+ All Categories
Home > Documents > Jt)jg a 4 foot x 30 foot piling pier to be connected by a 4 foot x 12 foot walkway to an existing 47...

Jt)jg a 4 foot x 30 foot piling pier to be connected by a 4 foot x 12 foot walkway to an existing 47...

Date post: 29-Mar-2019
Category:
Upload: ngodung
View: 215 times
Download: 0 times
Share this document with a friend
50
Jt)jg Wetlands Applications Decision Report Decisions Taken 01/22/2018 to 01/28/2018 DISCLAIMER: This document is published for information purposes only and does not constitute an authorization to conduct work. Work in jurisdiction may not commence until the applicant has received a posting permit. Decisions are subject to appeal, and are reviewed by the federal agencies for compliance with Section 404 of the Federal Clean Water Act. APPEAL: Any party aggrieved by a decision may file an appeal within 30 days of the date of this decision as specified in RSA 482-A:10, RSA 21-0:14, and the rules adopted by the Wetlands Council, Env-WtC 100-200. The appeal must be filed directly with the Council, c/o the Council Appeals Clerk, who may be contacted at (603) 271-6072 or atappeals©des.nh.gov. The notice of appeal must set forth fully every ground upon which it is claimed that the decision complained of is unlawful or unreasonable. Only those grounds set forth in the notice of appeal can be considered by the council.
Transcript

Jt)jgWetlands Applications Decision Report

Decisions Taken01/22/2018 to 01/28/2018

DISCLAIMER:

This document is published for information purposes only and does not constitute an authorization to conduct work.Work in jurisdiction may not commence until the applicant has received a posting permit.

Decisions are subject to appeal, and are reviewed by the federal agencies for compliance with Section 404 of the FederalClean Water Act.

APPEAL:

Any party aggrieved by a decision may file an appeal within 30 days of the date of this decision as specified in RSA482-A:10, RSA 21-0:14, and the rules adopted by the Wetlands Council, Env-WtC 100-200.

The appeal must be filed directly with the Council, c/o the Council Appeals Clerk, who may be contacted at (603)271-6072 or atappeals©des.nh.gov. The notice of appeal must set forth fully every ground upon which it is claimed thatthe decision complained of is unlawful or unreasonable. Only those grounds set forth in the notice of appeal can beconsidered by the council.

Decision Report 2 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

MAJOR IMPACT PROJECT

2017-02648 BETTENCOURT, DENISEIRONALD

ALTON LAKE WINNIPESAUKEE

Requested Action:

Construct a 4 foot x 30 foot piling pier to be connected by a 4 foot x 12 foot walkway to an existing 47 linear feet ofcantilevered pier and 42 linear feet of breakwater in a dog-leg configuration on an average of 106 feet of frontage along LakeWinnipesaukee on Barndoor Island, in Alton.

*********************************

Conservation Commission/Staff Comments:8/23/17 Con. Com. requests a hold’ on this application until they can conduct a site visit and issue comments. Their requestwas submitted prior to NHDES receiving the application package.9/18/17 Con. Com. has no objections to issuance of the permit.9/19/17 - No historic properties affected per DHR.

APPROVE PERMITConstruct a 4 foot x 30 foot piling pier to be connected by a 4 foot x 12 foot walkway to an existing 47 linear feet ofcantilevered pier and 42 linear feet of breakwater in a dog-leg configuration on an average of 106 feet of frontage along LakeWinnipesaukee on Barndoor Island, in Alton.

With Conditions:1. All work shall be in accordance with revised plans by Ambrose Marine dated December 19, 2017, as received by DES onJanuary 8, 2018.2. This permit is not valid and effective until it has been recorded with the appropriate county Registry of Deeds by theapplicant. Prior to starting work under this permit, the permiffee shall submit a copy of the recorded permit to the DESWetlands Program by certified mail, return receipt requested.3. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.4. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that noturbidity escapes the immediate dredge area and shall remain until suspended particles have settled and water at the worksite has returned to normal clarity.5. Any subdivision of the property frontage will require removal of a sufficient portion of the docking structures to comply withthe dock size and density requirements in effect at the time of the subdivision.6. Only those structures shown on the approved plans shall be installed or constructed along this frontage. All portions of thestructures, including the breakwater toe of slope, shall be at least 20 feet from the abutting property lines or the imaginaryextension of those lines into the water.7. Pilings shall be spaced a minimum of 12 feet apart as measured piling center to piling center.

With Findings:1. This project is classified as a major project per Rule Env-Wt 303.02(d), modification of a docking structure associated witha breakwater.2. The breakwater existing at this site is justified in accordance with Rule Env-Wt 402.07, Breakwaters.3. The applicant has an average of 106 feet of shoreline frontage along Lake Winnipesaukee.4. A maximum of 2 slips may be permitted on this frontage per Rule Env-Wt 402.13 Frontage Over 75’.5. The proposed docking facility will provide 2 slips as defined per RSA 482-A:2, VIII and therefore meets Rule Env-Wt402.13.6. The Department finds that because the project is not of significant public interest and will not significantly impair theresources of Lake Winnipesaukee a public hearing under RSA 482-A:8 is not required.-Send to Governor and Executive Council-

Decision Report 3 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

2017-02677 WARSCHAUER, JEFFREYISHARON

DOVER PISCATAQUA RIVER

Requested Action:

Construct a tidal docking structure consisting of a 4’ x 6’ landing in the upland tidal buffer zone, connecting to a 4’ x 15’access ramp, connecting to a 4’ x 55’ permanent pier with batter chains, connecting to a 3’ x 40’ gangway, connecting to a 6’x 30’ float and 10’ x 40’ float in a T configuration; overall structure length seaward of highest observable tide line 140’,providing three slips on 349’ of frontage on the Piscataqua River.

Conservation Commission/Staff Comments:9-19-1 7- No historic properties affected per DHR.

Inspection Date: 01/19/2018 by DAVID A PRICE

APPROVE PERMITConstruct a tidal docking structure consisting of a 4’ x 6’ landing in the upland tidal buffer zone, connecting to a 4’ x 15’access ramp, connecting to a 4’ x 55’ permanent pier with batter chains, connecting to a 3’ x 40’ gangway, connecting to a 6x 30’ float and 10’ x 40’ float in a T configuration; overall structure length seaward of highest observable tide line 140’,providing three slips on 349’ of frontage on the Piscataqua River.

With Conditions:1. All work shall be in accordance with revised plans by TM Marine dated 11/13/2017 and plans by Jones & BeachEngineers, Inc. dated 12/6/17, as received by the NH Department of Environmental Services (NHDES) on 12/26/2017.2. This permit shall not be effective until recorded at the Strafford County Registry of Deeds Office by the permittee. A copyof the recorded permit shall be submitted to the NHDES Wetlands Bureau prior to the commencement of construction.3. Not less than 5 state business days prior to starting work authorized by this permit, the permittee shall notify the NHDESWetlands Bureau Pease office and the local conservation commission in writing of the date on which work under this permitis expected to start.4. There shall be no removal of mature trees along the shoreline of the river on this property associated with the constructionof the dock.5. This tidal docking structure consisting of a 4’ x 6’ landing in the upland tidal buffer zone, connecting to a 4’ x 15’ accessramp, connecting to a 4’ x 55’ permanent pier with batter chains, connecting to a 3’ x 40’ gangway, connecting to a 6’ x 30’and 10’ x 40’ “T” shaped float; overall structure length seaward of highest observable tide line 140’, providing three slips on349’ of frontage on the Piscataqua River, shall be the only structure on the frontage. All portions of the dock approved hereinshall be at least 20 feet from abutting property lines or the imaginary extension of those lines into the water.6. The height of the pier’s decking over the surface of the tidal marsh at normal high tide shall equal the width of the decking.Decking shall have 3/4-inch spacing between the decking planks.7. The seasonal structures, including but not limited to the gangway and floats, shall be removed during the non-boatingseason and stored on the existing pier or in an upland location.8. Any future work in jurisdiction as specified in RSA 482-A on this property will require a new application and approval by theDepartment of Environmental Services (“DES”) Wetlands Bureau.9. No person undertaking any activity shall cause or contribute to, or allow the activity to cause or contribute to, any violationsof the surface water quality standards in RSA 485-A and Env-Wq 1700.10. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.11. Construction of the dock shall occur from land, or from a barge and crane if land-based construction is not feasible, toreduce potential impacts to the salt marsh and intertidal zone.12. Pile driving or pile removal work shall be done during low tide.13. Pilings to be removed shall be cut level with the substrate rather than pulled, in order to limit the creation of turbidity.14. All work shall be conducted in a manner so as to minimize turbidity and sedimentation to surface waters and wetlands.15. All work shall be conducted in a manner that avoids excessive discharges of sediments to fish spawning areas.

Decision Report 4 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

16. All construction-related debris shall be properly disposed of outside of the areas subject to RSA 482-A.17. Within three days of final grading or temporary suspension of work in an area that is adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tack or netting and pinning on slopes steeper than 3:1.

With Findings:1. This is a major impact project per Administrative Rule Env-Wt 303.02(a), projects in sand dunes, tidal wetlands, or bogs,except for the repair of existing structures pursuant to Env-Wt 303.04(v).2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01. There is currently nodock present on the frontage.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03. The dock is the minimum lengthnecessary to provide full tide access at mean lower low water at this location, to a water depth which will prevent the float andvessel from sitting on the mud at low tide.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(a) and (c), Requirementsfor Application Evaluation, has been considered in the design of the project.a. NH Natural Heritage Bureau (“NHB”) has record of sensitive species occurring within the project vicinity, but NHB does notexpect impacts to the species by the project.b. With respect to the proposal’s impact on navigation, the entire structure is located greater than 20 feet off the abuttingproperty lines or the imaginary extensions waterward thereof. The design has been reviewed by the Pease DevelopmentAuthority, Division of Ports and Harbors, who, per letter dated December 19, 2017, determined that the project would have nonegative effect on navigation in the channel.5. The Dover Newington Conservation Commission signed the application endorsing the project.6. This dock is consistent with other tidal dock facility approvals in the seacoast.7. NHDES staff field inspection on 1/19/2018 found that plans accurately reflect field conditions, and that the proposeddesign will not obstruct near-shore navigation.-Send to Governor and Executive Council-

2017-03299 STATE OF NH DNCR

NOTTINGHAM PAWTUCKAWAY POND

Requested Action:

Remove an existing 4 foot x 30 foot seasonal pier with a 4 foot x 32 foot “T” accessed by a 3 foot 6 inch x 10 foot gangway,install a 6 foot x 60 foot seasonal pier with five 4 foot x 12 foot fingers accessed by a 6 foot x 8 foot access ramp, with a 3foot x 4 foot stairs to the water on approximately 30,000 feet of frontage along Pawtuckaway Lake in Pawtuckaway StatePark in Nottingham.

APPROVE PERMITRemove an existing 4 foot x 30 foot seasonal pier with a 4 foot x 32 foot “T” accessed by a 3 foot 6 inch x 10 foot gangway,install a 6 foot x 60 foot seasonal pier with five 4 foot x 12 foot fingers accessed by a 6 foot x 8 foot access ramp. with a 3foot x 4 foot stairs to the water on approximately 30,000 feet of frontage along Pawtuckaway Lake in Pawtuckaway StatePark in Nottingham.

With Conditions:1. All work shall be in accordance with plans by Seth Prescott dated November 9, 2017 as received by the NH Department ofEnvironmental Services (DES) on November 15, 2017.2. This permit is not valid and effective until it has been recorded with the appropriate county Registry of Deeds by theapplicant. Prior to starting work under this permit, the permittee shall submit a copy of the recorded permit to the DESWetlands Program by certified mail, return receipt requested.3. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.4. This permit does not authorize the removal of trees or saplings within the waterfront buffer.5. Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.6.. Any subdivision of the property will require removal of a sufficient portion of the docking structures to comply with the

Decision Report 5 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

dock size and density requirements in effect at the time of the subdivision.7. Only those structures shown on the approved plans shall be installed or constructed along this frontage. All portions of thestructures shall be at least 20 feet from the abutting property lines or the imaginary extension of those lines into the water.8. No portion of the pier shall extend more than 60 feet from the shoreline at full lake elevation (Elevation 250).9. All seasonal structures shall be removed for the non-boating season.

With Findings:1. This is a major impact project per Administrative Rule Env-Wt 303.02(d), construction or modification of docking systemproviding 5 or more slips.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the departments jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(a) Requirements forApplication Evaluation, has been considered in the design of the project.5. The applicant has approximately 30,000 feet of shoreline frontage along Pawtuckaway Lake.6. A maximum of 401 slips may be permitted on this frontage per Rule Env-Wt 402.13 Frontage Over 75.7. The proposed docking facility will provide 7 slips as defined per RSA 482-A:2, VIII and therefore meets Rule Env-Wt402.13.8. The Department finds that because the project is not of significant public interest and will not significantly impair theresources of Pawtuckaway Lake a public hearing under RSA 482-A:8 is not required.-Send to Governor and Executive Council-

2017-03314 BARO, MELISSAIMICHAEL

ALTON LAKE WINNIPESAUKEE

Requested Action:

Place 67 cubic yards of fill on 490 square feet of lakebed to construct 35 linear feet of breakwater beginning 6 feet lakewardof the normal high water line with a 4 foot x 36 foot cantilevered pier connected to a 6 foot x 36 foot piling pier by a 6 foot x 12foot walkway, install a permanent boatlift, and drive two fender piles and one 3-pile ice cluster on an average of 100 feet offrontage along Lake Winnipesaukee on Sleeper Island in Alton.

Conservation Commission/Staff Comments:11/6/17 Con. Com. requests a ‘hold on this application until they can conduct a site visit and issue comments.11/15/2017 Con. Com. has no objections to issuance of permit.

APPROVE PERMITPlace 67 cubic yards of fill on 490 square feet of lakebed to construct 35 linear feet of breakwater beginning 6 feet lakewardof the normal high water line with a 4 foot x 36 foot cantilevered pier connected to a 6 foot x 36 foot piling pier by a 6 foot x 12foot walkway, install a permanent boatlift, and drive two fender piles and one 3-pile ice cluster on an average of 100 feet offrontage along Lake Winnipesaukee on Sleeper Island in Alton.

With Conditions:1. All work shall be in accordance with revised plans by Winnipesaukee Marine Construction dated November 15, 2017, asreceived by DES on November16, 2017.2. This permit is not valid and effective until it has been recorded with the appropriate county Registry of Deeds by theapplicant. Prior to starting work under this permit, the permittee shall submit a copy of the recorded permit to the DESWetlands Program by certified mail, return receipt requested.3. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.4. This permit does not authorize the removal of vegetation from areas within the waterfront buffer.5. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that noturbidity escapes the immediate dredge area and shall remain until suspended particles have settled and water at the worksite has returned to normal clarity.6. No portion of breakwater as measured at normal full lake (Elev. 504.32) shall extend more than 41 feet from normal full

Decision Report 6 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

lake shoreline.7. The breakwater shall not exceed 3 feet in height (Elev. 507.32) over the normal high water line fElev. 504.32).8. The width as measured at the top of the breakwater (Elev. 507.32) shall not exceed 3 feet.9. This facility is permitted with the condition that future maintenance dredging, if needed, shall not be permitted motefrequently than once every 6 years, and that a new permit shall be required for each dredge activity.10. The owner understands and accepts the risk that if this facility requires dredging to maintain a minimum slip depth of 3feet more frequently than once every 6 years, or is shown to have an adverse impact on abutting frontages, it shall be subjectto removal.11. Any subdivision of the property frontage will require removal of a sufficient portion ot the docking structures to complywith the dock size and density requirements in effect at the time of the subdivision.12. Only those structures shown on the approved plans shall be installed or constructed along this frontage. All portions ofthe structures, including the breakwater toe of slope, shall be at least 20 feet from the abutting property lines or the imaginaryextension of those lines into the water.13. Pilings shall be spaced a minimum of 12 feet apart as measured piling center to piling center.14. No portion of the piers shall extend more than 36 feet from the shoreline at full lake elevation (Elev. 504.32).

With Findings:1. This project is classified as a major project per Rule Env-Wt 303.02(j), construction of a breakwater in public waters.2. The construction of a breakwater to provide safe docking at this site is justified in accordance with Rule Env-Wt 402.07,Breakwaters.3. The applicant has an average of 100 feet of shoreline frontage along Lake Winnipesaukee.4. A maximum of 2 slips may be permitted on this frontage per Rule Env-Wt 402.13, Frontage Over 75’.5. The proposed docking facility will provide 2 slips as defined per RSA 482-A:2, VIII and therefore meets Rule Env-Wt402.13.6. The Department finds that because the project is not of significant public interest and will not significantly impair theresources of Lake Winnipesaukee a public hearing under RSA 482-A:8 is not required.

