DEWFORA Kick-off meeting Work-package 6 (Coordinator JRC) Implementation of improved methodologies in comparative case studies. JRC – P. Barbosa and J. Vogt PIK – F. Hattermann and S. Fournet UPORTO – R. Maia and J.P. Pego NFC – M. E. Elshamy and Mohamed Ahmed - PowerPoint PPT Presentation
25
DEWFORA Kick-off meeting Work-package 6 (Coordinator JRC) Implementation of improved methodologies in comparative case studies JRC – P. Barbosa and J. Vogt PIK – F. Hattermann and S. Fournet UPORTO – R. Maia and J.P. Pego NFC – M. E. Elshamy and Mohamed Ahmed IAV – A.S. Bennasser, Y. Imani, and O. Lahlou WATERNET – D. Love and J.-M. Kileshye-Onema
Transcript
Page 1: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

DEWFORA Kick-off meeting

Work-package 6 (Coordinator JRC)

Implementation of improved methodologies in comparative case studies

JRC – P. Barbosa and J. VogtPIK – F. Hattermann and S. FournetUPORTO – R. Maia and J.P. PegoNFC – M. E. Elshamy and Mohamed AhmedIAV – A.S. Bennasser, Y. Imani, and O. LahlouWATERNET – D. Love and J.-M. Kileshye-Onema

Page 2: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 2

WP6. Implementation of improved methodologies in comparative case studies

OUTLINE of PRESENTATION

• Main Objectives

• Case Studies

• Tasks 6.1 to 6.6

• Effort in Person-month by Participant and by Task

• Deliverables and Timing

• Planning for 2011

• Challenges and Risks

Page 3: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 3

WP6 Main Objectives

• Case studies will serve as demonstration sites for the implementation of the improved methodologies developed in work packages 3, 4, and 5

• A pre-operational pan-African system for drought monitoring and forecasting will be developed and tested.

• A comparative review of drought forecasting in Europe and Africa will be done.

• Relations exist with work packages 2, 3, 4, 5, 7 and 8(?).

Page 4: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 4

WP6 – 4 Case Studies + Pan-African

Page 5: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 5

WP6 TasksTask 6.1: Eastern Nile Basin(Partners: MWRI-NFC-NBCBN , IHE, ECMWF, GFZ, DCER. Months 1 – 30)

Task 6.2: Limpopo Basin(Partner: WaterNet, IHE, GFZ, UEM, WRNA, CSIR. Months 1 – 30)

Task 6.3: Oum-er-Rbia Basin(Partner: IAV, UPORTO, CSIR. Months 1 – 30)

Task 6.4: Niger River basin(Partner: PIK, IHE, WI. Months 1 – 30)

Task 6.5 Development and testing of a Pan-African forecasting system(Partner: JRC, DELTARES, IHE, ECMWF, ICPAC. Months 1 – 34)

Task 6.6 Drought forecasting: EU/Africa perspectives(Partner: UPORTO, JRC, MWRI-NFC-NBCBN , IAV, WRNA. Months 12 – 34)

Page 6: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 6

Task 6.1 Eastern Nile Basin

MWRI-NFC-NBCBN: Mohamed Elshamy, Mohamed AhmedIHE: Shreedhar Maskey, Patricia Trambauer, Marloes MulECMWF: Florian Pappenberger, Emanuel DutraGFZ: Heiko Apel, Yeshewatesfa Hundecha, José Miguel DelgadoDCER: Elftatih Eltahir, Mudathir Zaroug

AIM: • to provide and test all the improved tools for drought warning and prediction of

the effect of climate change on drought risk in the region. The study will focus on the Blue Nile and Atbara River basins.

ROLES and RESPONSIBILITIES: • TBD during Kick-off meeting

Page 7: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 7

Task 6.1 Eastern Nile Basin

OBJECTIVES:

• Conduct statistical (e.g. based on ENSO) and dynamical seasonal forecasting in the Blue Nile and Atbara Basins (linked to Task 4.1)

• Pilot the methods to produce a seasonal drought warning, combining indicators, thresholds and model outputs from meteorological models and hydrological models (WP 3 and 4). NFC already has hydrological models, and these will be used as a starting point in this case study.

