+ All Categories
Home > Documents > Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and...

Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and...

Date post: 15-Nov-2020
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
53
Land Acquisition and Resettlement Plan (LARP) Compliance Report Project Number: 48042-001 September 2020 AFG: Panj Amu River Basin Sector Project (Chardara Subprojects Irrigation Scheme Package 6) Prepared by National Water Affairs Regulation Authority for the Ministry of Finance and the Asian Development Bank. This Land Acquisition and Resettlement Compliance Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Transcript
Page 1: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

Land Acquisition and Resettlement Plan (LARP) Compliance Report Project Number: 48042-001 September 2020

AFG: Panj Amu River Basin Sector Project (Chardara Subprojects Irrigation Scheme – Package 6)

Prepared by National Water Affairs Regulation Authority for the Ministry of Finance and the Asian Development Bank.

This Land Acquisition and Resettlement Compliance Report is a document of the borrower. The

views expressed herein do not necessarily represent those of ADB's Board of Directors,

Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation

of or reference to a particular territory or geographic area in this document, the Asian

Development Bank does not intend to make any judgments as to the legal or other status of any

territory or area.

Page 2: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

i

Table of Contents

ABBREVIATIONS .......................................................................................................................................... 5

GLOSSARY ..................................................................................................................................................... 7

EXECUTIVE SUMMARY .............................................................................................................................. 9

1. Introduction ......................................................................................................................................... 11

1.1 Background ........................................................................................................................................... 11

1.2 Constraint .............................................................................................................................................. 12

1.3 Objectives of the LARP ........................................................................................................................ 12

1.2 LARP-related Conditionality ............................................................................................................. 12

2. SCOPE OF LAND ACQUISITION AND RESETTLEMENT ...................................................... 14

2.1 Scope and Rationale for Resettlement .............................................................................................. 14

2.2 Census Survey ..................................................................................................................................... 14

2.3 Types and Summary of Impact ................................................................................................................. 14

2.4 Impact Assessment .............................................................................................................................. 14

2.4.1 Affected Households and Population ................................................................................................ 14

2.4.2 Impact on Land ................................................................................................................................... 14

2.4.3 Impact on Trees................................................................................................................................... 15

2.4.4 Impact on Income and livelihood ...................................................................................................... 15

2.4.5 Impact on Vulnerable and Severely Affected Households .............................................................. 15

2.4.6 Indigenous Population ........................................................................................................................ 15

2.4.7 Gender Impact .................................................................................................................................... 16

3. SOCIOECONOMIC PROFILE OF THE AFFECTED PERSONS .............................................. 17

3.1 Socio-Economic Survey ........................................................................................................................... 17

3.1.1 Methodology ........................................................................................................................................ 17

3.2 Demographic Characteristics of the Ahs .......................................................................................... 17

3.2.1 Gender Segregation ............................................................................................................................. 17

3.2.2 Age of APs ............................................................................................................................................ 17

3.2.3 Education .............................................................................................................................................. 17

3.2.4 Marital Status ....................................................................................................................................... 18

3.2.5 Religion .................................................................................................................................................. 18

3.3 Household Characteristics ..................................................................................................................... 18

3.3.1 Family Structure .................................................................................................................................. 18

3.3.4 Occupation of the AHs ........................................................................................................................ 19

3.3.5 Income and Expenditure ..................................................................................................................... 19

4. LEGAL AND POLICY FRAMEWORK AND ENTITLEMENTS ..................................................... 20

Page 3: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

4.1 Policy and Legal Framework for Land Acquisition and Resettlement.............................................. 20

4.2 Land Acquisition and Resettlement Legislation in Afghanistan ........................................................ 20

4.3 Relevant Provisions from the Law on Land Management in Afghanistan ....................................... 20

4.4 Relevant Provisions from the Law on Land Acquisition in Afghanistan....................................... 20

4.5 ADB’s Involuntary Resettlement Policy ............................................................................................... 21

