Dear Ladies and gentlemen,

Kostroma region that I have the honour to represent has an abundant history of the successful partnership, the unique productions and natural resources.

This edition presents the investment appeal in the most perspective sectors, which are capable to open new hori-zons for your business development.

We do our best to extend the competitive advantages of the Kostroma region creating the most comfortable con-ditions for investments improving the measures of the ad-ministrative barriers lowering.

Your business development plans will be realized in the Kostroma region at the forming investment sites. From our side we provide you with necessary infrastructure.

We invite you to the mutually profitable business partner-ship.

Welcome to the hospitable Kostroma region.Sergey Sitnikov

Kostroma region Governor

Page 3: Kostroma region investment proposals 2012

3

Land lots for the industrial sites location ...................................... 5

Land lots for farming ....................................................................... 27

Investment proposals ...................................................................... 63

Industrial park “Industrial`nyi” ....................................................... 79

CONTENT

Page 4: Kostroma region investment proposals 2012
Page 5: Kostroma region investment proposals 2012

LAND LOTS FOR THE INDUSTRIAL SITES LOCATION

Page 6: Kostroma region investment proposals 2012

Kostromadistance to:

Yaroslavl` (75 km)

Nizhnii Novgorod (300 km)

Ivanovo (100 km)

Moscow (345 km)

Vologda (280 km)

Page 7: Kostroma region investment proposals 2012

7

Land lot limited by the streets Industrial`naya-Bazovaya-Galichskoe highway (Kostroma)

Area - 23,6 ha

Transport availabilityDistance to:Railway station – 5,4 km;• River port – 11,5 km;• Motorway sides with the land lot.•

Civil engineering infrastructure avaliabilityPower supply – along the land lot border;• Gas supply – 170 m far from the land lot border close to Vostochnyi • lane, out of Kostroma city territory;Heat supply – 350 m far from the land lot close to No.4 Vostochnyi • lane;Water supply – 300 m far from the land lot close to No.2 Vostochnyi • lane;Sewerage system - alongside the land lot border;• Communication cable - alongside the land lot border.•

Land lot usagePlacement of the industrial objects.

Page 8: Kostroma region investment proposals 2012

Kostromadistance to:

Yaroslavl` (75 km)

Nizhnii Novgorod (300 km)

Ivanovo (100 km)

Moscow (345 km)

Vologda (280 km)

Page 9: Kostroma region investment proposals 2012

9

Land lot in Moskovskaya Street near the Klyuchevka - river (Kostroma)

Area - 38,0 ha

Transport availabilityDistance to:Motorway: Moskovskaya Str. – 10 m;• Magistral`naya Str. – 300 m;• Railway – 1,2 km;• houses – 1,1 km•

Civil engineering infrastructure avaliabilityPower supply – 6 m far from the land lot close to Moskovskaya Str.;• Gas supply – 72 m far from the land lot close to Moskovskaya Str.;• Water supply – 20 m in the land lot close to Moskovskaya Str., piping • d-250; 60 m far from the land lot there is a d-800 piping;Sewerage system - 73 m far from the land lot close • to Moskovskaya Str.;Communication cable - across the land lot border from the Moskovs-• kaya Str. side.

Land lot usagePlacement of the industrial objects.

Page 10: Kostroma region investment proposals 2012

Kostromadistance to:

Yaroslavl` (75 km)

Nizhnii Novgorod (300 km)

Ivanovo (100 km)

Moscow (345 km)

Vologda (280 km)

Page 11: Kostroma region investment proposals 2012

11

Cluster in Magistral`naya street (Kostroma)

Area - 59,6 ha

Transport availabilityLocated out of the city borderDistance to:Motorway: Moskovskaya Str. – 10 m;• Solonkovskaya Str. – 10 m;• Railway – 1,0 km.•

Civil engineering infrastructure avaliabilityPower supply – 120 m far from the land lot close to Magistral`naya Str.; • Power cable goes alongside Solonikovskaya Str.Gas supply – 65 m far from the land lot close to Soloikovskya Str.;• Water supply – piping of d-150 crosses the land lot, • close to Solonikovskaya Str. there is as well piping d-500;Sewerage system – alongside the land lot • close the Magistral`naya Str.;Communication cable – alongside Magistral`naya Str.•

Land lot usagePlacement of the industrial objects.

Page 12: Kostroma region investment proposals 2012

Kostromadistance to:

Yaroslavl` (75 km)

Nizhnii Novgorod (300 km)

Ivanovo (100 km)

Moscow (345 km)

Vologda (280 km)

Page 13: Kostroma region investment proposals 2012

13

Land lot on the territory of Baksheevskoe rural settlement close to OAO “Motordetal”

Area - 40,0 ha

Transport availabilityLocated out of the city borderDistance to:Motorway Kostroma-Yaroslavl`– 10 m;• Railway-300 m.•

Civil engineering infrastructure avaliabilityPower supply – 0,3 km far from the land lot border;• Gas supply – 0,5 km far from the land lot border, pressure – 159 kg;• Water supply – 0,3 km far from the land lot;• Sewerage system – crosses the land lot;• Communication cable – crosses the land lot.•

Land lot usagePlacement of the industrial objects.

