Date post: | 02-Nov-2014 |
Category: |
Documents |
Upload: | barry-ross |
View: | 154 times |
Download: | 15 times |
John Barker Construction Ltd v London Portman Hotel Ltd
(1996) 83 BLR 31: Guideline on whether the
Architect/Contract Administrator has granted a fair and
reasonable extension of time
By Leonard Kok
1.0 The law relating to Extension of Time
1.1 Before embarking on a critical review of the assessment on the quantum
and validity of EOT being granted, it is pertinent to state briefly the current
state of the law as applicable. It was clearly stated in the English case of
Percy Bilton Ltd v Greater London Council (1982) 20 BLR 1 by Lord
Fraser: “….. The general rule is that the main contractor is bound to
complete the work by the date of completion stated in the contract. If he
fails to do so, he will be liable for liquidated damages to the employer.
That is subject to the exception that the employer is not entitled to
liquidated damages if by his acts or omissions he has prevented the main
contractor from completing his work by the completion date. "
1.2 Therefore, a Contractor is under a strict duty to complete on time and
failure to do so leaves him liable to damages either liquidated or general
according to the terms of the contract except to the extent that he is
prevented from doing so by the Employer or is given relief by the express
provisions of the contract for an extension of the time of completion.
Where an act of prevention by the Employer causes a delay to completion
and that delay is not covered by an extension of time provision in the
contract and/or where the extension of time provision have not been
properly administered or have been misapplied, time is then put at large
and the Contractor's obligation is to complete within a reasonable time.
Only when the Contractor has failed to complete within a reasonable time
would he then be liable for general damages.
1
1.3 The extension of time clause has the following purposes:
(i) to retain the Contractor's obligation to a defined time for completion
after dealing with specified causes of delay ;
(ii) to preserve the Employer's right to liquidated damages against acts of
prevention;
(iii)to give the contractor relief from his strict duty to complete on time in
respect of delay caused by designated events which are outside the
control of both the Employer and the Contractor
1.4 As indicated under paragraph 1.3 (i) and (ii) above, it is the Employer and
not the Contractor who would benefit from and therefore has most need of
extension of time provisions in that the courts would not uphold liquidated
damages where the Employer has prevented completion on time unless
there is an express provision in the contract to extend time for the
Employer's default.
1.5 However, under paragraph 1.3 (iii) above, it is the Contractor who has the
most to benefit from such delay events caused by neutral circumstances
for which he is given relief from his otherwise strict duty to complete on
time.
1.6 The phrase "the Contractor shall forthwith give written notice" does not
mean that an application for an extension of time is a condition precedent
to any extension being granted. The Contractor's obligation is to give
notice only of delay and there is an independent duty on the part of the
Architect as the contract administrator to consider the Contractor's
entitlement to an extension whether or not an application has been made
particularly when the Employer has caused any delay to completion. It is
important to understand that the facility for the Architect to grant
extensions if they fall due is essential in order to maintain the extension
provisions. Otherwise, if an application of the Contractor was a condition
precedent to an extension, it would be at the option of the Contractor to
determine whether or not the provisions were effective, and by choosing
2
not to apply for an extension to cover for acts of prevention the Contractor
could render the liquidated damages provision become inoperative. This
surely could be detrimental to the Employer.
1.7 Under the Malaysian Standard Form of Contract issued by Pertubuhan
Akitek Malaysia (PAM ) provided by Clause 23 thereof, if the Architect is of
the opinion that any of the events stated by the Contractor to be the
cause of the delay is a relevant event which entitled the Contractor to an
extension of time and that completion of the Works is likely to be delayed
thereby beyond the completion date, then he is required to give the
Contractor an extension of time by fixing such later date as the extended
completion date as he then estimates to be fair and reasonable. In
considering whether a relevant event is likely to cause delay for the Works
beyond completion, the Contractor need to prove that the variations and
late information etc. relied upon by the Contractor did cause delay
because the affected activities were on the critical path and on that
account did cause delay.
1.8 There are legal cases to suggest that where the Architect acts he must do
so in accordance to the contract, which requires him to grant a fair and
reasonable extension of time. What it means is that even if the architect
acts fairly his certificate may become invalid if it can be shown that he has
failed to apply the contractual machinery to his decision making process.
