2012-2013 QUARTER 1 REPORT July to September 2012
Reporting on the Implementation 2012-2013 Operational Plan (Year 3 of the Council’s 2010-2013 Delivery Program)
About This Report Page 1 Service Highlights Page 2 Other Issues Page 5 Quarterly Budget Review Statement Page 7
2012-2013 Quarter 1 Report
About this Report The provisions of Integrated Planning and Reporting under the Local Government Act, 1993 require that reports are provided to the Council on the progress in implementing the Delivery Program and Operational Plan as follows:
Budget review statement (quarterly);
Delivery Program progress report (6‐monthly); and
Annual report including audited financial reports (within 5 months of the end of each financial year).
This report provides the legislatively required budget review statement, as well as highlighting key achievements and any other issues to note for Quarter 1 of 2012‐2013 (July to September 2012).
The Purpose of Quarterly / Six‐Monthly Reports Quarterly and Six‐Monthly Reports have been designed:
To meet legislative requirements (transparency and accountability);
To provide a practical assessment of how the Council is tracking overall – whether we are delivering against our commitments on time and within budget; and
To demonstrate results / achievements and to formally document any issues that arise that impact on service delivery commitments.
How the Council will be assessing progress in 2012‐2013 Budget Review Statement The budget review statement must include details on the general financial position of the Council and if this position is regarded as unsatisfactory, also include recommendations for remedial action. The budget review statement will be provided to the Council as follows: Quarter 1 (July to September 2011) – reported in November 2012 Quarter 2 (October to December 2011) – reported in February 2013 Quarter 3 (January to March 2013) – reported in May 2013 Quarter 4 (April to June 2013) – reported in August 2013
Delivery Program and Operational Plan progress report The method for assessing progress in implementing the Council’s Delivery Program and Operational Plan includes: Action / project progress – tracking whether actions / projects are being delivered as planned
on time and within budget (reported every six months) Other service measures – used to measure specific results achieved by different services
(reported at the end of the financial year) Quantitative Quadruple Bottom Line (QBL) measures – used to measure Council’s
environmental, social, financial and governance performance against the Key Direction of Providing Good Government (reported at the end of the financial year)
Qualitative Community Survey – used to measure perceptions of key stakeholders on service performance results (reported at the end of the financial year)
Quantitative asset based measures – used to measure actual improvement in built asset condition e.g. roads, footpaths, pools (reported at the end of the council term)
Progress on the implementation of the 2010‐2013 Delivery Program and 2012‐2013 Operational Plan will be provided to the Council as follows: First six months (July to December 2012) – reported in February 2013 Final six months (January to June 2013) – reported in August 2013
1
2012-2013 Quarter 1 Report
SERVICE HIGHLIGHTS Child Care
The Family Day Care service achieved an outstanding result in the NSW Department of Education and Communities assessment of the service against the National Quality Standard.
Community Development and Cultural Development Public exhibition of the Development Application for the Springwood Community and
Cultural Facilities Upgrade commenced on 11 July 2012 for a 30 day period. The DA will be assessed and determined by the Joint Regional Planning Panel, which is an external and independent body to the Council. The revised timing of the construction tender from late 2012 to mid‐January 2013 due to requirements for further work including a Value Management process and car parking study in the schematic design process, was endorsed by the Council at the 28 August 2012 Council meeting.
Corporate Strategic Planning and Reporting The Council is legislatively required to prepare a number of reports on Council
progress in implementing its plans. The 2011‐2012 End‐of‐Year Report and 2008‐2012 End of Council Term Report were presented to the 28 August Council meeting highlighting the achievements of the outgoing Council. The 2012 Community Survey Report was also presented to the 28 August 2012 Council Meeting with the Council scoring the highest community satisfaction rating with overall Council performance since 1996.
Cultural Development The Council endorsed the 2012 funding recommendations for the Cultural
Partnerships Program at the 7 July 2012 Council Meeting.
Cultural Development: The Blue Mountains Cultural Centre was progressed:
- All Management and Officer positions for the Blue Mountains Cultural Centre were filled.
- The Operational program for the Blue Mountains Cultural Centre was set for the forward 12 months.
- Facebook Friends grown to 175 friends. - 13 merchandise lines were designed and manufactured for the Blue Mountains
Cultural Centre Shop. - 2 corporate sponsorships activated. - Opening exhibition catalogue designed and sent to print.
