+ All Categories
Home > Documents > J.P.Delahaye CLIC @ ACE 02-02-10 1 CLIC A dvisory C ommitte E (ACE) Introduction to the 5 th CLIC...

J.P.Delahaye CLIC @ ACE 02-02-10 1 CLIC A dvisory C ommitte E (ACE) Introduction to the 5 th CLIC...

Date post: 20-Jan-2016
Category:
Upload: mildred-booker
View: 214 times
Download: 0 times
Share this document with a friend
39
C L I C C L I C J.P.Delahaye CLIC @ ACE 02-02-10 1 CLIC Advisory CommitteE (ACE) Introduction to the 5 th CLIC Advisory Committee meeting (02-04/02/10) CLIC progress and perspectives Follow-up from last ACE meeting J.P.Delahaye for The Compact LInear Collider (CLIC) Study Team
Transcript
The CLIC studyJ.P.Delahaye for
CLIC Advisory CommitteE (ACE)
Follow-up of ACE’s recommendations
Major highlights from last ACE meeting
Plans towards CDR and beyond
J.P.Delahaye
M.Huening/DESY
A.Mosnier/CEA
Welcome the one who could not participate to previous meetings:
T.Shintake/Riken
Welcome
J.P.Delahaye
Specific to this ACE meeting
The 5th ACE meeting will focus on the technical progress towards the CDR design and the status of the R&D program needed to demonstrate CLIC feasibility in support of the CDR.
The ACE is asked to comment on:
i) the layout and schedule for the CDR
ii) the schedule of the CLIC feasibility demonstrations and timing of the CDR
iii) the technical and/or design status of the following subjects drawn from the “list of CLIC critical issues”:
1) RF structures (MB + DB)
2) DB + MB generation (phase, intensity, energy stability)
3) Two Beam Acceleration
5) Preservation of ultra low emittances, highest luminosity
J.P.Delahaye
This room reserved for the Committee up to Thursday night
Coffee breaks here (Committee and Speakers)
Lunches in CERN Main Cafeteria (tickets provided to Committee)
Dinner to-morrow in Glass Box (Main Cafeteria): (Committee and Speakers)
Report on ACE’s findings and recommendations by ACE chairman to:
CLIC team on Feb 04 pm
CLIC/CTF3 collaboration Board on Feb 05 am
J.P.Delahaye
Update on CLIC design (D.Schulte&G.Geschonke) next
Review of R&D status and plans critical of each critical issues (all presentations)
CLIC feasibility summary (JPD)
CDR organisation & schedule (H.Schmickler)
Other issues raised by Committee at ACE4 as well as overall progress of CLIC study :
Subject of this presentation
J.P.Delahaye CLIC @ ACE 02-02-10 *
4th ACE meeting (02-04/09/08)
Specific Mandate: Focused on progress and plans for critical R&D supporting the CDR and beyond
The Committee is invited to review, assess and comment on these plans. In specific, the committee is asked to evaluate:
a prioritized list of the most relevant CLIC technical issues and their classification by feasibility, performance and cost impact.
the R&D status and plans to address the critical issues
the R&D program and the schedule to complete a CLIC Feasibility Demonstration as well as a Conceptual Design Report
A first proposal of technical objectives and planning for the Technical Design Phase in the years 2011 - 2015
ACE report: Report not (yet?) available
Recommendations to CLIC team:
Extensive detail behind each topics providing greater
detail of feasibility demonstration for 2010 and future
studies in early TDR period (2010-2012)
CTC list did not prioritize between programs
Believe that this may be necessary
J.P.Delahaye
Concerned that a large task to complete by 2010
Focus on CLIC-specific items as much as possible
Consider CDR / feasibility schedule carefully
Plan to engage international community in extended workshop post-CDR
All issues addressed till 03/02 pm:
CDR schedule and organisation: H.Schmickler
CLIC feasibility summary: JPD
1 H00 discussion on feasibility benchmark and expected level of accomplishment by end 2010
J.P.Delahaye
Aggressive structure program
PETS HOM benchmark studies
Injector issues and stability …
Two beam Acceleration & CTF3 (02/02 pm)
TBTS high priority for key two beam acceleration demonstration
Increased effort for experimental program
Develop schedule & priorities
Significant extrapolations
Subsystems issues (Inj., DR, RTML, ML, BDS)
Stabilisation
Mobilize the CTF3 collaboration for increased participation in operating the test facility and in CDR
J.P.Delahaye
Possible for a strong CERN program (3 ~ 4x present)
Consideration of pre-construction demonstrations
~700 meters of TBA linac
Challenging to even demonstrate CLIC drive beam hardware and beam dynamics
100 A and 240 ns drive beam
Must balance between completing broad design and demonstrating near-final drive beam linac hardware
Ongoing discussion that should engage international community pre- and post-CDR
J.P.Delahaye
IAP (Russia)
IRFU / Saclay (France)
Jefferson Lab (USA)
World-wide CLIC&CTF3 Collaboration
J.P.Delahaye
Physics & Detectors
Civil Engineering & Conventional Facilities
Statement of common intent
(Accelerator & Detectors)
Joint CLIC & ILC (Accelerator and Detectors)
J.P.Delahaye
CLIC / ILC Joint Working Group on General Accelerator issues
ILCSC has approved formation of two CLIC/ILC General Issues working groups by the two parties (one on Accelerators and one on Detectors) with the following mandate:
Promoting the Linear Collider
Identifying synergies to enable the design concepts of ILC and CLIC to be prepared efficiently
Discussing detailed plans for the ILC and CLIC efforts, in order to identify common issues regarding siting, technical issues and project planning.
