projected revenue

    earnings out of natural gas pipeline tariff with the outflows of the

    capital and operating expenditures over the economic life of theproject by discounting these flows at the projects reasonable rate

    of return(viz.18.18% pre-tax).

    Capital employed includes Capex for pipelines besides Margin Money

    for working

    capital, Line Pack and interest during construction (IDC).

  • 8/9/2019 jhpl

    40/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    29 | P a g

    The major factor/assumption considered in the Financial Appraisal are as follows:

    Debt: Equity 70:30Long Term Debt Interest Rate

    10.25% Moratorium 1 year

    Term of loan including moratorium 10years Income Tax Rate

    33.99% Volume Build Up1

    st

    year2

    nd

    year3

    rd

    year4

    th

    year5th

    year

    60%70%80%90%100%

    Project life 25 yearsUnaccounted Gas 0.60% of throughputProject IRR (Post-Tax) on capitalemployed as perPNGRB guidelines

    12%

    Capital Outflow

    Year Deb Equit Total

    2009-10 638.0 273.4 911.542010-11 2977.7 1276.1 4253.8612011-12 1063.4 455.7 1519.232012-13 638.0 273.4 911.54Total 5317. 2278. 7596.18

    Cost Estimate & Operating Cost

    A detailed Capital Cost estimate (Capex) & Operating Cost (Opex) have beenprepared for the proposed pipeline system for transportation of gas to meet the

    gas demand of consumers and proposed city gas projects enroute Jagdishpur-

    Haldia Pipeline.

    The detailed cost estimate worked out to be Rs 7073.26Cr including foreign exchangecomponent of Rs

    726.27Cr, details are given below:-

  • 8/9/2019 jhpl

    41/80

    S.No Description

    EstimatedCost

    (Capex)

    Total Cost

    (Rs Crores)

    Fc Ic

    1 Pipeline System:

    Haldia to Phulpur Pipeline

    138.77 3937.34 4076.11

    2 Spur lines/Feeder Lines to:

    CGS Kolkata 12.21 126.83 139.0

    HFC Durgapur 13.46 229.83 243.2

    WBPDC Sagardighi 14.66 330.15 344.8

    CGSJamshedpur 6.99 104.75 111.74FCI Sindri 8.37 30.9

    039.2

    7CGS Ranchi 5.82 93.9

    599.7

    7HFC Barauni 19.97 311.44 331.4

    1Power Plant Barh 5.49 28.8

    934.3

    8CGS Patna 15.59 99.5 115.1

    CGS Chapra 4.82 82.0 86.8

    CGS Siwan 4.54 75.2 79.7

    CGS Gopalganj 4.64 47.68

    52.32

    Power Plant & CGS Betiah 9.60 57.7 67.3

    CGS Varanasi 5.97 29.22

    35.19

    FCI Gorakhpur 12.71 244.83 257.54

    CGS Allahabad 5.86 44.09

    49.95

    Total 289.47 5874.37 6163.8

    Capex (Rs

    Crores) Phase-

    1:16MMSCMD

  • 8/9/2019 jhpl

    42/80

    Phase-2:-Augmentation of capacity from 16 to 32 MMSCMD

    S.No Description

    EstimatedCost

    (Capex)

    Total Cost

    (Rs Crores)

    Fc Ic

    1 Pipeline System:

    CompressorHaldia

    379.27 135.94 515.21

    2 Spur Lines/Feeder Lines to:

    CSES Haldia 10.36 32.25

    42.61

    WBPDC Bandel 10.82 148.32 159.14

    WBPDC Katwa 7.77 97.4 105.1

    DPL Durgapur 11.79 16.5

    6

    28.3

    5SAIL & CGS Durgapur 4.99 8.64 13.6

    SAIL Bokaro 7.99 15.7 23.7

    Petrochemical Plant Barauni 3.80 17.7 21.5

    Total 436.79 472.61 909.40

    Grand Total(Phase-1 +Phase-2) 726.27 6346.99 7073.26

  • 8/9/2019 jhpl

    43/80

    Operating Cost(Rs

    Crores/Annum) Phase-1:-

    16MMSCMD

    S.No Description

    EstimatedCost

    (Capex)

    Total Cost

    (Rs Crores)

    Opex

    (Rs

    Fc Ic

    1 Pipeline System:

    Haldia to Phulpur Pipeline

    138.77 3937.34 4076.11

    69.35

    2 Spur Lines/Feeder Lines to:

    CGS Kolkata 12.21 126.83 139.0 2.63

    HFC Durgapur 13.46 229.83 243.2 4.54

    WBPDC Sagardighi 14.66 330.15 344.81

    6.08

    CGSJamshedpur 6.99 104.75 111.74

    2.21

    FCI Sindri 8.37 30.90

    39.27

    1.43

    CGS Ranchi 5.82 93.95

    99.77

    1.94

    HFC Barauni 19.97 311.44 331.41

    6.25

    Power Plant Barh 5.49 28.8 34.3 0.94

    CGS Patna 15.59 99.5 115.1 2.17

    CGS Chapra 4.82 82.0 86.8 1.74

    CGS Siwan 4.54 75.20 79.75 1.60

    CGS Gopalganj 4.64 47.6 52.3 1.21

    Power Plant & CGS Betiah 9.60 57.71

    67.31

    2.12

    CGS Varanasi 5.97 29.22

    35.19

    0.95

    FCI Gorakhpur 12.71 244.83 257.54

    4.76

    CGS Allahabad 5.86 44.0 49.9 1.18

    Total 289.47 5874.37 6163.84

  • 8/9/2019 jhpl

    44/80

    Phase-2:-Augmentation of capacity from 16 to 32 MMSCMD

    S.No Description

    EstimatedCost

    (Capex)

    Total Cost

    (Rs Crores)

    Opex

    (Rs

    Fc Ic

    1 Pipeline System:

    CompressorHaldia

    379.27 135.94 515.21

    147.66

    2 Spur line/Feeder Lines to:

    CSES Haldia 10.36 32.25 42.61

    1.48

    WBPDC Bandel 10.82 148.32 159.1 3.26

    WBPDC Katwa 7.77 97.40 105.1 2.43

    DPL Durgapur 11.79 16.56 28.3 1.26

    SAIL & CGS Durgapur 4.99 8.64 13.6 1.04

    SAIL Bokaro 7.99 15.73 23.7 1.18

    Petrochemical Plant 3.80 17.77 21.57

    1.16

    Total 436.79 472.61 909.40

    Grand Total(Phase-1+Phase-2

    726.27 6346.99 7073.26

    Source: GAIL (India) Ltd

  • 8/9/2019 jhpl

    45/80

    34 | P a g

    JAGDISHPUR-HALDIA PIPELINE: DEMAND ESTIMATION & TARIFF DETERMINATION

    2010 7. PROJECTFINANCIALS

    7. 1. Total Revenues

    Revenue details of the trunk line and other spur line has been arrived on the

    demand estimated provided by technical team of GAIL (India) Ltd. and PNGRB

    guidelines of capacity utilization, following table gives year wise revenues till year10 for trunk line and spur lines which are above 50 km in length.

