KITT PEAK NATIONAL OBSERVATORY
Operated by The
ASSOCIATION OF UNIVERSITIES FOR RESEARCH IN ASTRONOMY, INC.Under Contract With The
National Science Foundation
Member Institutions:UNIVERSITY OF ARIZONA
CALIFORNIA INSTITUTE OF TECHNOLOCY
UNIVERSITY OF CALIFORNIA
UNIVERSITY OF CHICAGO
UNIVERSITY OF COLORADO IN BOULDER
HARVARD UNIVERSITY
UNIVERSITY OF HAWAII
UNIVERSITY OF ILLINOIS
INDIANA UNIVERSITY
MASSACHUSETTS INSTITUTE OF TECHNOLOGY
UNIVERSITY OF MICHIGAN
OHIO STATE UNIVERSITY
PRINCETON UNIVERSITY
UNIVERSITY OF TEXAS AT AUSTIN
UNIVERSITY OF WISCONSIN
YALE UNIVERSITY
12 October 1983
LADIES AND GENTLEMEN:
We enclose a copy of the CT^O/KPNO Long Range Plarj coveringthe period FY-1985-89 which is bein£ formally submitted tothe National Science Foundation by tTh€t^Corporate_ Office thisweek.
With best wishes.
GB/fed
Enclosure
Yours sincerely,
Geoffrey BurbidgeDirector
RECEIVEDNOAO
OCT 14 1983
DIRECTOR'S OFFICE
950 North Cherry Avenue
P.O. Box 26732
Tucson, Arizona 85726
AC 602 327-5511
Cable: AURACORP, Tucson
Telex: 666-484 AURA KPNO TUC
JOINT
CERRO TOLOLO INTER-AMERICAN OBSERVATORY
AND
KITT PEAK NATIONAL OBSERVATORY
LONG RANGE PLAN
FY-85 THROUGH FY-89
CONTENTS
I. LNTRODUCT ION I- 1
II. THE SCIENTIFIC FORECAST II- 1
III. THE PLAN Ill- 1
Observatory Operations Ill- 1
Scientific Staff HI- 8
Telescopes , Instruments And Computers 111-10
Research and Development 111-30
IV . NEW LARGE APERTURE TELESCOPE AT CTIO IV- 1
V. 15 METER NATIONAL NEW TECHNOLOGY TELESCOPE (NNTT) V- 1
I. INTRODUCTION
The Kitt Peak National Observatory and the Cerro Tololo Inter-American
Observatory are together responsible for filling a large part of the national
need of U. S. astronomers for optical and infrared observing facilities. The
Observatories' facilities comprise 7 telescopes on Cerro Tololo and 9 night
time telescopes on Kitt Peak. The 4 meter telescopes at both Observatories
are their most important instruments for night-time astronomy, and they are
used for a wide variety of observations at the very limit of the technology in
optical astronomy. This long-range plan will outline what is needed over the
next five years to maintain and improve these facilities. It will also
describe the new projects which are essential to the vitality of U. S.
astronomy.
The planning basis for normal operations is that the Observatories will
continue to operate at their current levels of effort. Note that these levels
have improved in relation to those of the last long range plan when the
Observatories were at their lowest point after the cutbacks of previous years
and were not able to operate all their existing equipment, let alone undertake
major new projects. At present, as a result of the improved funding for FY-
84, lowered world inflation, and a more favorable exchange rate in Chile, the
Observatories have been able to rebuild to the point that they can reopen and
support most of their previously closed facilities. Consequently, for their
long range planning, the Observatories are assuming the future availability of
staff and resources for the operation of the existing telescopes and
improvement of their auxiliary instrumentation. In addition, both
Observatories are planning major new projects, the 3-5 meter class telescope
at CTIO and the National New Technology Telescope (NNTT) at KPNO, to meet the
needs of their user community and to make the first major increase in
1-1
telescope size since the completion of the Hale 5 meter telescope. Such
projects, of course, will require special funding, well in excess of the
normal operating budgets .
During the planning period KPNO intends to improve existing telescopes
and laboratory facilities and to continue the development of new
instrumentation. Telescope improvements include the installation of automatic
guiders, TV acquisition systems, computer control of pointing, finding and
instruments, automatic dome control, and console room observing at all
nighttime telescopes except the #4-0.4-meter and the Burrell-Schmidt . Effort
in the area of instrumentation will include the development of photon counting
detector systems, intensified CCDs and especially infrared arrays. Resources
will also be directed toward the development and improvement of existing
instrumentation. Improvements to the gratings laboratory and increased effort
in coatings research and techniques are also planned. The coating and grating
facilities at KPNO are unique national resources which must be maintained and
improved. Further development of remote observing techniques are anticipated,
and concomitant increases in the sophistication and capacity of KPNO computer
systems must be made. The major effort at KPNO during the period will of
course be continued work on the National New Technology Telescope. A detailed
description of the project is included as a separate section of this plan.
At CTIO the plans for improving existing instruments cover several
areas. Major efforts will continue in optical and infrared instrumentation to
keep the Observatory at the forefront of what is possible with modern
technology. Infrared detector arrays are expected to produce as large gains
as CCDs have for optical astronomy, with the result that factors of 10 to 100
or more improvement in observing efficiency can be expected for infrared
imaging and spectroscopic observations. Optical instrumentation efforts will
1-2
concentrate on making both higher spectral and angular resolution available
over what CTIO can now offer. It is anticipated that CCDs will be provided on
the smaller telescopes, thereby greatly increasing their power. To take full
advantage of the improved instrumentation, CTIO plans to complete its
modernization of the control and acquisition systems for the smaller
telescopes during the period. The increased use of two-dimensional detectors
will require expansion of CTIO's computing capabilities to handle the large
amounts of data produced by the devices . It is likely that recent
developments in microcomputers will enable data-handling needs to be met at a
cost below that of existing image processing.
CTIO's major project for 1985-1990 period will be the 3-5 meter class,
infrared-optimized telescope. A 5 meter telescope would be the world's
largest infrared telescope; at the same time it would double CTIO's light
gathering power for optical research. By basing the telescope structure and
building design on the Multiple Mirror Telescope (MMT) and by using a
lightweight mirror of the type being developed for the NNTT, engineering and
construction costs will be much lower than for a conventional design. It will
also be possible to build the telescope on a short timescale, so that it could
be ready soon after Space Telescope is launched.
All aspects of this plan are consistent with the conclusions reached by
the Astronomy Survey Committee of the National Academy of Sciences under the
Chairmanship of George B. Field. The Committee stated in its final report (p.
119):
"The National Centers face a difficult task in responding to the
diverse needs of a heterogeneous user community. They will continue
to need the strong support and encouragement of sponsoring federal
agencies in the decade ahead. The Centers must be funded at a level
1-3
that not only provides for the maintenance of existing facilities and
staff but also permits the acquisition of appropriate new equipment
in addition to the major capital expenditures recommended by the
Astronomy Survey Committee."
Finally, it is important to note that this plan is being written at a
time when the AURA ground based observatories are being consolidated into a
single organization. This reorganization is not yet complete, and it is
possible that the final structure may require alteration of some aspects of
this plan. However, the principal features of the plan arise from the goal of
providing the best astronomy possible, and thus it is unlikely that the major
objectives of the Observatories described herein will change under the new
administrative structure.
1-4
II. THE SCIENTIFIC FORECAST
While the prediction of future scientific directions is difficult, it is
possible to forecast trends in the technology and relate them to future
astronomical research and instrumentation. In addition, the NAS report
identifies priorities for support of existing programs and new facilities for
the decade of the 1980's.
One of the four major new projects which the NAS report recommended for
funding is a National New Technology Telescope (NNTT) of the 15 meter class .
In addition, a number of projects already underway will affect the operations
and require the support of the national nighttime observatories . The Space
Telescope and the associated Space Telescope Science Institute are already
using the observatories as they develop more precise photometry for lists of
selected guide stars in the northern and southern skies and for staff
research. After launch in 1986, the Space Telescope will undoubtedly generate
many new ground-based astrophysical and cosmological projects requiring new
observations at CTIO and KPNO.
Additional projects currently underway which will lead to new users for
the Centers include the Gamma-Ray Observatory, IRAS and other NASA level-of-
effort programs including research with aircraft, balloons and rockets. The
Explorer and Shuttle-borne Spacelab programs are currently being given high
priority by NASA and the Administration. The Shuttle Infrared Telescope
Facility, now under study by NASA, was strongly recommended by the Field
Committee and could represent a major advance in infrared astronomy.
Ground based optical measurements will continue to provide in most cases
the only tool by which distances, chemical compositions, temperatures,
densities, and velocity fields can be studied. Thus, although the fraction of
overall discoveries has naturally decreased at optical wavelengths as other
II-l
wavelength regimes have become accessible, the need for optical observations
as critical analytical tools has never been greater. The importance of
ground-based observations for understanding discoveries made in space has, for
example, been clearly shown by work on X-ray sources. There is no doubt that
both Observatories will play an important role once the new space instruments
are launched.
Another way to forecast the direction of astronomical research is to
consider the technological advances that are likely to occur and their effect
on the field. Already the application of solid state and electronic detectors
has increased the power of existing telescopes a hundredfold or more. In the
case of the infrared, an entirely new field of astronomy has been created. In
the next five years it is likely that infrared spectroscopy and imaging will
reach a level of sensitivity comparable to that of all but the most sensitive
optical techniques . It is imperative that both Observatories stay at the
forefront of infrared technology so that they can continue to play an
important role in this field.
In the field of optical detectors, there is no doubt that solid state,
two-dimensional arrays such as CCDs will dominate in the next few years, for
they are already being put into routine operation. To make full use of these
devices requires a strong effort and capability in computer hardware and
software. Single exposures from the arrays will produce a million data points
or more, and large computers with extensive image processing packages will be
as important as the detectors themselves. The Observatories must maintain and
strengthen their efforts in these areas.
Exciting progress has occurred in other fields as well. The development
of Fourier Transform Spectrometers (FTS) has enabled observations of
astronomical objects to be made at resolutions greater than were formerly
II-2
available in the laboratory. Indeed, the KPNO FTS is used for laboratory work
as well as for astronomy. Similarly, spectacular advances may occur in the
field of high resolution imaging. Should some of the interferometric devices
work as well as is expected, an order of magnitude or more improvement in the
optical or infrared may occur.
