8 The Esplanade – L Tower & 1 The Esplanade – Backstage April 14 – 21, 2012 Detailed daily construction schedules are available at: o http://ltowerconstructioninfo.com/ o Updates are also available via Twitter from “ltowerinfo ” or email us at [email protected] L Tower – highlights: Saturday, April 14 o L Tower crane mast extension starting at 9:00 am Tuesday, April 17 o Concrete slab pour, level 36, starting at 10:00 am, levels 33 – 34. Wednesday, April 18 o A wall and column concrete pour, levels 36 – 37 starting 1:00 pm Thursday, April 19 o A wall and column concrete pour, levels 36 – 37, starting 1:00 pm Saturday, April 21 o L Tower, further crane mast extension starting at 9:00 am Backstage – highlights: Daily, April 16 - 20 o Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons. o There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site. o Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.
Transcript

8 The Esplanade – L Tower & 1 The Esplanade – Backstage

April 14 – 21, 2012

Detailed daily construction schedules are available at:

o h t t p : / / l t o w e r c o n s t r u c t i o n i n f o . c o m / o Updates are also available via Twitter from “ltowerinfo” or email us at

[email protected]

L Tower – highlights: Saturday, April 14

o L Tower crane mast extension starting at 9:00 am

Tuesday, April 17 o Concrete slab pour, level 36, starting at 10:00

am, levels 33 – 34. Wednesday, April 18

o A wall and column concrete pour, levels 36 – 37 starting 1:00 pm

Thursday, April 19 o A wall and column concrete pour, levels 36 –

37, starting 1:00 pm Saturday, April 21

o L Tower, further crane mast extension starting at 9:00 am

Backstage – highlights: Daily, April 16 - 20

o Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons. o There will be two (2) concrete trucks

doing four rounds each (8 in total) in and out of the site.

o Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.