+ All Categories
Home > Documents > JPT1999_10_IS

JPT1999_10_IS

Date post: 08-Aug-2018
Category:
Upload: userscribd2011
View: 212 times
Download: 0 times
Share this document with a friend

of 14

Transcript
  • 8/22/2019 JPT1999_10_IS

    1/1426 OCTOBER 1999

    I N T E L L I G E N T S Y S T E M S

    An intelligent completion enables acqui-

    sition of real-time data and provides a com-

    pletion method that allows reconfiguring

    well architecture whenever needed, with-out rig intervention. Although intelligent-

    completion technology can assume several

    configurations, this study considered only

    downhole control valves and power/com-

    munication umbilicals needed to monitorand control multiple completions in a sin-

    gle wellbore. The study objectives were todetermine if the application of intelligent-

    completion technology could improve theeconomic performance of a field in the Gulf

    of Mexico (GOM) and to investigate meth-

    ods for predicting this performance.

    Many types of completion are used in the

    GOM. The simplest is a well with a singletubing string to drain one reservoir for the

    life of the field. When a single reservoir will

    not support a well for the life of the field,

    several reservoirs can be produced sequen-

    tially through a single tubing string byrecompleting the well as each reservoir is

    depleted. For two reservoirs, a single selec-

    tive completion (sliding-sleeve circulating-

    type device) can be used. A dual-tubing-string completion allows both reservoirs to

    produce simultaneously. Because the stud-

    ied field uses dry trees and targets a maxi-

    mum of two reservoirs per wellbore, these

    options are available.Candidates for intelligent completion are

    wells drilled through multiple productive

    reservoirs to capture reserves by simultane-

    ous or selective production. The intelligent

    completion allows monitoring and control

    of each reservoir to optimize the perform-

    ance of each well and the field continuous-ly. Intelligent-completion technology

    allows controlling the completion from the

    surface, eliminating the need for a

    workover rig to change the downhole con-

    figuration. Therefore, other completiontypes, such as multiple-tubing completions

    (which can limit production because of

    smaller tubing) are not needed for simulta-

    neous production from several produc-

    tive reservoirs.

    PROJECT FIELD

    The field chosen for the study is a deepwa-ter GOM field that produces oil from seven

    Late Pliocene to Early Pleistocene reser-

    voirs, named Z1 through Z7, from top to

    bottom. Core porosities of the sand units

    range from 15 to 35% and permeabilitiesfrom 10 to 2,400 md. The net-/gross-pay-

    thickness ratio ranges from 0.4 to 0.95. The

    structural trapping mechanism is a normal-

    fault system. Hydrocarbon trapping also

    occurs because of stratigraphic onlap.The original development plan entailed

    drilling several highly deviated wells from a

    single structure. Most wells in this field tar-

    geted multiple reservoirs, some with singlecompletions that would require plugging

    back and recompleting in higher reservoirs

    as time progressed. Some wells were com-

    pleted with dual tubing strings to permit

    simultaneous production. All wells wouldrequire a workover. The operators reser-

    voir-simulation model was run with this

    development plan and the reservoir per-

    formance analyzed. The results were used

    to identify poorly drained areas (such asisolated fault compartments not produced

    by any well), attic oil remaining in partial-

    ly drained compartments, or areas where

    the waterflood was not effective. An intelli-

    gent completion would be applicable todrain multiple reservoirs simultaneously in

    a controlled environment, even if the reser-

    voirs are in different fault blocks in the

    same reservoir or in different reservoirsseparated by shales.

    Several wells were identified as candi-

    dates for intelligent completion on the basis

    of simulation results. The two wells chosenfor the study met the following criteria.

    Intelligent completions would not beinstalled in water-injection wells.

    The existing drilling schedule would be

    honored, and wells were not considered if

    intelligent-completion hardware could not

    be obtained in time. Intelligent completions would not be

    used in areas of high geologic risk.

    SIMULATION MODEL

    Because it was felt that the full-field modelwas too big for the purposes of this study,

    the first step was to reduce its size. The sim-

    ulation model provided by the operatorincluded all the reservoirs. However, the

    only interaction between the upper and

    lower reservoirs was through the surface

    gathering system. No wells drilled to

    deplete the lower reservoirs were ever com-pleted in the upper reservoirs and vice

    versa. Because both of the wells selected for

    possible intelligent completion had not

    been completed in the lower reservoirs,these layers were eliminated from the sim-

    ulation model for this study.

    In addition, the east and west ends of the

    original model were removed because the

    two case-study wells were shielded fromthe new east and west boundaries of the

    model by faults. The resulting model used

    approximately 30,000 grid blocks, one-half

    the number of grid blocks used in the orig-

    inal model.

    Intelligent Completions. A simple defini-

    tion of an intelligent completion is that it is

    a configuration with a valve to separate the

    reservoir from the tubing. Opening thevalve reduces the pressure drop to that

    required to obtain a given rate. Closing thevalve reverses the effect.

    Essentially, this effect is the same as

    adjusting the skin factor of the completion.

    The difference is the location of the pres-sure drop. In the intelligent completion, the

    pressure drop occurs after the fluid has

    entered the wellbore. With the skin-factor

    adjustment, the pressure drop occurs as the

    fluid enters the wellbore. It was felt that thissmall difference could be ignored and that

    changing the skin factor would simulatethe workings of an intelligent completion.

    OPTIMIZING RESERVOIR MANAGEMENT

    IN GULF OF MEXICO DEEP WATER

    This article is a synopsis of paper SPE

    56670, Application of Intelligent-

    Completion Technology To Optimize the

    Reservoir Management of a Deepwater

    Gulf of Mexico FieldA Reservoir-

    Simulation Case Study, by Stephen

    Rester, SPE, Jacob Thomas, SPE,

    Madeleine Peijs-van Hilten, SPE, and

    William L. Vidrine, Halliburton Energy

    Services Inc., originally presented at the

    1999 SPE Annual Technical Conferenceand Exhibition, Houston, 36 October.

  • 8/22/2019 JPT1999_10_IS

    2/14

    OCTOBER 1999 27

    I N T E L L I G E N T S Y S T E M S

    The base-case response was obtained by

    simulating the performance of the field

    with the candidate wells initially opened in

    one reservoir and, later, in a second reser-voir. The alternative response was obtained

    by simulating the performance of the field

    with both reservoirs open with the pressure

    drop from the reservoir to the wellbore con-trolled by the skin factors of the two com-

    pletions. The skin-factor values were

    obtained by trial and error. First, a simula-

    tion was run with given values. The rates

    from the two reservoirs were studied todetermine when intervention would be

    needed. Then, the skin factor for the prob-

    lem reservoir was adjusted. This procedure

    was repeated until the optimum production

    performance was obtained.

    Results. The operation of the first candi-

    date, Well C1, was changed without makingany changes to the operation of the second

    candidate, Well C2. Then, the operation ofWell C1 was fixed at its optimum while theoperation of Well C2 was changed.

    The operation of the intelligent-comple-

    tion case began with Well C1 completed in

    the Z2 and Z4 reservoirs with skin factors

    of zero for both completions. After a periodof commingled flow, the water cut from the

    Z2 reservoir completion began to increase.

    The simulation was rerun with an initial

    skin factor for the Z2 reservoir equal to

    zero, then it was increased when the watercut began to increase. This scheme corre-

    sponded to starting with the intelligent

    completion fully open, then partially clos-

    ing the completion when the water cutbegan to increase. This scheme changed the

    rate but not the water cut. After repeating

    this procedure several times, it was deter-

    mined that the optimum operation is to

    shut in the Z2 reservoir completion when itbegins to water out.

    The intelligent-completion operation

    accelerated production from Well C1 by

    shifting the production from the Z2 reser-

    voir to the beginning of production. Also,the changed performance of Well C1 affect-

    ed the performance of other wells in the

    two targeted reservoirs, resulting in their

    recovery of additional reserves.

    In the original operation, Well C2 wascompleted initially in the Z3 and Z4 reser-

    voirs (the Z3 and Z4 reservoirs were treat-

    ed as a single reservoir) with the intention

    of recompleting to the Z1 reservoir whenthe production rate fell to the economical

    limit. In the 10 years represented by the

    simulated production, Well C2 did not

    reach the economical limit and, therefore,was never recompleted.

