OB15 – Paper 06 – KPI Report
KPI and SLA regime: May 2014 performance summary Reference Outcome Result Target Description
KPI A Fail 99.29% 100% Service Restoration within 10 working days where
household is a primary DTT user
KPI A1 Pass 99.35% 95% Installer visits completed as scheduled with viewer
KPI A2 Pass 93.76% 50% Installer visits completed within 3 working days
KPI A3 Pass 99.65% 85% Installer visits completed within 7 working days
KPI A4 Pass 99.53% 50% Vulnerable visits completed within 3 working days
KPI A5 Pass 100% 99% Vulnerable visits completed within 7 working days
KPI A6 Fail 95.00% 95% Communal installer visits completed as scheduled
with landlord where access and liability is confirmed
KPI A7 Pass 100% 86% Reactive filters issued in 2 working days
KPI A8 Pass 100% 94% Reactive filters issued in 4 working days
KPI A9 Pass 100% 99% Reactive filters issued in 5 working days
[KPI A10] N/A N/A 100% [SUSPENDED FOR REACTIVE-ONLY TRIAL]
Addresses in very high pixels mailed filters
SLA B1 Pass 100% 100% All identifiable addresses within forecast medium,
high and very high risk pixels (high risk only for
London) to be mailed at least once between 3 and 12
weeks ahead of scheduled mast activation
SLA B2
Qualitative and quantitative
reports provided. No specific
targets.
Report on households mailed and not mailed within
forecast pixels (i.e. number of low risk households)
SLA B3 Report on households reporting interference within
un-mailed forecast pixels.
SLA B4 Awareness to be maintained (reminder mailings) with
those viewers at continued risk of experiencing
interference from masts that were not activated as
scheduled.
SLA B5 Awareness to be maintained (reminder mailings) with
those viewers at renewed risk of experiencing
interference from infill masts where the addition of
the mast increases the risk of interference in that
pixel to very high
SLA B6 Report on households mailed and not mailed
reminders within forecast pixels (i.e. number of low
risk households)
SLA B7 Report on above the line comms and research
outcomes, including awareness in rollout areas
SLA C1 0.02% Pass 0.5% Complaint about quality of interaction
SLA C2 0.25% Pass 0.5% Complaint about quality of problem resolution
SLA C3 0.11% Pass 0.5% Complaint about timeliness of problem resolution
SLA C4
Qualitative and quantitative
reports provided. No specific
targets.
Report on total number and categories of complaints
SLA D1 Measure of the numbers of mailings per report of /
case of interference
SLA D2 Measure of the number of reported cases that occur
outside of mailed area
SLA D3 Measure of number of cases of interference per mast
remaining between 0.17 and 1.66 (5k to 50k cases of
interference for rollout)
May 2014: KPI and SLA performance summary, 10 June 2014
Page 2 of 10
KPI A – Service Restoration
KPI A: Service Restoration: 100% within 10 working days where household is a primary DTT user
(communal households and households where cable or satellite services are received are excluded)
Result: 99.29%
Of the 282 confirmed 4G cases in May 2014, 280 (99.29%) were resolved within 10 working
days
There were two breach cases, outlined below:
o Case 7797872
A mailing and proactive filter were sent in summer 2013
A mast was activated 282 metres from the property on 6 November 2013
A reminder mailing was sent in January 2014
The viewer called on 28 April 2014 citing reception problems suffered since before
Christmas
An installer visit on 3 May claimed to resolve the 4G interference being suffered by
installing a filter before the masthead amplifier, but the viewer refused to sign the
form
We made multiple attempts to get in touch with the viewer, finally getting back in
touch on 21 May. The viewer reported ongoing reception problems, and we
booked a further installer visit on 23 May
During this visit, it was discovered that the ongoing reception issues were not a
result of 4G, but that they could be resolved by removing a second signal booster
in the loft space and fitting a four-way splitter
On 28 May, we made a decision to arrange a further installer visit to perform the
above actions for the viewer, as these measures should have been actioned during
the original installer visit. The viewer signed the form after the visit on 29 May
Case closed in 21 working days. Map is below:
May 2014: KPI and SLA performance summary, 10 June 2014
Page 3 of 10
o Case 8488283
The viewer originally contacted us via the webform on 2 October 2013 reporting
interference but was ruled out in triage
A review of properties missed from interference predictions due to low in-pixel
population over-ruled the original triage and led us to re-contact the viewer and
book an installer visit for 5 November. Our installer indicated cables needed
replacing, and that there was no 4G interference. The viewer was reportedly happy
with the situation
An audit visit on 10 December indicated that, despite low DTT readings,
interference was related to 4G. However, an administrative error meant that the
case was not re-opened
The viewer used the webform again on 8 March to indicate that she was still
waiting to hear back from us. After an attempted phone call by us on 11 March, we
followed up by email on 12 March to confirm that the issue was not 4G. This was
because of a mix-up of audit forms
The viewer responded by email on 18 March to tell us that the auditor had
confirmed that the problem was 4G-related and that they were promised that it
would be addressed
We called back on 19 March to attempt to book an appointment. A delayed
response by the viewer meant that the visit was booked for 11 April. During this
visit, against our clear instruction to ‘fix it no matter what’, the installer undertook
a standard visit and confirmed that they had done the job right the first time and it
was not a 4G issue
The viewer called us on 14 April adamant that it was a 4G issue
We picked up the case on 1 May, and an installer visit was booked for 9 May,
delayed at the request of the viewer, during which a new aerial was installed that
resolved the problem
Case closed in 105 working days (based on an opening date of 10 December 2013).