Page 14: Kostroma region investment proposals 2012

Kostromadistance to:

Yaroslavl` (75 km)

Nizhnii Novgorod (300 km)

Ivanovo (100 km)

Moscow (345 km)

Vologda (280 km)

Page 15: Kostroma region investment proposals 2012

15

Land lot in Solonikovskaya street, close to No.6

Area - 4,35 ha

Transport availabilityDistance to:Solonikovskaya Str.– 300 m;• Railway – 630 m.•

Civil engineering infrastructure avaliability Power supply – 300-500 m;• Gas supply – 300-500 m;• Water supply – 300-500 m;• Railway•

Land lot usagePlacement of the industrial objects.

Page 16: Kostroma region investment proposals 2012

Volgorechenskdistance to:

Moscow (357 km)

Kostroma (43 km)

Yaroslavl` (122 km)

Ivanovo (65 km)

Page 17: Kostroma region investment proposals 2012

17

Land lot limited by:Volgorechensk-Ivankovo-Vladychnoe-Rostilovo-hole Pozdeevo-the Ivanovo region border up to Volgorechensk

Area - 3 600 ha

Transport availability

Motorways:Volgorechensk-Ivankovo-Vladychnoe – 6 km of asphalt• Ivankovo-Tolstokvasovo-Gorki-Neronovo – 11 km of asphalt;• Tolstokvasovo-Mikshino – 3 km of earth road;• Vladychnoe-Rastilovo-hole Pozdeevo-the Ivanovo region border – • 5,5 km of earth road.

Civil engineering infrastructure availabilityPower supply – there two lines VL-220 kW on the territory of the land • lot. The substation is needed;Gas supply – distributing net is 1 km from the land lot border;• Heat supply – there are two variants: gas boiling room or central heat-• ing supply from Kostroma regional power station – distance from the land lot border – 6 km;Water intake facility are 1,5 km far from the land lot border;• Sewerage system is 5,5 km far from the land lot border;•

Land lot usagePlacement of the industrial objects.

Page 18: Kostroma region investment proposals 2012

Kostromadistance to:

Yaroslavl` (75 km)

Nizhnii Novgorod (300 km)

Ivanovo (100 km)

Moscow (345 km)

Vologda (250 km)

Page 19: Kostroma region investment proposals 2012

19

Land lot situated on the west side of the village Pustoshki

Area - 35,4 ha

Transport availabilityFrom the South the lot has the common border with the motorway • Kostroma-V.Spasskoe (Nikol`skoe rural settlement);Railway is on the North of the land lot.•

Civil engineering infrastructure avaliabilityPower supply – on the territory of v.Pustoshki;• Gas supply – on the territory of v.Pustoshki.•

Land lot usagePlacement of the industrial objects.

Page 20: Kostroma region investment proposals 2012

Kostromadistance to:

Yaroslavl` (75 km)

Nizhnii Novgorod (300 km)

Ivanovo (100 km)

Moscow (345 km)

Vologda (250 km)

Page 21: Kostroma region investment proposals 2012

21

Land lot surrounding the village Pyesikovo

Area - 59,3 ha

Transport availability

From the South the lot has the common border with the railway; • Motorway – 3 km far from the land lot.•

Civil engineering infrastructure availability Power supply – VL-35 kW•

Land lot usagePlacement of the industrial objects.

Page 22: Kostroma region investment proposals 2012

Kostromadistance to:

Yaroslavl` (75 km)

Nizhnii Novgorod (300 km)

Ivanovo (100 km)

Moscow (345 km)

Vologda (250 km)

Page 23: Kostroma region investment proposals 2012

23

Land lot to the North of the village Kharino

Area - 66,5 ha

Transport availability

From the South the lot has the common border with the railway; • Motorway – 500 m far from the land lot.•

Civil engineering infrastructure availability Power supply – 200 m far from the land lot, on the territory of v.Kharino;• Gas supply – 200 m far from the land lot, on the territory of v.Kharino.•

Land lot usagePlacement of the industrial objects.

Page 24: Kostroma region investment proposals 2012

Kostromadistance to:

Yaroslavl` (75 km)

Nizhnii Novgorod (300 km)

Ivanovo (100 km)

Moscow (345 km)

Vologda (250 km)

Page 25: Kostroma region investment proposals 2012

25

Land lot 500 m to the West from the village Gubachevo

Area - 1,5 ha

Transport availabilityDistance to:The Centre of the city – 7 km; • Motorway Kostroma – V.Spasskoe – 800 m;• Railway – 1,5 km.•

Civil engineering infrastructure availabilityPower supply – 200 m far from the land lot.•

Land lot usagePlacement of the industrial objects.