4.7 Principles and Policies for the Project .............................................................................................. 21

4.8 Eligibility and Entitlements ............................................................................................................... 22

4.9 Entitlement Matrix ............................................................................................................................. 22

4.10 Assessment of Compensation ............................................................................................................. 24

5. PUBLIC CONSULTATION AND DISCLOSURE ............................................................................... 25

5.1 Consultation......................................................................................................................................... 25

6. GRIEVANCE REDRESS MECHANISM ................................................................................................. 27

6.1 General ...................................................................................................................................................... 27

6.2 Grievance Redress Committee .................................................................................................................. 27

6.3 Disclosure of the Grievance Process ........................................................................................................ 28

7. INSTITUTIONAL FRAMEWORK ........................................................................................................... 29

7.1 Institutional Arrangements ....................................................................................................................... 29

8. LARP BUDGET AND FINANCING ........................................................................................................ 30

8.1 Institutional Arrangement ......................................................................................................................... 30

8.2 Budget Description ................................................................................................................................... 30

9. IMPLEMENTATION SCHEDULE AND PREPARATORY ACTIONS ................................................. 31

9.1 LARP Implementation Schedule .............................................................................................................. 31

9.2 Preparatory Actions ............................................................................................................................ 33

10. MONITORING, EVALUATION and REPORTING ............................................................................... 34

10.1. Internal Monitoring ............................................................................................................................. 34

10.3 Reporting ............................................................................................................................................... 34

Men’s Public Consultation Meeting Agenda and Questionnaire .................................................................... 38

1.4 Minutes of the meeting-Chardara Canal Upstream, Middle stream, Men ............................................ 42

List of Tables:

Table 2.1: Summary of Impact under the Chardara ........................................................................................... 4

Table 2.2: Impact on Trees ........................................................................................................................... 4

Table 3.1: Age Distribution of APs in Ahs ....................................................................................................... 6

Table 3.2: Literacy Status of the Affected Persons .............................................................................................. 7

Table 3.3: Marital Status of the Aps .................................................................................................................... 7

Table 3.4: APs’ Family Structure ........................................................................................................................ 8

Page 4: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

Table 3.8: Income and Expenditure of Ahs ....................................................................................................... 10

Table 4.1: Entitlement Matrix .......................................................................................................................... 16

LIST OF ANNEXES:

ANNEX 1: PARTICIPANT LIST OF CONSULTAITON MEETING ............................................................. 39

ANNEX 2: ATTENDANCE LIST OF PUBLIC CONSULTAION MEETING, ............................................. 41

ANNEX 3: PHOTOGRAPHS OF PUBLIC CONSULTATION MEETINGS, ................................................. 43

ANNEX 4: PUBLIC INFORMATION BOOKLET........................................................................................... 44

ANNEX 5: LIST OF AHS WITH RESTTLEMENT IMPACT AND COMPENSATION .............................. 48

LIST OF FIGURE:

FIGURE 1:PROJECT LOCATION MAP ............................................................. Error! Bookmark not defined.

FIGURE 2:LARP IMPLEMENTAITON SCHEDULE ........................................ Error! Bookmark not defined.

Page 5: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

CURRENCY EQVELLENTS as of July 24, 2020

Currency Unit – AFN

AFN 1.00 -$ 0.01z

$1.00 - 77 AFN

ABBREVIATIONS

ADB : Asian Development Bank

AF : Affected Family

AFN : Afghan Currency

AH : Affected Household

AP : Affected Person

CSS : Census and Socioeconomic Survey

CAESU : Contract Administration and Engineering Support Unit

DMS : Detailed Measurement Survey

EA : Executing Agency

ESCS : Engineering and Supervision Consulting Services

ESSU : Environmental and Social Safeguard Unit

GoA : Government of Afghanistan

GRC : Grievance Redress Committee

GRM : Grievance Redress Mechanism

HH : Households

IA : Implementing Agency

IOL : Inventory of Losses

IA : Implementing Agency

IP : Indigenous People

LAR : Land Acquisition and Resettlement (impacts)

