+ All Categories
Home > Documents > July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting...

July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting...

Date post: 17-Aug-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
19
2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013 Delivery Program) About This Report Page 1 Service Highlights Page 2 Other Issues Page 5 Quarterly Budget Review Statement Page 7
Transcript
Page 1: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

 

 

 

2012-2013 QUARTER 1 REPORT July to September 2012

Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013 Delivery Program)

  

       

About This Report  Page 1 Service Highlights  Page 2 Other Issues  Page 5 Quarterly Budget Review Statement  Page 7 

 

Page 2: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

About this Report The provisions of  Integrated Planning and Reporting under  the  Local Government Act, 1993 require that reports are provided to the Council on the progress in implementing the Delivery Program and Operational Plan as follows: 

Budget review statement (quarterly);  

Delivery Program progress report (6‐monthly); and 

Annual  report  including audited  financial  reports  (within 5 months of  the end of each financial year). 

 This report provides the legislatively required budget review statement, as well as highlighting key achievements and any other issues to note for Quarter 1 of 2012‐2013 (July to September 2012).  

The Purpose of Quarterly / Six‐Monthly Reports Quarterly and Six‐Monthly Reports have been designed: 

To meet legislative requirements (transparency and accountability); 

To provide a practical assessment of how  the Council  is  tracking overall – whether we are delivering against our commitments on time and within budget; and 

To demonstrate results / achievements and to formally document any  issues that arise that impact on service delivery commitments. 

 

How the Council will be assessing progress in 2012‐2013   Budget Review Statement The budget review statement must include details on the general financial position of the Council and if this position is regarded as unsatisfactory, also include recommendations for remedial action. The budget review statement will be provided to the Council as follows:  Quarter 1 (July to September 2011) – reported in November 2012  Quarter 2 (October to December 2011) – reported in February 2013  Quarter 3 (January to March 2013) – reported in May 2013  Quarter 4 (April to June 2013) – reported in August 2013 

 Delivery Program and Operational Plan progress report The method for assessing progress in implementing the Council’s Delivery Program and Operational Plan includes:   Action / project progress – tracking whether actions / projects are being delivered as planned 

on time and within budget (reported every six months)  Other service measures – used to measure specific  results achieved by different services  

(reported at the end of the financial year)  Quantitative Quadruple Bottom Line (QBL) measures – used to measure Council’s 

environmental, social, financial and governance performance against the Key Direction of Providing Good Government (reported at the end of the financial year) 

Qualitative Community Survey  – used to measure perceptions of key stakeholders on service performance results (reported at the end of the financial year) 

Quantitative asset based measures – used to measure actual improvement in built asset condition e.g. roads, footpaths, pools (reported at the end of the council term) 

 Progress on the implementation of the 2010‐2013 Delivery Program and 2012‐2013 Operational Plan will be provided to the Council as follows:  First six months (July to December 2012) – reported in February 2013  Final six months (January to June 2013) – reported in August 2013 

1

Page 3: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

SERVICE HIGHLIGHTS  Child Care 

The Family Day Care service achieved an outstanding result in the NSW Department of Education and Communities assessment of the service against the National Quality Standard. 

 

Community Development and Cultural Development  Public exhibition of the Development Application for the Springwood Community and 

Cultural Facilities Upgrade commenced on 11 July 2012 for a 30 day period. The DA will be assessed and determined by the Joint Regional Planning Panel, which is an external and independent body to the Council. The revised timing of the construction tender from late 2012 to mid‐January 2013 due to requirements for further work including a Value Management process and car parking study in the schematic design process, was endorsed by the Council at the 28 August 2012 Council meeting. 

 

Corporate Strategic Planning and Reporting  The Council is legislatively required to prepare a number of reports on Council 

progress in implementing its plans. The 2011‐2012 End‐of‐Year Report and 2008‐2012 End of Council Term Report were presented to the 28 August Council meeting highlighting the achievements of the outgoing Council. The 2012 Community Survey Report was also presented to the 28 August 2012 Council Meeting with the Council scoring the highest community satisfaction rating with overall Council performance since 1996. 

 

Cultural Development  The Council endorsed the 2012 funding recommendations for the Cultural 

Partnerships Program at the 7 July 2012 Council Meeting.   

Cultural Development:   The Blue Mountains Cultural Centre was progressed: 

- All Management and Officer positions for the Blue Mountains Cultural Centre were filled. 

- The Operational program for the Blue Mountains Cultural Centre was set for the forward 12 months. 