    Operation of the intelligent-completioncase began with Well C2 completed in the

    Z1, Z3, and Z4 reservoirs. After a period of

    commingled flow, the water cut from the Z1

    reservoir began to increase. Following the

    procedure used for Well C1, the simulationwas rerun with the skin factor of the Z1

    reservoir equal to zero initially, thenincreased when the water cut began to

    increase. As was observed in Well C1, therate could be changed but not the water

    cut. Thus, shutting off water production

    was determined to be optimal.

    Operation with the intelligent comple-

    tion accelerated the production from WellC2 by shifting the production from the sec-

    ond completion to the beginning of pro-

    duction. Changing the performance of Well

    C2 had little influence on the performance

    of other wells in the field. Thus, the addi-

    tional reserves obtained by converting WellC1 to an intelligent completion were not

    lost when Well C2 was converted to an

    intelligent completion.

    COMPLETION OPTIONS

    Because the two candidate wells target only

    two reservoirs and the wellheads are on a

    platform, completion options are available.First, a single selective completion can be

    used to open one reservoir while closing a

    second reservoir, which is analogous to a

    recompletion option. Second, two reser-

    voirs can be produced through separatetubing strings, which is analogous to the

    intelligent completion. The differences

    occur in the capital investment required

    and the risks associated with completion

    installation and operation. For this field, itwas found that smaller-diameter tubing

    does not limit the production rate in the

    dual completion. A comparison of the eco-

    nomics of the four completion practiceswas made for Well C1 only. It was assumed

    that the completion practices would be the

    same for the second candidate.

    ECONOMICS

    Because only a portion of the original

    model received from the operator wasextracted for use in this study, some of the

    wells in the original model could not be

    simulated. The production profiles for

    those wells werecombined with those fromthe simulations to construct the full-field

    performance. This action allows comparing

    the results of the original model with the

    results of this study.

    The simulations were run for a period of10 years, at which time the economics were

    evaluated. For each economic analysis, theoil price was held constant. Several values

    of the oil price were used to determine the

    sensitivity of the net present value (NPV).

    Installing an intelligent completion inWell C1 increased production from the well

    by 0.73% and from the field by 3.54%.

    Individual-well performance is sensitive to

    the performances of other wells in the field.

    When Well C1 is completed with an intelli-gent completion, it produces less fluid from

    the Z4 reservoir compared with the con-

    ventional-completion scheme. Production

    from both reservoirs in the intelligent-com-pletion case equals the production from the

    Z4 reservoir alone in the base case. The Z4

    reservoir is depleted slower than in the base

    case, and another well initially completed

    in the same zone does not invoke the auto-matic recompletion option as early as in the

    base case. Therefore, the other well is still

    completed in the Z4 reservoir when water

    injection is initiated in that reservoir. Theimpact of water injection on that other well

    causes a large increase in total production.

    The incremental economic value comes

    from replacing the high cost of recomple-

    tion with the lower cost of a single selectivecompletion. Completing Well C1 with a

    dual-string completion would have NPV

    between 56 and 142% of the base-case drill-

    and-complete cost of the well, depending

    on the discount rate and the cost of recom-pleting the well. The improved economics

    reflect the lower cost of the dual-string

    completion compared with the intelligent

    completion. However, a dual-string com-

    pletion can consider only two reservoirs.Converting Wells C1 and C2 to intelli-

    gent completions would raise the NPV of

    the field by 98 to 342% of the base-case

    drill-and-complete cost of Well C1,depending on the discount rate and the cost

    of recompleting the well.

    CONCLUSIONS

    This study shows that intelligent-comple-tion technology has potential to improve

    project economics in the GOM through

    better reservoir-management practices. Thesimulations showed that an intelligentcompletion not only increased the ultimate

    recovery from a single well, it increased the

    total recovery from the reservoir as a whole.

    Although the conclusions were drawn from

    a simulation model, the capability to simu-late intelligent completions is still in a rudi-

    mentary stage of development.

    Please read the full-length paper for

    additional detail, illustrations, and ref-

    erences. The paper from which the

    synopsis has been taken has not beenpeer reviewed.

  • 8/22/2019 JPT1999_10_IS

    3/14

    I N T E L L I G E N T S Y S T E M S

    28 OCTOBER 1999

    Permanent downhole gauge (PDG) systems

    are an alternative to wireline-conveyed

    downhole surveys. PDG systems avoid haz-

    ardous operations and offer continuous

    measurements, which enable better reser-voir management and production opti-

    mization. Electrical pressure- and tempera-

    ture-monitoring systems are most com-

    mon. Other systems include the following. Permanent downhole flowmeters for

    liquid-only mixtures.

    Use of the power cable for data trans-mission in wells with electrical submersible

    pumps. Fiber-optic well monitoring for meas-

    uring pressure and temperature.

    Cableless communication.

    Surface-controlled reservoir-analysis

    and -management systems.Installation of electrical gas-lift valves,

    all-electrical inflow-control devices, and

    reservoir-monitoring systems are planned.

    Once these systems are available, the so-

    called intelligent well concept, defined asa modular combination of downhole mon-

    itoring and control systems, will become

    reality. For all these systems, reliability is

    key. Shells targets for monitoring systemsand actuators are 90% probability to sur-

    vive 5 years and 10 years, respectively.

    SYSTEM

    Fig. 1 shows an electrical PDG system for

    pressure and temperature measurement.

    The sensing element is an electronic gaugemounted in a mandrel that is part of the

    tubing string. The gauge is connected to the

    metal-sheathed electrical cable that runs

    along the tubing to the tubing hanger.The coaxial cable contains splices when

    its length is insufficient or if the cable

    breaks during installation. In a land or plat-

    form system, the cable is fed through the

    tubing hanger with compression fittings at

    the top and bottom. The cable can exit the

    tree through a downhole safety-valve-line

    port or a flanged outlet. To provide a pres-sure barrier inside the tree, a bulkhead

    splice is often made immediately outside

    the tree. An instrument cable is used to

    couple this connector to the surface acqui-

    sition unit. In a subsea installation, a wetconnector is used between the hanger and

    the tree. The wellhead outlet can be a

    flanged wet connector coupled to the con-trol pod, to a control line in the umbilical,

    or to an acoustic telemetry system througha diver-matable connector.

    Data from the PDGs are fed into a PC

    through an interface unit that can handle

    several gauges. Data are transmitted to anylocation by use of a communication system,

    such as a satellite link or even floppy disks.

    FIELD DATA

    Historical data were obtained from four

    major suppliers of these systems. The data

    were crosschecked with other sources,including articles in the literature and

    information from operators. Data from 952

    measurement systems, installed from 1987

    through August 1998, were obtained.

    Reports of all failed systems were collectedto determine the failing element.

    ANALYSIS

    The studied systems differ by their inherent

    properties or by the external conditionsunder which they operate. Other factors

    (such as the operator, field, well type, con-

    tractor, and installation date) may influence

    the failure behavior of the system. A physi-cal model explaining the influence of thesevariables on the reliability is not available.

    Therefore, a nonparametric method was

    used to analyze reliability. The results are

    based on the observed track records of the

    installed systems.

    ANALYSIS RESULTS

    Fig. 2 shows the number of installations for

    each year, divided into subsea, platform,

    and land installations. Before 1993, 30 sys-

    tems were installed yearly, whereas approxi-

    mately 100 systems per year were installedfrom 1993 until 1995, reaching a peak of

    192 systems in 1996. After 1996, the num-

    ber of installations decreased. Subsea instal-

    lations account for 39% of the total; approx-imately 61% are platform installations; and

    only a few are land installations.

    Reliability. Every 2 to 4 years, a new gen-

    eration of systems has come on the market.The reliability of each new system should

    improve. Therefore, the survival probability

    was calculated as a function of operational

    time for six 2-year periods: 19871988,19891990, 19911992, 19931994,

    19951996, and 19971998. Between 1987and 1992, substantial progress was made in

    PDG-system reliability: the 5-year survival

    probability improved from 40 to 75%.

    However, since 1992 no further improve-ments have been observed. The result is a

    5-year survival probability of 69% for the

    period 19931998.

