+ All Categories
Home > Documents > Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting,...

Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting,...

Date post: 01-Apr-2015
Category:
Upload: brayden-dorrington
View: 213 times
Download: 0 times
Share this document with a friend
Popular Tags:
38
Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City
Transcript
Page 1: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

Kenneth WilsonWECC Staff

Bulk Electric System (BES) Definition UpdateMay 14-15, 2013

RS Meeting, Salt Lake City

Page 2: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

2

• “Core” BES Definition• FERC Order• BES Definition Processes• Definitional Exclusion Reporting Process• Rules of Procedure Exception Process• Local Distribution Process• De-registration Process• Staff Points of Contact

Overview

Page 3: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

BES Core Definition

Page 4: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

4

BES Definition – Base

“… all Transmission Elements operated at 100 kV or higher and Real and Reactive Power resources connected at 100 kV or higher. This does not include facilities used in the local distribution of electric energy.”

Page 5: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

5

• The BES Definition provides specific criteria for “definitional” inclusions and exclusionso I1 – I5, E1 – E4

• These do not need to be submitted through the Rules of Procedure (RoP) Exception Process

• Element changes to the BES are reported to the Regions for review

BES Definition – Definitional Inclusions and Exclusions

Page 6: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

6

• I1 - Transformers with the primary terminal and at least one secondary terminal operated at 100 kV or higher unless excluded under Exclusion E1 or E3.

• I2 - Generating resource(s) with gross individual nameplate rating greater than 20 MVA or gross plant/facility aggregate nameplate rating greater than 75 MVA including the generator terminals through the high-side of the step-up transformer(s) connected at a voltage of 100 kV or above.

• I3 - Blackstart Resources identified in the Transmission Operator’s restoration plan.

Definitional Inclusions

Page 7: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

7

• I4 - Dispersed power producing resources with aggregate capacity greater than 75 MVA (gross aggregate nameplate rating) utilizing a system designed primarily for aggregating capacity, connected at a common point at a voltage of 100 kV or above.

• I5 –Static or dynamic devices (excluding generators) dedicated to supplying or absorbing Reactive Power that are connected at 100 kV or higher, or through a dedicated transformer with a high-side voltage of 100 kV or higher, or through a transformer that is designated in Inclusion I1.

Definitional Inclusions (cont.)

Page 8: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

8

• E1 - Radial systems: A group of contiguous transmission Elements that emanates from a single point of connection of 100 kV or higher and: a) Only serves Load.

or,

b) Only includes generation resources, not identified in Inclusion I3, with an aggregate capacity less than or equal to 75 MVA (gross nameplate rating). or,

c) Where the radial system serves Load and includes generation resources, not identified in Inclusion I3, with an aggregate capacity of non-retail generation less than or equal to 75 MVA (gross nameplate rating).

• Note – A normally open switching device between radial systems, as depicted on prints or one-line diagrams for example, does not affect this exclusion.

Definitional Exclusions

Page 9: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

9

• E2 - A generating unit or multiple generating units on the customer’s side of the retail meter that serve all or part of the retail Load with electric energy if: (i) the net capacity provided to the BES does not exceed 75 MVA, and (ii) standby, back-up, and maintenance power services are provided to the generating unit or multiple generating units or to the retail Load by a Balancing Authority, or provided pursuant to a binding obligation with a Generator Owner or Generator Operator, or under terms approved by the applicable regulatory authority.

Definitional Exclusions (cont.)

Page 10: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

10

• E3 - Local networks (LN): A group of contiguous transmission Elements operated at or above 100 kV but less than 300 kV that distribute power to Load rather than transfer bulk power across the interconnected system. LN’s emanate from multiple points of connection at 100 kV or higher to improve the level of service to retail customer Load and not to accommodate bulk power transfer across the interconnected system. The LN is characterized by all of the following: a) Limits on connected generation: The LN and its underlying Elements do not include generation

resources identified in Inclusion I3 and do not have an aggregate capacity of non-retail generation greater than 75 MVA (gross nameplate rating) ;

b) Power flows only into the LN and the LN does not transfer energy originating outside the LN for delivery through the LN; and

c) Not part of a Flowgate or transfer path: The LN does not contain a monitored Facility of a permanent Flowgate in the Eastern Interconnection, a major transfer path within the Western Interconnection, or a comparable monitored Facility in the ERCOT or Quebec Interconnections, and is not a monitored Facility included in an Interconnection Reliability Operating Limit (IROL).