- Facebook Friends grown to 175 friends. - 13 merchandise lines were designed and manufactured for the Blue Mountains 

Cultural Centre Shop. - 2 corporate sponsorships activated. - Opening exhibition catalogue designed and sent to print.  

 

Economic Development and Tourism  The Council appointed board members  to  the Blue Mountains Economic Enterprise 

Limited at the 7 August 2012 Council Meeting. The economic development entity is an initiative of the Council and will focus on generating ideas and initiatives for economic growth and jobs creation across the region. 

 WiFi was implemented at the Glenbrook and Katoomba Visitor Information Centres.   

  

2

Page 4: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

Hazelbrook toilet 

Environmental Sustainability  A review of Council systems and processes in place to comply with Part 5 Assessment 

in relation to environmental matters was undertaken with initial revised processes now in place. 

The Blue Mountains Bushcare’s Big Day Out was held on Sunday 9 September at Central Park, Falls Road, Wentworth Falls. A range of activities were held including a bird walk with botanist and bird enthusiast, Jill Dark, planting, weed removal, mulching, pruning and a site walk and a well celebrated morning tea. This event was sponsored by the Council as part of national Landcare Week.  

Human Resources  Bullying / Harassment workshops were provided to all staff. 

 

Land Use Management  Certification services were reviewed by the Building Professionals Board (BPB).   The 

BPB representative noted that the Council’s procedures and practices were of a high standard and recognised its monitoring and reporting systems as the first to be found to be fully compliant with its obligations under the Building Professionals Act. 

 

Libraries and Information  A number of library events were held including: 

- Annual ABC 702 Knit In - Children's Book Cover Art competition - Springwood Library hosted an introduction to Family History resources in 

collaboration with the Blue Mountains Family History Society (27 people attended) during Family History Week 

 

Sport and Recreation  The Plan of Management for Batman Reserve, Springwood was adopted at the 7 

August 2012 Council Meeting.  

The new Glenbrook Pool filtration plant is operational and the pool opened on time with a free community open day on Saturday 6 October 2012. The new filtration plant will improve water quality and clarity and the new heating system will maintain the water temperature at a comfortable 27degrees. Mayor, Councillor Daniel Myles utlisised a promotional YouTube video that provided the community and pool users with detailed information on the upgrade and its benefits. 

 

Town Centres  The  new  public  toilet  facility  at 

Hazelbrook  was  opened  by  Blue Mountains  City  Council  on Monday  20 August  2012.  The  facility  is  a modern design that includes an accessible toilet, a  baby  change  table  with  easy  access from  the  shopping  precinct.  The  new toilet  block  has  a  rainwater  capture system that enables the re‐use of water for  toilet  flushing  and  landscape watering  and  includes  an  on‐line flushing system to save water. Also, the building  panels  have  an  anti  graffiti coating. 

3

Page 5: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

Mayor, Cr Daniel Myles and Cr Chris Van der Kley  inspect the Council’s road sealing trial in Duperry St, north Wentworth Falls  

Transport and Public Access  The Council endorsed the use of electronic vehicle detection technology for managing 

parking in appropriate circumstances at the 7 July Council Meeting. This decision was based on a trial of the detection technology in Leura in response to requests from the Leura Village Association. The aim of the technology is to increase turnover of vehicles consistent with the existing time limited signs, to promote a more equitable use of the parking resource. 

The  Sealing  of  Unsealed  Roads  Program  commenced.    This  comprehensive  road sealing  program  of  selected  gravel  roads  in  the mid  and  lower mountains  aims  to reduce  ongoing  road maintenance  costs  as well as  eliminating  sediment run  off  and  also  providing improved  amenity  for residents. 

This  Council  hosted  Bike Week  for  Little  Kids  in September  in  Glenbrook Park,  partnering  with Lower  Mountains Neighbourhood  Centre, Gateway  Family  Services, 

Mountains  Outreach Community  Service, Connect  Child  and  Family Services and the Getting Around  In Community Project to deliver a bigger and better Bike Week. Bike Week activities provided  information and  instruction on bike safety, riding skills and the enjoyment of cycling. 

 

Water Resource Management  The Council was successful in its grant application for the 2012‐2013 Floodplain 

Management Program ‐ South Lapstone, South Glenbrook and South Blaxland Floodplain Risk Management Study & Plan $80,000 and Hazelbrook and Woodford Creeks Catchment Overland Flow Path Study $19,467. 

 

4

Page 6: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

Fire and Rescue NSW Hazardous Material team assist with the removal of contaminated material from a stormwater basin as part of the Jamison Creek pollution incident clean up effort.

