8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 1/18
1
Preliminary Study Report for Grant Aid Project
1. Title of the Cooperation Project and Name of the Project Proponent
1.1 Title of the Cooperation ProjectThe Project for Dualling of Ugong Road from Adams Arcade (Elgeyo Marakawet Road
Roundabout) to the Junction of Ngong Road/Kenyatta Avenue in the Republic of Kenya
2. Categorization and its reason
2.1 Categorization : Category B
2.2 Reason
(1) Several adverse impacts (rating B) are expected due to the project during planning,
construction and operation stage on environmental items such as land acquisition and involuntary
resettlement, fauna, flora and biodiversity, air pollution, water pollution, waste, etc.(2) In the Second Schedule of the Environmental Management and Co-ordination Act, 1999
(EMCA) Projects to undergo EIA are specified for plans of developments and activities for the
project in relation to road development. Thus the proposed project is required to be subject to EIA.
3. Outline of the Location (Maps, Environmental and Social Condition, Problems and so on)
3.1 The Project areas
Ugong Road is located in western area of the City of Nairobi, the capital of Kenya as shown in Map
1. The targeted road section is about 5km long running from Adams Arcade to the Junction of
Ngong Road/Kenyatta Avenue as shown in Map 2.
(1) Social environment
- Administrative units traversed by the road section are 1 Province (Nairobi), 2 Districts (Dagoreti
and Langata), 3 Divisions (Westlands, Dagoreti and Kibera) and 4 Locations (Kilimani, Riruta,
Kenyatta/Golf Course and Langata).
- The population of Nairobi was about 2.14 million at 1999 population census and estimated about
3 million in 2009. Populations corresponding to the administrative units are about 0.73 million for
3 Divisions and about 0.16 million for 4 Locations in 1999.
- Areas around the road are mostly utilized for residential, commercial and institutional facilities
and sports/recreational activities. In the eastern area there are many offices of government and
related organizations, and of business activities as a center of administrative, social and economic
activities in the City of Nairobi and in the whole Kenya. In the western area there are many public
facilities such as schools, hospitals as well as private facilities of commercial activities such as
shopping centers.
(2) Natural environment
- Nairobi area is divided into two physiographic units or landforms. The western portion including
the project area is on high ground (1,700-1,800 meters above the sea level) with rugged topography,
while the eastern side is generally low (1,600 meters above sea level) and flat. The geology is
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 2/18
2
dominated by volcanic activity and rocks of the area mainly comprise a succession of lavas and
pyroclatics of Cainozoic age overlaying the folded schist and gneiss of the Precambarian Basement
system.
- The climatic conditions within project area are similar to the City of Nairobi. A semi-humid
climate with a bi-modal rainfall occurring in from March to May and from mid-October tomid-December. The average annual mean rainfall is about 1,080 mm per year. The minimum and
maximum temperature ranges from of 12 to 28 with annual mean of about 19 .
- There are various conservation areas in the Nairobi City Area include two national parks, forest
areas, and city parks. However, areas around targeted Ugong Road section are mainly urban setting
where natural vegetation has been compromised by social and economic development.
(3) Environmental Pollution
- The air pollution along the road is associate with exhaust emissions from vehicles and domestic
emissions, although there is no existing data on air quality. Most of the motorable sections of theroad and its adjoining access roads are bitumen surfaced and hence limited level of dust emissions.
Like most other urban roads, the road section is characterized with constant flow of vehicles
implying vehicular air pollution and noise to receptors along the immediate neighborhood of the
road. This, however, varies with distance from the ROW as well as the nature and volume of traffic
using the road.
4. Legal framework of Environmental and Social Considerations
4-1 Laws and regulations
(1) Environmental Management and Conservation- The Constitution of Kenya
- Environmental Management and Co-ordination Act, 1999 (EMCA)
- Water Act, Wildlife (Conservation and Management) Act, Forests Act, Lakes and Rivers Act,
Public Health Act, Occupational Safety and Health Act, Local Government Act, etc.