MINOR IMPACT PROJECT

2013-00583 WINSLOW, PHILIP

RYE ATLANTIC OCEAN

Requested Action:

Request permit time extension to impact approximately 9,000 square feet within the 100-foot tidal buffer zone (including8,331 square feet of temporary impact) for the reconstruction of an existing riprap sea wall to protect and repair Harbor Roadto provide safe access and egress for vehicular traffic.

Conservation Commission/Staff Comments:February 20, 2013- Policy 201

Inspection Date: 02/28/2013 by EBEN M LEWISInspection Date: 04/09/20 14 by EBEN M LEWISInspection Date: 02/03/20 14 by EBEN M LEWISInspection Date: 03/21/2014 by EBEN M LEWISInspection Date: 01/15/2014 by EBEN M LEWIS

APPROVE TIME EXTENSIONImpact approximately 9,000 square feet within the 100-foot tidal buffer zone (including 8,331 square feet of temporaryimpact) for the reconstruction of an existing riprap sea wall to protect and repair Harbor Road to provide safe access andegress for vehicular traffic.

Decision Report 7 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

With Conditions:1. All work shall be in accordance with the Wetland Board Permit Plan (Sheet 02) and the Sea Wall Repair Cross Sections’(Sheet C3) by Ambit Engineering, Inc. dated January 2013 and revised through February 27, 2013, as received by the NHDepartment of Environmental Services (DES) on Match 4, 2013.2. NH DES Wetlands Bureau Southeast Region staff (Portsmouth office) shall be notified in writing prior to commencementof work and upon its completion.3. Any further alteration of areas on this property that are within the jurisdiction of the DES Wetlands Bureau may require anew application and/or further permitting by the Bureau.4. All activities shall be in accordance with the Shoreland Water Quality Protection Act, RSA 483-B.5. Appropriate siltation/erosion/turbidity controls shall be in place prior to construction, shall be maintained duringconstruction, and remain in place until the area is stabilized. Silt fence(s) must be removed once the area is stabilized.6. No work shall occur below the highest observable tide line.7. No concrete is to be used anywhere in the construction of the revetment.8. All work shall be dry laid or placed stone underlain with filter fabric.9. Construction equipment shall be inspected daily for leaking fuel, oil and hydraulic fluid prior to entering surface waters orwetlands.10. Faulty equipment shall be repaired prior to entering jurisdictional areas.11. The contractor shall have appropriate oil spill kits on site and readily accessible at all times during construction and eachoperator shall be trained in its use.12. All refueling of equipment shall occur outside of surface waters or wetlands.

With Findings:1 .The owner, authorized agent or applicant certifies that this permit qualifies for a permit extension in accordance with RSA482-A:3, XIV-a, and Env-Wt 502.01.2.This permit has been extended in accordance with RSA 482-A:3, XIV-a and Env-Wt 502.01.

2017-01807 SIRLES REV TRUST

DURHAM

Requested Action:

Fill 4,445 square feet of forested wetlands and installation of a 18 inch x 42 foot HDPE culvert to construct a driveway toserve a single-family residential lot.

Conservation Commission/Staff Comments:7-7-17 - Additional information needed per DHR.

APPROVE PERMITFill 4,445 square feet of forested wetlands and installation of a 18 inch x 42 foot HDPE culvert to construct a driveway toserve a single-family residential lot.

With Conditions:1. All work shall be in accordance with plans by MJS Engineering, P.C. dated May 24, 2017, and revised through January 25,2018 as received by the NH Department of Environmental Services (NHDES) on January 25, 2018.2. This permit is not valid unless a septic system construction approval or other compliance with RSA 485-A:29-44 andEnv-Wq 1000 is achieved.3. Any further alteration of areas on this property that are subject to RSA 482-A jurisdiction will require a new application andfurther permitting.4. No person undertaking any activity shall cause or contribute to, or allow the activity to cause or contribute to, any violationsof the surface water quality standards in RSA 485-A and Env-Wq 1700.5. Work shall be done during low flow.6. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,

Decision Report 8 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.7. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).8. Extreme precautions shall be taken within riparian areas to prevent unnecessary removal of vegetation duringconstruction. Areas cleared of vegetation must be revegetated with like native species within three days of the completion ofthe disturbance.9. Discharge from dewatering of work areas shall be to sediment basins that are: a) located in uplands; b) lined with haybales or other acceptable sediment trapping liners; c) set back as fat as possible from wetlands and surface waters, with apreferred undisturbed vegetated buffet of at least 50 feet and a minimum undisturbed vegetative buffer of 20 feet.10. Construction equipment shall be inspected daily for leaking fuel, oil, and hydraulic fluid prior to entering surface waters orwetlands or operating in an area where such fluids could reach groundwater, surface waters, or wetlands.11. The permittee’s contractor shall maintain appropriate oil/diesel fuel spill kits on site that are readily accessible at all timesduring construction, and shall train each operator in the use of the kits.12. All refueling of equipment shall occur outside of surface waters or wetlands during construction. Machinery shall bestaged and refueled in upland areas only.13. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackifiers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.

With Findings:1. This is a minor impact project per Administrative Rule Env-Wt 303.03(h), projects involving less than 20,000 square feet ofalteration in the aggregate in nontidal wetlands.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01. The applicant hasdemonstrated that wetland impact is necessary to access uplands.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03. The applicant has demonstrated that thewetland crossing is located at the most narrow location. In addition, the applicant has lowered the fill slope from 3:1 to 2.5:1to reduced the encroachment of the driveway fill slope into the wetland. This decreased the wetland impact by 695 squarefeet from the original proposal.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(b) Requirements forApplication Evaluation, has been considered in the design ot the project.5. The NH Natural Heritage Bureau (NHB) has record of sensitive species present within the vicinity of the project area, butNHB does not expect impacts to the species by the project.6. The Durham Conservation Commission did not submit comments to NHDES on the application.

2017-02460 TOWNSEND, THOMAS

EFFINGHAM PROVINCE LAKE

Requested Action:

Impact 1,577 square feet of bank and lake bed in order to replace 30 cubic yards of round stone with 30 cubic yards ofangular stone and install coir logs and plantings to stabilize 84 linear feet of bank on an average of 99 feet of frontage alongProvince Lake in Effingham.

Inspection Date: 10/13/2017 by ROSEMARY EAURES

APPROVE PERMITImpact 1,577 square feet of bank and lake bed in order to replace 30 cubic yards of round stone with 30 cubic yards ofangular stone and install coir logs and plantings to stabilize 84 linear feet of bank on an average of 99 feet of frontage alongProvince Lake in Effingham.

Decision Report 9 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

With Conditions:1. All work shall be in accordance with revised plans by Jones & Beach Engineers. Inc. dated December 21, 2017, asreceived by DES on December 28, 2017.2. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.3. This permit does not authorize the removal of trees or saplings within the waterfront buffer that would result in a tree andsapling point score below the minimum required per RSA 483-B:9, V, (a)(2)(D)(iv).4. Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.5. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.6. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that noturbidity escapes the immediate dredge area and shall remain until suspended particles have settled and water at the worksite has returned to normal clarity.7. All dredged and excavated material and construction-related debris shall be placed outside of the areas subject to RSA482-A. Any spoil material deposited within 250 feet of any surface water shall comply with RSA-483-B.8. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).9. No person undertaking any activity shall cause or contribute to, or allow the activity to cause or contribute to, any violationsof the surface water quality standards in RSA 485-A and Env-Wq 1700.10. This permit shall not preclude DES from initiating appropriate action if DES later determines that any of the structuresdepicted as “existing” on the plans submitted by or on behalf of the permitted were not previously permitted or grandfathered.11. Work shall be done during low flow and in the dry only.12. The repairs shall maintain the size, location, and configuration of the pre-existing structures.13. The retaining wall shall be constructed landward of the shoreline defined by the elevation of normal high water so as notto create land in public water.14. Rip-rap shall be located landward of the shoreline at the normal high water, and shall not extend more than 2 feetlakeward of that line at any point.15. The permittee/permiffee’s contractor shall revegetate the disturbed area with trees, shrubs and ground coversrepresenting the density and species diversity of the existing stand of vegetation removed for this project, exclusive of anyinvasive or nuisance species.16. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackifiers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.

With Findings:1. This is a minor impact project per Administrative Rule Env-Wt 303.03(k) projects that disturb between 50 and 200 linearfeet, measured along the shoreline, of a lake or pond or its bank.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(a) Requirements forApplication Evaluation, has been considered in the design of the project.

201 7-02622 VILLAGE DISTRICT OF EIDELWEISS

MADISON Unnamed T

Requested Action:

Dredge and fill 297 square feet (SF) of the bed and banks of a perennial, unnamed tributary stream to Banfield Brook (tier 2,impacting 70 Linear feet [LFJ) to remove two undersized culverts and install a 12 foot wide by 6 foot tall by 64 foot longprecast concrete box culvert with 2 feet of embedded stream simulation material and associated headwalls. In additiontemporarily impact 964 SF (144 LF) for erosion and turbidity controls and regrading.

Decision Report 10 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

APPROVE PERMITDredge and fill 297 square feet (SF) of the bed and banks of a perennial, unnamed tributary stream to Banfield Brook (tier 2,

impacting 70 Linear feet [LF]) to remove two undersized culverts and install a 12 foot wide by 6 foot tall by 64 foot long

precast concrete box culvert with 2 feet of embedded stream simulation material and associated headwalls. In addition

temporarily impact 964 SF (144 LF) for erosion and turbidity controls and regrading.

With Conditions:1. All work shall be in accordance with plans by DuBois and King, Inc., dated July 2017, and revised through January 10.

2017, as received by the NH Department of Environmental Services (NHDES) on January 10, 2017.

2. Not less than 5 state business days prior to starting work authorized by this permit, the permiffee shall notify the NHDES

Wetlands Program and the local conservation commission in writing of the date on which work under this permit is expected

to start.3. No person undertaking any activity shall cause or contribute to, or allow the activity to cause or contribute to, any violations

of the surface water quality standards in RSA 485-A and Env-Wq 1700.

4. All in-stream work shall be done during annual low flow conditions and during the months of May through September. No

in-stream work shall occur after October 1 unless a waiver of this condition is issued in writing by NHDES in consultation with

NH Fish & Game.5. Any further alteration of areas on this property that are subject to RSA 482-A jurisdiction will require a new application and

further permitting.6. Work shall be done during low flow and in the dry only.

7. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,

and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.

8. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that no

turbidity escapes the immediate dredge area, and shall remain until suspended particles have settled and water at the work

site has returned to normal clarity.9. Erosion control products shall be installed per manufacturers recommended specifications.

10. Work shall be conducted in a manner so as to minimize turbidity and sedimentation to surface waters and wetlands.

11, All dredged and excavated material and construction-related debris shall be placed outside of the areas subject to RSA

482-A. Any spoil material deposited within 250 feet of any surface water shall comply with RSA-483-B.

12. The contractor responsible for completion of the work shall use techniques described in the New Hampshire Stormwater

Manual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).

13. Cofferdams shall not be installed during periods of high flow, whether due to seasonal runoff or precipitation. Once the

cofferdam is fully effective, confined work can proceed without restriction.14. Work within the stream, inclusive of work associated with installation of a cofferdam, shall be done during periods of low

flow only. The permittee shall monitor local weather forecasts to avoid working during or following precipitation events.

15. Discharge from dewatering of work areas shall be to sediment basins that are: a) located in uplands; b) lined with hay

bales or other acceptable sediment trapping liners; c) set back as far as possible from wetlands and surface waters, with a

preferred undisturbed vegetated buffer of at least 50 feet and a minimum undisturbed vegetative buffer of 20 feet.

16. Dredged materials, whether to be stockpiled or disposed of, shall be dewateted in sedimentation basins lined with

siltation and erosion controls, and located outside of areas subject to RSA 482-A jurisdiction.

17. The temporary cofferdam shall be entirely removed within 2 days after work within the cofferdam is completed and water

has returned to normal clarity.18. Extreme precautions shall be taken within riparian areas to prevent unnecessary removal of vegetation during

construction. Areas cleared of vegetation must be revegetated with like native species within three days of the completion of

the disturbance.19. All work shall be done from the top of the bank only.

20. No machinery shall enter the water.21. No excavation shall be done in flowing water. No construction equipment shall be operated in flowing water.

22. Construction equipment shall be inspected daily for leaking fuel, oil, and hydraulic fluid prior to entering surface waters or

wetlands or operating in an area where such fluids could reach groundwater, surface waters, or wetlands.

23. The permittee’s contractor shall maintain appropriate oil/diesel fuel spill kits on site that are readily accessible at all times

during construction, and shall train each operator in the use of the kits.

24. All refueling of equipment shall occur outside of surface waters or wetlands during construction. Machinery shall be

staged and refueled in upland areas only.25. Faulty equipment shall be repaired immediately prior to entering areas that are subject to RSA 482-A jurisdiction.

26. Native material removed from the streambed during culvert installation shall be stockpiled separately and reused to

emulate a natural channel bottom within the culvert, between wing walls, and beyond. Any new materials used must be as

similar to the natural stream substrate as practicable and shall not include any shall not include angular riprap or gravel.

Decision Report 11 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

27. Any fill used shall be clean sand, gravel, rock, or other suitable material.28. Proper headwalls shall be constructed within seven days of culvert installation.29. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackifiers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.30. Areas from which vegetation has been cleared to gain access to the site shall be replanted with similar native species.31. A post-construction report, prepared by a Certified Wetland Scientist or Qualified Professional, as applicable,documenting status of the project area and restored jurisdictional area or buffer, including photographs, shall be submitted tothe NHDES Wetlands Program within 60 days of the completion of construction. NHDES Wetlands Program may requiresubsequent monitoring and corrective measures if NHDES deemed the area inadequately stabilized or restored.

With Findings:1. This is a minor impact project per Administrative Rule Env-Wt 303.03(o), for the replacement of a tier 2 stream crossingthat meets 903.01(fl(1)(c).2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01 as the existing culvertsare severely undersized and these crossings have a history of washing out.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03 as the proposed culvert will be embeddedwith stream simulation and will be appropriately sized to pass the stream crossing rules in Env-Wt 900.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(a) Requirements forApplication Evaluation, has been considered in the design of the project.5. This application was submitted in response to NHDES Wetlands Compliance File #2016-00115 involving two streamcrossings along an unnamed tributary stream to Banfield Brook along Bergdorf Place and Grison Road. NHDES Staffconducted a field inspection of the project site on January 07, 2016. Field inspection determined that repairs to thewashed-out culverts were completed without NHDES approval or permits. The town has since filed applications (WetlandsFile #2017-02622 and #2017-02638) to bring these two crossings into compliance with all NH Administrative Rules Env-Wt100-900.6. In a regulatory review of the site dated November 07, 2016, the US Fish and Wildlife Service found that while Northernlong-eared bats (Myotis septentrionalis) and small whorled pogonia (Isotria medeoloides) were present in the vicinity of thesite, there are no critical habitats for these species at this location.7. In a review letter dated December 08, 2016, the NH Natural Heritage Bureau (NHB) found that there were no records of asensitive species in the vicinity of the project.8. As of January 25, 2018, no comments of concern have been received by NHDES from abutters or local governingorganizations.9. While this project takes place in the vicinity of the Madison Boulder National Natural Landmark, it is not likely to have aneffect on it.10. The culvert as proposed passes the stream crossing rules in Env-Wt 900 for a tier 2 stream crossing.

201 7-02638 VILLAGE DISTRICT OF EIDELWEISS

MADISON Unnamed T

Requested Action:

Dredge and fill 66 square feet (SF) of the bed and banks of a perennial, unnamed tributary stream to Banfield Brook (tier 2,impacting 15 Linear feet [LFJ) to remove two undersized culverts and install a 12 foot wide by 6 foot tall by 64 foot longprecast concrete box culvert with 2 feet of embedded stream simulation material and associated headwalls. In additiontemporarily impact 211 SF (63 LF) for erosion and turbidity controls and regrading.

