Date post: | 15-Dec-2015 |
Category: |
Documents |
Upload: | adriana-worthington |
View: | 217 times |
Download: | 3 times |
June 17 and 19, 2008June 17 and 19, 2008
11
Luce Township Luce Township Regional Sewer Regional Sewer
District Community District Community ForumsForums
Welcome and Welcome and purposepurpose Review the facts and answer questions Review the facts and answer questions
that residents have about the proposed that residents have about the proposed sewerage system.sewerage system.
Review the feasibility of using an Review the feasibility of using an alternative wastewater treatment options.alternative wastewater treatment options.
Share some recommendations for moving Share some recommendations for moving forward.forward.
Identify the key challenges that residents Identify the key challenges that residents have.have.
22
The TeamThe Team
Contracted by the Spencer County Chamber of Contracted by the Spencer County Chamber of CommerceCommerce
USI Center for Applied ResearchUSI Center for Applied Research– Sue Ellspermann, PhDSue Ellspermann, PhD– 20+ years facilitation experience20+ years facilitation experience
USI Dept of EngineeringUSI Dept of Engineering– Dr. Mamun Rashid, PhD in Civil and Environmental Dr. Mamun Rashid, PhD in Civil and Environmental
Engineering from U of Utah and experience working for 4 Engineering from U of Utah and experience working for 4 engineering firms.engineering firms.
Thanks to all who shared information including the Thanks to all who shared information including the LTRSD Board, Commonwealth Engineering, Bernardin LTRSD Board, Commonwealth Engineering, Bernardin Lochmueller, and interested community members.Lochmueller, and interested community members.
33
Our AgendaOur Agenda
6:45 History of the Luce Township Sewer 6:45 History of the Luce Township Sewer
Project (Grady)Project (Grady)
Q&AQ&A
7:00 Engineering Design review, insights 7:00 Engineering Design review, insights
and recommendations (Dr. Rashid)and recommendations (Dr. Rashid)
Q&AQ&A
8:008:00 Community ProcessCommunity Process
8:30 Closing comments and next steps 8:30 Closing comments and next steps
44
What do you see?
GroundrulesGroundrules There will be differing perspectives There will be differing perspectives
represented tonight.represented tonight. Listening to one another carefully.Listening to one another carefully. Please do not “kill” each others’ ideas Please do not “kill” each others’ ideas
and comments.and comments. Try to hold Q&A to the end of each Try to hold Q&A to the end of each
presentation.presentation. However, if you need us to clarify along However, if you need us to clarify along
the way, let us know.the way, let us know.
66
History of the projectHistory of the projectQ&AQ&A
77
88
Analysis of Wastewater Analysis of Wastewater Management OptionsManagement Options
LUCE Township Regional Sewer LUCE Township Regional Sewer District District
Presented by: Presented by:
Dr. Mamunur RashidDr. Mamunur Rashid
Community Forums – South Spencer High Community Forums – South Spencer High SchoolSchool
June 17 and 19, 2008 June 17 and 19, 2008
99
OUTLINEOUTLINE
Background - key issues, alternatives to consider Background - key issues, alternatives to consider Overview of PER & feasibility study Overview of PER & feasibility study Fact sheet – septic tank & soil absorption systemFact sheet – septic tank & soil absorption system Soil & Water Quality conditions – NRCS/Dr. David Soil & Water Quality conditions – NRCS/Dr. David
Ralston studyRalston study Alternatives (Eco-treatment wetland) – Fulda Alternatives (Eco-treatment wetland) – Fulda
typetype Proposed solution to wastewater managementProposed solution to wastewater management Summary, conclusionsSummary, conclusions
1010
KEY ISSUES/FRAMEWORKKEY ISSUES/FRAMEWORK
Wastewater management challenges in Wastewater management challenges in LTRSDLTRSD
Economics, feasibility, cost effectivenessEconomics, feasibility, cost effectiveness Preliminary Engineering Report (PER) by Preliminary Engineering Report (PER) by
Commonwealth EngineersCommonwealth Engineers Feasibility study by Bernardin LochmuellerFeasibility study by Bernardin Lochmueller Real concerns about cost: cost-effectiveness Real concerns about cost: cost-effectiveness
of proposed sanitary sewerage system of proposed sanitary sewerage system Willingness for moving forward Willingness for moving forward