Last but far from least will be the scientific impact of the two major
new instruments proposed; the new large aperture telescope at CTIO and the
NNTT at KPNO. The probable scientific gains provided by the addition of a new
5 meter class telescope, in the southern hemisphere and open to all American
astronomers, are very great. Our understanding of H II regions, giant
molecular clouds, and the process of star formation itself will be enhanced
when such a telescope can be used to study objects such as the Magellanic
Clouds and the galactic center. Cosmology and the study of the nature of
active nuclei of galaxies will benefit from the extraordinarily good seeing at
CTIO. The benefits to all areas of astronomy afforded by the NNTT are widely
documented and generally recognized by the astronomical community; perhaps the
most exciting scientific results of this telescope will be those discoveries
which cannot be predicted.
Over the next decade, KPNO and CTIO expect and plan to develop telescopes
and instruments which will make unique and significant contributions to the
evolution of astronomical understanding. It is on this foundation that this
Long-Range Plan is based.
II-3
III. THE PLAN
In the Plan we consider what is required to maintain the Observatories at
their current operational level, allowing for the estimates of inflation over
the next five years . This plan assumes identical 5% inflation annually in the
U.S. and in CTIO's Chilean operating costs (as measured in dollars). It also
includes a number of small projects and R&D efforts which are considered
essential if the Observatories are to carry out their designated role in the
national picture. Such projects are also necessary to attract and keep the
high quality scientific and technical staff required to maintain the
Observatories at the forefront of astronomy. The major new projects, a large
aperture telescope for Cerro Tololo and the National New Technology Telescope
project at Kitt Peak, are discussed in the immediately following sections.
The role of the national observatories in contemporary astronomy is that
they are expected to provide state-of-the-art optical research facilities to
all qualified astronomers and support the efficient and effective use of these
facilities. They must also foster relevant and innovative research among
their engineering and scientific staff to ensure that the first requirement is
fulfilled at any future date. Finally, they must continually establish a
record of professional excellence and achievement in both service and
research, in order that the professional respect of the astronomical community
for them will be maintained. In order to fulfill this role our Long Range
Plan has several major components: Observatory Operations; Scientific Staff;
Telescopes, Instruments and Computers; and Research and Development.
Observatory Operations
Observatory operations include both the telescope and facilities
III-l
operations areas. A major issue in telescope operations is the increase in
the number of visitors who use the telescopes each year. KPNO, in particular,
is facing a problem in this area as it does not have the facilities to handle
much more than the present load of visitors . At CTIO the recent
instrumentation improvements are attracting more observing proposals, and the
number of visitors is expected to increase. The causes of the growth of the
visitor load can be traced to increases in the number of telescopes on both
mountains in the last decade. In addition, at Kitt Peak the trend toward team
research, the growing use of telescopes during the daylight hours, and
comparatively short observing runs has accentuated the growth. CTIO is also
seeing an increase in the number of teams coming to observe .
The number of visitors at Kitt Peak increased from 172 in 1970 to 369 in
1982, with the 369 visitors actually making over 750 visits during the year.
During the decade, the 4 meter Mayall Telescope, the Stellar Fourier Transform
Spectrometer, the Burrell Schmidt, and the Coude feed have all been brought
into operation on the mountain. At the same time the annual appropriation to
the observatory in constant value dollars was decreasing at an average rate of
3% per year. Corresponding figures for CTIO show a similar pattern. In 1971
there were 70 visiting observers, and this number increased to 166 in 1980.
The 1.0 meter and 4 meter telescopes have been installed during the decade.
The annual rate of growth in visitor load has been nearly as large as at Kitt
Peak.
Although the observatories have made strenuous efforts to maintain the
quality of the support to visiting and staff astronomers, the quantity has
III-2
necessarily been reduced, particularly at CTIO. In addition, the balance
between user support and development programs has changed, and both program
areas are suffering from lack of funds . CTIO plans to restore the efficiency
that was lost on the smaller telescopes by the reduction of the night
assistant services with a program of modernizing the control systems and the
auxiliary instruments. KPNO has demonstrated how effective a small telescope
equipped with computer controls and modern detectors can be.
KPNO is now implementing a new policy designed to handle and reduce the
rate of growth of the visitor load. While continuing to provide the full
range of telescopes and instrumentation to visitors and staff in an effective
and efficient manner, so that scientific productivity is unimpaired, this
policy contains rules to limit the extent of team research, minimizes the
number of instrument changes, and encourages the development of remote
observing. Also, it should not be forgotten that public visitors visit both
KPNO and CTIO in large numbers. For example 86,696 people visited KPNO in
1982. The intention is to maintain public visitor facilities on both
mountains.
Remote Observing
Many astronomers now observe from an enclosed data room, collecting and
examining digital data. In many cases there is little reason why that room
need be on the mountain and not in the observer's home town. Modern
communications technology allows efficient and effective interaction with many
kinds of telescopic data at larger distances with real-time response to the
telescope operator. The obvious advantages to such "remote" observing include
less time and money spent on travel, less strain on the mountain's
III-3
overburdened facilities, and the possibility of more efficient and adaptive,,
scheduling of telescopes depending upon weather and seeing conditions .
Moreover, such an observing mode will make possible the real time simultaneous
use of more than one observing facility, such as KPNO-VIA or KPNO-IUE. This
capability is of great importance when making multi-frequency observations of
rapidly varying serendipitous events such as supernovae, novae and comets at
perigee .
One possible disadvantage could be the reduced scientific interaction
between the KPNO scientific staff and visiting astronomers and a decreased
familiarity with instruments.
A series of remote observing experiments is presently under way at Kitt
Peak, and within the limitations imposed by the relatively slow telephone data
rate (one acquisition TV frame, every 30 seconds), the experiments have thus
far proved quite successful. They have proceeded to the point where the
Intensified Image Dissector Scanner will be available to visitors routinely
for remote observing in February' 1984. Further experiments are being made to
increase the video data transfer rate. At satellite data rates many of the
present inconveniences would disappear.
KPNO, therefore, is contemplating a proposal for a multi-observatory
time-shared observing link for use by a large number of users who would
receive but not transmit data. Observatories within the United States might
then be used by observers working from their home institutions. When
affordable satellite links become available, the service can be extended to
CTIO and to observers in Canada and Europe. Observers will communicate back
to observatories via land line voice and terminal links . Remote observing may
also be an essential feature for the most effective operation of the NNTT,
particularly since it must be located in a site of superlative seeing
III-4
conditions where hypoxia can appreciably reduce appreciably the effectiveness
of the people working there.
The evolution of this facility is being approached conservatively since
the hardware and software available for such a system are changing rapidly.
Our cost estimates are likely to need revision, downward, it is hoped, with
future advances.
Facilities Maintenance
At CTIO, the major projects for the physical plant that need to be
carried out are the acquisition of a supplemental frequency converter for
Cerro Tololo, an extension to the astronomers' dormitory on the mountain, the
long-mentioned Tololo road improvements, replacement of Tololo temporary
buildings, and construction of a new visitors' center on Tololo. In La
Serena, a number of worn vehicles are scheduled for replacement and a new
full-capacity stand-by generator for the office/workshop area should be
purchased.
Tololo's electrical connection to Chilean power is via a 50 to 60 Hz
frequency converter now running close to its rated capacity; such a system
provides electricity at about half the cost of running diesel generators . An
additional converter will be required to meet the increased needs of the new
large telescope and to serve as a backup for the existing one.
With the installation of modern detectors such as CCDs, the number of
visitor requests for telescope time and the number of teams of observers (as
opposed to single observers) has increased notably. As the detectors are
installed on additional telescopes besides the 4 meter and 1.5 meter, CTIO
anticipates that the number of visitors will exceed the capacity of the
present dormitory facilities, and plans to build a ten room annex to meet the
needs .
III-5
While it is unlikely that funds will be available in the early years of
this plan to pave the 23 mile long dirt road connecting Tololo to the public
highway, it should be feasible to install guardrails on the most dangerous 10
miles of the road, thereby reducing the hazards. This project now deserves
high priority.
The nearly 20-year-old "temporary" buildings on Tololo (powerhouse,
warehouse, garage, and workshops) are long overdue for replacement.
The present visitors' center also falls in the "temporary" category and
should be replaced with a new, well-equipped structure properly designed for
handling the growing numbers of visitors on the mountain. CTIO must presently
reject many requests for visits for lack of adequate and properly furnished
facilities .
CTIO projects that building maintenance will continue in the next six
years at its normal level, now that a main backlog of deferred projects will
soon be cleared .
CTIO's most pressing vehicle needs at the moment are: (1) replacement of
the Coquimbo-La Serena commuter bus (required by Chilean law if CTIO is not to
pay a transportation bonus to the entire Chilean staff); (2) a pick-up
delivery van for the Santiago Office; and (3) a stake-body pick-up for the La
Serena compound .
Finally, a supplementary emergency power generator is needed for the
offices, residences, shops and computer center of the La Serena Compound.
(The present generator is barely capable of supplying power needs for the
water system and computer center air-conditioning).
Kitt Peak National Observatory is now more than 20 years old. Many of
the basic facilities are in need of upgrading and general repair. In
particular, the water system is often pushed to its maximum capacity because
III-6
it depends upon collecting runoff from rainfall and melting snow. A water
well and pumping stations are required to provide a dependable source of
potable water.
The dining room and kitchen need to be upgraded and enlarged. A modern
serving line is needed to comply with health code standards for a cafeteria.
The dining room must be enlarged to replace table space lost to improved
serving lines and to continue to accommodate usage by personnel from McGraw
Hill Observatory, Steward Observatory, Warner and Swasey Observatory, National
Radio Astronomy Observatory, and engineering and operations staff from Kitt
Peak National Observatory.
A second story addition to the // 1-0.9 meter telescope building is
needed. The approximately 600 square foot addition is to house increased
computer and electronics required by CCD systems and to provide a console room
and astronomers office. This telescope is currently as oversubscribed as the
KPNO 4.0 meter telescope.
A first aid and fire station building is needed in a central location on
the mountain. The current first aid station is located in an old house
trailer across from the solar dormitory, and the fire station is located down
a hill in the maintenance area away from all telescope buildings . During the
winter with snow and ice on the road, it is difficult to drive the fire truck
up the hill. A combined first aid and fire station building located "on top"
near the Visitor Center would be the logical place for public visitors to go
to obtain emergency first aid treatment.
Larger, more spacious dormitory facilities are needed for the permanent
employees assigned to work at Kitt Peak. Permanent employees are currently
assigned a dormitory room only large enough to accommodate a single twin size
bed, and thus the rooms are too small for long term accommodations. A minimum
III-7
of five dormitory rooms built as studio apartments are needed for resident
staff members.
Normal maintenance of the mountain facilities includes such items as
repainting the 4-meter telescope building, repair of mountain roads, and
replacing the two ten year old buses used to transport employees to the
mountain.