Discussing issues that will be part of each project implementation plan
Identifying points of comparison between the two approaches .
The conclusions of the working group will be reported to the ILCSC and CLIC Collaboration Board with a goal to producing a joint document.
Members:
J.P.Delahaye
Bulgaria: Acad. of Science
Finland: Helsinki Univ, HIP
France: CEA/IRFU, Ecole Norm Sup, LLR-Ecole Polyt, IN2P3/LAL, IPNL, LAPP, LPHNE, UPMC
Germany: Bonn Univ.,DESY, Karlsruhe Univ, MaxPlanck Inst.
Greece: NTU Athens
Japan: KEK, Shinshu Univ, Tokohu Univ
Kenya: Jomom Kenyatta Univ
Romania: IFIN-HH
Sweden: Uppsala Univ.
Switzerland: ADAM, EPFL, ETH-Zurich, Lulea Univ Techn, PSI
Turkey: Abant I B Univ, Ankara Univ, Dumlupinar Univ, TAEA, Uludag Univ
United-Kingdom: ASTeC, Birmingham Univ., Cambridge Univ, Cockcroft Inst., Daresbury Lab, JAI, Lancaster Univ, Manchester Univ., Oxford Univ, RAL, RHUL, STFC, Univ College London
United-States: ANL, BNL, Caltech, Cornell Univ., Euclid Techlabs, FNAL, Iowa State Univ, LBNL, LLNL, Minesota Univ, Ohmega-P, Oregon Univ, SLAC, Yale Univ
Vietnam: Hanoi Univ
Address all feasibility issues
Conceptual Design Report (CDR) by end 2010 including
Physics, Accelerator and Detectors
R&D on critical issues and results of feasibility study,
Preliminary performance and cost estimation
L.Linssen
Driven by Physics requests:
Document in preparation (end Feb) by Physics (L.Linssen + int Cttee) to clarify the Physics requests in the Multi-TeV range as update of the similar document provided at 500 GeV by R.Heuer Cttee in 2004.
……?
Iteration process for best trade off between performance, risk, technical feasibility and cost
Relaxed parameters:
Provide flavor of luminosity range and parameters sensitivity
D.Schulte
next
G.Geschonke
next
J.P.Delahaye
Luminosity ∫Ldt = 500 fb-1 in 4 years
Ability to scan between 200 and 500 GeV
Energy stability and precision below 0.1%
Electron polarization of at least 80%
The machine must be upgradeable to 1 TeV
Being updated for a Multi-TeV Linear Collider
J.P.Delahaye
500 GeV nominal parameters
3 TeV relaxed parameters
3 TeV nominal parameters
DATA LC
LEP
SLC
ILC
RF pulse duration (nanosec)
Mean accelerating field (MV/m)
Cost (NLC 500 GeV = 1)
Relative costs of Linear Colliders (Acc field: TBLC = NLC, CLIC =3*NLC)
0
0
0
0
0
0
0
0
0
0
0
Cost (NLC 500 GeV = 1)
A first assessment of Two Beam Linear Coliders isssues at SLAC (G.Loew for NLC and TBLC in 1998: normalized to NLC @ 500 GeV ) -- -- -- estimation for CLIC with 3 times higher accelerating field
0
0
0
0
0
0
0
ILC 500 GeV
CLIC achieved
CLIC nominal
Cost (NLC 500 GeV = 1)
Relative costs of Linear Colliders (Acc field: TBLC = NLC, CLIC =3*NLC)
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Cost (NLC 500 GeV = 1)
A first assessment of Two Beam Linear Coliders isssues at SLAC (G.Loew for NLC and TBLC in 1998: normalized to NLC @ 500 GeV ) -- -- -- estimation for CLIC with 3 times higher accelerating field
0
0
0
0
0
0
0
0
0
0
0
Ex
Ey
Ex
Ey
mincrorad
microrad
microrad
microrad
SLC
50
5
SLC
30
3
ATF(design)
ATF(design)
ATF
SLC
FFTB
12
248 / 5.7
202 / 2.3
7.5%
6.8%
Center-of-mass energy
11.4
243/3
640/5.7
0.10
0.12
0.07
0.19
7.1%
9.4%
7.5%
Relaxed
parameters
J.P.Delahaye
Chart1
30
0.4
30
30
6.25
6.25
2.4
0.4
3
0.0024660393
4
0.55
23
3
3
3
3
8
8
8
8
8
8
3
3
3
Ex
Ey
Ex
Ey
mincrorad
microrad
mincrorad
microrad
SLC
50
5
SLC
30
3.000
ATF(design)
ATF(design)
ATF
ILC
Luminosity
Ex
Ey
Ex
Ey
mincrorad
microrad
mincrorad
microrad
SLC
50
5
SLC
30
3.000
ATF(design)