    The revenues for the project life are based on the estimated tariff/MMBTU.

    Following table indicates revenue details of the project till year 10.

    Revenue Details ofPipeline

    Volume Year1 Year2 Year3 Year4 Year5 Year6 Year7 Year8 Year9 Year

    MMSCM ------------------------------------------------------------Rs

    Trunk line and Spurlines which areunder the corridorof 50 kmrange

    28. 00 1289.95

    1504.95

    1719.94

    1934.93

    2149.92

    2149.92

    2149.92

    2149.92

    2149.92

    214992

    HFC Durgapur-SAILDurgapur-DPLDurgapur- WBPDCSagardighi

    10. 26 91. 97 107. 29 122. 62 137. 95 153. 28 153. 28 153. 28 153. 28 153. 28 153.

    WBPDC-Katwa 2. 00 22. 45 26. 20 29. 94 33. 68 37. 42 37. 42 37. 42 37. 42 37. 42 37. 4

    CGS Patna to Betiah 2. 25 84. 92 99. 07 113. 22 127. 38 141. 53 141. 53 141. 53 141. 53 141. 53 141.

    WBPDC-Bandel 2. 00 15. 87 18. 51 21. 16 23. 80 26. 44 26. 44 26. 44 26. 44 26. 44 26. 4

    HFC Barauni to Barah 3. 61 21. 55 25. 14 28. 74 32. 33 35. 92 35. 92 35. 92 35. 92 35. 92 35. 9

    CGS Kolkata 2. 00 11. 43 13. 43 15. 24 17. 15 19. 06 19. 06 19. 06 19. 06 19. 06 19. 0

    CGS Ranchi 0. 20 10. 31 12. 03 13. 75 15. 47 17. 19 17. 19 17. 19 17. 19 17. 19 17. 1

    FCI Gorakh ur 2. 11 35. 62 41. 56 47. 49 53. 43 59. 37 59. 37 59. 37 59. 37 59. 37 59. 3

    CGSJamshedpur 1. 00 13. 19 15. 39 17. 59 19. 79 21. 99 21. 99 21. 99 21. 99 21. 99 21. 9

    Total Revenue 1597.27

    1863.48

    2129.70

    2395.91

    2662.12

    2662.12

    2662.12

    2662.12

    2662.12

    266212

    7. 2. Capital Expenditure

    The capital expenditure of the project is computed based on the cost estimates provided bthe GAIL

    technical team.

    Cost of Compressor:

    Total cost of the compressor is computed at Rs 490. 84 Crores which includes

    compressor cost, compressor cooler, scrubber, fuel gas conditioning skid,

    compressor valves & accessories, compressor piping, fitting and equipment,

    electrical & instrumental items, utility items, compressor station construction cost

    .

  • 8/9/2019 jhpl

    46/80

    35 | P a g

    Below mentioned table provides phase wise details of capital expenditure:

  • 8/9/2019 jhpl

    47/80

    35 | P a g

    JAGDISHPUR-HALDIA PIPELINE: DEMAND ESTIMATION & TARIFF DETERMINATION

    2010

    Particulars Phase-1 Phase-2 Total (Rs. Crs)

    Haldia to Phulpur 3974. 14 0. 00 3974. 14

    Compressor 0. 00 490. 84 490. 84

    Survey 5. 35 0. 98 6. 33

    Land and ROW 51. 61 9. 13 60. 74

    PMC 54. 74 10. 36 60. 74

    Plant & Machinery 1767. 97 335. 72 2103. 69

    Owners Expenses 54. 74 10. 36 65. 10

    Contingencies 96. 89 18. 28 115. 17

    Line Pack 8. 91 1. 68 10. 59

    TOTAL 6014. 36 877. 35 6891. 71

    Total Interest

    during

    720. 15

    Total working capital 25. 47

    Total 745. 62

    GRAND TOTAL 7637. 33

    7. 3. Operating Expenditure:

    Operating cost required for the operation and maintenance of the project of the

    proposed Jagdishpur- Haldia Pipeline Project over its economic life is computed andfollowing table provides costs for various functional heads in phased manner.

    InCrore

    Total Operating expenditure

    S. No. Description Total Phase-1 Phase-2

    1 Trunk line 86. 84 86. 84 0. 00

    2 Compressor 126. 38 0. 00 126. 38

    3 Repair &Maintenan

    36. 40 30. 60 5. 80

    4 Manpower 9. 20 6. 00 3. 20

    5 Security 0. 00 0. 00 0. 006 O&M Contract 0. 00 0. 00 0. 00

    7 Insurance 11. 96 10. 03 1. 93

    8 Overheads ofGAIL 9. 20 6. 00 3. 20

    9 Fuel cons 0. 00 0. 00 0. 00

    10 Power (75KW) 1. 14 0. 73 0. 41

    TOTAL 281. 13 140. 20 140. 93

  • 8/9/2019 jhpl

    48/80

    36 | P a g

    JAGDISHPUR-HALDIA PIPELINE: DEMAND ESTIMATION & TARIFF DETERMINATION 20107. 4. Methodology for Tariff Calculation

    The natural gas pipeline tariff shall be determined by considering a reasonable

    rate of return on normative level of capital employed plus a normative level of

    operating expenses in the natural gas pipeline

    The unit rate of natural gas pipeline tariff to be charged for a period shall

    be the calculated based on the Discounted Cash Flow DCFmethodology considering the reasonable rate of return as specified in the

    regulation to be considered as projects internal rate of return.