Page 26: Kostroma region investment proposals 2012
Page 27: Kostroma region investment proposals 2012

LAND LOTS FOR FARMING

Page 28: Kostroma region investment proposals 2012

Antropovodistrict

Page 29: Kostroma region investment proposals 2012

29

Land lot of the village Prosek

Area - 631,4 ha

Transport availabilityDistance to the regional centre:By motorway – 167 km; • By railway (Antropovo station) – 178 m;• Distance to the district centre – 3 km;• Road with asphalt covering.•

Land lot property Regional

Civil engineering infrastructure availability Power supply – power line up to 1000 V;• Water supply - artesian well.•

Land lot usagePlacement of the agricultural objects.

Page 30: Kostroma region investment proposals 2012

Царево

Bui district

Page 31: Kostroma region investment proposals 2012

31

Land lot of the village Tsaryovo

Area - 100 ha (possibility of expansion to 200 ha)

Transport availabilityDistance to the regional centre – 67 km;• Distance to the district centre – 25 km;• 1,5 km of the earth road till the motorway Kostroma-Bui.•

Land lot property Regional.

Civil engineering infrastructure availabilityPower supply – own substation for 250 kWt;• Water supply - artesian well;• Gas supply – average pressure 128.•

Labor resources Area population is about 600 people including 250 employable.

Land lot usagePlacement of the agricultural objects.

Page 32: Kostroma region investment proposals 2012

Bui district

Page 33: Kostroma region investment proposals 2012

33

Land lot of the village Baranovo

Area - 475 ha

Transport availabilityDistance to the regional centre:By motorway – 100 km; • Railway (Bui station);• Road with asphalt covering• Distance to the district centre – 2 km.•

Land lot propertyThe land lot is under the procedure of converting into the regional property.

Civil engineering infrastructure availabilityPower supply – power line up to 1000 V;• Water supply - artesian well;• Gas supply – average pressure.•

Labor resourcesArea population is about 600 people.

Land lot usagePlacement of the agricultural objects.

Page 34: Kostroma region investment proposals 2012

Борок

Buidistrict

Page 35: Kostroma region investment proposals 2012

35

Land lot of the village Borok

Area - 371,7 ha

Transport availabilityDistance to the regional centre – 100 km;• Distance to the district centre – 10 km;• Road with asphalt covering. •

Land lot propertyThe land lot is under the procedure of converting into the regional property.

Civil engineering infrastructure availabilityPower supply – power line up to 1000 V;• Water supply - artesian well;• Gas supply – average pressure.•

Labor resourcesArea population is about 250 people.

Land lot usagePlacement of the agricultural objects.

Page 36: Kostroma region investment proposals 2012

Manturovodistrict

Page 37: Kostroma region investment proposals 2012

37

Land lotof the village Falino

Area - 3 ha (possibility of expansion)

Transport availabilityDistance to the regional centre – 280 km;• Distance to the district centre – 25 km;• Road with asphalt covering - 15 km;• Road with crushed stone covering - 10 km.•

Land lot propertyPrivate.

Civil engineering infrastructure availabilityElectrified.

CommentHalf-ruined livestock farm.

Land lot usagePlacement of the agricultural objects.

Page 38: Kostroma region investment proposals 2012

Mezhadistrict

Page 39: Kostroma region investment proposals 2012

39

Land lotof the Industrial complex

Area - 6 ha

Transport availabilityDistance to the regional centre – 360 km;• Distance to the district centre – 1 km;• Road with asphalt covering.•

Land lot propertyMunicipal.

Civil engineering infrastructure availabilityPower supply – power line up to 1000 V.

Labor resourcesAvailable.

CommentObject is not completed, no roof.

Land lot usagePlacement of the industrial objects.

Page 40: Kostroma region investment proposals 2012

Mezhadistrict

Page 41: Kostroma region investment proposals 2012

41

Land lot of the village Georgievskoe Production base of the former Industrial complex

Area - 4 ha (possibility of expansion)

Transport availabilityDistance to the regional centre – 360 km; • Road with asphalt covering.•

Land lot propertyPrivate.

Civil engineering infrastructure availabilityPower supply – power line up to 1000 V.

Labor resourcesAvailable.

CommentsThe construction total area 300 m2.Ceiling height exceeds 6 m.Barrels for petroleum product are available.Garage and warehouse avaliable.

Land lot usagePlacement of the industrial objects.

Page 42: Kostroma region investment proposals 2012

Mezhadistrict

Page 43: Kostroma region investment proposals 2012

43

Land lot of the village Serednyaya Production base of the former agricultural college

Area - 3 ha (possibility of expansion)

Transport availabilityDistance to the regional centre – 360 km; • Distance to the district centre – 5 km;• Road with asphalt covering. •

Land lot propertyPrivate.

Civil engineering infrastructure availabilityElectrified.

Labor resourcesAvailable.

CommentsCeiling height exceeds 6 m.Warehouse available.

Land lot usagePlacement of the industrial objects.

Page 44: Kostroma region investment proposals 2012

Nerekhtadistrict

Page 45: Kostroma region investment proposals 2012

45

Land lotof the village Yakushovka

Area - 30 ha (possibility of expansion up to 200 ha)According to the Land distribution Fund data there are about 655 ha of agricultural lands

Transport availabilityDistance to the regional centre – 35 km; • Distance to the district centre – 3 km;• Road with asphalt covering. •

Land lot propertyMunicipal.

