Date post: | 21-Apr-2017 |
Category: |
Business |
Upload: | informa-australia |
View: | 132 times |
Download: | 0 times |
Goldwind’s Experience in developing Wind/Solar hybrid generation in Australia
2nd Annual Large Scale Solar Conference3-4 April 2017
2
The Presenter – John Gardner
•B. Eng (Hons) University of Tasmania
•Previously employed in mining and materials handling industries.
• Involved in the wind industry for ~15 years.
• Involved in;
Tower Manufacture & Wind Farm Contractor (6 years at Keppel Prince)
EPC Wind Farm construction delivering projects to Energy Retailers and Developers (3 years at Suzlon)
Developer & EPC Constructor (6 years at Goldwind)
3
Contents
• Who is Goldwind and Why?
• Background / Comparison between projects
• Expected Advantages of Co-Location
• Gullen Solar Project Description
• White Rock Solar Project Description
• Comparison of Time of Day Generation and Curtailment
• Summary Comparison
• Key Learnings
4
Company overview
18 years Established in 1998, Goldwind is China’s pioneer in wind energy
+31 GW Goldwind has more than 31 GW of wind turbines installed globally
+22,200 units More than 22,200 WTG installed, including 17,856 PMDD units
USD 8 billion USD 8 billion in total assets (2015)
2 IPOs Goldwind is listed on the Shenzhen and Hong Kong stock exchanges
6,000 employees 6,000 employees globally, with more than 800 in R&D
Top 3 Globally Top 3 OEM in 2015
1st in China China’s leader in newly installed and cumulative capacity in 2015
Who is Goldwind?
Our history
• As one of China’s wind energy pioneers, Goldwind has led the growth of China’s renewable
energy industry
• As China’s demand for energy has increased, so has its need for clean and reliable power -
Goldwind has worked tirelessly to provide wind energy solutions
• Goldwind has steadily increased its international presence in line with its mission of providing
clean energy solutions for the world
1998-2006
Goldwind
Establishment
& Development
2007-2010
Rapid Growth &
Dynamic Change
1986-1996
First Research
into Wind
2011-Today
New Era &
Industry
Restructuring
1998 2006 2010 20161986
2015 China Market Share
Newly Installed Capacity
Competitive position: Goldwind is 1st in China and 1rd globally
2015 Global Market Share
Newly Installed Capacity
Goldwind14%
Vestas13%
GE Wind10%
Siemens5%
Gamesa5%
Suzlon 5%
United Power
5%Mingyang4%
Envision5%
CSIC3%
Other30%
Source: CWEA,BNEF
Goldwind, 25.2%
United Power, 10.0%
Envision, 8.2%
Mingyang, 8.2%
CSIC, 6.8%Sewind,
6.3%
XEMC, 4.9%
DEC, 4.5%
Windey, 4.1%
Sany, 3.1%
Others, 18.8%
8
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
New Installed (MW) 3.6 13.8 25.5 39.6 131.55 445 830 1145 2709 3735 3600 2522 3750 4434 7749
Cumulative Installed (MW) 3.6 17.4 42.9 82.5 214.05 659 1489 2634 5343 9078 12678 15199 18950 23384 31133
0
5000
10000
15000
20000
25000
30000
35000
Goldwind’s annual & cumulative installations 2001-2015
2013 Goldwind is ranked in the Top-500 New Energy
Companies by the China Institute of Energy Economics
Chinese Government’s Pioneer Enterprise of National Quality
Control Award
Goldwind has been recognized around the world for its pioneering work
Twice selected as one of MIT Technology Review’s 50 Most
Innovative Companies
Placed 3rd in the Most Innovative Chinese company category
One of Intellectual Asset Management’s Intellectual Property
Champions of China
2011 African Wind Project of the Year awarded to Goldwind’s
Adama Wind Farm in Ethiopia
Europe
178MW
China
South America
North America
449MW
74MW
31,133MW
185MW
Africa
51MW
Rest of Asia
240MW
Australia
Goldwind has a global footprint of 17 countries
covering all six continents
Regional Center
Sales Office
Update: 2015
Australian Presence of Goldwind
•Two fully owned subsidiaries of Goldwind Science and Technology were established in late 2009:
–Goldwind Australia Pty Ltd - Wind Turbine Supply, EPC, O&M
–Goldwind Capital Australia Pty Ltd - Goldwind’s Australian Investment Company
•Experienced Australian Team
–~75 employees, including site based operations and construction teams
–Offices in Sydney & Melbourne
•3 Projects
–Mortons Lane Wind Farm 13 x 1.5MW turbines will be installed in Western Victoria later this year
–Gullen Range Wind Farm , 73 wind turbines, Non-Recourse Project Financed. Completed 2014
–White Rock Wind Farm. 70 wind turbines, 175 MW, Merchant, in construction.