LARP : Land Acquisition and Resettlement Plan

LKIP : Lower Kokcha Irrigation Project

MAIL : Ministry of Agriculture, Irrigation and Livestock

MUDL : Ministry of Urban Development Land

MEW : Ministry of Energy and Water

MFF : Multi tranche Financing Facility

MOF : Ministry of Finance

NGO : Non-Government Organization

NOL : No Objection Letter

Page 6: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

PARBA : Panj-Amu River Basin Agency

PIO : Project Implementation Office

PMO : Project Management Office

PPR : Project Progress Report

ROW : Right of Way

RF : Resettlement Framework

SHC : Sharawan Canal

WRDIP : Water Resources Development Investment Program

Page 7: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

GLOSSARY

Affected Family: All members of a household residing under one roof and operating as a single economic unit;

who are adversely affected by the Project or any of its components. It may consist of a single nuclear

family or an extended family group.

Affected Person (AP): All the people (or household) affected by the Project through land acquisition,

relocation, or loss of income; and include any person, household [sometimes referred to as project

affected family (AF)], firms, or public or private institutions. APs, therefore, include (i) persons whose

agricultural land or other productive assets such as trees or crops are affected; (ii) persons whose

businesses are affected and who might experience loss of income due to the Project impact; (iii) persons

who lose work/employment as a result of Project impact; and (iv) people who lose access to community

resources/property as a result of the Project.

AFN: Local currency of Afghanistan, which is the Afghani.

Assistance: Support, rehabilitation and restoration measures extended in cash and/or kind over and above the

compensation for lost assets.

Census: The process of enumeration of the affected people and their assets.

Compensation: Payment in cash or kind for an asset to be acquired or affected by a project at replacement cost

at current market value.

Cut-off date: The date after which people will NOT be considered eligible for compensation, i.e. they are not

included in the list of APs as defined by the census. Normally, the cut-off-date is the date of the detailed

measurement survey.

Detailed measurement survey: The detailed inventory of losses that is completed after detailed design and

marking of project boundaries on the ground.

Entitlement: The range of measures comprising cash or kind compensation, relocation cost, income restoration

assistance, transfer assistance, income substitution, and relocation which are due to business restoration

which are due to APs, depending on the type and degree nature of their losses, to restore their social

and economic base.

External Experts: Experts not involved in day-to-day project implementation or supervision.

Inventory of Losses: The pre-appraisal inventory of assets as a preliminary record of affected or lost assets.

Jerib: Traditional unit of land measurement in Afghanistan. One Jerib is equal to 2000 square meter of land. 5

Jeribs make 1 hectare.

Non-titled: People who have no recognizable rights or claims to the land that they are occupying and includes

people using private or state land without permission, permit or grant i.e. those people without legal

title to land and/or structures occupied or used by them. ADB’s policy explicitly states that such people cannot be denied compensation.

Program: Water Resources Development Investment Program funded by ADB.

Rehabilitation: Compensatory measures provided under the Policy Framework on involuntary resettlement

other than payment of the replacement cost of acquired assets.

Page 8: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

Replacement Cost: Replacement cost means the amount needed to replace an asset and is the value determined

as compensation for:

I. Agricultural land at the pre-project or pre-displacement level, whichever is higher and is the market

value of land of equal productive potential or use located in the vicinity of the affected land, plus the

cost of preparing the land to levels similar to those of the affected land, plus the cost of any registration

and transfer taxes;

II. Land in urban areas: it is the pre-displacement market value of land of equal size and use, with similar

or improved public infrastructure facilities and services and located in the vicinity of the affected land,

plus the cost of any registration and transfer taxes;

III. Houses and other related structures based on current market prices of materials, transportation of

materials to construction site, cost of labor and contractor’s fee, and any cost of registration and transfer taxes. In determining replacement cost, depreciation of assets and value of salvaged building materials

are not taken into account and no deductions are made for the value of benefits to be derived from the

project;

IV. Crops, trees, and other perennials based on current market value; and

V. Other assets (i.e. income, cultural or aesthetic) based on replacement cost or cost of mitigating measures.

Resettlement: All the impacts associated with land acquisition including restriction of access to, or use of land,

acquisition of assets, or impacts on income generation as a result of land acquisition.