ISSUES TO NOTE  

City‐wide Strategic Planning  At the 7 August Council Meeting, the Council considered the requirement of the NSW 

Government that BMCC commit to a timetable to implement the Standard Instrument Local Environmental Plan within the Blue Mountains by mid 2013. This latest directive from the Minister for Planning and Infrastructure presents very real challenges to the Council and community. The sustained focused effort necessary to implement the drafting of the Local Environmental Plan to meet the requirements of the NSW Government will require re‐allocation of resources, which is likely to affect the planned work programs and services contained within the adopted Delivery and Operational Plan and may also require additional resources. This will be further considered in Quarter 2. 

The NSW Government has invited submissions to ‘A New Planning System for NSW Green Paper’. The Green Paper for the reform of the NSW Planning system represents the most significant review of the planning legislation for a generation.  At the 25 September 2012 Council Meeting, the Council agreed to make a submission to the Green Paper. It is the case, that the Blue Mountains is a highly complex planning environment, and one with a community with high expectations for the quality of the built environment and the protection of important places. It will be important that the Council maintain its focus as the reform process unrolls and concludes, to ensure that the values of the Blue Mountains and the expectations of its community are met now and in the longer term. 

Cultural Development 

The funding of the Bicentenary Crossing events was considered at the 28 August 2012 Council meeting. Funding of $90,000 for the three Council‐managed events ‐ the Government House Reception, ‘Top of Town’ in Katoomba, and ’21 Days on the Mountain’ – was identified from within the 2011‐2012 operating surplus. 

 

Environmental Sustainability  After a mass die‐off of  freshwater crayfish, 

native  fish  and  other  macro‐invertebrates (water bugs) was reported by a bushwalker, the  Council  commenced  investigations  into the  incident  immediately. An  inspection  by Council  staff  found  hundreds  of  crayfish, both adult and juvenile, dead or dying in the creek,  extending  from  the  Great  Western Highway  through  to  the  waterfall  at Wentworth  Falls.  The  NSW  Department  of Primary  Industries  Fisheries  Division  (DPI), the  Environmental  Protection Agency  (EPA) and  NPWS  continued  the  investigation with  support  from  the  Council.  The Environmental Protection Authority  (EPA), identified  the  contaminant  as  a termiticide,  a pesticide  commonly used  for  termite  control.  Test  results  suggest  the contaminant entered the creek via the stormwater outlet  in Wilson Park, Wentworth Falls. The Council, with the assistance of the Fire and Rescue NSW hazardous material team,  coordinated  the  removal of  contaminated  sediment  from  a  stormwater basin located  on  private  land  last  week,  as  a  matter  of  urgency,  to  prevent  further 

5

Page 7: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

contamination  of  Jamison  Creek.  The  Council  commenced  investigations  into  the potential  cause  of  the  pollution  and will  continue  regular monitoring  of  the water quality  and  macro‐invertebrates  (waterbugs)  in  Jamison  Creek  to  assess  ongoing impacts of the contamination and the rate of recovery. 

 

Governance  The Council elections on 8 September were successfully held with the election of eight 

new Councillors and four Councillors re‐elected from the previous term. The Council has provided the Councillors with a number of induction sessions. 

Emergency Management 

The Council considered the NSW State Government’s review of emergency services funding at the 28 August 2012 Council Meeting. The Council endorsed a submission being made based on the following themes: 

a) that Council supports the introduction of a broad‐based property levy as the State’s source of funding for emergency services, provided this replaces the current 11.7% statutory contributions made by Council; 

b) that Council’s preference is that the broad‐based property levy is applied as a flat rate per property and that some exemption is established for lands owned, vested in, or under the care, control and management of Council; 

c) that the State recognises that Blue Mountains City Council has significant risk and asset management obligations as a major land manager of a City within a fire‐prone, World Heritage area, and that Council should continue to be able to levy associated costs from ratepayers through the Emergency Services Annual Charge (ESAC); and 

d) that any broad‐based property levy is collected by the Office of State revenue, or if collected by Council on behalf of the State, that this be on a fee for service basis. 

  

6

Page 8: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

Quarterly Budget Review Statement by the Responsible Accounting Officer  In accordance with the Local Government Act, 1993 and the provisions of clause 9 of the Financial Management Regulation, a budget review statement and revision of estimates must be completed and submitted to the Council for formal adoption at the end of each financial quarter. This report must include details on the general financial position of the Council and if this position is regarded as unsatisfactory, also include recommendations for remedial action.  