(2) Environmental Regulation and Standards
- Environmental Management and Coordination (Water Quality) Regulations, 2006
- Environmental Management and Coordination (Waste Management) Regulations, 2006
- Environmental Management and Coordination (Noise and Excessive Vibration Pollution Control)
Regulations, 2008 (draft)
- Environmental Management and Coordination (Air Quality) Regulations, 2008 (in preparation)
(3) Environmental Impact Assessment
- Environmental Management and Co-ordination Act, 1999 (EMCA)
- Environmental (Impact Assessment and Audit) regulations, 2003 (EIAAR)
- Environmental Impact Assessment Guidelines and Administrative Procedures (draft)
(4) Land Tenure and Land Use
- Land Control Act, Government Land Act, Registration of Titles Act, Registered Land Act, Trust
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 3/18
3
Land Act, Physical Planning Act, Land Acquisition Act, Wayleaves Act, etc.
-
4-2 Projects subject to EIA
In the Second Schedule of the EMCA Projects to undergo EIA are specified for plans of
developments and activities for 15 sectors. Among them an EIA is required for the project of roadtransport development.
4-3 Procedures and requirements for Environmental Assessmen t
According to the EIAAR, the project proponent should obtain the Environmental Impact
Assessment (EIA) Licence from the National Environment Authority (NEMA) through two steps.
The first step is by applying a Project Report to the NEMA. The second step is by conducting EIA
Study and by submitting an EIA Study Report to the NEMA, if the NEMA is not satisfied with the
result of the Project Report.
EIA studies and reports required under the EMCA shall be conducted or prepared respectively byindividual experts or a firm of experts authorized in that behalf by the NEMA.
The general procedures in both steps are shown in Figure 1.
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 4/18
4
(Yes)
(No)
(Disagree)(Agree)
(No)
(Yes) (Agree)
(Disagree
Note1: Basically information discl osure and pub lic partcipation a re required for entrire process. Note2: * Mostly involved o rganizations Note 3: ** In terms of calendar days/months from receiving PR or EIA Study Report
(Within 3months
(Within 45days **
*
* *
* * *
Initial Environmental Audit
Self Environmental Audit
Process of applying and obtaining Environment Approval
* *
*
*
*
* *
*
*
* *
*
* *
*
*
* *
*
*
*
*
To implement the Project Plan
Redesign EIA or P roject Plan
*
*
*
*
*
*
*
Certified EIAExpert
Appeal to Environment Tribunal
EIA Licence
Public Hearing
*
Proponent
NEMA
Lead Agency(Ministryetc.
* *
*
Review & Comment
Review & Comment
To implement the Project Plan
Conduct EIA Study
Submit EIA Study Report to NEMA
Initial Environmental Audit
Self Environmental Audit
Plan of the Project (Activities,Programmes)
Submit PR to NEMA
Full EIA is required
Approval (Environment Licence)
Scoping process (like IEE)
Making "Project Report (PR)"
Decision of Approval (2)
Public Consultation
Decision of Approval (1)
Appeal to Environment Tribunal *
* *
* * *
Figure 1 Procedure of Obtaining EIA Licence
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 5/18
5
4-4 Competent Agency
Competent agency to evaluate, review the Project Report and the EIA Study Report and issue EIA
Licence is National Environment Management Authority (NEMA). It was established under the
EMCA as the principal agency of government in all matters of environmental management and a parastatal of the Ministry of Environment and Natural Resources as shown in Figure 2.
Source: Result of an interview and NEMA website.
District Director of Environment
National Environment ManagementAuthority (NEMA)
Ministry of Environment and Natural Resources
Coastal, Marine and Freshwater Sub-department
Provincial Director of Environment
Finance & Administration Department
Planning & Research Department
Environmental Information, Education and Public Participation Department
Compliance & Enforcement Department
Directorate
Figure 2 Organization chart of National Environment Management Authority (NEMA)
4-5 Information Disclosure and Public Participatio n
According to the EIAAR, the public consultation is a pre-requisite to all the projects to provide
different stakeholders with an opportunity to raise their concerns from the project scoping stage to
the approval of EIA Licence. Provision of intense public participation and consultation has been
made mandatory for EIA through public consulting during scoping and public hearing after draft
report preparation. Such participation of the related stakeholders take place through entire period of
preparation and reviewing of both the Project Report and EIA Study Report
5. Outline of relevant Agency and Institution which implement Project, EIA so on.
5.1 Name of the Project Proponent
-The Responsible Agency (Lead Agency)is the Ministry of Roads (MOR).
