Date post: | 25-Jun-2015 |
Category: |
Business |
Upload: | informa-australia |
View: | 255 times |
Download: | 1 times |
Mine to Port Supply Chains: Insights into asset utilisation and waiting time
4th Annual FeTech Conference, 26-27 November 2013
Duxton Hotel Perth
26/11/2013
Jim Netterfield
2
Supply chain - road simile 1
Capacity
Flexibility HIGH-CAPACITY road tunnel characteristics • Each movement: SMALL relative to total
capacity INDEPENDENT of other
movements – minimal interference
• Infrastructure “passive” –
reseal road surface, inspect tunnel structure every few years, maintain fans on-line, change lighting off-peak, close individual lanes
• Designed for short-term PEAK loading, average loading << peak 20,000 to 50,000 movements per day
User expectation – can access infrastructure 24/7, without reference to other users (motorists) or infrastructure provider
3
Supply chain - road simile 2
Operating Rules
Constraints
Queues
Access will be determined by the infrastructure, the operating rules and, critically, the demand or usage (arrival) pattern
LIMITED-CAPACITY road tunnel characteristics • Each movement MODERATE relative to total
capacity DEPENDENT on groups of
other movements – moderate interference
• Infrastructure “passive” –
reseal road surface every few years, inspect tunnel structure every year, maintenance activity interrupts operation
• Designed for average loading,
NOT short-term peak
• 200 to 1,000 movements per day
Supply chain – rail characteristics
4
Single-track rail line
A single-track railroad = a single lane road tunnel: An empty line does not mean spare capacity, it means waiting time for
conflicting movements
Single-track railroad characteristics • Each movement LARGE relative to total
capacity DEPENDENT on each other
movement – minimal interference
• Infrastructure “active” –
repair rail surface continuously, inspect track/rail structure every few days, maintenance activity interrupts operation
• Designed for average loading, NOT short-term peak
• 10 to 20 movements per day
Supply chain – the Oakajee example
5
Oakajee rail is a single line: It has finite, limited capacity and distinct operating characteristics that equate to performance
Oakajee single-track railroad characteristics • Effectively, a long series of single lane
sections (tunnels) • Passing siding at end of each section • Queuing at every section entry, exit at
Port • More passing sidings = more sections • More sections = more stop-starts, more
capex, opex • # sections optimised for passing
opportunities x stop-starts x capex, opex
• 10 to 20 movements per day
Shared access operating model example: A stand-alone infrastructure/supply chain company
6
Responsible for providing transport logistics to iron ore customers
Supply Chain Agreements • Quantum • Timing • Performance
Port & Rail Infrastructure Provider
• Customer Management1
• Supply Chain Management2
• Operations Management3 • Asset Management3 Optional above-
rail contracts
3rd Party Operator(s)
Resources as needed
Mine Rail Port Ship Mill
Ore Sales Contracts
Train control function of SCM
Employment & Service Contracts
Inform
Owners
State
State Agreements – Special Act, leases, Statutory Authority Agreements , Economic Regulator Undertakings et al • Concession rights: Tenure, Scope, Expansion • Safety and Security • Competition Principles • Investment
Vessel ordering
function of OSC
Port & Rail Infrastructure
Provider
Mine
1 Mine 2 Mine load-out to ship 3 Port/Rail Company Assets
Infrastructure/supply chain company has to balance the requirements of customers, owners, the State and its agencies
Typical iron ore supply chain system
7
Exploration Resource Definition Mine Planning
Drill & Blast Load & Haul Process Stockpile & Load-out
Rail
Dump Stockpile Reclaim Ship-load
Shipping Steel Mill
Mine Development
Mine Operations
Rail
Port
Port & Rail Infrastructur
e Provider
Shipping
Mine
Mine/Mill
Mine Mine
Mine/Mill Mine/Mill
Meeting all of the objectives requires the provision of a system, the components of which are supplied or managed by various parties
8
Manage by segment
Improve with Improvement program (eg 6s, Lean)
Measure with Key performance Indicator (productivity, utilisation, reliability, speed, etc...)