Economic Development and Tourism The Council appointed board members to the Blue Mountains Economic Enterprise
Limited at the 7 August 2012 Council Meeting. The economic development entity is an initiative of the Council and will focus on generating ideas and initiatives for economic growth and jobs creation across the region.
WiFi was implemented at the Glenbrook and Katoomba Visitor Information Centres.
2
2012-2013 Quarter 1 Report
Hazelbrook toilet
Environmental Sustainability A review of Council systems and processes in place to comply with Part 5 Assessment
in relation to environmental matters was undertaken with initial revised processes now in place.
The Blue Mountains Bushcare’s Big Day Out was held on Sunday 9 September at Central Park, Falls Road, Wentworth Falls. A range of activities were held including a bird walk with botanist and bird enthusiast, Jill Dark, planting, weed removal, mulching, pruning and a site walk and a well celebrated morning tea. This event was sponsored by the Council as part of national Landcare Week.
Human Resources Bullying / Harassment workshops were provided to all staff.
Land Use Management Certification services were reviewed by the Building Professionals Board (BPB). The
BPB representative noted that the Council’s procedures and practices were of a high standard and recognised its monitoring and reporting systems as the first to be found to be fully compliant with its obligations under the Building Professionals Act.
Libraries and Information A number of library events were held including:
- Annual ABC 702 Knit In - Children's Book Cover Art competition - Springwood Library hosted an introduction to Family History resources in
collaboration with the Blue Mountains Family History Society (27 people attended) during Family History Week
Sport and Recreation The Plan of Management for Batman Reserve, Springwood was adopted at the 7
August 2012 Council Meeting.
The new Glenbrook Pool filtration plant is operational and the pool opened on time with a free community open day on Saturday 6 October 2012. The new filtration plant will improve water quality and clarity and the new heating system will maintain the water temperature at a comfortable 27degrees. Mayor, Councillor Daniel Myles utlisised a promotional YouTube video that provided the community and pool users with detailed information on the upgrade and its benefits.
Town Centres The new public toilet facility at
Hazelbrook was opened by Blue Mountains City Council on Monday 20 August 2012. The facility is a modern design that includes an accessible toilet, a baby change table with easy access from the shopping precinct. The new toilet block has a rainwater capture system that enables the re‐use of water for toilet flushing and landscape watering and includes an on‐line flushing system to save water. Also, the building panels have an anti graffiti coating.
3
2012-2013 Quarter 1 Report
Mayor, Cr Daniel Myles and Cr Chris Van der Kley inspect the Council’s road sealing trial in Duperry St, north Wentworth Falls
Transport and Public Access The Council endorsed the use of electronic vehicle detection technology for managing
parking in appropriate circumstances at the 7 July Council Meeting. This decision was based on a trial of the detection technology in Leura in response to requests from the Leura Village Association. The aim of the technology is to increase turnover of vehicles consistent with the existing time limited signs, to promote a more equitable use of the parking resource.
The Sealing of Unsealed Roads Program commenced. This comprehensive road sealing program of selected gravel roads in the mid and lower mountains aims to reduce ongoing road maintenance costs as well as eliminating sediment run off and also providing improved amenity for residents.
This Council hosted Bike Week for Little Kids in September in Glenbrook Park, partnering with Lower Mountains Neighbourhood Centre, Gateway Family Services,
Mountains Outreach Community Service, Connect Child and Family Services and the Getting Around In Community Project to deliver a bigger and better Bike Week. Bike Week activities provided information and instruction on bike safety, riding skills and the enjoyment of cycling.
Water Resource Management The Council was successful in its grant application for the 2012‐2013 Floodplain
Management Program ‐ South Lapstone, South Glenbrook and South Blaxland Floodplain Risk Management Study & Plan $80,000 and Hazelbrook and Woodford Creeks Catchment Overland Flow Path Study $19,467.
4
2012-2013 Quarter 1 Report
Fire and Rescue NSW Hazardous Material team assist with the removal of contaminated material from a stormwater basin as part of the Jamison Creek pollution incident clean up effort.
ISSUES TO NOTE
City‐wide Strategic Planning At the 7 August Council Meeting, the Council considered the requirement of the NSW
Government that BMCC commit to a timetable to implement the Standard Instrument Local Environmental Plan within the Blue Mountains by mid 2013. This latest directive from the Minister for Planning and Infrastructure presents very real challenges to the Council and community. The sustained focused effort necessary to implement the drafting of the Local Environmental Plan to meet the requirements of the NSW Government will require re‐allocation of resources, which is likely to affect the planned work programs and services contained within the adopted Delivery and Operational Plan and may also require additional resources. This will be further considered in Quarter 2.