Funding for major maintenance projects has also been included for the
Tucson facilities. Typical projects to be considered are re-roofing,
replacement of heating and air conditioning equipment, and paving of parking
facilities. Recent studies have revealed significant deterioration of some of
the photographic plates in the KPNO plate collection. This collection is a
valuable national resource consisting of 6000 Palomar Sky Survey plates, about
4000 original KPNO plates, and the 660 plates of the recently acquired
Southern Sky Atlas. To prevent further damage, an environmentally controlled
plate storage facility is needed at the Tucson headquarters .
The Tucson library is one of the best astronomy libraries in the world,
but it has very nearly run out of shelf space. If no additional space is
found, older volumes of journals will have to be discarded to make room for
new ones, and the library's pre-eminence as a research facility will be
considerably diminished. A simple expansion to the library can be made which
utilizes existing structural members and thus greatly reduces the cost. Such
an expansion would provide the necessary shelf space for a period of about ten
years .
Scientific Staff
The Scientific Staff, which includes the tenure, tenure-track, support
Ill-i
scientists and postdoctoral fellows, takes an active part in the operation of
the observatories' research facilities in addition to carrying out independent
research. The activities include assisting visitors in the use of telescopes,
instrumentation, and data reduction equipment. The staff also assumes major
responsibilities in the development of new telescopes and instrumentation, the
improvement of existing research facilities, and in devising new methods to
increase the efficiency with which telescopic facilities can be used. In the
interval covered by this plan, the scientific staff at KPNO expects to be
increasingly involved with the development of systems and concepts that will
ultimately be related to the NNTT project. In order to fulfill this added
demand and at the same time maintain Observatory activities at their current
level, additional staff positions will have to be created during the planning
period. The plan also includes funding for a scientific meeting to be held
annually at KPNO, additions to the Visiting Research Scientist Program,
continuation of the summer student program, provision for a postdoctoral
program and increments to the staff and visiting observer travel budgets .
At CTIO the Visiting Resident Scientist Program will be continued and the
postdoctoral program will be restored; both programs contribute significantly
to the maintenance of a stimulating scientific atmosphere at CTIO's remote
location.
The advent of the new large telescope at CTIO will provide many new
research opportunities and increased operational responsibilities for the
Scientific Staff. As a result, at least two positions will have to be created
above the level planned for FY-84 as the telescope project gets underway.
Additional positions will be needed as the project proceeds.
III-9
Telescopes, Instruments And Computers
The most spectacular advances in ground-based observations in the last
decade have come from the utilization of new detectors . Solid state
electronic detectors are replacing photographic plates and image tubes for a
wide range of observations in the optical and infrared. These devices achieve
an enormous gain in observational capability, allowing in many cases
measurements limited only by photon statistics of the faintest detectable
sources and of the sky. However, for the most efficient utilization, their
particular characteristics in most cases require substantial modification of
existing instruments, or even construction of new ones. They also place a
much heavier burden on instrument control and data analysis computers and on
the telescopes themselves. Many of the instrument projects for the 1980's
will involve either major upgrading of existing instruments by incorporation
of these detectors or development of entirely new instruments specifically
matched to them.
Telescopes
Both KPNO and CTIO plan to improve the capabilities of their existing
telescopes in order that the telescope facilities continue to be suitable to
the ever-increasing needs of the instrumentation. By the end of this period
all KPNO night-time telescopes, with the exception of the #4-0.4 meter and
Burrell-Schmidt telescopes, will be equipped as follows:
integrating acquisition TV systemautomatic guider
computer controlled pointing and finding
automatic dome control
console room observingfull computer control of all instruments/spectrographs .
111-10
Increasing oversubscription rates, improved detection efficiency and
increased complexity of instrumentation require that the efficiency of
observing be improved comensurately. The above features have existed for some
time at the 2.1 and 4 meter telescopes and, in part, at some of the other
telescopes . The plan is to carry out this program at most of the other
telescopes at a steady rate, duplicating existing equipment where appropriate
and taking advantage of new technology where cost effective.
Integrating acquisition TV systems have been constructed for the KPNO and
CTIO 4 meter telescopes and for the KPNO 2.1 meter telescope. Planned systems
for the small KPNO telescopes would be similar but would utilize the currently
available higher density (64k or 256k verses 16k) memory chips in order to
reduce costs. All KPNO acquisition TV's, currently intensified silicon
intensified target (ISIT) vidicons, will be replaced with commercially
available intensified CCD cameras. These will provide improved spatial
resolution and stability as well as reduced distortion and extended service
life.
New automatic guiders will utilize either image dissector tube sensors or
TV guiders. These will improve the quality of the data taken both by better
guiding than can be provided by individuals as well as by freeing the
astronomer for quick-look review of the data. At some facilities, initially
the Coude Feed, high band-width image stabilizers will be implemented to
remove seeing induced image jitter. Such a system has been in use at the
McMath telescope for over 10 years and has proven capable of providing
increases in the throughput of a high resolution spectrograph by up to one-
half order of magnitude.
Computer controlled pointing and finding has been in operation at the 4
meter and 2.1 meter telescopes for some time. Its availability at the other
III-l 1
telescopes requires no new hardware, only completion of the software and
determination of the pointing error maps. This is being done as part of the
effort to replace the Varian computer systems .
Automatic dome control is a simple matter of adding a coarse encoder to
the dome track and implementing software developed for the larger
telescopes. This is also being done with the computer replacement.
Console room observing has become a necessity with array detectors such
as the CCDs. CCDs are currently in use at the 4 meter, 2.1 meter, Coude'
Feed, and #1-0.9 meter telescopes. Plans are currently underway to implement
similar detectors at the #2-0.9 meter telescope and to install infrared arrays
at the 1.3 meter telescope. Tne plan is to significantly increase the
observing room area at the #1-0.9 meter telescope and to construct a similar
room at the #2-0.9 meter facility.
Full computer control of the instrumentation spectrographs is necessary
if console room observing is to be fully implemented. As older instruments
are retired, their replacements are being designed and fabricated with this in
mind. With the distributed processing philosophy, most new instruments will
have either micro-computers or micro-processors built into them to provide
control and sequencing functions. The communication to the facility host
computer will be simple and strictly for the purpose of commands and data
recording. Existing spectrographs are being upgraded to provide remote
control of apertures, calibration sources, etc. Provision for more classical,
on-the-platform observing will be maintained at all facilities to permit the
testing and development of new equipment as well as the use of non-KPNO
equipment.
The above-listed improvements will achieve the following objectives:
maintain the facilities of the national optical observatory at thelevel of first rate capabilities;
111-12
upgrade the capabilities of the telescopes to a level commensuratewith the increased requirements of the planned new instrumentation;
prepare these facilities for interactive remote observing.
The planned improvements to the #4-0.4 meter and the Burrell-Schmidt
include a subset of the above listed equipment. Given that the #4-0.4 meter
telescope has a computer for control of the photometer, it will be a simple
matter to implement automatic tracking of the dome as well as computer
controlled finding. The most pressing need for the Burrell-Schmidt is an
automatic guider. The combination of the better site (KPNO versus Cleveland)
plus improved optics (primary and prisms) have demonstrated the structural
deficiencies of the telescope. Users are now interested in fainter objects at
higher dispersion, so that longer exposures are required and as a result an
automatic guider has become necessary. Construction of an automatic guider is
more difficult at the Schmidt because the use of objective prisms dictates
that an auxilliary telescope be used for guiding. This necessitates some
system to ensure mutual collimation of the guide telescope and the Schmidt,
and this can be accomplished by servoed collimation of the telescope and guide
telescope. Proper automatic guiding would require replacement of the 30-year
old drives with more modern torque motor systems. Finally, we plan to
implement automatic tracking of the dome via use of a small microprocesser for
conversion of hour angle and declination to azimuth.
In FY 1983 KPNO began work devoted to the understanding of atmospheric
phenomena and its relation to and effects on imaging in ground based
telescopes. In FY 1984 a program of systematic monitoring of the telescope
and dome thermal and turbulence environment and of the image size and motion
will be begun. Midway through the period of this plan the results of these
two efforts will be used to improve the imaging properties of existing KPNO
telescopes and will be applied to the design of the 15 meter telescope. The
111-13
thermal and image monitoring program will very likely lead to additional
environmental conditioning equipment being installed at the telescopes. This
will presumably consist of heat rejection and air conditioning equipment. The
investigation of seeing phenomena will probably lead to the application of
active and/or adaptive optics at least at the major facilities. The
utilization of such devices is anticipated for the 15 meter telescope, and
thus the early implementation on existing telescopes would provide the double
benefit of improving the performance of those facilities while providing
valuable experience for the design of the large telescope.
At CTIO, the plan is to finish the small telescope drive modernization.
New drives on the 1 meter and 0.9 meter should be installed in FY 1984 but
may, along with the system on the 1.5 meter, require some additional effort in
order to maximize their usefulness .
CTIO plans to purchase additional acquisition TV systems . The existing
Quantex systems are growing old and unreliable. It is also difficult to
obtain spare parts for these obsolete units. The addition of remote control
capability for the small telescopes requires that TV acquisition systems be
purchased for the 1 meter and 0.9 meter as well. Current plans for the 1.5
meter remote offset guider call for its incorporation in a TV autoguider
system also, this in addition to the aperture-viewing TV. Thus, at least two
new acquistion TV systems should be obtained early in this period. (one is
budgeted for FY 1984).
During the period CTIO will finish the remote offset guider for the 1.5
meter telescope (start FY 1984).
Leaky memory autoguider units will be purchased for all the small
telescope acquisition TV systems.
CTIO will continue efforts to improve local dome seeing. Insulation,
111-14
heat control, ventilation, and monitoring equipment will be used in a
concentrated effort at measurement and seeing improvement .
The 5 meter telescope project should be at a stage where it requires most
of CTIO's resources in the area of telescope engineering very early in this
period. Additional support personnel will be required as the project
develops.
Instrumentation'
The plan for the FY 1985 - FY 1989 period is to maintain the present
level of emphasis on instrument development relative to other observatory
programs. However, the increasing sophistication, complexity, and cost of
modern systems makes the state-of-the-art more expensive each year. Thus,
unless a substantial infusion of funds is obtained, the real level of activity
in this area can be expected to decrease. It is particularly important that
the national observatories provide instrumentation at least as modern as that
provided at university observatories . In recent years this has not been the
case. The first imaging photon counting detector systems will not be put into
service at the national observatories until late in calendar year 1984, but
other observatories, including U.S. institutions as well as foreign national
centers, have had such systems available to their users for over half a
decade. During the remainder of the 1980's it is planned that the national
optical observatories improve their competitive position in instrumentation in
order that the nation's astronomers be provided with the very best, most
modern equipment.
During the remainder of this decade KPNO will attempt to maintain
intensive efforts in the area of optical instrumentation while intensifying
111-15
its activities in the application of self-scanned infrared detectors. In
addition, KPNO will emphasize the improvement of instrumental efficiency, from
the point of view of throughput as well as spectral and spatial utilization.