-The Implementing Agency (Proponent) is Kenya Urban Roads Authority (KURA).
- Organization chart of both agencies are shown in Figure 3 and 4.
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 6/18
6
Mechanical &
Transport
Department
AssistantMinisters
RoadsSecretar
y
KanyanInstitute
of Highwa
y &BuildingTechnol
materials
Testing&
researchDepartm
ent
RoadsDepartm
ent
Kenya National
RoadsAuthorit
y
KenyaRuralRoad
Authority
KenyaRoad Board
Administration
Secretar y
Ministers
PermamentSecretary
QualityAssuran
ceDepartm
ent
enyaUrbanRoads
Authority
KURA
Figure 3 Organization Chart of Ministry of Roads (MOR)
HumanResourc
es &Administration
eneraManager
-Planning&
Environment
Road Planning
&Environ
ment
Legal &Corpora
teAffairs
SurveyServices
Board of Directors
Director General
General
Manager -Mainten
ance
General
Manager -
Finance
AuditQualityAssuran
ce
Procurement &Contract
s
FinanceICT
Design&
Construction
Structur
es
AxleLoad
MaintenanceEast
MaintenanceWest
GeneralManager
- Design&
Construction
Figure 4 Organization Chart of Implementation Agency (KURA)
6. Outline of the Project and Analysis of Alternatives
6.1 Outline of the Project
The objective of the proposed project is to meet increasing transportation demand and contribute to
reduction of traffic jam, especially in the west side of City of Nairobi through widening of Ngong
Road in City of Nairobi in the Republic of Kenya.
The scope of the project was originally the widening of existing two-lane two-way Ngong Road to
four-lane two-way from Dagoreti Corner to the Kenyan National Library Services. However, as a
result of discussion with Kenyan side, the scope was finalized the widening of the Ngong Road to
four-lane two-way from Adams Arcade to the Junction on Ngong Road/Kenyatta Avenue as shown
in Figure 2.
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 7/18
7
6.2 Analysis of Alternatives
Analysis of alternatives was examined for following three cases.
(1) No action (without project)
The high urban population growth rate in City of Nairobi has created rapid urban spatial growthand associated problems such as inadequate housing, traffic congestion, environmental degradation,
land use conflicts etc. Among them heavy traffic congestion is the most serious problem in view of
hampering economic activities and living conditions, and causing air pollution.
The present transport infrastructure is inadequate to meet the rapidly increasing traffic demand in
the Nairobi Metropolitan Area. An inadequate supply of the road capacity, road structure and traffic
management measures have been causing heavy traffic congestion and traffic accidents.
No action means that any efforts will not be made to reduce heavy traffic congestion and the
present serious problem will be left unsolved.
(2) Project plan by MOR
To reduce traffic congestion of Ugong Road, Ministry of Roads planned independently road
widening project for full stretch of Ugong Road and a part of Langata Road, covering a total of
31km long and including section of this project*.
* Ministry of Roads (2009.8): “Preliminary and Detailed Engineering Design of All Saints Cathedral Junction –
City Mortuary – Dagoreti Corner – Ngong Town (C61/C60) Roads – Karen – Bomas Roads” Volume (by APEC
Consulting Engineers, CAS Consulting Engineers Limited and Consulting Engineering Services (India) Private
Limited)
The project intends to existing two-lane two-way road to widen to six-lane two-way road at a burst
to solve the present traffic congestion through a drastic increase of traffic volume. However,
construction cost is estimated high enough to be beyond the limits of the budget. In addition, the
plan has difficulties even for the same section as this project in terms of environmental and social
considerations as follows:
a) The project plan includes construction of flyovers and underpass which are expected to
cause significant impacts during construction and operation stage.
b) Considerable numbers of plots are likely to be affected by land acquisition to secure ROW
(Right-of-Way) and many encroachments into ROW by business activities and structures
are also expected in numbers and types. These mean that the involuntary resettlement and
generation of PAPs are expected to occur considerably.