    Failing Elements. PDG systems failedbecause of the downhole cable, fixed (such

    as splices and the gauge-to-cable connec-tion) and matable connections, the down-

    RELIABILITY ANALYSIS OF PERMANENT

    DOWNHOLE MONITORING SYSTEMS

    This article is a synopsis of paper OTC

    10945, Reliability Analysis of Per-

    manent Downhole Monitoring Sys-

    tems, by S.J.C.H.M. van Gisbergen,

    Shell Intl. Deepwater Services B.V.,

    and A.A.H. Vandeweijer, Shell Intl.

    E&P B.V., originally presented at the

    1999 Offshore Technology Confer-ence, Houston, 36 May.

    Fig. 1Subsea PDG system.

  • 8/22/2019 JPT1999_10_IS

    4/14

    I N T E L L I G E N T S Y S T E M S

    OCTOBER 1999 29

    hole sensor, and other failures. Fig. 3

    depicts system status 1 year after installa-

    tion and shows the percentage of installa-

    tions still operating and the percentage thathave failed (split by failing element).

    Failures of fixed and matable connectionshave declined from 59% during

    19871988 to less than 7% during

    19951996 and 19971998. Also, reliabili-ty of the cable has improved. However, the

    number of gauge failures has shown an

    increasing trend.

    Current Generation. The authors arbitrar-

    ily define the current generation as systems

    installed during 19951998, 557 systems

    for measuring pressure and temperature.

    The dominant failing element is the gauge

    (40%), followed by the cable (17%).Gauge Failure. Originally, PDG-system

    gauges were identical to the memory gauges

    used in well tests. The lifetime requirement

    for well-test gauges is several months, com-

    pared with 5 to 10 years for PDG systems.To improve gauge reliability, the authors rec-

    ommend use of dedicated electronic circuits

    and improved burn-in and vibration-test

    procedures. Destructive sample testing is

    recommended to verify performance.Testing should be done at actual conditions

    (i.e., in the closed housing, instead of elec-

    tronic boards tested in open furnaces). The

    failure rate of electronic circuitry is temper-ature dependent. Most of the PDG systemsare operating at 100C or less. Use of dedi-

    cated electronics and other efforts are

    extending this limit to 200C.

    Decreased reliability is expected withincreased temperature. As a rule of thumb,

    the failure rate of electronic circuitry dou-

    bles for each 8C temperature increase. A

    decreasing trend of the 1-year system-sur-

    vival probability of systems installed dur-ing 19951998 is a function of bottom-

    hole temperature.

    Cable Failure. Until 1990, all cables con-tained splices, a major source of failures.

    However, splice-free cables in lengths of

    more than 10 000 m are available. Also,

    current cables use an Incoloy 825 sheath

    rather than an American Iron and SteelInst. (AISI) 316L sheath to improve relia-

    bility. Most cable-related failures occurredduring or shortly after installation. Some

    cable failures occurred when the cable was

    crushed by the tubing hanger while landingthe tree. These failures can be prevented by

    use of a protective cap or centralizer for the

    cable in the tubing section, immediately

    below the tubing hanger.Tubing loads can crush the cable, espe-

    cially in severe doglegs. To prevent these

    failures, use of cables with bumper bars is

    recommended where the load on the cable

    is expected to exceed its crush resistance.Cable failures also occur when the cable

    must be guided across large components in

    the completion string. Use of special pro-

    tectors is recommended. Another option is

    to provide a recess in the component forthe cable.

    Fixed-Connections Failure. Fixed con-

    nections include splices and the connection

    between the gauge and cable but exclude

    the make-break connections, such as wet

    connectors. With improved cable quality,

    fewer splices are used. Also, the use of part-ly redundant metal-to-metal seals for fixed

    connections has led to improvements.

    Fixed connections may be a significant partof the unidentified failures. Therefore, theauthors see a need to improve the connec-

    tions further and to use fully redundant

    metal-to-metal seals.

    Matable-Connectors Failure. Although

    most matable connectors are the wet con-nectors in subsea completions, they also are

    used at the wellhead outlet on platform and

    land systems. Failures of these elements

    often are caused by a broken seal where the

    connector is attached to the cable or by an

    improper electrical contact between the

    cable and connector. Use of redundantmetal-to-metal seals has reduced failures.

    Further improvements can be made by tak-

    ing more care during installation.

    Other Failures. Functional testing of the

    complete PDG system after completion alsoshould be completed to ensure that the pod

    interface and downhole system are per-forming to specification. Standardizing

    downhole communication protocol could

    result in fewer types of control cards.

    CONCLUSIONS

    Historically, PDG systems for measuring

    pressure and temperature have exhibited

    low reliability. During 19871992, substan-tial improvements were made that increased

    the 5-year survival probability to 75% for

    systems installed during 19911992.

    However, since 1992, no further improve-

    ments have been made in reliability.Needed improvements to achieve the tar-

    get 5-year survival probability of 90%

    include technical quality, care during instal-

    lation, and management of the interface.

    Financial incentives (such as making thesystem part of the well gain-share-incentive

    scheme or pay-for-data schemes) could

    stimulate improvements.

    Improvements in reliability will berequired not only for PDG systems that

    measure pressureand temperature, but also

    for more complex downhole systems, such

    as inflow-control devices, flowmeters, and

    reservoir-monitoring devices. For all thesesystems, reliability will be a key issue in the

    decision whether to install them. The

    lessons learned from pressure- and temper-

    ature-monitoring systems can be very use-

    ful input to achieve the required high levelof reliability.

    Fig. 3PDG system status (working or failed element) 1 yearafter installation.Fig. 2PDG installations by year.

    Please read the full-length paper for

    additional detail, illustrations, and ref-

    erences. The paper from which the syn-

    opsis has been taken has not been peer

    reviewed. Copyright 1999 OffshoreTechnology Conference.

    Year of Installation

    Period of Installation

    NumberofInstallations

  • 8/22/2019 JPT1999_10_IS

    5/14

    30 OCTOBER 1999

    I N T E L L I G E N T S Y S T E M S

    Designing a fracture-treatment schedule

    that creates the desired propped length is a

    challenge. For given reservoir conditions,

    use of several fluid types and volumes,proppant types and concentrations, and

    injection rates must be considered.

    Hundreds of possible combinations exist

    for modeling each treatment schedule. The

    results of each run must be studied beforeinput parameters are altered for the next

    run to get one step closer to the desired out-come. To reduce the complexity of

    hydraulic-fracture design, an intelligenttool was developed. This tool uses virtual-

    intelligence techniques, neural networks,

    and genetic algorithms. Neural networks

    are tools that (when trained properly) pro-

    vide rapid results (output) for a particularinput. A series of neural networks were

    used to replicate the functionality of a 3D

    hydraulic-fracture computer model.

    METHOD

    To produce a desirable hydraulic-fracturedesign, neural networks were integrated

    with genetic algorithms. The genetic algo-

    rithm searches possible combinations of

    input parameters and finds the most-desir-

    able input combinations. Several neuralnetworks were trained for the design-opti-

    mization process. The neural-network

    model (NNM) is capable of designing treat-

    ment ramp and stage schedules. Specific

    rules (process constraints) can be intro-duced to prohibit unrealistic or unaccept-

    able designs.

    A 3D hydraulic-fracture model (HFM)

    was used extensively to train the neuralnetworks. Designs developed with thismethod provide reasonable accuracy when

    run in the HFM. However, fracture treat-

    ments designed with the NNM require no

    specific expertise in hydraulic-fracturedesign. The NNM provides a starting point

    that is very close to the optimum design. As

    shown in Fig. 1, the engineer provides

    reservoir characteristics and the desired

    fracture geometry as input. The NNM out-

    put consist of fluid and proppant character-istics as well as a detailed treatment sched-

    ule including the number of stages, amount

    of fluid and proppant, and the pump rate.

    RESULTS AND DISCUSSION

    The full-length paper details two fieldexamples. In these examples, a successful

    job designed by an expert engineer was

    modeled with the HFM. The issue was

    whether the NNM could design fracturetreatments comparable with those designed

    by an expert. The NNM was provided with

    reservoir characteristics and the target frac-

    ture length (the same fracture lengthreached with the experts design).

    The first design was a hydraulic fracture

    pumped in a Redfork formation. The NNM

    provided several potential designs that were

    entered into the HFM, thus, giving the

    engineer a choice in selecting the mostappropriate design. The process generated

    four near-optimum designs having fracture

    lengths within 3% of the desired value.

