+ All Categories
Home > Documents > July 17, 2006 - Burlington · Concrete Shorewall The primary concrete shorewall has a recurved...

July 17, 2006 - Burlington · Concrete Shorewall The primary concrete shorewall has a recurved...

Date post: 19-Oct-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
28
W.F. Baird & Associates Coastal Engineers Ltd. www.baird.com Baird oceans engineering lakes design rivers science watersheds construction Baird & Associates 1267 Cornwall Road, Suite 100 Oakville, Ontario Canada L6J 7T5 T. 905 845 5385 F. 905 845 0698 December 18, 2015 Mr. Ron Thomson 39 Pennsylvania Ave. Unit 1 Concord, ON L4K 4A5 By email: Ron Thomson <[email protected]> Dear Ron: Re: Natural Hazard Assessment and Shoreline Engineering, 105 Avondale Court, Burlington W.F. Baird & Associates Coastal Engineers Ltd. (Baird) was retained by Ron Thomson (Owner) to review the existing shoreline conditions and assess the shoreline setback for the proposed redevelopment at 105 Avondale Court, Burlington. The Owner proposes to demolish the existing dwelling, merge some of the adjacent lots, and construct a multi-unit residential development. This assessment was prepared by Baird for Ron Thomson. The material in it reflects the judgment of Baird in light of the information available to them at the time of preparation. Any uses which a Third Party makes of this report, or any reliance on decisions to be made based on it, are the responsibility of such Third Parties. Baird accepts no responsibility for damages, if any, suffered by any Third Party as a result of decisions made or actions based on this report. 1. Site Conditions Visual reconnaissance investigations of the shoreline were undertaken on August 4, 2015 and November 25, 2015. Select photographs from these reconnaissance visits have been referenced in this letter and are provided at the end of the letter. During the first reconnaissance visit a small Unmanned Aerial Vehicle (UAV) with a wide angle lens camera was flown above the shoreline of the property and captured photos at altitudes of 10-50 metres. Oblique views of the shoreline are provided in Photographs 1, 2 and 3, showing the central portion, west flank and east end respectively. The lake level recorded by the Canadian Hydrographic Services (CHS) gauge in Burlington at the time of the reconnaissance investigations were 75.17 m IGLD’85 on August 4, 2015, and 74.58 m IGLD’85 on November 25, 2015. There is no shift between IGLD’85 and the Canadian Geodetic Vertical Datum 1928 (CGVD’28) at the Burlington gauge. All elevations in this report are referenced to CGVD’28, unless otherwise noted. A topographic survey of the shoreline from June 2011 (Asenhurst Neouwens Limited Plan No. 11112, June 10, 2011) was used as the base mapping for the plans in Attachment A. Additional topographic details of the shorewall, obtained in a follow-up survey, were also incorporated into the plans. A slope stability assessment was prepared by Terraprobe Inc. on November 4, 2015 (Terraprobe, 2015 File No. 71-15-5064), and provided to Baird by the Owner. Geotechnical information from this assessment was used to determine the stable slope allowance of the erosion hazard limit.
Transcript
  • W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    o c e a n s

    e n g i n e e r i n g

    l a k e s

    d e s i g n

    r i v e r s

    s c i e n c e

    w a t e r s h e d s

    c o n s t r u c t i o n

    B a i r d & A s s o c i a t e s

    1267 Cornwall Road, Suite 100

    Oakville, Ontario Canada L6J 7T5

    T . 9 0 5 8 4 5 5 3 8 5

    F . 9 0 5 8 4 5 0 6 9 8

    December 18, 2015

    Mr. Ron Thomson

    39 Pennsylvania Ave. Unit 1

    Concord, ON L4K 4A5

    By email: Ron Thomson

    Dear Ron:

    Re: Natural Hazard Assessment and Shoreline Engineering, 105 Avondale Court, Burlington

    W.F. Baird & Associates Coastal Engineers Ltd. (Baird) was retained by Ron Thomson (Owner) to

    review the existing shoreline conditions and assess the shoreline setback for the proposed

    redevelopment at 105 Avondale Court, Burlington. The Owner proposes to demolish the existing

    dwelling, merge some of the adjacent lots, and construct a multi-unit residential development.

    This assessment was prepared by Baird for Ron Thomson. The material in it reflects the judgment of

    Baird in light of the information available to them at the time of preparation. Any uses which a Third

    Party makes of this report, or any reliance on decisions to be made based on it, are the responsibility of

    such Third Parties. Baird accepts no responsibility for damages, if any, suffered by any Third Party as a

    result of decisions made or actions based on this report.

    1. Site Conditions

    Visual reconnaissance investigations of the shoreline were undertaken on August 4, 2015 and

    November 25, 2015. Select photographs from these reconnaissance visits have been referenced in this

    letter and are provided at the end of the letter. During the first reconnaissance visit a small Unmanned

    Aerial Vehicle (UAV) with a wide angle lens camera was flown above the shoreline of the property and

    captured photos at altitudes of 10-50 metres. Oblique views of the shoreline are provided in

    Photographs 1, 2 and 3, showing the central portion, west flank and east end respectively.

    The lake level recorded by the Canadian Hydrographic Services (CHS) gauge in Burlington at the time

    of the reconnaissance investigations were 75.17 m IGLD’85 on August 4, 2015, and 74.58 m IGLD’85

    on November 25, 2015. There is no shift between IGLD’85 and the Canadian Geodetic Vertical Datum

    1928 (CGVD’28) at the Burlington gauge. All elevations in this report are referenced to CGVD’28,

    unless otherwise noted.

    A topographic survey of the shoreline from June 2011 (Asenhurst Neouwens Limited Plan No. 11112,

    June 10, 2011) was used as the base mapping for the plans in Attachment A. Additional topographic

    details of the shorewall, obtained in a follow-up survey, were also incorporated into the plans.