The NSW Government has invited submissions to ‘A New Planning System for NSW Green Paper’. The Green Paper for the reform of the NSW Planning system represents the most significant review of the planning legislation for a generation. At the 25 September 2012 Council Meeting, the Council agreed to make a submission to the Green Paper. It is the case, that the Blue Mountains is a highly complex planning environment, and one with a community with high expectations for the quality of the built environment and the protection of important places. It will be important that the Council maintain its focus as the reform process unrolls and concludes, to ensure that the values of the Blue Mountains and the expectations of its community are met now and in the longer term.
Cultural Development
The funding of the Bicentenary Crossing events was considered at the 28 August 2012 Council meeting. Funding of $90,000 for the three Council‐managed events ‐ the Government House Reception, ‘Top of Town’ in Katoomba, and ’21 Days on the Mountain’ – was identified from within the 2011‐2012 operating surplus.
Environmental Sustainability After a mass die‐off of freshwater crayfish,
native fish and other macro‐invertebrates (water bugs) was reported by a bushwalker, the Council commenced investigations into the incident immediately. An inspection by Council staff found hundreds of crayfish, both adult and juvenile, dead or dying in the creek, extending from the Great Western Highway through to the waterfall at Wentworth Falls. The NSW Department of Primary Industries Fisheries Division (DPI), the Environmental Protection Agency (EPA) and NPWS continued the investigation with support from the Council. The Environmental Protection Authority (EPA), identified the contaminant as a termiticide, a pesticide commonly used for termite control. Test results suggest the contaminant entered the creek via the stormwater outlet in Wilson Park, Wentworth Falls. The Council, with the assistance of the Fire and Rescue NSW hazardous material team, coordinated the removal of contaminated sediment from a stormwater basin located on private land last week, as a matter of urgency, to prevent further
5
2012-2013 Quarter 1 Report
contamination of Jamison Creek. The Council commenced investigations into the potential cause of the pollution and will continue regular monitoring of the water quality and macro‐invertebrates (waterbugs) in Jamison Creek to assess ongoing impacts of the contamination and the rate of recovery.
Governance The Council elections on 8 September were successfully held with the election of eight
new Councillors and four Councillors re‐elected from the previous term. The Council has provided the Councillors with a number of induction sessions.
Emergency Management
The Council considered the NSW State Government’s review of emergency services funding at the 28 August 2012 Council Meeting. The Council endorsed a submission being made based on the following themes:
a) that Council supports the introduction of a broad‐based property levy as the State’s source of funding for emergency services, provided this replaces the current 11.7% statutory contributions made by Council;
b) that Council’s preference is that the broad‐based property levy is applied as a flat rate per property and that some exemption is established for lands owned, vested in, or under the care, control and management of Council;
c) that the State recognises that Blue Mountains City Council has significant risk and asset management obligations as a major land manager of a City within a fire‐prone, World Heritage area, and that Council should continue to be able to levy associated costs from ratepayers through the Emergency Services Annual Charge (ESAC); and
d) that any broad‐based property levy is collected by the Office of State revenue, or if collected by Council on behalf of the State, that this be on a fee for service basis.
6
2012-2013 Quarter 1 Report
Quarterly Budget Review Statement by the Responsible Accounting Officer In accordance with the Local Government Act, 1993 and the provisions of clause 9 of the Financial Management Regulation, a budget review statement and revision of estimates must be completed and submitted to the Council for formal adoption at the end of each financial quarter. This report must include details on the general financial position of the Council and if this position is regarded as unsatisfactory, also include recommendations for remedial action.
The following information details the budget review statement to the end of September 2012 in accordance with the requirements of the legislation. The Department of Local Government has issued guidelines for the minimum requirements of Quarterly Budget Review Statements. The minimum requirements are mandatory from 1 July 2011. The statements included in the budget review statement by the responsible accounting officer comply with the minimum requirements of the Department of Local Government.
