KICK STARTING THE
PHILIPPINE RESIDENTIAL
ROOFTOP MARKET
by: Mike de Guzman
CEO, Solaric Corp.
www.solaric.com.ph
The Philippine Market
•High power rates at P12/kWh (~US $0.26/kWh)
•Fragmented- 7,107 islands, reliance on diesel peaking
plants
•Severe energy shortage on the horizon
•Frequent power outages due to shortage. Mindanao-
davao-CDO and even metro manila had some rotating
outages in 2014 and prediction is dire in 2015 with the
shutdown of Malampaya plant.
•Large popluation base in remote unelectrified areas.
Common to find entire towns with only 12 hours a day
coverage. Heavy reliance on Diesel plants.
The Power Shortage
•According to Department of Energy’s (DOE) forecast, the
worst of the rolling power outages will hit the country
second week April of 2015 when power supply deficiency is
seen at 285 megawatts
•This will most likely result in rotating power outages of up
to 2 hours.
•Severe brownouts will also be felt in March, April, and May
•The DOE said it is extremely problematic sourcing out the
system’s need for contingency reserve – placed at about
647MW for the Luzon grid.
Distribution Utilities•MERALCO is the Philippines’ largest distributor of power, powering 5.1M
customers. It accounts for 75% of Luzon and 55% of the entire Philippines’
energy sales.
Why small scale rooftop?
• It displaces the highest power rates at ~P12/kWh (~US
$0.26/kWh)
• Regulatory frameworks and Utility interconnection
policies are becoming more defined.
• Payback of Solar installations is about 5 years for
residential customers, if built below daytime baseload
• Low labor costs
•Economics now back up grid tie solar, next is
implementation and education.
RESIDENTIAL COMMERCIAL INDUSTRIAL
P12.48/kWh P 11.04/kWh P8.78/kWh
Philippine homes with solar
SOLARIC is leading the trend in rooftop PV in the Philippines. SOLARIC has the most
number of rooftop installations and the most number of approved net metering
installations in the country. We’ve installed 1MW in the past year and doubling capacity
every quarter
Philippine SMEs with solar
•Solaric does 3 to 4 rooftop installations per
week in Metro Manila, and another 3 to 4 per
week in other provinces, ranging from 500Wp
to 15kWp
•Solaric has a dealer network, a sales training
program, and an installer training program
Permitting & Net Metering
•Submit Net Metering application form to Distribution
Utility (DU)
•Submit Electrical Permit & certificate application to
City hall
• Wait for contract, permit/certification, and finally,
installation of the net meter
•The whole process takes 3 months to 6 months,
depending on the area having jurisdiction, and multiple
visits to the DU office and various city hall offices.
•Other DUs don’t have a Net Metering application form
yet, we have to provide one. In these instances, it could
take up to 10 months or more.
Net meters installed90 Days from application
to code retrofit, to
approval and net meter
installation.
Total cost: P14,000 (USD
$311)
78 Days from
application to code
retrofit, to approval and
net meter installation.
Total cost: P10,000
(USD $222)
Permitting Costs
• Net Metering Distribution Impact Study : P5,500 or
P19,500 – depends on the DU.
• ERC charges P1,500 (collected by the DU)
• City Halls charge anywhere from P1,500 to P11,000+
• Best case scenario total: P8,500 (US $188)
•Worst case scenario total: P42,000+ (US $933)
•Total Average Cost: P12,000 (US $266)
*costs do not include time / manpower
Philippine’s first POP-NET (Peak Off Peak with Net Metering) Installation
Other Costs
•Most homes older than 3 years or so do not have a
“service disconnect” and will also be required to change
their “meter base” to have a Net Meter installed. This
will cost the homeowner roughly P8,000 to P20,000+
depending on size of main line. (US $ 177 to $444+)
Inspections
DU and City Hall inspection of customer facilities include:
• service disconnect, grounding, certification of equipment,
verification of anti-islanding and reclosing times, etc.
•Must pass all requirements prior to the installation of
actual Net Meter.
No Net Metering?
• Without net metering, its highly likely
the unidirectional meter will count any
export as consumption – customer’s bill
will go up.
• No requirements on the DU end, but
the local building department / City
Hall requires an electrical permit.
Supply Chain Economics
• Expensive logistics channel to get goods through to
Manila.
•Red tape, brokerage fees, VAT, port delays and
congestion.
•Solar Modules are DUTY FREE, but must still pay VAT.
All other items (rails, inverters, etc have a duty and a
VAT)
•It costs almost the same amount of money to get a
container from Shanghai to Manila, vs a truck from
Manila port to an address within Manila.
•It takes 3-5 days from Guangzhou to Manila, but 10 to
14 days to unload the boat due to port congestion
The Market
• Clients demand local presence for after sales
service and warranty - looking for dependable
outfits at reasonable rates
• Clients are looking for hybrid grid-tie and off-grid
solutions due to the looming power crisis.
Hybrid OffGrid•San Jose Nat’l High School, Tacloban
•10kVa, 3kW with 48V/400Ah
battery bank – enough to power 2hp
aircon and 20+ computers
The Market
• Financing or loans to middle class consumers will
open the floodgates to mass adaptation. If we can
prove that monthly payments are less than
savings created by solar it will be a win-win
proposition.
•PPA agreements to large institutional users, and
also light commercial 10-100kWp and 100kWp to
2 MW, heavy industrial users. 15 year PPA
The Market
�The Philippine market is vast and the need for cost effective
renewable energy is universal.
Technology Transfer
SOLARIC provides training on the basics of PV, as well as PV
installer training for it’s nationwide network of installers and
dealers.
Typhoon Haiyan Relief Efforts
SOLARIC has put power in schools, geothermal power plants, hospitals, churches, town centers,
clinics, police stations