+ All Categories
Home > Documents > KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional...

KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional...

Date post: 08-Aug-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
26
KUDU POWER PROJECT MAY 2014
Transcript
Page 1: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

KUDU POWER PROJECT

MAY 2014

Page 2: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

UPDATE ON THE POWER SUPPLY

SITUATION IN NAMIBIA

May 2014 2

Page 3: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Short-Term Supply initiatives planned for 2012-2017

o The following initiatives are being investigated to address

the anticipated power supply shortage during 2012 – 2016:

1) Increase imports from the region

2) Possible refurbishment of the Van Eck Power Station,

3) Possible refurbishment of Ruacana Unit 1, 2 & 3,

4) IPP projects: solar, wind & biomass

Kudu remains the long-term flagship

power generation project

for NamPower and Namibia.

May 2014 3

Page 4: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

0

200

400

600

800

1000

1200

Low Demand +Reserve

High Demand + Reserve

May 2014 4

Namibian Forecast Demand (including Reserve) and Firm Power Station Capacity

Page 5: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

0

200

400

600

800

1000

1200

Hydro

Coal

Kudu Firm

STCS & Renewables

NP Small Thermals

Firm Imports

Ruacana Firm

Low Demand +Reserve

High Demand + Reserve

Namibian Forecast Demand (including Reserve) and Firm Power Station Capacity

May 2014 5

Page 6: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

PROJECT PROFILE

May 2014 6

Page 7: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Power Station developers/partners:

NamPower: 51%

CEC Africa 30%

Strategic Equity Partner: 19%

Location of power plant: Uubvley (25km north of

Oranjemund)

Technology: CCGT

Power Output: 800MW (nominal)

Main Off-taker: NamPower

Secondary off-takers: Zambia & South Africa

Overview: Downstream Structure

May 2014 7

Page 8: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Kudu Gas Field developers (owners):

Namcor - 54% (in the process of securing a carry partner)

Tullow Oil - 31%

ITOCHU - 15%

Location of gas field: 170km off-shore

Proven reserve: 1.3tcf (trillion cubic feet)

Off-taker of the gas: KuduPower (Pty) Ltd

Overview: Upstream Structure

May 2014 8

Page 9: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Location of Kudu Power Station

May 2014 9

Page 10: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Gas Field – Power Station scheme

10

Page 11: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Gas pipeline route

May 2014 11

Page 12: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Kudu Gas field reserve & location

Water depth : 170m

Reservoir depth 4400m

170km from shore

Deterministic GIIP estimates (tscf):

EA GCA

Proved 1.38 1.45

Probable 3.28 2.72

Possible 9.92 7.12

May 2014 12

Page 13: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Upstream

Namcor (54%)

Tullow Oil (31%)

ITOCHU (15%)

Downstream

800 MW CCGT Power

Station

KuduPower (Pty) Ltd

(NamPower + Partners)

Gas

Sales/Supply

Agreement

Power

Purchase

Agreements

NamPower

Domestic supply

Power Export

Agreements

May 2014 13

Page 14: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Kudu commercial structure

4

Kudu Project Commercial Arrangements

NamPower& other

equity partnersLenders

Shareholders A

greement

Financing A

greements

O&

MA

greement

Operations and Maintenance

Company

OEM & EPC Contractor

EPC & LTSA

Contract

Gas Sales/Supply Agreement

UpstreamParties

KuduPower NamPower

Power PurchaseAgreement

Regional Buyers

Power Export

Agreem

ent

Transmission Agreement(s)

Power to Namibia

May 2014 14

Page 15: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

KUDU’S REGIONAL COMPETITIVENESS

May 2014 15

Page 16: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Kudu’s regional competitiveness

o Regional project comparison that was carried out indicates

that:

Kudu is forecast to cost approximately US$11-12c / kWh

which is competitive with any regional new build coming

on-stream by 2017/18,

Kudu’s technology is environmentally clean compared

to several regional coal projects planned,

it will be the first CCGT power station in the SADC

region, and the first CCGT of this size in Africa.