Shura: Local institution which represent the seniors of a rural community. They are mostly the decision makers

at village level. There are two types of Shura - NSP/MRRD established shuras and tribal shuras. NSP

shuras or CDCs are responsible mostly for developmental work while the tribal shuras are responsible

for conflict resolutions, jirgas etc. Currently both shuras function for both responsibilities and are

represented by the same group of people

vulnerable household: Anyone who might suffer disproportionately or face the risk of being marginalized from

the effects of resettlement and includes; (i) female-headed households with dependents; (ii) disabled

household heads; (iii) poor households (within the meaning given previously); (iv) landless or without

title to land; (v) elderly households with no means of support; (vi) households without security of tenure;

(vii) ethnic minorities; and (viii) marginal farmers (with landholdings of five Jeribs or less).

Severely Affected Households/persons: refers to affected households who will (i) lose 10% or more than

10% of their total productive land and/or assets, (ii) have to relocate; and/or (iii) lose 10% or more

than 10% of their total income sources due to the Project.

Page 9: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

EXECUTIVE SUMMARY

The proposed Panj-Amu Basin Project will increase agricultural productivity in the Panj-Amu River

Basin through improving access and use of water at farm, scheme and river levels. Project interventions

will be undertaken in approximately 21 irrigation schemes in the basin. In order to assess the viability

of the project, three representative schemes (sub-projects) were chosen from a list of candidate sub-

projects as being representative of the type of scheme that will be assisted in the project, and which will

be the first to be implemented. Selection of the representative sub-projects was also based on

government priority and ease of access from both a security and logistical point of view. Chardara canal

length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

also with 2-3 meter ROW in both side inKunduz Province (Panj Amu River basin) is one of these

representative sub-projects.

As part of the project interventions a number of structures will be built along the canal. Notably new

off-takes, cross regulators with a spill weir, protection wall, bridges, drop structures and canal lining is

part of this project.

All of these structures will be built along the public right of way (RoW) of the canal. There is no land

acquisition requirement and no physical displacement. The only impact constitutes the removal of 1,296

non-fruit trees on the RoW (2-3 meters1), of which only 346 are mature, 774 midel age and 176 sapling

which are located in both side of canal and used by 17 household that will be removed.

Since there is no severely affected persons by the project, it is categorized as B for involuntary

resettlement. No indigenous people have been identified in the project area and therefore it is category

C for IP.The concept of a public RoW is fairly new in Afghanistan but traditionally farmers whose land

is adjacent to such RoW use such land. As the RoW is government land, they are not owners of the

trees per se, but traditional users. Their livelihoods do not depend on these trees, which are not grown

commercially and are simply ancillary. They sometimes use the trees for fuelwood. Willow trees were

used in the past for construction materials but this is no longer the case. The households’ economic dependence on these trees is less than 1% of their income, as obtained through the stakeholder

consultations.

For compensation, ADB’s replacement cost principle have been followed and the trees have been valued

based on the market value of their dry wood volume. The budget for this LARP covers the compensation

for the removal of trees. It is set at US$ 19,727.11. The LARP budget will be met from the ADB-EU

grant funding.