1111
ALTERNATIVESALTERNATIVES
Do nothing Do nothing - allow the existing septic - allow the existing septic tank and absorption system to exist, tank and absorption system to exist, let them deterioratelet them deteriorate
Implement sanitary sewerage Implement sanitary sewerage alternative alternative designed by designed by Commonwealth EngineersCommonwealth Engineers
Consider other alternatives such as: Consider other alternatives such as: – Eco-treatment Wetland - as used in FuldaEco-treatment Wetland - as used in Fulda
1212
PER FINDINGSPER FINDINGS
Existing system deficiencies: Existing system deficiencies: – System constructed prior to soil evaluation System constructed prior to soil evaluation
requirementrequirement– Many systems have direct connections to Many systems have direct connections to
surface water bodiessurface water bodies– Soil conditions/high groundwater levels do not Soil conditions/high groundwater levels do not
allow for the repair/rehabilitation of most of the allow for the repair/rehabilitation of most of the system within current regulationssystem within current regulations
– Approximately 13 project locations are designated as 100-year floodplains
4 wastewater treatment alternatives 4 wastewater treatment alternatives were identifiedwere identified
1313
PER RECOMMENDATIONSPER RECOMMENDATIONS
Alternative C – 3 (all areas and treatment
at Rockport) appears to be cost-effective No significant negative environmental
impact is expected Right-of-way/Easement acquisition will be
required Purchase of land for lift station will be
necessary Easement for sewer lines/grinder pumps
necessary Inter-local agreement will be necessary
1414
FEASIBILITY STUDY FEASIBILITY STUDY (Bernardin Lochmuehler)(Bernardin Lochmuehler)
Findings/Recommendations – 90% of County soils are unsuitable to
septic systems– Most existing septic systems failed or are
failing– Discard existing septic systems to
eliminate non-point source pollution– Provide wastewater collection and
treatment facilities– Use “Regionalization” approach
1515
SEPTIC SYSTEM SEPTIC SYSTEM SURVEYSURVEY
Facts, Figures & Pertinent Study Facts, Figures & Pertinent Study
1616
SPENCER COUNTY HEALTH SPENCER COUNTY HEALTH DEPARMENT (2001)DEPARMENT (2001) Strongly Supports sanitary sewer Strongly Supports sanitary sewer
projectproject Rationale:Rationale:
– On-site system failure is well documented On-site system failure is well documented – Causes of failure: flood-zone, topography, lot Causes of failure: flood-zone, topography, lot
size, high groundwater table, and slow size, high groundwater table, and slow permeability of soilspermeability of soils
– Consequences: closure and/or limited use of Consequences: closure and/or limited use of food establishment; several residences have food establishment; several residences have been forced to vacate been forced to vacate
Conclusion:Conclusion: – Many problems cannot be solved by on-site disposal Many problems cannot be solved by on-site disposal
methodmethod– Sanitary sewer is the only solutionSanitary sewer is the only solution
1717
INDIANA STATE DEPT OF INDIANA STATE DEPT OF HEALTH (2007)HEALTH (2007)
261 locations 261 locations (35%)(35%) were surveyed were surveyed Status of system failuresStatus of system failures
– 16 observed to have failed 16 observed to have failed – 11 had a history of failure11 had a history of failure– 5 had past failure documented by local 5 had past failure documented by local
health departmenthealth department– 23 locations or structures identified as 23 locations or structures identified as
vacant during survey vacant during survey
1818
Existing system statusExisting system status – 82 (31%) had construction permit for new or 82 (31%) had construction permit for new or
repair; 32 (12%) inadequate system; 147 (56%) repair; 32 (12%) inadequate system; 147 (56%) no informationno information
Availability of room for replacementAvailability of room for replacement– 164 (63%) had adequate area; 61 (24%) limited 164 (63%) had adequate area; 61 (24%) limited
area; 36 (14%) inadequate areaarea; 36 (14%) inadequate area Existing soil Existing soil
– 43 (16%) had specific soil descriptions; 8 (19%) 43 (16%) had specific soil descriptions; 8 (19%) had soil descriptions had soil descriptions notnot conducive to onsite conducive to onsite system installation (pursuant to IAC 6-8.1)system installation (pursuant to IAC 6-8.1)