    The rate of return on capital employed shall be the rate of return on capitalemployed equal to

    percentage post-tax. The rate of return on capital employed once applied

    to a natural gas pipeline project shall remain fixed for the entire economic

    life of the project.

    The total capital employed shall be equal to the grossed fixed assets

    in the project less

    accumulated depreciation plus normative working capital (equal to thirty

    days of operating cost excluding depreciation and eighteen days of natural

    gas pipeline receivables).

    The volumes of natural gas to be considered as divisor in the determination ofunit natural gas

    pipeline tariff over the economic life of the project shall be computed on a

    normative basis as indicated below.

    The divisor for each of the first five years of operation of the natural gas

    pipeline shall be arrived

    by multiplying the applicable percentage utilization for the year, as per

    the basis indicated below, with the sum of the capacity requirement of

    the entity and the firmed up contractedcapacity with other entities as specified under the PNGRB Regulations 2008.

    Year of Natural Gas Pipeline Percentage Utilization

    First 60%

    Second 70%

    Third 80%

    Fourth 90%

    Fifth 100%

    The divisor for the sixth and the subsequent years of operations of the

    natural gas pipeline be equal to one hundred percent of the sum of the

    capacity requirement of the entity or the actual

    volume of the natural gas transported on common carriers

  • 8/9/2019 jhpl

    49/80

    37 | P a g

    Considering the present project configuration, the subsequent

    capital cost and the profitability projections, the line wise transportation for 12%

    (post-tax) return on capital employed are given in the following table:

  • 8/9/2019 jhpl

    50/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    38 | P a g

    7. 5. Transportation Tariffs for Trunk Lines

    Description Transportation Tariff

    (Rs/MSC (INR/MMBTU)

    Base Case: Gas volume,24 MMSCMD, excluding 8 MMSCMD as common carrierTariff for mainline and spur lines within the corridor up to 50 kmMain TrunkLine(Haldia toPhulpur)and spur lines/feeder lineswithin and upto 50km (CSESHaldia,WBPDC Bandel,

    HFC Durgapur,CGSJamshedpur, FCISindri, CGSRanchi, SAILBokaro HFC

    2771.42

    83.15

    Transportation Tariffs for Spur lines

    Description Transportation Tariff

    (Rs/MSCM) (INR/MMBTU)

    Base Case: Gas volume,24 MMSCMD, excluding 8 MMSCMD as common carrierTariff for spur lines/feeder lines to beyond 50 kmSpur lines to:

    -CGS Kolkata-WBPDC Bandel-HFC Durgapur-SAIL Durgapur-DPL Durgapur-WBPDC

    Sagardighi-WBPDC Katwa-CGS Jamshedpur-CGS Ranchi-HFC Barauni-PE PlantBarauni-Power PlantBarh

    348.03483.06545.51545.51545.51545.51

    683.23803.243139.37363.22363.22363.222266.762266.76

    10.4414.4916.3716.3716.3716.37

    20.5024.1094.1910.9010.9010.9068.0168.01

  • 8/9/2019 jhpl

    51/80

    (Rs/MSCM) (INR/MMBTU)

    CSES Haldia 2771.42 83.15

    CGS Kolkata 3119.45 93.59WBPDC Bandel 3254.48 97.64HFC Durgapur 3316.93 99.52

    SAIL Durgapur 3316.93 99.52

    DPL Durgapur 3316.93 99.52

    WBPDC Sagardighi 3316.93 99.52WBPDC Katwa 3454.65 103.65

    CGS Jamshedpur 3574.66 107.25

    FCI Sindri 2771.42 83.15

    SAIL Bokaro 2771.42 83.15CGS Ranchi 5910.78 177.34

    HFC Barauni 3134.64 94.05Petrochemical Plant 3134.64 94.05

    Power Plant Barh 3134.64 94.05CGS Patna 5038.18 151.16

    CGS Chapra 5038.18 151.16

    CGS Siwan 5038.18 151.16

    CGS Gopalganj 5038.18 151..16CGS Betiah 5038.18 151.16

    Power Plant Betiah 5038.18 151.16

    CGS Varanasi 2771.42 83.15

    FCI Gorakhpur 3800.66 114.03CGS Allahabad 2771.42 83.15

    39 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    -CGS Siwan 2266.76 68.01-CGS Gopalganj 2266.76 68.01-CGS Betiah 2266.76 68.01-Power Plant 2266.76 68.01-FCI Gorakhpur 1029.24 30.88

    (Conversion Factor: 33.3330 for CV of 84, 00 kcal/SCM; 1USD=48)

    Levelized Transportation tariff

    Description ofConsumers

    Transportation Tariff(Mainline with tariff of spur line up to 50 km/Mainline tariff and additional tariff for spurlines beyond 50 km)

    Transportation Tariff

    The Levelized Tariff in respect of the consumers(trunk line tariff/zonal

    tariff + customer connectivity tariff) of Dabhol-Bangalore pipeline for 12%

    project IRR on capital employed(at,8400 kcal/SCM) as per PNGRB

  • 8/9/2019 jhpl

    52/80

    40 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    guidelines are given above.

  • 8/9/2019 jhpl

    53/80

    Applicable transportation tariff for pipeline for consumers enroute Haldia-Phulpur

    pipeline will be in the tune of 83.15-177.34 INR/MMBTU, as tabulated above and the

    tariff applicability will be subject to approval of the regulatory authority.

    Marketing group confirms that the above tariff is applicable to gas consumers

    and contract will be executed at this tariff.

    The committee deliberated on tariff, it has emerged that presently tariff has beenworked out for 24

    MMSCMD without considering common carrier gas volume i.e.8 MMSCMD. The

    tariff calculated above will proportionally reduce on availability of common carrier

    gas volume for transportation.

    .

  • 8/9/2019 jhpl

    54/80

    40 | P a g

    JAGDISHPUR-HALDIA PIPELINE: DEMAND ESTIMATION & TARIFF DETERMINATION20108. MEANS OFFINANCE

    The project is proposed to be funded by term loans from Banks/Financial

    Institutions and equity contribution from internal resources in the ratio of 70:30.