    A slope stability assessment was prepared by Terraprobe Inc. on November 4, 2015 (Terraprobe, 2015

    – File No. 71-15-5064), and provided to Baird by the Owner. Geotechnical information from this

    assessment was used to determine the stable slope allowance of the erosion hazard limit.

  • R. Thomson

    December 18, 2015

    Page 2 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    It is not know if an arborist has reviewed the site and assessed if parts of the site fall under the

    significant woodland designation. This should be reviewed by your planner.

    The Lake Ontario shoreline frontage is approximately 120 m and can be considered as three different

    sections based on the existing shore protection, orientation (exposure) and backshore conditions. The

    shoreline sections are as follows:

    A 95 m long concrete shorewall with armour stone along the toe provides the primary

    protection for the southerly side of the site fully exposed to Lake Ontario. Oblique aerial and

    ground-level views of this wall are provided in Photograph 1, Photograph 4, and Photograph 5.

    An 8 m long (alongshore dimension) shingle/cobble beach is located at the east end of the

    property. The beach is backed by a low timber retaining wall. Oblique and ground-level views

    of the beach and timber wall are provided in Photograph 7 and Photograph 8, respectively.

    The 18 m long western flank of the property is protected by a combination of a 7 m long

    section of the concrete shorewall (continuation of the primary shorewall) and a low stacked

    armour stone wall (see Photograph 2 and in foreground of Photograph 9). Beyond the property

    line, along the western flank, the adjacent property is protected by a higher stacked armour

    stone shorewall (in background Photograph 9).

    The top elevation of the bluff varies from approximately 84 m at the west side of the site to 77.5 m at

    the east side of the site. The bluff face is heavily vegetated with several large trees located immediately

    behind the concrete shorewall at both the west and east ends.

    Exposed bedrock and covering patches of cobbles and shingles are clearly visible in the nearshore all

    along the shore in front of the shorewall (example Photograph 10).

    A small drainage course is located at the easterly limit. The outlet of the drainage course is adjacent to

    the shingle beach (Photograph 11).

    Concrete Shorewall

    The primary concrete shorewall has a recurved front face and a cap elevation of approximately 76.40 to

    76.45 m. The construction date of the concrete shorewall is not known, but it appears to be several

    decades old. The backshore area immediately behind the wall is about 0.5 m lower than the crest of the

    wall and about 1.5-2 m wide to the toe of the bluff slope. This area has miscellaneous stone material,

    debris and vegetation (Photograph 12). There does not appear to be any formal splash pad behind the

    wall.

    The water depth at the wall on November 25, 2015 varied but was approximately 0.5 m.

    Armour stones and mass poured concrete have been placed at the toe of the concrete shorewall along its

    entire length (Photograph 5 and Photograph 6). In places there is a double row of armour stone and

  • R. Thomson

    December 18, 2015

    Page 3 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    additional mass poured concrete (Photograph 13). Some steel reinforcing bars were observed in the

    poured concrete. The height of the double row of armour stone varies, but is about 1.7 m above the

    lakebed. It appears that the armour stone and poured concrete was placed sometime after the original

    shorewall construction.

    The concrete shorewall is in fair condition. It appears to be upright and in good alignment (Photograph

    14). Several cracks (e.g., Photograph 15) and areas of moderate spalling (Photograph 16) are present

    and evidence of previous concrete repairs was observed (Photograph 17). The armour stones along the

    toe appear to be generally in place and functional as protection. The poured concrete at the toe remains

    generally intact, but is showing some deterioration and cracking (Photograph 18). The toe concrete will

    continue to deteriorate over time.

    We estimate that the combined concrete shorewall with armour stone toe protection has a residual

    design life of approximately 20 years. Cracks and spalling in the shorewall should be repaired. A

    splash pad should be added behind the crest of the wall. The pad would be about 1.5 – 2 m wide and

    consist of heavy stone rip rap over a geotextile.

    Shingle/Cobble Beach

    The shingle/cobble beach was about 8 m wide from the water line (November 25, 2015) to the timber

    retaining wall. The timber wall was about 0.7 m high. The west side of the beach is flanked by stacked

    armour stone and a large concrete pad (Photograph 7). The size of the shingle/cobble material can be

    seen in Photograph 19.

    The shingle/cobble beach should be preserved. The timber wall has little residual design life remaining

    (less than 5 years) and should be replaced with a stacked armour stone wall at the back of the beach that

    ties into the stone and concrete on the west side of the beach.

    Western Flank

    The stacked armour stone wall along the western flank of the subject property is too low and is readily

    overtopped by wave action. Rip rap stone has been placed behind the wall to mitigate the effects of the

    overtopping but it is insufficient. Signs of bluff erosion above the wall were observed during the site

    reconnaissance (refer to Photograph 20).

    The low stacked armour stone shorewall in its present condition is inadequate to provide erosion

    protection and would have to be rebuilt to a higher crest elevation.

    Adjacent Shorelines

    The shoreline of the adjacent property to the west is protected by a stacked armour stone wall (about

    15 m long at west flank) and stacked concrete blocks (Photograph 21). To the east, the adjacent

    property is protected by a combination of armour stone and concrete blocks (Photograph 22).

  • R. Thomson

    December 18, 2015

    Page 4 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    2. Natural Hazard Assessment and Development Setback

    This section provides a description of the policies and reports that were considered in assessing the

    natural hazards of the subject property, followed by the details of the assessment for each of the natural

    hazards.