•Project Development Activities
–Market entry strategy & buffer against market fluctuations
11
Why is Goldwind involved in Solar?
• We believe solar/wind hybrid power plants make sense
• Manufacturing Solar Inverters at our Wind Turbine Converter Factory (eTechwin)
• Add value to existing developments
• Build on our expertise in project development and operations and maintenance.
• Utilise resources during the lean ‘Abbott’ years.
12
Comparison of Gullen Solar & White Rock Solar at Solar Project
Commencement
13
Gullen Solar White Rock Solar
Wind Farm Status at Solar Farm
Development & Planning
Construction Complete Construction Not Started
Characterisation of Region Grazing and Lifestyle Grazing and Cropping
Community Experience in similar
large scale development
Prior experience in large scale
renewables development (Wind)
Nil
Land Tenure Owned by a Goldwind Company,
leased to neighbour for grazing
Owned by wind farm landowner,
leased to White Rock Solar Pty
Ltd
Easements for Connection 1 6 (all wind farm landowners)
Community/Neighbour Relations Sensitive. Difficult history. Good, Supportive
Project Location < 3 hrs from Sydney CBD ~ 7 hrs drive from Sydney CBD
~ 4.5 hrs drive from Brisbane
Project Development Phase
• Use existing environmental studies
• Build on community engagement
• Possible add-on to existing PPA & Finance
• Use existing landowner relationships
Savings achieved by sharing existing
infrastructure
• Grid Substation & Switchyard
• Roads
• Buildings
Complimentary generation allows improved
utilisation of connection assets
Operational Savings
• Use wind farm maintenance staff
The Expected Advantages of Co-location
14
Copyright © Goldwind Science & Technology Co., Ltd
Sources of Cost Savings from Co-location
15
Infrastructure Savings by
Sharing:• Access tracks
• Buildings
• Communications / Scada
• Substation
Grid Connection Savings:• Stronger shared transmission
connection
• Less reactive plant
• Grid negotiation mostly complete
Development Savings• Existing knowledge
• Developed engagement plans
• Additional benefit for landowners
Stand Alone
66kV
Stand Alone
22kV
Build Wind
then build Solar
Build Wind &
Solar together
Infrastructure Costs Grid Connection Costs Development Costs
Key Facts Gullen Range Wind & Solar Hybrid
16
175.5 MW Total Generation• 165.5MW wind existing• 10 MW (AC) solar
30km northwest of Goulburn
Connection to Transgrid 330kV transmission system via Wind Farm 33/330kv Substation
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
En
erg
y Y
ield
(G
Wh
)
High wind generation during Winter months at Gullen Range
Wind
Solar
Annual and Diurnal Complimentary Generation
17
• Gullen wind peak output is in winter– Solar is lower but
still requires export capacity at greater than the substation
was originally intended for.
• Total grid output needs to be able to handle the combined
export.
• Gullen wind farm output peaks during the middle of the
day – this is not the case for many windfarms.