    The proposal means of finance for the project will be as under

    Means of Finance

    Means of Finance Total

    Rupee Term Loan proposed @ 70% 5346. 13

    Promoters Contribution through Internal 2291. 20accruals @ 30%

    TOTAL 7637. 33

    Equity Contribution:

    The total amount of promoters contribution for the proposed expansion project is

    estimated at Rs.2291. 20 Crores, which can be met from internal accruals.

    Term Loan

    The company proposes to raise Rupee term loans to the extent of Rs. 5346. 13

    Crores from Banks & Financial Institutions to part finance the project.

    The broad terms of the proposed loan is as given below

    Nature of borrowing Rupee term LoanLoan Amount Rs. 5346. 13 Crore

    Interest Rate 10. 25%Moratorium period 1 year

    Tenor 8 years

    Installments per year 4

    Free Cash Flow Available

    Based on the cash flow projection of GAIL for the next five years the free cash flowavailable with GAIL

    for future projects has been arrived as detailed below (Assuming Debt Equity Ratio of

    70:30).

  • 8/9/2019 jhpl

    55/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    41 | P a g

    Free Cash Flow

    S. No. Particulars 2009-10 2010-11 2011-12 2012-13 2013-14

    1.

    2.

    3.

    4.

    5.

    6.

    7.

    8.

    Funds Available 5624 2980 3185 3027 2676

    Total Capex 7957 9605 11412 73773509

    Pipeline Project(Future Project ) 553 2463 6405 5310 1905

    Total Capex (Excluding future Pipelines) 7404 7142 5007 2067 1604

    Fund Commitment for equity excluding future Projects 2221. 20 2142. 60 1502. 02 620. 10

    Availability of funds for future projects 3402. 80 837. 40 1682. 90 2406. 90 2194. 8

    Requirement of fund for future project(JHPL) 278. 78 1321. 92 584. 83 274. 52

    Cumulative Availability of funds for future projects 3402. 80 4240. 20 5923. 10

    Cumulative Requirement of funds for future projects 278. 78 1600. 70 2185. 53

    Surplus after meeting fund for future projects 3124. 02 2639. 50 3737. 57 5869. 95

    Source: GAIL (India) Ltd.

    It is observed that GAIL has sufficient cash to meet its equity obligation for the

    proposed JHPL project. However GAIL have other pipeline projects which are in

    process of approvals, it is therefore recommended to have check on the fund

    availability for its equity contribution before the projects commissioned.

    Source: GAIL (India) Ltd

  • 8/9/2019 jhpl

    56/80

    42 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    9. BasicAssumption

    Broad Assumptions:

    Capital cost estimates for Jagdishpur-Haldia

    pipeline project system have been provided by technical consultants of GAIL and as

    on 2010. Further no escalation has been considered. However appropriate inflation

    has been taken into account for overall

    project development.

    Construction Period 36 months

    Interest rate on loans 10.25%

    Debt: Equity ratio 70:30

    Moratorium period 2 years of commissioning of

    Project life 25 years

    Corporate tax 33.99%

    Depreciation method 3.17% p.a. Straight line method

    IDC 720.15Unaccounted gas 0.60%

    Statutory and Indirect costs including taxes and duties

    Parameter Corresponding

    Ocean Freight5%Inland Insurance 1%

    Port handling charges 1.5%

    Excise duty 8.24%

    Service tax 10.3%

    WCT 4.00%

    Basic custom duty + additional CD in Cess 25.58%

    No. of working days 365

    Design Capacity:

    As per authorization, the capacity of this pipeline is 16 MMSCMD (which is inclusiveof 4 MMSCMD for common carrier), however based on prevailing gas demand and

    gas availability scenario, the design capacity for JHPL in first phase will be 16

    MMSCMD and which will be augmented in second phase from

    16 to 32 MMSCMD.

    Line Pack:

    Line pack has been estimated by GAIL and technical consultants of GAIL for JHPL

    project. Total Line pack of Rs. 10.59 Crore has been considered with Rs. 8.91 Crore

  • 8/9/2019 jhpl

    57/80

    43 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201in Phase-1 and Rs. 1.68 Crore in Phase-2.

    Line pack has been considered as part of capital cost and assumed to be

    financed in the same proportion as the capital cost.

  • 8/9/2019 jhpl

    58/80

    44 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    Unaccounted Gas Losses:

    A provision of 0.6% of the annual throughput has been assumed towards UnaccountedGas Losses.

    Variable Costs:

    Various variable costs incurred due to JHPL project has been considered.

    Fixed Operating Costs:

    Fixed operating expenses like: salaries & wages, Plan & Administrative overheads,

    insurance, repairs and maintenance.

    Escalation in operating costs:

    The operating costs have been escalated at 5% per annum during operations

    period to account for any increase due to inflation and other factors.

    Operational life of project:

    For the purpose of profitability projection, the operational life of the project has

    been considered as 25 years from the date of commencement of commercialoperations.

    Compressor replacement:

    A provision of RS 490.84 Crore has been considered on the present cost ofcompressor for 15 years.

    Depreciation Rates:

    Depreciation has been considered at 3.17% (including for compressor) and

    straight line method has been used to compute the depreciation.

    Salvage value:The salvage at the end of 25 years has been assumed. For working capital it has beenassumed at 100%

    and total line pack is added into total salvage value.