Lastly, work on speckle techniques will commence.
In the area of optical detectors, KPNO will implement intensified CCDs
operated in an integrating mode for imaging at the 4 meter and 2.1 meter
telescopes and for medium and high-resolution spectroscopy at the 4 meter
telescope. This work was begun in early FY 1983 with the first instrument
being put in service for visitors in mid-FY 1983. Un-intensified CCD imagers
have been in service at the 4 meter telescope prime focus and the #1-0.9 meter
telescope for a number of years. In addition, un-intensified CCDs are in
service as spectroscopic detectors at the 4 meter R-C and echelle
spectrographs and at the 2.1 meter coude spectrograph. A CCD
spectrophotometer will be constructed for use at the #2-0.9 meter telescope
during the period FY 1984 - 1985. At this point, five of the KPNO telescopes
will be equipped with integrating CCDs. Efforts will continue for the testing
and implementation of new CCDs as they become available. The KPNO CCD
controller/display system can operate CCDs with formats up to 4096 square, and
currently there are three such controller/display systems available for use on
KPNO. Depending upon user demand, it may be necessary to construct one or
more additional units, given that CCDs will be useable on five of the
nighttime telescopes by the end of FY 1985.
An intensified CCD operated in a photon counting mode will become
available at KPNO in late 1984. This instrument will be used with the 4 meter
R-C spectrograph and will be similar in concept to that developed at the Mount
Wilson and Las Companas Observatories. Investigation and testing of other
photon counting concepts is expected to lead to the deployment of higher
111-16
performance systems later in the period of this plan. Multi-anode-
microchannel-array (MAMA) detector systems offer the potential of higher
photon flux rates and greater time resolution than intensified CCDs . The
latter property makes them more suitable for speckle observations. Other
concepts, such as those utilizing encoded optical feeds to sets of
photomultiplier tubes offer the potential for even greater count rates and
time resolution. Instruments employing these or other types of photon
counting detectors will be developed first for spectroscopic use and later as
speckle systems .
The availability of both blue and red sensitive detector systems at KPNO
provides the opportunity for more efficient utilization of the telescopes via
such devices as double spectrographs and the array-equivalents of multi
channel photometers. During FY 1984 KPNO will construct a fast blue-optimized
spectrograph camera for use with the 4 meter R-C and echelle spectrographs .
Later during the period of this plan a double spectrograph will be constructed
to utilize that camera, or a version thereof, to feed a two-dimensional photon
counting detector for blue sensitivity and a red-optimized camera to feed an
integrating CCD detector for red sensitivity. Such a spectrograph could be
fed using the currently available aperture plate/slit technique or remotely
controllable fiber-optic feeds. KPNO also has planned a multi-color prime
focus camera to permit simultaneous multi-band CCD photometry. This system
would be similar to a 3-channel photometer but would utilize three CCD
detector heads .
KPNO also plans to take advantage of the higher sensitivity of
integrating intensified CCDs and two-dimensional photon counting detectors by
implementing very narrow band imagers. These will be developed utilizing both
Fabry-Perot and tuneable Lyot type filters.
111-17
The level of resources applied to the implementation of infrared array
detectors at KPNO will be increased during the period of this plan. A 32-
element linear indium-antimonide (InSb) charge injection device (CID)
currently being evaluated by the KPNO Detector and R&D Program is the first
major effort in this area. KPNO and CTIO have undertaken joint efforts in the
evaluation of this type of array and in the procurement of other similar
devices. The utilization of other technologies (CCDs, hybrid devices, etc) by
manufacturers has made the availability of area arrays with sensitivities out
to 20 microns imminent. Recognizing that KPNO is an excellent site for 10
micron observations, a high resolution cryogenically cooled echelle conceptual
design has been developed for the utilization of such an array.
Lastly, KPNO plans to continue the development and improvement of
existing instrumentation. This will include the production of new gratings
for existing instruments, the implementation of high reflectivity coatings as
they become available, and the upgrade of "work-horse" type instruments such
as photometers and polarimeters. Further improvements to the 4 meter Fourier
Transform Spectrometer (FTS) are planned, including the implementation of
array detectors and a multiband slicer. This combination will permit
simultaneous high resolution spectra to be obtained.
At present CTIO is directing its main efforts in optical detectors at
present toward improving its CCDs and making them available on the smaller
telescopes and toward obtaining two-dimensional photon-counting systems. CTIO
will construct three complete CCD systems which can be used at the 1.5 meter,'
1 meter, and 0.9 meter telescopes and at the Cassegrain focus of the 4 meter
telescope. A substantial effort to take full advantage of new, large-format
CCDs currently under development is planned. Such a device would have an
order of magnitude larger number of pixels than CCDs currently in use at
III-l*
C-.C. _i replace the vidicon detectors, CTIO is presently beginning the
c:ns:r.::i3n of two-dimensional photon-counting systems for use at the 4 meter
and -.: nezer or 1.0 meter telescopes. It is likely that these projects will
ay-a-d :-:d 1985.
3-:= these very basic instruments and detector systems are brought up to
state-::-trie-art efficiency, CTIO plans to add a number of somewhat more
specialized instruments so as to allow its Southern Hemisphere observational
studies :o branch out into new directions. This is an important thing for
CTIC t: do because there is only one major private U.S. Observatory in the
S:ut'~, vhich might otherwise have been able to provide this more specialized
Tr.ise new instruments would include:
- A high-resolution, high signal-to-noise optical spectrometer foruse on the 4 meter telescope. At this telescope it is presentlypossible to obtain a maximum resolution of about 8-10 km/sec withdigital detectors and using a wide enough slit to observe fainterobjects. About four times higher resolution would provide areasonable match to the widths of the absorption lines in the spectraof dwarf stars, and thus permit line profile studies and betterdetection of weak absorption lines. CTIO is studying a pier-mounted,Cassegrain fiber-optics fed echelle spectrograph for this purpose.
- A spectropolarimeter device to be added to the complement ofexisting spectrographs. This should be designed to work at quitehigh resolution, for detailed studies of the profiles of emissionlines in the spectra of active galaxies.
- A multi-object, remotely controllable fiber optics feed for usevith the 4 meter and possibly the 1.5 meter spectrographs. This willoffer a great increase in the efficiency of these telescopes for sometypes of observing.
- A speckle interferometer.
Irvards the end of the 1985 - 1989 period CTIO will be fully occupied
producing the instruments for the 5 meter telescope. These instruments
include:
- A double spectrograph, similar to the one designed by Oke for useon the 200 - inch telescope.
111-19
- CCD and 2D photon counting detectors for the double spectrograph.
- A CCD direct-imaging system.
- A duplicate multi-object, fiber-optics spectrograph feed system.
- A duplicate high-resolution, high signal-to-noise spectrometer.
The infrared program at CTIO has five main goals for the 1985-1989
period, namely:
(1) To upgrade the performance of existing telescopes until they arenearly competitive with similar telescopes at otherobservatories which were optimized for infrared observations abinitio.
(2) To provide the required instrumentation for the proposed newtelescope when its design is finalized.
(3) To take advantage of new detector technology as it becomesavailable. In this regard CTIO will try to stay competitivewith northern hemisphere observatories, while not attemptingmajor technological development which is beyond CTIO'sresources.
(4) To provide support or follow-up for space-based observations(both in the infrared and at other wavelengths).
(5) Within the constraints of major projects, to undertake smallerprojects of a highly opportunistic nature, in accordance withcurrent developments in astronomy.
These goals can be achieved by means of several projects, some of them
already underway:
(1) The 4 meter LR photometer performance will be upgraded. Thisincludes replacement of the 4 meter wobbling secondary andconstruction of an IR photometer optimized for the CTIO 4meter. The wobbling secondary is nearing completion and isscheduled for installation in January 1984. Design work isbeginning on photometer optimization. Construction will notbegin, though, until current major IR projects are completed,which will be in the early part of FY 1984. This represents
about a one year delay over previous time estimates because of
limited human resources at the Observatory.
(2) CTIO plans to develop instruments which use infrared arrays. Anarray of 32 infrared detectors has recently become availablecommercially. CTIO has begun a joint program with KPNO, andwill proceed to implement it in a system usable on a telescope
so that its performance can be judged. This will take placearound the middle of FY 1984 and continue into FY 1985.
111-20
Implementation of near-infrared arrays is likely to be thedominant activity within the IR program during the first yearsof the plan period. Obvious uses of such arrays are in twoareas:
Spectroscopy. The CTIO IR spectrometer, to be completed in
FY 1984, has been designed to accept a small (8-element)
array initially, and should be adaptable in the future to
somewhat larger arrays as they become available.
Mapping (Imaging). Either 1- or 2-dimensional arrays willradically improve the efficiency and resolution of infraredmapping, making it more directly comparable with visualwavelength imaging. The chief difficulties withinstrumentation of this sort are likely to be dataacquisition hardware and software, since reductionprocedures will in all probability resemble those currentlyused for visual wavelength CCD imaging.
(3) New infrared instrumentation for the large aperture CTIOtelescope must be developed. This telescope will be optimizedfor IR performance. It should have dedicated infraredinstrumentation. Construction would begin toward the end of theplan period. The instrumentation would have capabilitiesresembling that of existing 4 meter and 1.5 meter telescopeinstruments.
(4) A number of smaller projects will be of value. Some maycomplement or support space-based observations . These are seenas small, specialized instruments which can be constructed with
a relatively modest effort. Work on some of these may begin atthe start of the plan. They include:
Mm./sub-mm. detector. This would be a state-of-the-art(helium-3 cooled) far infrared detector which would beoperated at the Cassegrain focus of the 4 meter telescopetogether with the other 4 meter infrared detector
systems . Since millimeter observations can be carried outduring dry but non-photometric conditions, this wouldprovide a considerable amount of "free" time for millimeter
work. Millimeter and sub-millimeter observations in theSouthern Hemisphere are likely to become of increasinginterest as observations from IRAS and from several
Southern molecular-line surveys become available .
High spatial resolution. Interest in achieving neardiffraction-limited spatial resolution in the infrared hasincreased in recent years, and a number of Northern
observatories have already implemented one-dimensional"speckle" systems in the near-infrared. Such a system maybe implemented at CTIO by the end of FY 1984. Considerable
111-21
improvement in efficiency (though not in resolution) shouldbe achievable with infrared arrays of modest size .
Long range planning for visual photometers must take into account the
expected utilization of CCDs. For applications involving either crowded field
photometry and/or stars fainter than 14th magnitude, CCD photometry is clearly
superior to classical single or multiple channel photoelectric work. This
does not mean that one should abandon the old ways: photoelectric photometry
will continue to have several applications .