    Conservation Halton

    Under Ontario Regulation 162/06 Conservation Halton (CH) regulates development of the shoreline

    within the shoreline hazard limit. Permission is required from CH to undertake development within the

    shoreline hazard limit. CH may grant permission for development in hazard areas “…if, in its opinion,

    the control of flooding, erosion, dynamic beaches, pollution or the conservation of land will not be

    affected by the development”. Conservation Halton’s development standards for the shoreline are based

    on their interpretation of the Provincial Policy Statement and supporting Technical Guidelines and are

    defined in the “Policies, Procedures and Guidelines for the Administration of Ontario Regulation

    162/06 and Land Use Planning Policy Document, 2006” prepared by CH.

    The shoreline development setback at the site is governed by the erosion hazard. The following

    paragraphs outline the erosion hazard requirements as presently established by Conservation Halton.

    The flooding and dynamic beach hazards, which do not govern at this site, are summarized in

    subsequent paragraphs.

    Erosion Hazard

    The Lake Ontario erosion hazard limit is determined by the sum of the erosion hazard allowance,

    considering the long-term recession of unprotected shoreline, and the stable slope allowance. With

    shoreline protection, the Engineered Development Setback (EDS) can be determined in accordance

    with CH policies. In summary, the key requirements of CH with respect to the EDS are as follows:

    Development planning horizon: 100 years

    Average annual shoreline erosion rate: 0.30 m/yr

    Maximum design life for shoreline protection with maintenance access: 35 years

    Minimum erosion allowance: 20 metres

    Stable slope allowance: 3:1 (or determined by geotechnical study)

    Minimum width of maintenance access: 5 metres.

    The planning horizon for development is established by CH as 100 years. The average annual shoreline

    recession rate is defined by CH as 0.3 m/year. As such, using a 100-year planning horizon, the erosion

    allowance for unprotected shoreline is 30 m.

  • R. Thomson

    December 18, 2015

    Page 5 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    If shore protection exists, then the erosion allowance component of the EDS may be reduced,

    depending on the design life of the protection works. Structure design life is the length of time that a

    structure, with routine maintenance, is able to safely and adequately perform its function. Structure

    design life differs from the planning horizon of the project. Structures requiring replacement or

    significant rehabilitation have reached the end of their useful design life. The primary concrete

    shorewall shore protection at 105 Avondale is in fair condition. For the purpose of this report we have

    estimated the remaining design life of the existing shore protection structure, with some modest repairs,

    to be 20 years, resulting in an erosion allowance of 24 m [(100 yrs – 20 yrs) x 0.3 m/yr].

    The maximum design life of shoreline protection permitted by CH is 35 years, even for shoreline

    protection that is new, well engineered and well constructed. The design life of a structure can be

    extended beyond its original design life by rehabilitation or restoration provided sufficient funds and

    suitable construction access are available. Despite this, CH only permits a maximum design life of 35

    years. Therefore, for new shore protection the minimum erosion allowance permitted by CH is 20 m

    [i.e., (100 yrs - 35 yrs) x 0.3 m/yr].

    At the shingle/cobble beach at the east end, either the timber wall at the back of the beach can be

    replaced with a new stacked armour stone wall to achieve an erosion allowance of 20 m, or it can be left

    as is, requiring an erosion allowance of 30 m. It should be noted that the City may require upgrades to

    the timber wall, independent of the requirements of Conservation Halton.

    Along the western flank, the low stacked wall needs to be upgraded to provide an appropriate level of

    protection.

    The erosion allowance is measured from the estimated toe of the natural bluff. The toe of the natural

    bluff was estimated as elevation of 75.0 m CGVD.

    The erosion allowance components of the EDS at the site with existing shore protection (repaired as

    required for the concrete shorewall and no residual life for the western flank and eastern beach) and

    with all new shore protection are shown in Attachment A.

    The stable slope allowance is then added to the erosion allowance to determine the EDS. The stable

    slope allowance is defined by consideration of the geotechnical conditions at a site and the appropriate

    factors of safety. The stable slope assessment completed by Terraprobe indicates that the subsurface

    profile consists of four main layers:

    Top layer (1-2 m of loose silty sand fill);

    Upper middle layer (4-6 m compact to dense silty sand);

    Lower middle layer (1.0-1.5 m of very stiff clayey silt till);

    Bottom layer (weathered Queenston shale.

  • R. Thomson

    December 18, 2015

    Page 6 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Terraprobe determined the safe stable slope inclination is 1.8 horizontal: 1 vertical. The position of the

    stable slope allowance along the shoreline is provided in Attachment A.

    Maintenance Access

    CH policy requires a minimum 5 m wide unobstructed maintenance access to shore (from the road) and

    along the shoreline. This is to allow heavy machinery access to the shoreline for regular maintenance

    purposes and/or to repair the shore protection works should damage or failure occur. The maintenance

    access along the shore can be located within the erosion hazard allowance. Maintenance access to the

    shoreline would likely be along the east corridor adjacent to drainage course.

    Flood Hazard

    The flood hazard at the site is below the top of the existing bank and therefore does not govern at the

    site. The flood hazard is a result of the level of Lake Ontario and wave uprush onto the shore. Lake

    Ontario water levels fluctuate over the long-term, seasonally, and in the short-term. Long-term

    variations are mostly the result of climatic conditions (precipitation, evaporation); other factors, such as

    regulation also play a role. Over the past 100 years or so, the mean monthly lake level has varied over a

    range of approximately 2.0 m (from elevation 73.75 m to 75.75 m). The average seasonal variation is

    from about 74.5 m to 75.0 m. The fluctuation over any given year will vary. The water level typically

    peaks during June of each year. The lowest levels generally occur during December and January. The

    "stormy season" (when severe wave conditions and storm surge are more likely to occur) generally

    extends from October to April. From May to August the probability of severe storms occurring is

    reduced. Storm surge, also known as wind setup, is a short-term increase in the water level caused by

    the wind blowing across the water.