• If the grid at Gullen was constrained then this would have
caused issues
Av
era
ge
op
utp
ut
Win
d (
(MW
)
hour
Wind+Solar Wind Solar
0
20
40
60
80
100
120
140
160
180
200
0% 20% 40% 60% 80% 100%
Gullen Range Wind/Solar Hybrid vs. Transmission Limit
Wind + 11 MW Solar
Transmission Limit
Likelihood of >100MW 20%
Curtailment Analysis of Gullen Range
18Gullen Range grid capacity limited by 90 MVA transformer size (1 of 2)
Gullen Range Community Considerations
19
• Community attitudes well known. Difficult history.
• Wind Farm construction is disruptive to community. Residual issues may bepresent.
• Developer needs to consider existing Wind Farm/ Community relationship as wellas the future relationship of the solar project.
• Ability to involve the community in the site selection process can be beneficial.
• Timeline for community consultation is uncertain when seeking to achieveagreement. Arena timeline is fixed*.
Community Engagement
20
• When a site had been selected Goldwind entered aninform and consult engagement process
• Unrealistic to think that the community would considerthe solar as a separate project. Same developer.
• Concern regarding further development – DevelopmentFatigue
• Extensive consultation via numerous face to facemeetings two public consultation days were undertakenin the local village hall
Community consultation process
21
• Goldwind unwilling to progress project without community support
• Community made clear that they would expect financial incentives to providesupport
• A budget for neighbour agreements identified – not normal in solar industry
• Community group was informed of budget, options and allowed to proposealternative ways to distribute funds – moving engagement right up to empower.
• The group did not deliver a solution but did ensure wider community felt fullyconsulted
Gullen Range Landowner Challenges
22
• For a ‘bolt on’ hybrid there are limited places to locate the facility and stillgain advantage of infrastructure
• Existing easements are likely to be specifically for the wind farm
• Landowners are aware of the project constraints of location and time andhave just been through very disruptive construction process.
• Project proponent does not control the timeline when negotiating landdeals.
• Relations between wind farm hosts and neighbours can be strained,particularly through the construction of the Wind Farm
• Complex legal documents required to implement solar farm onto wind farmleases and easements
Gullen Solar Site Options
23
• Following initial consultation 4 siteswere considered of which 2 wereconsidered realistic options
• The two options left had differentcommunity issues and impacteddifferent neighbours
• Environment and Cultural Heritageissues differed
• Photo montages developed for newsite
• Further individual meetings set up withnear neighbours
• Further Community information dayheld
Gullen Solar Planning Process
24
• Development process for renewable energy projects is well understood, butpotential challenges arise through successive development proposals in a smallcommunity.
• Change in site location resulted in a lot of rework of planning documents
• Legacy issues regarding the wind farm process and planning issues. Council opposedthe Wind Farm.
• Early engagement with council helped to build on existing relationship.
• Agencies not familiar with solar farm environmental impacts, again time constraintshad to be managed. E.g. Sydney Water.
• Transportation studies were helped by previous work, but further road worksrequired
Gullen Solar Site Progress
25
White Rock Wind Farm Introduction
26
Construction committed by Goldwind/CECEP on a merchant basis (China Energy Conservation and
Environmental Protection Group)
Located about 20km west of Glen Innes, northern NSW
Goldwind Australia – Wind Farm EPC Contractor
From Sydney: Fly Sydney to Armidale ~
1 hr Drive Armidale to Wind
farm site ~ 1 hr 30 mins
• 70 turbine locations used in stage 1 (119 approved).
• 17km north to south• Construction Compound and O&M
Compound at north end of the site near highway.
• Additional O&M facilities at substation and in south of project
• 8km of 132kv Overhead line to connect to substation in centre of the site.
• Site Access to North (Highway), East and South.
• Remaining turbine locations available for stage 2 mostly located in the Eastern and Southern part of the project.