• E4 – Reactive Power devices owned and operated by the retail customer solely for its own use.

Definitional Exclusions (cont.)

Page 11: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

FERC Order

Page 12: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

12

• Approved by NERC Board of Trustees on 1/19/12

• FERC proposed to approve definition and revisions to the Rules of Procedure in its 6/22/12 Notice of Proposed Rulemaking

• FERC approval 12/20/12 (Order 773)• FERC final approval 4/18/13 (Order 773-A)

BES Definition - History

Page 13: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

13

• Definition effective July 1, 2013• Compliance for newly added facilities July

1, 2015

Effective Dates

Page 14: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

14

• Local Distribution• E1 and E3 do not apply to generation tie lines (NERC

will Modify Definition)• 100 kV minimum on local networks removed (NERC

will Modify Definition)• FERC can designate elements as part of the BES on

its own• Registered Entities must notify its Regional Entity

of elements that changed BES status per application of the new BES definition (per section 501 of RoP)

FERC Order Changes

Page 15: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

Definitional Inclusion/Exclusions Reporting Process

Page 16: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

16

• Provides guidance on application

• Revisions related to FERC order and comments received expected in April

• NERC Informational webinar after release of document

BES Definition Guidance Document

Page 17: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

17

• Required by paragraph 317 of FERC Order 773 and Section 501 of the NERC Rules of Procedure

• Notification through “NERC BES Notification and Exception System” available July 1, 2013

• Submission by asset owner (GO/TO)• More detailed info at 5/30 webinar

Notification of Self-Determination

Page 18: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

18

• Data Required o List of element(s) that are included/exclude per the

definitiono System Mapo If required two years of flow data into network

• WECC registration staff notifies entities of concurrence/non-concurrence of elements

Definitional Exclusion/Inclusion Reporting Process

Page 19: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

Rules of Procedure Exception Process

Page 20: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

20

“ Elements may be included or excluded on a case-by-case basis through the Rules of Procedure exception process.”

Exceptions requests will only be considered after Compliance staff determines the network/element is in the BES per the definition

Rules of Procedure Exception Process

Page 21: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

21

(a) Exclusion Exception• An entity may request and obtain Approval from NERC for

an Exclusion Exception on the grounds that the Element(s) for which the Exception Request is filed is included within the BES based on application of the BES Definition but is not necessary for the Reliable Operation of the interconnected bulk-power transmission system as evidenced by Required Information provided pursuant to Detailed Information to Support an Exception Request (Section III.B of the Exception Request Form).

Ongoing RoP Exception Process Activities

Page 22: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

22

(b) Inclusion Exception• An entity may request and obtain Approval from NERC for

an Inclusion Exception on the grounds that the Element(s) for which the Exception Request is filed is not included within the BES based on application of the BES Definition but is necessary for the Reliable Operation of the interconnected bulk-power transmission system as evidenced by Required Information provided pursuant to Detailed Information to Support an Exception Request (Section III.B of the Exception Request Form).

Ongoing RoP Exception Process Activities

Page 23: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

23

• Section 215 of the FPA states: o ‘‘(4) The term ‘reliable operation’ means

operating the elements of the bulk-power system within equipment and electric system thermal, voltage, and stability limits so that instability, uncontrolled separation, or cascading failures of such system will not occur as a result of a sudden disturbance, including a cybersecurity incident, or unanticipated failure of system elements.”