    The 100-year flood level is the combined mean lake level plus storm surge with a return period of 100

    years (i.e., on average there is 1% chance in any given year that the lake will reach that level). The 100-

    year flood level is 76.0 m CGVD. The flood level does not include the additional effects of wave

    uprush at the shoreline. The generic allowance for wave uprush is 15 m measured horizontally from the

    100-year flood level. On a bluff shoreline, the horizontal wave uprush offset will be less than 15 m.

    The elevation of the tablelands (approximately 84.0 m CGVD) is approximately 8 m above the 100-

    year flood level. The flood hazard at the site is therefore readily addressed by the height of the tableland

    above the 100-year flood level and does not govern the hazard setback. At the lower portion of the site,

    behind the cobble beach, the backshore elevation reaches up to about 77.5 m and is subject to the flood

    hazard. However, the generic 15 m wave uprush allowance is less than the minimum required 20 m

    erosion allowance, therefore the flood hazard does not govern the hazard setback.

  • R. Thomson

    December 18, 2015

    Page 7 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Dynamic Beach Hazard

    There is no dynamic beach, as defined by the policies, at the site. Therefore, there is no dynamic beach

    hazard.

    Drainage Course Hazard

    The drainage course hazard was established by Terraprobe and is shown on drawings in Attachment A.

    The setback includes:

    5 m toe erosion allowance

    Stable slope allowance

    7.5 m setback from top of stable top of slope.

    City of Burlington

    It is our understanding that the Owner is proposing to redevelop the property into multiple units. In

    cases such as this, the City of Burlington Land Use Policies may require additional setbacks. The City

    may require the shoreline protection for the newly acquired park to be new or like new condition, with a

    design life meeting the typical standards of Conservation Halton. For this particular redevelopment

    proposal, we recommend that you establish the requirements for the City of Burlington park dedication

    and rear yard setbacks directly with the City.

    Natural Hazard and Development Setback Summary

    The following summarizes the natural hazard and development setbacks that apply to 105 Avondale

    Court:

    The Engineered Development Setback (EDS) is defined by the erosion hazard and the stable

    slope allowance.

    Erosion Allowance (dependent on the design life of the shore protection):

    o 30 m without any shore protection or protection with no residual life

    o 24 m with the existing shore protection with repairs (assuming 20 year remaining

    design life)

    o 20 m with new or like-new engineered shore protection (minimum 35 year design life).

    Erosion allowance is measured horizontally from toe of the natural bluff at elevation 75.0 m.

    Stable slope allowance presented by Terraprobe is 1.8:1.

    Required 5 m wide maintenance access along the shore is located within the erosion hazard

    allowance.

    5 m wide maintenance access must be provided perpendicular to the shoreline from the road.

    Recommend consultation with planner to confirm City parkland and rear setback requirements.

  • R. Thomson

    December 18, 2015

    Page 8 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Cross-sectional and plan drawings which delineate the natural hazards are included in Attachment A.

    3. Shore Protection

    The changing water levels, severe wave action, ongoing nearshore lakebed erosion, and ice forces result

    in hazards to shoreline properties. Protection works can reasonably mitigate these hazards but do not

    eliminate the hazards entirely. There is a risk that the lake conditions will exceed the design conditions

    of the protection structure and the structure may be damaged, requiring repair. Also, as noted, shoreline

    protection structures have a finite design life.

    Concrete Shorewall

    Two general shoreline protection options were identified for determining the EDS for the concrete

    shorewall portion of the site: 1) repair the existing protection as is and achieve 20 year design life; and

    2) rebuild existing protection to achieve minimum design life of 35 years recognized by Conservation

    Halton.

    1) Several repairs to the existing concrete shorewall need to be made in order for the shorewall to

    achieve a 20 year design life. These repairs include:

    Grouting or filling any cracks in the concrete;

    Patching repairs made to any spalling concrete;

    Construction of a rip rap splash pad behind the wall. This splash pad would be approximately

    2 m wide, and would have geotextile placed underneath.

    2) If you wish to forego any repairs and would like to upgrade or replace the existing shorewall in order

    to achieve a design life of 35 years, new shore protection could be designed and constructed. The

    design life of this new shore protection would likely exceed 35 years; however CH only permits a

    design life of 35 years. Should you wish to improve the shore protection at this property such that it is

    like new, there are several alternatives to improving or replacing the existing shoreline protection:

    Armour Stone Structures

    A sloped (2:1 horizontal:vertical) armour stone revetment consists of quarried armour stone blocks

    placed over an underlayer of riprap stone. Figure 1 shows an example of an armour stone revetment.

    Local experience has shown well designed and constructed sloping armour stone revetments to be

    reasonably durable, have a good track record, and perform well under the prevailing lake conditions.

    Experienced local shoreline contractors can readily construct this type of structure. Typically, the cost

    of an armour stone revetment is about $4,000 per metre of shoreline. Costs for a stacked armour stone

    wall would likely be comparable to the costs associated with an armour stone revetment. It is likely that

    some of the stone or concrete from the existing walls could be used in the new structure, which may

    lower the cost of materials. This amount of material would be estimated during the design phase and

  • R. Thomson

    December 18, 2015

    Page 9 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    has not been accounted for in this preliminary cost estimate. The revetment would likely be built in

    front of the existing concrete shorewall.

    Boulder Berm

    A boulder berm consists of multiple layers of rounded stone. It would have a milder slope than the

    armour stone revetment (approximately 3:1) and would be constructed in front of the existing

    protection (example shown in Figure 2). The cost of a boulder berm is about $3,500 per metre of

    shoreline. Due to the gentler slope, the boulder berm would occupy more of the exiting lakebed.