APPROVE PERMITDredge and fill 66 square feet (SF) of the bed and banks of a perennial, unnamed tributary stream to Banfield Brook (tier 2,impacting 15 Linear feet [LF]) to remove two undersized culverts and install a 12 foot wide by 6 foot tall by 64 foot longprecast concrete box culvert with 2 feet of embedded stream simulation material and associated headwalls. In additiontemporarily impact 211 SF (63 LF) for erosion and turbidity controls and regrading.

Decision Report 12 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

With Conditions:1. All work shall be in accordance with plans by DuBois and King, Inc., dated July 2017, and revised through January 10,2017, as received by the NH Department of Environmental Services (NHDES) on January 10, 2017.2. Not less than 5 state business days prior to starting work authorized by this permit, the permiffee shall notify the NHDESWetlands Program and the local conservation commission in writing of the date on which work under this permit is expectedto start.3. No person undertaking any activity shall cause or contribute to, or allow the activity to cause or contribute to, any violationsof the surface water quality standards in RSA 485-A and Env-Wq 1700.4. All in-stream work shall be done during annual low flow conditions and during the months of May through September. Noin-stream work shall occur after October 1 unless a waiver of this condition is issued in writing by NHDES in consultation withNH Fish & Game.5. Any further alteration of areas on this property that are subject to RSA 482-A jurisdiction will require a new application andfurther permitting.6. Work shall be done during low flow and in the dry only.7. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.8. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that noturbidity escapes the immediate dredge area, and shall remain until suspended particles have settled and water at the worksite has returned to normal clarity.9. Erosion control products shall be installed per manufacturers recommended specifications.10. Work shall be conducted in a manner so as to minimize turbidity and sedimentation to surface waters and wetlands.11. All dredged and excavated material and construction-related debris shall be placed outside of the areas subject to RSA482-A. Any spoil material deposited within 250 feet of any surface water shall comply with RSA-483-B.12. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).13. Cofferdams shall not be installed during periods of high flow, whether due to seasonal runoff or precipitation. Once thecofferdam is fully effective, confined work can proceed without restriction.14. Work within the stream, inclusive of work associated with installation of a cofferdam, shall be done during periods of lowflow only. The permittee shall monitor local weather forecasts to avoid working during or following precipitation events.15. Discharge from dewatering of work areas shall be to sediment basins that are: a) located in uplands; b) lined with haybales or other acceptable sediment trapping liners; c) set back as far as possible from wetlands and surface waters, with apreferred undisturbed vegetated buffer of at least 50 feet and a minimum undisturbed vegetative buffer of 20 feet.16. Dredged materials, whether to be stockpiled or disposed of, shall be dewatered in sedimentation basins lined withsiltation and erosion controls, and located outside of areas subject to RSA 482-A jurisdiction.17. The temporary cofferdam shall be entirely removed within 2 days after work within the cofferdam is completed and waterhas returned to normal clarity.18. Extreme precautions shall be taken within riparian areas to prevent unnecessary removal of vegetation duringconstruction. Areas cleared of vegetation must be revegetated with like native species within three days of the completion ofthe disturbance.19. All work shall be done from the top of the bank only.20. No machinery shall enter the water.21. No excavation shall be done in flowing water. No construction equipment shall be operated in flowing water.22. Construction equipment shall be inspected daily for leaking fuel, oil, and hydraulic fluid prior to entering surface waters orwetlands or operating in an area where such fluids could reach groundwater, surface waters, or wetlands.23. The permiffee’s contractor shall maintain appropriate oil/diesel fuel spill kits on site that are readily accessible at all timesduring construction, and shall train each operator in the use of the kits.24. All refueling of equipment shall occur outside of surface waters or wetlands during construction. Machinery shall bestaged and refueled in upland areas only.25. Faulty equipment shall be repaired immediately prior to entering areas that are subject to RSA 482-A jurisdiction.26. Native material removed from the streambed during culvert installation shall be stockpiled separately and reused toemulate a natural channel bottom within the culvert, between wing walls, and beyond. Any new materials used must be assimilar to the natural stream substrate as practicable and shall not include any shall not include angular riprap or gravel.27. Any fill used shall be clean sand, gravel, rock, or other suitable material.28. Proper headwalls shall be constructed within seven days of culvert installation.29. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackifiers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.30. Areas from which vegetation has been cleared to gain access to the site shall be replanted with similar native species.31. A post-construction report, prepared by a Certified Wetland Scientist or Qualified Professional, as applicable,

Decision Report 13 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

documenting status of the project area and restored jurisdictional area or buffer, including photographs, shall be submitted tothe NHDES Wetlands Program within 60 days of the completion of construction. NHDES Wetlands Program may requiresubsequent monitoring and corrective measures if NHDES deemed the area inadequately stabilized or restored.

With Findings;1. This is a minor impact project per Administrative Rule Env-Wt 303.03(o), for the replacement of a tier 2 stream crossingthat meets 903.01(f1(1)(c).2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01 as the existing culvertsare severely undersized and these crossings have a history of washing out.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03 as the proposed culvert will be embeddedwith stream simulation and will be appropriately sized to pass the stream crossing rules in Env-Wt 900.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(a) Requirements forApplication Evaluation, has been considered in the design of the project.5. This application was submitted in response to NHDES Wetlands Compliance File #2016-00115 involving two streamcrossings along an unnamed tributary stream to Banfield Brook along Bergdorf Place and Grison Road. NHDES Staffconducted a field inspection of the project site on January 07, 2016. Field inspection determined that repairs to thewashed-out culverts were completed without NHDES approval or permits. The town has since filed applications (WetlandsFile #2017-02622 and #2017-02638) to bring these two crossings into compliance with all NH Administrative Rules Env-Wt100-900.6. In a regulatory review of the site dated November 07, 2016, the US Fish and Wildlife Service found that while Northernlong-eared bats (Myotis septentrionalis) and small whorled pogonia (Isotria medeoloides) were present in the vicinity of thesite, there are no critical habitats for these species at this location.7. In a review letter dated December 08, 2016, the NH Natural Heritage Bureau (NHB) found that there were no records of asensitive species in the vicinity of the project.8. As of January 25, 2018, no comments of concern have been received by NHDES from abutters or local governingorganizations.9. While this project takes place in the vicinity of the Madison Boulder National Natural Landmark, it is not likely to have aneffect on it.10. The culvert as proposed passes the stream crossing rules in Env-Wt 900 for a tier 2 stream crossing.

2017-02796 OBRIEN, MARYELEN/WILLIAM

ALTON LAKE WINNIPESAUKEE

Requested Action;

Excavate 202 square feet of bank, dredge 173 square feet of lakebed and existing dug-in basin, and temporarily impact 208square feet of bank in order to expand an existing dug-in basin to be 12 feet x 25 feet, replace 109 linear feet of retaining walland install a 12 foot x 25 foot seasonal canopy on an average of 68 feet of frontage along Lake Winnipesaukee, in RandCove, in Alton.

* ********* *************** * ****** *

Conservation Commission/Staff Comments;9/18/17 Con. Corn. had not requested a “hold” on this application prior to their issuing comments. They are asking if agrandfathered dug-in boat slip can be enlarged and the Town of Alton has a 15 ft. height restriction for canopies, not 20 ft.

APPROVE PERMITExcavate 202 square feet of bank, dredge 173 square feet of lakebed and existing dug-in basin, and temporarily impact 208square feet of bank in order to expand an existing dug-in basin to be 12 feetx 25 feet, replace 109 linear feet of retaining walland install a 12 foot x 25 foot seasonal canopy on an average of 68 feet of frontage along Lake Winnipesaukee, in RandCove, in Alton.

With Conditions;1. All work shall be in accordance with revised plans by Folsom Design & Construction Management dated January 8, 2018,as received by DES on January 12, 2018.

Decision Report 14 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

2. This permit is not valid and effective until it has been recorded with the appropriate county Registry of Deeds by theapplicant. Prior to starting work under this permit, the permittee shall submit a copy of the recorded permit to the DESWetlands Program by certified mail, return receipt requested.3. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.4. Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.5. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that noturbidity escapes the immediate dredge area and shall remain until suspended particles have settled and water at the worksite has returned to normal clarity.6. All dredged and excavated material and construction-related debris shall be placed outside of the areas subject to RSA482-A. Any spoil material deposited within 250 feet of any surface water shall comply with RSA-483-B.7. Any subdivision of the property frontage will require removal of a sufficient portion of the docking structures to comply withthe dock size and density requirements in effect at the time of the subdivision.8. Only those structures shown on the approved plans shall be installed or constructed along this frontage.9. The canopy, including the support frame and cover, shall be designed and constructed to be readily removed at the end ofthe boating season and the flexible canopy shall be removed for the non-boating season.10. The permiffee/permittee’s contractor shall revegetate the disturbed area with trees, shrubs and ground coversrepresenting the density and species diversity of the existing stand of vegetation removed for this project, exclusive of anyinvasive or nuisance species11. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackifiers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.12. The owner understands and accepts the risk that if this facility requires dredging to maintain a minimum slip depth of 3feet more frequently than once every 6 years, or is shown to have an adverse impact on abutting frontages, it shall be subjectto removal.13. This facility is permitted with the condition that future maintenance dredging, if needed, shall not be permitted morefrequently than once every 6 years, and that a new permit shall be required for each dredge activity.14. The retaining wall repairs shall maintain the size, location, and configuration of the pre-existing wall.15. No person undertaking any activity shall cause or contribute to, or allow the activity to cause or contribute to, anyviolations of the surface water quality standards in RSA 485-A and Env-Wq 1700.16. This permit shall not preclude DES from initiating appropriate action if DES later determines that any of the structuresdepicted as “existing” on the plans submitted by or on behalf of the permitted were not previously permitted or grandfathered.

With Findings:1. This is a minor impact project per Administrative Rule Env-Wt 303.03(g), dredge of less than 20 cubic yards of materialfrom public waters.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(a) Requirements forApplication Evaluation, has been considered in the design of the project.5. The Applicant has submitted a signed notarized waiver of the 20 foot setback to property lines from the owner of theabutting property identified as Lot # 12 on Alton Tax Map 36 for the wall repairs, basin expansion, and canopy installation.

2017-03178 NH DEPT OF TRANSPORTATION

GORHAM Unnamed Stream

Requested Action:

Install a 6 in. concrete invert, with a low flow notch, lining the 7 ft. high x 11 ft. wide x 90 ft. long metal arch pipe, add cutoffwalls and a downstream fish weir impacting 2,247 sq. ft. (768 sq. ft. temporary) of riverine and palustrine wetlands. NHDOTproject 41393

Conservation Commission/Staff Comments:Cons. Comm. - no comment

Decision Report 15 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

APPROVE PERMITInstall a 6 in. concrete invert, with a low flow notch, lining the 7 ft. high x 11 ft. wide x 90 ft. long metal arch pipe, add cutoffwalls and a downstream fish weir impacting 2247 sq. ft. (768 sq. ft. temporary) of riverine and palustrine wetlands. NHDOTproject 41393

With Conditions:1. All work shall be in accordance with plans by NHDOT Bureau of Bridge Maintenance dated 8/24/17 as received by theDepartment on Oct. 26, 2017.2. Dredged materials, whether to be stockpiled or disposed of, shall be dewatered in sedimentation basins lined with siltationand erosion controls, and located outside of areas subject to RSA 482-A jurisdiction.3. Unconfined work within the stream, exclusive of work associated with installation of a cofferdam, shall be done duringperiods of low flow.4. Cofferdams shall not be installed during periods of high flow, whether due to seasonal runoff or precipitation. Once acofferdam is fully effective, confined work can proceed without restriction.5. Prior to commencing work on a substructure located within surface waters, a cofferdam shall be constructed to isolate thesubstructure work area from the surface waters.6. Temporary cofferdams shall be entirely removed immediately following construction.7. Construction equipment shall not be located within surface waters.8. Discharge from dewatering of work areas shall be to sediment basins that are: a) located in uplands; b) lined with haybales or other acceptable sediment trapping liners; c) set back as far as possible from wetlands and surface waters, with apreferred undisturbed vegetated buffer of at least 50 feet and a minimum undisturbed vegetative buffer of 20 feet.9. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that noturbidity escapes the immediate dredge area, and shall remain until suspended particles have settled and the water at thework site has returned to normal clarity.10. Wthin three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackifiers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.11. The contractor responsible for completion of the work shall utilize techniques described in the New HampshireStormwater Manual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).12. Extreme precautions shall be taken within riparian areas to prevent unnecessary removal of vegetation duringconstruction. Areas cleared of vegetation must be revegetated with like native species within three days of the completion ofthe disturbance.13. There shall be no further alteration to wetlands or surface waters without amendment of this permit.14. Precautions shall be taken to prevent import or transport of soil or seed stock containing nuisance or invasive speciessuch as Purple Loosestrife, Knotweed, or Phragmites. The contractor responsible for work shall appropriately addressinvasive species in accordance with the NHDOT Best Management Practices for Roadside Invasive Plants (2008).15. The impacts associated with the temporary work shall be restored immediately following construction.16. The permittee shall monitor the success of the weir for no fewer than 5 growing seasons per Env-Wt 803.04 (b).

With Findings:1. This is a minor project per Env-Wt 904.06(d) as the tier 2 stream project should not adversely impact the stability of thebed or banks and not cause an increase in flooding.2. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.3. The applicant has demonstrated by plan and e*ampfe that each factor listed in Env-Wt 302.04(a) Requirements forApplication Evaluation, has been considered in the design of the project.4. The project was coordinated through the Natural Resource Agency monthly meetings and discussed in on May 17, 2017.5, Although there was a Natural Heritage Bureau record it was determined that it is not expected to be impacted.

2017-03179 ARMAND J CARON REVOCABLE TRUST

STARK SOUTH PONDS

Decision Report 16 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

Requested Action:

Impact 384 square feet of bank to replace 65 linear feet of concrete block retaining wall with a pre-cast block retaining walland associated drainage system on an average of 81 feet of frontage along South Pond in Stark.

APPROVE PERMITImpact 384 square feet of bank to replace 65 linear feet of concrete block retaining wall with a pre-cast block retaining walland associated drainage system on an average of 81 feet of frontage along South Pond in Stark.

With Conditions:1. All work shall be in accordance with plans by Robert Eich dated July 24, 2017 as received by the NH Department ofEnvironmental Services (DES) on October 26, 2017.2. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.3. Work authorized shall be carried out such that there are no discharges in or to spawning or nursery areas during spawningseasons. Impacts to such areas shall be avoided or minimized to the maximum extent practicable during all other times ofthe year.4. Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.5. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.6. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that noturbidity escapes the immediate dredge area and shall remain until suspended particles have settled and water at the worksite has returned to normal clarity.7. All excavation and construction-related debris shall be placed outside of the areas subject to RSA 482-A. Any spoilmaterial deposited within 250 feet of any surface water shall comply with RSA-483-B.8. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).9. Only those structures shown on the approved plans shall be installed or constructed along this frontage.10. No person undertaking any activity shall cause or contribute to, or allow the activity to cause or contribute to, anyviolations of the surface water quality standards in RSA 485-A and Env-Wq 1700.11. This permit shall not preclude DES from initiating appropriate action if DES later determines that any of the structuresdepicted as “existing” on the plans submitted by or on behalf of the permitted were not previously permitted or grandfathered.12. The retaining wall shall be constructed landward of the shoreline defined by the elevation of normal high water line(Elevation 1 ,115)so as not to create land in public water.13. The permittee/permiffee’s contractor shall revegetate the disturbed area with trees, shrubs and ground coversrepresenting the density and species diversity of the existing stand of vegetation removed for this project, exclusive of anyinvasive or nuisance species.14. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackifiers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.

With Findings:1. This is a minor impact project per Administrative Rule Env-Wt 303.03(j), replacement of existing retaining walls thatrequires work in the water, but that results in no change in height, length, location, or configuration. No wall refacing isproposed.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(a) Requirements forApplication Evaluation, has been considered in the design of the project.5. The applicant has provided a signed written agreement as required in Env-Wt 304.04(a) for work proposed within 20 feetof the abutting property.

201 7-03334 THE LUCILLE ANNIS TRUST

Decision Report 17 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

GILFORD LAKE WINNIPESAUKEE

Requested Action:

Drive 4 piling to support a permanent boatlift and install two addition 8 inch x 8 inch seasonal supports for a 14 foot x 30 footseasonal canopy adjacent to a 115 linear foot “L” shaped breakwater and 4 foot x 105 foot cantilevered pier on an average of157 feet of frontage along Lake Winnipesaukee in Gilford.

