+ All Categories
Home > Documents > JIT Final_Snehal 11E04

JIT Final_Snehal 11E04

Date post: 14-Apr-2018
Category:
Upload: hemant-komte
View: 213 times
Download: 0 times
Share this document with a friend

of 12

Transcript
  • 7/30/2019 JIT Final_Snehal 11E04

    1/12

    JUST

    IN

    TIME

    BySnehal Adsule

    Roll no. 11-E04

  • 7/30/2019 JIT Final_Snehal 11E04

    2/12

    Introduction

    Ford X

    Invented byTaiichi Ohino

  • 7/30/2019 JIT Final_Snehal 11E04

    3/12

    JIT Objectives Zero Inventory.

    Zero lead time.

    Zero failures.

    Flow process.

    Flexible

    manufacture. Eliminate waste.

  • 7/30/2019 JIT Final_Snehal 11E04

    4/12

    Implementing JIT Starts with a company shared vision of where it

    is and where it wants to go

    Management needs to create the rightatmosphere

    Implementation needs a designated Champion

    Implement the sequence of following steps

    Make quality improvements

    Reorganize workplace

    Reduce setup times

  • 7/30/2019 JIT Final_Snehal 11E04

    5/12

    Implementing JIT - continued Reduce lot sizes & lead times

    Implement layout changes

    Cellular manufacturing & close proximity

    Switch to pull production

    Develop relationship with suppliers

  • 7/30/2019 JIT Final_Snehal 11E04

    6/12

    The Major Misconceptions of

    JIT JIT is Only an Inventory Control System

    It is a Method to Push Inventory Backto the Supplier

    JIT is a Quality Control Program

  • 7/30/2019 JIT Final_Snehal 11E04

    7/12

    Advantage Minimum stock

    holding cost

    Eliminates waste Less Working Capital

    Elimination of over

    production Ease of

    incorporatingchanges.

  • 7/30/2019 JIT Final_Snehal 11E04

    8/12

    Limitations Zero tolerances for mistakes.

    Higher dependency on suppliers

    Unexpected demand increase cannot befulfilled

    Higher transaction cost

    Detrimental effects on the environment

  • 7/30/2019 JIT Final_Snehal 11E04

    9/12

    JIT is a suitable production

    system when: Have steady production of clearly defined

    standard products A reasonable number of units made A high value product Have flexible working practices and a

    disciplined workforce Short setup times on machines Quality can be assured, e.g. zero defects

    either though good working practices orthough a cost penalty

  • 7/30/2019 JIT Final_Snehal 11E04

    10/12

    General Motors General Motors (GM) in the USA has (approximately) 1700 suppliers

    who ship to 31 assembly plants scattered throughout the continentalUSA. These shipments total about 30 million metric tons per day andGM spends about 1,000 million dollars a year in transport costs onthese shipments (1990 figures).

    JIT implies frequent, small, shipments. When GM moved to JIT therewere simply too many (lightly loaded) trucks attempting to deliver toeach assembly plant. GM's solution to this problem was to introduceconsolidation centersat which full truckloads were consolidated fromsupplier deliveries.

    This obviously involved deciding how many consolidation centers to

    have, where they should be, their size (capacity) and which suppliersshould ship to which consolidation centers (suppliers can also still shipdirect to assembly plants).

    As of 1990 some 20% by weight of shipments go through consolidationcenters and about 98% of suppliers ship at least one item through aconsolidation centre.

    All this has been achieved withoutsacrificing the benefits of JIT.

  • 7/30/2019 JIT Final_Snehal 11E04

    11/12

    List of Companies that use

    just in time (JIT) Harley Davidson

    Toyota Motor Company

    General Motors

    Ford Motor Company

    Manufacturing Magic Hawthorne Management Consulting

    Strategy Manufacturing Inc.

  • 7/30/2019 JIT Final_Snehal 11E04

    12/12

    Thank You


Recommended