June 8, 2011
Report on
7800 S. Finished Water Pipeline
Phase III – 2700 W. to Bangerter
7800 S. Phase III
Engineer: CH2M HILL Inc.
Contractor: UDOT/Condie Construction
Contract Award Date: November 12, 2008Project Scope: Installation of 24-inch and 30-inch pipeline from 2700 West to Bangerter Highway and new vault at 3200 West.
Original Contract Amount
Final Contract Amount
% Change from Original Amount
$2,282,661 $2,588,810 13.4%
Change Order #3: $225,640Change in depth of the bore underneath Bangerter Highway due to conflicting utilities.
Change Order #4: $2,088Additional potholing at Bangerter Highway.
Change Order #7: $3,175Changes to the connection to the existing pipe at 2700 West.
Change Order #12: $7,014Changes in the pressure rating of the pipe in the 3200 West vault and deletion of the interconnection to the old 16-inch pipe.
Change Order #17: $61,811Project Acceleration Costs.
Change Order #20 $0Changes to the Pipe Coating Specification
7800 S. Phase III
Change Order #23: $22,626Utility conflicts on the 24-inch and 30-inch pipeline and changes to the vault at 3200 West.
Change Order #24: $58,825Delay claims, traffic control credit, Bangerter jack and bore standby costs and liquidated damages.
7800 S. Phase III
Jack and bore underneath Bangerter Highway
7800 S. Phase III
24-inch pipe being installed in 7800 S.
Final piece of 30-inch pipe Final piece of 30-inch pipe being installedbeing installed
7800 S. Phase III
3200 West Vault under construction3200 West Vault under construction