In the English case of John Barker Construction Ltd v London
Portman Hotel Ltd (1996) 83 BLR 31 which involves the refurbishment of
a multi-storey hotel in London, it was held by the judge Mr. Recorder
Toulson QC that it was an implied requirement of a valid decision under
the extension of time clause 25 that the architect should act fairly and
lawfully and that such a duty is consistent with the architect's quasi-arbitral
position, and the courts are used to applying a fairness test when
reviewing a decision of a person with quasi- arbitral powers. [*B9-26]
1.9 On the evidence it was ruled that the effect of the architect making an
impressionistic assessment instead of a logical analysis of delay rendered
3
his extension of time fundamentally flawed. The judge came to this
conclusion based on the following evidence of the architect Mr. Miller as to
how he came to his assessment of a fair and reasonable extension of
time:
Generally
(1) He listed 21 items considered to be relevant events contributing to
an extension of time, and concluded that an extension of 9 days
should be given for floors 9 to 11 and of 7 days for floors 2 to 8.
(2) He looked at the job in three section, bedrooms (or guest rooms),
bathrooms and corridors, on the basis that the workforce could get
on in each one of those three areas without being impeded by what
was happening (or not happening) in either of the others. He said
that it was apparent that the area of greatest delays was the
bathrooms, so he arrived at his assessment of a reasonable
extension by adding the individual periods, which he considered
allowable for each relevant event affecting the bathrooms.
(3) He said that he had done an analysis of the contractor's claim in a
methodical way, taking into account the contractor's stated
programme, the progress of the works at the time and the effect of
the relevant events on subsequent works.
However, there is not documentary evidence to support Mr. Miller's
evidence that such an exercise was conducted or to indicate what form it
took. When it came to the details of individual items, Mr. Miller was in
difficulty in recalling how he assessed the periods of time, which he did.
1.9 The following passages, which appeared in the judgment of Mr. Recorder
Toulson QC, indicated the incorrect approach taken by the architect Mr.
Miller in the assessment of a fair and reasonable extension of time:
(a) Item 9: The cutting of pockets in bathroom screeds to accommodate legs
of baths and bath waste
For example, he was right in treating this item a relevant event as the
problem did not manifest itself at the time when a sample bathroom was
4
built, and the contractors were not to blame for the late emergence of the
problem. But how he allowed 2 days for it was never clear until the case
came to trial. The work had to be carried out with percussion tools, and it
was done by sub-contractors. It began on 14 July 1994 and continued until
9 September 1994. It took about 4 days per floor and disrupted the second
fix plumbing, with consequent serious delaying effect on the completion of
the bathrooms. In the opinion of the plaintiff's expert it did not ultimately
delay the overall completion of the works, but that was because greater
delay was caused by matters outside the bathrooms, which were the
corridors.
On the basis that the critical path lay through the bathroom, Mr. Miller
explained the 2 days in oral evidence under cross examination by saying
that this was not an allowance for the time which the work took, but only
for the time when the contractors were unable to do it, because the hotel
objected at certain times to the noise caused by the Kango hammers used
to break the screed. However, this contradicted his reference to CV 67 JD
on his annotated copy of his extension of time report, his letter dated 2
February 1995 to the contractors setting out the relevant events which he
had taken into account, and his witness statement, which all suggest that
he intended to allow for delay caused by having to do the work, rather than
merely for the time it could not be done.
It is not thought that Mr. Miller in giving his explanation for his assessment
of 2 days was trying to mislead, but it seems an improbable explanation
and, if correct, it is irrational. Even the defendant's counsel accepted that it
was not rational to allow 2 days for the item when the work could not be
done. Either the item should have been disallowed or it should have been
allowed and a proper assessment made of its consequences.