Civil engineering infrastructure availabilityPower supply – power line up to 1000 V;• Water supply - artesian well;• Gas supply – average pressure 108.•

Labor resourcesPopulation is 708 people including employable 400.

CommentsCeiling height exceeds 6 m.Warehouse available.

Land lot usagePlacement of the agricultural objects.

Page 46: Kostroma region investment proposals 2012

Sudislavl`district

Page 47: Kostroma region investment proposals 2012

47

Land lot of the village AleksandrovoState farm “Aleksandrovskii”

Area - 2 325 ha

Transport availabilityDistance to the regional centre – 64 km; • Distance to the district centre – 12 km;• Road with gravel (partially earth) covering. •

Land lot propertyPrivate, share, municipal, Land distribution Fund.

Civil engineering infrastructure availabilityPower supply – substation;• Water supply - artesian well.•

Land lot usagePlacement of the agricultural objects.

Page 48: Kostroma region investment proposals 2012

Sudislavl`district

Page 49: Kostroma region investment proposals 2012

49

Land lot of the village IsajevoOOO “Isajevo”

Area - 1 611 ha

Transport availabilityDistance to the regional centre – 92 km; • Distance to the district centre – 42 km;• Road with gravel (partially earth) covering. •

Land lot propertyPrivate, share, municipal.

Civil engineering infrastructure availabilityPower supply - available;• Water supply - artesian well.•

Land lot usagePlacement of the agricultural objects.

Page 50: Kostroma region investment proposals 2012

Sudislavl`district

Page 51: Kostroma region investment proposals 2012

51

Land lot of the village ZhvalovoAgricultural customer cooperation “Zhvalovo”

Area - 2 587 ha

Transport availabilityDistance to the regional centre – 55 km; • Distance to the district centre – 6 km;• Road with gravel (partially earth) covering.•

Land lot propertyPrivate (2 016 ha);Share (414,4 ha);Municipal (156,9 ha).

Civil engineering infrastructure availabilityPower supply – available;• Water supply - artesian well.•

Land lot usagePlacement of the agricultural objects.

Page 52: Kostroma region investment proposals 2012

Sudislavl`district

Page 53: Kostroma region investment proposals 2012

53

Land lot of the village SvozovoAgricultural customer cooperation “Svozovo”

Area - 2 627 ha

Transport availabilityDistance to the regional centre – 84 km; • Distance to the district centre – 32 km;• Road with gravel (partially earth) covering. •

Land lot propertyPrivate (496 ha);Share (1 508 ha);Municipal (623 ha).

Civil engineering infrastructure availabilityPower supply – available;• Water supply - artesian well.•

Land lot usagePlacement of the agricultural objects.

Page 54: Kostroma region investment proposals 2012

Sudislavl`district

Page 55: Kostroma region investment proposals 2012

55

Land lot of the village OshurkiAgricultural customer cooperation “Rassvet”

Area - 2 195 ha

Transport availabilityDistance to the regional centre – 64 km; • Distance to the district centre – 12 km;• Road with gravel (partially earth) covering; • Railway route KOSTROMA-GALICH runs through the territory of the • land lot.

Land lot propertyPrivate (1415 ha);Share (536 ha);Municipal (244 ha).

Civil engineering infrastructure availabilityPower supply – available;• Water supply - artesian well.•

Land lot usagePlacement of the agricultural objects.

Page 56: Kostroma region investment proposals 2012

Sudislavl`district

Page 57: Kostroma region investment proposals 2012

57

Land lot of the village ZavrazhjeAgricultural customer cooperation “Zavrazhje”

Area - 672,2 ha

Transport availabilityDistance to the regional centre – 64 km; • Distance to the district centre – 12 km;• Road with gravel (partially earth) covering.•

Land lot propertyPrivate (402,7 ha);Share (192,5 ha);Municipal (77 ha).

Civil engineering infrastructure availabilityPower supply – available;• Water supply - artesian well;• Gas supply - projected.•

Land lot usagePlacement of the agricultural objects.

Page 58: Kostroma region investment proposals 2012

Sudislavl`district

Page 59: Kostroma region investment proposals 2012

59

Land lotof the village ShakhovoCollective farm “Rossia”

Area - 2 929 ha

Transport availabilityDistance to the regional centre – 57 km; • Distance to the district centre – 7 km;• Road with gravel (partially earth) covering.•

Land lot propertyPrivate (1 817 ha);Share (1 112,6 ha).

Civil engineering infrastructure availabilityPower supply – available;Water supply - water tower;Gas supply - projected.

Land lot usagePlacement of the agricultural objects.

Page 60: Kostroma region investment proposals 2012

Sudislavl`district

Page 61: Kostroma region investment proposals 2012

61

Land lot of the village KalinkiFormer Agricultural customer cooperation “Oktyabr`”

Area - 1 809 ha

Transport availabilityDistance to the regional centre – 22 km; • Distance to the district centre – 30 km;• Motorway (partially earth covering).•

Land lot propertyPrivate (945,9 ha);Share (505 ha);Municipal (358,1 ha).