ISDH RECOMMENDATIONSISDH RECOMMENDATIONS
SOIL AND WATER SOIL AND WATER QUALITYQUALITY
PUBLICATIONS:PUBLICATIONS:
1. Soil Survey of Spencer County by 1. Soil Survey of Spencer County by
NRCSNRCS
2. Preliminary Engineering Report2. Preliminary Engineering Report
1919
2020
Predominant SoilsPredominant Soils: : WheelingWheeling Limitations for onsite systemLimitations for onsite system: : small lot small lot
size; large number of failing system in size; large number of failing system in close proximity; adjacent flood plain;close proximity; adjacent flood plain;
Classification of absorption field Classification of absorption field Limitations: Limitations: SlightSlight
Water quality of stream (E. Coli/100 mL of Water quality of stream (E. Coli/100 mL of sample): sample): 14,00014,000
Need for wastewater facility: Need for wastewater facility: SevereSevere
ENTITY - HATFIELD ENTITY - HATFIELD
2121
Predominant SoilsPredominant Soils: : Wheeling, WeinbachWheeling, Weinbach Other considerationsOther considerations: : 3 homes vacated; 3 homes vacated;
closing of a tavern;closing of a tavern; Limitations for onsite systemLimitations for onsite system: : Slow Slow
permeable soil; small lot size; high permeable soil; small lot size; high water table; improper construction of water table; improper construction of existing systemexisting system
Classification of absorption field Limitations: Classification of absorption field Limitations: Slight to severeSlight to severe
Water quality of stream (E. Coli/100 mL of Water quality of stream (E. Coli/100 mL of sample): sample): 10,00010,000
Need for wastewater facility: Need for wastewater facility: SevereSevere
ENTITY - RICHLANDENTITY - RICHLAND
2222
Predominant SoilsPredominant Soils: : Weinbach, AlfordWeinbach, Alford Limitations for onsite systemLimitations for onsite system: : Poor Poor
drainage; low permeable soilsdrainage; low permeable soils Classification of absorption field Limitations: Classification of absorption field Limitations:
Slight to severeSlight to severe Water quality of stream (E. Coli/100 mL of Water quality of stream (E. Coli/100 mL of
sample): sample): 90,00090,000 Need for wastewater facility: Need for wastewater facility: ModerateModerate
ENTITY - EUREKAENTITY - EUREKA
2323
Predominant SoilsPredominant Soils: : Woodmere, Woodmere, HuntingtonHuntington
Limitations for onsite systemLimitations for onsite system: : within 100 within 100 year floodplain; flooding is the main year floodplain; flooding is the main limiting factor;limiting factor;
Classification of absorption field Limitations: Classification of absorption field Limitations: Slight to severeSlight to severe
Water quality of stream (E. Coli/100 mL): Water quality of stream (E. Coli/100 mL): N/AN/A
Need for wastewater facility: Need for wastewater facility: SevereSevere
ENTITY – FRENCH ISLANDENTITY – FRENCH ISLAND
SOIL AND WATER SOIL AND WATER QUALITY – cont.QUALITY – cont.Source:Source:
11. . Study: Study: Dr. David Ralston, Soil Dr. David Ralston, Soil
Tech, Inc.Tech, Inc.
2. Publication: 2. Publication: Custom Soil Resource Custom Soil Resource
Report for Spencer County,Report for Spencer County,
Indiana (USDA/Soil ConservationIndiana (USDA/Soil Conservation
Service)Service)
2424
2525
SevereSevere = = 55% of LTRSD area (9735 acres) 55% of LTRSD area (9735 acres) Primarily due to slow percolation, wetness, flooding, andPrimarily due to slow percolation, wetness, flooding, and
slope (and other factors)slope (and other factors)
Slight Slight = = 35% of LTRSD area (5382 acres)35% of LTRSD area (5382 acres)
No reason providedNo reason provided
ModerateModerate = = 9% of LTRSD area (1536 acres)9% of LTRSD area (1536 acres)
Primarily due to slopePrimarily due to slope
UnknownUnknown == 1% of LTRSD area (171 acres) 1% of LTRSD area (171 acres)
FINDINGS – LIMITATIONSFINDINGS – LIMITATIONSTO SEPTIC SYSTEMTO SEPTIC SYSTEM
2626
ALTERNATIVE SYSTEMALTERNATIVE SYSTEM
Facts, Figures & Pertinent Study Facts, Figures & Pertinent Study
2727
FULDA SYSTEM FULDA SYSTEM
Eco-Treatment System, consists of: Subsurface-flow constructed wetland A vegetated re-circulating gravel filter, and Soil absorption system (drip irrigation). Serving 64 connections. Peak design flow = 13,300 gallons per day.