The amount for compensation for tree removal has been included in the BOQ for the construction

contractor who will be tasked with paying this compensation before commencement of civil works and

acceptance of LARP implementation compliance report by ADB. During public consultations

stakeholders include River Basin Agency, District governor, WUAs and CDC recommended that no

compensation is made, since trees are on RoW and compensation may encourage false claims in the

future. It was recommended that compensation is instead made for building or enhancing community

assets. The project recommends that this could be used for construction of additional domestic or

livestock access points, which are already a task of the contractor.

If all APs and the mirabs do not agree, then compensation payment will be made directly to the APs.

This will be made to their bank accounts if they have one. If they do not then as this is a one-off payment

1 To be clear the project is rehabilitation of existing structures, and the structures are located in the existing alignment of canal which is 12-18 meters, also with 2-3 meter ROW in both side. There won’t be any changes in the location and size of structures.

Page 10: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

they will not be asked to set-up a bank account for this purpose, so payment will be made as a cash

payment to the AP in the presence of the WUAs head, CDC representativesm, supervision consultant

and PIU representative. A payment slip confirming receipt of payment will be signed by the AP and

some one as a witness.

Consultations and the grievance redress mechanism will continue throughout the project cycle. The

LARP implementation will be reported to ADB semi-annually.

Page 11: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

1. Introduction

1.1 BACKGROUND

1. The Panj-Amu River Basin Project Sector Project (PARB), Afghanistan Project will support improved water allocation and availability, enhanced on-farm water management, and protection of watersheds in the Panj-Amu River basin, through construction of water conveyance and irrigation infrastructure at 21 priority subprojects (construction costs approximately $50 million); the establishment, strengthening, and support of subproject water user associations (WUAs) and irrigator associations (IAs); training on on-farm water management and improved agronomic techniques; implementation of watershed management plans at sites adjacent to the priority subprojects; and improved basin water resources planning and management.

2. Since 2004, the European Union (EU) has supported the Government of the Islamic Republic of Afghanistan (GoIRA) in its reconstruction efforts by funding integrated water management programmes in the Panj Amu River basin. The Qulbars-Shorab subprojects continues this EU support in partnership with ADB as co-financier and administrator. This approach aims to improve Government’s ownership of fund management and conform to EU policy in Afghanistan of moving funding on-budget or into co-financing arrangements, and to increase sustainability.

3. The importance of the PARB Project is in its impact on the well-being of rural communities in the basin, and in its support for Afghanistan’s sector investment plan, the $1.1 billion National Water and Natural Resources Development Program.

Brief Description of Location, Nature and Size of the Project

4. Chardara irrigation scheme is located around 28 km from Kunduz center. The GPS of the intake is N

36.492372 E 68.880859. The length of the main canal is 61 km with 2-3 meter RoW. To be clear the

project is rehabilitation of existing structures, and the structures are located in the existing alignment of

canal which is 12-18 meters, also with 2-3 meter ROW in both side. There won’t be any changes in the location and size of structures. It is located in Omerkhil Village of Ali Abad district of Kunduz province.

The command area is located on left bank of Kunduz River. It has a command area of around 15,904

ha. The canal is the traditional one has been running more than 100 years.

5. The original age of the Chardara irrigation scheme is unknown but according to local people the canal

is about 100 years old. After taking water from the Kunduz River the canal is aligned in the south

direction passing through the villages and along the Kunduz river. The headwork is constructed by the

KRBP it includes automatic escape structure and weir structure to divert the water into the river during

flood season. The main canal intake has 10 gates in Chardara Headwork ( Intake has 10 nos. of gate

with size of 1.5m (w), 1.2m (h), the canal is unlined and irregular.

Page 12: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

1.2 CONSTRAINT

1. This should however be mentioned that there were severe restrictions due to the

security situation, preventing some of the fieldworks to be carried out as intended. The

obvious constraint to carrying out all the pursuits had been the threat of insurgency in many parts of the

project area. Field visit by the international consultants could be very poorly possible due to increasingly

dangerous condition. Nevertheless, the national consultants attempted to carry out the relevant tasks to

the best of their ability.