(1) monitoring of objects with very fast time variability and foroccultations .
(2) work in spectral regions where CCDs are not sensitive (ultravioletand infrared, for example).
(3) setting up bright standards for checking calibration of CCD fields(especially if CCD data were obtained on non-photometric nights).
(4) work on individual stars widely scattered over the sky
Therefore, needs for visual photometers during the period FY 1985-1989
are dominated primarily by the necessity to maintain existing photometric
equipment at a level of high reliability. Visual photometry represents
roughly 40% of total telescope usage at present, primarily on the smaller
telescopes. As the older equipment wears out, it is desirable to replace it
with equipment with greater efficiency, as has been done in the past. As
computers are made available on all but the smallest telescopes, the manual
photometers should be replaced by automatic photometers . Two of these are now
in service, but in the face of increased demand a third may be required during
the period of this plan.
Another minor improvement would be provision of a capability of quasi-
simultaneous visual and infrared observations. On the new 4 meter photometer
this can be accomplished simply by the construction of an appropriate f/30
visual coldbox.
111-22
A third improvement would be the construction of a modern 2-channel
visual photometer for the 1.5 meter (also usable on the 0.9 meter). This
represents a greater development effort than those listed above, and would be
justified only by strong user interest in such an instrument. It should be
flexible enough to be used as a faint star photometer (star and sky channels)
and also as a 2-color photometer. Such a device would require a staff
scientist to devote his support effort to optical photometry.
Finally, fiber optics can be used to develop a multiple object
photometer. This instrument would be useful for monitoring variability of
objects against a reference star, especially on nights when thin clouds would
ordinarily preclude such observations .
Computers
New computer systems are being implemented at the Kitt Peak National
Observatory, both on the mountain and downtown. The new mountain facilities
are designed to replace the Varian 620 systems with a system of computers
which will provide reliable data acquisition and process control along with
augmented data reduction and real time processing capabilities . The Tucson
computers are designed to replace the Interactive Picture Processing System
(IPPS), the Varian V74, the Hewlett Packard 2100, and the Cyber 170/720
systems with a facility that can better handle the current and anticipated
volume of two dimensional data. The new computer systems for both the
mountain and downtown will be based upon using Digital Equipment Corporation
(DEC) systems. This will provide benefits of both hardwark and software
compatibility.
On the mountain, the Varian computers will be replaced with DEC 11/24 or
111-23
11/44's depending on the need of each telescope facility. The replacement
computers will operate independently in a stand alone mode for data
acquisition and telescope control . The new computers are required to handle
the increased volume of data supplied by array detectors. The systems will be
equipped with much greater disk and memory to accommodate the needs of two
dimensional data. Data reduction capability will be provided at the
telescopes to provide many basic reductions in full and quick look reductions
in all cases. In the continuing development of research capabilities, the
most important features of the mountain computer systems are the capacity for
expansion and availability of the peripherals, since these are the most common
limiting features .
A VAX 11/750 will be installed in the mountain administration building to
serve as a central data reduction facility. The observatory has included
funding for a limited facility in the FY 1984 Program Plan. Future
requirements include connecting the central data reduction computer to all
telescope computers by a network system. By providing hardware that is
equivalent to the downtown data reduction, all of the interactive reduction
and analysis facility (IRAF) software will thus be available for use on the
mountain. The VAX 11/750 may serve as a full IRAF satellite, which would
require the purchase of additional peripherals .
Eventually, there should be a high speed data link (possibly microwave)
between Kitt Peak and Tucson. This will provide the full power of the
downtown computer systems to the domes, and reduce the need for additional VAX
class computers on the mountain where they are difficult to maintain. The
data link will also be needed if remote observing is to be supported
efficiently on a regular basis .
All computer systems, both on Kitt Peak and downtown need to be connected
111-24
by a network such as Ethernet . This will permit sharing of expensive
peripherals and provide extensive computer power at all facilities .
In the FY 1984 Program Plan we discussed the importance of replacing the
Cyber 170/720 computer with a system more compatible with current observatory
needs . Funding limitations may not allow us to replace the Cyber facility
during FY 1984. In this case it should be replaced in early FY 1985.
The Cyber computer system serves two purposes . It serves first as a
batch data reduction and analysis systems for the entire observatory and
second as a host for the IPPS system. The Cyber, despite its large computing
capability, is becoming a hindrance in fulfilling the computing requirements
of the observatory. The architecture of the system is archaic and it is a
major obstacle in providing portable code that visitors can run at their home
institutions, or that the observatory can run on Kitt Peak. We need to
replace the Cyber with a system that is more compatible with the other data
collection and data reduction systems at the observatory and throughout the
national and international community. For the Cyber lease costs alone, we
could purchase several VAX-class machines per year and give KPNO far more
computing resources than are currently available with the Cyber. Thus, we
need to replace the Cyber with a "host" computer of the super VAX class.
The downtown IPPS facility was developed in 1975, and, it is no longer
able to cope with the increased volume of data coming from an increased number
of digital detectors. To illustrate the need, we note that the IPPS was
unable to completely fill the demand for image analysis, even in 1975. In
1975 no digital arrays were in regular use at KPNO. Today, the 5 CCD systems
are in use and a 6th is under construction. The need for image analysis
exceeds the available facilities by a factor of 3 or 4. Even more important,
astronomers cannot now explore reduction techniques, but are forced to
111-25
concentrate on a few minimal operations . In order to manage the increasing
volume of image data and to allow Kitt Peak to exchange image processing
software with other astronomical centers, the development of the IRAF is
underway.
The IRAF will consist of satellite computers dedicated primarily to a
single image reduction user. Each satellite will be capable of driving an
image display for interactive image processing and general data reduction and
analysis. The VAX 11/750 has been selected as the first IRAF satellite
computer and two of these systems have been installed in Tucson. These
satellite computers will be connected to a large host so that expensive
peripherals (array processors, large disks, group encoded magnetic tapes) may
be concentrated on one system, and so that the interactive user on a satellite
can spawn large numbers of batch reductions (on the host) without destroying
the interactive usefulness of his satellite. Tnis is a very important
feature, needed to permit the visitor who is resident in Tucson for only a few
days to complete reductions which are partially interactive and partially
computation intensive. Implementation of these major software and hardware
programs on Kitt Peak and in Tucson will require that additional staff
positions be filled in the Computer Support Department.
With the introduction at CTIO of new instrumentation such as the 2D
Photon Counting Devices, large-format CCD chips, IR arrays, and an Imaging
Fabry-Perot, CTIO expects that by 1985 the data reduction and analysis load
both in La Serena and on the mountain will have suffered a several-fold
increase. The experience at other major observatories indicates that the
MV/8000 in La Serena will not be able to handle more than two users
simultaneously reducing 2D data, and most likely only one user at a time
carrying out reductions of 3D data (such as produced by an Imaging Fabry-
111-26
Perot) or sophisticated programs such as RICHFIELD. On Cerro Tololo, of
course, not even this capability is currently available. The instrumentation
currently planned will produce, by 1985, a quadrupling of the data output on
the mountain as well as the need for facilities to allow simultaneous
reduction of 2D and 3D data by six to eight users. By 1989, we anticipate yet
another factor of two increase in demands on the computers. Hence, thre will
be an urgent need by 1985 to significantly increase CTIO's computing
facilities.
Within realistic funding constraints, two options exist for increasing
the capacity for data reduction and analysis in La Serena and Cerro Tololo.
These are (a) the purchase of another large, multi-user computer such a the
MV/10000 or VAX-11/780, or (b) acquisition of several of the new generation of
super-micro computers such as the Sun Workstation. Under option (a), CTIO
would very likely install the new computer in La Serena, and relocate the
MV/8000 on Cerro Tololo. A fast data transfer link between the MV/8000 and
the central S230 Eclipse computer in TOLNET would allow the former to be used
for on-line data reduction by observers on the various telescopes included in
TOLNET (although the practical limitation of two simultaneous 2D users will
probably still apply). In La Serena, the new computer replacing the MV/8000
would handle the same number of users as before, but most likely at a 50-100%
increase in speed.
With option (b), CTIO envisions employing super-micro computers as
satellite workstations to the MV/8000 in La Serena, connected in a limited
network such as Ethernet. Each super-micro would have its own large (80-160
MByte) disk, an inexpensive image display device, and possibly a magnetic tape
drive. The VICOM image display system would be left on the MV/8000 for users
requiring it's sophisticated facilities. The super-micros would run UNIX,
111-27
offering considerable software compatibility with other astronomical
institutions. The implementation of super-micros on the mountain could also
take the form of satellite workstations of TOLNET or as stand-alone data
acquisition and reduction systems.
CTIO, in consultation with KPNO, is presently studying both options (a)
and (b) in further detail, and expects to reach a decision by the middle of FY
1984 as to which it will pursue. In fact, a combination of both options may
eventually be required to meet the expected data reduction and analysis
burden .
By 1985, CTIO expects to have the 4 meter, 1.5 meter, 1 meter and 0.9
meter telescopes included in TOLNET, and to be using this as the data
acquisition system for the optical photometers, IR photometer/spectrometer,
SIT Vidicon, and CCD. However, for new instrumentation CTIO will most likely
begin to utilize the new, more-powerful, stand-alone super-micro computers.
In the period 1985-1989, CTIO expects to improve communications between
La Serena and Cerro Tololo to allow for the possibility of remote observing.
This would probably entail the purchase or leasing of a multi-channel
microwave link. This link might also be feasible for data transmission
between the Cerro Tololo and La Serena computer systems.
Software support requirements can be expected to increase in direct
proportion to any increase in hardware. Hence, for the increase in computing
facilities outlined above, an additional four to five programmers should be
added to the staff. At least two more electronics engineers will also
probably be needed to support the hardware increases .
111-28
Laboratory Improvements
While the KPNO optical fabrication facilities are excellent, continual
improvement is required if the needs of sophisticated new instrumentation and
of the 15 meter NNTT are to be met. Most of the optical polishing equipment
is nearly 20 years old and more capable equipment is now available.
Similarly, better test equipment, primarily that associated with digitally
recorded interferometric testing, has decreased the amount of art while
increasing the amount of science, and thus the cost-effectiveness, of the
optical polishing process. During the period of this long range plan, KPNO
will procure new large aperture interferometric test equipment, probably a
ZYGO interferometer, as well as implement computer controlled polishing,
either by the modification of existing equipment or by procurement of a
complete system.
The KPNO Gratings Laboratory is a unique national resource which can
produce gratings which are unavailable from any other source. This equipment
is also over 20 years old and recent attempts to rule large, high blaze angle
gratings have demonstrated the need for improvements to this facility.