Wind Farm Project Layout
27
Northern
Access
Eastern
Access
Southern
Access
Construction and O&M
Compounds
Substation
Overhead
132kV line
Additional
areas available
for Stage 2
Ecology Flora & Fauna
28
• Endangered Ecological Community (EEC’s)• Yellow Box• Ribbon Gum
• Vegetation clearing strictly limited under the Project Approval
• Wind Turbine locations adjusted to minimise impact
White Rock Grid Connection
29
• Existing 132kV line crosses the site• Line to be re-directed to the
substation and back• Line to substation is approx. 8km of
double circuit 132kV• Agreements executed with Transgrid:
Preliminary Works Underwriting Agreement (PWUA)
Project Agreement Connection Agreement
• Transgrid is currently constructing the Connection Works.
Connection to
existing line
New double
circuit 132kV
line
Substation
Community Engagement
30
• Positive Community
• Sponsorships.
• Near Neighbour Agreement Plan – For all
residences within 3km (14)
• Co-location of Vodafone mobile phone
base station on monitoring tower
• Local Business Participation Program –
In conjunction with the ICN
• Local Jobs Program – Local Media
• Community Benefits Fund – Once
Operational
White Rock Solar Farm
31
• On 12 September 2016 it was announced that White Rock Solar is one of 12 projects to be awarded a grant from the Australian Renewable Energy Agency (ARENA) Large Scale Solar Competitive Round.
• The construction of the solar farm will commence during second quarter of 2017, to be fully operational by the end of 2017.
• The development forms a pioneering hybrid solar-wind renewable energy facility in the New England Tablelands.
• Shared infrastructure with White Rock Wind Farm will maximise the use of existing facilities grid connection substation and operations building some access tracks
White Rock Wind & Solar Hybrid
32
195MW Total Generation
• 175 MW wind planned
• 20 MW solar planned
Connection to Transgrid 132kV
transmission
• 170 MW export capability
Negotiating with preferred EPC Contractor
Construction in 2017
White Rock Solar Site
33
White Rock Land & Planning Issues
34
• Alternate sites had either significant environmental issues (trees) or were not contiguous
• All sites was not part of the original wind farm environmental studies – required new studies in all cases
• Paper Roads dissected the final site• State approved development. NSW was motivated to approve promptly
• Landowners seeking compensation equivalent to wind $/MW. This is far in excess of the $/Ha they would earn from the land or gain from leasing their land for agriculture purposes.
White Rock Solar Grid and Power sales
• Will connect into windfarm, taking advantage of windfarm infrastructure• Windfarm grid connection currently limited to 175MW - however Low coincidence
of generation (1.1%)• Project proposed on basis of merchant power sales but could be included in any
future Windfarm PPA.
35
• Market participation and Metering means separate 33kv cabling to switchroom.
Comparison of generation and grid constraint
36
0
10
20
30
40
50
60
70
80
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
En
erg
y Y
ield
(G
Wh
)
High wind generation during Winter months at Gullen Range
Wind
Solar
0
20
40
60
80
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
En
erg
y Y
ield
(G
Wh
)
High wind generation months align with Summer & Winter months at White
Rock
Wind
Solar
Annual Complimentary Generation
37
Average Time of Day Power Outputs
Diurnal complimentary generation at WRWF
Gullen Range White Rock
Av
era
ge
op
utp
ut
Win
d (
(MW
)
hour
Wind+Solar Wind Solar
Day
Av
era
ge
op
utp
ut
Win
d (
(MW
)
hour
Wind+Solar Wind Solar
Day
Not Grid Constrained Grid Constrained
38
WRWF 132kV grid capacity limited by network thermal rating
0
20
40
60
80
100
120
140
160
180
200
0% 20% 40% 60% 80% 100%
White Rock Wind/Solar Hybrid vs. Transmission Limit
Transmission Limit
Wind + 20MW Solar
Curtailment Analysis of White Rock
39
Curtailment Analysis of Gullen Range
40Gullen Range grid capacity limited by 90 MVA transformer size (1 of 2)
0
20
40
60
80
100
120
140
160
180
200
0% 20% 40% 60% 80% 100%
Gullen Range Wind/Solar Hybrid vs. Transmission Limit
Wind + 11 MW Solar
Transmission Limit
Comparison of Gullen Solar & White Rock Solar Sites
41
Gullen Solar White Rock Solar
Project Size 10 MW AC 20 MW AC
Availability of Suitable Land Limited Limited
Number of Site Options
Considered*
2 (4) 1 (3)
Distance to Substation < 2km >8km
PV Array Compact - Fixed Tilt, Closely
spaced
Fixed Tilt
Grid Constraint Not Grid Constrained Grid Constrained
* Gullen conducted detail studies on 2 sites, White Rock carried preliminary environmental assessment of 3
sites and detail studies on 1 site only.