1.3 OBJECTIVES OF THE LARP

2. This draft LARP defines the practical procedures by which the Implementing Agency

addressed the resettlement impacts under the Project, in line with the applicable

policy and legal framework of the Government, and ensuring that the principles of the ADB’s safeguard

requirements on involuntary resettlement under the Safeguard Policy Statement are complied with. The

primary objectives of the LARP are to:

• Identify the project impact on the community in terms of loss of assets, and impact on livelihood and

income;

• Outline measures to mitigate the adverse impact;

• Provide an estimate for budgetary allocation for compensation of loss of assets and resettlement

benefits; and

• Provide procedure for internal monitoring of resettlement implementation.

1.2 LARP-related Conditionality

3. Initiation of project implementation works will be contingent on the compliance to the

following conditions:

4. Acceptance of this LARP by ADB.

5. Disclosure of this LARP to the public, ADB and government websites.

6. Implementation of the LARP, i.e., delivery of compensation to the AHs, if applicable.

7. Submission of LARP implementation compliance report for ADB review, acceptance and disclosure.

Page 13: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

8. No-Objection Certificate (NOC) issued by ADB for commencement of civil works up on acceptance of

LARP implementation compliance report.

Page 14: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

2. SCOPE OF LAND ACQUISITION AND RESETTLEMENT

2.1 Scope and Rationale for Resettlement

9. Chardara canal improvement works have been planned to be carried out

within the available land owned by the government along the existing canal alignments which are 12-

18 meters with 2-3 meter ROW in both sides. However, in the course of censuse and socio-economic

CSS survey, it was found that the people residing adjacent to the canal alignments are using this canal

RoW land over the years and benefiting from the land by planting and growing of trees in common, but

some used for boundary walls and dwelling houses. Based on ROW regulation, the canal ROW are

based on the discharge of the canal, acoording to regulation this canal with discharge of about 30 cubic

meter per second have 10-12 meter ROW in both side. And currently there is only 2-3 meter exist and

rest are used by farmers.

2.2 Census Survey

10. As mentioned earlier, implementation of the Chardara will have unavoidable impact of loss of non-land

assets such as trees. To ascertain the magnitude of the impacts, census combined with socioeconomic

survey was carried out intermittently on June 2020 to make an inventory of losses (IOL), and to develop

a baseline of socioeconomic status of the households likely to suffer from project intervention.

2.3 TYPES AND SUMMARY OF IMPACT

11. Rehabilitation and upgrading of the canals and its structures will have major impact on trees which

grown in the ROW of canal. The land is government land but currently it is used by farmesrs adjacent

to the canal.

Table 2.1: Summary of Impact under the Chardara

Type of Impact Magnitude of Impact

Affected Households and Persons

Total Number of Affected Households 17 Households

Total Number of Affected Persons (APs) 205 Persons

Total Affected Male APs 105 Persons

Total Affected Female APs 100 Persons

Affected Assets 0

Total Number of Affected Trees (Grown on Govt. Land) 1,296 Numbers

12. A total of 17 households will be affected due to implementation of the Project as already mentioned.

The foregoing summary table shows that a numbers of APs are identified in the affected households

(AHs), estimated at about 205 people. 1,296 different types of non-fruit trees will have to be removed

and compensated based on market value.

2.4 Impact Assessment

2.4.1 Affected Households and Population

13. As already mentioned, a total of 17 households and 205 APs will be partially affected due to the project

implementation, out of that 105 male and 100 females. However, the effects on the AHs will be small

since there will be no household to lose any part of its land-holding. Also, project implementation will

not cause any major impact involving demolishing of any house or physical displacement of any

households from their existing dwellings.

2.4.2 Impact on Land

Page 15: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

14. The structures will be built in the existing ROW (2-3meter) of canal, and there is no need for land

acquisition privately owned land due to the project. To be clear the project is rehabilitation of existing

structures, and the structures are located in the existing alignment of canal which is 12-18 meters, also

with 2-3 meter ROW in both side. There won’t be any changes in the location and size of structures.