Working Capital Result The Council’s Working Capital Result is a financial measure that highlights the Council’s ability to satisfy financial obligations in the short term. The Working Capital Position is defined as the net amount of uncommitted funds available to the Council in the next 12 month period and importantly it excludes non‐cash items like depreciation. A surplus indicates how much uncommitted funds the Council has provided to account for cash tied up in inventory and long outstanding debts. The Council aims to maintain an optimum level of working capital of around $1.7 million to $1.8 million. The Council’s Working Capital for the year ended 30 June 2012 was a surplus of $1.862 million. An analysis of actual results and revised projections as at September 2012 Quarter has resulted in no change to the projected working capital position and therefore the position is maintained at $1.862 million projected to 30 June 2013. Subject to the Council adopting the recommended variations, the estimated effective working capital of $1,862,000 is maintained within the calculated optimum level. The following reconciliation illustrates the projected Working Capital position as at the 30 June 2013 review.
7
2012-2013 Quarter 1 Report
Table 1
Actual Working Capital Result– 1 July, 2012 1,862,000
Original Budget 2012‐2013 Forecast Improvement in Working Capital 0
September 2012 Review 0
Revised Estimated Working Capital Result– 30 June 2013 1,862,000
Revised Estimated Working Capital Result– 30 June 2013. Working Capital is the net amount of uncommitted funds consisting of:
Estimated
2012‐2013
Unrestricted current cash 2,757,000
Current receivables 5,905,000
Inventories 400,000
Prepayments 300,000
Payables (excluding liabilities budgeted next year 2013‐2014) (7,500,000)
Total 1,862,000
Operational Budget – Significant Variations There are no significant variations to the Operational Budget for Quarter 1. CAPITAL WORKS PROGRAM SUMMARY Total 2012‐2013 budget* $28,836,773
Total Dollars spent as at 30 September 2012 $1,909,754
Percentage spent 6.6%
Percentage of projects on target or completed 98%*Includes funding carried over from 2011‐2012, recommended / adopted variations and capital funding for Major Projects. Excludes IT assets and plant and equipment.
Note that whilst expenditure of 6.6% is relatively low, this is generally consistent with the planning, project brief development and procurement phases of most capital projects in Quarter 1.
Capital Works Program – Significant Variations The following variations relating to capital projects are recommended.
Increase/Decrease to Capital Works Program Variation
Heatherbrae house improvements stage 2 (funding from restricted asset) $325,000
Cultural Centre new library and fit‐out (funding from library development grant $200k and library special purpose grant $114k)
$314,000
Footpath upgrade Katoomba Street Katoomba, Minute No. 169, 23 April 2012 (funding from Section 94 restricted asset)
$186,000
Total 825,000
8
2012-2013 Quarter 1 Report
Cash Flow The Council’s cash position has increased by $0.87 million from a balance of $32.97 million at 30 June 2012 to a balance of $33.84 million at 30 September 2012 as presented below.
Loan Position The Council’s outstanding loan position as at 30 June 2012 was $48.06 million. At the end of September 2012 the loan position stands at $47.98 million. The figure below indicates that the total loan balance will increase from $48.06 million from 30 June 2012 to $60.20 million at 30 June 2013. The new borrowings in 2012‐2013 are $15.6 million and in 2013‐2014 $8.31 million, and then projected at $2.31 million per annum each year thereafter. The total balance decreases to $55.53 million by 2017‐2018. Loans are raised over the period to fund the following major projects:
Cultural Centre, Library and Civic Centre $5.3 million
Lawson Town Centre $4.4 million
Katoomba Waste Transfer Station $8.8 million
Blaxland Waste Facility $6.1 million
Local Infrastructure Renewal Scheme $10.86 million
9
2012-2013 Quarter 1 Report
The figures in the previous graph are in accordance with the Council’s 2011‐2021 Long Term Financial Plan and include the latest anticipated loan funding required for the Cultural Centre, Lawson Town Centre, Waste Transfer Station, Blaxland Waste Facility and Local Infrastructure Renewal Scheme projects. Measuring the Council’s Financial Performance The following series of measures are being used to monitor and report on the Council’s financial performance. Results for these measures will be provided at the end of the financial year.