Treats only “gray water” after solids
removal
2828
FULDA SYSTEM, cont. FULDA SYSTEM, cont. Cost summary:
Total project cost = $1,083,0001,083,000 Cost per connection = $19,000 (Mark
Harrison) System performance:
Appears to be cost-effective in terms of
Operating and Maintenance Meets pertinent groundwater regulations
(<10 mg/L total nitrogen)
2929
FULDA SYSTEM, cont. FULDA SYSTEM, cont.
Permitted as land application projectPermitted as land application project Funds:Funds:
– User fees, IDEM, COIT, CFF & SRFUser fees, IDEM, COIT, CFF & SRF– Fulda did not apply for USDA/RD Fulda did not apply for USDA/RD
grant)grant) Estimated user feeEstimated user fee = $63/month = $63/month General recommendations by
residents: – Water sampling frequency can be
reduced.
3030
IS A FULDA-TYPE SYSTEM IS A FULDA-TYPE SYSTEM FEASIBLE?FEASIBLE?
YES or NO, because: Fulda has 64 vs. LUCE’s 798 connections Capital cost: $ 15.2 M (Fulda-Type) vs. Capital cost: $ 15.2 M (Fulda-Type) vs.
$12.4 M (Sewer) (using $12.4 M (Sewer) (using $19,000/connection) Possibly more capital cost, but less ore capital cost, but less OperatingOperating
and Maintenance and Maintenance Cost Cost for piping & septic system replacement
must be determined
3131
IS A FULDA-TYPE SYSTEM IS A FULDA-TYPE SYSTEM APPLICABLE?APPLICABLE?Yes or NoYes or No, because, because
Fulda system may not be cost-effective (in terms of capital cost) for LUCE
Obtaining COIT/RD grant Obtaining COIT/RD grant notnot certain certain Engineering/Non-engineering cost forEngineering/Non-engineering cost for
proposed sewer system will be proposed sewer system will be lost lost Pumping of septic tank Pumping of septic tank stillstill will be will be
necessarynecessary Regulatory compliance must be obtained Regulatory compliance must be obtained
Therefore, further detailed analysis is necessary.
3232
FULDA SYSTEM – FULDA SYSTEM – ADVANTAGESADVANTAGES
Existing septic tanks are being used Meets sewer district’s goals (i.e., user fee) Green technology - energy efficient Cost-effective solution Secondary benefits through drip irrigation
3333
FULDA SYSTEM- FULDA SYSTEM- DISADVANTAGESDISADVANTAGES
Not a permanent solution for waste water
treatment Potential to meet future growth is
uncertain Performance is a function of temperature
and loading Septic tank will still need pumping Water quality sampling will be necessary
3434
POTENTIAL SOLUTIONSPOTENTIAL SOLUTIONS
Many options can be identified to meet LUCE’s need but objectives cannot be a moving target and consensus must be built
6-possible considerations:
1. Do nothing
2.Consider all 4-areas (Richland, Hatfield, Eureka & French Island) for sewerage
3.Consider all 4-areas (Richland, Hatfield, Eureka & French Island) for clustered Fulda-Type System
3535
POTENTIAL SOLUTIONS, POTENTIAL SOLUTIONS, Cont.Cont.
4. Consider Richland, Hatfield and Eureka for sewerage; French Island -other treatment alternatives or do nothing
5. Consider Richland, Hatfield and Eureka for clustered Fulda-Type System; French Island -other treatment alternatives or do nothing
6. Consider only Richland & Hatfield for sewerage; Eureka for other treatment alternatives; French Island for “do nothing”
CONSIDERATION No. 1CONSIDERATION No. 1
Do Nothing.Do Nothing.
3636
3737
CONSIDERATION NO. 2CONSIDERATION NO. 2
Permanent wastewater collection & Permanent wastewater collection & treatmenttreatment– Eliminates concern of septic back up; operating, Eliminates concern of septic back up; operating,
maintenance, pumping & replacement of septic maintenance, pumping & replacement of septic system.system.