    Figure 1 Example of an Armour Stone Revetment (foreground)

  • R. Thomson

    December 18, 2015

    Page 10 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Figure 2 Example of Boulder Berm

    The boulder berm approach may be viewed as favourable by CH, as these structures have milder slopes

    and are less reflective to wave energy than steeper sloped revetments. In addition, the smaller stone

    material provides diversity for aquatic habitat. These types of shorelines are consistent with the

    principles of the Halton Waterfront – Shoreline and Aquatic Habitat Restoration Strategy. However,

    these berm/beach type shorelines also occupy more lakebed than an armour stone revetment, which

    MNR or DFO may not view as favourable. The natural hazard limits and corresponding EDS associated

    with the boulder berm are the same as the limits associated with construction of a new armour stone

    structure.

    Western Flank

    Along the western flank, the stacked armour stone wall will have to be rebuilt with new shore

    protection, similar to the revetment option presented above.

    Beach

    The cobble beach should be retained. Based on the condition of the existing shore protection it is our

    opinion that the timber wall behind the cobble /shingle beach at the east end of the property should be

    replaced with new shore protection, such as an armour stone revetment or boulder berm.

  • R. Thomson

    December 18, 2015

    Page 11 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    4. Permitting Requirements

    Permits for any work in or near the water, including shore protection, will be required from CH,

    Department of Fisheries and Oceans Canada (DFO), and the Ontario Ministry of Natural Resources

    (MNR).

    Conservation Halton

    A permit for shoreline development will be required from CH. CH also acts in a review capacity for

    planning applications in the City of Burlington. The City establishes conditions based on the

    requirements of CH. It is recommended that discussions be initiated with CH as soon as preliminary

    designs are developed. Owners of neighbouring properties must be provided with the opportunity to

    comment on the proposed work.

    Department of Fisheries and Oceans – Federal Fisheries Act

    Authorization may be required from the DFO under the Federal Fisheries Act. It is recommended that

    discussions be initiated with DFO as soon as preliminary designs are developed. Once the design

    development phase is complete, they will review and advise whether or not an Authorization is

    required.

    Ontario Ministry of Natural Resources

    Work along the shorelands may require a Work Permit from the MNR. Unless there is a water lot, or

    some other legal property designation giving title to the shore owner, the lakebed below the water level

    is Crown Land administered by MNR. If it is proposed to locate works on Crown Land, it may be

    necessary to acquire or lease the land from the province.

    5. Summary

    The existing primary concrete shorewall with armour stone toe protection has an estimated residual

    design life of approximately 20 years, provided some repairs are undertaken. The erosion allowance

    along the southern edge of the property is 24 m with the existing concrete shorewall and repairs, or

    20 m with new shore protection. The armour stone wall along the western flank is in poor condition,

    has no estimated residual design life remaining, and needs to be rebuilt. The shingle/cobble beach at the

    east side should be retained, however, the existing timber beach wall at the back of the beach has no

    residual design life remaining and as is requires a 30 m erosion allowance. If the beach wall is rebuilt

    as a stacked armour stone wall (and the beach is retained), the erosion allowance could be reduced to

    20 m. The stable slope allowance is added to the erosion allowance to establish the Engineering

    Development Setbacks. The erosion allowance and associated Engineering Development Setbacks with

  • R. Thomson

    December 18, 2015

    Page 12 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    existing and new shore protection are delineated in the drawings provided in Attachment A. Any

    parkland dedication and rear yard setbacks should be confirmed by your planner.

    A summary of the approximate costs for the various shore protection options for the three sections of

    the shoreline is provided in Table 1. Note that the costs associated with replacing the concrete shorewall

    are only applicable if you wish to have an erosion allowance of 20 m along the southern edge of the

    property.

    Table 1 Approximate costs for various shore protection options

    Western Flank

    (18m)

    Concrete Shorewall

    (95 m)

    Wall at East Beach

    (17 m)

    Shorewall Repairs n/a $60,000

    (for 24 m EDS) n/a

    Armour Stone

    Structure $72,000

    $380,000

    (for 20 m EDS) $68,000

    Boulder Berm $63,000 $333,000

    (for 20 m EDS) n/a

    We trust this information meets with your approval. If you have any questions please do not hesitate in

    contacting our office.

    Yours truly,

    W.F. Baird & Associates Coastal Engineers Ltd.

    Chris Gibbons, P.Eng.

    Project Engineer, Associate

    Enc: Attachment A – Natural Hazard and Engineered Development Setback Delineation Drawings (4 pages)

    Cc: Mark Kolberg

    12439.101

  • R. Thomson

    December 18, 2015

    Page 13 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    References

    Ministry of Natural Resources (MNR). 2001. Natural Hazards Guide for Great Lakes – St. Lawrence

    River System and large inland lakes, river and stream systems, and hazardous sites. Report 51499

    (5.0kP.R., 30 03 01). Queen’s Printer for Ontario, Ontario.

    Ontario Regulation (162/06). Regulation of the Development, Interference with Wetlands, and

    Alterations to Shorelines and Watercourses. Published by the Conservation Halton under the

    Conservation Authorities Act. May, 2006.

    Terraprobe, 2015. Geotechnical Investigation and Engineering Review of Slope Stability – 105

    Avondale Court and 143 Bluewater Place, Burlington ON. Report prepared by Terraprobe Inc.