Federal Power Act

Page 24: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

24

• Entity submits request• Regional Entity accepts or rejects (submitting

entity can appeal)• If accepted, Regional Entity performs substantive

review• Regional Entity recommends approval or

disapproval (if recommending disapproval, forward request to Technical Review Panel (TRP))

• NERC makes final decision (submitting entity can appeal)

RoP Exception Process

Page 25: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

25

• Scope of responsibility:oOwneroRegional Entity (RE)o Planning Authority (PA)oReliability Coordinator (RC)o Transmission Operator (TOP)o Transmission Planner (TP)o Balancing Authority (BA)

Eligible Submitter

Page 26: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

26

• Complete screening either 60 days after initial receipt or 30 days after receiving owner’s response, whichever is later

• Assign unique identifier• Review for whether:

o Submitting entity was eligibleo Required information was submitted

• Send notice to submitter• Regional Entity Can accept or reject in whole or in

part

Initial Screening

Page 27: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

27

• Complete within six months of acceptance• Regional Entity may request additional info• Regional Entity develops recommendation

o If recommendation is for disapproval, engage a TRP Not involved in original review Regional Entity not bound by recommendation of TRP

• Submitting entity or owner can supplement the request at any time

Substantive Review

Page 28: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

28

• Complete 90 days after receiving Recommendation

• NERC develops team of three subject matter experts to review request

• NERC may request interviews with Regional Entity, submitting entity, or owner

• NERC President makes final decision

Approval or Disapproval

Page 29: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

29

• Registered entity training/outreach to comeo Submittal processo Acceptable file formatso Start datesoGuidance on detailed information for Section III

Ongoing RoP Exception Process Activities

Page 30: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

30

• May 24, 9am MT, Application of Definition webinar• May 30, 2pm MT, Notification of Self Determination

webinar• June 4-5, Compliance Users Group• June 11, 2pm MT, Exception Process for TO/GOs webinar• June 13, 2pm MT, Exception Process for TOP/BA/RC/PC

webinar• June 20, 3pm MT, Next Steps and Q&A webinar• June 17-28, NERC webinars on BES Notification and

Exception System• July 1, 2013 BES Definition Effective Date

Outreach and other important dates

Page 31: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

31

• A one-line breaker diagram identifying the Element(s) for which the exception is requested must be supplied with every request. The diagram(s) supplied should also show the Protection Systems at the interface points associated with the Elements for which the exception is being requested.

• The Detailed Information to Support an Exception Request provides a list of questions for Transmission Elements and Generation Resources that should be addressed (see http://www.nerc.com/docs/standards/sar/bes_criteria_third_posting_exception_request_form_20111107_clean.pdf)

Detailed Information to Support an Exception Request

Page 32: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

32

• Entities are required to supply the data and studies needed to support their submittal. Studies should:o Be based on an Interconnection-wide base case that is suitably

complete and detailed to reflect the electrical characteristics and system topology;

o Clearly document all assumptions used;o Address key performance measures of BES reliability through

steady-state power flow; and, transient stability analysis as necessary to support the entity’s request, consistent with the methodologies described in the Transmission Planning (TPL) standard and commensurate with the scope of the request.

• Supporting statements for the submitted position from other entities are encouraged.

Detailed Information to Support an Exception Request

Page 33: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

Local Distribution

Page 34: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

34

• Submit requests directly to FERC• FERC will use the 7 Factor Test (Order 888)

to determine applicability• Once FERC issues a favorable decision the

Local Distribution network is no longer part of the BES.

Local Distribution

Page 35: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

De-registration Process

Page 36: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

36

• Current Process o Submit letter to [email protected]

identifying reason for request (i.e. definitional exclusion, exception request etc.)

• Future Process o Notification through “NERC BES Notification

and Exception System” available July 1, 2013

De-registration Process

Page 37: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

37

• Application of “Core” Definition and Definitional Exclusion Submittals, De-registration ProcessoRichard Mabry:

Email: [email protected], Phone: 801.883.6847

• Rules of Procedure Exception Processo Kenneth Wilson:

Email: [email protected], Phone: 801.883.6886

WECC Staff Contacts

Page 38: Kenneth Wilson WECC Staff Bulk Electric System (BES) Definition Update May 14-15, 2013 RS Meeting, Salt Lake City.

Kenneth Wilson – [email protected]

Richard Mabry – [email protected]

Questions?


Recommended