(3) The cooperation project
This project plan widening to four-lane two-way road is more feasible in view of the consistency
with the limits of the budget and cope with urgent needs, although improvement of traffic
congestion is expected to less than the project by MOR. However, in terms of environmental and
social considerations, the extent of involuntary resettlement and PAPs are expected to be less than
the project by MOR and impacts on other environment items to be not significant.
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 8/18
8
Thus, the project will materialize various beneficial such as reduction of severe congestion,
improvement of accessibility to work places and public service such as schools, hospitals and
consequently stimulation to the local economy and industry.
7. Adverse Environmental and Social Impacts7.1 Activities due to the cooperation project
Expected activities due to the project are shown in Table 1.
Table 1 Activities due to the Projects
Stage Activities due to the Projects
Planning StageLand acquisition and/or involuntary resettlement
Change of plan for use of lands and local resources
Construction
Stage
Extraction and transportation of construction materials from quarries and borrow pits
Engineering works for earthmoving, cutting and filling
Installation of plants, warehouse and worker's campsOperation of construction plants, machines and vehicles
Construction work of road and related facilities and structures
Operation StageOperation of road transportation
Space occupancy of roads and related facilities and structures
7.2 Envisioned adverse environmental and social impacts (Environmental Scoping)
Envisioned adverse environmental and social impacts due to the project are identified, predicted
and evaluated with rating for 31 items of social environment, natural environment and
environmental pollution according to the scoping procedure of JICA Guidelines for Environmentaland Social Considerations, and summarized in Table 2.
Table 2 Result of Environmental Scoping
Environment item *, **Rating
***Description of expected impacts ****
S o c i a l
E n v
i r o n m e n
t
1Involuntary
ResettlementB
P) (1) ROW(Road Reserve) was almost secured for target road section of
Ugong Road. However, land acquisition is expected to secure ROW on
some part of the road section, although necessary spaces are mostly part of
the full plots such as corner boundaries and area for car park and fence. (2)
Encroachment on ROW are found for obstacles such as car park, fence,
vendors and kiosks, small offices, etc., structures such as high voltage
electric lines, signboards and planted trees. However, most of these
obstacles have been utilized after permission by City Council Nairobi,
although some illegal encroachment is expected. (3) Thus involuntary
resettlement is expected to give rise for two types of the Project Affected
Persons (PAPs) (1) land owners by land acquisition and (2) people
having promise and structures and activities on ROW.
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 9/18
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 10/18
10
9Cultural property
and heritageC
C) There are many churches which are a kind of cultural property and at
the same time spiritual places to citizens. There are some possibility of
disturbance to go to church due to construction work.
10
Water usage or
Water rights and
Rights of
Common
C
There are little information on water rights, fishery r ight and rights of
common in the area. However, activities such as water intake and fishing
are not operated along the road.
11Public health and
SanitationC
C) O) Air pollution due to increase of traffic volume may cause some
adverse effect to respiratory organ. However, extent of impact is unknown.
12
Infectious
diseases such as
HIV/AIDS
B
It was reported some possibility of infection with HIV/AIDS and venereal
disease at worker's camp in case of other African countries. However,
extent of impact is not known at present stage.
13
Hazards (cyclone,
drought, etc.) and
risk
C
In the late night time, there is found security problem in the project area.
However, no additional risk of disaster and security are not expected,
although there is little information at present.
14 Accidents C
P)Traffic accidents likely to increase due to increase of vehicles for
construction work. O) Improvement of traffic congestion may give raise to
increase in number of vehicles travelling Ugong Road. This may also result
in number of traffic accidents, if proper traffic management measures such
as signaling, grading up traffic manners of both drivers and pedestrians are
not arranged.
N a t u r a l
E n v
i r o n m e n t
15Topography and
GeologyC
The project is only to make dualling the existing two road lanes. Thus no
large-scale topographical and geological alteration are expected. However,
extent of impact is unknown at present stage.
16 Soil erosion C
The project is only to make dualling the existing two road lanes. Thus no
large-scale land cut and land mound are expected. However, extent of
impact is unknown at present stage.
