29
Hydrologic Engineering Center Alternatives, Simulations, and Analysis of Results HEC-ResSim 3.1
Transcript
Page 1: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 1/30

Hydrologic Engineering Center 

Alternatives, Simulations,and Analysis of Results

HEC-ResSim 3.1

Page 2: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 2/30

Overview & Objectives

HEC-ResSim Modules

What are Alternatives? and How to create one…

What is a Simulation? How to create one andwhat to do with it…

Analysis of Results HEC-ResSim Output Options

WatershedSetup

NetworkModule

SimulationModule

Alternative

Page 3: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 3/30

 What is a ResSim Alternative?

An HEC-ResSim Alternative is a specific

selection of:

A Reservoir Network (model schematic with

physical properties plus operating plan(s)) The Computation Type and Interval (timestep)

The Active Operation Set for each Reservoir

The Initial Conditions for each Reservoir

The Inflows and other required Time Series Inputs

Page 4: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 4/30

Std. Ops Normal Pool 100-yr

Planning Ops Encr. Pool 500-yr

ALT 3

Composing an Alternative

NETWORK OPERATION

SET

LOOKBACK INPUT TIME

SERIES

Std. Ops Normal Pool 100-yr

Planning Ops Encr. Pool 500-yr

ALT 1

ALT 2

One Reservoir

ALT 4

Two Reservoirs

Page 5: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 5/30

The Alternative Editor

RequiredSpecifications Network

(Based on aConfiguration)

Run Control Operations

Lookback

Time-Series

Optional

Observed Data

Hotstart

List of

Alternatives

Tabs

Page 6: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 6/30

Creating an Alternative…

Create NewAlternative

Name theAlternative

Add a Description Select a Network

NOTE: Once youpress OK here, youcannot change thenetwork selection.

Page 7: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 7/30

Setting Up an Alternative…Run Control

Run Control Tab

Time Step

Flow Computation

Method

ComputeUnregulated Flows

Compute Holdouts

Log Level

Page 8: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 8/30

Setting Up an Alternative…Operations

Operations Tab

Select an

operation set foreach reservoir

Save theAlternative

List of Reservoir Systems

and Associated Storage Balance Operation Sets

List of Reservoirs

and Associated Operation Sets

Page 9: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 9/30

Lookback Tab

Lookback Variables

Pool Elevation or

Storage

Outlet Releases Diversion Flow

State Variables

Lookback Types

Constant

Time Series Computed 

Setting Up an Alternative…Initial Conditions

Page 10: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 10/30

Time-Series Tab Time Series Variables

include:● Inflow (Known Flow)● Evaporation Rate●  Zone Elevation

● Lookback Elevation &Release

● External Data for a Ruleor Diversion

The DSS Path Selector is

used to map (associate)

HEC-DSS time series records

to each entry in the table.

Inflow Multipliers

Plot and Tabulate

Setting Up an Alternative…Inflows & Other Time-Series

Page 11: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 11/30

To enter apathname into arow on the TimeSeries Tab First, select the

row you want to

fill in, then…

From the DSSPath Selector

Highlight arecord andDouble Click

or

Highlight arecord and ClickSet Pathname

Setting Up an Alternative…The DSS Path Selector

Page 12: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 12/30

Setting Up an Alternative…Inflow Multipliers

Page 13: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 13/30

Setting Up an Alternative…Observed Data

Observed Data Tab

The Observed Data tabis similar to the Time-

Series Tab, however…

The Locations and

Variables are identifiedin the Network elementeditors (reservoir,

 junction, etc).

Specification ofobserved data is

optional .

Page 14: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 14/30

Managing Alternatives

Alternative Menu New Save Save As

This option willcreate a COPY of the

currently selectedalternative.

The Network

selection cannot bechanged, buteverything else can…

Delete Close

Page 15: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 15/30

 What is a ResSim Simulation?

An HEC-ResSim Simulation is a “workspace” in whichyou can compute alternatives, analyze results, andrefine your model.

A simulation is defined by the specification of a Time

Window and a selection of alternatives. The default Name of a simulation is formed from the start

time of the specified time window. HOWEVER, a more

descriptive name can and should be entered to replace the

default.