ATF(design)
ATF
ILC
Luminosity
Overall list of critical issues (Risk Register) under:
Issues classified in three categories:
CLIC design and technology feasibility
Fully addressed by 2010 by specific R&D with results in Conceptual Design Report (CDR) with Preliminary Performance & Cost
Performance and/or Cost
Both being addressed now by specific R&D to be completed before 2016 with results in Technical Design Report (TDR) with Consolidated Performance & Cost
For each feasibility issue, R&D program and objectives defined:
Discussed @ Advisory CommitteE (ACE) on June 2009
Two Beam Module
Alignment and stabilisation
Adaptation to large background at high beam collision energy
Operation and Machine Protection System (MPS)
CLIC specific
Vol1: Executive Summary
Vol3: The CLIC physics and detectors
including detailed value Estimate
specific contribution in vol. 2&3; summary in vol. 1.
Editorial Board for Volume 2:
H.Schmickler (chair), N.Phinney/SLAC, N.Toge/KEK,
Presentation and discussion at Collaboration Board (05/02/10)
Vol 3 under responsibility of LCD project (L.Linssen)
J.P.Delahaye
Inform authors after workshop
Draft CDR
Finalisation of concepts
Feedback from CTC
Feasibility R&D, Extra Studies, Finalization of concepts
Feedback from Cost WG
Abstracts and keywords from authors
Q4/2009
Q1/2010
CDR
TDP1
TDP2
CDR
Intermediate
TD
TDR
Linear Collider assessment based on
technology maturity, performance, cost and risks?
CLIC cost peer review
Conceptual design&cost est.
and Technical Design
Engineering optimisation
Commissioning & Operation
Commissioning & Operation
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
LHC
Technical design & industrialisation
Technical design & industrialisation
Conceptual design&cost est.
and Technical Design
Engineering optimisation
Commissioning & Operation
Commissioning & Operation
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
LHC
Technical design & industrialisation
Technical design & industrialisation
(pending Council decision in June 2011)
TDR task force chaired by R.Corsini presented @ Advisory Committee (May09):
J.P.Delahaye
Start from needs and not from (potentially) available budget / resources
Begin with list of activities and feasibility / critical items
Determine where we will likely stand in 2010.
Define a logical extension of R&D for each activity in the short term (2010-2012) - when needed - setting clear goals.
Try to define additional R&D needed to arrive at a TDR in 2015 for each activity & identify schedule critical items.
J.P.Delahaye
TDR major activities
Project Implementation Plan (PIP) to be added with extra resources in the period 2014 to 2016
2010
2011
2012
2013
2014
2015
2016
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
testing
precision metrology, fabr. procedures
up to 40 structures built, establish precision machining at CERN or elsewhere, 5 mm tolerances achieved
more than 200 structures built, final cost optimization, pre-series with industry
RF test infrastructure
CERN test stand testing and upgrades (at least two slots)
continue testing with increased capabilities, CERN or elsewhere, up to 10 slots
testing, up to 200 accelerating structures plus PETS and RF components
Prototypes of critical components
J.P.Delahaye
CERN/2796 (June 2009)
The CLIC enhancement program aims to provide proof of feasibility by 2010.
In the event of a positive outcome of the feasibility study, the increase of resources
from 2011 onwards will allow for the preparation of a technical design report.