Conservation Commission/Staff Comments:11/8/17 Per DHR, no historic properties affected.11/20/17 Con. Com. requests a ‘hold until they can investigate and issue comments.11/29/2017 Con. Com. voted to recommend approval of the application and plans as submitted but did note in theircomments that this point of land gets a lot of wind, ice and weather.

APPROVE PERMITDrive 4 piling to support a permanent boatlift and install two addition 8 inch x 8 inch seasonal supports for a 14 foot x 30 footseasonal canopy adjacent to a 115 linear foot “L’ shaped breakwater and 4 foot x 105 foot cantilevered pier on an average of157 feet of frontage along Lake VVinnipesaukee in Gilford.

With Conditions:1. All work shall be in accordance with plans by Watermark Marine Construction dated October 16, 2017, as received byDES on November 8, 2017.2. This permit is not valid and effective until it has been recorded with the appropriate county Registry of Deeds by theapplicant. Prior to starting work under this permit, the permittee shall submit a copy of the recorded permit to the DESWetlands Program by certified mail, return receipt requested.3. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.4, Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.5. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during constructiqn such that noturbidity escapes the immediate dredge area and shall remain until suspended particles have settled and water at the worksite has returned to normal clarity.6. Any subdivision of the property frontage will require removal of a sufficient portion of the docking structures to comply withthe dock size and density requirements in effect at the time of the subdivision.7. Only those structures shown on the approved plans shall be installed or constructed along this frontage. All portions of theseasonal canopy and boat lift shall be at least 20 feet from the abutting property lines or the imaginary extension of thoselines into the water.8. The canopy, including the two 8 inch x 8 inch supports, frame, and cover, shall be designed and constructed to be readilyremoved at the end of the boating season and the flexible canopy shall be removed for the non-boating season.

With Findings:1. This is a minor impact project per Administrative Rule Env-Wt 303.03(m) the addition of piling that do not by theirinstallation increase the number of slips provided by the docking facility.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(a) Requirements forApplication Evaluation, has been considered in the design of the project.

201 7-03376 JOHNSON, JANE

MOULTONBOROUGH LAKE WINNIPESAUKEE

Decision Report 18 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

Requested Action:

Permanently remove a U-shaped dock consisting of two 3 foot x 30 foot seasonal piers connected by a 7 foot x 18 foot deckover the water, install two 6 foot x 40 foot piers and a 6 foot x 12 foot connecting walkway in a “U’ configuration to beanchored by two 4 foot x 7 foot concrete anchor pads, and install a seasonal boat lift between the piers and two seasonalpersonal watercraft lifts adjacent to the western pier along an average of 150 feet of frontage along Lake Winnipesaukee inMoultonborough.

Conservation Commission/Staff Comments:1-12-18 - No historic properties affected per DHR.

APPROVE PERMITPermanently remove a U-shaped dock consisting of two 3 foot x 30 foot seasonal piers connected by a 7 foot x 18 foot deckover the water, install two 6 foot x 40 foot piers and a 6 foot x 12 foot connecting walkway in a “U” configuration to beanchored by two 4 foot x 7 foot concrete anchor pads, and install a seasonal boat lift between the piers and two seasonalpersonal watercraft lifts adjacent to the western pier along an average of 150 feet of frontage along Lake Winnipesaukee inMoultonborough.

With Conditions:1. All work shall be in accordance with plans by Watermark Marine Construction dated October 20, 2017 as received by theNH Department of Environmental Services (DES) on November 14, 2017.2. This permit is not valid and effective until it has been recorded with the appropriate county Registry of Deeds by theapplicant. Prior to starting work under this permit, the permittee shall submit a copy of the recorded permit to the DESWetlands Program by certified mail, return receipt requested.3. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.4. Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.5. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.6. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that noturbidity escapes the immediate dredge area and shall remain until suspended particles have settled and water at the worksite has returned to normal clarity.7. All dredged and excavated material and construction-related debris shall be placed outside of the areas subject to RSA482-A. Any spoil material deposited within 250 feet of any surface water shall comply with RSA-483-B.8. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).9. Any subdivision of the property will require removal of a sufficient portion of the docking structures to comply with the docksize and density requirements in effect at the time of the subdivision.10. Only those structures shown on the approved plans shall be installed or constructed along this frontage. All portions ofthe structures shall be at least 20 feet from the abutting property lines or the imaginary extension of those lines into the water.11. No portion of the piers shall extend more than 40 feet from the shoreline at full lake elevation (Elevation 504.32).12. All seasonal structures, including watercraft lifts, shall be removed for the non-boating season.

With Findings:1. This is a minor impact project per Administrative Rule Env-Wt 303.03(d), construction or modification of a docking systemthat provides 3 boat slips.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(a) Requirements forApplication Evaluation, has been considered in the design of the project.

Decision Report 19 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

MINIMUM IMPACT PROJECT

2016-01410 TOWN OF CANAAN

CANAAN UNNAMED INTERMITTENT STREAM

Requested Action:

Retain 920 square feet (SF) of dredge and fill within the bed and banks of an unnamed intermittent tributary stream to theIndian River (tier 1, impacting 45 linear feet) to install a 36 inch diameter by 20 foot long culvert to allow access from aparking area to an athletic field.

APPROVE PERMITRetain 920 square feet (SF) of dredge and fill within the bed and banks of an unnamed intermittent tributary stream to theIndian River (tier 1 impacting 45 linear feet) to install a 36 inch diameter by 20 foot long culvert to allow access from aparking area to an athletic field.

With Conditions:1. AlT work shall be in accordance with plans by Beaver Tracks, LLC., dated July 24, 2017, and revised through November 14,2017, as received by the NH Department of Environmental Services (NHDES) on November 16, 2017.2. Revegetation of the stream banks shall be done in accordance with the narrative provided by Beaver Tracks, LLC., datedDecember 27, 2017.3. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.4. Erosion control products shall be installed per manufacturers recommended specifications.5. All dredged and excavated material and construction-related debris shall be placed outside of the areas subject to RSA482-A. Any spoil material deposited within 250 feet of any surface water shall comply with RSA-483-B.6. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).7. All work shall be done from the top of the bank only.8. Work shall be done during non-flow.9. No machinery shall enter the water.10. No excavation shall be done in flowing water. No construction equipment shall be operated in flowing water.11. Any fill used shall be clean sand, gravel, rock, or other suitable material.12. Bank stabilization shall not extend land into the stream/river channel.13. Only native plant species shall be used to revegetate the riverbank.14. Native live plantings shall be installed by September 15th on previously stabilized, riprap banks. Dormant willows shall beplanted in the spring by June 1st or in the fall after September 15th and before October 30th.15. The river banks and buffer plantings shall have at least 75% successful vegetation establishment after two (2) growingseasons, or they shall be replanted and re-established in a manner satisfactory to the NHDES Wetlands Program.16. A post-construction report, prepared by a Certified Wetland Scientist or Qualified Professional, as applicable,documenting status of the project area and restored jurisdictional area or buffer, including photographs, shall be submitted tothe NHDES Wetlands Program within 60 days of the completion of construction. NHDES Wetlands Program may requiresubsequent monitoring and corrective measures if NHDES deemed the area inadequately stabilized or restored.

With Findings:1. This is a Minimum Impact Project per NH Administrative Rule Env-Wt 303.04(ah), as it involves the construction of a newtier 1 stream crossing that meets all of the requirements in Env-Wt 900.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01 as there is no otheravailable public access point for the ball fields that will not involve crossing the Canaan Elementary School Property.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03 as it will occur across a manmade channelthat used to convey sewage into the Indian River.

Decision Report 20 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(b) Requirements forApplication Evaluation, has been considered in the design of the project.5. In a review letter dated July 09, 2017, the NH Natural Heritage Bureau (NHB) found that there were no records of asensitive species in the vicinity of the project.6. On December 15, 2017, an extension agreement until December 20, 2017, was signed and submitted by the agent,Jonathan Sisson to allow for additional time to complete a hydraulic analysis of the crossing, to formulate a revegetation plan,and to complete a stream downgrade request.7. On December 20, 2017, an extension agreement until December 27, 2017, was signed and submitted by the agent,Jonathan Sisson to allow for additional time to complete a hydraulic analysis of the crossing, to formulate a revegetation plan,and to complete a stream downgrade request.8. In a letter dated December 27, 2017, the applicant requested that the stream crossing tier be downgraded from a tier 3crossing within a 100-year floodplain, to a tier 1 crossing as the watershed size at the site of the stream crossing is 108.8acres per Env-Wt 904.04(b).9. In a HydroCAD report dated January 12, 2018, and received by NHDES on January 16, 2018, it was determined that theproposed crossing would not pass the 50-year storm event with peak flow elevations at 946.48 feet while the culvert invert isat 946.20 feet at its peak. However, this report did not account for the presence of attenuation due to upstream culverts thatexist within the watershed at the stream crossings along Blain Road or Canaan Street. For example, approximately 142 feetupstream of the proposed crossing (measured using Google Earth 7.1.8.3036), there is a 30 inch diameter culvert thatcrosses Canaan Street that was installed by the NH Department of Transportation in 2010 (See Wetlands File #2010-01798).The larger 36 inch culvert proposed in this application should therefore be sufficient to handle the flows through this areawithout negatively impacting flood stages on abutting properties.

2016-02540 SCOPA, WILLIAM

MADISON BIG PEA PORRIDGE POND

Requested Action:

Impact 420 square feet in order to construct a 25 foot x 11 foot beach delimited by 27 linear feet of retaining wall with 4 footwide access stairs on 104 feet of frontage along Pea Porridge Pond in Madison.

*********************************

APPROVE PERMITImpact 420 square feet in order to construct a 25 foot x 11 foot beach delimited by 27 linear feet of retaining wall with 4 footwide access stairs on 104 feet of frontage along Pea Porridge Pond in Madison.

With Conditions:1. All work shall be in accordance with revised plans by William Scopa dated January 14, 2018, and received by NHDES onJanuary 23, 2018.2. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.3. This permit does not authorize the removal of trees or saplings within the waterfront buffer.4. Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.5. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.6. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that noturbidity escapes the immediate dredge area and shall remain until suspended particles have settled and water at the worksite has returned to normal clarity.7. All excavated material and construction-related debris shall be placed outside of the areas subject to RSA 482-A. Anyspoil material deposited within 250 feet of any surface water shall comply with RSA-483-B.8. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).9. No more than 2 cubic yard of sand shall be used and all sand shall be located above the normal high water line.10. Any future beach replenishment shall require a new permit.11. The permittee shall provide appropriate diversion of surface water runoff to prevent erosion of beach area.12. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surface

Decision Report 21 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

waters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackifiers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.13. A combination of trees, shrubs and ground covers representing the density and species diversity of the vegetationpresent prior to construction shall be replanted beginning at a distance no greater than 5 feet landward from the beach area.

With Findings:1. This is a minimum impact project per Administrative Rule Env-Wt 303.04(m) projects that disturb less than 50 linear feet,measured along the shoreline, of a lake or pond or its bank.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the departments jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(b) Requirements forApplication Evaluation, has been considered in the design of the project.5. The applicant has submitted evidence of a pre-existing sloped beach.

2017-00980 SYLVAIN, MARY

DOVER

Requested Action:

An amendment request received on January 17, 2017, requested an additional 120 square feet of wetland impact due toproposed building layout.

APPROVE AMENDMENTFill 2,970 square feet of emergent/scrub-shrub wetlands for commercial lot development.

With Conditions:1. AMENDED: All work shall be in accordance with revised plans by TEC, Inc. and Seekamp Environmental Consulting, Inc.dated December 4, 2017, as received by the NH Department of Environmental Services (NHDES) on January 17, 2018.2. Any requirements by the UNH Stormwater Centers review of the proposal shall be adequately addressed by thepermittee.3. Any further alteration of areas such as wetlands, wetlands buffers or impervious surface on this property will require thepermittee to meet and coordinate with the City of Dover Conservation Commission.4. Any further alteration of areas on this property that are subject to RSA 482-A jurisdiction will require a new application andfurther permitting.5. No person undertaking any activity shall cause or contribute to, or allow the activity to cause or contribute to, any violationsof the surface water quality standards in RSA 485-A and Env-Wq 1700.6. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.7. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).8. Extreme precautions shall be taken within riparian areas to prevent unnecessary removal of vegetation duringconstruction. Areas cleared of vegetation must be revegetated with like native species within three days of the completion of

the disturbance.9. Construction equipment shall be inspected daily for leaking fuel, oil, and hydraulic fluid prior to entering surface waters or

wetlands or operating in an area where such fluids could reach groundwater, surface waters, or wetlands.10. The permiffees contractor shall maintain appropriate oil/diesel fuel spill kits on site that are readily accessible at all timesduring construction, and shall train each operator in the use of the kits.11. All refueling of equipment shall occur outside of surface waters or wetlands during construction. Machinery shall bestaged and refueled in upland areas only.12. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackiflers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.

Decision Report 22 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

With Findings:DES reaffirms finding no.’s 1 - 8:

1 This is a minimum impact project per administrative rule Env-Wt 303.04(f), alteration of less than 3,000 square feet ofswamps or wet meadows.2. The need for the proposed impacts has been demonstrated by the applicant per administrative rule Env-Wt 302.013. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per administrative rule Env-Wt 302.03. The applicantminimized impacts by incorporating retaining walls and avoiding the higher function and value wetlands on the property.Further, the applicant has demonstrated that the impacted wetland is within a previously disturbed sewer easement area andgroundwater is likely intercepted upslope of the impacted area and follows the sewer pipe down-slope until it is forced to thesurface.4. The applicant is incorporating low impact development (LID) stormwater features into the design of the project that will bepeered reviewed by the University of NH Stormwater Center.5. While not required by NHDES, the applicant is providing wetland replication areas on the property as a mitigationrequirement of the Conditional Use Permit by the City of Dover Planning Board.6. The applicant has demonstrated by plan and example that each factor listed in administrative rule Env-Wt 302.04(a)Requirements for Application Evaluation, has been considered in the design of the project.7. NH Natural Heritage Bureau has no record of sensitive species within the project vicinity.8. The Dover Conservation Commission unanimously voted to endorse the application with the condition that therequirements of the UNH Stormwater Center review letter be adequately addressed by the applicant and that if there are anyincreased impacts to wetlands, wetlands buffers or impervious surface, the applicant will have to return to the ConservationCommission. NHDES has conditioned the wetlands permit to address the Conservation Commission’s concerns.

2017-01240 CRAIG, KATHLEEN

FREEDOM OSSIPEE LAKE

Requested Action:

Replace existing 4 foot wide steps and 20 linear feet of retaining wall in-kind on 100 feet of frontage along Ossipee Lake inFreedom.

APPROVE PERMITReplace existing 4 foot wide steps and 20 linear feet of retaining wall in-kind on 100 feet of frontage along Ossipee Lake inFreedom.

With Conditions:1. All work shall be in accordance with plans and application materials by Xavier Simonsen as received by DES.2. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.3. This permit does not authorize the removal of trees or saplings within the waterfront buffer that would result in a tree andsapling point score below the minimum required per RSA 483-B:9, V, (a)(2)(D)(iv).4. Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.5. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.6. All construction-related debris shall be placed outside of the areas subject to RSA 482-A.7. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).8. This permit does not authorize the placement of sand for any purpose.9. No person undertaking any activity shall cause or contribute to, or allow the activity to cause or contribute to, any violationsof the surface water quality standards in RSA 485-A and Env-Wq 1700.10. This permit shall not preclude DES from initiating appropriate action if DES later determines that any of the structuresdepicted as “existing” on the plans submitted by or on behalf of the permitted were not previously permitted or grandfathered.

Decision Report 23 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

11. The repairs shall maintain the size, location, and configuration of the pre-existing structures.12. The permiffee/permittee’s contractor shall revegetate the disturbed area with trees, shrubs and ground coversrepresenting the density and species diversity of the existing stand of vegetation removed for this project, exclusive of anyinvasive or nuisance species.13. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackifiers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.

With Findings:1. This is a minimum impact project per Administrative Rule Env-Wt 303.04(x) maintenance, repair, or replacement of anon-docking structure such as a culvert, headwall, bridge, dam, residential utility line, or rip-rap slope of less than 50 linearfeet, provided there shall be no change in location, configuration, construction type, or dimensions of the structures.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(b) Requirements forApplication Evaluation, has been considered in the design of the project.

2017-01958 NOBREGA, ARTHURJCHERYL

SALEM ARLINGTON MILL RESERVOIR

Requested Action:

Amend permit to correctly reflect frontage length and distance the pier is allowed to extend from shore in under SpecificCondition #7.