Gullen Solar White Rock Solar
Characterisation of Region Grazing and Lifestyle Grazing and Cropping
Community Experience in
similar large scale development
Prior experience in large scale
renewables development (Wind)
Nil
Wind Farm Construction Stage
at DA
Complete Commenced <2 Months
Land Tenure Owned by a Goldwind
Company, leased to neighbour
for grazing
Owned by wind farm
landowner, leased to White
Rock Solar Pty Ltd
Easements for Connection 1 6 (all wind farm landowners)
Community/Neighbour
Relations
Sensitive Good, Supportive
Negotiations Emotive - Site relocated after
community feedback
Commercial
Comparison of Community, Neighbour and Landowner
42
Gullen Solar White Rock Solar
Approving Authority Joint Regional Planning Panel
(local government)
NSW Department of Planning
Characterisation of Region Grazing and Lifestyle Grazing and Cropping
Local Government
State Government
Not Supportive / Not Opposed
Not involved
Supportive
Supportive
Environmental Sensitivity Some hollow bearing trees to be
removed
Some degraded native forest
derived grassland. Able to be
avoided
Cultural Heritage Significance Several sites to be avoided No
Water, Sediment & Erosion Sydney Water Catchment No significant issues
Development Approval Process
– Concept to Approval (including
preliminary design, consultation &
assessment)
18 months 9 months
Comparison of Gullen Solar & White Rock Solar Approval
43
Expected Advantage Gullen Solar White Rock Solar
Use existing
Environmental Studies
Some background information however
new specialist studies needed to be
performed for the selected site.
Some background information however
new specialist studies needed to be
performed for each of the proposed sites.
Build on community
engagement
No, project development was too late Yes, able to use WRWF shopfront at Glen
Innes and existing staff
Possible add-on to
existing PPA
No – Wind Specific PPA and counterparty
not buying
Merchant project
Possible add-on to
existing Finance
Yes – able to draw down on the project
finance
Undecided – subject to final ownership
Use existing landowner
relationships
Yes, however new agreements required Yes, however new agreements required
The Advantages of Co-location - Actual
44
Expected Advantage Gullen Solar White Rock Solar
Grid Substation &
Switchyard cost savings
Yes, <2km underground cable.
Switchroom had spare switchboard
cabinets
Yes, >8km underground cable.
Switchroom had planned for spare
switchboard cabinets
33kv reticulation cable No, already constructed No, separately metered
Roads cost savings No, additional approval requirements for
public roads
Yes, Site entrance
Buildings cost savings Yes, however expansion may be needed Yes, solar planned from start
Use wind farm
maintenance staff
Yes Yes
The Advantages of Co-location - Actual
45
• Options for sites are few but they help the community and planning process
• Not able to utilize most of Wind Farm environmental studies• Timelines are uncertain for community engagement and
planning• Complex legal framework for connection, access and
easements• Land costs may be greater than expected• Earlier you think about solar/wind hybrid the better• Greenfield hybrid development could maximize benefits
Key Learnings
46
Despite several sub-optimal situations, cost savings can be achieved in;• Project development• Savings achieved by sharing existing infrastructure• Complimentary generation allows improved utilisation of connection
assets• Operational savings by sharing operation and maintenance staff
Wind & Solar Hybrids reduce market costs
47