A sub-directory or folder is created to hold the simulation’sfiles. It has the same structure as the watershed and

includes copies of all the files that define the alternatives.

Page 16: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 16/30

Simulation Time Window

Lookback Period To initialize the model

elements and routing andreaches

Should be at least as long asthe travel time from the

upstream-most reservoir to thedownstream-most control point 

Simulation Period The period during which the

model evaluates the input andmakes release decisions then

routes the releases and inflowthrough the network

Should be at least 2x thelength of the lookback period

32

Hours

28

Hours

Page 17: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 17/30

The Simulation Module

CreateSimulations

ComputeAlternatives

Review Results

Refine the model

Perform “Whatif..?” scenarios

Page 18: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 18/30

Creating a Simulation

From the Simulation Module’sSimulation Menu, select New…

Enter the Lookback, Start andEnd Dates and Times for thesimulation’s time window.

Select the Alternatives youwant to work with.

Enter a Name and Descriptionfor your Simulation.

Page 19: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 19/30

Creating a Simulation

When a Simulation is created, ResSim

creates…

a new folder with the name of the Simulation in

the watershed /rss folder and puts a copy of the

watershed in it with those files needed to

represent the selected alternatives

a DSS file called simulation.dss in the simulation

folder and puts a copy of all the input time-series

records needed for the selected alternatives.

Page 20: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 20/30

Running a Simulation

Make an alternative

“Active”

(right click menu)

Compute and check

the Compute Dialog

for successfulcomputation or

errors and

warnings.

Page 21: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 21/30

Common Simulation Errors

Choosing a simulation time window that is beyond the coverageof the selected time-series data

One or more Initial conditions are not specified in the Lookbacktab of the Alternative Editor

Input time-series has missing data

Page 22: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 22/30

Common Simulation Errors

Input Time-Series have not been specified on the Time-series tab of the Alternative Editor

A required Time Teries is incompletely specified or thespecified file &/or pathname cannot be found .

Inflows at Headwater junction(s) are not identified orspecified

Routing parameters are not entered

Reservoir data is incomplete (pool definition, outlet

capacity, zones, rules) Incomplete or broken network connectivity 

Page 23: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 23/30

Editing a Simulation

Open the Simulation

Editor from the … Simulation menu:

Select New…

Or

Context menu:

Right-click on the simulationname in the Control Panel

Change Lookback or End dateand/or time

Add or Drop an Alternative

Run a New Extract

Page 24: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 24/30

When changing input time series links

When expanding the simulation time window beyond

the dates for which the data was extracted:

If the lookback is changed to an earlier date.

If the end of the simulation is changed to a later date.

Note …

The simulation start time cannot be changed.

 When to make a new Extract?

Page 25: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 25/30

Simulation Control Panel

Set anAlternative Active

Compute anAlternative that

is not active.Check the

Alternativeboxes to accessresults for the

checked Alternatives.

Create Trials…

Page 26: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 26/30

“Set As Active”

Set As Active - This command makes the

alternative editable and displays its network in

the map region.

Page 27: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 27/30

Run Manager

Select andcompute

multiplealternatives

ReviewComputeStatus

ViewCompute

Logs

Page 28: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 28/30

An Alternative is createdin the Reservoir Networkmodule and belongs tothe “base” rss folder of

the watershed. When a simulation is

created, a copy of theAlternative is made andstored in the

simulation’s rss folder ofthe watershed.

The “base”rss directory

The “simulation” 

rss directory

To Save-to-Baseor Replace-from-Base?

Page 29: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 29/30

Save-to-Base: Updates the ReservoirNetwork module’s (base) copy of theselected alternative and its associatednetwork data from the Simulation

module’s copy.

Replace-from-Base: Recreates theSimulation module’s copy of analternative and its associated network

data from the Reservoir Networkmodule’s (base) copy.

To Save-to-Baseor Replace-from-Base?

Page 30: L 06a Alternatives&Simulations

7/23/2019 L 06a Alternatives&Simulations

http://slidepdf.com/reader/full/l-06a-alternativessimulations 30/30

Points to Remember

Alternatives are a combination of: A network

An operation scheme

A set of initial conditions

A set of inflows

Run Control selections

Simulations are a combination of: A time window

A set of alternatives to run, refine, and compare


Recommended