Conservation Commission/Staff Comments:7/7/17 Con. Com. requests a “hold” on this application until a site investigation can be conducted and a report issued.9-19-17 - No histroic properties affected per DHR.

APPROVE AMENDMENTCorrect permit to read: Remove an existing 4 foot x 20 foot seasonal pier and install a 4 foot x 30 foot seasonal pier to beaccessed by a 4 foot x 12 foot ramp on 31 feet of frontage along Arlington Mill Reservoir, in Salem.

With Conditions:1. All work shall be in accordance with revised plans by Cheryl Nobrega dated September 23, 2017, as received by DES onSeptember 23, 2017.2. This permit is not valid and effective until it has been recorded with the appropriate county Registry of Deeds by theapplicant. Prior to starting work under this permit, the permittee shall submit a copy of the recorded permit to the DESWetlands Program by certified mail, return receipt requested.3. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.4. Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.5. Any subdivision of the property frontage will require removal of a sufficient portion of the docking structures to comply withthe dock size and density requirements in effect at the time of the subdivision.6. Only those structures shown on the approved plans shall be installed or constructed along this frontage.7. No portion of the pier shall extend more than 40 feet from the shoreline.8. All seasonal structures shall be removed for the non-boating season.

With Findings:1. This is a minimum impact project per Administrative Rule Env-Wt 303.04(a) modification of a seasonal docking structureproviding 2 slips.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impact

Decision Report 24 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

to areas and environments under the departments jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(b) Requirements forApplication Evaluation, has been considered in the design of the project.5. The applicant has provided a signed notarized waiver of the 20 foot setback to property lines from the abutter to the eastas require per RSA 482-A:3, IV-a.

207 7-02474 RILEY, PAUL

DANVILLE COLBY BROOK

Requested Action:

Impact a total of 1,951 square feet (sq. ft.) of palustrine forested wetland to include retaining 1,145 sq. ft. of fill for lotdevelopment for an existing greenhouse and restore 806 sq. ft. of fill, including culverts and logs used to create an accessway.

APPROVE AFTER THE FACTImpact a total of 1,951 square feet (sq. ft.) of palustrine forested wetland to include retaining 1,145 sq. ft. of fill for lotdevelopment for an existing greenhouse and restore 806 sq. ft. of fill, including culverts and logs used to create an accessway.

1. Remove approximately 806 sq. ft. of fill, including culverts and logs from wetland and restore disturbed area with wetlandvegetation.2. Retain approximately 1145 sq. ft. of fill under and around existing greenhouse used for organic agriculture.

With Conditions:1. All work shall be in accordance with restoration plan prepared by Meridian Land Services, Inc, dated July 24, 2017 andreceived by NHDES on August 18, 2017,2. Retention of the 1,145 sq. ft. of fill under and around the greenhouse is contingent on successful restoration of the 806 sq.ft. of forested wetlands3. All work associated with this project shall be conducted in compliance with RSA 482-A and Administrative Rule Env-Wt100. etseq.4. Consideration of an after-the-fact application shall not preclude or limit the department’s exercise of any additionalenforcement action.

With Findings:1. On November 23, 2015, NHDES received a Land Resources Management Complaint Form from a confidentialcomplainant alleging the property owner had filled in areas of a jurisdictional wetland and installed a dock without properauthorization from NHDES.2. On December 2, 2015, NHDES issued an Alleged Violator Letter to the property owner notifying them of the complaintreceived by NHDES.3. On December 9, 2015, NHDES personnel inspected the property in response to the complaint received to determine theextent of the violations. A copy of the Compliance Inspection Report with requests to remove the stumps and manure fromthe jurisdictional areas and not reinstall the dock without NHDES approval was given to the property owner.4. On February 10, 2017, NHDES sent a letter to the property owner requesting an update on the status of the debrisremoval and dock.5. On February 16, 2017, the property owner phoned NHDES in response to the letter dated February 10, stating that therequested actions had been taken care of.6. On March 6, 2017, NHDES personnel conducted a site inspection of the property. The report noted the followingobservations:(a) There were several access roads with crossings and undersized culverts from Creek Hill Drive leading to thestream/wetland complex, two of which were through forested wetlands; (b) Fill within wetlands jurisdiction was evident,including piles of compost, yard waste, rubble, and an in-stream diversion which was redirecting water flow from it naturalcourse; (c) A larger area adjacent to the stream has been cleared of native vegetation, re-graded, and maintained by mowing.7. On April 20, 2017, NHDES sent a Notice of Findings (NOF) to the property owner. In addition to items (a) - (C) noted in

Decision Report 25 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

finding #6, the NOF also noted that based on a review of the subdivision plan by Lavelle Associates dates June 29, 2005, andstamped by Timothy J. Ferwerda, NH Certified Wetlands Scientist (CWS), on September 21, 2015 for Wetlands andNon-Site Specific Permit #2005-02303 (the Permit), as well as NHDES’ site assessment, the unauthorized impacts occurredin jurisdictional wetlands. As a result, NHDES requested the property owner to (a) retain a CWS to re-delineate the wetlandson the property by May 31, 2017; and (b) submit the CWS stamped wetland delineation clearly showing the impacted areasto NHDES by June 30, 2017.8. The Permit authorized 2,510 sq. ft. of impacts to wet meadow to construct a roadway and cul-de-sac (Creek Hill Lane) toaccess a 9-lot residential subdivision.9. On August 18, 2017, NHDES received a Wetland Permit Application and Restoration Plan, prepared by Meridian LandServices, Inc., dated August 8, 2017 satisfying the requests of the NOF.10. This is a Minimum Impact Project per Administrative Rule Env-Wt 303.04ffI; projects involving alteration of less than3000 sq. ft. in swamps or wet meadows that ate not in prime wetlands or do not meet the requirements of Env-Wt 303.02(k),provided that no previous department permit has placed restrictions on the property of the applicant.11. The applicant has demonstrated the need for the proposed impacts per Env-Wt 302.01(b).12. The applicant has provided evidence that the proposed project is the alternative with the least adverse impact to areasand environments under the department’s jurisdiction per Env-Wt 302.03.13. The application included NH Natural Heritage Bureau (NHB) Datacheck Results Letter NHBJ7-2277 which identified norecorded occurrences for sensitive species near the project area.14. No comments were submitted from the NHB or the NH Fish and Game Nongame and Endangered Wildlife Program.15. The application included a US Army Corps of Engineers NH Programmatic General Permit (PGP) Appendix B - CorpsSecondary Impacts Checklist.16. The application included a US Fish & Wildlife Service (USFWS) Information for Planning and Consultation (IPaC) report(Event Code E5E1NEOO-2017-E-05325) which identified one (1)threatened species that may occur within the boundary ofthe project: Northern Long-eared Bat (Myotis septentrionalis). There were no critical habitats under USFWS jurisdictionidentified within the project area.17. No comments were received from the Danville Conservation Commission.

201 7-02742 MORRIS, KRISTINA

NEW LONDON MESSER POND

Requested Action:

Dredge and fill 415 square feet of palustrine scrub-shrub wetland to upgrade an existing boardwalk.

*********************************

APPROVE PERMITDredge and fill 415 square feet of palustrine scrub-shrub wetland to upgrade an existing boardwalk.

With Conditions:1. All work shall be in accordance with plans and narrative by CLD Consulting Engineers dated May 2017, and last receivedby the NH Department of Environmental Services (DES) on January 17, 2018.2. All work shall be done using hand tools only.3. In accordance with the plans and narrative provided, the height of the boardwalk shall be at least one foot above theexisting ground to provide wildlife passage, allow sunlight to penetrate and to maintain the natural hydrologic regime beneaththe structure.4. All dredged and excavated material and construction-related debris shall be placed outside of the areas subject to RSA482-A. Any spoil material deposited within 250 feet of any surface water shall comply with RSA-483-B.5. Appropriate siltation, erosion and turbidity controls shall be in place prior to construction, shall be maintained duringconstruction, and shall remain until the area is stabilized. Temporary controls shall be removed once the area has beenstabilized.6. Work shall be conducted in a manner so as to minimize turbidity and sedimentation to surface waters and wetlands.7. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).

Decision Report 26 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

8. Erosion control products shall be installed per manufacturers recommended specifications.9. No person shall collect, transport, import, export, move, buy, sell, distribute, propagate or transplant any living and viableportion of any plant, which includes all of their cultivars and varieties listed in Table 3800.1 of the New Hampshire prohibitedinvasive species list fAgr 3802.01).

With Findings:1. This is a Minimum Impact Project per Administrative Rule Env-Wt 303.04(f), alteration of less than 3,000 square feet in aswamp or wet meadow.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01. The existing boardwalk isin a state of disrepair.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.4. The proposed structure will be elevated over the surface of the wetland with permeable decking and an aluminum frame.The existing structure is composed of deteriorating wooden planks laid directly on the ground.5. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(b) Requirements forApplication Evaluation, has been considered in the design of the project.6. No comments of concern were received by DES from abutters or local governing organizations.7. The Natural Heritage Bureau (NHB) report submitted with the application (NHB17-2162) stated that there are “no recordedoccurrences for sensitive species near this project area.”8. There is an existing legal seasonal dock on the property (DES file #2013-02343).

EXPEDITED MINIMUM************************************************************

2012-02831 MANCHESTER HOUSING & REDEVELOPMENT AUTHORITY

MANCHESTER Unnamed Stream

Requested Action:

Request a time extension.

Conservation Commission/Staff Comments:1. The Conservation Commission signed the expedited application waiving their right to intervene.

APPROVE TIME EXTENSIONDredge and fill 140 sq. ft. of swamp wetlands for access to a proposed commercial building. The project also includes onsitestorm water treatment before discharging to adjacent wetlands.

With Conditions:1. All work shall be in accordance with plans by Long Beach Development Associates revision date of February 1, 2013, asreceived by the NH Department of Environmental Services (DES) on February 4, 2013.2. Appropriate siltation/erosion/turbidity controls shall be in place prior to construction, shall be maintained duringconstruction, and remain in place until the area is stabilized. Silt fence(s) must be removed once the area is stabilized.3. Discharge from dewatering of work areas shall be to sediment basins that are: a) located in uplands; b) lined with haybales or other acceptable sediment trapping liners; c) set back as far as possible from wetlands and surface waters, in allcases with a minimum of 20 feet of undisturbed vegetated buffer.4. Dredged material shall be placed outside of the jurisdiction of the DES Wetlands Bureau.5. Within three days of final grading, all exposed soil areas shall be stabilized by seeding and mulching during the growingseason, or if not within the growing season, by mulching with tack or netting and pinning on slopes steeper than 3:1.6. Where construction activities have been temporarily suspended within the growing season, all exposed soil areas shall bestabilized within 14 days by seeding and mulching.

Decision Report 27 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

7. Where construction activities have been temporarily suspended outside the growing season, all exposed areas shall bestabilized within 14 days by mulching and tack. Slopes steeper than 3:1 shall be stabilized by matting and pinning.8. The contractor responsible for completion of the work shall utilize techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).9. Any further alteration of areas on this property that ate within the jurisdiction of the DES Wetlands Bureau will require anew application and further permitting by the Bureau.10. Construction equipment shall be inspected daily for leaking fuel, oil and hydraulic fluid. Faulty equipment shall berepaired immediately.11. The contractor shall have appropriate oil spill kits on site and readily accessible at all times during construction and eachoperator shall be trained in its use.12. All refueling of equipment shall occur outside of surface waters or wetlands.

With Findings:1. The owner certifies that this permit qualifies for a permit extension in accordance with RSA 482-A:3, XIV-a, and Env-Wt502.01.2. This permit has been extended in accordance with RSA 482-A:3, XIV-a and Env-Wt 502.01.

2017-02920 PEGGYS COVE ASSOCIATION

ALTON LAKE WINNIPESAUKEE

Requested Action:

Replenish sand on 2,498 square feet of private community beach on approximately 168 feet of frontage along LakeWinnipesaukee, in Alton.

*********************************

APPROVE PERMITReplenish sand on 2,498 square feet of private community beach on approximately 168 feet of frontage along LakeWinnipesaukee, in Alton.

With Conditions:1. All work shall be in accordance with plans by Dan Pikora as received by DES on December 22, 2017.2. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.3. Work authorized shall be carried out such that there are no discharges in or to spawning or nursery areas during spawningseasons. Impacts to such areas shall be avoided or minimized to the maximum extent practicable during all other times ofthe year.4. Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.5. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.6. No mote than 10 cubic yards of sand shall be used and all sand shall be located above the normal high water line.7. This permit authorizes a single beach replenishment only. Any future beach replenishment shall require a new permit.8. The permittee shall provide appropriate diversion of surface water runoff to prevent erosion of beach area.

With Findings:1. This is a minimum impact project per Administrative Rule Env-Wt 303.04(aa) replenishment of sand on an existing beach,provided no sand shall be placed below the high water line or full pond elevation and no more than 10 cubic yards of sandshall be used.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(b) Requirements forApplication Evaluation, has been considered in the design of the ptoject.

Decision Report 28 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

2017-03622 HARRIS, JOHN

PELHAM Unnamed Wetland

Requested Action:

Dredge and fill 1500 square feet of forested wetland for the installation of a 48-inch HDPE culvert for the construction of adriveway to access buildable uplands on a lot of approximately 7.5 acres.

APPROVE PERMITDredge and fill 1500 square feet of forested wetland for the installation of a 48-inch HDPE culvert for the construction of adriveway to access buildable uplands on a lot of approximately 7.5 acres.

With Conditions:1. All work shall be in accordance with plans by Benchmark Engineering, Inc. dated May 30, 2014 and revised 6-7-14 asreceived by the NH Department of Environmental Services (NH DES) on December29 2017.2. This permit is not valid unless a septic system construction approval is authorized pursuant to RSA 485-A:29-44 andEnv-Wq 1000.3. Any further alteration of areas on this property that are subject to RSA 482-A jurisdiction will require further permitting.4. No person undertaking any activity shall cause or contribute to, or allow the activity to cause or contribute to, any violationsof the surface water quality standards in RSA 485-A and Env-Wq 1700.5, Work shall be done during low flow and in the dry only.6. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.7. In order to minimize impacts to protected turtles including spotted turtles, avoid the use of welded plastic or ‘biodegradableplastic’ netting or thread in erosion control matting. There are numerous documented cases of wildlife being trapped andkilled in erosion control matting with synthetic netting and thread. Several ‘wildlife friendly’ options such as woven organicmaterial (e.g., coco or jute matting) are commercially available, if needed on this job.8. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).9. The channel at the culvert inlet and outlet must maintain the natural and a consistent elevation and not impede water flow.10. Proper headwalls shall be constructed within seven days of culvert installation.11. Construction equipment shall be inspected daily for leaking fuel, oil, and hydraulic fluid prior to entering surface waters orwetlands or operating in an area where such fluids could reach groundwater, surface waters, or wetlands.12. The permittee’s contractor shall maintain appropriate oil/diesel fuel spill kits on site that are readily accessible at all timesduring construction, and shall train each operator in the use of the kits.13. All refueling of equipment shall occur outside of surface waters or wetlands during construction. Machinery shall bestaged and refueled in upland areas only.14. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackifiers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.

With Findings:1. This is a minimum impact project per Administrative Rule Env-Wt 303.04(f) Projects involving alteration of less than 3,000square feet in swamps or wet meadows that are not in prime wetlands or do not meet the requirements of Env-Wt 303.02(k),provided that no previousdepartment permit has placed restrictions on the property of the applicant.2. The impacts are necessary to access buildable uplands; therefore, the need for the proposed impacts has beendemonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(b) Requirements forApplication Evaluation, has been considered in the design of the project.5. The Pelham Conservation Commission signed the application waiving their right to intervene pursuant to RSA 482-A:11.6. The application included NH Natural Heritage Bureau (NHB) Datacheck Results Letter NHB17-3797 identifying five (5)

Decision Report 29 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

plant species and one vertebrate species, Spotted Turtle (Clemmys guttata) in the vicinity of the proposed impact.7. NHB reviewed the report provided with the application by Blue Moon Environmental, Inc. and stated, “[biased on thisassessment, and provided that no other sensitive plant species were observed during field surveys, I have no furtherconcerns about the proposed work.”8. In response to the NHB letter, in an email dated November 13, 2017, NH Fish and Game Nongame and EndangeredSpecies Program (NHFG) stated, “[aJs the culvert is oversized, we will allow a HDPE [culvertj in this situation. In order tominimize impacts to protected turtles including spotted turtles, avoid the use of welded plastic or ‘biodegradable plastic’netting or thread in erosion control matting.”9. In response to the recommendation by NHFG, NHDES has added a condition to the permit to reflect their request.