Operating Result from Continuing Operations ‐ Total operating revenue less total operating expenses (including depreciation and excluding capital grants, capital expenditure and capital movements)
Operating Balance Ratio – Operating result from continuing operations divided by operating revenue
Unrestricted Working Capital – Unrestricted current assets less unrestricted current liabilities
Current Ratio (Unrestricted) – Current Assets less Externally Restricted Current Assets divided by Current Liabilities less Specific Purpose Current Liabilities
Rates & Annual Charges Coverage Ratio – Rates and annual charges as a percentage of operating revenue
Rates and Annual Charges Outstanding – Rates and annual charges outstanding as a percentage of Rates and annual charges collectible
Asset Renewal Ratio (Buildings & Infrastructure) – Asset Renewals (Buildings & Infrastructure) divided by Depreciation, Amortisation & Impairment (Buildings & Infrastructure)
Asset Renewal Gap ratio – Estimated Required Asset Renewal Expenditure divided by Current renewal expenditure on assets
Debt Service Ratio – Interest divided by Operating Revenue
10
2012-2013 Quarter 1 Report
Report by Responsible Accounting Officer
The following statement is made in accordance with Clause 203(2) of the LocalGovernment (General) Regulations 2005.
It is my opinion that the Quarterly Budget Review Statement for Blue Mountains City Council forthe quarter ended 30 September 2012 indicates that Council’s projected financial position at30/6/2013 will be satisfactory at year end, having regard to theprojected estimates of income and expenditure and the original budgetedincome and expenditure.
Signed:
Responsible Accounting Officer
Date: 26 October 2012
11
2012-2013 Quarter 1 ReportIncome & Expense- General Fund Budget Review Statement for the quarter ended - 30 September 2012
R'meded Projected
Original changes year end
Budget Revised for Council result Actual
Review
(carry‐over) Review Budget Resolution YTD
Income
Rates and Annual Charges 55,608,609 562,422 56,171,031 56,171,031 56,073,687
User Charges and Fees 14,910,352 14,910,352 14,910,352 3,202,716
Interest and Investment Revenue 1,632,629 1,632,629 1,632,629 408,344
Other Revenues 4,340,663 4,340,663 4,340,663 910,727
Grants & Contributions ‐ Operating 11,578,339 ‐4,493,573 7,084,766 7,084,766 1,621,860
Grants and Contributions ‐ Capital 5,503,090 2,855,567 8,358,657 8,358,657 305,179
Net gain from the disposal of assets 420,380 420,380 420,380 82,744
Share of interests in joint ventures 0 0
Total Income from continuing
operations 93,994,062 2,855,567 ‐3,931,151 92,918,478 0 92,918,478 62,605,257
Employee costs 43,295,685 175,048 43,470,733 43,470,733 10,327,392
Borrowing Costs 3,382,546 3,382,546 3,382,546 636,034
Materials & Contracts 18,554,161 816,455 34,560 19,405,176 19,405,176 4,279,744
Depreciation 33,600,000 33,600,000 33,600,000 7,112,642
Legal Costs 722,500 722,500 722,500 110,837
Consultants 678,270 135,419 813,689 813,689 213,010
Other Expenses 11,931,215 9,228 11,940,443 11,940,443 3,462,437
Interest and Investment Losses 0 0
Net Loss from Disposal of Assets 0 0
Share of interests in joint ventures 0 0
Total Expense from continuing
operations 112,164,377 1,136,150 34,560 113,335,087 0 113,335,087 26,142,096
Net Operating Result from
continuing operations ‐ Surplus
(Deficit) ‐18,170,315 1,719,417 ‐3,965,711 ‐20,416,609 0 ‐20,416,609 36,463,161
Net Operating Result before
capital items ‐ Surplus(Deficit) ‐23,673,405 ‐1,136,150 ‐3,965,711 ‐28,775,266 0 ‐28,775,266 36,157,982
Statement of Financial Position (including Capital Movements for Year)
Net Operating Result from
continuing operations ‐18,170,315 1,719,417 ‐3,965,711 ‐20,416,609 0 ‐20,416,609 36,463,161
Movements in Restricted Assets ‐ 0
Transfer from 7,824,708 12,201,311 4,148,711 24,174,730 24,174,730 7,344,098
Sale of Assets 1,512,031 1,512,031 1,512,031 404,681
Capital Acquisitions 21,300,424 13,920,728 183,000 35,404,152 35,404,152 2,531,454
Loan/Lease Repayments 3,466,000 3,466,000 3,466,000 75,103
Non Cash Budget for Depreciation 33,600,000 33,600,000 33,600,000 7,112,642
Change in Working Capital 0 0 0 0 0 0 48,718,025
Notes:
This document forms part of Blue Mountains City Council's Quarterly Budget Review Statement (QBRS) for the quarter ended and should
be read in conjunction with other documents in the QBRS.