MTP09
MTP09
Launch of new project on Linear Collider Detector R&D with add. resources (L.Linssen)
J.P.Delahaye
Chart2
2008
2008
2008
2009
2009
2009
2010
2010
2010
2011
2011
2011
2012
2012
2012
2013
2013
2013
2014
2014
2014
2015
2015
2015
2016
2016
2016
Man-Power
Material
Total
12.3
10.1
22.4
12.2
10.1
22.3
12.2
10
22.2
15
15
30
24
26
50
24
26
50
28.8
31.2
60
32.5
37.5
70
37.5
42.5
80
MTP09 resources distribution
Man-Power
Material
Total
Man-Power
Material
Total
2010 (updated from APT data)
2011
2012
2013
2014
TOTAL
P
M
15
15
30
39
41
80
63
67
130
91.8
98.2
190
124.3
135.7
260
161.8
178.2
340
MTP09 resources distribution
Man-Power
Material
Total
Man-Power
Material
Total
2010 (updated from APT data)
2011
2012
2013
2014
TOTAL
P
M
assuming 1/3 of resources provided by ext collaborations
J.P.Delahaye
for approval by CERN council in June 2010
Work program (51 work packages) approved as draft by CERN sector and Directorate on January 12-15, 2010
Discussion with CERN Departments and Groups about work packages under group responsibility and necessary (M&P) resources in preparation for Medium Term Plan document MTP10 to be presented at CERN council in June 2010
Discussion at CLIC/CTF3 Collaboration Board on February 5 about possible work packages under Collaborating Institute responsibility with additional (M&P) resources.
J.P.Delahaye
J.P.Delahaye CLIC @ ACE 02-02-10 *
CLIC program towards CDR
2010 resources (CERN and Collaborations) compatible with completion of work program towards a draft CDR (accelerator) end 2010 and a final CDR (including detectors) by June 2011
The Concept of a Multi-TeV Linear Collider based on CLIC technology is mature enough to be described in CDR.
All accelerator feasibility issues are being addressed
A large part of them are or will be demonstrated by the time.
A few of them (stability,…) still need some time to be fully addressed with an R&D program well under way (final results by 2012) and for which preliminary and promising results are already available.
The CDR will include the R&D status, available results and remaining program to fully address CLIC technology feasibility issues
in preparation for the development of a CLIC Technical Design (pending Council approval) with technology optimisation and industrialisation in parallel with R&D completion
Still to be reviewed (peer review Nov 2010) if and when cost figures should be included
ACE’s (wise) comments and advices appreciated
J.P.Delahaye
Demonstrate nominal CLIC structures with damping features at the design
gradient, with design pulse length and breakdown rate .
100 MV/m
240 ns
RF Power production structures:
Demonstrate nominal PETS with damping features at the design power,
with design pulse length, breakdown rate and on/off capability
136 MW, 240 ns
Demonstrate RF power production and Beam acceleration with both beams
in at least one Two Beam Module equipped with all equipments
Two Beam Acceleration with simultaneous &
nominal parameters as quoted above for
individual components
7.5 10
- Rf power extration
Emittances(nm): H= 600, V=5
Absolute blow-up(nm): H=160, V=15
Stabili
zation
Main Linac : 1 nm vert. above 1 Hz;
BDS: 0.15 to 1 nm above 4 Hz depending on
final doublet girder implementation
MTBF, MTTR
Machine protection
Detector
beam beam effects during collisions at high energy
3.8 10
Technical design & industrialisation
0
10
20
30
40
50
60
70
80
90
200820092010201120122013201420152016
Man-Power
Material
Total
0
50
100
150
200
250
300
350
400
201120122013201420152016
Man-Power
Material
Total
Q3Q4Q1Q2Q3Q4
Update
Baseline
20092010
Finalisation of concepts
150 MeV
0
1
2
3
4
5
6
7
MCHF
commitments
3.2
5.8
4.6
2.4
1.0
0.2
spending
1.2
5.5
5.5
3.2
1.4
0.5
2004
2005
2006
2007
2008
2009
0
5
10
15
20
25
Drive Beam Accelerator
30 GHz high-gradient testing (4 months per year)
R1.1 feasibility test of CLIC accelerating structure
Delay Loop
Combiner Ring
CLEX

Test beam line

2004 2005 2006 2007 2008 2009
Drive Beam Accelerator
30 GHz high-gradient testing (4 months per year)
R1.1 feasibility test of CLIC accelerating structure
Delay Loop
Combiner Ring
CLEX

Test beam line

Work Package Provider Schedule Resources
1. Combiner Ring (CR), Transfer Line (TL1) to CR and Transfer Line (TL2) with bunch
compressor to CLIC EXperimental Area (CLEX)
Collaborating institute or CERN
14 m*y
1.1 Optics layout
A reference layout exists from INFN, further optimisation and follow -up in conjunction with final
integration is necessary.
