    KSPCS CHIMNEY TO RISE 110 METERS HIGH INTO THE SKY

    ebu Power Plants tall chimney will soon rise into the sky as the

    astounding erection of this important feature of the project has already

    commenced.

    Concrete pouring work has started and will continue until the height of 110

    meters from the ground of the structure is achieved. The slip-forming

    equipment used was imported from Sweden. The technology was introduced in

    the country by a Hungarian. This is now being enjoyed by both the Filipinos

    and the Korean nationals who are implementing the construction work.

    KSPCS Chimney to Rise 110m High

    EDITION NO. 14, May 20, 2009The Cebu CFBC Plant Chronicle

    KSPCs chimney that will soon be a new landmark of Naga,Cebu (May 18, 2009)

    CCCC

  • 8/14/2019 KSPC Newsletter Vol14 May09

    2/102

    Into the Sky (Cont.)

    eanwhile, the rate of concrete casting is 600 mm high every 4 hours.

    The cement to be poured is being monitored and the temperature is being

    controlled in order to stabilize the concrete before the forms slip up to the next

    elevation. The rebar preparation and installation are done in advance so that

    they will not be caught up by the advancing pouring of concrete.

    The chimney has strong foundation that can withstand the forces of nature

    and carry the load of the structure itself. The foundation alone can consume

    770 cubic meters of ready mix concrete with strength of 30 megapascals

    reinforced by 231 tons of rebar. Once completed, the new skyscraper, which

    has a fascinating dome figure on its top, will be a new landmark in Naga, Cebu.

    MMMM

    The swift work progress in the erection of chimney

    (Left Photo, May 5, 2009/ Right Photo, May 18, 2009)

  • 8/14/2019 KSPC Newsletter Vol14 May09

    3/103

    MMTS 1st Quarterly Meeting

    SPCs Multi-Partite Monitoring Team (MMT) held its first quarter meeting

    last April 21, 2009 at the Cebu Construction Office. Majority of the members

    representing the concerned stakeholders of the project, namely, DENR-EMB 7,

    CENRO, LGUs, NGOs, academe and rural health units attended the whole-day

    activity.

    The highlights of the affair included the updating of the official listing of MMT

    members, presentation of the current KSPC project status, review and

    discussion of the MMT Manual of Operations (MOO), and the planning of

    future activities and meetings.

    The MMT members during the CY 2009 1st QuarterlyMeeting (April 21, 2009)

    KKKK

  • 8/14/2019 KSPC Newsletter Vol14 May09

    4/104

    MMT Meeting (Cont)

    he MOO defines how the MMT should operate with regards to monitoring

    activities, rules and regulations, trainings, sampling methods, and all other

    areas of concern. With the development of this manual, the different activities

    of the group can be done smoothly and in line with their goals.

    There was a site visit in the afternoon to provide a visual compliment of the

    project status. The whole event created a benchmark for the committees goals

    in formulating the yearly work and financial plan. Furthermore, this marked

    the beginning of the groups adherence to their Mission and Vision for the year

    2009: Our Environment, Our People, Our Concern.

    MMT members given updates on the project status as theytour the project site (April 21, 2009)

    TTTT

  • 8/14/2019 KSPC Newsletter Vol14 May09

    5/105

    KSPC Joins Barangay Colons Fiesta

    iving up to its commitment of community involvement, KSPC has

    organized a basketball team to participate in Barangay Colons Summer

    League Basketball Tournament, as part of the activities for the fiesta

    celebration on May 28, 2009.

    Aside from the direct involvement of its employees to the sports activity of its

    host barangay, KSPC also provided financial donation to ensure the success of

    the lined up socio-cultural events, such as variety show, drama, dance and

    singing contest, for the feast of San Vicente Ferrer.

    KSPCs Basketball Team joins the opening of Barangay

    Colons Summer Basketball League (May 10, 2009)

    LLLL

  • 8/14/2019 KSPC Newsletter Vol14 May09

    6/106

    Project Progress

    View of the Unit 1 HP Turbine Assembly

    View of the Unit 1 IP & LP Turbine Assembly

  • 8/14/2019 KSPC Newsletter Vol14 May09

    7/10

  • 8/14/2019 KSPC Newsletter Vol14 May09

    8/108

    Project Progress

    Rebar and form works for the discharge tunnel(May 18, 2009)

    On-going fabrication of Coal Silo Shell for Unit No. 1 Boiler(May 18, 2009)

  • 8/14/2019 KSPC Newsletter Vol14 May09

    9/109

    Project Progress

    Rebar and form works for Unit No. 1 Turbine GeneratorPedestal (May 18, 2009)

    On-going work for the Administration Building(May 18, 2009)

  • 8/14/2019 KSPC Newsletter Vol14 May09

    10/1010

    PROJECT PROPONENT : KEPCO SPC Power Corporation (KSPC) CAPACITY : 100 MW x 2 Units PLANT TECHNOLOGY : CFBC (Circulating Fluidized Bed Combustion) LOCATION : Colon, City of Naga (20 Km from Cebu City) TARGET COMPLETION : Unit No. 1: February 2011; Unit No. 2: May 2011

    Project Information