2.4.3 Impact on Trees

15. A total of 1,296 trees will be affected, of which 346 are mature trees, 774 are medium size or pole and

176 are small size trees. Point to be noted that, most of the trees are non fruit trees except some mublery

and Russian olive which are generally used as public in the canal ROW.

Table 2.2: Impact on Trees

S. N Province District Canal

Name Types of Tree Tree Category

Kunduz Ali Abad

Char

Dara

Canal

Local

Name Scientific Name Sip Pole Tree

1 Chinar Platanus 41 254 99

2 Bid Willow 52 153 49

3 Sinjad Russian Olive 30 68 38

4 Tot Mulbery 37 109 10

5 Safidar Populus alba 16 190 150

Sub-Total 176 774 346

Grand Total 1,296

2.4.4 Impact on Income and livelihood

16. Although the affected households use the government owned land for various purposes along the canals,

these lands are not being used for agricultural purposes. Therefore, there is no impact on crops. The

trees planted on the land are not fruit or productive trees. These are used as firewood and for household

consumption, the loss of which is very insignificant in comparison with the total income of the

households. The structures affected are used for residential purpose, not for any commercial activity.

Total impact of the project is less than 10% for all the affected households.

2.4.5 Impact on Vulnerable and Severely Affected Households

17. The impact assessment has taken care whether the Chardara irrigation scheme will have any impact on

vulnerable population, defined in Glossary list, i.e. whether any household below poverty line or

women-headed household or any households who are mentally or physically challenged. During the

socioeconomic survey, it was found that the per capita income per day of the 8 APs are under the poverty

line. Also, all AHs are headed by male household heads. Besides, there are no households whose

agricultural land or income will be severely affected, impacting more than 10% of any AP’s agricultural land holding, also The project is rehabilitation of existing structures and there is no any new

project to affect the vulnerable household, the only impact is due to removal of a number of

trees in the canal ROW, there is no impact on lan and structures (houses or business income)..

2.4.6 Indigenous Population

18. Afghanistan is composed of a multi-ethnic and multi-lingual society. The ethnic composition of the

country comprises the groups of Poshtun, Tajik, Hazara, Uzbek, Aimak, Turkmen, Baloch, Pashai,

Nuristani, Gujjar, Arab, Brahui, Pamiri and some others. These communities are at par with the

mainstream and do not fall under the definition of ADB’s indigenous people (IP) groups. Similar is the case with all APs in the project areas who are collectively residing in the region for hundred years and

considered to be mainstream Afghan residents, and do not fall under the IP definition. All the surveyed

APs were found to be followers of Islam.

Page 16: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

2.4.7 Gender Impact

32. Attempt was made during the course of census survey to assess the gender impacts of the Project.

Discussions were undertaken with the community people to look into the current status and needs of

the women in the project area and the potential impact of the Project on them. The assessment has not

brought forth any adverse impacts of the Project on women in particular.

Page 17: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

3. SOCIOECONOMIC PROFILE OF THE AFFECTED PERSONS

3.1 SOCIO-ECONOMIC SURVEY

3.1.1 Methodology

33. A socio-economic survey was conducted during the same time of carrying out the census survey, using

a Semi-structured questionnaire. Due to security reason, it was planned to conduct this socioeconomic

survey at one time combined into a single initiative together with the census survey, not making a

separate round of field trips.

34. Discussions were held mainly with the household heads, but there was presence of the other male

members of the households in common. Mention should be made that during the course of conducting

the survey in the project area discussion could take place only with the heads of the households. Due to

the cultural restrictions, the women members of the households could not be interviewed at all.

Participation of women was fully absent due to strict controls on their movement outside the house in

these remote areas. Hence, the respondents of the survey were only male APs. However, efforts were

made to the extent possible to collect information about the female members in the households during

the course of interviewing the male respondents.