2017-03664 HAHN, DAVID

STODDARD HIGHLAND LAKE

Requested Action:

Impact 340 square feet of bank along 20.6 linear feet of shoreline to construct a 321 square foot perched beach enclosed bya 1 foot wide stone wall on an average of 103 feet of frontage along Highland Lake in Stoddard.

APPROVE PERMITImpact 340 square feet of bank along 20.6 linear feet of shoreline to construct a 321 square foot perched beach enclosed bya 1 foot wide stone wall on an average of 103 feet of frontage along Highland Lake in Stoddard.

With Conditions:1. All work shall be in accordance with plans by Meridian Land Services, Inc. dated October 25, 2017 as received by the NHDepartment of Environmental Services (DES) on December 22, 2017.2. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.3. This permit does not authorize the removal of trees or saplings within the waterfront buffer that would result in a tree andsapling point score below the minimum required per RSA 483-B:9, V, (a)(2)(D)(iv).4. This permit does not authorize any work on the existing 5 foot by 16 foot dock or its anchor pad.5. No person undertaking any activity shall cause or contribute to, or allow the activity to cause or contribute to, any violationsof the surface water quality standards in RSA 485-A and Env-Wq 1700.6. This permit shall not preclude NHDES from initiating appropriate action if NHDES later determines that any of thestructures depicted as “existing” on the plans submitted by or on behalf of the permitted were not previously permitted orgrandfathered.7. Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.8. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.9. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that noturbidity escapes the immediate dredge area and shall remain until suspended particles have settled and water at the worksite has returned to normal clarity.10. All excavated material and construction-related debris shall be placed outside of the areas subject to RSA 482-A. Anyspoil material deposited within 250 feet of any surface water shall comply with RSA-483-B.11. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).12. Only those structures shown on the approved plans shall be installed or constructed along this frontage. All portions ofthe structures shall be at least 20 feet from the abutting property lines or the imaginary extension of those lines into the water.13. Stone placed along the beach front for the purpose of retaining sand shall be placed above and landward of those rockscurrently located along the normal high water line (Elevation 1294.52). The rocks existing at the normal high water line shallremain undisturbed such that the natural shoreline remains visible and intact.14. No more than 10 cubic yards of sand shall be used and all sand shall be located above the normal high water line.15. Any future beach replenishment shall require a new permit.16. The permiffee shall provide appropriate diversion of surface water runoff to prevent erosion of beach area.17. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surface

Decision Report 30 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

waters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackifiers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.

With Findings:1. This is a minimum impact project per Administrative Rule Env-Wt 303.04(d), construction of a beach provided the beachserves a privately-owned single family residence; no fill or dredge shall occur below the high water line or full pond elevation;the total amount of dredge or fill shall not exceed 900 square feet; no work shall be conducted in a swamp, marsh, tidalbuffer zone, bog, or in or adjacent to a prime wetland; the work shall not alter more than 20 percent of the applicant’scontiguous shoreline up to a maximum of 50 feet; and no more than 10 cubic yards of sand shall be used;2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(b) Requirements forApplication Evaluation, has been considered in the design of the project.

2017-03678 MARSHALL, DAWNIJAMES

ALEXANDRIA NEWFOUND LAKE

Requested Action:

Impact 324 square feet of bank along 18 linear feet of shoreline to construct a 243 square foot perched beach enclosed by a2 foot wide stone wall; construct 6 foot wide dock access stairs; construct a 6 foot x 4 foot concrete anchor pad; install a 6foot x 40 foot seasonal pier on an average of 102.6 feet of shoreline along Newfound Lake in Alexandria.

APPROVE PERMITImpact 324 square feet of bank along 18 linear feet of shoreline to construct a 243 square foot perched beach enclosed by a2 foot wide stone wall; construct 6 foot wide dock access stairs; construct a 6 foot x 4 foot concrete anchor pad; install a 6foot x 40 foot seasonal pier on an average of 102.6 feet of shoreline along Newfound Lake in Alexandria.

With Conditions:1. All work shall be in accordance with plans by New Hampshire Environmental Consultants LLC dated October 31, 2017 asreceived by the NH Department of Environmental Services (DES) on December 27, 2017.2. This permit is not valid and effective until it has been recorded with the appropriate county Registry of Deeds by theapplicant. Prior to starting work under this permit, the permittee shall submit a copy of the recorded permit to the DESWetlands Program by certified mail, return receipt requested.3. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.4. This permit does not authorize the removal of trees or saplings within the waterfront buffet that would result in a tree andsapling point score below the minimum required per RSA 483-B:9, V, (a)(2)fD)fiv).5. Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.6. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.7. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that noturbidity escapes the immediate dredge area and shall remain until suspended particles have settled and water at the worksite has returned to normal clarity.8. All excavated material and construction-related debris shall be placed outside of the areas subject to RSA 482-A. Anyspoil material deposited within 250 feet of any surface water shall comply with RSA-483-B.9. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).10. Any subdivision of the property will require removal of a sufficient portion of the docking structures to comply with thedock size and density requirements in effect at the time of the subdivision.11. Only those structures shown on the approved plans shall be installed or constructed along this frontage. All portions ofthe structures shall be at least 20 feet from the abutting property lines or the imaginary extension of those lines into the water.12. No portion of the pier shall extend more than 40 feet from the shoreline at full lake elevation (Elevation 589.12).

Decision Report 31 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

13 All seasonal structures shall be removed for the non-boating season.14. Stone placed along the beach front tot the purpose of retaining sand shall be placed above and landward of those rockscurrently located along the normal high water line (Elevation 589.12). The rocks existing at the normal high water line shallremain undisturbed such that the natural shoreline remains visible and intact.15. The steps installed for access to the water shall be located completely landward of the normal high water line.16. No more than 10 cubic yards of sand shall be used and all sand shall be located above the normal high water line.17. Any future beach replenishment shall require a new permit.18. The permittee shall provide appropriate diversion of surface water runoff to prevent erosion of beach area.19. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tackiflers on slopes less than 3:1 or netting and pinning on slopes steeper than 3:1.

With Findings;1. This is a minimum impact project per Administrative Rule Env-Wt 303.04(a), construction or modification of a seasonalpier or wharf of no more than 2 slips, including previously existing slips, are proposed; and Env-Wt 303.04(d) construction ofa beach for a single family, with no fill below the high water line, does not exceed 900 square feet, and does not alter greaterthan 20% or mote that 50 feet of the applicant’s contiguous shoreline.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(b) Requirements forApplication Evaluation, has been considered in the design of the project.5. The applicant has an average of 102.6 feet of shoreline frontage along Newfound Lake.6. A maximum of 2 slips may be permitted on this frontage per Rule Env-Wt 402.13, Frontage Over 75’.7. The proposed docking facility will provide 2 slips as defined per RSA 482-A:2, VIII and therefore meets Rule Env-Wt402.13.

2017-03679 ANDERSON SR, WILLIAM

WASHINGTON ASHUELOT RIVER

Requested Action:

Permanently remove 4 foot x 12 foot seasonal pier with 3 foot x 5 access ramp and install 5 foot x 20 foot seasonal pier witha 5 foot x 10 foot seasonal “L” accessed by a 5 foot x 6 foot ramp on an average of 400 feet of shoreline along the AshuelotRover in Washington.

APPROVE PERMITPermanently remove 4 foot x 12 foot seasonal pier with 3 foot x 5 access ramp and install 5 foot x 20 foot seasonal pier witha 5 foot x 10 foot seasonal “L” accessed by a 5 foot x 6 foot ramp on an average of 400 feet of shoreline along the AshuelotRover in Washington.

With Conditions:1. All work shall be in accordance with plans as received by the NH Department of Environmental Services (DES) onDecember 27, 2017.2. This permit is not valid and effective until it has been recorded with the appropriate county Registry of Deeds by theapplicant. Prior to starting work under this permit, the permittee shall submit a copy of the recorded permit to the DESWetlands Program by certified mail, return receipt requested.3. All development activities associated with this project shall be conducted in compliance with applicable requirements ofRSA 483-B and N.H. Code of Administrative Rules Env-Wq 1400 during and after construction.4. This permit does not authorize the removal of trees or saplings within the waterfront buffer that would result in a tree andsapling point score below the minimum required per RSA 483-B:9, V, (a)(2)(D)(iv).5. Work shall be carried out in a time and manner to avoid disturbances to migratory waterfowl breeding and nesting areas.6. Appropriate siltation and erosion controls shall be in place prior to construction, shall be maintained during construction,and shall remain until the area is stabilized. Temporary controls shall be removed once the area has been stabilized.

Decision Report 32 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

7. Appropriate turbidity controls shall be installed prior to construction, shall be maintained during construction such that noturbidity escapes the immediate dredge area and shall remain until suspended particles have settled and water at the worksite has returned to normal clarity.8. All construction-related debris shall be placed outside of the areas subject to RSA 482-A.9. The contractor responsible for completion of the work shall use techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).10. Any subdivision of the property will require removal of a sufficient portion of the docking structures to comply with thedock size and density requirements in effect at the time of the subdivision.11. Only those structures shown on the approved plans shall be installed or constructed along this frontage. All portions ofthe structures shall be at least 20 feet from the abutting property lines or the imaginary extension of those lines into the water.12. No portion of the pier shall extend more than 20 feet from the shoreline Ordinary High Water Mark13. All seasonal structures shall be removed for the non-boating season.

With Findings:1. This is a minimum impact project per Administrative Rule Env-Wt 303.04(a), construction or modification of a seasonalpier or wharf if no more than 2 slips, including previously existing slips, are proposed.2. The need for the proposed impacts has been demonstrated by the applicant per Env-Wt 302.01.3. The applicant has provided evidence which demonstrates that this proposal is the alternative with the least adverse impactto areas and environments under the department’s jurisdiction per Env-Wt 302.03.4. The applicant has demonstrated by plan and example that each factor listed in Env-Wt 302.04(b) Requirements forApplication Evaluation, has been considered in the design of the project.5. The applicant has an average of 400 feet of shoreline frontage along the Ashuelot River.6. A maximum of 6 slips may be permitted on this frontage per Rule Env-Wt 402.13, Frontage Over 75’.7. The proposed docking facility will provide 2 slips as defined per RSA 482-A:2, VIII and therefore meets Rule Env-Wt402.13.

PERMIT BY NOTIFICATION

201 8-00080 HAYNES III, HENRY/SANDRA

ENFIELD MASCOMA LAKE

Requested Action:

Repair 100 linear foot retaining wall footer in-kind according to plans by Riverside Ecological Designs LLC dated 12/14/2017and revised 01/19/2018 as received by NHDES on 01/21/2018 along frontage on Mascoma Lake in Enfield.

PBN IS COMPLETERepair 100 linear foot retaining wall footer in-kind according to plans by Riverside Ecological Designs LLC dated 12/14/2017and revised 01/19/2018 as received by NHDES on 01/21/2018 along frontage on Mascoma Lake in Enfield.

With Findings:1. This project is classified as a minimum impact project per Rule Env-Wt 303.04(c) for the repair or replacement of existingretaining walls that is performed “in the dry” during drawdown of waters, and that results in no change in height, length,location, or configuration. If this wall is to be refaced such additional width shall not exceed 6 inches.

FORESTRY NOTIFICATION

201 8-00153 JANSEN, CHRISTINA/RONALD

Decision Report 33 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

THORNTON Unnamed Stream

COMPLETE NOTIFICATIONTHORNTON, MAP# 15; LOT# 20; BLOCK# 1

2018-00154 TRESCOTT COMPANY INC

HANOVER Unnamed Stream

COMPLETE NOTIFICATIONHANOVER; MAP# 5; LOT# 112

2018-001 56 CHASE, CLAUDIA

FRANCESTOWN Unnamed Stream

COMPLETE NOTIFICATIONFRANCESTOWN; MAP# 9; LOT# 19

201 8-00170 BAYROOT LLC

DIXVILLE Unnamed Stream

COMPLETE NOTIFICATION

DIXVILLE; MAP# 1626; LOT# 9

2018-00176 MACLEAN, LANCE/MARILOU

BROOKFIELD Unnamed Stream

Decision Report 34 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

COMPLETE NOTIFICATIONBROOKFIELD; MAP#4; LOT# 10

2018-00177 WHITE, CHERYL/ROBERT

BROOKFIELD Unnamed Stream

COMPLETE NOTIFICATIONBROOKFIELD; MAP# 4; LOT# 11

201 8-001 79 BADGER REV TRUST, CHERRYIJAY

BROOKFIELD Unnamed Stream

COMPLETE NOTIFICATIONBROOKFIELD; MAP# 3; LOT(S)# 7,101OA

201 8-001 80 BYRNE, SANDRA

BROOKFIELD Unnamed Stream

COMPLETE NOTIFICATIONBROOKFIELD; MAP# 4; LOT(S)# 7,8

2018-001 86 ATWOOD HEIRS, DONALD

BRIDGEWATER Unnamed Stream

COMPLETE NOTIFICATIONBRIDGEWATER; MAP# 205; LOT# 11; BLOCK# 1

Decision Report 35 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

201 8-00205 PATTEN, ADAM

WENTWORTH Unnamed Stream

Conservation Commission/Staff Comments:

2/1/17:Tyvek returned as undeliverable. Resent to Foresters other known address. Updated address in database.

COMPLETE NOTIFICATIONWEN]WORTH; MAP# 8; LOT(S)# 4,7; BLOCK# 13

2018-00227 ADAMS, DAVID/DES

FRANCESTOWN Unnamed Stream

COMPLETE NOTIFICATIONFRANCESTOWN; TAX MAP#3; LOT# 100

TRAILS NOTIFICATION

2018-00167 USA NATIONAL PARK SERVICE

HANOVER Unnamed Stream

COMPLETE NOTIFICATIONInstallation of 9 bog bridges over 3 wet sections of trail: a 20’ section, a 30’ section and a 40’ section.

GOLD DREDGE

2018-00152 THAYER, BRIAN

(ALL TOWNS) Unnamed Stream

Decision Report 36 2/6/2018For Actions Taken 01/22/2018 to 01 /28/2018

COMPLETE NOTIFICATIONGOLD DREDGE

201 8-00201 BLOWEY, ZACHARY

(ALL TOWNS) Unnamed Stream

COMPLETE NOTIFICATIONGold Dredge

201 8-00202 WINN, GANNON

(ALL TOWNS) Unnamed Stream

COMPLETE NOTIFICATIONGOLD DREDGE

ROADWAY MAINTENANCE NOTIFICATION

201 8-00216 SALEM, TOWN OF

SALEM Unnamed Wetland

2018-00217 SALEM, TOWN OF

SALEM Unnamed Wetland

201 8-00219 SALEM, TOWN OF

SALEM Unnamed Wetland

Decision Report 37 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

UTILITY NOTIFICATION

201 8-00150 EVERSOURCE ENERGY

NORTHWOOD Unnamed Wetland

201 8-00151 EVERSOURCE ENERGY

ROCHESTER Unnamed Wetland

2018-00158 EVERSOURCE ENERGY

SEABROOK Unnamed Wetland

201 8-00159 EVERSOURCE ENERGY

SOUTH HAMPTON Unnamed Wetland

2018-001 62 EVERSOURCE ENERGY

SPRINGFIELD Unnamed Wetland

201 8-00164 EVERSOURCE ENERGY

STODDARD Unnamed Wetland

201 8-001 66 EVERSOURCE ENERGY

STRAFFORD Unnamed Wetland

Decision Report 38 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

201 8-00168 EVERSOURCE ENERGY

SULLIVAN Unnamed Wetland

2018-001 87 EVERSOURCE ENERGY

SUNAPEE Unnamed Wetland

2018-00188 EVERSOURCE ENERGY

TAMWORTH Unnamed Wetland

201 8-001 90 EVERSOURCE ENERGY

WEARE Unnamed Wetland

-Send to Governor and Executive Council-

201 8-001 92 EVERSOURCE ENERGY

WILMOT Unnamed Wetland

2018-00193 EVERSOURCE ENERGY

WINCHESTER Unnamed Wetland

201 8-001 95 EVERSOURCE ENERGY

BOW Unnamed Wetland

Decision Report 39 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

SHORELAND PERMIT

2011-03119 PUOPOLO, KEVIN/MARGARET

MEREDITH LAKE WINNIPESAUKEE

Requested Action:

Impact 14,897 square feet in order to construct a path toward the reference line, two patios and a fire pit.