1.2 Magnets
Design and procurement of all magnets for the Combiner Ring the transfer lines and the bunch
compressor.
Collaborating institute or CERN
4 m*y
1.3 Vacuum system
Design and procurement of the aluminium vacuum chambers for the 80 m circumference ring and
transfer lines, vacuum pumps, pumping ports, vacuum gauges, shielded bellows.
A large part of the design of equipment made by INFN for the Delay Loop can be used. Detailed
design work is required.
Collaborating institute or CERN
1.4 Beam diagnostic equipment
Supply of 32 beam position monitors, and vacuum ports for synchrotron light. Suc h monitors have
already been developed for the CTF3 Delay Loop. This design could be used without modification
Collaborating institute or CERN
Some power supplies are available from LPI.
CERN
CERN
1.7 Control system for combiner ring and related software
The system has to be compatible with the existing controls infras tructure
CERN, possibly in collaboration
1.8 Fast kicker with High Voltage pulser
Design and manufacture of the fast kicker system (kicker and high voltage pulser) for the Combiner
ring
Special attention has to be given to the impedance seen by the beam.
Collaborating institute or CERN
1.9 RF distribution system for RF deflector
Fabrication and installation of the complete waveguide system from the klystron to the RF deflector
in the Combiner Ring
Total WP2
2.9 MCHF
Design, procurement, installation and participation in exploitation of all equipment required for the 30
GHz test stand. This includes all RF and diagnostic equipment as well as the software for
automatically operating this installation. Such a test stand will be installed during 2005 in CTF3.
This work package includes participation in structure testing.
Collaborating institute or CERN
implemented in
Work Package Provider Schedule Resources
1. Combiner Ring (CR), Transfer Line (TL1) to CR and Transfer Line (TL2) with bunch
compressor to CLIC EXperimental Area (CLEX)
Collaborating institute or CERN
14 m*y
1.1 Optics layout
A reference layout exists from INFN, further optimisation and follow -up in conjunction with final
integration is necessary.
1.2 Magnets
Design and procurement of all magnets for the Combiner Ring the transfer lines and the bunch
compressor.
Collaborating institute or CERN
4 m*y
1.3 Vacuum system
Design and procurement of the aluminium vacuum chambers for the 80 m circumference ring and
transfer lines, vacuum pumps, pumping ports, vacuum gauges, shielded bellows.
A large part of the design of equipment made by INFN for the Delay Loop can be used. Detailed
design work is required.
Collaborating institute or CERN
1.4 Beam diagnostic equipment
Supply of 32 beam position monitors, and vacuum ports for synchrotron light. Suc h monitors have
already been developed for the CTF3 Delay Loop. This design could be used without modification
Collaborating institute or CERN
Some power supplies are available from LPI.
CERN
CERN
1.7 Control system for combiner ring and related software
The system has to be compatible with the existing controls infras tructure
CERN, possibly in collaboration
1.8 Fast kicker with High Voltage pulser
Design and manufacture of the fast kicker system (kicker and high voltage pulser) for the Combiner
ring
Special attention has to be given to the impedance seen by the beam.
Collaborating institute or CERN
1.9 RF distribution system for RF deflector
Fabrication and installation of the complete waveguide system from the klystron to the RF deflector
in the Combiner Ring
Total WP2
2.9 MCHF
Design, procurement, installation and participation in exploitation of all equipment required for the 30
GHz test stand. This includes all RF and diagnostic equipment as well as the software for
automatically operating this installation. Such a test stand will be installed during 2005 in CTF3.
This work package includes participation in structure testing.
Collaborating institute or CERN
implemented in
I.C Collaborating institute or
I.I Addresses all conceptual, design, and some fabrication issues for accelerating
structures. Most of this work is covered in the CERN medium term plan (MTP).
I.J Collaborating institute or
I.M 7.2 PETS development:
I.N Addresses all conceptual, design, and some fabrication issues for PETS structures (covered
by MTP).
I.P Collaborating institute or
I.W Addresses technological and fabrication issues for accelerating and PETS structure
developments (refractory metals, copper alloys, composite s, 5-axis machining and
metrology). The TS department at CERN would be the most appropriate place to do
this work if the necessary resources can be found.
I.X Collaborating institute or
I.DD Support for operating the facility. This essentially concerns development of
operation software .
I.JJ
I.KK
I.LL
I.MM The following item is not part of this request for extra resources, but is considered to be highly desirable (see chapter 12).
I.NN

Recommended