System – an integrated set of elements, subsystems, or assemblies that accomplish a defined objective. These elements include products/plant (facilities, hardware, software, firmware), processes, (information, techniques, services) and people.*
Inputs Outputs
•Two distinguishing criteria •Emergence - formation of
complex but regular patterns from the interaction of the many simple parts of a system c.f. complicated and chaotic (no regularity) •Self-organising - closely
related to emergence and refers to the ability of the system to organise itself. The emergent features of the system appear spontaneously. There is no one (entity) in control of the (whole) system. (eg; telecoms, power supply)
Model system to understand performance c.f. “reductionism” – breaking systems down into component parts to understand performance Australian Academy of Science, A quiet Revolution – the Science of Complex Systems , Oct 2006
The iron ore supply chain – a complex system
*International Council on Systems Engineering (INCOSE), Systems Engineering Handbook, January 2010
An iron ore supply chain is a complex system, and this requires an adaptive approach by stakeholders
Information
Supply chain performance – Systems engineering approach
9
• “Capacity” is a throughput rate – units of output (or input) per time frame through a system
• “System” = resources and information to “process” inputs into outputs
• “Process” = operations to transform, convert, combine, transport etc…
System
Inputs Outputs
System determines • Speed • Characteristics (e.g. quality, reliability) • Cost
Understanding the nature of the system enables understanding of the outputs (the “product”)
Utilisation of capacity
10
Unit cost
$/t [Z]
Annual costs
$m 800 + 5 * [Y]
Fixed Cost (Capex, Labour & Admin)
$m 800 pa
Variable cost (Opex)
$m = $5/t * [Y]
Throughput
[Y] mtpa
Choke capacity
50 mtpa
Utilization, %
[X]
All numbers indicative, for illustration purposes only
Utilisation X (%)
Throughput Y (mtpa)
Unit Cost Z ($/t)
70% 35 28
80% 40 25
90% 45 23
11
Utilisation of capacity
Choke Capacity, mtpa
50 m ±
Tonnes per day
144,000 ±
Tonnes per hour
9,000 ±
Op hours per day
16 ±
Delay hours per day
8 ±
Op days per year
350 ±
Down days per year
15 ±
Choke capacity by deterministic method: hourly, daily, annual
Typical for 160,000 DWT vessel
Speed factors • Rates • Delays
Rate factors • Stockpile geometry • Ore flow properties • Vessel • Terminal specification
Delay factors • Process • Vessel • Terminal
Operating day factors • No vessels arrived (berth vacancy) • No product available • Weather/ Wave • Scheduled Maintenance
12
Utilisation of capacity
Throughput, mtpa
45 m ±
Choke Capacity, mtpa
50 m ±
Tonnes per day
144,000 ±
Tonnes per hour
9,000 ±
Op hours per day
16 ±
Delay hours per day
8 ±
Op days per year
350 ±
Down days per year
15 ± Utilisation, % 90%
Queue time
System performance Throughput & Queue Time
0
100
Utilisation, %
Queu
e Tim
e ∞ Demand factors
• Level • Variability Service factors • Speed • Rules • Variability
Speed factors • Rates • Delays
Operating day factors • No vessels arrived (berth vacancy) • No product available • Weather/ Wave • Scheduled Maintenance
Rate factors • Stockpile geometry • Ore flow properties • Vessel • Terminal specification Delay factors
• Process • Vessel • Terminal
13
Utilisation of capacity
Target Utilisation
90%
Demand Vessels per day
0.81
Server Capacity Vessels per day
0.90
Tonnes per day
144,000
Tonnes per year
50m
Days per year
350 Tonnes per vessel
160,000
0 100
Utilisation, %
Queu
e Tim
e
∞ Random arrivals
Semi-scheduled arrivals (managed demand)
Variability in demand pattern and service sets the curve to read queue time from
Utilisation determines how far across the curve to read up to queue time
/
/
/
14
Random queue characteristics
• 35 mtpa demand@ 160kt/vessel = 222 ships • Service rate = 0.9 vessels per day (50 mtpa) • Arrival rate = 0.63 vessels per day (70% utilisation)
• 53% of days = no vessel arrive!
Queue can reduce (> half year)
• 13% of vessels arrive
same day as another (2,3,4, or 5 vessels arriving same day)
Queue builds up (< half year)
• Queue average = 1.6
vessels
15
Random queue characteristics
• 45 mtpa demand@ 160kt/vessel = 285 ships • Service rate = 0.9 vessels per day (50 mtpa) • Arrival rate = 0.81 vessels per day (90% utilisation)
• 44% of days = no vessels arrive!
Q can reduce (< half year)
• 20% of vessels arrive
same day as another (2,3,4, or 5 vessels arriving same day)
Q builds up (> half year) • Q average = 8.1 vessels
16
Capacity Parameters
Description Comment
1. Level of Demand vs. Capacity
Allowable level of demand on the infrastructure, taking into consideration the associated vessel waiting time
Strategic choices are “high” to target lowest possible capex amortisation unit cost or “low” to allow for new entrants, and “spare” capacity to allow for variability in demand and service
2. Vessel Arrival Pattern
The manner in which vessels present at the Port (may vary from random, where there is no vessel coordination, through to highly managed vessel arrivals)
If ‘high” utilisation is chosen, then arrival pattern must be managed to avoid high demurrage. If random arrival pattern is allowed for, then level of demand must be kept low if demurrage is to be avoided
3. Production Rates & Variability
The material handling rates through the infrastructure of the supply chain
Given, the demand profile above (1 and 2 above) then service rate and variability of service rate is the driver of performance. Being able to manage root causes of poor performance across boundaries is critical, as well as being able to offset intra-system variability.
4. Operating Days
Calendar days less idle days (no vessel available to load), less other systemic down days (scheduled maintenance, weather, holidays not worked)
The number days of idle time in the system, directly relates to the desired level of utilisation (or demand) on the infrastructure. If demand is set “low”, then berth vacancies must arise. If berth vacancies are to be avoided, then “demand” must be set “high”. Even at “high” utilisation, idle days will far outweigh other down days.
Parameters for supply chain management
17
Strategic options for determining utilisation
High wait time
High unit cost due to high wait time costs
and missed throughput due to higher vacancies
Low wait time
Lowest unit cost due to high throughput and low wait time
Low wait time
High unit cost due to low throughput
Low wait time
High unit cost due to low throughput
Not managed Managed
Demand management
“Spare” capacity lost to waste (e.g.,
declining speed or rates) or
incremental demand increase
High
UTILISATION
Low
Key points
18
Supply chains work as a complex system, even if the system is not recognised fully
by its stakeholders
The physical relationships that drive the outcomes of the complex system are
universal and immutable
Any contractual relationship set out between parties within a complex system, at
best, can only avoid making things worse than if a single entity operated. At worst,
will reduce performance or increase total costs
Playing $800m waiting game
The number of coal ships queued
at Dalrymple Bay and Hay Point
coal terminals has skyrocketed to
90, as demand for coal returns.
This time last year, just 19 ships
queued for the ports.
Kate Bastable | Daily Mercury |
14th November 2009
END