• Pilot the methods to identify the effects of climate change on drought risk using climate projections and vulnerability maps from WP 3.

• Recommend methods for strengthening drought preparedness and improving farming practices in response to drought in the Blue Nile basin.

Page 8: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 8

Task 6.2: Limpopo BasinWaterNet: David Love, Jean-Marie Kileshye-OnemaIHE: Shreedhar Maskey, Patricia Trambauer, Marloes MulGFZ: Heiko Apel, Yeshewatesfa Hundecha, José Miguel DelgadoUEM: Nelson Matsinhe, Jaime PalalaneWRNA: Washy Nyabeze, Mike Kubare, Mike TumbareCSIR: Francois Engelbrecht, William Landman

AIM:• The focus in this case study is on the flow of information during drought early

warning. Information will be generated by the forecasting system developed in WP 4. This information will flow from the warning system through the institutional framework from regional to local scale. The Limpopo is therefore a pilot for the application of DEWFORA’s drought early warning framework. In close collaboration with other stakeholders in the region, improvements in the institutional framework and procedures will be suggested and implemented, building on the technical developments.

ROLES and RESPONSIBILITIES: • TBD during Kick-off meeting

Page 9: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 9

Task 6.2: Limpopo Basin

OBJECTIVES:

• Implement improvements to existing monitoring and forecasting systems and drought mitigation policies by coupling meteorological, hydrological and agricultural forecasting tools into a water allocation model (WP 4).

• Pilot the drought early warning framework by identification and involvement of the end-users and analyze how the issued warnings flow through the institutional structure. The piloting will reveal potential shortcomings in the institutional structure, which will result in recommendations for improvement.

Page 10: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 10

Task 6.3: Oum-er-Rbia BasinIAV: A.S. Bennasser, Y. Imani, and O. LahlouUPORTO: Rodrigo Maia, Joao Pedro PêgoCSIR: Francois Engelbrecht, William Landman

AIM:• The aim of this case study is to further agricultural drought forecasting by

means of the newly developed indicators (WP 3) and model techniques (WP 4). First of all the seasonal forecasting of agricultural drought in the basin will be improved to gain lead time for effective drought mitigation. Second, recommendations will be made how to reduce vulnerability through the implementation of better adapted agricultural practices. The case study will be led by IAV and will capitalize on the results from the MEDROPLAN project (MEDA-Water).

ROLES and RESPONSIBILITIES: • TBD during Kick-off meeting

Page 11: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 11

Task 6.3: Oum-er-Rbia Basin

OBJECTIVES:

• Test improved agricultural drought indicators (WP 3) and forecasting of agricultural drought (WP 4)

• Transfer drought forecasts to drought warnings according to the framework developed in WP 5.

• Pilot and analyze the effectiveness of adapted agricultural practices on vulnerability.

Page 12: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 12

Task 6.4: Niger River basinPartners: PIK: Fred Hattermann, Samuel FournetIHE: Shreedhar Maskey, Patricia Trambauer, Marloes MulWISO: Bakary KONE, Nicolas Tubbs, Chris Baker, Jaime Garcia Moreno

AIM:• The aim of this case study is to provide a climate projection for the

region to strengthen preparedness to droughts and in this way improve future food security (WP 5, Task 5.3). The implementation of this case study will be closely linked to the WETwin project (FP7).

ROLES and RESPONSIBILITIES: • TBD during Kick-off meeting

Page 13: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 13

Task 6.4: Niger River basin

OBJECTIVES:

• Application of a mesoscale distributed eco-hydrological model combining hydrology and agriculture (and other vegetation types).

• Pilot the drought preparedness by predicting future hydrological and agricultural drought risk through climate projections using model outputs from WP 3 and 4.

