US LHC ACCELERATOR PROJECT. berkeley - brookhaven - fermilab. Joseph Rasson LBNL DOE LHC Quarterly Status Meeting at FNAL 12 February 2004. Outline. Project Overview IR Absorbers (TAS and TAN) Cryogenic Distribution Boxes (DFBX). LBNL Cost Performance Summary Through Dec 2003. - PowerPoint PPT Presentation
Popular Tags:
30
DOE-QRT Review 12 Feb2004 Joseph Rasson LHC Project Update 1 Joseph Rasson LBNL DOE LHC Quarterly Status Meeting at FNAL 12 February 2004 US LHC ACCELERATOR PROJECT berkeley - brookhaven - fermilab
Transcript
Page 1: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 1

Joseph RassonLBNL

DOE LHC Quarterly Status Meeting at FNAL12 February 2004

US LHC ACCELERATOR PROJECT berkeley - brookhaven - fermilab

Page 2: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 2

Outline

Project Overview IR Absorbers (TAS and TAN) Cryogenic Distribution Boxes (DFBX)

Page 3: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 3

LBNL Cost Performance SummaryThrough Dec 2003

WBS Description BAC%

Complete

1.1.1 IR Quads 1,921.9 100

1.1.3 Cryo Feedboxes 8,251.2 90

1.1.4 IR Absorbers 4,557.8 100

1.3.2 SC Cables 936.2 100

1.4.3 Accelerator Physics 626.2 100

1.5.4 Project Mgmt 1,491.5 96

OH 264.9 91 GA 2,317.0 95

Total (k$) 20,366.8 87

Complete 2002

Complete 2001

Complete 2002

Page 4: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 4

Cryogenic Dist. Boxes (DFBX)Functional Diagram

LBNLDFBX

FNAL, KEK, CERNMQX (Q1 - Q3),

Correctors

ELECTRICAL SIGNALS

VACUUMVACUUM

M AGNET & HEATER POW ER

EL

EC

. S

IG'S

.

50 -

75

K,

18 B

AR

CRYOGENIC

4.5

K,

1.3

BA

R

300

K,

1 B

AR

1.9

K,

16 m

BA

R

BNLMBX (D1)

CRYOGENIC

M AGNET & HEATER POW ER

ELECTRICAL SIGNALS

CERNINSULATION

PUMPINGCERN

CONTROL and POW ERCONVERTERS

CERNQRLS

CERNGHe RECOVERY

INSTALLATION

and

ALIGNMENT

20 K

, 1.

3 B

AR

DFBX Functional Diagram (IP’s 2 & 8)

Page 5: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 5

CAD Model of DFBX Illustrates Complexity

Page 6: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 6

DFBX Highlights Since Last Year’s Review

Great progress was achieved toward completing the DFBX

project

Major fabrication, assembly and integration operations are

underway at Meyer Tool and Mfg Inc.

Fabrication of Government Furnished Material (GFM) is

complete

Page 7: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 7

40 Each 7,500A HTS Current LeadsFabrication and Test

Fabrication is complete

Fabrication is Completeat Pirelli

Cold Test is underway at FNAL

Page 8: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 8

32 Each Vapor Cooled Power Leads Fabricationis Complete

Fabrication at American Magnetics (AMI) is complete:

16 ea 6-lead, 600 A assemblies

8 ea 2-lead, 600 A assemblies

8 ea 10-lead 120 A assemblies

All Leads are shipped to Meyer Tool for Integration

Page 9: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 9

1. Insert Busses into G-10 Plug

2. 2850 MT Potting in Vacuum

3. Seal Magnet Side with 2850

MT

4. Seal DFBX side with 2850 MT

5. Voila!

Bus Duct/Lambda Plate Fabrication at LBLis Complete

Completed

Page 10: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 10

Bus Duct Fabrication Completeat LBNL

Page 11: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 11

Beam Tube Fabrication at LBNLis Complete

8 Beam Tubes were shipped to MTM for integration

Page 12: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 12

Magnet Instrumentation Conduits Fabricationat Fermilab

All conduits to be delivered to MTM by the

End of Feb 04

Page 13: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 13

All Mechanical Components are Fabricated

8 Liquid Helium Vessels

Page 14: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 14

Quadrupole Diagnostic Feedthrough Assemblies

Page 15: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 15

Spool Pieces are Complete

Page 16: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 16

DFBX Assembly and Integrationis Underway at MTM

Page 17: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 17

Subsystem Vacuum Leak Test

Page 18: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 18

Thermal Shield Components are Complete

Page 19: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 19

DFBX Production Schedule

DFBX No. 1and 2 Ready to Ship 1 Aug 2004

DFBX Nos. 3 and 4 Ready to Ship 15 Dec 2004 DFBX Nos. 5 and 6 Ready to Ship 12 Jun 2005 DFBX Nos. 7 and 8 Ready to Ship 1 Sep 2005

Schedule Constraints:

1. First DFBX needed at CERN for sector test 24 Sep 2004

2. Last DFBX should be shipped before end of DOE’s end of project milestone (30 Sep 05)

Page 20: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 20

IR Absorber Overview - TAN

The TAN consists of three major assemblies;

1. Absorber box 2. Beam tube, 15 ft long3. Steel shielding and

marble headstone 33 Tons total weight

Absorber Box (includes the Beam Tube)

Steel ShieldingBeam Tube

Page 21: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 21

Vacuum Chamber E-Beam Weld at Sciaky in Chicago Land

•Total of 9 e-beam welds per tube

Page 22: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 22

E-beam weld is completeBake out is completeVacuum seal qualification is completeParts for a spare beam tube is available

Page 23: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 23

TAN Absorber Fabrication, Assembly and Test are Complete

Page 24: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 24

TAN Shield Loaded on Truck, 10 Feb 2004

Page 25: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 25

Absorber Boxes Loaded on Truck

Page 26: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 26

Beam Tubes Loaded on Truck

Page 27: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 27

TAN Auxiliary Components

Page 28: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 28

IR ABSORBER OVERVIEW-TAS

The TAS consists of three major assemblies:

Copper ClamshellsVacuum Beam Tube Alignment/support System

Page 29: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 29

Subcontracted Shipping to CERN, Jul 2003

Page 30: Joseph Rasson LBNL DOE LHC Quarterly Status  Meeting at FNAL 12 February 2004

DOE-QRT Review12 Feb2004

Joseph RassonLHC Project Update 30

Summary

Great progress in DFBX fabrication and assembly

HTS and VC lead fabrication is complete

Fabrication of LBL furnished material is complete

DFBX cost is stable, all procurements placed

Adhering to the fabrication schedule will require careful

oversight

TAS/TAN fabrication and assembly are complete

TAS arrived at CERN and passed inspection. TAN is in transient

TAS CERN’s Acceptance Specification has been approved, TAN’s

to be submitted for review next week