17 Groundwater C
A large scale exploitation of groundwater is not expected. However,
underground facilities such as water pipe and sewer lines likely damaged
due to road construction work. In addition, some possibility of utilizing
underground water in case of lack of city water supply.
18
Hydrological
situation/Drainage
pattern
C
C) Construction of gutters and reconstruction of culverts may result in
some changes in hydrological situation. However, extent of impact is
unknown.
19 Coastal zone DThe Project area is not located in coastal zone.
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 11/18
11
20Fauna, Flora and
BiodiversityB
C),O) No rare, endangered or endemic terrestrial plant and animal species
were observed during the site visit. However, planted trees such as
Jakaranda and Eucaliptus species and greens along the road contribute
somewhat amenity of the area and mitigate threat of air pollution and noise.
C) Some impact is expected due to increase in road traffic duringconstruction stage and operation stage.
21 Landscape C
C) Removal and/or relocation of trees and greens on ROW may result
greenery and aesthetics of the projected area. However, extent of impact is
unknown at the present stage.
22 Meteorology D No large-scale topographical alteration are expected.
23 Global Warming D
Generation of greenhouse gases such as CO2 is expected to increase due
to increase of number traffic volume. However. Extent f impact is not
known.
E n v i r o n m e n
t a l P o
l l u t i o n
24 Air pollution B
C) Emission of air pollutants from vehicles and machines for construction
work are expected. O) Improvement of traffic congestion may give rise to
increase in number of vehicles travelling Ugong Road. This may also result
in increase in emission of air pollutants such as SO2, NOx, exhaust
particulates. In addition, poor emission control of many vehicles due to
insufficient maintenance and inspection may accelerate to spew out bad
smell and black smoke along the road.
25 Water pollution B
C) Water pollution due to inflow of soil and sand from construction work
and wastewater from worker' camps is expected somewhat.
26Soil
contaminationB
C) Toxic materials such as asphalt emulsifiers utilized for road construction
may give rise to soil contamination. However, extent of impact is
unknown.
27 Bottom sediment D No reclamation and dredging work is expected.
28 Waste B
C) Generation of soil, sand and construction waste is expected at quarry,
borrow pits, road construction work and worker's camp, etc.
29 Noise and
VibrationB
C) Generation of noise and vibration from construction machines and
vehicles is expected. O) Increase of noise and vibration due to increase in
traffic volume is expected.
30Ground
SubsidenceC
C) No major earth moving or reclamation is expected.
30 Offensive odor C
O) Increase in traffic volume may accelerate to spread over bad smell along
the road due to poor emission control of vehicles. However, extent ofimpact is unknown.
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 12/18
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 13/18
13
concerned organizations. conditions and livelihood after implementation.
2
Local economy
such as
employment and
livelihood etc.
D
Survey on present employment
condition and sources of
income/livelihood in the Project area.
1) Promote cooperation with other city
development projects, 2) Give local residents
preference to have a chance to construction
work.
3
Land use and
utilization of local
resources
C
Survey on existing land & resources
use and regulation.
1) Promote an adequate land and water resource
development plan.
4
Social institutions
such as social
infrastructure and
local
decision-making
institutions
C
Survey on community structures,
procedure of decision-making and
opinion leaders in the Project area.
Information disclosure and public participation
should be fully considered for all the
stakeholders from early stage of planning for
obtaining thorough understanding and consensus
of the people and communities.
5
Existing social
infrastructures
and services
D
Survey on present situation and urgent
needs of social infrastructures and
services in the Project area.
Promote cooperation with development plan of
other social infrastructure and services.
6
The poor,
indigenous of
ethnic people
C
1) Survey on living conditions and
water supply needs of vulnerable
social groups such as the poor, women
and children and indigenous ethnic
people like Maasai in the Project area.
If the poor and indigenous of ethnic people are
expected to become PAPs, their rights in relation
to land and resources must be respected and
efforts should be made to obtain the consent of
them with fully considerations to compensate
properly or support to restore the present living
condition.
7
Misdistribution of
benefit and
damage
C
Survey on past experiences and causes
which may give rise to the
misdistribution of benefit and damage
in the communities.
Consultation with stakeholders including PAPs
and community organization, should be planned
from early stage to obtain understanding and
consent among the stakeholders in order to share
equal benefit and damage.
