AD6/March 2017
Advanced diploma in procurement and supply
Operations management in supply chains
Date Wednesday 8 March 2017
Time Start 14:00 End 17:00 Duration 3 hours
QUESTION PAPERINSTRUCTIONS FOR CANDIDATES
This examination has FOUR compulsory questions worth 25 marks each.
1. Do not open this question paper until instructed by the invigilator.
2. All answers must be written in the answer booklet provided.
3. All rough work and notes should be written in the answer booklet.
QP04
Page 3 of 8 AD6 Exam Questions March 2017
QUESTIONS
You are advised to spend 45 minutes on each question.
Q1 Examine the main activities and responsibilities of an operations manager within an organisation of your choice. (25 marks)
Q2 A manufacturing organisation is considering relocating its main production site within the same country.
Examine FIVE influences on the choice of the new production site location. (25 marks)
Q3 (a) Explain the key features of Materials Requirements Planning (MRP) for planning and control in operations management. (12 marks)
(b) Explain Manufacturing Resource Planning (MRP II) and suggest how it differs from MRP. (13 marks)
Q4 Examine the objectives and cost implications of preventive maintenance and repair maintenance. (25 marks)
END OF QUESTION PAPER
Page 8 of 8 AD6 Exam Questions March 2017
PLEASE RETURN TO:
CIPS ASSESSMENT MANAGEMENT CENTRE
c/o LINNEY DIRECT, A2 GOODS IN
BELLAMY ROAD, MANSFIELD
NOTTINGHAMSHIRE NG18 4LN
UNITED KINGDOM
TEL: +44(0) 845 880 1188
FAX: +44(0) 845 880 1187
www.cips.org