The following information details the budget review statement to the end of September 2012 in accordance with the requirements of the legislation. The Department of Local Government has issued guidelines for the minimum requirements of Quarterly Budget Review Statements. The minimum requirements are mandatory from 1 July 2011. The statements included in the budget review statement by the responsible accounting officer comply with the minimum requirements of the Department of Local Government.  

Working Capital Result The Council’s Working Capital Result is a financial measure that highlights the Council’s ability to satisfy financial obligations in the short term. The Working Capital Position is defined as the net amount of uncommitted funds available to the Council in the next 12 month period and importantly it excludes non‐cash items like depreciation. A surplus indicates how much uncommitted funds the Council has provided to account for cash tied up in inventory and long outstanding debts.  The Council aims to maintain an optimum level of working capital of around $1.7 million to $1.8 million.   The Council’s Working Capital for the year ended 30 June 2012 was a surplus of $1.862 million. An analysis of actual results and revised projections as at September 2012 Quarter has resulted in no change to the projected working capital position and therefore the position is maintained at $1.862 million projected to 30 June 2013.  Subject to the Council adopting the recommended variations, the estimated effective working capital of $1,862,000 is maintained within the calculated optimum level.     The following reconciliation illustrates the projected Working Capital position as at the 30 June 2013 review.    

7

Page 9: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

Table 1  

Actual Working Capital Result– 1 July, 2012   1,862,000

Original Budget 2012‐2013 Forecast Improvement in Working Capital       0   

September 2012 Review  0

Revised Estimated Working Capital Result– 30 June 2013  1,862,000

Revised Estimated Working Capital Result– 30 June 2013. Working Capital is the net amount of uncommitted funds consisting of: 

Estimated

2012‐2013

Unrestricted current cash   2,757,000

Current receivables  5,905,000

Inventories  400,000

Prepayments  300,000

Payables (excluding liabilities budgeted next year 2013‐2014)  (7,500,000)

Total  1,862,000

 

 Operational Budget – Significant Variations There are no significant variations to the Operational Budget for Quarter 1.  CAPITAL WORKS PROGRAM SUMMARY Total 2012‐2013 budget*  $28,836,773

Total Dollars spent as at 30 September 2012  $1,909,754

Percentage spent  6.6%

Percentage of projects on target or completed  98%*Includes funding carried over from 2011‐2012, recommended / adopted variations and capital funding for Major Projects. Excludes IT assets and plant and equipment. 

 

Note that whilst expenditure of 6.6% is relatively low, this is generally consistent with the planning, project brief development and procurement phases of most capital projects in Quarter 1.  

Capital Works Program – Significant Variations The following variations relating to capital projects are recommended. 

Increase/Decrease to Capital Works Program  Variation 

Heatherbrae house improvements stage 2 (funding from restricted asset)  $325,000

Cultural Centre new library and fit‐out (funding from library development grant $200k and library special purpose grant $114k) 

$314,000

Footpath upgrade Katoomba Street Katoomba, Minute No. 169, 23 April 2012 (funding from Section 94 restricted asset)   

$186,000

Total  825,000

8

Page 10: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

Cash Flow The Council’s cash position has increased by $0.87 million from a balance of $32.97 million at 30 June 2012 to a balance of $33.84 million at 30 September 2012 as presented below.  

  Loan Position The Council’s outstanding loan position as at 30 June 2012 was $48.06 million.  At the end of September 2012 the loan position stands at $47.98 million.   The figure below indicates that the total loan balance will increase from $48.06 million from 30 June 2012 to $60.20 million at 30 June 2013. The new borrowings in 2012‐2013 are $15.6 million and in 2013‐2014 $8.31 million, and then projected at $2.31 million per annum each year thereafter. The total balance decreases to $55.53 million by 2017‐2018. Loans are raised over the period to fund the following major projects:  

Cultural Centre, Library and Civic Centre $5.3 million 

Lawson Town Centre $4.4 million 

Katoomba Waste Transfer Station $8.8 million  

Blaxland Waste Facility $6.1 million 

Local Infrastructure Renewal Scheme $10.86 million 

  

9

Page 11: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

The figures in the previous graph are in accordance with the Council’s 2011‐2021 Long Term Financial Plan and include the latest anticipated loan funding required for the Cultural Centre, Lawson Town Centre, Waste Transfer Station, Blaxland Waste Facility and Local Infrastructure Renewal Scheme projects.  Measuring the Council’s Financial Performance The following series of measures are being used to monitor and report on the Council’s financial performance. Results for these measures will be provided at the end of the financial year. 