    Income tax Rates:

    Income tax estimation is based on corporate tax of 33.99%

    Conversion Factor for transportation tariff

    1 MMBtu 251996 kCal

    CV 8400 kCal/ SCM

    1 MMBtu 28 SCM1 MMSCMD 35715 MMBtu

  • 8/9/2019 jhpl

    59/80

    44 | P a g

    JAGDISHPUR-HALDIA PIPELINE: DEMAND ESTIMATION & TARIFF DETERMINATION 201010.Profitability Analys

    isBelow mentioned tables would provide

    estimated profit margins for the proposed

    project. Separate profitability

    details have been provided for Main line andSpur Lines

    Key Project Financials for Trunk line till Year 10

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year

    Revenue 1,290 1,505 1,720 1,935 2,150 2,150 2,150 2,150 2,150 2,150

    Opex 248 262 276 290 305 320 335 351 368 386

    Operating Margin 1,042 1,243 1,444 1,645 1,845 1,830 1,815 1,799 1,782 1,764

    Depreciation 172 172 172 172 172 172 172 172 172 172

    Amortization 2 2 2 2 2 2 2 2 2 2

    EBIT 868 1,069 1270 1,471 1,671 1,656 1,641 1,624 1,608 1,590

    Interest on Term 417 436 416 361 307 252 198 143 89 34

    Interest on WC 8 9 11 12 13 14 14 14 14 14

    PBT 443 624 844 1,098 1,350 1,390 1,429 1,467 1,505 1,541

    Tax(@)33.99% - 91 193 302 407 437 464 489 512 533

    PAT 443 533 651 796 943 953 965 978 993 1,008

    HFC Durgapur-SAIL Durgapur-DPL Durgapur-WBPDC Sagardighi

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year

    Revenue 92 107 123 138 153 153 153 153 153 153

    Opex 12 12 13 14 14 15 16 16 18 18

    Operating Margin 80 95 110 124 139 138 137 137 136 135

    Depreciation 12 12 12 12 12 12 12 12 12 12

    Amortization 1 1 1 1 1 1 1 1 1 1

    EBIT 67 82 96 111 126 125 124 123 122 122

    Interest on Term 32 34 32 28 24 19 15 11 7 3

    Interest on WC 1 1 1 1 1 1 1 1 1 1

    PBT 34 47 64 82 101 105 108 111 115 118

    Tax(@)33.99% - 7 15 23 31 33 35 37 39 41

  • 8/9/2019 jhpl

    60/80

    45 | P a g

    PAT 34 40 49 59 70 72 73 74 76 77

  • 8/9/2019 jhpl

    61/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    WBPDC-Katwa

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year

    Revenue 22 26 30 34 37 37 37 37 37 37

    Opex 3 3 3 3 4 4 4 4 4 5

    Operating Margin 20 23 27 30 34 34 34 33 33 33

    Depreciation 3 3 3 3 3 3 3 3 3 3

    Amortization 0 0 0 0 0 0 0 0 0 0

    EBIT 16 20 24 27 31 31 30 30 30 30

    Interest on Term 8 8 8 7 6 5 4 3 2 1

    Interest on WC 0 0 0 0 0 0 0 0 0 0

    PBT 8 12 16 20 25 26 26 27 28 29

    Tax(@)33.99% - 2 4 6 8 8 9 9 10 10PAT 8 10 12 15 17 17 18 18 18 19

    CGS Patna to Betiah

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year

    Revenue 85 99 113 127 142 142 142 142 142 142

    Opex 11 11 12 12 13 14 14 15 16 17

    Operating Margin 74 88 101 115 129 128 127 126 126 125

    Depreciation 11 11 11 11 11 11 11 11 11 11

    Amortization 1 1 1 1 1 1 1 1 1 1

    EBIT 62 76 89 103 116 116 115 114 113 113

    Interest on Term 30 31 30 26 22 18 14 10 6 2

    Interest on WC 0 1 1 1 1 1 1 1 1 1

    PBT 32 44 59 76 94 97 100 103 106 109

    Tax(@)33.99% 0 6.906 13.773 21.191 28.371 30.565 32.585 34.453 36.19 37.813

    PAT 32 37 45 55 65 66 67 69 79 72

  • 8/9/2019 jhpl

    62/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    WBPDC-Bandel

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year

    Revenue 16 19 21 24 26 26 26 26 26 26

    Opex 2 2 3 3 3 3 3 3 3 4

    Operating Margin 14 16 19 21 24 24 23 23 23 23

    Depreciation 2 2 2 2 2 2 2 2 2 2

    Amortization 0 0 0 0 0 0 0 0 0 0

    EBIT 12 14 17 19 22 22 21 21 21 21

    Interest on Term 5 6 5 5 4 3 3 2 1 0

    Interest on WC 0 0 0 0 0 0 0 0 0 0

    PBT 6 8 11 14 17 18 18 19 20 20

    Tax(@)33.99% 0 1.2935 2.5606 3.9281 5.2522 5.6454 6.0064 6.3395 6.6484 6.9362

    PAT 6 7 8 10 12 12 12 13 13 13

    HFC Barauni to Barah

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year

    Revenue 22 25 29 32 36 36 36 36 36 36

    Opex 3 4 4 4 4 4 5 5 5 5

    Operating Margin 19 21 25 28 32 32 31 31 31 31

    Depreciation 3 3 3 3 3 3 3 3 3 3

    Amortization 0 0 0 0 0 0 0 0 0 0

    EBIT 15 19 22 26 29 29 29 28 28 28

    Interest on Term 7 8 7 6 5 4 3 2 2 1

    Interest on WC 0 0 0 0 0 0 0 0 0 0

    PBT 8 11 15 19 23 24 25 26 26 27

    Tax(@)33.99% - 2 4 5 7 8 8 9 9 9

    PAT 8 9 11 14 16 17 17 17 17 18

  • 8/9/2019 jhpl

    63/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    CGS Kolkata

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year

    Revenue 11 13 15 17 19 19 19 19 19 19

    Opex 2 2 2 2 2 2 2 3 3 3

    Operating Margin 9 11 13 15 17 17 17 16 16 16

    Depreciation 1 1 1 1 1 1 1 1 1 1

    Amortization 0 0 0 0 0 0 0 0 0 0

    EBIT 8 10 12 13 15 15 15 15 15 15

    Interest on Term 4 4 4 3 3 2 2 1 1 0

    Interest on WC 0 0 0 0 0 0 0 0 0 0

    PBT 4 6 8 10 12 13 13 13 14 14

    Tax(@)33.99% - 1 2 3 4 4 4 4 5 5

    PAT 4 5 6 7 9 9 9 9 9 9

    CGS Ranchi

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year

    Revenue 10 12 14 15 17 17 17 17 17 17

    Opex 1 1 2 2 2 2 2 2 2 2

    Operating Margin 9 11 12 13 15 15 15 15 15 15

    Depreciation 1 1 1 1 1 1 1 1 1 1

    Amortization 0 0 0 0 0 0 0 0 0 0

    EBIT 8 10 11 12 14 14 14 14 14 14

    Interest on Term 4 5 4 3 3 2 2 1 1 0

