K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011

Date post: 23-Mar-2016
Category:
Upload: guri
View: 33 times
Download: 0 times
Share this document with a friend
Description:
SEE upsets in collimator control Mitigation options. K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011. Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team. R2E events. - PowerPoint PPT Presentation
10
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team EE upsets in collimator control Mitigation options
Transcript
Page 1: K. Foraz & Perrot  A. L.,  EN/MEF -  R2E Project LMC 25th May 2011

K. Foraz & Perrot A. L., EN/MEF - R2E Project

LMC 25th May 2011

Thanks toEN/EL, EN/HE, EN/MEF, equipment ownersthe LHC integration team & the R2E team

SEE upsets in collimator controlMitigation options

Page 2: K. Foraz & Perrot  A. L.,  EN/MEF -  R2E Project LMC 25th May 2011

- 1rst May 2011: SEU in UJ14 collimation control rack -> beam dump(see presentation of Markus in LMC 4th May)

- 5th May 2011: emergency action plan request

- May 2011: SEU in UJ14/16 cryogenics SEU in UJ14/16 biometry ; SEU in others areas (see RADWG for details)

LMC, 25 May 2011, A. L. Perrot 1

QPS

PIC

collimation

current leads heaters

BPM

cryogenics

UJ14/16 racks layout

R2E events

TODAY

UL16

UJ16

Courtesy A. Tursun, Y. Muttoni

transport reserved volume

PC

PC spare

Symmetrical layout in UJ14

Page 3: K. Foraz & Perrot  A. L.,  EN/MEF -  R2E Project LMC 25th May 2011

Mitigation options

4 mitigation options can be considered

Option # 0: full relocation + shielding activities during 7 months for 10 groups

Option # 1: relocate only the 2 collimation racks

Option # 2: relocate all the racks except the Power Converters

Option # 3: shielding

Duration & sequence optimized with Katy, EN/EL & EN/HE

LMC, 25 May 2011, A. L. Perrot 2

Page 4: K. Foraz & Perrot  A. L.,  EN/MEF -  R2E Project LMC 25th May 2011

Option 1- collimation racks relocation

Time estimation per side

EN/EL 7 days activityEN/STI 10 days activity

Total= 15 days

Work anticipation in a Technical Stop Phase I: EL (cables + optical fibers) 5 days during 1 TSPhase II: EL (cables connection), EN/STI 12 days emergency or

Christmas break

Advantage: EL manpower available for other activities during ‘Christmas break’

Group

Activity Duration [days]

EN/EL racks disconnection 1 cable trays installation 1 pull cables 1

connection // optical fibers 2

EN/STI racks displacement 5 commissioning

Partial equipment relocation not an effective R2E approach

LMC, 25 May 2011, A. L. Perrot 3

Time estimation for both sides

Page 5: K. Foraz & Perrot  A. L.,  EN/MEF -  R2E Project LMC 25th May 2011

Option 2 – UJ14/16 racks relocation

TODAY

UL16UJ16

Courtesy A. Tursun, Y. Muttoni

transport reserved volume

exclusion area

PC

QPS

PIC

collimation

current leads heaters

BPM

PC spare

cryogenics(profibus-> moves FIP -> stays)

CYCIP01 + DYPG02DYPG01

TYCFL01

QYC01

QYC02

RYSC01

RYLC01RYLB01

RYMCB01RYMCB02RYMCB03RYMCB04

RQX.R1RTQX2.R1

RYMCC01

RYCA01RYCA02

UL16 after relocation

Relocation 6 racks /side(without power converters)

5 groups impacted

LMC, 25 May 2011, A. L. Perrot 4

Courtesy P. Orlandi, JC Guillaume

UJ14/16 racks layout

Page 6: K. Foraz & Perrot  A. L.,  EN/MEF -  R2E Project LMC 25th May 2011

‘crash program for EN/EL’possible manpower issue for the other activities

LMC, 25 May 2011, A. L. Perrot 5

Group activity Duration [week]

EN/EL 11 Equipment owners (without TE/EPC) 7 displacement commissioning TOTAL 18

Option 2 – UJ14/16 racks relocation

Christmas break 2011-2012: 11 weeks activities in tunnel

co-activity

Conclusion:not possible to relocate the 12 racks during next Christmas break

Study under progress

Fluence decrease by factor8-30

Page 7: K. Foraz & Perrot  A. L.,  EN/MEF -  R2E Project LMC 25th May 2011

Option 3 - Shielding

Location Weight [t] Blocks # Bars # Delivery @ CERN

RB16 60 85 mid-July 2011UJ16 190 500 1400 Nov 2011UJ17 300 250 Nov 2011

TOTAL /2 sides 1100 1670 2800

Courtesy F.Delsaux

LMC, 25 May 2011, A. L. Perrot 6

UL16

UJ16

UJ17

RB16

After relocation & shielding

Courtesy JP Corso

UJ16

UJ17

RB16

Shielding installation in RB16

Courtesy F.Delsaux

L shielding= 28 m

Page 8: K. Foraz & Perrot  A. L.,  EN/MEF -  R2E Project LMC 25th May 2011

Parallel activitiesEmpty He liquid in 1 sectorDepressurize the triplet He line(discussed with Safety)

Time estimation for both sides

Activity Duration [week]

Preparatory work 1 MAD removal Survey motors removal Tablotins' (AUG, siren, red phones, anti-panic lightning) Shielding installation (*) 4 2 shifts Rehabilitation work 1 MAD reinstallation test safety equipments

TOTAL 6(*) if chicane replaced by a ‘plug’ -> 2 additional weeks

Option 3 - Shielding

EN/HE: manpower effort

Conclusion: shielding installation could be scheduled for next Christmas break

LMC, 25 May 2011, A. L. Perrot 7

ALARA : installation during Christmas break (residual dose rate along the triplets)

Fluence decrease by factor7-10

Page 9: K. Foraz & Perrot  A. L.,  EN/MEF -  R2E Project LMC 25th May 2011

Courtesy K. Foraz, M. Brugger & R2E simulation team

Option Mitigation action work duration [weeks]

Fluence decrease factor

Option 0 full relocation + shielding 30 40 to 100 (**)Option 2 12 racks relocated into UL 18 (*) 8 to 30 (**)Option 3 shielding + chicane (plug) 6 (8) 7 to 8 (8 to 10) (**)

Option2 +3 12 racks relocation into UL + shielding+ chicane 24 40 to 100 (**)

Options comparison

LMC, 25 May 2011, A. L. Perrot 8

General remark:co-activity not possible between shielding & relocation(~1000 transports of blocks are foreseen in each UL i.e. lift 4000 up/down)

(*) EN/EL ‘crash program’(**) depending of the location

Page 10: K. Foraz & Perrot  A. L.,  EN/MEF -  R2E Project LMC 25th May 2011

Conclusions

LMC, 25 May 2011, A. L. Perrot 9

R2E proposals:- No independent equipment relocation unless clear impact

on LHC operation

- Shielding installation during next Christmas break (ALARA)

R2E monitors constantly radiation levels, failures & scenarios

‘R2E review’ in November: presentation/discussions of the optimization solutions