Operating Result from Continuing Operations  ‐ Total operating revenue less total operating expenses (including depreciation and excluding capital grants, capital expenditure and capital movements) 

Operating Balance Ratio – Operating result from continuing operations divided by operating revenue 

Unrestricted Working Capital – Unrestricted current assets less unrestricted current liabilities 

Current Ratio (Unrestricted) – Current Assets less Externally Restricted Current Assets divided by Current Liabilities less Specific Purpose Current Liabilities 

Rates & Annual Charges Coverage Ratio – Rates and annual charges as a percentage of operating revenue 

Rates and Annual Charges Outstanding – Rates and annual charges outstanding as a percentage of Rates and annual charges collectible 

Asset Renewal Ratio (Buildings & Infrastructure) – Asset Renewals (Buildings & Infrastructure) divided by Depreciation, Amortisation & Impairment (Buildings & Infrastructure) 

Asset Renewal Gap ratio – Estimated Required Asset Renewal Expenditure divided by Current renewal expenditure on assets  

Debt Service Ratio – Interest divided by Operating Revenue  

10

Page 12: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

 2012-2013 Quarter 1 Report

Report by Responsible Accounting Officer

The following statement is made in accordance with Clause 203(2) of the LocalGovernment (General) Regulations 2005.

It is my opinion that the Quarterly Budget Review Statement for  Blue Mountains  City Council forthe quarter ended 30 September 2012 indicates that Council’s projected financial position at30/6/2013 will be satisfactory at year end, having regard to theprojected estimates of income and expenditure and the original budgetedincome and expenditure.

Signed:

Responsible Accounting Officer

Date: 26 October 2012

11

Page 13: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 ReportIncome & Expense- General Fund Budget Review Statement for the quarter ended - 30 September 2012

R'meded Projected

Original changes year end

Budget Revised for Council result Actual

Review 

(carry‐over) Review Budget Resolution YTD

Income

Rates and Annual Charges 55,608,609 562,422 56,171,031 56,171,031 56,073,687

User Charges and Fees 14,910,352 14,910,352 14,910,352 3,202,716

Interest and Investment Revenue 1,632,629 1,632,629 1,632,629 408,344

Other Revenues 4,340,663 4,340,663 4,340,663 910,727

Grants & Contributions ‐ Operating 11,578,339 ‐4,493,573 7,084,766 7,084,766 1,621,860

Grants and Contributions ‐ Capital 5,503,090 2,855,567 8,358,657 8,358,657 305,179

Net gain from the disposal of assets 420,380 420,380 420,380 82,744

Share of interests in joint ventures 0 0

Total Income from continuing 

operations 93,994,062 2,855,567 ‐3,931,151 92,918,478 0 92,918,478 62,605,257

   

Employee costs 43,295,685 175,048 43,470,733 43,470,733 10,327,392

Borrowing Costs 3,382,546 3,382,546 3,382,546 636,034

Materials & Contracts 18,554,161 816,455 34,560 19,405,176 19,405,176 4,279,744

Depreciation 33,600,000 33,600,000 33,600,000 7,112,642

Legal Costs 722,500 722,500 722,500 110,837

Consultants 678,270 135,419 813,689 813,689 213,010

Other Expenses 11,931,215 9,228 11,940,443 11,940,443 3,462,437

Interest and Investment Losses 0 0

Net Loss from Disposal of Assets 0 0

Share of interests in joint ventures 0 0

Total Expense from continuing

operations 112,164,377 1,136,150 34,560 113,335,087 0 113,335,087 26,142,096

Net Operating Result from

continuing operations ‐ Surplus

(Deficit) ‐18,170,315 1,719,417 ‐3,965,711 ‐20,416,609 0 ‐20,416,609 36,463,161

Net Operating Result before

capital items ‐ Surplus(Deficit) ‐23,673,405 ‐1,136,150 ‐3,965,711 ‐28,775,266 0 ‐28,775,266 36,157,982

Statement of Financial Position (including Capital Movements for Year)

Net Operating Result from

continuing operations ‐18,170,315 1,719,417 ‐3,965,711 ‐20,416,609 0 ‐20,416,609 36,463,161

Movements in Restricted Assets ‐ 0

Transfer from 7,824,708 12,201,311 4,148,711 24,174,730 24,174,730 7,344,098

Sale of Assets 1,512,031 1,512,031 1,512,031 404,681

Capital Acquisitions 21,300,424 13,920,728 183,000 35,404,152 35,404,152 2,531,454

Loan/Lease Repayments 3,466,000 3,466,000 3,466,000 75,103

Non Cash Budget for Depreciation 33,600,000 33,600,000 33,600,000 7,112,642

Change in Working Capital 0 0 0 0 0 0 48,718,025

Notes:

This document forms part of Blue Mountains City Council's Quarterly Budget Review Statement (QBRS) for the quarter ended and should 

be read in conjunction with other documents in the QBRS.