Civil engineering infrastructure availabilityPower supply – available;• Water supply - artesian well.•

Land lot usagePlacement of the agricultural objects.

Page 62: Kostroma region investment proposals 2012
Page 63: Kostroma region investment proposals 2012

INVESTMENT PROPOSALS

Page 64: Kostroma region investment proposals 2012

WOOD PROCESSING INDUSTRYProject name Construction of the pulp-paper plant

Location of the project realization

subject of the Russian Federation Kostroma region

municipality Manturovo municipal district(Manturovo township)

Project coordinator Name Forestry department of the Kostroma regionPostal addressTelephoneFaxe-mail addressweb-site

128a, Mira avenue,156013 Kostroma007(4942) 55-36-21007(4942)[email protected]://www.kostroma-depleshoz.ru

Project description Sector Deep wood processing

Target of the project Production of the competitive capable to replace import paper and cardboard goods

Basic products (usage) Paper, cardboard

Production capacityPlain paper - 250 000 tonCoated paper – 250 000 tonCoated cardboard – 300 000 ton

Trade area Russia, the near abroad and foreign countries

Main competitors Pulp-paper plants in Ust`-Ilimsk and in Arkhangel`sk

Financial aspects Project total cost 51 billion RUR

Forms of investment Direct investments, equipment delivery, long-term partnership, share in building

NPV 21 897 million RURDPB 10,8 yearsPlanning period 15 yearsIRR 16,5%

Additional information Project is included in the list of the prior investment projects in Kostroma region in the sphere of forest exploitation

Contact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33Email address spi@[email protected]

Page 65: Kostroma region investment proposals 2012

Project name Creation of the OSB production in the Kostroma region

Location of the project realization

Subject of the Russian Federation Kostroma region

municipality Bui municipal districtProject coordinator Name Forestry department of the Kostroma region

Postal addressTelephoneFaxe-mail addressweb-site

128a, Mira avenue,156013 Kostroma007(4942) 55-36-21007(4942)[email protected]://www.kostroma-depleshoz.ru

Project description Sector Deep wood processing

Target of the project

Maximal satisfaction of the home market needs for boards OSB produced with the usage of the new technologies and equipment

Basic products (usage) OSB boards

Production capacity 400 000 m3

Trade area Russian Federation

Main competitors No competitors in RussiaFinancial aspects Project total cost 5 445 million RUR

Forms of investment Direct investments, equipment delivery, long-term partnership, share in building

NPV 4 663,9 million RUR

DPB 6,75 years

Planning period 13 years

IRR 31,85%Additional information Estimated annual cutting area volume

– 725 000 m3 Forest composition: 4B2As2P2F

Contact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 66: Kostroma region investment proposals 2012

Project name Creation of the integrated house-building factory in the Kostroma region

Location of the project realization

Subject of the Russian Federation Kostroma region

municipality Chukhloma municipal district

Project coordinatorName Forestry department of the Kostroma region

Postal addressTelephoneFaxe-mail addressweb-site

128a, Mira avenue,156013 Kostroma007(4942) 55-36-21007(4942)[email protected]://www.kostroma-depleshoz.ru

Project description Sector Deep wood processing

Target of the project Creation of the complete wood processing complex

Basic products (usage) House assembly

Production capacity Up to 180 000 m3 per year

Trade area CFD regions

Main competitors CFD productionsFinancial aspects Project total cost 900 million RUR

Forms of investmentDirect investments, equipment delivery, long-term partnership, share in building

NPV 247,9 million RUR

DPB 5 years

Planning period 7 years

IRR 24,7%Additional information Estimated annual cutting area volume

– 175 000 m3Contact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 67: Kostroma region investment proposals 2012

Project nameCreation of the modern wasteless timber processing production

in the Kostroma region

Location of the project realization

subject of the Russian Federation Kostroma region

municipality Vokhma municipal district

Project coordinator Name Forestry department of the Kostroma region

Postal addressTelephoneFaxe-mail addressweb-site

128a, Mira avenue,156013 Kostroma007(4942) 55-36-21007(4942)[email protected]://www.kostroma-depleshoz.ru

Project description Sector Deep wood processing

Target of the project Competitive production output

Basic products (usage)Squared beamBoardPellet

Production capacity 72 000 m3 of lumber72 000 m3 of pellets

Trade area Russian Federation

Main competitors Far offFinancial aspects Project total cost 900 million RUR

Forms of investment Direct investments, equipment delivery, long-term partnership, share in building

NPV 268,8 million RUR

DPB 3,7 years

Planning period 6 years

IRR 53,9 %Additional information Estimated annual cutting area volume

– 180 000 m3Contact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 68: Kostroma region investment proposals 2012

Project nameCreation of the production of furniture workpieces made out of birch in the

Kostroma region

Location of the project realization

subject of the Russian Federation Kostroma region

municipality Shar`ja municipal districtProject coordinator

Name Forestry department of the Kostroma region

Postal addressTelephoneFaxe-mail addressweb-site

128a, Mira avenue,156013 Kostroma007(4942) 55-36-21007(4942)[email protected]://www.kostroma-depleshoz.ru