  • R. Thomson

    December 18, 2015

    Page 14 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Photograph 1 Oblique aerial view of shoreline at 105 Avondale Court (Aug. 4, 2015)

    Photograph 2 Oblique aerial view of western flank (Aug. 4, 2015)

  • R. Thomson

    December 18, 2015

    Page 15 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Photograph 3 Oblique aerial view of shingle/cobble beach at east end (Aug. 4, 2015)

    Photograph 4 Oblique aerial view of concrete shorewall with armour stone toe (Aug. 4, 2015)

  • R. Thomson

    December 18, 2015

    Page 16 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Photograph 5 Concrete shorewall with armour stone toe (Nov. 25, 2015)

    Photograph 6 Close up aerial view of concrete shorewall (Aug. 4. 2015)

  • R. Thomson

    December 18, 2015

    Page 17 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Photograph 7 Oblique aerial view of shingle/ cobble beach at east end (Aug. 4, 2015)

    Photograph 8 Shingle/cobble beach backed by timber wall at east end (Nov. 25, 2015)

  • R. Thomson

    December 18, 2015

    Page 18 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Photograph 9 Western flank with concrete wall and low stacked stone wall (foreground)

    Photograph 10 Shingles and cobbles on bedrock lakebed (Nov. 25, 2015)

  • R. Thomson

    December 18, 2015

    Page 19 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Photograph 11 Drainage course outlet at east side of site (Nov. 25, 2015)

    Photograph 12 Area behind primary concrete shorewall and bluff face (Nov. 25, 2015)

  • R. Thomson

    December 18, 2015

    Page 20 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Photograph 13 Example of double row of armour stone and mass concrete (Aug. 4, 2015)

    Photograph 14 Concrete shorewall and toe protection in fair condition (Nov. 25, 2015)

  • R. Thomson

    December 18, 2015

    Page 21 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Photograph 15 Example of crack in concrete shorewall (Nov. 25, 2015)

    Photograph 16 Example of concrete spalling (Nov. 15, 2015)

  • R. Thomson

    December 18, 2015

    Page 22 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Photograph 17 Evidence of previous concrete repairs (Nov. 25, 2015)

    Photograph 18 Crack in wall and toe concrete

  • R. Thomson

    December 18, 2015

    Page 23 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Photograph 19 Shingle/cobble beach (field book is 20 x 14 cm).

    Photograph 20 Erosion of bluff behind low armour stone wall along western flank (Nov. 25, 2015)

  • R. Thomson

    December 18, 2015

    Page 24 of 24

    W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

    Baird

    Photograph 21 Adjacent west property (right side, stacked armour stone; left side, concrete blocks)

    Photograph 22 Adjacent east property

  • BH 2

    BH 1

    BH 3

    BH 4

    BH 5

    D

    F'

    F

    EDS Limit

    WITH REPAIRS TO

    EXISTING SHORE

    PROTECTION

    EDS Limit

    WITH LIKE NEW

    SHORE PROTECTION

    VALLEY LANDS

    LONG TERM STABLE

    TOP OF SLOPE

    (TERRAPROBE 2015)

    VALLEY LANDS

    7.5m REGULATORY

    SETBACK

    (TERRAPROBE 2015)

    TIMBER WALL

    SHINGLE/COBBLE

    BEACH

    ARMOUR STONE

    REVISIONS

    REV

    (T.I.)

    T.I.

    TYPE OF

    ISSUE

    DESCRIPTION DRN DSN APR DATE

    REV T.I. DESCRIPTION DRN DSN APR DATE

    REVISION

    PREPARED FOR:

    (A) PRELIMINARY

    (B) FOR REVIEW (D) FOR INFORMATION (F) FOR CONSTRUCTION

    (G) AS BUILT

    (H) CANCELLED

    (E) CONTRACT DOCUMENT(C) FOR APPROVAL

    PREPARED BY:

    DRAWING NUMBER:

    ISSUE

    PREPARED WITH:

    105 AVONDALE CT. BURLINGTON

    NATURAL HAZARD ASSESSMENT

    PLANVIEW

    12439.101 SKT 01

    1 A REVISION TO EDS LIMIT with Repairs to Existing Shore Protection BKC CMG MOK 14/12/15

    1. SUPPLEMENTARY SURVEY MEASUREMENTS OF EXISTINGSEAWALL PROVIDED BY MACKAY PETERS LIMITED 2015

    2. ELEVATIONS REFERENCED TO CITY OF BURLINGTON BENCHMARKNo 380. BRASS PLAQUE ON THE NORTH FACE AT THE TOPNORTHWEST CORNER OF A CONCRETE RETAINING WALL AT THENORTHEAST CORNER OF THE INTERSECTION OD POPLAR DRIVEAND LAKESHORE ROAD. ELEVATION 82.57m

    3. ALL DIMENSIONSAND DISTANCES IN METRES UNLESS OTHERWISENOTED

    5. GEOTECHNICAL INFORMATION PROVIDED BY TERRAPROBE(2015) PROJECT NUMBER 71-15-5064

    Meters

    0

    6

    12

  • 9876 65646362616059585756555453525150494847464544434251 2 3 4 10 11 201918171615141312 21 22 23 24 25 30292827260 4140393837363534333231

    DISTANCE (m)

    717069686766

    76

    77

    78

    79

    80

    81

    82

    86

    85

    84

    83

    ELE

    VA

    TIO

    N (m

    ), geodetic datum

    73

    74

    75

    72

    71

    70

    WL 76.0 (100 year)

    WL 74.8 (AUG 2015)

    LAKE ONTARIO

    BH 1

    FILL

    silty sand, loose, brown

    QUEENSTON FORMATION

    weathered shale bedrock, reddish brown

    SILTY SAND, trace gravel

    compact to dense, lt. brown

    CLAYEY SILT TILL

    very stiff, reddish brown

    CONCRETE SEAWALL WITH

    ARMOUR STONE TOE

    1.3H: 1V

    Erosion Allowance with Like New Shore Protection 20.0 m

    STABLE SLOPE

    PROFILE

    1.8H : 1V

    Stable Slope Allowance 16.3 m

    INFERRED TOE OF SLOPE (ELEV. 75.0)