Approved Changes

12

Page 14: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

Income & Expense‐ Activities Budget Review Statement for the quarter ended ‐ 30 September 2012

R'mended Projected

Original changes year end

Budget Revised for Council result Actual

Review 

(carryover) Review Budget Resolution YTD

Income 

Looking after the Environment

‐ Environmental Sustainability 2,427,480 2,427,480 2,427,480 614,701

‐ Water Resource Management 25,152 25,152 25,152 0

‐ Waste Resource Management 19,479,256 19,479,256 19,479,256 13,637,052

Looking after People

‐ Child Care 1,361,243 1,361,243 1,361,243 462,072

‐ Community Development 1,009,226 1,009,226 1,009,226 478,330

‐ Emergency Management 2,429,425 2,429,425 2,429,425 1,748,818

‐ Cultural Development 658,081 658,081 658,081 185,048

‐ Environmental Health & Reg. Compliance 480,806 480,806 480,806 371,136

‐ Libraries & Information 396,831 396,831 396,831 37,805

‐ Sport & Recreation 5,469,364 5,469,364 5,469,364 877,985

Using Land and Moving Around

‐ Burial & Ashes Placement 365,828 365,828 365,828 85,943

‐ Land Use Management 1,484,170 1,484,170 1,484,170 444,214

‐ Town Centres 253,372 253,372 253,372 24,522

‐ Transport & Public Access 2,640,082 2,640,082 2,640,082 51,998

Sustainable Economy

‐ Economic Development & Tourism 1,754,559 1,754,559 1,754,559 329,755

Governance & Corporate Support 15,795,379 15,795,379 15,795,379 5,184,830

Non Attributable 53,490,871 53,490,871 53,490,871 49,518,721

Total Income 109,521,125 0 0 109,521,125 0 109,521,125 74,052,930

Approved Changes

13

Page 15: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 ReportIncome & Expense‐ Activities Budget Review Statement for the quarter ended ‐ 30 September 2012 continued

R'meded Projected

Original changes year end

Budget Revised for Council result Actual

Review 

(carryover) Review Budget Resolution YTD

Expense

Looking after the Environment

‐ Environmental Sustainability 4,356,045 4,356,045 4,356,045 899,033

‐ Water Resource Management 374,835 374,835 374,835 155,221

‐ Waste Resource Management 19,482,512 19,482,512 19,482,512 4,219,441

Looking after People

‐ Child Care 1,693,183 1,693,183 1,693,183 454,544

‐ Community Development 3,524,125 3,524,125 3,524,125 817,172

‐ Emergency Management 3,364,295 3,364,295 3,364,295 1,249,356

‐ Cultural Development 2,095,610 2,095,610 2,095,610 272,263

‐ Environmental Health & Reg. Compliance 2,258,998 2,258,998 2,258,998 682,205

‐ Libraries & Information 2,684,781 2,684,781 2,684,781 603,053

‐ Sport & Recreation 11,091,125 11,091,125 11,091,125 2,260,522

Using Land and Moving Around

‐ Burial & Ashes Placement 683,584 683,584 683,584 21,389

‐ Land Use Management 4,189,130 4,189,130 4,189,130 733,445

‐ Town Centres 4,077,662 4,077,662 4,077,662 376,049

‐ Transport & Public Access 9,627,344 9,627,344 9,627,344 1,523,134

Sustainable Economy

‐ Economic Development & Tourism 2,752,345 2,752,345 2,752,345 539,535

Governance & Corporate Support 30,182,176 30,182,176 30,182,176 9,757,133

Non Attributable 7,083,375 7,083,375 7,083,375 771,410

0 0

Total Expense 109,521,125 0 0 109,521,125 0 109,521,125 25,334,905

Notes:

This document forms part of Blue Mountains City  Council's Quarterly Budget Review Statement (QBRS)for the quarter ended and should be

read in conjunction with other documents in the QBRS.