Approved Changes
12
2012-2013 Quarter 1 Report
Income & Expense‐ Activities Budget Review Statement for the quarter ended ‐ 30 September 2012
R'mended Projected
Original changes year end
Budget Revised for Council result Actual
Review
(carryover) Review Budget Resolution YTD
Income
Looking after the Environment
‐ Environmental Sustainability 2,427,480 2,427,480 2,427,480 614,701
‐ Water Resource Management 25,152 25,152 25,152 0
‐ Waste Resource Management 19,479,256 19,479,256 19,479,256 13,637,052
Looking after People
‐ Child Care 1,361,243 1,361,243 1,361,243 462,072
‐ Community Development 1,009,226 1,009,226 1,009,226 478,330
‐ Emergency Management 2,429,425 2,429,425 2,429,425 1,748,818
‐ Cultural Development 658,081 658,081 658,081 185,048
‐ Environmental Health & Reg. Compliance 480,806 480,806 480,806 371,136
‐ Libraries & Information 396,831 396,831 396,831 37,805
‐ Sport & Recreation 5,469,364 5,469,364 5,469,364 877,985
Using Land and Moving Around
‐ Burial & Ashes Placement 365,828 365,828 365,828 85,943
‐ Land Use Management 1,484,170 1,484,170 1,484,170 444,214
‐ Town Centres 253,372 253,372 253,372 24,522
‐ Transport & Public Access 2,640,082 2,640,082 2,640,082 51,998
Sustainable Economy
‐ Economic Development & Tourism 1,754,559 1,754,559 1,754,559 329,755
Governance & Corporate Support 15,795,379 15,795,379 15,795,379 5,184,830
Non Attributable 53,490,871 53,490,871 53,490,871 49,518,721
Total Income 109,521,125 0 0 109,521,125 0 109,521,125 74,052,930
Approved Changes
13
2012-2013 Quarter 1 ReportIncome & Expense‐ Activities Budget Review Statement for the quarter ended ‐ 30 September 2012 continued
R'meded Projected
Original changes year end
Budget Revised for Council result Actual
Review
(carryover) Review Budget Resolution YTD
Expense
Looking after the Environment
‐ Environmental Sustainability 4,356,045 4,356,045 4,356,045 899,033
‐ Water Resource Management 374,835 374,835 374,835 155,221
‐ Waste Resource Management 19,482,512 19,482,512 19,482,512 4,219,441
Looking after People
‐ Child Care 1,693,183 1,693,183 1,693,183 454,544
‐ Community Development 3,524,125 3,524,125 3,524,125 817,172
‐ Emergency Management 3,364,295 3,364,295 3,364,295 1,249,356
‐ Cultural Development 2,095,610 2,095,610 2,095,610 272,263
‐ Environmental Health & Reg. Compliance 2,258,998 2,258,998 2,258,998 682,205
‐ Libraries & Information 2,684,781 2,684,781 2,684,781 603,053
‐ Sport & Recreation 11,091,125 11,091,125 11,091,125 2,260,522
Using Land and Moving Around
‐ Burial & Ashes Placement 683,584 683,584 683,584 21,389
‐ Land Use Management 4,189,130 4,189,130 4,189,130 733,445
‐ Town Centres 4,077,662 4,077,662 4,077,662 376,049
‐ Transport & Public Access 9,627,344 9,627,344 9,627,344 1,523,134
Sustainable Economy
‐ Economic Development & Tourism 2,752,345 2,752,345 2,752,345 539,535
Governance & Corporate Support 30,182,176 30,182,176 30,182,176 9,757,133
Non Attributable 7,083,375 7,083,375 7,083,375 771,410
0 0
Total Expense 109,521,125 0 0 109,521,125 0 109,521,125 25,334,905
Notes:
This document forms part of Blue Mountains City Council's Quarterly Budget Review Statement (QBRS)for the quarter ended and should be
read in conjunction with other documents in the QBRS.