    However, the proppant concentrations inthe fractures are different, a good starting

    point for experts or those with little or no

    experience with sophisticated 3D computermodels. The NNM is not a substitute for

    high-performance computer models but

    can be a useful companion to complement

    such software and make them useful to

    petroleum professionals who are not

    experts in hydraulic-fracture design.The second example tested the NNM

    against a fracture designed by another

    expert in the Teapot formation of the Kaye

    field. The original successful design had

    eight stages. Modeling the original designwith the HFM, the fracture length and con-

    ductivity were determined. The NNM pro-

    vided four fracture designs, three with nine

    stages and the fourth with seven stages. All

    designs generated by the NNM are compa-rable with the original design by the expert.

    The next step in developing the NNM

    includes addition of two modules. The first

    is a set of virtual-intelligence routines toreduce the need for detailed reservoir char-

    acteristics that might be difficult to acquire.The user can provide a suite of wireline logs

    (such as gamma ray, density, and resistivity)

    and let the model generate reservoir char-acteristics. The second module is an eco-

    nomic module to aid selection of the most

    economical design from those provided by

    the NNM.

    INTELLIGENT SYSTEMS TO DESIGN

    OPTIMUM FRACTURE TREATMENTS

    This article is a synopsis of paper SPE

    57433, Intelligent Systems Can Design

    Optimum Fracturing Jobs, by Shahab

    Mohaghegh, Andrei Popa, and Sam

    Ameri, West Virginia U., scheduled for

    presentation at the 1999 SPE Eastern

    Regional Meeting, Charleston, WestVirginia, 2122 October.

    Fig. 1Data-flow schematic of the NNM.

    Please read the full-length paper for

    additional detail, illustrations, and ref-

    erences. The paper from which the

    synopsis has been taken has not beenpeer reviewed.

  • 8/22/2019 JPT1999_10_IS

    6/14

    32 OCTOBER 1999

    I N T E L L I G E N T S Y S T E M S

    The goal of a European Drilling Engineers

    Assn. joint-industry project is to integrate

    an electric motor into a smart closed-loop

    drilling system. It is believed that, on thebasis of feedback from near-bit sensors,

    such a system could adjust drilling parame-

    ters automatically to optimize drilling per-

    formance. In most coiled-tubing-drilling

    (CTD) services, downhole power is frompositive-displacement motors (PDMs). The

    output profile of these motors is well suitedto the drilling environment, providing high

    torque at low rotational speeds. However,short run life, poor performance in high-

    temperature operations, and a limited

    choice of drilling media restrict the effec-

    tiveness of PDMs in many areas where an

    electric motor offers an efficient and reli-able alternative.

    Electric motors have been used success-

    fully for horizontal-well drilling in the for-

    mer Soviet Union. However, more-recent

    attempts to integrate electric motors into arotary-drilling assembly have not succeed-

    ed, mainly because of the difficulties of pro-

    viding a high-capacity electrical link to the

    downhole drilling assembly.Advances in artificial-lift technology

    have enabled a new type of electrical-sub-

    mersible-pump (ESP) installation on CT.

    In these innovative completions, a high-

    capacity power cable is installed inside theCT to isolate and protect the cable from the

    downhole environment. This concept was

    transferred to CTD, and the joint-industry

    project was formed to produce a cost-effec-

    tive electrical-CTD (ECTD) prototype. By

    use of only existing technology, an ESP

    motor was combined with a planetarygearbox and an electromechanical CT con-

    nector. The motor was controlled from the

    surface with a laptop computer connected

    to a variable-speed-drive unit. A com-

    mand/control software package was devel-oped that interrogated the drive to acquire

    and record real-time drilling data from

    the motor.

    ECTDPhase 1 demonstrated fundamental benefits

    of ECTD by providing superior feedback

    from and control of drilling processes inreal time. The power output per unit length

    of the Phase 2 motor is comparable to

    PDMs, while longevity increases of one

    order of magnitude are expected.

    Drive Power. The electric downhole

    motor (EDM) is controlled directly by the

    operator as commands are sent through

    the surface gear and computer, whereas a

    PDM is controlled indirectly by variationsin the mud flow. The electric motor allows

    complete direct control of the motor. Speed

    may be increased or decreased with a joy-

    stick or set with a keyboard instruction.

    Motor stall may be avoided almost entirelyby setting current limits in conjunction

    with weight-on-bit limits. As the motor

    approaches stall condition, a feedback loop

    to the CT unit reduces the weight on bit

    automatically to obtain an acceptable cur-rent level. Thus, the system may be set to

    optimize the rate of penetration (ROP)

    without danger of overpowering the bot-

    tomhole assembly (BHA).Hydraulic power is required only for

    cooling and cuttings removal. This system

    provides control of the drilling process

    while allowing circulation flexibility, which

    could be of high value when passing sensi-tive or weak formations.

    Energized Fluids. The BHA is insensitive

    to aerated or energized drilling media. Air

    drilling may be considered with the electric

    motor. A large range of underbalanced-

    drilling techniques may be used, some of

    which would reduce the performance ofconventional CTD motors.

    High Temperature. The Phase 2 electric

    motor was designed to operate at tempera-

    tures up to 450F, making the motor suit-

    able for high-temperature work where aPDM would have an extremely short life

    span. Vane-type motors also have been pro-

    posed as an alternative.

    Feedback and Control. Continuous feed-back on hole condition, torque, weight on

    bit, and lithology changes enables makingbetter drilling decisions that reduce hole

    problems, speed up the drilling process,

    and allow timely trajectory alterations toensure reaching geological targets. Bit-con-

    dition and performance-drop-off indicators

    from the electric motor may also enable

    optimal timing for routine trips, such as bit-

    change-out runs.

    Scalable Motor. The electric motor has

    been designed in 3.3-ft modular lengths

    that may be combined to increase torque

    and power output. Besides its drilling func-tion, the motor package provides a source

    of electrical and mechanical power for aux-

    iliary BHA functions, such as active trac-

    tion and orientation tools and new devel-

    opments in formation-evaluation and -test-ing equipment.

    Real-Time Data Transmission. The

    power line also provides a high-quality

    telemetry link with the EDM and downholesensors. Real-time feedback from the BHA

    enables precise control of the EDM. In

    Phase 2 of the project, pressure, tempera-

    ture, and weight-on-bit sensors are includ-ed in the BHA. Phase 3 will expand capa-bilities to include full directional drilling,

    with an option to gather gamma ray and

    correlation-resistivity data. Because high-

    bandwidth communication is available

    through the power cable, logging-while-drilling tools also could be incorporated

    into the BHA.

    Motor Longevity. The motor was designed

    with a conservative target life span of more

    than 1,000 hours (drilling in ambient mud

    temperatures of approximately 150F). Onthe basis of preliminary results from the

    ELECTRICAL COILED-TUBING DRILLING:

    A SMARTER DRILLING SYSTEM

    This article is a synopsis of paper

    SPE 52791, Electric Coiled-Tubing

    Drilling: A Smarter CT-Drilling

    System, by D.R. Turner, SPE, XL

    Technology Ltd.; T.W.R. Harris, SPE,

    Shell Expro U.K. Ltd.; M. Slater, SPE,

    Amoco Corp. E&P Technology; M.A.

    Yuratich, SPE, TSL Technology Ltd.;

    and P.F. Head, SPE, XL Technology

    Ltd., originally presented at the 1999

    SPE/IADC Drilling Conference,Amsterdam, 911 March.

  • 8/22/2019 JPT1999_10_IS

    7/14

    Phase 2 motor design, the life span could

    increase to between 2,000 and 5,000 hours,

    depending on the service environment.

    Vibration. Unlike a PDM, the motor shaft

    driving the bit is centered and dynamically

    balanced to reduce vibration and increase

    the longevity of the BHA, especially the bitand sensitive electronic instrumentation.Sensitive measurements, such as nuclear

    magnetic resonance and gyros, could be

    moved nearer to the drilling face.

    Reversible Rotation. With suitable

    (locked) connections, the EDM provides a

    simple means of reversing the direction of

    rotation. As Fig. 1 shows, reversal of BHA

    direction could help to push the BHA

    back up the hole in a sticking environment.Reversible rotation also could be advanta-

    geous in sensitive cutting operations, suchas milling out casing shoes.