Map is below.
Failed.
May 2014: KPI and SLA performance summary, 10 June 2014
Page 4 of 10
KPI A1: Installer visits completed as scheduled with viewer: 95%
Result: 99.35%
Of the 925 installer visits originally scheduled in May 2014:
o 860 were undertaken and closed on schedule
o 6 visits were cancelled or missed by the installer
o 59 visits were cancelled by the viewer
Total scheduled visits not missed by installer / total visits scheduled
(860 + 59) / (860 + 59 + 6) = 919 / 925
Result: 99.35%
Passed.
KPI A2: Installer visits completed within 3 working days: 50%
Result: 93.76%
Of the 925 scheduled installer visits detailed above, there were 866 visits scheduled where
the viewer did not cancel
Of these 866, 812 (93.76%) were completed within three working days
Passed.
KPI A3: Installer visits completed within 7 working days: 85%
Result: 99.65%
Of the 866 visits, 863 (99.65%) were completed within seven working days
Passed.
KPI A4: Vulnerable visits completed within 3 working days: 50%
Result: 99.53%
In May 2014, there were 211 scheduled installer visits to people marked as vulnerable,
where the viewer did not cancel
Of the 211 visits to be measured, 210 (99.53%) were completed within three working days
Passed.
KPI A5: Vulnerable visits completed within 7 working days: 99%
Result: 100%
All of the 211 visits to be measured were completed within seven working days, the longest
taking four working days
Passed.
KPI A6: Communal installer visits completed as scheduled with landlord where access and liability is
confirmed: 95%
Result: 94.74%
May 2014: KPI and SLA performance summary, 10 June 2014
Page 5 of 10
Of the 40 communal jobs in the month of May 2014:
o 2 were cancelled by the installer
o 2 were cancelled by the viewer
o 36 were completed as agreed with the customer
Therefore, of the 40 jobs scheduled, 38 were either completed as scheduled or cancelled by
the viewer giving a success rate of 95%
Of the two jobs cancelled by the installer:
o One was a clerical error that resulted in the appointment not appearing in our
systems
o The other was booked for the 8am–1pm Tuesday slot, but morning appointments
took longer than expected, the installer called the viewer to say that he might be a
little late and the viewer had to go to work at 1pm. The appointment was
rescheduled and completed the following Saturday morning.
Passed.
KPI A7: Reactive filters issued in 2 working days: 86%
Result: 100%
There were 1,066 filter requests in May 2014. All of these were issued within one working
day, and hence passed the two working day measure
Passed.
KPI A8: Reactive filters issued in 4 working days: 94%
Result: 100%
See KPI A7
Passed.
KPI A9: Reactive filters issued in 5 working days: 99%
Result: 100%
See KPI A7
Passed.
KPI A10 [SUSPENDED]: 100% of identifiable addresses in very high pixels mailed proactive filter.
Not applicable.
May 2014: KPI and SLA performance summary, 10 June 2014
Page 6 of 10
SLA B – Awareness
SLA B1: 100% of identifiable addresses within forecast medium and high risk pixels (high risk only for
London) to be mailed at least once between 3 and 12 weeks ahead of scheduled mast activation
Result: 100%
A total of 90,393 households were identified within “very high”, “high” or “medium” risk
pixels in the June 2014 rollout data and all were mailed on 2 May 2014
Passed.
SLA B2: Report on households mailed and not mailed within forecast pixels (i.e. number of low risk
households)
The following table shows the breakdown of households by risk category and those confirmed as
mailed.
Mailed Date V_HIGH HIGH MED LON MED LOW Grand Total
2 May 2014 33,199 24,294 32,900
90,393
Not mailed 14,653 38,545 53,198
SLA B3: Report on households reporting interference within un-mailed forecast pixels. More than 40%
of total reports of interference – DMSL to address through operational adjustments (e.g. mailing low
risk pixels in a certain area or adjusting the risk score for pixels), however, a de minimis threshold to
apply.
In May 2014, we were contacted by a total of 1,826 households reporting interference that
we believed may be caused by 4G
Of these, 252 (14%) contacted us in May who were suppressed by the risk-based mailing
A further 105 (6%) contacted us who would have remained un-mailed under the previous
model.