    Interest on WC 0 0 0 0 0 0 0 0 0 0

    PBT 4 5 7 9 11 12 12 12 13 13

    Tax(@)33.99% - 1 2 3 3 4 4 4 4 5

    PAT 4 4 5 6 8 8 8 8 8 9

  • 8/9/2019 jhpl

    64/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    FCI Gorakhpur

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year

    Revenue 36 42 48 53 59 59 59 59 59 59

    Opex 4 5 5 5 5 5 6 6 6 6

    Operating Margin 32 37 43 49 54 54 54 54 53 53

    Depreciation 5 5 5 5 5 5 5 5 5 5

    Amortization 0 0 0 0 0 0 0 0 0 0

    EBIT 27 32 38 43 49 49 49 48 48 48

    Interest on Term 13 13 13 11 9 8 6 4 3 1

    Interest on WC 0 0 0 0 0 0 0 0 0 0

    PBT 14 19 25 32 40 41 42 44 45 46

    Tax(@)33.99% - 3 6 9 12 13 14 15 15 16

    PAT 14 16 19 23 28 28 29 29 30 30

    CGS Jamshedpur

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year

    Revenue 13 15 18 20 22 22 22 22 22 22

    Opex 2 2 2 2 2 3 3 3 3 3

    Operating Margin 11 13 16 18 20 19 19 19 19 19

    Depreciation 2 2 2 2 2 2 2 2 2 2

    Amortization 0 0 0 0 0 0 0 0 0 0

    EBIT 9 11 14 16 18 17 17 17 17 17

    Interest on Term 4 4 4 4 3 2 2 2 1 0

    Interest on WC 0 0 0 0 0 0 0 0 0 0

    PBT 5 7 10 12 15 15 15 15 16 17

    Tax(@)33.99% - 1 2 3 5 5 5 5 5 6

    PAT 5 6 8 9 10 10 10 10 11 11

  • 8/9/2019 jhpl

    65/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    Combined P&L Account Statement

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year

    Revenue 1,597 1,863 2,130 2,396 2,662 2,662 2,662 2,662 2,662 2,662

    Opex 289 304 320 337 355 372 390 408 428 449

    Operating Margin 1,308 1,559 1,809 2,059 2,308 2,290 2,272 2,254 2,234 2,213

    Depreciation 212 212 212 212 212 212 212 212 212 212

    Amortization 5 5 5 5 5 5 5 5 5 5

    EBIT 1,091 1,341 1,592 1,841 2,090 2,073 2,055 2,036 2,016 1,995

    Interest on Term 524 548 522 454 385 317 248 180 111 43

    Interest on WC 9 11 13 15 16 17 17 17 17 17

    PBT 557 782 1,056 1,373 1,688 1,739 1,790 1,839 1,888 1,935

    Tax(@)33.99% - 116 243 378 510 547 582 614 643 669

    PAT 557 666 814 994 1,178 1,192 1,208 1,226 1,245 1,266

    It is observed that if the project is executed as per the time lines defines and if

    GAIL secures itself with marketing and distribution of the gas to defined capacity

    then the estimated profit margins can be met easily. Below mentioned picture

    reflects the projected profit margin for 10 years from the

    commissioning of the project.

    Profit After Tax (PAT)-Combined P&L

    1600

    PAT in Rs Crore

    1400

    1200

    1000

    800

    600

    PAT in Rs Crore

    400

    200

  • 8/9/2019 jhpl

    66/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 2010

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10

  • 8/9/2019 jhpl

    67/80

    Projected Financial

    Project IRR Project IRR Equity IRREquity IRR

    Trunk line and Spur lines which are under the corridor of 50 km range 17.24% 12.00%

    HFC Durgapur-SAIL Durgapur-DPL Durgapur-WBPDC Durgapur 17.18% 12.00% 34.40%

    WBPDC Katwa 17.21% 12.00% 34.53% 27.02%CGS Patna to Betiah 17.19% 12.00% 34.41% 26.95%

    WBPDC Bandel 17.22% 12.00% 34.61% 27.09%

    HFC Barauni to Barah 17.36% 12.00% 35.21% 27.46%

    CGS Kolkata 17.22% 12.00% 34.67% 27.15%

    CGS Ranchi 17.23% 12.00% 34.62% 27.08%

    FCI Gorakhpur 17.19% 12.00% 34.43% 26.95%

    CGS Jamshedpur 17.25% 12.00% 34.78% 27.20%

    As per the PNGRB Guidelines, 12% post IRR for the project has been fixed through-

    out all the spur lines and Main line to arrive at the tariff.

  • 8/9/2019 jhpl

    68/80

    51 | P a g

    JAGDISHPUR-HALDIA PIPELINE: DEMAND ESTIMATION & TARIFF DETERMINATION 201011. SWOTANALYSIS

    Strengths:

    1. The project is being executed by GAIL, which is an existing profit making

    company having a good track record and credibility.

    2. GAIL is Indias largest gas transmission company with almost 80% marketshare.

    3. The company is in complete value chain of gas business.

    4. GAIL is also present in overseas for exploration business.

    5. GAIL has market share of around 80% in natural gas market.

    6. GAIL is supported by Government of India.

    Weakness:1. As a Public Sector Organization, GAIL has the obligation to work within

    the parameters of the policies and directions of the Government of India.

    2. GAIL has to meet all their statutory requirements before a

    commencement of commercial operations.

    Opportunities:1. Resources in KG Basin and Mahanadi Basin ha increased the availability ofnatural gas.

    2. There is a steady growth in demand for petroleum products.3. Pipelines projects can be leveraged for telecom business.

    4. There is potential in cross country pipeline business.

    Threat:1. GAIL is subject to threat of subsidy and pricing policy of ministry of petroleumand natural gas.

    2. Raise in natural gas prices can lead to reduction in margin in petrochemical

  • 8/9/2019 jhpl

    69/80

    52 | P a g

    business.

  • 8/9/2019 jhpl

    70/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    53 | P a g

    The major risk identified are delay in execution, increase inproject cost, firm gas tie -up with stream and downstreamagencies.

