2
L ) Camino TGM Our Ref: 20080-01 Contact: Chris Marshall 17th August 2021 Helen Evans Statutory Planning Department Colac Otway Shire P.O. Box 283 COLAC 3250 Dear Helen, Planning Application PP41/2021-1 80 Great Ocean Road, Apollo Bay Buildings and works associated with a vehicle crossing bridge and Creation of a Carriageway Easement We write in response to your email of which requires additional information regarding the abovementioned planning permit application. 1. Alter application to include creation of carriageway easement Please see attached the altered application form. 2. Additional fee of 1 / 2 of $1318.10 (an invoice will be forward to you shortly) Payment has been made. 3. Owner to acknowledge that all repairs and maintenance of the bridge will be the landowner's responsibility. A brief written description of why this site was chosen for the bridge. Please see attached an attached letter of acknowledgement from the owner that all repairs and maintenance of the bridge will be the landowner's responsibility. The letter also clarifies the rationale regarding the proposed siting of the bridge. 4. Revised plans showing: - the bridge and driveway needs to be shown as 3.5 metres wide to allow for CFA access. - showing location of existing easements and the proposed easement, including dimensions from lot boundaries. more detail on the length and width of each angle of the easement. Please see attached revised plans with additional detail regarding the bridge design and easement details. Australia Belgium Canada Colombia Ecuador Germany Indonesia Kenya Myanmar New Zealand Nigeria Papua New Guinea Peru Philippines Singapore Timor-Leste United Kingdom United States Operations in over 100 countries TGM Group Pty Ltd (a Cardno Company) ABN 11 125 568 461 Level 1 27-31 Myers Street Geelong VIC 3220 Australia Phone +61 3 5202 4600 Fax +61 3 5202 4691 www.cardno.com D21/171278
Transcript

L ) Camino TGM

Our Ref: 20080-01 Contact: Chris Marshall

17th August 2021

Helen Evans Statutory Planning Department Colac Otway Shire P.O. Box 283 COLAC 3250

Dear Helen,

Planning Application PP41/2021-1 80 Great Ocean Road, Apollo Bay Buildings and works associated with a vehicle crossing bridge and Creation of a Carriageway Easement

We write in response to your email of which requires additional information regarding the abovementioned planning permit application.

1. Alter application to include creation of carriageway easement

Please see attached the altered application form.

2. Additional fee of 1/2 of $1318.10 (an invoice will be forward to you shortly)

Payment has been made.

3. Owner to acknowledge that all repairs and maintenance of the bridge will be the landowner's responsibility. A brief written description of why this site was chosen for the bridge.

Please see attached an attached letter of acknowledgement from the owner that all repairs and maintenance of the bridge will be the landowner's responsibility. The letter also clarifies the rationale regarding the proposed siting of the bridge.

4. Revised plans showing: - the bridge and driveway needs to be shown as 3.5 metres wide to allow for

CFA access. - showing location of existing easements and the proposed easement,

including dimensions from lot boundaries. more detail on the length and width of each angle of the easement.

Please see attached revised plans with additional detail regarding the bridge design and easement details.

Australia • Belgium • Canada • Colombia • Ecuador • Germany • Indonesia • Kenya • Myanmar • New Zealand • Nigeria • Papua New Guinea • Peru • Philippines • Singapore • Timor-Leste • United Kingdom • United States • Operations in over 100 countries

TGM Group Pty Ltd (a Cardno Company)

ABN 11 125 568 461

Level 1 27-31 Myers Street Geelong VIC 3220 Australia

Phone +61 3 5202 4600 Fax +61 3 5202 4691

www.cardno.com

D21/171278

Carvino TGM

5. Please provide a flood report for the bridge and easements or written advice from CCMA that this is not required.

Please see the attached response from the COMA which does not require a Flood Impact Report and also note the site chosen is outside the Flood Overlay.

6. Provide copy of instrument/dealing no. AT100817E 23/4/20 as described on title for TP180997V & TP106695H

Please see attached.

7. How does the easement and proposed bridge link up with the existing easements created? Only creating easement for the house lot and not the other lot? It is considered appropriate to review the easements for the 3 lots and 'clean up' and remove unnecessary easements and create the appropriate access easements now. If you do this, please update the application form and also provide copy of title for the 3rd lot as well as providing the revised plan.

Noted please see the attached plan which provides a logical easement location to access all three lots.

8. An application for a permit by a person other than the relevant public land manager must be accompanied by the written consent of the public land manager, indicating that the public land manager consents generally or conditionally either:

- To the application for permit being made.

- To the application for permit being made and to the proposed use or development. - Where there is no public land manager, an application for a permit must be accompanied by

the written consent of the Secretary to the Department of Environment, Land, Water and Planning.

We have discussed this matter with Geoff Brooks of DELWP who has not objected to the requirement for a bridge however he has advised that DELWP is unable to provide long term tenure over the land. He has suggested that Council extend the road reserve over the land and enter into a maintenance agreement with the landowner. As you are aware we have already requested Council's view regarding this matter and await your reply.

If you have any queries please do not hesitate to contact me on 5202 4600.

Yours sincerely, CardnoTGM

Chris Marshall Planning Manager, Regional Victoria/Principal

Attachments — Amended application form Letter of acknowledgement from the owner Revised bridge plans Advice from the COMA Copy of Instrument Proposed Easement details

17 August 2021 Commercial in Confidence 2