SLA B4: Awareness to be maintained (reminder mailings) with those viewers at continued risk of
experiencing interference from masts that were not activated as scheduled. Report on reminder
mailing numbers to be provided.
A reminder mailing was undertaken on 20 May 2014 to 68,024 households forecast to be
affected by masts originally expected to activate in December 2013.
SLA B5 Awareness to be maintained (reminder mailings) with those viewers at renewed risk of
experiencing interference from infill masts where the addition of the mast increases the risk of
interference in that pixel – low to medium, new mail; medium to high, reminder mail
This activity is not distinguished from that detailed in the summary of SLA B4.
May 2014: KPI and SLA performance summary, 10 June 2014
Page 7 of 10
SLA B6: Report on households mailed and not mailed reminders within forecast pixels (i.e. number of
low risk households)
The following table shows the breakdown of households by risk category and those confirmed as
mailed.
Mailed Date V_HIGH HIGH MED LON_MED LOW Grand Total
20 May 2014 496 31,552 35,976
69,023
Not mailed
52,598 85,858 138,456
SLA B7: Report on above the line communications and research outcomes, including awareness in
rollout areas
There were no ‘new’ areas to support in May, and so we did not run any PR, or above-the-line or
digital advertising. Similarly, we did not run any research.
PR, above-the-line and digital advertising has now begun in Belfast on 9 June. This will be followed
by online research.
We engaged with local MPs, councils and social housing providers in South Wales in line with
mailings.
Background: DMSL runs above-the-line, PR or digital advertising communication when masts are
activated/the operators begin offering 4G services (at 800 MHz), and not necessarily in line with
DMSL’s mailing activity. Prior to mast activations/4G at 800 MHz launch, our primary means of
communication with viewers is direct mail postcards.
May 2014: KPI and SLA performance summary, 10 June 2014
Page 8 of 10
SLA C – Quality of Service
SLA C1: No more than 0.5% of households interacting with DMSL make a formal complaint about
quality of interaction
Result: 0.02%
There were a total of 4,365 household interactions in May 2014
There was 1 interaction that could constitute this type of complaint in May 2014. This
amounts to a complaint rate of 0.02%
Passed.
SLA C2: No more than 0.5% of households interacting with DMSL make a formal complaint about
quality of problem resolution
Result: 0.25%
There were a total of 11 interactions that could constitute this type of complaint in May
2014, out of a total of 4,365 interactions. This amounts to a complaint rate of 0.25%
Passed.
SLA C3: No more than 0.5% of households interacting with DMSL make a formal complaint about
timeliness of problem resolution
Result: 0.11%
There were a total of 5 interactions that could constitute this type of complaint in May 2014,
out of a total of 4,365 interactions. This amounts to a total complaint rate of 0.11%
Passed.
SLA C4: Report on total number and categories of complaints
Below is a breakdown of the 37 complaints received in May 2014
Compensation: 15
Installer-related: 6
Rollout in general: 6
Diagnostics over the phone: 4
Non-4G issue that we cannot help with: 3
Communal process: 2
Contact centre: 1.
[SLA C5:] Vulnerable viewer complaints
Out of 416 interactions with viewers flagged as being vulnerable in May 2014, four (1.0%)
complained. Three of these related to the installer; the other one related to compensation.
May 2014: KPI and SLA performance summary, 10 June 2014
Page 9 of 10
SLA D – Scale
SLA D1: Measure of the numbers of mailings per report of / case of interference
The following table shows the number of mailings per reported case and confirmed case of
interference to date for May 2014 rollout households that relate to masts planned to be
activated in May 2014.
Number of mailings per report of interference
∞
Number of mailings per confirmed case of interference
∞
SLA D2: Measure of the number of reported cases that occur outside of mailed area
Of the 282 households identified as experiencing 4G interference in May 2014:
May cases not mailed due to risk profile or low pop in pixel
4 (1.4%)
May cases never identified in modelling 2 (0.7%)
Total May cases outside mailed area 6 (2.1%)
Total May cases caught by mailing 276 (97.9%)
SLA D3: Measure of number of cases of interference per mast remaining between 0.17 and 1.66 (5k
to 50k cases of interference for rollout) exceeding or trending towards exceeding the range will be
raised to the OB for review / action
May 2014: KPI and SLA performance summary, 10 June 2014
Page 10 of 10
Appendix: Tracking against previous KPI A breaches
There were two breaches against KPI A in April 2014 against which we monitored progress.
Case 1 (4919715) - since this case, three further cases have been raised within the same postcode
district (G73). Of these, two are in the same postcode sector (G73 2). All closed in a timely fashion,
and none constituted a breach against KPI A.
Case 2 (7626420) - since this case, 15 further cases of 4G interference have been raised within the
same postcode district (EH9). Eight are in the same postcode sector (EH9 1). All were closed in a
timely fashion, and none constituted a breach against KPI A. A further case is not yet completed.