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 14/18
14
8Local conflict of
interestsC
Survey on the causes and solutions of
local conflicts of interests in the
Project area.
Consultation with stakeholders including PAPs
and community organization, should be planned
from early stage to obtain understanding and
consent among the stakeholders in order to avoid
or minimize local conflict of interests.
9Cultural property
and heritageC
Inventory survey on cultural, historical
and religious property in the Project
area.
1) Avoid the alignment very close to churches in
the plan, 2)Promote campaign for protection of
cultural property and heritage.
10
Water usage or
Water rights and
Rights of
Common
C
Survey on water rights, fishing rights
and rights of common in the Project
area.
Promote participation of those who have the
rights and making consent in the course of the
stakeholder meeting.
11 Public health and
SanitationC
Survey on public health including
prevalence and cause of diseases, and
sanitary condition in the Project area.
12
Infectious
diseases such as
HIV/AIDS
B
Survey on existing cases and cause of
HIV/AIDS in the Project area.
1) Monitoring cases of HIV/AIDS before and
after the construction phase, 2) Enlightenment
and campaign of prevention and cure of
HIV/AIDS.
13
Hazards (cyclone,
drought, etc.) and
risk
C
Suitable planning and management of road
construction work and traffic management
operation of to prevent and minimize the hazard
and disasters.
14 Accidents C
Collect and analyze accidents data due
to construction work.
Suitable planning and management for road
construction work and for road traffic operation
to prevent and minimize the accidents.
N a t u r a l
E n v i r o n m e n t
15Topography and
GeologyC
1) Survey on the area of unstable
ground conditions, 2) Detailed survey
on ground conditions (stability,
strength, etc.) of sites.
1) Avoid the area of unstable ground conditions,
2) Measures for prevention of landslide at the
construction site
16 Soil erosion C
Survey on the area of susceptible to
soil erosion
1) Avoid the site of susceptible to soil erosion, 2)
Measures for prevention of soil erosion at
construction site.
17 Groundwater C
Detailed survey on groundwater
(capacity, quality, aquifer materials
etc.)
Measures to prevent penetration of polluted
water to underground.
18
Hydrological
situation/Drainage
pattern
C
Detailed survey on hydrological
features of rivers in the area (flow rate,
water level, water quality etc.).
Monitoring water flow and quality of Ugong
river.
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 15/18
15
19 Coastal zone D
20Fauna, Flora and
Biodiversity
B
Detailed survey on protected and/or
precious plant and animal species in
the Project area.
1) Formulate environmental management plan
for conservation of natural environment in
accordance with Beautiful and Clean NairobiPlan of the City.
21 Landscape C
Survey on important landscape in the
Project area.
1) Regulation to preserve important landscape,
2) Measure for greening water supply facilities
to harmonize surrounding landscape.
22 Meteorology D
23 Global Warming D
E n v
i r o n m e n t a l
P o l l u
t i o n
24 Air pollution B
1) Inventory survey on major air
pollution sources, 2) Collect data of
complaint about air pollution
(C) Control of emission of air pollutants (dust,
NOx etc.) from construction machines and
vehicles due to construction work. (O) Proper
management for control of vehicle exhaust
emission and establish inspection system of
exhaust gas emission
25 Water pollution B
1) Inventory survey on major water
pollution sources, 2) Survey on water
quality of rivers and streams in both
dry and rainy season.
1) Proper treatment of water pollutants generated
from construction work to comply with water
quality regulation, 2) Water quality monitoring
of rivers.
26Soil
contaminationB
Survey on present situation of soil
contamination in the Project area.
1) Prevent to accumulate of toxic materials in
soil during construction and operation phase. 2)
Monitoring of soil contamination around the
sites of earth moving and construction work
sites.
27 Bottom sediment D
Survey on present situation of bottom
sediment pollution in the Project area .
1) Monitoring of bottom sediment pollution in
rivers.
28 Waste B
1) Survey on present situation and
institutional structures of waste
management system in the Project
area, 2) Establish proper management
system of waste during construction
stage, 3) Estimation of sludge
generation from water treatment plant.