    Investment Committee has deliberated on the above RiskAnalysis and is of the opinion that considering the past trackrecord of GAIL in executing the pipeline projects , timelypipeline completion can be achieved by having regularproject review at site, corporate and Management level.However, committee felt that considering large Capexinvolvement and debt services required, firm gas tie-up

    with upstream and downstream consumer / transmissionagreement is critical for meeting the required levelrevenue generation to maintain financial viability of theproject and liquidity of the company.

    In absence of firm gas supply agreement beforecommissioning the project and clear indication of likelyavailability of gas and the time line of such gas availabilityand completion of RIL's Kakinada-Basudevpur-Howrah pipelinewill affect the project IRR and the return on investment toGAIL. Availability of KG Basin/ONGC Mahanadi at Haldia isdepending upon the laying of Kakinada- Basudevpur-Howrah

    pipeline by Reliance. However, GAIL has signed MoU with RILfor transmission of KG Basin gas and ONGC fortransportation of ONGC Mahanadi gas. Any failure or delayon the part of instillation of Kakinada- Basudevpur-Howrahpipeline and availability of low gas volume will affect theproject IRR and return on investment to GAIL. If the 60 % (1styear) to 100 % (6th year) capacity is not achieved due to gassourcing tie-up, GAIL will not achieve the minimum 12% IRRon the project

    GAIL is currently executing DVPL-GREP expansion and layingDBNPL and CJHPL pipeline projects worth of Rs 14,500 Crore.

    In addition, it is proposed to take up three new pipelineprojects at a cost of Rs 15,243 Crore. To finance theseexisting and new projects, GAIL has to resort to large debt.The total debt burden on GAIL will increase to estimated levelof Rs 20,000 Crore by 2012-13 from the current level of Rs1,100 Crore. Any mismatch due to lower capacity utilization ofthe pipeline due to non availability of sufficient gas orconsumers will result in reduced cash inflow/revenue and thusimpact the financial health and the liquidity of the company.

    12.

    RISK

    ANALYS

    IS

    &

    MITIGATIO

    NSTRATEGI

    ES

  • 8/9/2019 jhpl

    71/80

    13. Sensitivity AnalysisA sensitivity analysis has been carried out to ascertain the effect of the

    following scenarios on the major financial parameters for the Main line / Trunk

    Line. Following Table provides the analysis for parameter like Project IRR post

    tax, Minimum DSCR and the

    Average DSCR.

    Sensitivity analysis has been

    carried out to assess the

    impact of changes in the

    operating environment o

    the project on its viability

    The following

    parameters were consideredfor this:

    Particulars

    Description Project

    IRR

    DSC

    Minimum Average

    Base 12 1.31 1.83

    Case 1 Increase in the project cost by 5% 11.55 1.26 1.76

    Case 2 Increase in the variable cost of the company by 5% 11.87 1.30 1.81

    Case 3 Increase in term loan interest by 1% & WC interest 12.20 1.27 1.77

    Case 4 Benefit under income tax section 80(IA) 17.42 1.31 2.10

    Case 5 Increase in Tariff Price by 10% 13.25 1.42 2.02

    Case 6 Decrease in Tariff Price by 10% 10.69 1.19 1.64

    Case 7 Increase in revenue by 10% 13.25 1.42 2.02

    Case 8 Decrease in revenue by 10% 10.69 1.19 1.64

    Case 9 Change in gearing to 60:40 11.69 1.50 2.11

    Case 10 Decrease in interest rate for term loan by 1% & WC 11.79 1.35 1.89

    It is observed that availing benefit of Section 80 IA has a greater impact on the IRR of theproposed JHPL

    project with Project IRR Post Tax at 17.40% as compared to Base case Project IRR post tax

    at 12%.

    Further it is observed that change in tariff price and / or revenue has good

    amount of impact on the project IRR at 13.25%.

    It is also evident that, project is highly sensitive to the volume. It is therefore

    recommended that GAIL Marketing team should be ready with all consumer tie

    ups before the start of the project.

  • 8/9/2019 jhpl

    72/80

    The sensitivity analysis shows that project IRR and DSCR levels are good in respect

    to JHPL Project. However, the base case IRR and DSCR levels are robust enough to

    withstand adverse variations in critical parameters, as stated above.

  • 8/9/2019 jhpl

    73/80

    54 | P a g

    JAGDISHPUR-HALDIA PIPELINE: DEMAND ESTIMATION & TARIFF DETERMINATION 2010

    14. Conclusion&Recommendati

    onsGAIL (India) Limited, is India's flagship Natural Gas company with a turnover of overRs 24,996/- Crores

    As part of National Gas Grid (India) Limited now wishes to undertake Jagdishpur-

    Haldia Pipeline Project with total investment of around Rs 7637.33 Crore proposed

    to be funded at debt equity ratio of 70:30. The proposed Project loan is estimated

    at Rs 5346.13 Crore, for which GAIL will approach Banks and Financial Institutions

    to finance the proposed project. GAILs free cash flow is adequate to support the

    required equity contribution.

    GAIL (India) Limited have received authorization from Ministry of Petroleum &

    Natural Gas (MoP&NG) for installation of Jagdishpur-Haldia Pipeline System for

    transportation and distribution of gas from various sources like Reliance, ONGC

    from KG Basin & Mahanadi Basin respectively for meeting the gas demand of

    customers in this sector. The capacity available for this pipeline would be 32

    MMSCMD (this includes 4 MMSCMD for common carrier).

    In addition to this, as per the market projections and as estimated by GAIL, major

    customer tie ups are done in this corridor to maintain the stability and there also

    exists demand potential from various small and medium scale industrial units inand around the corridor of JHPL.

    It is recommended that GAIL should enter into long-term Take or Pay contracts

    with its prospective consumers for sale of natural gas with provision to cover

    fixed cost in case of no off-take.

    The consumer transportation tariff works out to Rs 2103.40/-MSCM to Rs

    4457.92/-MSCM (Rs 63.11/- MMBTU to Rs 133.75/-MMBTU) which is in the

    acceptable range for the consumers.

    Since gas supply arrangements for the projects are not entirely in place, it is

    suggested that GAIL enter into firm agreements before the commencement of theproject.

    Timely completion of the project is must to avoid undue cost and to improve theprofitability of GAIL.

    GAIL will be engaging respected EPC contractors and credible suppliers for

    various equipments and other components of the project as to make the

    project a viable one and complete in time.