• Trade-off upstream – downstream management with one focus on the Inner Nile Delta

Page 14: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 14

Task 6.5 Development and testing of a Pan-African forecasting systemJRC: Paulo Barbosa, Jürgen Vogt, N.N.DELTARES: Micha Werner, Sophie Vermooten IHE: Shreedhar Maskey, Patricia Trambauer, Marloes MulECMWF: Florian Pappenberger, Emanuel DutraICPAC: Ouma Gilbert

AIM:• The aim of this case study is to develop and test a pre-operational system for

drought monitoring and forecasting in Africa at the continental scale, using medium-range, monthly and seasonal probabilistic forecasts. For the implementation of this case study the project will capitalize on the experience gained by JRC with the development of the European Drought Observatory (EDO) and with the European Flood Alert System (EFAS), as well as with pilot studies on flood and drought early warning in the Horn of Africa. This will provide at the same time, the opportunity to compare the two systems.

ROLES and RESPONSIBILITIES: • TBD during Kick-off meeting

Page 15: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 15

Task 6.5 Development and testing of a Pan-African forecasting system

OBJECTIVES:• Collection of meteorological and ancillary data needed for implementation of the

case study.• Development and testing of drought indicators at Pan-African scale. From the

drought indicators and extreme forecast indices developed in Task 3.1, the ones suitable for Pan-African scale will be selected and tested.

• Risk assessment by integration of vulnerability and hazard at Pan-African level. Indicators for vulnerability and hazard estimates will be integrated in this task by using the tools and results produced in WP 3. The selected global models (ECMWF for meteorology and the selected hydrological model from WaterMIP) will be used in order to produce current Pan–African vulnerability and risk maps as well as future projections.

• Integration of meteorological, hydrological and agricultural drought forecasts at Pan-African level into an African drought map server. The results produced in WP4 will be integrated in this task to produce Pan–African drought forecasts and integrated with the results from the case studies at different spatial scales.

• Development and implementation of the African drought map server. This server will contain all the products created in the previous tasks. Products from different spatial scales, going from continental to regional will be integrated by the map server.

Page 16: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 16

Task 6.6 Drought forecasting: EU/Africa perspectivesUPORTO: Rodrigo Maia, Joao Pedro PêgoJRC: Paulo Barbosa, Jürgen Vogt, N.N.MWRI-NFC-NBCBN : Mohamed Elshamy, Mohamed AhmedIAV: A.S. Bennasser, Y. Imani, and O. LahlouWRNA: Washy Nyabeze, Mike Kubare, Mike Tumbare

AIMS:• Comparative review of drought forecasting in European and African river

basins. • Evaluation of the implementation of the newly proposed methodologies to

selected African river basins • Guidelines for bilateral improvement of forecasting methods

ROLES and RESPONSIBILITIES: • TBD during Kick-off meeting

Page 17: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 17

Task 6.6 Drought forecasting: EU/Africa perspectives

OBJECTIVES:•Trends on drought monitoring and early warning systems in Europe. Capitalizes from previous (e.g. MEDROPLAN, AquaStress, Watch, CIRCE) and ongoing (XEROCHORE, MIRAGE, CLIMB, WASSERMed) projects. Focus on river basins from Southern Europe (e.g.,from Portugal, Spain and Greece).

•Performance of improved drought monitoring and early warning systems in Africa. Uses the output from WP2 and WP5 and the results from the regional case studies (Tasks 6.1 to 6.5)

•Comparison of drought forecasting in Europe and Africa

Page 18: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 18

Participant

number

Participant short name(Tasks)

Person-months per participant

1 DELTARES (Task 6.5) 22 UNESCO-IHE (Tasks 6.1, 6.2,

6.4 and 6.5)7

3 ECMWF (Tasks 6.1 and 6.5) 84 JRC (WP6 Leader, Task 6.5

Leader and 6.6)26

5 PIK (Task 6.4 Leader) 106 GFZ (Tasks 6.1 and 6.2) 109 UPORTO (Task 6.6 Leader,

and 6.3)10

10 WI (Task 6.4) 1811 MWRI-NFC-NBCBN (Task

6.1 Leader and 6.6)12

12 DCER (Task 6.1) 1213 ICPAC (Task 6.5) 1014 UEM (Task 6.2) 1215 CSIR (Tasks 6.2 and 6.3) 516 WRNA (Tasks 6.2 and 6.6) 617 IAV (Task 6.3 Leader and