    ECTD DEVELOPMENT

    The joint-industry project was split into

    three phases to reduce the overall risk

    exposure. The objective of Phase 1 was to

    prove the concept of ECTD. Existing com-

    ponents were used wherever possible,including an ESP motor section to provide

    downhole power. The motor was shrouded

    to allow mud flow past the motor.

    Phase 2 developed a fit-for-purpose

    drilling motor. A 31/8-in.-outside-diameter(OD), hollow-shaft, brushless direct-cur-

    rent motor was designed. The total length

    of the BHA is 15.3 ft, with a motor length

    of 7.2 ft. The EDM operates without a gear-

    box in the 0- to 1,000-rev/min range with apeak power output of 28 hp at 500 rev/min

    and a stall torque of 290 lbf-ft. Currently,

    the EDM is undergoing tests to evaluate

    the longevity and effectiveness. Fig. 2

    shows the equipment setup used for allthree phases.

    Phase 3 will produce an all-electric BHA

    with electronically controlled directional-

    drilling capabilities. Phase 3 adds gammaray, inclination, azimuth, and tool-facemeasurements to provide vital directional

    and lithological information. A 31/8-in.-OD,

    electronically controlled, dynamically

    steerable system will provide orientation

    and bend ahead of the motor for full direc-tional-drilling functions. A feedback loop

    will be added between the surface con-

    troller (the software command/control

    functions) and the CTD unit. While this

    represents a tentative step toward closed-loop drilling, it is intended that the intelli-

    gent BHA will be able to react to changes inweight-on-bit measurements by controlling

    the rate at which the CT unit injects tubinginto the well.

    Initially, the system would optimize ROP,

    though the implications of integration of

    more-sophisticated geosteering feedback are

    clear. Further developments should enable

    the all-electric BHA to follow a predeter-mined course to locate geological targets

    with small continuous changes in direction.

    This method will ensure that the borehole

    remains smooth and stable to minimize thechances of drilling a dogleg and having to

    deal with its associated problems.

    Further integration of formation-evalua-tion tools will provide a state-of-the-art intel-

    ligent-drilling assembly. Initially, this devel-opment will be controlled by the operator

    through surface software. Additional down-

    hole sensors will enable an automatically

    secured geological target, constant progress

    review by the BHA to maximize ROP, andadjustment of drilling performance to main-

    tain optimal hole condition.

    OCTOBER 1999 33

    I N T E L L I G E N T S Y S T E M S

    Please read the full-length paper for

    additional detail, illustrations, and ref-

    erences. The paper from which the

    synopsis has been taken has not beenpeer reviewed.

    Fig. 2Equipment schematic for testing the ECTD system.

    Fig. 1Rotation effect on the passive-traction tool.

  • 8/22/2019 JPT1999_10_IS

    8/14

    34 OCTOBER 1999

    I N T E L L I G E N T S Y S T E M S

    Arco Alaska Inc. developed the West Sak

    field on the North Slope with several new

    technologies implemented with respect to

    the control system and operations. Oneinvolved the use of an expert-system soft-

    ware package to manage wells equipped

    with electrical submersible pumps (ESPs).

    The development plan included significant

    automation of field drillpads and field oper-ations without increasing staff. Therefore, a

    software tool was chosen, in addition to thebasic capability of a supervisory-control

    and data-acquisition (SCADA) system, toanalyze and advise of abnormal situations

    arising at individual wells. This application

    uses first principles to operate producing

    wells within design constraints of the

    downhole equipment.

    PROBLEM DEFINITION

    Generally, production management has not

    been treated as a real-time function.

    Significant reductions of operating cost and

    increased well productivity can be realizedthrough the use of intelligent systems that

    combine real-time wellhead-sensor infor-

    mation with knowledge of well characteris-

    tics and production operations from people.

    To reduce operating costs, this technologyaddresses increasing the well on-production

    time and optimizing deliverability. The

    SCADA system provides rapid data acquisi-

    tion. Analysis tools are used that contain

    elements of artificial intelligence to captureand apply practical knowledge and assist in

    the management of field assets.

    OBJECT-ORIENTED

    PROGRAMMING

    Traditional software platforms requiretranslation from knowledge held by the

    end user of the softwarein this case, pro-

    duction-technology expertsto the soft-

    ware programmer. The object-oriented-

    programming environment reduces thedevelopment time required to build the

    application by enabling people with the

    production-technology background to

    build the application directly. With object-oriented software, characteristics of the

    wells and drillpads are represented by an

    object. Software operations act with theobjects to produce graphical displays that

    represent the behavior being modeled.Each well object contains well-information

    attributes. Instructions to drill and analyze

    well performance start with the well object,

    which is used generically. When expanding

    the application for multiple wells, theproperties of the well object are inherited

    each time a well is cloned.

    ANALYZING WELL PERFORMANCE

    An ESP system can be analyzed on the basis

    of a single-point stabilized test where thepump-intake pressure and annulus-gas-

    production rate are known. The results are

    tubing flow performance, estimated pump-

    discharge pressure, suction-to-discharge

    pump performance, and a well-inflow-capability curve for a single point at the

    top-of-perforations depth for the tubing-

    head pressure during the test.

    By applying known characteristics for the

    producing zone, the well-inflow capabilityat the top-of-perforations depth can be

    established for producing pressures ranging

    between static reservoir pressure and zero.

    Pressure-traverse procedures can be appliedto transpose the well-inflow characteristics

    to the pump-intake depth, establishing the

    well capability at pump-intake depth. Data

    provided by the pump manufacturer are

    overlaid on the pump-intake-depth well-capability data to provide a benchmark data

    set of operating constraints.

    RULES

    Natural-language rules are used for generic

    control of the behavior of the objects repre-

    sented graphically. Variable interaction and

    knowledge embedded in the rules make theapplication unique. The rules provide intel-

    ligent analysis of situations that can be rec-

    ognized according to sensor-data trends.

    OPTIMIZATION STRATEGY

    This application addresses the following

    elements as criteria to accomplish the

    desired result. These elements are solved in

    the order presented.

    1. Apply intelligent alarming diagnosticinformation in real time to infer downhole

    conditions to determine when a well is introuble.

    2. Operate within the design constraints.

    3. Optimize field performance.A real-time on-line inventory of available

    process-system capacities also can be main-

    tained. Real-time on-line decisions can be

    made to ramp up or ramp down indi-vidual wells to maximize the economical

    benefit within the available processing-sys-

    tem-capacity constraints.

    A primary control-room operator re-

    ceives the alarms and advice generated bythe application. While the operations staff

    monitors production, surveillance engi-

    neers can view historical performance

    curves and production engineers can use

    the application to test a pump configura-tion with well test data sets.

    APPLIC ATION BENEFITS

    Expert technology can solve complex oper-

    ational and information-delivery problems

    to lengthen equipment life, increase pro-duction, and reduce downtime. Knowledge

    is captured and consistency established

    throughout the facilities to reduce operat-

    ing costs by reducing equipment failures.Production is increased by operating thedownhole equipment within design limits.

    Continuous surveillance is achieved,

    and production is accelerated by optimiz-

    ing asset use and minimizing overall oper-

    ating costs.

    MANAGEMENT OF WELL PRODUCTION

    WITH REAL-TIME EXPERT SYSTEMS

    This article is a synopsis of paper SPE

    54635, Management of Well Pro-

    duction Using Real-Time Expert-

    Systems Technology, by Dan McLean,

    SPE, Kenonic Controls Ltd., Jim

    Wilcoxson, Arco Alaska Inc., and

    Roger Clay,Arco E&P Technology, orig-

    inally presented at the 1999 SPE

    Western Regional Meeting, Anchorage,2628 May.

    Please read the full-length paper for

    additional detail, illustrations, and ref-

    erences. The paper from which the

    synopsis has been taken has not beenpeer reviewed.

  • 8/22/2019 JPT1999_10_IS

    9/14

    36 OCTOBER 1999

    I N T E L L I G E N T S Y S T E M S

    Real-time monitoring of the bottomhole-

    assembly (BHA) and drill-bit dynamicbehavior is critical to improving drilling

    efficiency. It allows the driller to avoid

    detrimental drillstring vibrations and main-

    tain optimum drilling conditions through

    periodic adjustments to various surfacecontrol parameters. However, selecting the

    correct control parameters is not a trivial

    task and several correction attempts may be

    required. Therefore, development of effi-

    cient methods to predict the dynamicbehavior of the BHA and methods to select

    the appropriate control parameters is

    important for drilling optimization.