Planned improvements include replacement of the bell-crank operated diamond
carriage with a linear motor stroker and implementation of closed-loop
positioning of the diamond.
Research and development performed under the Technology Development
Program for a National 15 meter Telescope has demonstrated the need for
improvement of KPNO's optical coating facilities. Again, these facilities
must meet requirements which cannot be met cost-effectively by commercial
sources. The efforts will be directed to two areas: the first toward solving
the problems associated with providing multiple layer coatings on large
111-29
surfaces and the second toward research on the coatings themselves . NNTT
conceptual designs include the utilization of refractive elements to obtain
large fields of view. Tnus the study of broad band anti-reflection coatings
must also be included.
Research and Development
The Observatories will continue to take a leading role in Research and
Development for the Optical/IR community. The purpose of the R&D program at
KPNO is to provide the technological basis for advanced planning of new
telescopes, such as the NNTT and the CTIO Large Aperture telescope, and for
the upgrading of existing facilities. The direction, emphasis and goals of
this program are based on our current understanding of the scientific needs of
astronomy and of current technological capabilities and potentials . Thus the
plan emphasizes basic technology, particularly in the detector field, and work
toward development of an NNTT.
There are two necessary ingredients for a successful R&D program.
First, there must be a very tight coupling between the scientific goals of the
community, the scientific staff, the instrumentation program, and the R&D
effort. This coupling will be provided by the users committees of the two
Observatories and by strong scientific staff involvement in all phases of
these activities. Secondly, since virtually all the R&D effort is at or
beyond the technological state-of-the-art, a knowledgeable, creative and
imaginative engineering and technical group will be maintained in the
Observatories.
In the following exposition, research and development will be subdivided
under the following subheadings: Basic Technology, including detectors,
111-30
cryogenics, and optical coatings, Prototype Instrumentation, and NNTT
Instrumentation.
Basic Technology
Included in this area is the development, adaptation and evaluation of
optical/IR detectors, development of cryogenic capabilities, and possibly
grating and coating improvement. In general, this effort should be directed
toward applications of clear scientific need, either for improvements in the
efficiency, capabilities or performance of existing instrumentation or for new-
instrumentation for existing telescopes.
It is anticipated that the adaptation and evaluation of both linear and
two-dimensional IR detectors will be a major, high priority effort over the
next 5 years at KPNO and CTIO. The application of high quantum efficiency,
multi-detector arrays to IR spectroscopy and mapping will result in enormous
gains in sensitivity and efficiency over our present techniques which, in
virtually all cases, utilize single detectors.
The relatively small IR arrays (32 x 32, 32 x 1) are expensive ($20K
each) compared to silicon CID's and CCDs, and the evaluation and application
costs are still dominated by manpower. Nevertheless, every attempt will be
made to incorporate LR arrays into effective, usable instruments for staff and
visitor use in the near future. It is a major Observatory goal to use solid
state arrays as the primary detectors on most instruments. Their compactness,
high quantum efficiency, geometric stability and large dynamic range make them
the clear choice for foreseeable detector applications. In order to reach
this goal, it is most important to continue the R&D evaluation and
adaptation of silicon CCDs into the near future. In addition, R&D work on
111-31
high speed, two-dimensional detectors with application in advanced sub seeing
instruments and possible spectroscopic systems is necessary. Tnis work would
include techniques for cryogenic temperature control, efficient use of
cryogens, cryogenic actuators, etc., as required.
Prototype Instrumentation
At present the R&D program at KPNO is working on a prototype cryogenic
spectrometer. Two examples of areas for future prototype instruments are IR
cameras and spatial interferometric devices:
IR Cameras
With the availability of two-dimensional IR arrays comes the possibility
of vastly improved mapping capabilities . The scientific potential and
importance of efficient "picture taking" in the IR cannot be overestimated.
It is comparable to the importance of optical imagery to all of astronomy and
heretofore has been unattainable. Prototype cameras for rapid picture taking
on a variety of spatial scales and spectral regions will be required in order
to demonstrate observing techniques and background suppression approaches, as
well as the limitations and scientific utility of such devices.
Spatial Interferometry (both optical and IR)
The next frontier in optical astronomy is probably the development of
very high spatial/angular resolution capability. This area is also of high
scientific interest in the IR. R&D work will begin on the development of
111-32
fast two-dimensional photon counting arrays and on-line processing hardware.
The capability has clear application to spectroscopy as well as imaging.
NNTT: National New Technology Telescope Instrumentation
In addition to work on the NNTT itself, which is described in Section V,
the R&D effort must aim toward defining the instrumentation needs and
understanding the required associated technology. In order to take full
advantage of the potential capabilities of an NNTT, virtually all
instrumentation will require careful design and development. Included in this
are the following:
1. larger area and pixel size detectors2. large gratings3. spatial and spectral interferometry techniques4. seeing studies
In the case of detectors, whether applied to imagery or spectroscopy, a
problem exists in a resolution mismatch between the best currently available
solid state detectors and the image forming characteristics of a 15 meter
class telescope. It is part of our Long Range Plan to start a special program
in detector and instrument development that will address this problem and
assure the availability of appropriate detectors and instrumentation when the
telescope is placed in operation. It is clear that detector developments
should proceed in two distinct areas: large-scale CCDs and large-scale event-
sensitive photoelectric detectors. In both cases, significant departures from
current and anticipated technology are involved. Moreover, until there is
secure knowledge of the technological possibilities, there will be no
competent basis for predicting the level of performance that is desired and
required. Therefore, serious attention to the subject of detectors will begin
in FY 1984.
111-33
IV. NEW LARGE APERTURE TELESCOPE AT CTIO
If the United States is to maintain a balanced astronomical program in
the next decade, it is important that small to moderate projects be funded in
addition to the major ones. For example, the major project currently under
way, Space Telescope, and the first priority project recommended by the NAS
Committee, AXAF, have a total cost between 1.5 and 2.0 billion dollars.
Unquestionably both instruments will depend heavily on ground-based telescopes
and will increase the demand for their use. Being space instruments, both
will have all-sky coverage. For the U.S. to take full advantage of their
potential, it must ensure that adequate ground-based facilities are available
in both hemispheres . If we consider that CTIO can double its light-gathering
power in the optical and increase its infrared capability by more than a
factor of ten for about one tenth of the cost of the NNTT and one hundredth of
the cost of Space Telescope, the conclusion is inescapable that a relatively
small project such as CTIO's planned 3-5 meter class telescope deserves
serious consideration. Indeed the NAS Committee and its panels recognized
this fact. Examination of the Committee's recommendation and the report of
the panel on Ultraviolet, Optical, and Infrared Astronomy shows that the
highest ranked groundbased optical/IR projects are first, the NNTT, and second
a 4 meter class IR telescope in the Southern Hemisphere.
It is also important to realize that ground-based telescopes offer
capabilities in certain areas that are far superior to the current generation
of space instruments. A 5 meter telescope on the ground has more light
gathering power than the Space Telescope and is superior for high resolution
spectroscopy of objects brighter than the night sky. Space Telescope will
have no infrared instruments at all initially and SIRTF missions will only
last a week. Thus, ground-based telescopes will offer the only long term,
IV-1
continually available infrared facilities for many years. Finally, of course,
ground-based telescopes have a much wider field of view than does Space
Telescope.
As a result of the improved outlook for funding in FY 1984. CTIO has been
carrying out studies together with its users and outside consultants of an
infrared-optimized telescope with an aperture as large as 5 meters. The
concept, which has the enthusiastic support of the users and staff, is based
on the lightweight mirror technology being developed for the NNTT and the
Multiple Mirror Telescope (MMT) mount and building design. A single,
lightweight 5 meter mirror in an altitude-azimuth (alt-az) mount and building
similar to that used for the MMT would be much less expensive to build and
requires a considerably smaller engineering effort that a telescope and dome
of conventional design. The MMT has proven that it meets the stringent
tracking and pointing requirements for a modern infrared telescope; therefore,
it is logical to utilize as much of the design effort and expertise that went
into it as possible. First estimates indicate that such an instrument would
cost about SIOM and could be built in three years after a mirror blank became
available.
A preliminary proposal for the project has been prepared and submitted to
the NSF with the FY 1984 program plan; consequently, the full details of the
project are not repeated here. Since the submission of the proposal, CTIO has
been fortunate to have the assistance of the project scientist for the MMT
from the Harvard-Smithsonian Center for Astrophysics, Dr. N. Carleton, and the
project engineer, Mr. T. Hoffman, in beginning a study of how the MMT design
can be modified to accept a single, lightweight 5 meter mirror (Figure IV-
1). The availability of alternate mirrors is also being investigated. The
main work for FY 1984 and FY 1985 will be as follows: to establish the
IV-2
Figure IV-1. Perspective view of proposed 5 meter telescope for CTIO,
IV-3
optical and mechanical specifications of the telescope and carry out the
corresponding optical and structural design studies, to obtain detailed cost
estimates, to test and select a site for the telescope on Tololo or Cerro
Morado, and to begin design work on the auxiliary instrumentation. Once these
steps are carried out, actual construction can be initiated.
As an illustration of how the MMT design can be modified to accept a 5
meter single mirror, Figure IV-2 shows two views of the resulting telescope
and building. The modifications to the mount mean that the yoke base would be
shortened by 36 inches . The azimuth bearing support height would be reduced
by 16 inches and a 12 inch high spacer would have to be added under the
elevation bearings. However, the rest of the design can be taken over
virtually unchanged, so that a minimal amount of engineering work (less than
or equal to two months) would be needed before the mounting fabrication could
go out for bids .
The side view of the mount and building in Figure IV-2 indicates that the
building profile would change from rectangular to a more oval form because the
shutters would have to be reconfigured. Otherwise the only building
modifications would be to replace the existing bridge crane with a shutter-
supported crane and to increase the width of the side rooms . It would not be
necessary to develop the building interior as extensively as was done for the
MMT because laboratory and shop facilities already exist on Tololo; this would
reduce the building costs somewhat.
IV-4
?&
o^1 v
H^
s
^
Figure IV-2. Elevation views of proposed 5 meter telescope for CTIO,
IV-5
Mr. Hoffman has developed a time schedule, shown in Figure IV-3, that
illustrates how the telescope could be completed in three years after funding
became availble. As mentioned above, the modification to the mount and
building would be minor and both could go out to bid within the first months
of the project. The telescope tube structure, mirror cell, and head rings
would, of course, require new designs, but they are all conventional and
should not cause any difficulties. The lightweight, honeycomb mirror will be
strong, and will not require a special mirror mount to maintain its optical
figure .