Project description Sector Deep wood processing

Target of the project Organization of the furniture components production

Basic products (usage) Furniture platesWood chips

Production capacity 40 000 m3 of ready goods80 000 m3 of chips

Trade area Russian Federation, EU countries

Main competitors Far offFinancial aspects Project total cost 1,5 billion RUR

Forms of investmentDirect investments, equipment delivery, long-term partnership, share in building

NPV 122,6 million RUR

DPB 7 years

Planning period 10 years

IRR 28,4 %Additional information Estimated annual cutting area volume

– 160 000 m3Contact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 69: Kostroma region investment proposals 2012

Project nameConstruction of the plant producing granulated timber-fuel (pellets) and

lumber in the Kostroma region

Location of the project realization

Subject of the Russian Federation Kostroma region

municipality Galich municipal districtProject coordinator

Name Forestry department of the Kostroma region

Postal addressTelephoneFaxe-mail addressweb-site

128a, Mira avenue,156013 Kostroma007(4942) 55-36-21007(4942)[email protected]://www.kostroma-depleshoz.ru

Project description Sector Deep wood processing

Target of the project Organization of the production of the innovative goods - pellets

Basic products (usage) Lumber Pellets

Production capacity 120 000 m3 of lumber140 000 m3 of pellets

Trade area Russian Federation, EU countries

Main competitors CFD productionsFinancial aspects Project total cost 2 billion RUR

Forms of investment Direct investments, equipment delivery, long-term partnership, share in building

NPV 396 million RUR

DPB 6 years

Planning period 8 years

IRR 27,6 %Additional information Estimated annual cutting area

volume – 200 000 m3Contact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 70: Kostroma region investment proposals 2012

EXTRACTION AND PROCESSIING OF MINERAL RESOURCESProject name Construction of the ferrosilicon plant in the Kostroma region

Location of the project realization

Subject of the Russian Federation Kostroma region

municipality Bui municipal districtProject coordinator

NameThe department of natural resources and environmental protection of the Kostroma region

Postal addressTelephoneFaxe-mail addressweb-site

128a, Mira avenue,156013 Kostroma007(4942) 55-36-21007(4942)[email protected]://www.dpr44.ru

Project descriptionSector Extraction and processing of mineral

resources

Target of the project Creation of the ferrosilicon production – the fi rst one in the European part of Russia

Basic products (usage) Ferrosilicon FS75

Production capacity 20 000 ton

Trade area European Russian iron and steel plants

Main competitors Far offFinancial aspects Project total cost 4 020 million RUR

Forms of investment Direct investments, equipment delivery, long-term partnership, share in building

NPV 128,7 million RUR

DPB 5,9 years

Planning period 9 years

IRR 9,2 %Additional information Estimated annual cutting area volume

– 169 000 m3 High-silica sand deposits – 40 million ton

Contact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 71: Kostroma region investment proposals 2012

Project nameExtraction and processing of sapropel at the deposit “Galichskoe”

in the Kostroma region

Location of the project realization

subject of the Russian Federation Kostroma region

municipality Galich municipal districtProject coordinator

NameThe department of natural resources and environmental protection of the Kostroma region

Postal addressTelephoneFaxe-mail addressweb-site

128a, Mira avenue,156013 Kostroma007(4942) 55-36-21007(4942)[email protected]://www.dpr44.ru

Project descriptionSector Extraction and processing of mineral

resources

Target of the projectOrganization of the extraction and processing of sapropel, construction of the processing plant

Basic products (usage) Farming, municipal engineering, chemical and pharmaceutical industries, other

Production capacity 10 000 ton

Trade area Russia, CNI and foreign countries

Main competitors Producers of chemical fertilizerFinancial aspects Project total cost 580 million RUR

Forms of investment Direct investments, equipment delivery, long-term partnership, share in building

NPV 193,3 million RUR

DPB 7,5 years

Planning period 10 years

IRR 26,8 %Additional information Estimated sapropel deposit of the

Galichskoe Lake – 258 195 000 tonThe capacity of sapropel deposition is about 12,0 m with average index of 5,73 m

Contact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 72: Kostroma region investment proposals 2012

Project namePeat extraction at the deposits “Kremnevo”, “Chapyzhnoe”, “Petrovskoe”

and construction of the peat pellet plantin the Kostroma region

Location of the project realization

subject of the Russian Federation Kostroma region

municipality Pyschug municipal districtProject coordinator

NameThe department of natural resources and environmental protection of the Kostroma region

Postal addressTelephoneFaxe-mail addressweb-site

128a, Mira avenue,156013 Kostroma007(4942) 55-36-21007(4942)[email protected]://www.dpr44.ru

Project descriptionSector Extraction and processing of mineral

resources

Target of the project Increase of local fuel assortment in the fuel balance of the Kostroma region

Basic products (usage)Peat pelletMilled peatFarming peat

Production capacity 50 000 ton

Trade area Russia

Main competitors Far off Financial aspects Project total cost 100 million RUR

Forms of investment Direct investments, equipment delivery, long-term partnership, share in building