  • 8/9/2019 jhpl

    74/80

    55 | P a g

    The economic viability of JHPL project has been examined as

    envisaged by GAIL. The tariff has been calculated based on

    PNGRB guidelines.

    Based on the appraisal exercise, it may be concluded that:

    Considering GAILs past and projected performance, the company is expectedto meet its debt

    serving obligations towards the project.

    The overall financial, liquidity and profitability parameters of the

    project are considered reasonable and satisfactory.

  • 8/9/2019 jhpl

    75/80

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    56 | P a g

    Subject to

    1. Weakness and threats encountered and impact of the various scenarios as

    analyzed under the sensitivity analysis.

    2. Availability of consumers and gas from the proposed sources

    3. Volume of gas availability based on the project requirement4. Meeting time lines of availability of gas with respect to project completion

    5. Laying & availability of Reliance pipeline from Kakinada to Haldia.

  • 8/9/2019 jhpl

    76/80

    57 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    ANNEXURE-1: ENVISAGED MARKET

  • 8/9/2019 jhpl

    77/80

    58 | P a g

    AGDISHPUR-HALDIA DEMAND ESTIMATION & TARIFF 201

    Jagdishpur-Haldia

    Capacity as per authorization: 16 MMSCMDS.No Custom Sector Location State 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 201

    Phase 1

    1 FCI Gorakhpur Fertilizer Gorakhpur UP 1.015 2.03 2.03 2.03 2.03 2.03 2

    2 HFC Barauni Fertilizer Barauni Bihar 1.015 2.03 2.03 2.03 2.03 2.03 2

    3 FCI Sindhri Fertilizer Sindri Bihar 1.015 2.03 2.03 2.03 2.03 2.03 2

    4 HFC Durgapur Fertilizer Durgapur WB 1.015 2.03 2.03 2.03 2.03 2.03 2

    5 West Bengal PowerDev.

    Power Sagardighi WB 1.000 2.000 4.000 4.000 4.000 4.000 4.

    6 DIL Fertilizer Kanpur UP 0.950 0.950 1.900 1.900 1.900 1.900 1.

    7 Bhushan Steel Steel Jharkhand Jharkhand 0.009 0.009 0.009 0.009 0.009 0.009 0.8 JMT Auto Others amshedp Jharkhand 0.012 0.012 0.012 0.012 0.012 0.012 0.

    9 Dina Iron & steel LtdDidargange

    Others Patna Bihar 0.004 0.004 0.004 0.004 0.004 0.004 0.

    10 Dadijis Steels Ltd Steel Patna Bihar 0.011 0.011 0.011 0.011 0.011 0.011 0.

    11 Balmukund Concast Others Bihita Bihar 0.003 0.003 0.003 0.003 0.003 0.003 0.12 Patwari Udyog , Patna Others Patliputra Bihar 0.004 0.004 0.004 0.004 0.004 0.004 0.

    13 Patwari Steel Pvt Ltd Steel Fatoah Bihar 0.001 0.001 0.001 0.001 0.001 0.001 0.

    14 Patwari Forgings Pvt Steel Patliputra Bihar 0.000 0.000 0.000 0.000 0.000 0.000 0.

    15 Sai Iron (India) Ltd Steel Patna Bihar 0.005 0.005 0.005 0.005 0.005 0.005 0.

    16 Shriya International Oil&

    Power Rai Bareily UP 1.214 1.214 1.214 1.214 1.214 1.214 1.

    17 Bawani Paper Mills Others Rai Bareily UP 0.012 0.012 0.012 0.012 0.012 0.012 0.

    18 Anjali Steels Steel Jaunpur UP 0.011 0.011 0.011 0.011 0.011 0.011 0.

    19 Rania Industrial Area Others Rania UP 0.083 0.083 0.083 0.083 0.083 0.083 0.

    20 Triveni Sheet Glass Others Allahabad UP 0.081 0.081 0.081 0.081 0.081 0.081 0.

    21 UP Rajya Vidyut Nigam Power Kanpur UP 0.750 0.750 0.750 0.750 0.750 0.750 0.

    22 Mohan steels Steel Unnao UP 0.500 0.500 0.500 0.500 0.500 0.500 0.

    23 Hindustan NationalGlass

    Others Rishra WB 0.090 0.090 0.090 0.090 0.090 0.090 0.

    24 Exide Industries Ltd Others Haldia WB 0.005 0.005 0.005 0.005 0.005 0.005 0.

    25 Hindustan Lever Ltd Others Haldia WB 0.005 0.005 0.005 0.005 0.005 0.005 0.

    26 ALSTOM Others Durgapur WB 0.003 0.003 0.003 0.003 0.003 0.003 0.

    27 Reckitt Benkeiser Ltd Others Asansol WB 0.007 0.007 0.007 0.007 0.007 0.007 0.

    28 Durgapur Chemicals Power Durgapur WB 0.059 0.117 0.117 0.117 0.117 0.117 0.29 La Opela RG Ltd Others Madhupur WB 0.013 0.013 0.013 0.013 0.013 0.013 0.

    City Gas Projects 0.500 0.500 1.000 1.000 1.000 1.000 1.

    Sub Total(1) 9 15 19 19 19 19 1

    Phase 2

    1 SAIL Steel Bokaro Jharkhand 0 1.067 1.067 1.067 1.067 1.067 1.

    2 WBPDC Power Katwa WB 0 1.000 2.000 2.000 2.000 2.000 2.

    3 SAIL Steel Durgapur WB 0 0.578 0.578 1.156 1.156 1.156 1.4 WBPDC Power Bandel WB 0 1.000 2.000 2.000 2.000 2.000 2.

    5 Culcutta Electric Power Kolkata WB 0 2.000 3.000 3.000 3.000 3.000 3.

    6 Durgapur Projets Ltd Power Durgapur WB 0 2.980 2.980 2.980 2.980 2.980 2.

    7 SAIL Steel Rourkela Orissa 0 0.214 0.427 0.427 0.427 0.427 0.

    Sub Total(2) 0 9 12 13 13 13 1

    Total(1+2) 9 24 31 32 32 32 3

  • 8/9/2019 jhpl

    78/80

    59 | P a g

    AGDISHPU