Approved Changes
14
2012-2013 Quarter 1 Report
Capital Budget Review Statement for the quarter ended ‐ 30 September 2012
R'mended Projected
Original changes year end
Budget Revised for Council result Actual
Review
(carry‐over) Review Budget Resolution YTD
Capital Funding
Rates and other untied funding 4,515,760 4,515,760 4,515,760 153,641
Capital Grants & Contributions 5,503,090 2,855,567 8,358,657 314,000 8,672,657 305,179
Internal Restrictions
‐ renewals 2,089,401 410,000 2,499,401 325,000 2,824,401
‐ new assets 1,030,000 2,320,057 3,350,057 3,350,057
‐ plant replacement 3,451,852 3,451,852 3,451,852
‐ Waste Facilities debt servicing 262,865 262,865 262,865
External Restrictions
‐ infrastructure levy 0 0
‐ Developer Contributions 345,000 341,317 686,317 186,000 872,317
‐ Specific Purpose Grants 0 0 0
Other Capital Funding Sources 0 0
‐ loans 5,967,425 7,149,916 13,117,341 13,117,341 1,604,576
Income from sale of assets
‐ plant and equipment 1,512,031 1,512,031 1,512,031 404,681
‐ land and buildings 0 0 0
Total Capital Funding 24,677,424 13,076,857 0 37,754,281 825,000 38,579,281 2,468,077
Capital Expenditure
R'meded Projected
Original changes year end
Budget Revised for Council result Actual
Review
(carry‐over) Review Budget Resolution YTD
New Assets 0 0
‐ Plant and Equipment 976,244 976,244 976,244 258,314
‐ Land and Buildings 5,040,000 5,600,464 10,640,464 314,000 10,954,464 1,195,363
‐ Roads, Bridges, Footpaths & Other 5,119,425 3,909,049 9,028,474 9,028,474 196,549
Renewals (Replacement) 0 0
‐ Plant and Equipment 5,389,264 5,389,264 5,389,264 224,905
‐ Land and Buildings 475,000 1,856,186 2,331,186 325,000 2,656,186 271,380
‐ Roads, Bridges, Footpaths & Other 4,300,491 1,711,158 6,011,649 186,000 6,197,649 246,463
Loan Repayments (principal) 3,377,000 3,377,000 3,377,000 75,103
Total Capital Expenditure 24,677,424 13,076,857 0 37,754,281 825,000 38,579,281 2,468,077
Notes:
This document forms part of Blue Mountains City Council's Quarterly Budget Review Statement (QBRS)for the quarter ended and should be
read in conjunction with other documents in the QBRS.
Approved Changes
Approved Changes
15
2012-2013 Quarter 1 ReportCash and Investments Budget Review Statement for the quarter ended - 30 June 2013
note: original budget is movement 2012/2013 plus opening balance at 30 June 2012
R'meded Projected
Original changes year end
Budget Revised for Council result Actual
(incl b/fwd
balance)
Review &
carry‐over Review Budget Resolution YTD
Unrestricted 0 0 530,000
Externally restricted
RTA contributions 140,287 ‐40,000 100,287 100,287 100,287
Developer contributions 50,894 ‐341,317 ‐186,000 ‐476,423 ‐476,423 ‐476,423
Other contributions 144,240 144,240 144,240 144,240
Domestic waste management 195,369 ‐71,824 123,545 123,545 123,545
Rural Fire Service 125,460 125,460 125,460 125,460
Special rates 53,968 ‐21,996 31,972 31,972 31,972
Unexpended loans 3,151,158 3,151,158 3,151,158 3,151,158
Special purpose grants 4,996,665 ‐286,452 4,710,213 4,710,213 4,710,213
Total Externally restricted 8,858,041 ‐761,589 ‐186,000 7,910,452 0 7,910,452 7,910,452
Internally restricted
Employee leave entitlements 3,157,422 3,157,422 3,157,422 3,157,422
Replacement of plant and vehicles 622,147 622,147 622,147 622,147
Waste bins 364,154 364,154 364,154 364,154
Waste ‐ Blaxland Waste Facility 311,726 311,726 311,726 311,726
Tip improvements 994,977 994,977 994,977 994,977
Waste Management ‐ Carbon Pricing Works 0 562,422 562,422 562,422 562,422
Pay & display 1,166,503 ‐25,752 1,140,751 1,140,751 1,140,751
Elections 400,332 400,332 400,332 400,332
Environmental levy 627,789 ‐625,000 2,789 2,789 2,789
Property investment fund 1,707,913 1,707,913 1,707,913 1,707,913
Property fund (Heatherbrae) 325,500 325,500 ‐325,000 500 500
Property fund (Lawson town centre) 474,500 ‐474,500 0 0 0
Katoomba civic centre/cultural centre 1,321,216 ‐1,321,261 ‐45 ‐45 ‐45