Under the assumption that funding started in FY 1986, then the telescope
could be ready in FY 1988. The availability of the mirror blank is, of
course, crucial. As it will depend on the progress of the NNTT project, it is
also important to investigate other sources for mirrors . To date two
possibilities are known for backup mirrors: a Canadian 4 meter blank and an
Italian 3.5 meter blank. Should a lightweight 5 meter mirror not be produced,
then it would be logical to see if the Canadian 4 meter blank could be
obtained as an interim solution. First conversations suggest that this may be
possible .
In any case, the budget tables consider that the project will start in FY
1986 and follow the schedule described in Figure IV-3. Note, however, that
the project could get under way earlier if funding were available and the
production of lightweight mirrors could be accelerated. Given the success of
IRAS and the need for ground-based observations of the new infrared sources it
is finding, there is ample justification for building the telescope now. For
the same reason it would be desirable to have the telescope ready as soon
after the launch of Space Telescope as possible.
IV-6
<I
OqC
1
*
o HH H-
M yo (D
* Ui
oJ(13D.
C
o
1-1
oo
Den
rr
fiCa
oo
ol-tl
•a
<-\o
XIo
(Da.
3n>rr
0)
rf
rc>\-'
rt>
nc
XIID
c
^OJECT PLAN FOR SM TELESCOPE - EARLIEST FIRST LIGHT OPT/ON
MONTHSAFrza
PROJSC 7
STAA'T
STEGGlNO,Comm Tree
MECHANICAL
OESt&N 4FA&RICATION
TEL? SCOPE
TUBS
ST£<JC 7 ORE
(TTS)
MOUNT
BUJLD/AJ&
OA/- J/ Fe:
SELEC7 jACQUIRE
Blank
, TRANSTOSTSELECT \ BLANK
OPT SAO"
Cg^V
PrelimW llOUSS
OPTICALffEPlNE f P/NALIZEOPTICAL CUSS/ON
I Ye
V
PROCURE
secondary BLAA/k:
F/Guke PR/mavy * SECONDARY MiRVORS ( 2,'i ,*1
2 y-eyV
2'/
\7 kwSPVR r
/ MIRROK
I Optical shop
AluMINUEMfRROtiS
f1 TESTpA'/s-tA.? y/a/ cell w/SECCWOW/
„x-
DeE/rJ£
TELESCOPi'ZEQ73 Review/\ree/ne Telescope Pears, define acceptance tests,direct / Oversee p#oc*c*s} establish operational. p\ams, etc.
A7EE-/NE j P//UA l /2EMECHANICAL OE SlG^I OPPRI rt/XJIOX C£LL , SEC Mi.K^OK MTG $,frtSTR MT£ ETC
PB/rfA/t •/
CELL
OXTAIL
OES/GN
SECOND \\ M/RMOR \, rfTG osr
SELECT
\ VEKDOg
\ 2-Pa&RiCATE
SEC MiliklOkl Mm siEST
SOLiCir B'L>S \
SELECT •JaMDOkZ \j f CO^ITMACT FOX \' PJi! CELL PAS „ PA9.VICA7E PV/rtAH'/ MiutOk> C£ll f9/K>ii-yF^ms^j
ANALYTICAL j STRUCTURAJDESlGw OF TELESCOPE TUBE $7XVC7U#e(Urns) . Fabricate Misc mech items
SOliCiT QiOS,SEl£QT vendor
T",rB &%%£?*.QCavJiNGS^jm pursy n*& xj
SELECT
&UIL.DIN& #£VlEWJ #£V'S£ S^KUCTUfZALARCHITECT/Et** MMT 'ait**/** AsjalKI? J ^Cawtf
Sol tor B/osi StlLECTcoNraAcroR. Hoe.
TTS PAO. TTS FAOQiCATtON (<j /-Of,)
Transport
Mount ConpoN£NTS
Solicit SiOS I5CLEC7 COMUACTOe
POR SHUTTER PA9^
Solicit &jdsSELECT
Covtrac rcxR
l^f^^ff9 0fZp SrTG &<"<-&** PAMICA7ION (a/IPJ)CONDUCT
SeE/NG. , 0/J S/r^ teir/wrem etc / ( s^'am, stvi a***'**
/ CXCAVAT/ON r^
SPOTTER PAORlCAT/QM^
7)tANSPO/2T
%P/*IFORCING
Confer(tvcr/ON JUav/W;
SuvrrefiCOrfPONElN TS
TRANSPORTSlog- CortroNENri
to site i installEXCCT&l/ilOiaih ?teo«/c* \ J^liGN, ISCRVICEI //mttaic SMirrrctl ^ j rs
I 'TRANSPORT
IPa/nam yPft/1M OR
CELL TO
TEST I OPTICAL.PKiMAJiA shopCEIL 1*4 I
Jranspor rPRIMARYMirror / cellANO £*£COND.Aiey
Mirror / mtqto Site
FINISH>*/STALJ_ 3OILDIAJ0.
V
}-
V. 15 METER NATIONAL NEW TECHNOLOGY TELESCOPE (NNTT)
During the next decade the role of the national ground-based observatory
will change. Implementation of the VIA to its fullest capability, successful
launching of the Space Telescope, and the data from IRAS will all serve to
place unprecedented demands upon ground-based observatories for complementary
investigations and observations of newly-discovered phenomena. The case for
these investigations and the new, ground-based telescope required to make them
has been set forth by the Strittmatter Committee and, more recently, by the
NAS Astronomy Survey Committee. These committees, and other important groups
in astronomy, have shown the need for a 15 meter class telescope on the ground
optimized for optical and IR observations. Furthermore, there is a stated
need for the National Observatory to assume leadership in the quest for its
completion.
During FY 1984 the 15 meter National New Telescope project will pass one
of the most important milestones along the path to completion: a final
selection of the telescope concept. This decision will be the product of five
years of concept studies (FY 1975 through FY 1980 through the Next Generation
Telescope Program), three years of technical feasibility activitis (the 15
Meter Technology Development Program), and innumerable contributions from
individuals and groups in and out of KPNO concerned with telescope design. In
mid-FY 1983 the Universities of Arizona and California joined with KPNO to
form a consortium to work toward the final concept selection. The major
activities of these groups will be the completion of technical feasibility
studies initiated under the Technology Development Program and the comparison
of the two competing concepts. A Scientific Advisory Committee (SAC) composed
of astronomers from throughout the United States has been established. The
Committee has been given the task of recommending which of the two concepts
should be chosen for the NNTT:
V-l
The Multiple Mirror Telescope (MMT) concept with four 7.5 metertelecopes mounted on a common structure and feeding light toeither separate foci or to a central optical beam combiner. Theexisting six-mirror MMT on Mt. Hopkins serves as a prototype formany of the important design features .
The Segmented Mirror Telescope (SMT) which differs from moreconventional telescopes principally in using a primary mirrorcomprised of segments held in position by a system of sensorsand acutators. The University of California has adopted this
approach for their Ten-Meter Telescope. The UC design is in arelatively advanced state of completion.
Figure V-l shows scale models of the two concepts along with a model of
the KPNO 4 meter telescope. For comparison purposes the three models were
constructed to the same scale.
It is planned that the concept decision be made in mid FY 1984.
Following the choice, the work will turn toward detailed design of the
telescope with emphasis on those technical areas most in need of better
definition. The telescope enclosure as well as the optical polishing facility
will be designed during this period. This work will carry on through FY 1985
and 1986. A major portion of the detailed engineering and architectural
design work will be carried out under subcontract. Only modest increases in
the NNTT Program staffing will be required to monitor such contracts and to
carry out the conceptual design of the telescope and instrumentation. A
complete telescope proposal will be generated in FY 1986.
Concurrent with the telescope design work in FY 1986 we intend to carry
out plans developed earlier for building an optics facility that will serve,
at a minimum, as the means for making the NNTT primary optics. At present,
none of the optical fabrication facilities available anywhere in the world are
really suitable for making all of the off-axis aspherics for the SMT or for
polishing the 7.5 meter mirrors for the MMT. A substantial investment in the
V-2
The Segmented Mirror Telescope(SMT)
FIGURE V-l.
15 METER NNTT CONCEPT SCALIi MODELS
The KPNO 4-Meter Telescope The Multiple Mirror Telescope
(MMT)
development of new optical technology has been made in recent years . There is
a follow-on need for a facility to produce optics taking advantage of this
technology and, in particular, to fabricate the NNTT optics. Properly
planned, the cost of this facility will be offset by reductions in the cost of
the NNTT optics that might otherwise have to be produced at high risk with
inadequate facilities or under subcontracts that would be inflated to include
the cost of new facilities. In order to avoid costly delays in the NNTT
completion, it is important to have the optics facility ready at the outset.
As with most large telescopes, the special nature of the primary mirrors
mandates special equipment and talent. Thus it is planned that the
construction of the optical fabrication/polishing facility be started in FY
1986. The cost of this in FY 1986 is modest and is felt to be cost effective
in that early availability of the facility will serve to shorten the duration
of the project.
It is planned that construction of the telescope commence in FY 1987 with
completion in FY 1992. Further increases in the staffing level will be
required to monitor the construction contracts as well as complete the design
and construction of the instrumentation.
Efforts are also being devoted to the selection of a site for the 15
meter telescope. A minimum-level two-year program of critically needed tests
was begun in mid FY 1983. This program and the sites to be tested were
defined by the Ad Hoc NNTT Site Survey Committee in the spring of 1983. On
the basis of the requirements set down by the committee, two sites were
selected for testing: Mauna Kea on Hawaii and the Pinaleno Mountains in
Southern Arizona. Preliminary testing of these sites has determined no
significant detrimental factors . The testing program will continue into late
FY 1985 with the actual site selection being made in late FY 1985.
The details of the plan for the 15 meter NNTT for the period of this long
V-4
range plan are given in Table V-l. This Table shows the progress of the
project from 1982 along with plans through the end of FY 1989. Table V-2
gives the details of the spending schedule through this period while Table V-3
shows the staffing schedule.
It is recongized that the 15 meter telescope will be instrumented and
operated in a fashion significantly different than current facilities .
Certainly, the telescope will be scheduled quite a bit differently than most
present facilities . More remote observing and queue scheduling will
undoubtedly be done. The scale of the instrumentation will be very much
different form that in use today. Study of these areas is necessary and is a
vital element of the large telescope program. KPNO, with its expertise and
experience in the construction and operation of major astronomical facilities
is in a unique position to lead and participate in the development of
telescope technology while at the same time pushing foward in the related
areas of detectors and instrumentation that will serve both present day and
future astronomers.
V-5
Table V-l
NNTT 15 Meter Telescope Project - Planning Schedule
Activity
SEGMENTED MIRROR TELESCOPE:
Segment Fab. DevelopmentSegment Control Tests
MULTIPLE MIRROR TELESCOPE:
Borosilicate Blank Devlp.Mirror Support Devlp.