(b) Items 7,8 and 27: Redecoration of Corridor Walls
At the time of tender, the contractor was required to: remove the old
wallpaper; wash the walls to remove all adhesive and sand; (if necessary)
score the old plaster to provide a key for the wallpaper adhesive; wash the
5
wall once more; and (where necessary) fill and rub down the old plaster
surface until flat and smooth. However, when the wallpaper was removed,
it was found that underneath was only a very thin plaster coat, which had
been sprayed on. This made it impossible to achieve a truly flat and
smooth finish. Parts of the plaster were also live, and places plaster came
away with the wallpaper. In the event the architect required the contractor
to patch the existing defective plaster before redecorating but refused to
give an EOT on the basis that he thought he was asking the contractor to
do no more than to " render the old plaster surfaces flat and smooth"
before decorating which he maintained was as required by the bills
description. The judge is satisfied that Mr. Miller misdirected himself in not
finding the change in preparation of the plaster to be relevant event
saying: " In his witness statement, Mr. Miller said that the specification
required the wall surfaces to be filled and rubbed down until perfectly flat
and smooth, implying that there was no variation. The walls, when
prepared, were not perfectly smooth as the specification required, a point
confirmed by the defendant employer's project manager Mr. Baillie in his
written witness statement and in his oral evidence. The discovery of the
true condition of the plaster meant that the defendants, and the architect
on their behalf, were faced with a choice either to instruct extra works in
order to make achievement of the specification practicable or to authorize
some other solution to overcome the imperfections in the walls. They
chose to order a variation of the contract. Mr. Miller accordingly gave
instructions, on 26 August 1994, for the walls to be stripped, cross-lined
and re-papered. Mr. Miller accepted this item 7 as a relevant event and
allowed an extension of 3 days .It is not clear though how he arrived at the
figure of 3 days. It is the evidence of Mr. Downey; the contractor's site
agent who described the work involved and estimated that it took about 5
days per floor, although there would have been overlapping. The work
came at a late stage of the contract and involved interference with the
finishing trades. The time ultimately spent by the plasterers was
6
approximately the same as the period allowed for in the contractor's
programme at the time of the acceleration agreement, but hold up was
caused by the delay in determining what was to be done. In any case this
did not affect Mr. Miller's total award because he considered that the
critical path was through the bathrooms and not through the corridors.
Mr. Miller subsequently admitted in cross-examination that if the contractor
did not have clear instructions how to deal with the walls before 20 July
1994 and the instructions on preparation were a relevant event, it would
be necessary to add to his extension of time assessment.
Based on all the above evidence the judge is satisfied that Mr. Miller's total
allowance of 3 days for items 7,8 and 27 bore no logical relation to the
delay caused by those items, except on the false premise that because
the contract provided for the walls to be filled and rubbed down until
perfectly flat and smooth, these items were not to be regarded as involving
any significant additional work. Moreover, Mr. Miller did not examine the
impact, which they had on the contractor's planned programme, coming
when they did. Had he done so, he could not have concluded that the
critical path lay simply through the bathroom.
(c) Items 29 and 5: Fire stopping
This work was provided by way of a provisional sum which was defined as
' Fire stopping bathroom riser ducts where they pass through floor slabs. '
The contractors did not contemplate the nature or magnitude of the work,
which was subsequently instructed to be done. The contract drawings
indicated more fire stopping, but insofar as the bills were erroneous or
deficient, any correction would be a deemed variation under clause 2.2.2.2
of the general conditions of contract.
The architect rejected an application for an EOT for the effect on time on
an increase in fire stopping (measured as a series of provisional sums in a
bill of quantities under JCT 80, from a provisional sum of 6,000 pound
sterling to a final cost of 35,000 pound sterling) on the grounds that as it
7
was required by the Building Regulations, in conformity with which the
contractor was contractually obliged to build.
There were in theory various ways of achieving the required integrity of the
shaft wall. It was for the architect (in conjunction with the mechanical and
electrical consultants) to specify the necessary design. The changes,
which occurred after the acceleration agreement of 11 July 1994, were
variations or deemed variations, which on the evidence of Mr. Taylor, the
contractor's contracts manager had a delaying effect. They were then a
relevant event that Mr. Miller was required to take into account. Therefore,
Mr. Miller's rejection of item 29 as a relevant event on the ground that the
contractors had full knowledge of the requirements for maintaining the
one-hour integrity of the shaft wall shows an error of law in relation to the
respective responsibilities of the contractor and the employer (through the
design team).