Approved Changes

14

Page 16: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

Capital Budget Review Statement for the quarter ended ‐ 30 September 2012

R'mended Projected

Original changes year end

Budget Revised for Council result Actual

Review 

(carry‐over) Review Budget Resolution YTD

Capital Funding 

Rates and other untied funding 4,515,760 4,515,760 4,515,760 153,641

Capital Grants & Contributions 5,503,090 2,855,567 8,358,657 314,000 8,672,657 305,179

Internal Restrictions

‐ renewals 2,089,401 410,000 2,499,401 325,000 2,824,401

‐ new assets 1,030,000 2,320,057 3,350,057 3,350,057

‐ plant replacement 3,451,852 3,451,852 3,451,852

‐ Waste Facilities debt servicing 262,865 262,865 262,865

External Restrictions

‐ infrastructure levy 0 0

‐ Developer Contributions 345,000 341,317 686,317 186,000 872,317

‐ Specific Purpose Grants 0 0 0

Other Capital Funding Sources  0 0

‐ loans 5,967,425 7,149,916 13,117,341 13,117,341 1,604,576

Income from sale of assets

‐ plant and equipment 1,512,031 1,512,031 1,512,031 404,681

‐ land and buildings 0 0 0

Total Capital Funding 24,677,424 13,076,857 0 37,754,281 825,000 38,579,281 2,468,077

Capital Expenditure

R'meded Projected

Original changes year end

Budget Revised for Council result Actual

Review 

(carry‐over) Review Budget Resolution YTD

New Assets 0 0

‐ Plant and Equipment 976,244 976,244 976,244 258,314

‐ Land and Buildings 5,040,000 5,600,464 10,640,464 314,000 10,954,464 1,195,363

‐ Roads, Bridges, Footpaths & Other 5,119,425 3,909,049 9,028,474 9,028,474 196,549

Renewals (Replacement) 0 0

‐ Plant and Equipment 5,389,264 5,389,264 5,389,264 224,905

‐ Land and Buildings 475,000 1,856,186 2,331,186 325,000 2,656,186 271,380

‐ Roads, Bridges, Footpaths & Other 4,300,491 1,711,158 6,011,649 186,000 6,197,649 246,463

Loan Repayments (principal) 3,377,000 3,377,000 3,377,000 75,103

Total Capital Expenditure 24,677,424 13,076,857 0 37,754,281 825,000 38,579,281 2,468,077

Notes:

This document forms part of Blue Mountains City Council's Quarterly Budget Review Statement (QBRS)for the quarter ended and should be 

read in conjunction with other documents in the QBRS.

Approved Changes

Approved Changes

15

Page 17: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

 2012-2013 Quarter 1 ReportCash and Investments Budget Review Statement for the quarter ended - 30 June 2013

note: original budget is movement 2012/2013 plus opening balance at 30 June 2012

R'meded Projected

Original changes year end

Budget Revised for Council result Actual

(incl b/fwd 

balance)

Review & 

carry‐over Review Budget Resolution YTD

Unrestricted 0 0 530,000

Externally restricted

RTA contributions 140,287 ‐40,000  100,287 100,287 100,287

Developer contributions 50,894 ‐341,317  ‐186,000  ‐476,423  ‐476,423  ‐476,423 

Other contributions 144,240 144,240 144,240 144,240

Domestic waste management 195,369 ‐71,824  123,545 123,545 123,545

Rural Fire Service 125,460 125,460 125,460 125,460

Special rates 53,968 ‐21,996  31,972 31,972 31,972

Unexpended loans 3,151,158 3,151,158 3,151,158 3,151,158

Special purpose grants 4,996,665 ‐286,452  4,710,213 4,710,213 4,710,213

Total Externally restricted 8,858,041 ‐761,589  ‐186,000  7,910,452 0 7,910,452 7,910,452