Family day care 166,186 166,186 166,186 166,186
Loan repayments debt servicing 699,000 699,000 699,000 699,000
Workers compensation insurance 1,602,289 1,602,289 1,602,289 1,602,289
Insurance PR & PI 66,000 66,000 66,000 66,000
Operational improvement initiatives 35,485 35,485 35,485 35,485
Telephone/Information Systems 215,865 215,865 215,865 215,865
Local committees ‐ halls & other 385,118 385,118 385,118 385,118
Printing equipment 49,718 49,718 49,718 49,718
Floodplain risk mngt study & plan 40,000 40,000 40,000 40,000
Works carried forward 809,504 ‐809,504 0 0 0
Cemeteries Improvements 35,835 35,835 35,835 35,835
Major capital projects 5,571 5,571 5,571 5,571
Sports field fees 163,096 163,096 163,096 163,096
Approved Changes
16
2012-2013 Quarter 1 ReportCash and Investments Budget Review Statement for the quarter ended - 30 June 2013 continued
R'meded Projected
Original changes year end
Budget Revised for Council result Actual
(incl b/fwd
balance) Review Review Budget Resolution YTD
RTA Agency Further Works 74,683 74,683 74,683 74,683
Rental on crown lands 82,544 82,544 82,544 82,544
FAG in advance 4,177,573 ‐4,177,573 0 0 0
Investments devaluation/losses funding 738,550 738,550 738,550 738,550
‐1,694,475 ‐1,694,475 ‐1,694,475 ‐1,694,475
Special Rate Variation 10/11 534,134 534,134 534,134 534,134
Reduced Debt/Contigent Budgets 550,000 550,000 550,000 550,000
Enviro. Sus. WaSIP funds 81,652 81,652 81,652 81,652
Walking Track Improvements 56,125 56,125 56,125 56,125
Living Catchments 22,379 22,379 22,379 22,379
Rate income provision 2012/13 104,000 104,000 104,000 104,000
Information Solutions 66,000 66,000 66,000 66,000
Leura Toilets (Land Sale Funding) 323,800 ‐323,800 0 0 0
FAG shortfall 2012/13 316,000 ‐316,000 0 0 0
Bi Centennial Crossing 90,000 90,000 90,000 90,000
Contigency (GM provision) 190,000 190,000 190,000 190,000
Rating Review ‐20,110 20,110 0 0 0
Contingent Budget 2012/13 150,000 150,000 150,000 150,000
Economic Development Contingent 2012/13 50,000 50,000 50,000 50,000
Asset renewal & maintenance 267,691 ‐40,000 227,691 227,691 227,691
Total Internally restricted 21,908,392 ‐2,969,065 ‐4,561,793 14,377,534 ‐325,000 14,052,534 14,052,534
Total Restricted 30,766,433 ‐3,730,654 ‐4,747,793 22,287,986 ‐325,000 21,962,986 21,962,986
Total cash and investments 30,766,433 22,287,986 21,962,986 22,492,986
Available cash 0 0 0 530,000
Notes:
The available cash position excludes restricted funds. External restrictions are funds that must be spent for a specific purpose
and cannot be used by council for general operations. Internal restrictions are funds that council has determined will be used
for a specific purpose.
This document forms part of Blue Mountains City Council's Quarterly Budget Review Statement (QBRS)for the quarter ended and should be
read in conjunction with other documents in the QBRS.
Approved Changes
Unfunded reserves ‐ investments downward
devaluations
17
2012-2013 Quarter 1 Report
Budget Review Contracts and Other Expenses for the quarter ended ‐ 30 September 2012
PART A: Contracts Listing
Contractor Contract detail & purposeContract value
$
Commencement
date
Duration of
contract
Budgted
(Y/N)
3M Australia Pty Ltd2 self checkout machines
(Library)56,000 29/09/2012 1 month Y
CBD Traffic Control Laying 2 coat seal 67,400 24/09/2012 1 month Y
The Green Horticultural Group Renovations work at Lapstone 75,664 27/08/2012 1 month Y
Freeman Ryan Design Pty Ltd Cultural Centre ‐ Public Art 91,799 21/09/2012 1 month Y
Elarmcom Electrical Services Gloria Park lighting 75,097 6/07/2012 1 month Y
PART B ‐ Consultancy and Legal expensesExpenditure
YTDBudgeted
Expense $ (Y/N)
Consultancies 213,010 Y
Legal Fees 110,837 Y
Note:
This document forms part of Blue Mountains City Council's Quarterly Budget Review Statement (QBRS) for the quarter ended
and should be ead in conjunction with other documents in the QBRS.
18