    A revolutionary step in the drillingdynamics field occurred with the develop-

    ment of smart downhole-vibration meas-

    urement-while-drilling (MWD) tools. A

    multisensor downhole MWD tool acquires

    and processes dynamic measurements andgenerates diagnostic parameters that quan-

    tify the vibration-related drilling dysfunc-

    tions. These diagnostics then are transmit-

    ted to the surface in real time with MWDtelemetry. The transmitted information is

    presented to the driller in a simple form

    (e.g., as green, yellow, and red traffic lights

    or color bars) on a display on the rig floor.Basic recommendations for possible cor-

    rective actions also are presented alongside

    the transmitted diagnostics. On the basis of

    this information and by use of his own

    experience, the driller can modify the rele-vant control parameters (such as hook

    load, drillstring rotary speed, and mud

    flow rate) to avoid or resolve a drilling

    problem. This process may require several

    iterations before the desired drilling modeis achieved, and, even then, the result may

    not be optimized.

    Advanced MWD dynamics tools and the

    closed-loop vibration-control concept needa more reliable method of generating the

    corrective advice presented to the driller.One modeling technique being investigated

    is a neural-network (NN) -based method

    that can be used to develop a real-world on-line adviser for the driller in the closed-loop

    drilling-control system.

    NN FUNDAMENTALS

    The first conceptual elements of NNs were

    introduced in the mid-1940s, and the con-

    cept developed gradually until the 1970s.

    The most significant steps in developing

    the robust theoretical aspects of this new

    method were made during the explosion incomputer technology and use of artificial

    intelligence. More recently, interest has

    been generated in applying NNs in controlsystems. These systems have proved reli-

    able in situations with complex, nonlinear,

    and uncertain parameters. Properties that

    make NNs suitable for intelligent controlapplications include the following.

    Learning by experience (human-like

    learning behavior).

    Ability to generalize (map similar

    inputs to similar outputs). Parallel distributed processing.

    Robust in the presence of noise.

    Multivariable capabilities.

    The basic processing element of NNs is

    called a neuron. As shown in Fig. 1a, eachneuron has multiple inputs and a singleoutput. Each time, n, a neuron is supplied

    with an input, p, it computes output, a, on

    the basis of an activation function, ; a

    weight, w; and a bias, b. Fig. 1c shows twoactivation functions.

    Two or more neurons may be combinedin a layer (Fig. 1b). A layer may have a dif-

    ferent number of inputs and neurons. A

    network can have several layers. Each layer

    has a weight matrix, a bias, and an output.The output from each intermediate layer

    becomes the input for the following layer. A

    layer that produces the network output is

    an output layer. All others are hidden lay-

    ers. Thus, the network shown in Fig. 2 hasone output layer and two hidden layers.

    Once a topology and activation functionare defined, training procedures are

    NEURAL NETWORKS FOR PREDICTIVE

    CONTROL OF DRILLING DYNAMICS

    This article is a synopsis of paper SPE

    56442, Application of Neural

    Networks for Predictive Control in

    Drilling Dynamics, by D. Dashevskiy,

    U. of Houston, and V. Dubinsky, SPE,

    and J.D. Macpherson, SPE, Baker

    Hughes Inteq, originally presented at

    the 1999 SPE Annual Technical

    Conference and Exhibition, Houston,36 October.

    Fig. 1NN basics: a. neuron components; b. neurons combinedinto layer; c. activation functions examples.

    Fig. 2Multilayer NN used to simulate a dynamic system(TDL = tapped delay line).

  • 8/22/2019 JPT1999_10_IS

    10/14

    applied. In supervised learning, a set of

    input data and correct output data (targets)

    is used to train the network. The network,

    by use of the training input, produces itsown output. This output is compared with

    the targets, and the differences are used to

    modify the weights and biases. The proce-

    dure for modifying the weights and biasesof a network is called learning rules.

    A test set (inputs and targets not used in

    training the network) is used to verify the

    quality of the NN and how well it can gen-

    eralize. Generalization is an attribute of anetwork whose output for a new input vec-

    tor tends to be close to the output generat-

    ed for similar input vectors in its

    training set.

    CONTROLLED DYNAMIC SYSTEM

    To simulate and control the dynamic

    behavior of a drilling system with an NN,the structure of the system and its relation-

    ship with the outside world must be for-

    malized (Fig. 3). The surface and down-hole equipment is represented by the

    object rig, and the following parameters

    influence its performance.

    Control parameters are those that the

    driller can control interactively to affect rigoutput. These parameters include hook

    load, weight on bit (WOB), rotary speed,

    and mud flow rate and properties.

    Plant characteristics are those that relate

    directly to the drilling equipment, such asgeometric and mechanical parameters of

    the BHA, characteristics of the drill bit and

    downhole motor, and other technical para-

    meters of the drilling rig and its components. Media parameters are those that affect

    rig performance but whose values are

    either unknown or only known to a certain

    degree while drilling. These parameters

    include formation lithology, mechanicalproperties of the formation, wellbore

    geometry, and well profile.

    Because the goal is to drill efficiently, rig

    output defines only those parameters used

    for control, namely rate of penetration(ROP), drillstring and BHA vibration,

    WOB, and rotary speed.

    Values of some of these parameters are

    available in real time at the surface.

    However, an MWD tool is required toobtain values of other parameters, a serious

    limitation in the control process. The limit-

    ed bandwidth of MWD mud-pulse teleme-

    try results in an excessive delay in trans-mitting raw data to the surface. The down-

    hole analyzer can identify each drilling phe-

    nomenon and quantify its severity. The vol-

    ume of data sent to the surface is reducedsignificantly and provides the driller with

    condensed information about the most-

    critical downhole dynamic dysfunctions.The combination of the key components of

    the system is referred to as the plant.

    SIMULATED RESPONSES

    VS . REAL DATA

    Because the amount of data used to train

    the model was limited, the model was not

    trained adequately for all possible combina-tions of input parameters. Therefore, when

    parameter values fell outside the training

    range, attempts to simulate system behav-

    ior produced unsatisfactory results.

    However, the results were sometimes quitemeaningful because a strong correlation

    exists between the values of some down-

    hole parameters (e.g., an increase in WOB

    causes an increase in torque on the bit).

    Good overall agreement was observedbetween real data and those simulated by

    the NN model for ROP and for diagnosis of

    whirl and bending moment. In most cases,

    the simulation error was less than 50%.Interesting results were produced when

    an automated optimizer was used. When a

    severe whirl dysfunction and a moderate

    bending dysfunction were entered, approx-

    imately 15 to 20 time steps (5 to 6 min-utes) were required to stabilize the plant.

    The corrective action requires approxi-

    mately 10 of these time steps (3 minutes)

    to cure the dysfunction and to bring the

    system into the green zone. The drillstringrotary speed was reduced from 80 to 35 to

    25 rev/min, as the WOB was reduced from

    8,000 to 2,000 lbm. Two minutes later, the

    WOB was increased gradually to 11,000lbm and the rotary speed was raised to 60

    rev/min. By reducing the dynamic dysfunc-

    tions, the ROP increased by 600%. When a

    severe stick/slip dysfunction was intro-duced, the simulator recommended

    increasing rotary speed while decreasing

    WOB, then bringing the values of the con-trol parameters to new levels.

    These and other simulated scenarios

    demonstrated that the corrective actions

    suggested by the simulator could optimize

    the system in an efficient manner. Theseactions are in good agreement with com-

    mon empirical steps used to resolve similar

    drilling problems.

    CONCLUSIONS

    The NN simulator, with its predictive and

    optimization capabilities, is a natural step

    to improve a drilling-dynamics simulator.The power of NNs allowed a more accurate

    simulation of the nonlinear drilling system

    through observation of its dynamic behav-

    ior. However, the following serious limita-

    tions were encountered. A very limited amount of data was used

    for training the model.

    Data points were very localized and

    provided an uneven distribution.

    Several important parameters, such asmud properties, were not used for model

    construction.

    No deviated-well data were available.

    No supplemental formation-evaluationMWD data were used in the simulation.

    Overcoming these limitations should

    help improve the models accuracy signifi-

    cantly. In addition, experimental validation

    of the modeling, prediction, and optimiza-tion capabilities of the simulator in the field

    is crucial for its future application.