TELESCOPE DESIGN STUDIES:
Comparative Design Studies
Comparative Instrument Studies
Final Concept Selection
TELESCOPE DESIGN:
Telescope MountingInstrumentation
Telescope Enclosure
Optics Polishing Facility
CONSTRUCTION:
TelescopeMirror Blank Mfg
Optical Polish Fac .Optical PolishingMirror Supports
Telescope EnclosureInstrumentation
Computers & Controls
SITE SELECTION:
Select Test Sites
Site Evaluation
Site Selection
Site Preparation
1982 1983 1984
-#
-#
-1.8m
V-6
Fiscal Year
1985 1986 1987 1988 1989
-3 .5m- -7 .5m
-#
-#
-#
»
#
•#>>
»
»
»
»
Tabic V-2
NNTT PROGRAM - SPENDING LEVELS
(amounts in thousands)
Fiscal Year
Category 1982 1983 1984 1985 1986 1987 1988 1989
Personnel $ 363 $ 450 $ 460 $ 757 $ 893 $1280 $1630 $1746
Supp. & MatIs . 30 39 190 145 200 200 200 200
Other Services 157 336 1362 1470 1500 500 200 200
Dom. Travel 5 22 52 40 40 50 60 60
For . Travel 1 6 10 15 15 20 30 30
Equipment 12 159 165 440 1000
Construction 2000 10000 20000 30000
TOTALS $ 568 $1012 $2238 $2867 $5648 $12050 $22120 $32236
Notes: 1. Project scientist & site survey scientist are budgeted underthe KPNO scientific staff.
2. 5% inflation assumed for FY 1985, no inflation assumed thereafter
V-7
Category 1982
Table V-2
NNTT PROGRAM STAFFING PROJECTION
1983
Fiscal Year
1984 1985 1986 1987 1988 1989
Scientific 1 1 2 2 3 4 4
Tech. Prof. 3 5 5 8 9 12 13 14
Prof. Admin . 1 1 1 2 2 3 3 3
Admin/Clerical 1 2 2 2
Tech/Other 5 5 5 8 9 14 20 22
Maint/Service
TOTALS 9 12 12 20 23 34 42 45
Notes: 1. Authorized staffing level at end of fiscal year.2. Does not include project scientist (R. Lynds) and
Site Survey Scientist (M. Merrill), both arebudgeted under KPNO scientific staff.
V-8
TAIII.K 1
CLKKO Tlllillil INTLK-AMKKICAN 1Hi S i: l( V All IKY
AND
KITT I'KAK NATIONAL oh.SF.KVATOHY
I.ONO KANI.TC I'Ij\N SUMMARY
(FY I'JII.'. - FY 1989)
(An, d:; In Til,hi:,,11,(1:, )
FY-84 FY-85 FY--H6 FY-H7 FY-Ml FY-89
CTIO KI'NO CTIO KI'NO CTIO KI'NO CI 10 KI'NO CTIO KI'NO CTIO KI'NO
OBSERVATORY OPERATIONS 5 '.,951 5 9.1)5 5 5,(.8'. 5 9,901 5 6,255 510,57'. 5 h,'.:)2 511,015 5 6,'.II 511,'..15 5 (,,70/ 511,995
SCIENTIFIC STAFF 4 SUITOKT 952 1,465 1,000 1,656 1,050 1,7)9 1,101 1,1)26 1,157 1,917 1,215 2,01)
OBSERVATORY, 1'RO.ItCTS 1,397 1,382 1,64'J 1,1)09 5,6)1 2,024 6,1148 1,843 1,564 1,765 2,414 1,891
OTHER I'ROC-RAMS 2,643 3,445 6,249 12,682 22,7111 32,9)1
TOTAL I'UN $ 7 3(.)0 514,825 5 8,3)3 $16,813 512,916 520,586 $14,381 527,166 511,112 517,898 $10,356 $48,830
TOTAL CTIO 6, KI'NO $22,125 $25,146 5)3,522 541,749 549,030 $59,186
Inflation Rate: 5Z
OBSERVATORY OPERATIONS
Operations 4 Maintenance
TABLE 2
CERRO I'OLOIJl I (ITER-AMERICAN OBSF.HVA I'OKY
AMU
KITT I'EAK NATIONAL OBSERVATORY
I.ONC RANCE I'l.AN SUMMARY
(FY 1984 - FY 1989)
(Amounts In Thou;;au<Ls )
FY-84 FY-85 FY-86 FY-87 FY-88 FY-89crl0 KI'NO CTIO KI'NO CTIO KI'NO CTIO KI'NO (.Til) KI'NO (.Til) KI'NO
"''pay rol l\ Payroll Expenses $1,037 $ 2,988 $1,089 $ 3,142 5 1,143 5 3,299 51,200 5 3,464 5 1,260 $ 3,637 5 1,324 S3,8194 10 614 441 645 46) 677 486 711 511 747 5)6684 420 725 441 761 463 799 486 839 511 8IH
$1 ,037
585
400
52 ,02 2
5 333
98
62
5 493
Materials 4 SuppliesServices 4 Other Costa
Sub-total
Eiii'lneerlng 4 Technical Services .Payroll 4 Payroll Expenses 5 333 5 1.436 $ 350 $ 1.508 $ 367 $ 1.583 $ 3115 5 1.662 $ 405 5 1./45 $ 425 5 1,813
y 360 11)3 378 108 397 113 417 119 438 125 459199 65 209 68 219 72 2)0 75 242 79 254
Materials 4 Supplies
Services 4 Other Costs
Sub-tot a I
5 4,082 52,123 $ 4,308 $2,229 $ 4,523 $2,340 ?_^'49 W,_457_ $ 4.987 5 2.582 i_J_.JT±
5 493 $ 1,995 5 518 5 2.095 $ 543 $ 2,199 $ 570 S^09 S_ J>99_ $ 2,425 $ 629 5^546
Intlac Ion Kate: it
TAHI.F. 2 (Coiitlnueil)
l'.i|;e 2 of 4Inflation Kate: 57.
Administrative Services
Payroll 4 Payroll ExpensesMaterials 4 SuppliesServices 4 Other Costs
Sub-total
Suh-totnl 04M
Management Fee
Total OSM
FY-84
CTIO KPNO
$ 866 $ 1,7 73
117 205
983 755
$2,166 $ 2 733
$4,681 5 8 RIO
5 150 $ 300
54,831 $ 9 1 10
Construction 4 Major Maintenance Projects
Mountain Facilities $ $
City Facilities 120225
Sub-total
TOTAL OBSERVATORY OPERATIONS
5 120 $ 225(1)
54.951 5 9,335
(1) To be funded from FY 03 carryover
~~"
- .- .__
5 909 $ 1,875 5 95 5 $ 1,969 SI 00 1 $ 2 06/ $1 05 1 5 2 1 71
33 1 215 14 9 2 26 16 7 2 1/ 18 5 2'.9
1 0 32 799 1 084 8 19 1 1 18 8111 1 1 9'", 92 5
$2 2 74 $ 2,889 $2 1118 $ 1,014 $2 508 5 1 1 8 5 $2 6 ) 1 5 1 14 5
$4 915 $ 9,2 92 $5 160 5 9,/56 $5 4 18 510 24 ) $5 6119 $10 7 57
5 158 $ 315 $ 165 $ 111 $ 174 5 14 7 5 182 C; 16 5
55 073 $ 9,607 $5 12 5 $10,087 $5 592 $10 ,590 55 87 1 $11 12 2
$ 320 5 20 7 $ 860 $ 300 $ 840 e 150 $ 540 s 2 50
291 89 70 187 75 63
5 611 $ 282 $ 930 $ 3 7 5 $ 840 $ 4 2 5 $ 540 $ 113
$5 684 $ 9,901 $6 2 55 $10,574 $6 412 $i i ,015 56 .411 $11 415
FY-89
CI 10 KPNO
$1,105 $ 2,279
405 262
1,255 971
$2,765 $ 1,512
5 5,976 $11,294
$ 191 $ IHI
56,167 $11,677
5 540 $ 2 52
66
$ 540 $ 118
$6,707 $11,995
TABLE 2 (Cml Inued)
Page 3 of 4Inflation Rate: 57.
SCJE_NT 1FIC STAKE 4 SUPPORT
Payroll 4 Payroll ExpensesMaterials 4 SuppliesServices 4 Other G.sts
FY-84
CTIO KPNO
FY-85
CTIO KI'NO
752 $ 1.278 $ 790 $ 1,46027 28
200 160 210 168
FY-86
CTIO KI'NO
FY -87
CTIO KPNO
FY-88
CTIO KI'NO
829 5 1,533 $ 871 5 1,610 $ 914 S 1.69030 31 33
221 176 232 185 243 194
FY-89
CTIO KPNO
$ 960 $ 1,77534
255 204
TOTAL SCIENTIFIC STAKE 4 SUPPORT 5 952 5 1.465 5 1,000 $ 1,656 $ 1.050 $ 1.739 S 1,103 5 1.826 5 1,157 $ 1.917 5 1,215 $ 2.013
OBSERVATORY PROJECTS
New lnlt1 at ives
Coiupul e rs
l-irge Aperture Telescope
TOTAL OBSERVATORY PROJECTS
$1,081 $ 1,020 $362
316
915 $ 1,309 $ 1,381 5 1.174 $ 1,518 $ 1,443 $ 1,809 $ 1.515350 500 350 650 300 400 100 250384 3,900 5.030 1,655
$ 1,804 5 1.591
200 300
4 30
1.397 $ 1.382 $ 1,649 $ 1.609 5 5,631 $ 2,024 $ 6,848 5 1.843 $ 3,564 5 1,765 $ 2.434 $ 1,891
ft
TABLE 2 (Continued)
Pa£e 4 of 4Inflation Rate: 57.
FY-84 KY-85 KY-86 i'Y-87 KY-IIII FY-89
CTIO KPNO CTIO KPNO CTIO KPNO CTIO KI'NO CTIO KI'NO CTIO KI'NO
OTHER I'ROCRAMS
Detector Research & Development $ $ 278 $ $ 397 5 5 417NN1T Program 2,198 2,872 5,648Coalings Lib 70 74 77Oral logs Lib 67 70 74Visitor Pi ograin-Fore I gn Travel 30 12 II
TOTAL OTHER I'ROCRAMS 5 5 2,641 5 $ 1,445 $ $ 6,249
$ 418 S $ 4 5912,050 2 2,120
111 85
78 HI
15 16
SI 2,682 $ $22,781
$ 4 82
32, 216
119
86
18
$32, 911
TOTAL PI AN $ 7,300 $14,825 $ 8,333 $16,813 $12,936 $20,586 514,383 527,366 511,132 537,898 $'0,356 $48,8)0