1) Careful planning and management for
construction work to minimize waste generation.
2) Proper treatment and disposal of wastes
generating from construction work.
29 Noise and
VibrationB
1) Inventory survey on source of noise
and vibration, 2) Collect data of
complaint about noise and vibration.
1) Use low-noise and vibration equipment. 2)
Examine construction schedule and avoid
working in night time. 3) Installation of
soundproof walls and buffer zones.
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 16/18
16
30Ground
SubsidenceC
Survey on complaint on ground
subsidence in the Project area
Monitoring the occurrence of ground subsidence.
30 Offensive odor C
Survey on complaint on offensive odor
in the Project area.
Proper management for control of vehicle
exhaust emission and establish inspection
system of exhaust gas emission
Note 1*, 2**, 3*** and 4**** are same as those of Table 2.
9. Consultation
9-1 Stakeholder meeting on IEE and involuntary resettlement issue
The meeting was held in the course of Preliminary Study. Participants were peoples of
Implementing Agency (KURA), Council of City Nairobi, Ministry of Lands and environment
expert.
9-2 Items of discussions
(1) Identification of major impacts due to the cooperation project and mitigation measures
Some adverse impacts are expected for environmental items of involuntary resettlement (and/or
land acquisition), air pollution, water pollution, noise and vibration etc. Among them involuntary
resettlement is a matter of main concern. Thus further efforts should be conducted to confirm ROW
to be surely secured and encroachments into ROW for identifying PAPs, and prepare Resettlement
Action Plan by KURA.
(2) EIA Approval by NEMA
It is necessary to follow the progress in EIA approval for the project by MOR at first. Then it is also
necessary to confirm if additional EIA and/or environmental and social considerations for the
cooperation project are required or not.
10. Social Acceptability in case of involuntary Resettlement and Land Acquisition
There are found gaps between Kenyan laws and donor’s policy including the JICA Guidelines
about land acquisition and involuntary resettlement. For example, cash compensation is based upon
market value and illegal encroachers are not entitled to compensation in Kenyan law, while
compensation is based on replacement cost and Project Affected Persons (PAPs) are entitled to
some forms of compensation whatever the legal/illegal recognition of the occupancy in donor’s
policy.
11. Important Notice on Basic Design Research
Before deciding the dispatch of the Basic Design Team, it is necessary to confirm the progress in
the following matters to the Kenyan sides as mentioned in 9-2.
(1) EIA Approval by NEMA
- EIA approval for the project by MOR
- Additional EIA and/or environmental and social considerations for the cooperation project arerequired or not.
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 17/18
17
(2) Identification of PAPs and preparation of RAP
- To confirm ROW to be surely secured and encroachments into ROW for identifying PAPs, and
prepare Resettlement Action Plan by KURA.
13. Other relevant Information
13.1 References
- Environmental Management and Co-ordination Act, 1999 (EMCA)
- Environmental (Impact Assessment and Audit) regulations, 2003 (EIAAR)
- Ministry of Roads: Environmental and Social Impact Assessment Study on the proposed
Upgrading of All Saints Cathedral Junction - City Mortuary - Dagoreti Corner - Ngong Town
(C61/C60) Roads - Karen - Bomas Roads” (by APEC Consortium/CAS Ltd., August 2009).
- JICA (2006.3): The Study on Master Plan for Urban Transport in the Nairobi Metropolitan Area in
the Republic of Kenya, by Katahira & Engineers International and RECS International Inc.- Office of the Deputy Prime Minister and Ministry of Local Government: The Environmental
Impact Assessment (EIA) Study – A Final Report for the Missing Links Roads NOs. 3, 6 and 7 in
the City f Nairobi (by AMI Development Services, Limited, July 2009.
- City Council of Nairobi and Permanent Secretary, Office of the Deputy Prime Minister and
Ministry of Local Government: The Study on Socio-economic Impacts and Resettlement Action
Plan for the Missing Links Numbers 3,6 &7 – Intermediate Report (August 2009).
Map 1 Location map of the project area
8/13/2019 kenya6_01
http://slidepdf.com/reader/full/kenya601 18/18
18
Map 2 Detailed Map of Ugong Road section- End -