– Provides opportunity to meet future treatment Provides opportunity to meet future treatment needneed
– Eliminates water quality concern, and provides Eliminates water quality concern, and provides all levels of wastewater treatmentall levels of wastewater treatment
Cost items: Cost items: – Construction/non-construction cost; Construction/non-construction cost;
labor/materialslabor/materials– Administrative, general expenses (1998-2008)Administrative, general expenses (1998-2008)– Operating, maintenance & treatment (annual Operating, maintenance & treatment (annual
value)value)
3838
COST & USER FEE COST & USER FEE ESTIMATESESTIMATES Funding sources: Funding sources:
– USDA/RD grant and loan;USDA/RD grant and loan;– Tap-in fees ($1000/connection)Tap-in fees ($1000/connection)– COIT grant (annual payment of $150,000 COIT grant (annual payment of $150,000
for 22 years)for 22 years) Others: Others:
– Interest rate = 4.5%, payment period = Interest rate = 4.5%, payment period = 40 yrs40 yrs
– Number of users = 798Number of users = 798
3939
SUMMARY - COST SUMMARY - COST ESTIMATESESTIMATES
Cost Item Description 2008 Estimates
Estimated Project Construction & Non-construction Cost $11,140,000
Adjustment for Inflation and Price Increases, Others (2001-2007) $1,850,000
Administrative/General/Construction Expenses (1998-2008) $2,159,513
Total Project Cost $15,149,513
Funding Sources
RD Grant $2,000,000
Tap-In Fees $798,000
USDA/RD Loan $8,180,000
Total Funds $10,978,000
Amount to Be Paid (in terms of sewer fee) during 40 years $12,351,513
4040
USER FEE ($78/Connection)USER FEE ($78/Connection)
Annual Revenue Requirements 2008 Estimates
Annual Principal & Interest (40 years at 4.5% interest rate) $671,305
Annual 10% Reserve $67,130
Annual Operation, Maintenance & Replacement $261,600
Estimated Annual Revenue Required $1,000,035
Less COIT Funds per year (22 payments) $150,000
Net Total Annual Revenue Required $850,035
Number of Users 798
Estimated Average Monthly Sewer Bill $77.5
4141
DESIRED USER FEE DESIRED USER FEE ($64/Connection)($64/Connection)
Present value of the principal & interest that can be paid by desired sewer rate
$8,380,000
Annual principal & interest (40 years, 4.5% interest rate) that can be paid by desired sewer rate
$455,453
Annual 10% Reserve $45,545
Annual Operation, Maintenance & Replacement $261,600
Estimated increased annual revenue required $762,598
Less COIT funds per year (22 payments) $150,000
Net total annual revenue required to obtain desired sewer rate $612,598
Number of users 798
Estimated average monthly bill (desired rate) $64
Amount of additional RD grant required to obtain desired sewer rate $5.6 M
4242
SUMMARYSUMMARY Consideration No. 2 (sewerage for all Consideration No. 2 (sewerage for all
areas)areas)– Based on 2008 total project cost, expenses and Based on 2008 total project cost, expenses and
funding sources => User fee = 78/Connectionfunding sources => User fee = 78/Connection– To obtain desired user fee = $64/ConnectionTo obtain desired user fee = $64/Connection
Additional grant of $5.6 M must be obtainedAdditional grant of $5.6 M must be obtained Cost of $1.5 M to Rockport Wastewater Cost of $1.5 M to Rockport Wastewater
Treatment Plant could be renegotiatedTreatment Plant could be renegotiated A Wastewater Treatment Plant can be built in A Wastewater Treatment Plant can be built in
LUCE to minimize cost of sewer line, LUCE to minimize cost of sewer line, but it but it does not appear to be cost-effectivedoes not appear to be cost-effective
4343
SUMMARY, cont. SUMMARY, cont. Consideration No. 3 (Fulda-system for all Consideration No. 3 (Fulda-system for all
areas)areas)– Based on $19,000/connection, capital cost = $15.2 Based on $19,000/connection, capital cost = $15.2
M (about the same as sewerage)M (about the same as sewerage)– Location for Eco-treatment wetland construction Location for Eco-treatment wetland construction
must be identified; sewer line length must be must be identified; sewer line length must be determined; regulatory agencies must be determined; regulatory agencies must be consulted consulted
– To obtain user fee: total project cost, amount and To obtain user fee: total project cost, amount and sources of loans, grants, and tap-in fees must be sources of loans, grants, and tap-in fees must be quantifiedquantified
– Detailed engineering and economic analysis is Detailed engineering and economic analysis is necessarynecessary
4444
SUMMARY, cont. SUMMARY, cont.