Internally restricted

Employee leave entitlements 3,157,422 3,157,422 3,157,422 3,157,422

Replacement of plant and vehicles 622,147 622,147 622,147 622,147

Waste bins 364,154 364,154 364,154 364,154

Waste ‐ Blaxland Waste Facility 311,726 311,726 311,726 311,726

Tip improvements 994,977 994,977 994,977 994,977

Waste Management ‐ Carbon Pricing Works 0 562,422 562,422 562,422 562,422

Pay & display 1,166,503 ‐25,752  1,140,751 1,140,751 1,140,751

Elections 400,332 400,332 400,332 400,332

Environmental levy 627,789 ‐625,000  2,789 2,789 2,789

Property investment fund 1,707,913 1,707,913 1,707,913 1,707,913

Property fund (Heatherbrae) 325,500 325,500 ‐325,000  500 500

Property fund (Lawson town centre) 474,500 ‐474,500  0 0 0

Katoomba civic centre/cultural centre 1,321,216 ‐1,321,261  ‐45  ‐45  ‐45 

Family day care 166,186 166,186 166,186 166,186

Loan repayments debt servicing 699,000 699,000 699,000 699,000

Workers compensation insurance 1,602,289 1,602,289 1,602,289 1,602,289

Insurance PR & PI 66,000 66,000 66,000 66,000

Operational improvement initiatives 35,485 35,485 35,485 35,485

Telephone/Information Systems 215,865 215,865 215,865 215,865

Local committees ‐ halls & other 385,118 385,118 385,118 385,118

Printing equipment 49,718 49,718 49,718 49,718

Floodplain risk mngt study & plan 40,000 40,000 40,000 40,000

Works carried forward 809,504 ‐809,504  0 0 0

Cemeteries Improvements 35,835 35,835 35,835 35,835

Major capital projects 5,571 5,571 5,571 5,571

Sports field fees 163,096 163,096 163,096 163,096

Approved Changes

16

Page 18: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

 2012-2013 Quarter 1 ReportCash and Investments Budget Review Statement for the quarter ended - 30 June 2013 continued

R'meded Projected

Original changes year end

Budget Revised for Council result Actual

(incl b/fwd 

balance) Review Review Budget Resolution YTD

RTA Agency Further Works 74,683 74,683 74,683 74,683

Rental on crown lands 82,544 82,544 82,544 82,544

FAG in advance 4,177,573 ‐4,177,573  0 0 0

Investments devaluation/losses  funding 738,550 738,550 738,550 738,550

‐1,694,475  ‐1,694,475  ‐1,694,475  ‐1,694,475 

Special Rate Variation 10/11  534,134 534,134 534,134 534,134

Reduced Debt/Contigent Budgets 550,000 550,000 550,000 550,000

Enviro. Sus. WaSIP funds 81,652 81,652 81,652 81,652

Walking Track Improvements 56,125 56,125 56,125 56,125

Living Catchments 22,379 22,379 22,379 22,379

Rate income provision 2012/13 104,000 104,000 104,000 104,000

Information Solutions 66,000 66,000 66,000 66,000

Leura Toilets (Land Sale Funding) 323,800 ‐323,800  0 0 0

FAG shortfall 2012/13 316,000 ‐316,000  0 0 0

Bi Centennial Crossing 90,000 90,000 90,000 90,000

Contigency (GM provision) 190,000 190,000 190,000 190,000

Rating Review ‐20,110  20,110 0 0 0

Contingent Budget 2012/13 150,000 150,000 150,000 150,000

Economic Development Contingent 2012/13 50,000 50,000 50,000 50,000

Asset renewal & maintenance 267,691 ‐40,000  227,691 227,691 227,691

Total Internally restricted 21,908,392 ‐2,969,065  ‐4,561,793  14,377,534 ‐325,000  14,052,534 14,052,534

Total Restricted 30,766,433 ‐3,730,654  ‐4,747,793  22,287,986 ‐325,000  21,962,986 21,962,986

Total cash and investments 30,766,433 22,287,986 21,962,986 22,492,986

Available cash 0 0 0 530,000

Notes:

The available cash position excludes restricted funds.  External restrictions are funds that must be spent for a specific purpose 

and cannot be used by council for general operations.  Internal restrictions are funds that council has determined will be used 

for a specific purpose.

This document forms part of Blue Mountains City Council's Quarterly Budget Review Statement (QBRS)for the quarter ended and should be

read in conjunction with other documents in the QBRS.

Approved Changes

Unfunded reserves ‐ investments downward 

devaluations

17

Page 19: July to September 2012...2012/11/27  · 2012-2013 QUARTER 1 REPORT July to September 2012 Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013

2012-2013 Quarter 1 Report

Budget  Review Contracts and Other Expenses for the quarter ended ‐ 30 September 2012

PART A: Contracts Listing

Contractor Contract detail & purposeContract value

$

Commencement 

date

Duration of 

contract

Budgted

(Y/N)

3M Australia Pty Ltd2 self checkout machines 

(Library)56,000 29/09/2012 1 month Y

CBD Traffic Control Laying 2 coat seal 67,400 24/09/2012 1 month Y

The Green Horticultural Group Renovations work at Lapstone 75,664 27/08/2012 1 month Y

Freeman Ryan Design Pty Ltd Cultural Centre ‐ Public Art  91,799 21/09/2012 1 month Y

Elarmcom Electrical Services Gloria Park lighting 75,097 6/07/2012 1 month Y

PART B ‐ Consultancy and Legal expensesExpenditure 

YTDBudgeted

Expense $ (Y/N)

Consultancies 213,010 Y

Legal Fees 110,837 Y

Note:

This document forms part of Blue Mountains City  Council's Quarterly Budget Review Statement (QBRS) for the quarter ended  

and should be ead in conjunction with other documents in the QBRS.

18


Recommended