May 2014 16

Page 17: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Figure 4: Basic Cost Comparison

0

2

4

6

8

10

12

14

16

ITT (120MW) Maamba (300MW) Kafue Lower

(600MW)

Kudu

US

c/k

Wh

Transmission markup

Plant Gate Cost

Basic Cost Comparison (Zambian Projects vs. Kudu)

Source Copperbelt Energy Corporation: 2011

Indicative 2015 Tariffs

May 2014 17

Page 18: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Regional Pricing Forecast (Border Price)

May 2014 18

Page 19: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Regional Perspective of Pricing Trends

-

2.00

4.00

6.00

8.00

10.00

12.00

14.00

US

D c

en

ts/

kW

h

Average Electricity Price

2006

2007

2008

Forecast of Industrial Tariffs (2010 - 2020)

0

2

4

6

8

10

12

14

16

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

Year

US

c p

er k

Wh

RSA

Zambia

•Low Tariffs but rising to cost

reflectivity

•Annual increases of 20-30%

•Driven by new investments

needed to meet growing

demand

Source Copperbelt Energy Corporation: 2011

May 2014 19

Page 20: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

LATEST PROJECT UPDATE

May 2014 20

Page 21: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Update on Government support/guarantees:

o Engagement with Government on-going on:

o Shareholder (parent) guarantees,

o Policy & regulatory support for guaranteed tariff & protection

from impacts of future change of law.

o Africa Development Bank (AfDB) has been contracted by the

Government to advise it on how best to structure the

guarantees required for the project.

o Government has availed N$1.6bn during the 2014/2015 FY for

Kudu. Further funding support envisaged for the 2015/2016 &

2016/2017 FY’s.

May 2014 21

Page 22: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Procurement of additional equity partners

o Procurement of Strategic Partner(s):

The Joint Development Agreement (JDA) between NamPower

and CEC Africa was signed on 7 February 2014.

A JDA Steering Committee has been established to oversee the

development of the Kudu Power Project.

CEC Africa has committed to take 30% equity in KuduPower

(Pty) Ltd.

The remaining equity (19%) in KuduPower will be allocated to a

Strategic Equity Investor by the end of May 2014.

May 2014 22

Page 23: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Power Export negotiations

PXA Termsheet negotiations with CEC Plc was signed on 7 February

2014. The negotiations for the full PXA is expected to commence in

May 2014.

An additional of-take by Eskom for +-100MW is still being

negotiated.

Delays in progressing the negotiations with Eskom were largely due

to the new legislation on procurement of power from IPP’s and

imports from the region.

There has been high-level discussion with DoE in 2013, and there

seems to be positivism in advancing the off-take negotiations.

May 2014 23

Page 24: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Update on Kudu tenders

Kudu tenders that are under evaluation:

o EPC tender - evaluation completed

o Investor tender - evaluation completed

o Financing tender - evaluation completed

o O&M tender - evaluation nearly complete

All commercial agreements on the above expected to be

negotiated and concluded by June/July 2014.

May 2014 24

Page 25: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

Indicative project timelines (2014 – 2018):

o Conclusion of all agreements: July 2014

o Final Investment Decision: July/Aug 2014

o Financial Close: Jan 2015

o Commencement of construction: 1st or 2nd Q 2015

o Commercial Operations Date (COD): 1st quarter 2018

o (36 months construction period)

May 2014 25

Page 26: KUDU POWER PROJECT Project Update... · 2014-05-13 · Kudu’s regional competitiveness o Regional project comparison that was carried out indicates that: Kudu is forecast to cost

For more info contact:

The Kudu Project Office

Tel. +264-61-205 2221

Tel. +264-61-205 2214

Fax: +264-61-205 9221

E-mail: [email protected]

For attention: Mr. S. Muyenga-Muyenga

Project Coordinator: Stakeholder Management & Project Promotion

E-mail: [email protected]

Email: [email protected]

Website: www.nampower.com.na

May 2014 26


Recommended