Consideration No. 4, 5 & 6Consideration No. 4, 5 & 6– Wastewater treatment objectives must be Wastewater treatment objectives must be
identifiedidentified– Consensus must built among decision Consensus must built among decision
makersmakers– Detailed engineering and economic Detailed engineering and economic
analysis is necessary analysis is necessary (more cost to (more cost to LTRSD)LTRSD)
4545
RECOMMENDATIONSRECOMMENDATIONS
1. Identify and build consensus on wastewater 1. Identify and build consensus on wastewater management goals & options (select your management goals & options (select your Consideration No.) Consideration No.)
2. For Consideration 2 (sanitary sewerage for 2. For Consideration 2 (sanitary sewerage for all areas): all areas): – Negotiate to reduce $1.5 cost to a lower amount Negotiate to reduce $1.5 cost to a lower amount
to obtain a more desirable user fee, to obtain a more desirable user fee, – Obtain more grant money (obtaining more loans Obtain more grant money (obtaining more loans
will not reduce user fee, unless the loans are at will not reduce user fee, unless the loans are at lower than 4.5% interest rate)lower than 4.5% interest rate)
– Identify a location in LUCE for WWTP constructionIdentify a location in LUCE for WWTP construction
4646
RECOMMENDATIONS, cont.RECOMMENDATIONS, cont.
3. For Consideration 3 (Fulda-type system for all 3. For Consideration 3 (Fulda-type system for all areas): areas): – Consult with regulatory agencies to ensure Consult with regulatory agencies to ensure
permitting will be allowed.permitting will be allowed.– Identify locations for Eco-treatment wetland Identify locations for Eco-treatment wetland
(Bernardin Lochmueller & Commonwealth could (Bernardin Lochmueller & Commonwealth could possibly assist in this regard).possibly assist in this regard).
– Detailed analysis will be necessary to determine Detailed analysis will be necessary to determine feasibility.feasibility.
– Remember: The only permanent solution to Remember: The only permanent solution to wastewater management is to build wastewater management is to build Sanitary Sanitary Sewerage SystemSewerage System – which is the best solution – which is the best solution available today. available today.
4747
Questions?
Next Steps
Community ProcessCommunity Process
Travel to the Commons Area and sit Travel to the Commons Area and sit at a table with a flipchart.at a table with a flipchart.
Pick a scribe from your table Pick a scribe from your table (someone who will capture (someone who will capture comments on the flipchart).comments on the flipchart).
4848
Questions to ProcessQuestions to Process
1.1. To what extent do you think Luce To what extent do you think Luce Township needs sanitary sewers to Township needs sanitary sewers to survive and thrive into the future? survive and thrive into the future? Explain.Explain.
2.2. What are the challenges residents at your What are the challenges residents at your table face with signing on to the table face with signing on to the easement. Select the two most important easement. Select the two most important to share back.to share back.
3.3. What, if any, additional information would What, if any, additional information would help us move forward?help us move forward?
4949
SharebackShareback
1 person from each group come 1 person from each group come forward.forward.
Bring your table’s flipchart sheets.Bring your table’s flipchart sheets. Share the comments from your table.Share the comments from your table. Post on the wall.Post on the wall.
5050
““Dotting”Dotting” ““Dotting” helps understand what is most Dotting” helps understand what is most
important to each of you. They act as important to each of you. They act as an “exclamation point!” to comments.an “exclamation point!” to comments.
Place your dots by the few items which Place your dots by the few items which you would like to have the LTRSD Board you would like to have the LTRSD Board give particular consideration. It can be a give particular consideration. It can be a comment, suggestion or a concern.comment, suggestion or a concern.
These sheets will be summarized for the These sheets will be summarized for the next Board meeting.next Board meeting.
5151
Thank you!Thank you! The Board will review the comments The Board will review the comments
and Sue will facilitate their next steps at and Sue will facilitate their next steps at the LTRSD Board meeting.the LTRSD Board meeting.
Closing comments (Grady and Kathy)Closing comments (Grady and Kathy) Thank you for giving your evening to Thank you for giving your evening to
participate in this important community participate in this important community decision.decision.
Encourage those who could not attend Encourage those who could not attend tonight to join us Thursday evening.tonight to join us Thursday evening.
5252