NPV 45,5 million RUR

DPB 5,5 years

Planning period 8 years

IRR 22,8 %Additional information Estimated peat deposits - 7,7 million

tonContact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 73: Kostroma region investment proposals 2012

AGRICULTURAL SECTORProject name Creation of the dairy farm for 1200 heads

Location of the project realization

subject of the Russian Federation Kostroma region

municipality Susanino municipal districtProject coordinator

Name The department of the agricultural sector of the Kostroma region

Postal addressTelephoneFaxe-mail addressweb-site

37, Marshala Novikova Street,156602 Kostroma007(4942) [email protected]://www.apkkostroma.ru

Project description Sector Agricultural sector

Target of the project Increase of heavy beasts livestock

Basic products (usage) Milk,Milk products

Production capacity 9,6 thousand ton

Trade area Russia

Main competitors Far off Financial aspects Project total cost 534,6 million RUR

Forms of investment Direct investments, equipment delivery, long-term partnership, share in building

NPV 5,96 million RUR

DPB 6 years

Planning period 8 years

IRR 10,72 %Additional information The land lot area – 3 600 haContact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 74: Kostroma region investment proposals 2012

BUILDINGProject name Construction of the housing estate “Agashkina Gora”

Location of the project realization

subject of the Russian Federation Kostroma region

municipality Kostroma

Project coordinator Name The building, architecture and urban planning department of the Kostroma region

Postal addressTelephoneFaxe-mail addressweb-site

17, Sennaya Street,156602 Kostroma007(4942) 31-28-12007(4942)[email protected]://www.depstroyko.ru

Project description Sector Building

Target of the project Creation of the up-to-date residential complex

Living area 121 000 m3

Flats number 2 190

Main competitors Building companies of Kostroma

Financial aspects Project total cost 5 569,5 million RUR

Forms of investment Direct investments, share in building

NPV 149,9 million RUR

DPB 3,3 years

Planning period 4 years

IRR 6,04 %

Additional information The land lot area 23,6 ha

Contact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 75: Kostroma region investment proposals 2012

Project name Construction of the cement plant, annual capacity - 2,7 million ton

Location of the project realization

Subject of the Russian Federation Kostroma region

municipality Susanino municipal district Project coordinator

Name The building, architecture and urban planning department of the Kostroma region

Postal addressTelephoneFaxe-mail addressweb-site

17, Sennaya Street,156602 Kostroma007(4942) 31-28-12007(4942)[email protected]://www.depstroyko.ru

Project description Sector Building materials production

Target of the project Creation of the modern industrial production

Basic products Cement

Production capacity 2,7 million ton

Trade area Russia

Main competitors Far offFinancial aspects Project total cost 14,8 billion RUR

Forms of investment Direct investments, equipment delivery, long-term partnership, share in building

NPV 3,4 billion RUR

DPB 5 years

Planning period 12 years

IRR 16,3 %Additional information For the project implementation

it is possible to use Bedinskoe deposit

Contact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 76: Kostroma region investment proposals 2012

PROCESSING INDUSTRYProject name Creation of the energy-efficient lamps production

Location of the project realization

Subject of the Russian Federation Kostroma region

municipality Nerekhta and Nerekhta municipal district Project coordinator

Name Body of investment and industrial policy of the Kostroma region

Postal addressTelephoneFaxe-mail address

15, Dzerzhinskogo Street,156006 Kostroma007(4942) 31-20-01007(4942) [email protected]

Project description Sector Industrial production

Target of the projectCreation of the production for output of the advanced technology products – energy-effi cient lamps

Basic products Energy-effi cient lamps

Production capacity 28 million pcs

Trade area Russia

Main competitors Low-quality products from AsiaFinancial aspects Project total cost 2 billion RUR

Forms of investment Direct investments, equipment delivery, long-term partnership, share in building

NPV 2 164,7 million RUR

DPB 4,9 years

Planning period 7 years

IRR 31,8 %Additional information

Land lot area of the plant – 20 ha There is a possibility of OAO ROSNANO partnership

Contact data Tel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 77: Kostroma region investment proposals 2012

ENERGYProject name Construction of the building block boiler rooms

Location of the project realization

Subject of the Russian Federation Kostroma region

municipality

Project coordinator

Name The department of the fuel-energy complex and tariff policy of the Kostroma region

Postal addressTelephoneFaxe-mail addressweb-site

129G, Sverdlova Street,156029 Kostroma007(4942) 31-52-13007(4942) [email protected]://tektarif.ru

Project description

Sector Heat power engineering

Target of the project Creation of the modern system of the heat supply

Basic products Heat energyHot water

Production capacity 35 000 Hkal

Trade area Kostroma region

Main competitors Absent

Financial aspects

Project total cost 100 million RUR

Forms of investment Direct investments, equipment delivery, long-term partnership, share in building

NPV 8,5 million RUR

DPB 5 years

Planning period 7 years

IRR 16,28 %

Additional informationThe project can be implemented in the form of state-and-private partnership