Mr. Miller accepted item 5 as a relevant event and allowed 2 1/2 days,
because he estimated that at the time, which it would have taken Gerco
the specialist sub-contractor to do the work. It had to be done from the
inside the bathroom duct and was fiddly work. There were sixteen
bathrooms per floor. Mr. Taylor's evidence was that the work took Gerco
10 days, doing one floor per day. Mr. Miller said that his figure of 2 1/2
days would have been based on assuming the availability of a sufficient
team to complete the work at that time, but he could not recall what
assumption he had made about the size of the team.
(d) Judgment
The crux of the judgment of this case is when Mr. Recorder Toulson QC
sitting as an Official Referee said this:
'I accept that [the architect] believed, and believes, that he made a fair
assessment of the extension of time due to the Plaintiffs [contractor]. It is
fairly apparent that the Defendants were concerned by the overrun of the
contract in time and costs, and I have no doubt that [the architect] was
conscious of this, I believe also that he endeavoured to exercise his
8
judgment independently. However, in my judgment his assessment of the
extension of time due to the Plaintiffs [contractor] was fundamentally
flawed in a number of respects, namely:
(1) [The architect] did not carry out a logical analysis in a methodical
way of the impact, which the relevant matters had or were likely to
have on the Plaintiffs' planned programme.
(2) He made a impressionistic, rather than a calculated, assessment of
the time, which he thought, was reasonable for the various items
individually and overall. (The Defendants themselves were aware of
the nature of [the architect's] assessment, but decided against
seeking to have any more detailed analysis of the Plaintiff's claim
carried out unless and until there was litigation.)
(3) [The architect] misapplied the contractual provisions, as more
particularly set out above. Because of the unfamiliarity with SMM 7
he did not pay sufficient attention of the content of the bills, which
was vital in the case of a JCT contract with quantities.
(4) Where [the architect] allowed time for relevant events, the
allowance, which he made in important instances (such as the
items relating to the walls or the cutting of pockets in the bathroom
screeds), bore no logical or reasonable relation to the delay caused.
I recognise that the assessment of a fair and reasonable extension
involves an exercise of judgment, but that judgment must be fairly and
rationally based.
All in all, I am satisfied that the Plaintiffs [contractor] have established that,
although there was no bad faith or excess of jurisdiction on the part of the
architect, his determination of the extension of time due to the Plaintiff was
not a fair determination, nor was it based on a proper application of the
provisions of the contract, and it was accordingly invalid. '
(e) Conclusions
The conclusions that can be drawn from this case are as follows: -
9
(1) The architect is appointed as agent of the employer and he has an
obligation to act fairly in certifying extensions of time for delay.
(2) There can no longer be any reasonable doubt that it is not acceptable
for the architect to determine extensions of time by instinct alone.
They must be dealt with fairly and reasonably, with proper calculations
and logical analysis based on the contractual provisions. There was
cogent evidence that there were matters, which caused delay, and in
not taking them into account when granting his extension of time, the
architect failed to take into account relevant matters.
(3) The effect of delay to a float activity has changed it into a critical
activity. This came about when the contractor had programmed two
paths of construction sequence: one through the corridor
refurbishment and one through the bathroom refurbishment of a multi-
storey hotel. Originally, a path through the bathrooms was planned to
be the critical path, with the path through the corridors in float.
However, a delay in giving instructions as to what to do about repairs
of defective plaster, necessary before redecoration could commence,
between June 1994 and August 1994 had radically altered the
construction logic or sequence and delayed the corridors float path to
such an extent that by 12 July 1994 which was towards the end of the
contract, the redecorations to the corridors became critical activities
and all the work to the bathroom was then in float.
(4) For provisional sums for defined work the contractor will be deemed
to have made due allowance in programming the Works so that the
execution of work under this kind of provisional sum (provided it is
within the value of the provisional sum) can never provide grounds for
an EOT. If any of the information for such "defined" provisional sums
required by SMM7 rule 10.3 is not given in the bills, then a variation
instruction to correct that omission would be needed. The omission of
such information thus renders the sum an "undefined provisional sum"
and then by SMM7 rule 10.6, the contractor is deemed not to have
10
made any allowance in programming, planning and pricing
preliminaries for that provisional sum irrespective of what it is called.
(f) Case application
The principles of law derived in the John Barker Construction case will
be applied to review whether the determination of extension of time by the
Architect or any Contract Administrator named in the contract is fair and
reasonable.
11