    EDS LIMIT

    (20 m Erosion

    Allowance)

    PHYSICAL TOP OF SLOPE

    EXISTING STABLE TOP OF SLOPE

    Erosion Allowance with Repairs to Existing Shore Protection 24.0 m

    EDS LIMIT

    (24.0 m Erosion Allowance)

    Stable Slope Allowance 16.2 m

    9876 65646362616059585756555453525150494847464544434251 2 3 4 10 11 201918171615141312 21 22 23 24 25 30292827260 4140393837363534333231

    DISTANCE (m)

    717069686766

    76

    77

    78

    79

    80

    81

    82

    86

    85

    84

    83

    ELE

    VA

    TIO

    N (m

    ), geodetic datum

    73

    74

    75

    72

    71

    70

    WL 76.0 (100 year)

    WL 74.8 (AUG 2015)

    LAKE ONTARIO

    INFERRED TOE OF SLOPE (ELEV. 75.0)

    BH 2

    FILL

    silty sand

    loose, brown

    QUEENSTON FORMATION

    weathered shale bedrock, reddish brown

    SILTY SAND,

    trace gravel

    compact to dense

    lt. brown

    CLAYEY SILT TILL

    very stiff, reddish brown

    Basement

    EDS LIMIT

    (20 m Erosion

    Allowance)

    Erosion Allowance with Like New Shore Protection 20.0 m

    Stable Slope Allowance 17.0 m

    STABLE SLOPE PROFILE

    1.8H : 1V

    PHYSICAL TOP OF SLOPE

    EXISTING STABLE TOP OF SLOPE

    1.4H: 1V

    Erosion Allowance with Repairs to Existing Shore Protection 24.0 m

    EDS LIMIT

    (24.0 m Erosion Allowance)

    Stable Slope Allowance 17.3 m

    SECTION B-B'

    SECTION A-A'

    CONCRETE SEAWALL WITH

    ARMOUR STONE TOE

    REVISIONS

    REV

    (T.I.)

    T.I.

    TYPE OF

    ISSUE

    DESCRIPTION DRN DSN APR DATE

    REV T.I. DESCRIPTION DRN DSN APR DATE

    REVISION

    PREPARED FOR:

    (A) PRELIMINARY

    (B) FOR REVIEW (D) FOR INFORMATION (F) FOR CONSTRUCTION

    (G) AS BUILT

    (H) CANCELLED

    (E) CONTRACT DOCUMENT(C) FOR APPROVAL

    PREPARED BY:

    DRAWING NUMBER:

    ISSUE

    PREPARED WITH:

    105 AVONDALE CT. BURLINGTON

    NATURAL HAZARD ASSESSMENT

    TYPICAL SECTIONS

    12439.101 SKT 02

    1 A REVISION TO EDS LIMIT with Repairs to Existing Shore Protection BKC CMG MOK 14/12/15

    1. SUPPLEMENTARY SURVEY MEASUREMENTS OF EXISTINGSEAWALL PROVIDED BY MACKAY PETERS LIMITED 2015

    2. ELEVATIONS REFERENCED TO CITY OF BURLINGTON BENCHMARKNo 380. BRASS PLAQUE ON THE NORTH FACE AT THE TOPNORTHWEST CORNER OF A CONCRETE RETAINING WALL AT THENORTHEAST CORNER OF THE INTERSECTION OD POPLAR DRIVEAND LAKESHORE ROAD. ELEVATION 82.57m

    3. ALL DIMENSIONSAND DISTANCES IN METRES UNLESS OTHERWISENOTED

    5. GEOTECHNICAL INFORMATION PROVIDED BY TERRAPROBE(2015) PROJECT NUMBER 71-15-5064

    Meters

    0

    4

    8

  • 9876 65646362616059585756555453525150494847464544434251 2 3 4 10 11 201918171615141312 21 22 23 24 25 30292827260 4140393837363534333231

    DISTANCE (m)

    777675747372717069686766

    76

    77

    78

    79

    80

    81

    82

    86

    85

    84

    83

    ELE

    VA

    TIO

    N (m

    ), geodetic datum

    73

    74

    75

    72

    71

    70

    WL 76.0 (100 year)

    WL 74.8 (AUG 2015)

    LAKE ONTARIO

    BH 3

    BH 4

    FILL

    CLAYEY SILT TILL

    very stiff, reddish brown

    STABLE SLOPE PROFILE

    1.8H : 1V

    TIMBER WALL

    STABLE SLOPE

    ALLOWANCE

    INFERRED TOE OF SLOPE (ELEV. 75.0)

    SHINGLE/COBBLE BEACH

    FILL silty clay, stiff, brown

    QUEENSTON FORMATION

    weathered shale bedrock, reddish brown

    CLAYEY SILT TILL very stiff, reddish brown

    Erosion Allowance with Repairs to Existing Shore Protection 30.0 m

    EDS LIMIT

    (30.0 m Erosion Allowance)

    Stable Slope

    Allowance 5.3 m

    EXISTING STABLE TOP OF SLOPE

    SECTION D-D'

    EDS LIMIT

    (20 m Erosion

    Allowance)

    Erosion Allowance with Like New Shore Protection 20.0 m

    Stable Slope

    Allowance 5.2 m

    REVISIONS

    REV

    (T.I.)

    T.I.