Inspection Date: 07/28/2016 by MIRANDA L ADAMS

APPROVE AFTER THE FACTRetain 14,897 square feet for the construction of a path toward the reference line, two patios and a fire pit.

With Conditions:1. All work shall be in accordance with plans by NH Environmental Consultants, LLC dated October 20, 2016 and receivedby the NH Department of Environmental Services (NHDES) on November 10, 2016 and the Shoreline Restoration Plan datedSeptember 21, 2017 and received by the Department on September 26, 2017.2. No more than 6.1% of the area of the lot within the protected shoreland shall be coveted by impervious surfaces unlessadditional approval is obtained from NHDES.3. At least 4,564 square feet of the Natural Woodland Buffer beyond the primary building setback must remain in anunaltered state in order to comply with RSA 483-B:9, V, (b), (2).4. Erosion and siltation controls shall be appropriate to the size and nature of the project and to the physical characteristicsof the site, including slope, soil type, vegetative cover, and proximity to wetlands or surface waters.5. Al? activities conducted in association with the completion of this project shall be conducted in a manner that complies withapplicable criteria of Administrative Rules Chapter Env-Wq 1400 and RSA 483-B during and after construction.6. No person undertaking any activity in the protected shoreland shall cause or contribute to, or allow the activity to cause orcontribute to, any violations of the surface water quality standards established in Env-Ws 1700 or sucoessor rules in Env-Wq1700.

201 5-02073 CORCORAN, JANE

NEW DURHAM MERRYMEETING LAKE

Requested Action:

Request name change to Timothy and Pamela Courounis to impact 5,509 sq ft in order to construct a new house, well andseptic system. Other construction and installation includes, infiltration steps, drip edges, and a catch basin with a leachingchamber.

Decision Report 40 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

APPROVE NAME CHANGEChange name to Timothy and Pamela Courounis 54 Beaver Dam Road, Alton NH 03810 to impact 5,509 sq ft in order toconstruct a new house, well and septic system. Other construction and installation includes, infiltration steps, drip edges, anda catch basin with a leaching chamber.

With Conditions:1. All work shall be in accordance with revised plans by Varney Engineering, LLC dated September 9, 2015 and received bythe NH Department of Environmental Services (DES) on August 6, 2015.2. This permit is contingent on approval by the DES Subsurface Systems Bureau.3. This permit does not authorize the removal of trees or saplings within the waterfront buffer that would result in a tree andsapling point score below the minimum required per RSA 483-B:9, V, (a), (2), fD), (iv).4. No more than 15% of the area of the lot within the protected shoreland shall be covered by impervious surfaces unlessadditional approval is obtained from DES.5. At least 1,684 sq ft of the Natural Woodland Buffer beyond the primary building setback must remain in an unaltered statein order to comply with RSA 483-B:9, V, (b), (2).6. All activities conducted in association with the completion of this project shall be conducted in a manner that complies withapplicable criteria of Administrative Rules Chapter Env-Wq 1400 and RSA 483-B during and after construction.7. Erosion and siltation control measures shall be installed prior to the start of work, be maintained throughout the project,and remain in place until all disturbed surfaces are stabilized.8. Erosion and siltation controls shall be appropriate to the size and nature of the project and to the physical characteristicsof the site, including slope, soil type, vegetative cover, and proximity to wetlands or surface waters.9. No person undertaking any activity in the protected shoreland shall cause or contribute to, or allow the activity to cause orcontribute to, any violations of the surface water quality standards established in Env-Ws 1700 or successor rules in Env-Wq1700.10. Any fill used shall be clean sand, gravel, rock, or other suitable material.11. The individual responsible for completion of the work shall utilize techniques described in the New HampshireStormwater Manual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).12. This permit shall not preclude DES from taking any enforcement or revocation action if DES later determines that any ofthe structures depicted as ‘existing” on the plans submitted by the applicant were not previously permitted or grandfathered.

2077-00778 ZELLER, ROBERT

NEW LONDON PLEASANT LAKE

Requested Action:

Impact 26,312 square feet of protected shoreland in order to replace existing residential structure and outbuildings,reconfigure driveway, construct pervious walkways and septic system.

AMENDMENT DESCRIPTION: Plans revised in order to alter driveway and add garage with no increase in impervious area.

APPROVE AMENDMENTImpact 26,312 square feet of protected shoreland in order to replace existing residential structure and outbuildings,reconfigure driveway, construct pervious walkways and septic system.

AMENDMENT DESCRIPTION: Plans revised in order to alter driveway and add garage with no increase in impervious area.

With Conditions:1. All work shall be in accordance with plans by CLD Consulting Engineers dated as revised through January 17, 2018 andreceived by the NH Department of Environmental Services (NHDES) on January 19, 2018.2. Neither the new primary structure nor the proposed septic system may be constructed until the system is approved by theNHDES Subsurface Systems Bureau.3. Orange construction fencing shall be installed at the limits of the temporary impact area as shown on the approved plans

Decision Report 41 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

prior to the start of work and shall be maintained throughout the project in order to prevent accidental encroachment intoareas in which impacts have not been approved.4. No more than 14.2% of the area of the lot within the protected shoreland shall be covered by impervious surfaces unlessadditional approval is obtained from NUDES.5. Within 90 days the completion of the framing of the proposed structure the Permittee shall provide documentation,including photos, showing that all restoration plantings within the Waterfront Buffer have occurred, to the NUDES WetlandsBureau6. Following planting, all planting areas within the restored Waterfront Buffer areas shall be allowed to revert back to anatural state. The regeneration of ground cover shall not be suppressed by the use of bark mulch or other materials.7. All planting as shown on the approved plans shall be completed prior to the occupancy of the residential structure.8. The plantings shall be inspected at the beginning and end of the growing season for a period of 3 years after initialplantings have been completed during which time any failed plantings shall immediately be replaced by the owner of theproperty.9. At the completion of the 3 year monitoring period the Owner of the property shall submit a report including photographs ofthe planted buffer to the Department.10. Native vegetation within an area of at least 5,861 sq. ft. within the Natural Woodland Buffer located between 50 and 150ft. landward of the reference line shall be retained in an unaltered state in order to comply with RSA 483-B:9, V, (b), (2).11. Erosion and siltation control measures shall be installed prior to the start of work, be maintained throughout the project,and remain in place until all disturbed surfaces are stabilized.12. Erosion and siltation controls shall be appropriate to the size and nature of the project and to the physical characteristicsof thesite, including slope, soil type, vegetative cover, and proximity to wetlands or surface waters.13. No person undertaking any activity in the protected shoreland shall cause or contribute to, or allow the activity to cause orcontribute to, any violations of the surface water quality standards established in Env-Wq 1700.14. Any fill used shall be clean sand, gravel, rock, or other suitable material.15. The proposed stormwater management structures shall be installed and maintained to effectively absorb and infiltratestormwater.16. All pervious technologies used shall be installed and maintained to effectively absorb and infiltrate stormwater.17. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tack or netting and pinning on slopes steeper than 3:1.18. The individual responsible for completion of the work shall utilize techniques described in the New Hampshire StotmwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).19. This permit shall not be interpreted as acceptance or approval of any impact that will occur within wetlands jurisdictionregulated under RSA 482-A including all wetlands, surface waters and their banks, the tidal-buffer zone, and sand dunes.The owner is responsible for maintaining compliance with RSA 482-A and Administrative Rules Env-Wt 100-900 andobtaining any Wetland Impact Permit that may be required prior to construction, excavation or fill that will occur withinWetlands jurisdiction.20. This permit shall not preclude NHDES from taking any enforcement or revocation action if NHDES later determines thatany of the structures depicted as “existing” on the plans submitted by the applicant were not previously permitted orgrandfathered.

With Findings:1. Correspondence was received from NH Fish and Game indicating that no impacts to wood turtles or nesting or broodingloons are expected as a result of this project. It was recommended that pruning and removal of vegetation be minimized andthat restoration plantings be incorporated.

2017-00838 WALSH, DANIELIDEBORAH

MEREDITH WINNISQUAM LAKE

Requested Action:

Impact 7,700 square feet of protected shoreland in order to remove the existing residential structure and construct a newlarger structure, expand the existing driveway and convert to a pervious driveway, install a walkway between the drivewayand residence, install a new septic system, install a stormwater management system, and plant vegetation in the waterfrontbuffer.

AMENDMENT DESCRIPTION: Plans revised in order to expand permeable driveway and reconfigure walkway.

Decision Report 42 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

APPROVE AMENDMENTImpact 7,700 square feet of protected shoreland in order to remove the existing residential structure and construct a newlarger structure, expand the existing driveway and convert to a pervious driveway, install a walkway between the drivewayand residence, install a new septic system, install a stormwater management system, and plant vegetation in the waterfrontbuffer.

AMENDMENT DESCRIPTION: Plans revised in order to expand permeable driveway and reconfigure walkway.

With Conditions:1. All work shall be in accordance with plans by Ames Associates dated as revised through January 5, 2018 and received bythe NH Department of Environmental Services (NHDES) on January 12, 2018.2. Neither the new primary structure nor the proposed septic system may be constructed until the system is approved by theNHDES Subsurface Systems Bureau.3. Orange construction fencing shall be installed at the limits of the temporary impact area as shown on the approved plansprior to the start of work and shall be maintained throughout the project in order to prevent accidental encroachment intoareas in which impacts have not been approved.4. No more than 20% of the area of the lot within the protected shoreland shall be covered by impervious surfaces unlessadditional approval is obtained from NHDES.5. Native vegetation within an area of at least 1,620 sq. ft. within the Natural Woodland Buffer located between 50 and 150 ft.landward of the reference line shall be retained in an unaltered state in order to comply with RSA 483-B:9, V, (b), (2).6. All planting as shown on the approved plans shall be completed prior to the occupancy of the residential structure.7. The plantings shall be inspected at the beginning and end of the growing season for a period of 3 years after initialplantings have been completed during which time any failed plantings shall immediately be replaced by the owner of theproperty.8. At the completion of the 3 year monitoring period the Owner of the property shall submit a report including photographs ofthe planted buffer to the Department.9. Erosion and siltation control measures shall be installed prior to the start of work, be maintained throughout the project,and remain in place until all disturbed surfaces are stabilized.10. Erosion and siltation controls shall be appropriate to the size and nature of the project and to the physical characteristicsof the site, including slope, soil type, vegetative cover, and proximity to wetlands or surface waters.11. No person undertaking any activity in the protected shoreland shall cause or contribute to, or allow the activity to cause orcontribute to, any violations of the surface water quality standards established in Env-Wq 1700.12. Any fill used shall be clean sand, gravel, rock, or other suitable material.13. The proposed drywells for gutter outlets shall be installed and maintained to effectively absorb and infiltrate stormwater.14. Photographs documenting the construction of the proposed drywells for gutter outlets shall be submitted to theDepartment prior to any party taking up occupancy of the new residential primary structure.15. The proposed permeable payers and porous asphalt drive shall be installed and maintained to effectively absorb andinfiltrate stormwater.16. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tack or netting and pinning on slopes steeper than 3:1.17. The individual responsible for completion of the work shall utilize techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).18. This permit shall not be interpreted as acceptance or approval of any impact that will occur within wetlands jurisdictionregulated under RSA 482-A including all wetlands, surface waters and their banks, the tidal-buffer zone, and sand dunes.The owner is responsible for maintaining compliance with RSA 482-A and Administrative Rules Env-Wt 100-900 andobtaining any Wetland Impact Permit that may be requited prior to construction, excavation or fill that will occur withinWetlands jurisdiction.19. This permit shall not preclude NHDES from taking any enforcement or revocation action if NHDES later determines thatany of the structures depicted as “existing” on the plans submitted by the applicant were not previously permitted orgrandfathered.

201 7-01182 MCWHIRTER, DONALD

Decision Report 43 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

TUFTONBORO LAKE WINNIPESAUKEE

Requested Action:

Impact 15,056 square feet of protected shoreland in order to replace existing house and garage, reconfigure driveway, andinstall septic system.

APPROVE PERMITImpact 15,056 square feet of protected shoreland in order to replace existing house and garage, reconfigure driveway, andinstall septic system.

With Conditions:1. All work shall be in accordance with plans by Fernstone Associates for the Natural Resources dated as revised throughJanuary 6, 2018 and received by the NH Department of Environmental Services (NHDES) on January 6, 2018.2. This permit does not authorize any work outside of the protected shoreland including any alteration to the location ofaccess to the property.3. Neither the new primary structure nor the proposed septic system may be constructed until the system is approved by theNHDES Subsurface Systems Bureau.4. Orange construction fencing shall be installed at the limits of the temporary impact area as shown on the approved plansprior to the start of work and shall be maintained throughout the project in order to prevent accidental encroachment intoareas in which impacts have not been approved.5. No more than 19.3% of the area of the lot within the protected shoreland shall be covered by impervious surfaces unlessadditional approval is obtained from NHDES.6. Native vegetation within an area of at least 2,935 sq. ft. within the Natural Woodland Buffer located between 50 and 150 ft.landward of the reference line shall be retained in an unaltered state in order to comply with RSA 483-B:9, V, (b), (2).7. Erosion and siltation control measures shall be installed prior to the start of work, be maintained throughout the project,and remain in place until all disturbed surfaces are stabilized.8. Erosion and siltation controls shall be appropriate to the size and nature of the project and to the physical characteristics ofthe site, including slope, soil type, vegetative cover, and proximity to wetlands or surface waters.9. No person undertaking any activity in the protected shoreland shall cause or contribute to, or allow the activity to cause orcontribute to, any violations of the surface water quality standards established in Env-Wq 1700.10. Any fill used shall be clean sand, gravel, rock, or other suitable material.11. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tack or netting and pinning on slopes steeper than 3:1.12. The individual responsible for completion of the work shall utilize techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).13. This permit shall not be interpreted as acceptance or approval of any impact that will occur within wetlands jurisdictionregulated under RSA 482-A including all wetlands, surface waters and their banks, the tidal-buffer zone, and sand dunes.The owner is responsible for maintaining compliance with RSA 482-A and Administrative Rules Env-Wt 100 - 900 andobtaining any Wetland Impact Permit that may be required prior to construction, excavation or fill that will occur withinWetlands jurisdiction.14. This permit shall not preclude NHDES from taking any enforcement or revocation action if NHDES later determines thatany of the structures depicted as “existing” on the plans submitted by the applicant were not previously permitted orgrandfathered.

2017-03152 HOEY, LAURIEIPETER

TILTON SILVER LAKE

Requested Action:

Decision Report 44 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

Impact 3,819 square feet of protected shoreland in order to replace the existing primary structure, located within the primarybuilding setback, with a larger primary structure to be located 5 feet 3 inches further back from the reference line.

AMENDMENT DESCRIPTION: Plans revised in order to add the installation of a utility pole and trench for undergroundutilities.

APPROVE AMENDMENTImpact 3,819 square feet of protected shoreland in order to replace the existing primary structure, located within the primarybuilding setback, with a larger primary structure to be located 5 feet 3 inches further back from the reference line.

AMENDMENT DESCRIPTION: Plans revised in order to add the installation of a utility pole and trench for undergroundutilities.

With Conditions:1. All work shall be in accordance with plans by Bryan L. Bailey Associates, Inc. dated as revised through January 10, 2018and received by the NH Department of Environmental Services (NHDES) on January 12, 2018.2. Orange construction fencing shall be installed at the limits of the temporary impact area as shown on the approved plansprior to the start of work and shall be maintained throughout the project in order to prevent accidental encroachment intoareas in which impacts have not been approved.3. The proposed structure shall not be constructed until any approval as may be required under RSA 485-A and RulesEnv-Wq 1000 is obtained from NHDES Subsurface Systems Bureau.4. No more than 1 8.7% of the area of the lot within the protected shoreland shall be covered by impervious surfaces unlessadditional approval is obtained from NHDES.5. Nonative vegetation shall be removed from within the Natural Woodland Buffer located between 50 and 150 ft. landwardof the reference line in order to comply with RSA 483-B:9, V, (b), (2).6. This permit does not authorize the removal of any trees or saplings from areas within the waterfront buffer.7. This permit does not authorize the removal of any natural ground cover from areas within the waterfront buffer.8. Erosion and siltation control measures shall be installed prior to the start of work, be maintained throughout the project,and remain in place until all disturbed surfaces are stabilized.9. Erosion and siltation controls shall be appropriate to the size and nature of the project and to the physical characteristics ofthe site, including slope, soil type, vegetative cover, and proximity to wetlands or surface waters.10. No person undertaking any activity in the protected shoreland shall cause or contribute to, or allow the activity to cause orcontribute to, any violations of the surface water quality standards established in Env-Wq 1700.11. Any fill used shall be clean sand, gravel, rock, or other suitable material.12. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tack or netting and pinning on slopes steeper than 3:1.13. The individual responsible for completion of the work shall utilize techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).14. This permit shall not be interpreted as acceptance or approval of any impact that will occur within wetlands jurisdictionregulated under RSA 482-A including all wetlands, surface waters and their banks, the tidal-buffer zone, and sand dunes.The owner is responsible for maintaining compliance with RSA 482-A and Administrative Rules Env-Wt 100 - 900 andobtaining any Wetland Impact Permit that may be required prior to construction, excavation or fill that will occur withinWetlands jurisdiction.15. This permit shall not preclude NHDES from taking any enforcement or revocation action if NHDES later determines thatany of the structures depicted as “existing” on the plans submitted by the applicant were not previously permitted orgrandfathered.