6.6)12

18 WATERNET (Task 6.2 Leader)

9

Total 169

Effort in Person-month by Participant

Page 19: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 19

Effort in Person-month by Task

Task 6.1 Task 6.2 Task 6.3 Task 6.4 Task 6.5 Task 6.6DELTARES 2

UNESCO-IHE 2 2 2 1

ECMWF 2 6

JRC 2 2 2 2 16 2

PIK 10

GFZ 5 5 ? 5

UPORTO 4 6

WI 18

MWRI-NFC-NBCBN

10 2

DCER 12

ICPAC 10

UEM 12

CSIR 2 3

WRNA 5 1

IAV 10 2

WATERNET 9

TOTAL 33 3732 19 24 32 35 13

Page 20: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 20

WP6 – Deliverables and TimingDeliverable

Title Lead beneficiary Estimated indicative persons-month

Delivery date

D6.1 Inception report for each case study

Case study leaders + JRC

20.00 October 2011

D6.2 Final report for each case study

Case study leaders + JRC

48.00 101.00

April 2013

D6.3 Testing of drought indicators at Pan-African level

JRC 10.00 8.00 June 2012

D6.4 Integration of drought vulnerability and hazard into risk maps at the Pan-African level

JRC 10.00 8.00 October 2012

D6.5 Integration of drought forecasting tools for Africa into the Pan-African map server

JRC 6.00 8.00 October 2013

D6.6 Development and implementation of Pan-African map server

JRC 35.00 11.00 June 2013

D6.7 Performance of the proposed improved drought forecasting methods applied to selected river basins

UPORTO 20.00 8.00 June 2013

D6.8 Comparative review of drought forecasting in Europe and Africa

UPORTO 20.00 5.00 August 2013

Page 21: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 21

WP6 - Planning for year 2011

D6.1: Inception report for each case study: For each regional case study (Task 6.1, 6.2, 6.3 and 6.4), an inception report will be delivered in Month 10 (October 2011). Besides general descriptions of the case study area, this report will contain information, tailored to the specific case study objectives such as the current problems related to drought, the available hydro-meteorological data to be used throughout the case study, drought management practices and stakeholders involved in drought management. This report is needed as input for WP 2, 3 and 4.

Page 22: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 22

WP6 - Planning for year 2011January-October 2011:• Assess the existing drought monitoring and forecasting networks, practices

and capacities in the region and provide this information to WP 2.• Synthesize the current state of the art of climate research in the basin.• Identify key stakeholders in the region to be invited to participate in the

Stakeholders Platform and provide this information to WP 7.• Identify and maintain contact with end-users throughout the project.• Collect case specific meteorological and ground data needed for

implementation of the case study, provide this information to WP 4.• Collect information on regional water resources use for identification of indicator

thresholds in WP 3.• Collection of meteorological and ancillary data needed for implementation of

Task 6.5.

October 2011-December 2011• Investigate the applicability of the methodologies developed in WP 4• Development and testing of drought indicators at Pan-African scale (Task

6.5) with input from Task 3.1.• Task 6.6 will start in December 2011

Page 23: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 23

WP6 – Challenges and risks

Challenges:

• To really tailor the work to the needs of the local people

• Communication of uncertainty in any scenario results

• Promote exchanges between stakeholders and decision-makers

• Exchange information with other ongoing projects

Page 24: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 24

WP6 – Challenges and risksRisks:

• Data accessibility and missing data management

• After the inception report on month 10 no other deliverables were foreseen for each regional case studies until the final report on month 30 (June 2013)

• There is a need to establish milestones for each regional case study between month 10 and month 30

• Broad range of regional specificities in Africa. The case studies are not all addressing the same issues. There is a need to define intermediate Task Meetings in order to better steer and harmonize the case studies

• The WP6 coordinator should put some effort (person-month) following the case studies (proposal shown in previous Table)

Page 25: JRC  – P. Barbosa and J. Vogt PIK  – F. Hattermann and  S. Fournet UPORTO  – R. Maia and J.P. Pego

April 22, 2023 25

WP6 – Challenges and risks

Risks (cont.):

• WP6 provides information but is also dependent from other work packages (WP2, WP3, WP4 and WP5)

• Task 6.6 is dependent from other case-studies (Tasks 6.1 to 6.5)

• Task 6.5 is partially dependent from other case-studies (Tasks 6.1 to 6.4)