    TYPE OF

    ISSUE

    DESCRIPTION DRN DSN APR DATE

    REV T.I. DESCRIPTION DRN DSN APR DATE

    REVISION

    PREPARED FOR:

    (A) PRELIMINARY

    (B) FOR REVIEW (D) FOR INFORMATION (F) FOR CONSTRUCTION

    (G) AS BUILT

    (H) CANCELLED

    (E) CONTRACT DOCUMENT(C) FOR APPROVAL

    PREPARED BY:

    DRAWING NUMBER:

    ISSUE

    PREPARED WITH:

    105 AVONDALE CT. BURLINGTON

    NATURAL HAZARD ASSESSMENT

    TYPICAL SECTIONS

    12439.101 SKT 03

    1 A REVISION TO EDS LIMIT with Repairs to Existing Shore Protection BKC CMG MOK 14/12/15

    1. SUPPLEMENTARY SURVEY MEASUREMENTS OF EXISTINGSEAWALL PROVIDED BY MACKAY PETERS LIMITED 2015

    2. ELEVATIONS REFERENCED TO CITY OF BURLINGTON BENCHMARKNo 380. BRASS PLAQUE ON THE NORTH FACE AT THE TOPNORTHWEST CORNER OF A CONCRETE RETAINING WALL AT THENORTHEAST CORNER OF THE INTERSECTION OD POPLAR DRIVEAND LAKESHORE ROAD. ELEVATION 82.57m

    3. ALL DIMENSIONSAND DISTANCES IN METRES UNLESS OTHERWISENOTED

    5. GEOTECHNICAL INFORMATION PROVIDED BY TERRAPROBE(2015) PROJECT NUMBER 71-15-5064

    Meters

    0

    4

    8

  • 9876 656463626160

    595857565554535251

    50494847464544434251 2 3 4

    1011

    201918171615141312 21 22 23 24

    25 30292827260 41

    40393837363534333231

    DISTANCE (m)

    767574737271

    7069686766

    76

    77

    78

    79

    80

    81

    82

    86

    85

    84

    83

    ELE

    VA

    TIO

    N (m

    ), geodetic datum

    73

    74

    75

    72

    71

    70

    BH 3

    FILL silty clay, stiff, brown

    QUEENSTON FORMATION

    weathered shale bedrock, reddish brown

    CLAYEY SILT TILL very stiff, reddish brown

    9876 656463626160

    595857565554535251

    50494847464544434251 2 3 4

    1011

    201918171615141312 21 22 23 24

    25 30292827260 41

    40393837363534333231

    DISTANCE (m)

    7473727170

    69686766

    76

    77

    78

    79

    80

    81

    82

    86

    85

    84

    83

    ELE

    VA

    TIO

    N (m

    ), geodetic datum

    73

    74

    75

    72

    71

    70

    76

    77

    78

    79

    80

    81

    82

    86

    85

    84

    83

    73

    74

    75

    72

    71

    70

    FILL

    silty sand, loose, brown

    BH 4

    FILL silty clay, stiff, brown

    QUEENSTON FORMATION

    weathered shale bedrock, reddish brown

    CLAYEY SILT TILL very stiff, reddish brown

    BH 5

    CLAYEY SILT TILL very stiff, reddish brown

    QUEENSTON FORMATION

    weathered shale bedrock, reddish brown

    GABION WALL

    CREEK

    CREEK

    5.0 m

    EROSION

    ALLOWANCE

    3.7 m

    LONG TERM STABLE TOP OF SLOPE

    (TERRAPROBE 2015)

    STABLE SLOPE

    ALLOWANCE

    5.0 m

    EROSION

    ALLOWANCE

    5.6 m

    STABLE SLOPE

    ALLOWANCE

    BH 2

    FILL

    silty sand

    loose, brown

    QUEENSTON FORMATION

    weathered shale bedrock, reddish brown

    CLAYEY SILT TILL

    very stiff, reddish brown

    STABLE SLOPE PROFILE

    1.8H : 1V

    STABLE SLOPE PROFILE

    2H : 1V

    SILTY SAND, trace gravel

    compact to dense, lt. brown

    SECTION E-E'

    SECTION F-F'

    REGULATORY SETBACK

    (TERRAPROBE 2015)

    7.5 m

    LONG TERM STABLE TOP OF SLOPE

    (TERRAPROBE 2015)

    REGULATORY SETBACK

    (TERRAPROBE 2015)

    7.5 m

    1. SUPPLEMENTARY SURVEY MEASUREMENTS OF EXISTINGSEAWALL PROVIDED BY MACKAY PETERS LIMITED 2015

    2. ELEVATIONS REFERENCED TO CITY OF BURLINGTON BENCHMARKNo 380. BRASS PLAQUE ON THE NORTH FACE AT THE TOPNORTHWEST CORNER OF A CONCRETE RETAINING WALL AT THENORTHEAST CORNER OF THE INTERSECTION OD POPLAR DRIVEAND LAKESHORE ROAD. ELEVATION 82.57m

    3. ALL DIMENSIONSAND DISTANCES IN METRES UNLESS OTHERWISENOTED

    5. GEOTECHNICAL INFORMATION PROVIDED BY TERRAPROBE(2015) PROJECT NUMBER 71-15-5064

    Meters

    0

    4

    8

    REVISIONS

    REV

    (T.I.)

    T.I.

    TYPE OF

    ISSUE

    DESCRIPTION DRN DSN APR DATE

    REV T.I. DESCRIPTION DRN DSN APR DATE

    REVISION

    PREPARED FOR:

    (A) PRELIMINARY

    (B) FOR REVIEW (D) FOR INFORMATION (F) FOR CONSTRUCTION

    (G) AS BUILT

    (H) CANCELLED

    (E) CONTRACT DOCUMENT(C) FOR APPROVAL

    PREPARED BY:

    DRAWING NUMBER:

    ISSUE

    PREPARED WITH:

    105 AVONDALE CT. BURLINGTON

    NATURAL HAZARD ASSESSMENT

    TYPICAL SECTIONS

    12439.101 SKT 04

    1 A REVISION TO EDS LIMIT with Repairs to Existing Shore Protection BKC CMG MOK 14/12/15


Recommended