201 7-03226 BARKIE, DAVID

WASHINGTON HIGHLAND LAKE

Decision Report 45 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

Requested Action:

Impact 5,480 square feet of protected shoreland in order to construct a residential structure, driveway, and septic system.

Conservation Commission/Staff Comments:The porch being converted to living space is a finished porch and therefore does not require a more nearly conformingrequest or review as a shoreland application - SAD

APPROVE PERMITImpact 5,480 square feet of protected shoreland in order to construct a residential structure, driveway, and septic system.

With Conditions:1. All work shall be in accordance with plans by A.C. Engineering and Consulting dated as revised through January 12, 2018and received by the NH Department of Environmental Services (NHDES) on January 17, 2018.2. Neither the new primary structure nor the proposed septic system may be constructed until the system is approved by theNHDES Subsurface Systems Bureau.3. Orange construction fencing shall be installed at the limits of the temporary impact area as shown on the approved plansprior to the start of work and shall be maintained throughout the project in order to prevent accidental encroachment intoareas in which impacts have not been approved.4. No more than 11.2% of the area of the lot within the protected shoreland shall be covered by impervious surfaces unlessadditional approval is obtained from NHDES.5. Native vegetation within an area of at least 1,619 sq. ft. within the Natural Woodland Buffer located between 50 and 150 ft.landward of the reference line shall be retained in an unaltered state in order to comply with RSA 483-B:9, V, (b), (2).6. Cleared areas within the waterfront buffer legally developed prior to July 1, 2008 may be maintained but not enlarged.7. Erosion and siltation control measures shall be installed prior to the start of work, be maintained throughout the project,and remain in place until all disturbed surfaces ate stabilized.8. Erosion and siltation controls shall be appropriate to the size and nature of the project and to the physical characteristics ofthe site, including slope, soil type, vegetative cover, and proximity to wetlands or surface waters.9. No person undertaking any activity in the protected shoreland shall cause or contribute to, or allow the activity to cause orcontribute to, any violations of the surface water quality standards established in Env-Wq 1700.10. Any fill used shall be clean sand, gravel, rock, or other suitable material.11. Within three days of final grading or temporary. suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tack or netting and pinning on slopes steeper than 3:1.12. The individual responsible for completion of the work shall utilize techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).13. This permit shall not be interpreted as acceptance or approval of any impact that will occur within wetlands jurisdictionregulated under RSA 482-A including all wetlands, surface waters and their banks, the tidal-buffer zone, and sand dunes.The owner is responsible for maintaining compliance with RSA 482-A and Administrative Rules Env-Wt 100 - 900 andobtaining any Wetland Impact Permit that may be required prior to construction, excavation or fill that will occur withinWetlands jurisdiction.14. This permit shall not preclude NHDES from taking any enforcement or revocation action if NHDES later determines thatany of the structures depicted as ‘existing” on the plans submitted by the applicant were not previously permitted orgrandfathered.

2017-03602 MORENA, RICHARDITONI

TUFTONBORO LAKE WINNIPESAUKEE

Decision Report 46 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

Requested Action:

Impact 5,464 square feet of protected shoreland in order to construct an addition to the primary structure, storm watermanagement features, and replace the leach bed.

APPROVE PERMITImpact 5,464 square feet of protected shoreland in order to construct an addition to the primary structure, storm watermanagement features, and replace the leach bed.

With Conditions:1. All work shall be in accordance with plans by Varney Engineering, LLC dated as revised through January 16, 2018 andreceived by the NH Department of Environmental Services (NHDES) on January 19, 2018.2. Neither the new primary structure addition nor the proposed septic system components may be constructed until thesystem is approved by the NHDES Subsurface Systems Bureau.3. This permit shall not be interpreted as acceptance or approval of any impact that will occur within wetlands jurisdictionregulated under RSA 482-A including any work to the bank for access to the site, wetlands, and surface waters. The owneris responsible for maintaining compliance with RSA 482-A and Administrative Rules Env-Wt 100-900 and obtaining anyWetland Impact Permit that may be required prior to construction, excavation or fill that will occur within Wetlands jurisdiction.4. Orange construction fencing shall be installed at the limits of the temporary impact area as shown on the approved plansprior to the start of work and shall be maintained throughout the project in order to prevent accidental encroachment intoareas in which impacts have not been approved.5. No more than 3% of the area of the lot within the protected shoreland shall be covered by impervious surfaces unlessadditional approval is obtained from NHDES.6. Native vegetation within an area of at least 5,702 sq. ft. within the Natural Woodland Buffer located between 50 and 150 ft.landward of the reference line shall be retained in an unaltered state in order to comply with RSA 483-B:9, V, (b), (2).7. Erosion and siltation control measures shall be installed prior to the start of work, be maintained throughout the project,and remain in place until all disturbed surfaces are stabilized.8. Erosion and siltation controls shall be appropriate to the size and nature of the project and to the physical characteristics ofthe site, including slope, soil type, vegetative cover, and proximity to wetlands or surface waters.9, No person undertaking any activity in the protected shoreland shall cause or contribute to, or allow the activity to cause orcontribute to, any violations of the surface water quality standards established in Env-Wq 1700.10. Any fill used shall be clean sand, gravel, rock, or other suitable material.11. The proposed stormwater management structures shall be installed and maintained to effectively absorb and infiltratestormwater.12. Photographs documenting the construction of the proposed stormwater management structures shall be submitted to theDepartment prior to any party taking up occupancy of the new residential primary structure.13. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tack or netting and pinning on slopes steeper than 3:1.14. The individual responsible for completion of the work shall utilize techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).15. This permit shall not preclude NHDES from taking any enforcement or revocation action if NHDES later determines thatany of the structures depicted as ‘existing’ on the plans submitted by the applicant were not previously permitted or

grandfathered.

2017-03668 WILSON, DAVIDIDIANE

PELHAM GUMPAS POND

Requested Action:

Impact 7,194 square feet (SF) of protected shoreland in order to construct a new primary structure on an existing lot ofrecord. The new house will be serviced by an onsite well and septic system that will partially impact the shoreland zone.

Decision Report 47 2/6/2018For Actions Taken 01/22/2018 to 01/28/2018

APPROVE PERMITImpact 7194 square feet (SF) of protected shoreland in order to construct a new primary structure on an existing lot ofrecord. The new house will be serviced by an onsite well and septic system that will partially impact the shoreland zone.

With Conditions:1. All work shall be in accordance with plans by Meridian Land Services, Inc. dated December 5, 2017 and received by theNH Department of Environmental Services (DES) on December 26, 2017.2. Neither the new primary structure nor the proposed septic system may be constructed until the system is approved by theDES Subsurface Systems Bureau.3. Orange construction fencing shall be installed at the limits of the temporary impact area as shown on the approved plansprior to the start of work and shall be maintained throughout the project in order to prevent accidental encroachment intoareas in which impacts have not been approved.4. No more than 27% of the area of the lot within the protected shoreland shall be covered by impervious surfaces unlessadditional approval is obtained from DES.5. Erosion and siltation control measures shall be installed prior to the start of work, be maintained throughout the project,and remain in place until all disturbed surfaces are stabilized.6. Erosion and siltation controls shall be appropriate to the size and nature of the project and to the physical characteristicsof the site, including slope, soil type, vegetative cover, and proximity to wetlands or surface waters.7. No person undertaking any activity in the protected shoreland shall cause or contribute to, or allow the activity to cause orcontribute to, any violations of the surface water quality standards established in Env-Wq 1700.8. Any fill used shall be clean sand, gravel, rock, or other suitable material.9. The proposed (stormwater management structures) shall be installed and maintained to effectively absorb and infiltratestormwater.10. Photographs documenting the construction of the proposed (stormwater management structures) shall be submitted tothe Department prior to any party taking up occupancy of the new residential primary structure.11. The individual responsible for completion of the work shall utilize techniques described in the New HampshireStormwater Manual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).12. This permit shall not preclude DES from taking any enforcement or revocation action if DES later determines that any ofthe structures depicted as “existing on the plans submitted by the applicant were not previously permitted or grandfathered.

2017-03690 WINNISQUAM BEACH CAMPGROUND

BELMONT WINNISQUAM LAKE

Requested Action:

Impact 1,590 square feet (SF) of protected shoreland in order to replace existing primary structure with a new structure,replace patio and driveway with a pervious payers, and reconstruct the the existing landing and screen porch within the samefootprint.

APPROVE PERMITImpact 1,590 square feet (SF) of protected shoreland in order to replace existing primary structure with a new structure,replace patio and driveway with a pervious payers, and reconstruct the the existing landing and screen porch within the samefootprint.

With Conditions:1. All work shall be in accordance with plans by Terrain Planning and Design LLC dated December 13, 2017 and received bythe NH Department of Environmental Services (DES) on December 28, 2017.2. Orange construction fencing shall be installed at the limits of the temporary impact area as shown on the approved plans

Decision Report 48 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

prior to the start of work and shall be maintained throughout the project in order to prevent accidental encroachment intoareas in which impacts have not been approved.3. No more than 27.4% of the area of the lot within the protected shoreland shall be covered by impervious surfaces unlessadditional approval is obtained from DES.4. Erosion and siltation control measures shall be installed prior to the start of work, be maintained throughout the project,and remain in place until all disturbed surfaces are stabilized.5. Erosion and siltation controls shall be appropriate to the size and nature of the project and to the physical characteristicsof the site, including slope, soil type, vegetative cover, and proximity to wetlands or surface waters.6. No person undertaking any activity in the protected shoreland shall cause or contribute to, or allow the activity to cause orcontribute to, any violations of the surface water quality standards established in Env-Wq 1700.7. Any fill used shall be clean sand, gravel, rock, or other suitable material.8. All pervious technologies used shall be installed and maintained to effectively absorb and infiltrate stormwater.9. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tack or netting and pinning on slopes steeper than 3:1.10. The individual responsible for completion of the work shall utilize techniques described in the New HampshireStormwater Manual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).11. This permit shall not preclude DES from taking any enforcement or revocation action if DES later determines that any ofthe structures depicted as “existing” on the plans submitted by the applicant were not previously permitted or grandfathered.

2017-03700 SCHUSSEL, GEORGEISANDRA

MEREDITH LAKE WINNIPESAUKEE

Requested Action:

Impact 2,405 square feet (SF) of protected shoreland in order to create walkway and retaining wall toward the reference lineand along a portion of the driveway. Project includes mulching and replanting along impacted area where possible.

APPROVE PERMITImpact 2405 square feet (SF) of protected shoreland in order to create walkway and retaining wall toward the reference lineand along a portion of the driveway. Project includes mulching and replanting along impacted area where possible.

With Conditions:1. All work shall be in accordance with plans by Stephens Landscaping Professionals, LLC dated December 26, 2017 andreceived by the NH Department of Environmental Services (DES) on December 29, 2017.2. Orange construction fencing shall be installed at the limits of the temporary impact area as shown on the approved plansprior to the start of work and shall be maintained throughout the project in order to prevent accidental encroachment intoareas in which impacts have not been approved.3. No more than 10% of the area of the lot within the protected shoreland shall be covered by impervious surfaces unlessadditional approval is obtained from DES.4. Native vegetation within an area of at least 54,315 SF within the Natural Woodland Buffer located between 50 and 150feet Iandward of the reference line shall be retained in an unaltered state in order to comply with RSA 483-B:9, V, (b), (2).5. Erosion and siltation control measures shall be installed prior to the start of work, be maintained throughout the project,and remain in place until all disturbed surfaces are stabilized.6. Erosion and siltation controls shall be appropriate to the size and nature of the project and to the physical characteristicsof the site, including slope, soil type, vegetative cover, and proximity to wetlands or surface waters.7. No person undertaking any activity in the protected shoreland shall cause or contribute to, or allow the activity to cause orcontribute to, any violations of the surface water quality standards established in Env-Wq 1700.8. Any fill used shall be clean sand, gravel, rock, or other suitable material.9. The individual responsible for completion of the work shall utilize techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).10. This permit shall not be interpreted as acceptance or approval of any impact that will occur within wetlands jurisdictionregulated under RSA 482-A including all wetlands, surface waters and their banks. The owner is responsible for maintainingcompliance with RSA 482-A and Administrative Rules Env-Wt 100 - 900 and obtaining any Wetland Impact Permit that may

Decision Report 49 2/6/2018

For Actions Taken 01/22/2018 to 01/28/2018

be required prior to construction, excavation or fill that will occur within Wetlands jurisdiction.11. This permit shall not preclude DES from taking any enforcement or revocation action if DES later determines that any ofthe structures depicted as “existing” on the plans submitted by the applicant were not previously permitted or grandfathered.

201 8-00001 CONNOR, KELLEY/TERRANCE

NOTTINGHAM PAWTUCKAWAY POND

Requested Action:

Impact 7,180 square feet of protected shoreland in order to construct a residential structure, driveway, and septic system.

APPROVE PERMITImpact 7,180 square feet of protected shoreland in order to construct a residential structure, driveway, and septic system.

With Conditions:1. All work shall be in accordance with plans by Blaisdell Survey LLC dated December 10, 2017 and received by the NHDepartment of Environmental Services (NHDES) on January 3, 2018.2. Neither the new primary structure nor the proposed septic system may be constructed until the system is approved by theNHDES Subsurface Systems Bureau.3. Orange construction fencing shall be installed at the limits of the temporary impact area as shown on the approved plansprior to the start of work and shall be maintained throughout the project in order to prevent accidental encroachment intoareas in which impacts have not been approved.4. No more than 16% of the area of the lot within the protected shoreland shall be covered by impervious surfaces unlessadditional approval is obtained from NHDES.5. Native vegetation within an area of at least 708 sq. ft. within the Natural Woodland Buffer located between 50 and 150 ft.landward of the reference line shall be retained in an unaltered state in order to comply with RSA 483-B:9, V, (b), (2).6. Erosion and siltation control measures shall be installed prior to the start of work, be maintained throughout the project,and remain in place until all disturbed surfaces are stabilized.7. Erosion and siltation controls shall be appropriate to the size and nature of the project and to the physical characteristics ofthe site, including slope, soil type, vegetative cover, and proximity to wetlands or surface waters.8. No person undertaking any activity in the protected shoreland shall cause or contribute to, or allow the activity to cause orcontribute to, any violations of the surface water quality standards established in Env-Wq 1700.9. Any fill used shall be clean sand, gravel, rock, or other suitable material.10. Within three days of final grading or temporary suspension of work in an area that is in or adjacent to wetlands or surfacewaters, all exposed soil areas shall be stabilized by seeding and mulching during the growing season, or if not within thegrowing season, by mulching with tack or netting and pinning on slopes steeper than 3:1.11. The individual responsible for completion of the work shall utilize techniques described in the New Hampshire StormwaterManual, Volume 3, Erosion and Sediment Controls During Construction (December 2008).12. This permit shall not be interpreted as acceptance or approval of any impact that will occur within wetlands jurisdictionregulated under RSA 482-A including all wetlands, surface waters and their banks, the tidal-buffer zone, and sand dunes.The owner is responsible for maintaining compliance with RSA 482-A and Administrative Rules Env-Wt 100-900 andobtaining any Wetland Impact Permit that may be required prior to construction, excavation or fill that will occur withinWetlands jurisdiction.13. This permit shall not preclude NHDES from taking any enforcement or revocation action if NHDES later determines thatany of the structures depicted as “existing” on the plans submitted by the applicant were not previously permitted orgrandfathered.


Recommended