Contact dataTel.:/fax 007(4942) 31-20-01 / 31-87-33

Email address spi@[email protected]

Page 78: Kostroma region investment proposals 2012
Page 79: Kostroma region investment proposals 2012

INDUSTRIAL PARK “INDUSTRIAL`NYI”

Page 80: Kostroma region investment proposals 2012

Kostromadistance to:

Yaroslavl` (75 km)

Nizhnii Novgorod (300 km)

Ivanovo (100 km)

Moscow (345 km)

Vologda (280 km)

Page 81: Kostroma region investment proposals 2012

81

Land lot in Moskovskaya Str., No.105 close to OAO “Motordetal” (Kostroma)

Area - 137,0 ha

Transport availabilityDistance to:Motorway Kostroma-Yaroslavl`– 10 m;• 3,342 km of railway crosses the land lot.•

Civil engineering infrastructure avaliabilityPower supply - own step-down substation for 220/110/10 kW with the • capacity reserve of 20 MVt;Total consumption - 191,88 MVA;• Gas supply – from distributing net of Kostroma city. Free gas capaci-• ties – 1000 m3/h;Heat supply – own boiling room with the water heating (4PTVM 50) and • steam (2DKVP 20/13 – DKVP 10/13) boilers. Released energy – 75 Hkal/h with reserve of 50 Hkal/h. Total capacity in delivery water – 200 Hkal/h, in steam – 10 ton/h;

Page 82: Kostroma region investment proposals 2012
Page 83: Kostroma region investment proposals 2012

83

Water supply – water is delivered from the Volga and from the arte-• sian wells. Household water supply –up to 100 m3/h, total debit – 250 m3/h, free capacities – up to 100 m3/h. Water recycling is provided by 5 water-cooling towers with capacity of 1300 and 1200 m3/h. Free capacity – up to 500 m3/h;Water drain – water escape is performed via city collector in volume • of 150 m3/h;Water treatment – buffer pool equipped with the aeration system, • through load – 900 m3/year. Sewerage system – crosses the land lot;Neutralization system:• - Coolant drain – 20 000 m3/year;- Acid-based substance drain – 100 000 m3/year;- Chrome-containing drain – 36 000 m3/year.

Land lot usagePlacement of the industrial objects.

Page 84: Kostroma region investment proposals 2012
Page 85: Kostroma region investment proposals 2012

85

Industrial park is a territory of the former machine building plant possessing up-to-date engineering buildings outfit with the latest in technical equipment and united by the joint infrastructure and service system.

Industrial park specializes in: automobile components production.

Industrial park potential participants:companies organizing new productions;• companies interested in relocation of their productions to the • regions with the higher competitive conditions;foreign companies planning to create their production in • Russia.

Industrial park proposes the unique conditions for the favorable location of the residents` production.

Basic advantages:free connection to the power supply system;• free capacity of gas;• tax remissions for residents;• low costs for land and property;• own heat power produced by the boiler house.•

Page 86: Kostroma region investment proposals 2012

CONTACTS

Body of Investment and Industrial policy of Kostroma region Administration Telephone: +7(4942) 31-20-01

Kostroma region economic development department Telephone: +7 (4942) 620-519Fax: +7 (4942) 620-536

Kostroma region agricultural sector department Telephone: +7 (4942) 55-16-31Fax: +7 (4942) 45-65-41

Kostroma region forestry department Telephone: +7 (4942) 55-33-02Fax: +7(4942) 55-80-32

Kostroma region natural resources and environmental protection department

Telephone: +7 (4942) 45-01-10Fax: +7 (4942) 51-35-91

Kostroma region property and land relation department Telephone: +7 (4942)45-65-66Fax: +7 (4942) 45-78-50

Kostroma region building, architecture and urban planning department

Telephone: +7 (4942)31-76-30Tel/fax: +7 (4942) 31-28-12

Kostroma region fuel and energy sector and tariff policy department

Telephone: +7 (4942)31-52-13Fax: +7 (4942) 37-34-01

Kostroma region housing and communal services department Telephone: +7 (4942) 31-44-86Fax: +7 (4942) 37-17-32

Page 87: Kostroma region investment proposals 2012

ADDITIONAL INFORMATIONIn case you have not find the information you are looking for in this booklet and if you have any offers for cooperation with the Kostroma region Administration, we ask you to fill in the following application form and send it to our e-mail address: [email protected] form can be found as well at the Kostroma region authority portal: www.adm44.ru.

1 Investor

2 Investment project name

3

Necessary resources, namely:

Land lot area

Civil engineering infrastructure with the capacity indication (electricity, gas, water)

railway, motorway

other resources (nature, forest etc.)

4Preferable location of the industrial site (city/town, region, distance to the regional or district centre)

5 Other conditions

6 Contacts

Page 88: Kostroma region investment proposals 2012

Kostroma region Administration15, Dzerzhinskogo Street 156013 Kostroma

Tel.: +7 (4942) 31 34 72www.adm44.ru

Body of Investment and Industrial policy of Kostroma region Administration

15, Dzerzhinskogo Street 156013 KostromaTel.: +7 (4942) 31 20 01