    OCTOBER 1999 37

    I N T E L L I G E N T S Y S T E M S

    Please read the full-length paper for

    additional detail, illustrations, and ref-

    erences. The paper from which the

    synopsis has been taken has not beenpeer reviewed.

    Fig. 3Plant definition and data flow chart.

  • 8/22/2019 JPT1999_10_IS

    11/14

    38 OCTOBER 1999

    I N T E L L I G E N T S Y S T E M S

    The lift-gas-injection rate correlates to the

    oil-production rate. State-of-the-art elec-

    tronic flow controllers are used to improve

    the efficiency of the injection process.Traditional methods of controlling gas

    injection use a fixed orifice or a gas-flow

    regulator. Where the lift-gas-supply pres-

    sure is reasonably stable, a simple choke

    will suffice for gas control. When certainconditions exist, such as the presence of

    hydrates or cool ambient temperatures,freezing may occur at the injection choke

    and cause a reduction or complete blockageof injection. Where the lift-gas-supply pres-

    sure fluctuates, a gas-flow regulator often is

    placed upstream of the choke to inject gas

    at a constant volume.

    In a stable situation, the optimum ratewould remain constant; however, stability

    is rare. Reservoir changes, injection pres-

    sure, total gas available for injection, and

    water production are dynamic variables

    that affect overall production. With an elec-tronic controller, each of these variables can

    be accounted for on a real-time basis and

    adjustments can be made to the system to

    yield optimum production.Electronic gas-lift controllers have

    proved to be effective in maintaining the

    production from constant-rate wells on a

    controller-by-controller basis. Individual

    controllers can be linked directly (hardwired) or remotely through radio, modem,

    or microwave communication. Once

    linked, data can be exchanged through a

    supervisory-control-and-data-acquisition

    (SCADA) system, which, in turn, can pass

    data to a field-modeling program that per-forms complete gas-lift-system analysis.

    Although the field-modeling program pro-

    vides a more-in-depth field overview, use ofthe controller on a well-by-well basis can

    optimize individual-well production if an

    unlimited supply of lift gas exists. Because

    an unlimited supply is unlikely, each con-

    troller can be configured to restrict theamount of injection gas available to

    each well.

    Traditionally, the optimum gas-injection

    rate is the flow rate that yields the maxi-

    mum oil production. Now, it is recognizedthat a unique point exists on a gas-lift-per-

    formance curve where the cost of the addi-

    tional injection gas is greater than the addi-

    tional profit realized from the increased oilproduction. This point is now considered by

    most to be the optimum gas-injection rate.

    Although the curve is generated by a step-

    rate well test, determination of the optimum

    point requires an economic analysis.

    MULTIWELL INSTALLATION

    On many offshore multiwell production

    platforms, local compressors supply theinjection gas and the capacity is sufficient

    to produce all the wells at their optimum

    rates. When compressors are out of service

    for repair or maintenance, the capacity

    often becomes insufficient. In these circum-stances, it is important to have accurate

    production-test data on each well to enable

    proper injection-gas allocation.

    This automated continuous-gas-lift con-

    trol system has an electronic gas-lift con-troller that monitors injection-gas flow rate

    and controls an automated choke. Each

    wells gas-lift control algorithm is dynamic

    and based on that wells performance. Oil-production-rate data are plotted as a func-

    tion of gas-injection rate to generate the

    gas-lift-performance curve. The controller

    uses this data in its control logic to ensure

    that each well receives its optimum injec-tion rate.

    The systems primary objective is to con-

    trol the injection gas to each well to opti-

    mize the gas-injection rate. The rates are

    held constant, even when the supply pres-sure varies. An economic analysis can use

    the wells production-performance curve to

    determine the optimum injection rate. Byuse of the compressor-output data to deter-

    mine the total amount of injection gas

    available, the controller can be configuredto optimize gas injection for each well.

    Unlike a simple regulator, should the

    injection gas become limited, the controller

    can be configured to inject less gas to the

    less productive wells but continue to injectthe optimum amount to the stronger pro-

    ducers. As injection gas becomes limited,

    the lift-gas-supply pressure will decrease

    and, therefore, the total available gas-injec-tion rate also decreases.

    APPLIC ATIONS

    One of the benefits of electronic gas-lift

    controllers is their capability to properly

    use available lift gas in situations where all

    necessary or desired gas is unavailable for

    lifting purposes. Fields with limited gassupplies must be monitored to ensure lift

    gas is properly allocated by gas injection to

    wells that yield a higher production rate.

    Proper allocation in a field where supply

    pressures fluctuate becomes very difficult.These pressure fluctuations can be caused

    by compressor-output problems, check-

    valve failure, and system-back-pressure

    fluctuations. Recent installations of elec-tronic gas-lift controllers have demonstrat-

    ed that controlling the injection, regardless

    of the pressure fluctuations, yields an over-

    all field-production increase.

    FUTURE PLANS

    Design development and prototype testingare in progress to incorporate an optimizing

    routine within the electronic gas-lift-injec-

    tion controller. Performance curves gener-ated for each well could be transferred to amathematical equation by use of a curve-fit

    routine. The controller then could be pro-

    grammed to find solutions for gas-injec-

    tion-rate allocations that would yield the

    highest oil recovery. The primary improve-ment would be for the controller to opti-

    mize allocation decisions.

    AUTOMATED CONTINUOUS-

    GAS-LIFT CONTROL

    This article is a synopsis of paper SPE

    52123, New Automated Continuous-

    Gas-Lift Control System Improves Op-

    erational Efficiency, by Terry Bergeron

    and Andrew Cooksey, Halliburton

    Energy Services Inc., and J. Scott

    Reppel, Texaco E&P, originally present-

    ed at the 1999 SPE Mid-continent

    Operations Symposium, Oklahoma City,Oklahoma, 2831 March.

    Please read the full-length paper for

    additional detail, illustrations, and ref-

    erences. The paper from which the

    synopsis has been taken has not beenpeer reviewed.

  • 8/22/2019 JPT1999_10_IS

    12/14

    40 OCTOBER 1999

    I N T E L L I G E N T S Y S T E M S

    Technological advances in the oil and gas

    E&P industry have improved the efficiency

    of the processes required to search and pro-duce hydrocarbons. E&P companies can

    apply these advances in reservoir-manage-

    ment techniques and system technologies

    to create intelligent, self-sufficient systems

    for exploring and producing hydrocarbons.These intelligent systems provide precise

    access to hydrocarbons, enhanced reservoirproduction over the asset life, and control

    of produced-fluids processes to improve oilrecovery, decrease the number of unsched-

    uled interventions, and minimize the envi-

    ronmental impact.

    Process inefficiencies can have a signifi-

    cant impact on project costs, up to 30% ofthe overall costs for producing hydrocar-

    bons. The need to optimize the processes

    used to search and produce hydrocarbons

    has driven the development and deploy-

    ment of new technologies in the oil field.These new technologies should improve

    access to hydrocarbons, decrease the num-

    ber of wells drilled, optimize reservoir pro-

    duction, improve produced-fluids process-

    ing, and integrate data management foraccess to and updating of reservoir and pro-

    duction information.

    The use and integration of new tech-

    nologies for optimized reservoir manage-ment and improved hydrocarbon recovery

    will create more productive wellbores, in

    less time, with fewer environmental risks.

    Intelligent-system technology includes 4D-

    seismic surveys, closed-loop drilling, intel-

    ligent completions, downhole oil/waterseparation (DOWS), reservoir modeling,

    and knowledge-management technology.

    The petroleum industry relies on new tech-

    nologies and processes to reduce hydrocar-bon-exploration costs.

    TECHNOLOGY REQUIREMENTS

    Optimization of hydrocarbon production

    depends on sensor and material technolo-gies and new power-generation and fiber-

    optic systems. Sensor technology for moni-

    toring the parameters inside and outside the

    well is critical for optimizing and under-

    standing the exploration processes. Sensortechnology provides on-demand access to

    the information needed to achieve hydrocar-bon-production and cost goals. Material

    technology also is playing a critical role infulfilling exploration requirements.

    Composite materials are entering the oil field

    in areas such as coiled-tubing and drillable

    completion tools. Deformable-pipe technol-

    ogy will affect many sectors, includingdownhole multilateral junctions where pre-

    fabricated joints with high-pressure integrity

    can be built and deployed in the wellbore.

    New power-generation systems, such as

    fuel cells and fuel reformers, may allow elec-tricity generation at the wellsite from oil and

    gas. New microgeneration plants could

    improve industry economics in such areas

    as heavy-oil production and processing.Fiber-optic cable and sensor technology will

    improve the reliability of downhole systems

    and the ability to place sensors in the well-

    bore. Distributed sensors, embedded inside

    the fiber-optic cable, will allow monitoringthe entire well instead of a specific zone.

    Power from light can change the way ener-

    gy is delivered to systems in the oil field.

    WELLBORE CONSTRUCTION

    New ways of extracting hydrocarbons are

    vital to achieve breakthroughs in oilfieldeconomics in the new decade. The first step

    is to design and build the main wellbore

    and associated laterals that will comple-

    ment the production systems. As these

    wellbores are built, simultaneous advancedformation evaluations will be conducted

    and the information gathered from these

    evaluations will be integrated into reservoir

    modeling programs, creating virtual pic-

    tures of target reservoirs.Extended-reach-drilling, seismic-while-

    drilling, smart-drill-bit, underbalanced-

    PRODUCTION AND RESERVOIR

    MANAGEMENT APPLICATIONSPaulo Tubel, SPE, Weatherford-SubTech Intelligent Systems

    This paper (SPE 58956) is taken from

    an original manuscript, Production and

    Reservoir-Management Applications

    Using Intelligent Systems, submitted at

    the invitation of the Journal of

    Petroleum Technology. This paper hasnot been peer reviewed.

    Fig. 1Surface-system layout for UBD operation.

  • 8/22/2019 JPT1999_10_IS

    13/14

    drilling (UBD), geosteering, and coiled-tub-

    ing-drilling technologies are improving

    drilling efficiency, reducing the cost of

    drilling, and minimizing the total number ofwells being drilled in fields. In this new

    form of well construction, communication

    and information management have new and

    larger roles. Instrumentation is added to thedrilling equipment and then to the wellbore

    to make the system intelligent. This sys-

    tem can acquire and process more informa-

    tion faster than conventional methods.

    A key technology for wellbore construc-tion is UBD operations, which reduce dam-

    age to the formations during drilling

    (Fig. 1). With UBD, the bottomhole pres-

    sure is designed to be less than the pressure

    in the formation being drilled. This under-

    balanced condition is achieved by loweringthe density of the drilling fluid by injecting

    gas, such as nitrogen, into the system.Advantages of this technology include pre-

    venting lost-circulation problems, minimiz-

    ing damage to pay zones, increasing pene-tration rates, extending bit life, decreasing

    mud loss, and enabling production

    while drilling.

    Most UBD operations have been onshoreapplications in the U.S. and Canada.

    Concerns about safety, logistics, and equip-

    ment have restricted the use of UBD off-

    shore. However, new techniques and equip-

    ment are being developed for offshore usein deep and ultradeep water.

    PRODUCTION OPTIMIZATION

    Production optimization requires down-

    hole systems that enable maximum hydro-

    carbon recovery with minimal interventionto maintain production at its maximum

    level. Development of multilateral wells has

    heightened the need for monitoring and

    control of production parameters for each

    lateral zone inside the wellbore. Remotecontrol of the pressure at each lateral

    enables simultaneous production from

    multiple zones within a single main bore.

    The result is maximized rate of return onthe investment.

    Fig. 2 shows an intelligent-completion

    system (ICS) that is capable of controlling

    the position, the state of the tools, and the

    flow of fluids in wellbores. Normally, the sys-

    tem is composed of surface control hardwareand downhole modules that permit the

    operator to monitor and control, from a sin-

    gle location, the activities of different zones

    in a number of wells in real time. To fulfill

    the needs in different areas of the world, ser-vice companies are developing two versions

    of intelligent downhole completions: fullyelectric and hydraulic-actuated systems.

    Frequently, water is produced with oil

    and gas and, as the field matures, more

    water than hydrocarbons is produced, caus-ing a negative impact on operations and a

    reduction in the life of a field. The main

    purpose of DOWS technology is to separate

    water from oil downhole inside the well-

    bore and leave the water in the ground.

    IN-SITU POWER GENERATION

    An emerging technology for processing

    hydrocarbons at the wellsite is developing

    rapidly. Converting gas and oil into elec-

    tricity on location and connecting that elec-tricity to the local power grids may change

    the way energy is processed and transport-

    ed. Simple, efficient, and reliable fuel-to-

    electricity-conversion technologies are

    available. Promising technologies includefuel reformers, turbines, and fuel cells.

    RESERVOIR MONITORING

    New technology has improved the accura-

    cy, resolution, and speed of data acquired

    for the reservoir-monitoring process. Time-lapsed 3D-seismic surveys are used to

    model water movement in the wellbore

    during production, which enables a better

    understanding of water encroachment intothe hydrocarbon-producing zones and

    should help optimize hydrocarbon produc-

    tion and achieve higher recovery.

    Emerging seismic-sensor technology

    will enable permanent placement ofsources and receivers inside the wellbore,

    which will allow 4D-seismic surveys on

    demand. Permanent placement of the

    receivers in the wellbore will eliminate

    position uncertainty of conventionalretrievable receivers and will generate data

    with higher resolution and a better sig-

    OCTOBER 1999 41

    I N T E L L I G E N T S Y S T E M S

    Fig. 2Technologies under development to optimize reservoir management and improveoil recovery.

  • 8/22/2019 JPT1999_10_IS

    14/14

    nal/noise ratio than is achieved with sur-

    face seismic surveys.

    LEVERAGING FROM OTHER

    INDUSTRIES

    Robots are used in space exploration. The

    same technology used to survey Mars may

    be used in the oil industry. Permanentlydeployed learning systems will be capableof investigating, repairing, or replacing

    equipment in the wellbore. Learning-

    behavior machines will allow the operator

    to retrieve information continuously, which

    enables evaluation of reservoir and wellboreconditions. Advanced software techniques,

    such as neural networks and fuzzy logic,

    will provide the decision-making process

    and autonomy required for these new

    machines to operate inside the wellbore.Fiber-optic-based instrumentation is

    moving from the telecommunications and

    medical industries to the oil field. This new

    technology can bring major changes in the

    way data acquisition and processing, as

    well as downhole-tool control, are per-formed. The functional properties of fiber-

    optic sensors include remote operation,

    immunity to electromagnetic interference,

    use in high-temperature and -pressure envi-

    ronments, small size, long-term reliability,and the capability of responding to a wide

    variety of measurements. Real-time on-line

    measurement and monitoring of key bore-

    hole parameters are important to optimizedownhole production. Fiber-optic technol-

    ogy can achieve improvements over electri-

    cal-based systems in the areas of capability,

    cost-effectiveness, and reliability. These

    improvements can lead to reduction ofdevelopment and operating costs and to

    increased hydrocarbon recovery.

    CONCLUSIONIntelligent systems can improve operations

    and optimize the processes used both

    downhole and at the surface. Technology ischanging the way oil E&P is achieved, from

    floating production, storage, and offloading

    vessels, to fewer platforms for production

    because of multiphase pumping, multilat-

    eral drilling, and improved ICS.Integration of new sensor, hardware, and

    communication technologies with existing

    tools will be critical for complete systems

    and successful introduction of new prod-

    ucts. To optimize the E&P processes, sys-tems such as seismic, drilling, completions,

    production, hydrocarbon processing, and

    artificial lift should be integrated to provide

    entire packages that will achieve productiongoals. Hardware and software standards are

    needed for applications from drilling to

    enhanced recovery. Plug-and-play systems

    with an open architecture for hardware and

    software will provide proper and timelyintroduction of systems and technologies in

    the field without redesigning the host sys-

    tem for each sensor upgrade. The ability to

    review, use, modify, and integrate historical

    and real-time data into shared-earth modelsis critical for improving drilling and pro-

    duction processes. Knowledge management

    will be used to evaluate hydrocarbon

    reserves throughout the life of the well toincrease the recoverable resources from the

    reservoirs significantly.

    Partnerships among service companies

    and between E&P companies and service

    companies will enable resource sharing, todevelop new systems. These partnerships,

    through joint-industry projects, will play a

    significant role in the development and

    introduction of new technologies tooil fields.

    I N T E L L I G E N T S Y S T E M S