3.2 Demographic Characteristics of the Ahs

3.2.1 GENDER SEGREGATION

35. There are in total 205 APs or an average of 13.2 persons per household. Among the total APs,

105(51%) are male and 100 (49%) are female, with no significant difference in the sex ratio.

3.2.2 Age of APs

36. Table 3.1 shows the age of affected peoples. Majority of APs in the AHs are within the age group of 18

to 50 years - about 36% APs in age of 18 to 50 years. A very minimum APs were found to be above 70

years of age. No female headed household ould be found among the AHs.

able 3.1: Age Distribution of APs in AHs

Age Range

Kunduz Province

No. of Aps in Chardara District

% of Aps in Chardara District

Less than 5 years 39

19

5 to 17 years 72 35

18 to 50 years 73 36

51 to 70 years 16 8

More than70 years 5 2

al 205 100

3.2.3 Education

37. Table 3.2 show the education level of affected people. Majority of the APs were found to be Middle

School – 42 %. Around 17% of APs were graduated from university and 40% of the Aps were illiterate.

able 3.2: Literacy Status of the Affected Persons

Education Level Kunduz Province

Page 18: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

No. of Aps in Chardara District % of Aps in Chardara District

Higher than Graduate 2 1.0

Graduate 35 17.1

Middle School 87 42.4

Illiterate 40 19.5

Below School going Age 41

20.0

Total 205 100.0

3.2.4 Marital Status

38. Greater part of the AP population was found unmarried - 61%, married number of APs was also found

relatively high - 36%. And there is 3% widow in the project area.

able 3.3: Marital Status of the APs

Marital Status

Kunduz Province

No. of Aps in Chardara District

% of Aps in Chardara District

single 125 61

Married 73 36

Widow 7 3

Total APs of Marriage Age 205 100

3.2.5 Religion

39. All the affected households are mainstream Muslim families and all the APs are followers of Islam

religion

3.3 Household Characteristics

3.3.1 Family Structure

40. Majority of the household are living in extended families as 71 % of the families are living in the

extended family. The maximum numbers of family members were found as high as 20. And 29% or 5

families are living in the nuclear family. All the affected household heads are male and Majority of the

household heads are illiterate due to the war period.

able 3.4: APs’ Family Structure

Province District Family Type

Nuclear Extended

Page 19: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

No of AHs % of AHs No of AHs % of AHs

Takhar Khwaja Ghar 5 29 12 71

Total 5 29 12 71

Maximum Number of People in Affected Households 20

Minimum Number of People in Affected Households 7

Average Number of People in Affected Households 13.2

3.3.4 Occupation of the AHs

41. Agriculture is the major economic activitiy in the project area and providing about 93 % of all

employment for their income earning. Traditionally, men are involved in bulk of the income earning

activities. Especially, in almost all cases of agricultural activities men are involved. However,

significant women involvement was visible in livestock rearing. It has been understood that women in

most cases are involved in cattle feeding and watering. Livestock is another significant income earning

source for the households. Some of the APs in the AHs were found to be engaged in more than one

profession.

able 3.7: Occupation of AHs

Source of Income

No of AHs % of AHs Total AHs in the Category

Agriculture 14 93 14

Trade and Service 1

7 1

Non-farm labour 2

1 2

Livestock 0 0 0

3.3.5 Income and Expenditure

42. Average income of the households was found to be around AFN 32,013 per month. People spend

relatively higher amount on food items, monthly average AFN 14,711 , followed by AFN 6,087 on

non food items. As it has been mentioned earlier that the average family size for the AHs is 11.2, which

means, per person per day income in the affected area is around AFN 80.84 , which is equivalent to

USD 1.04. Based on ALCS 2016-17, in 2007-08, the national average threshold for the cost of covering

basic needs – the poverty line – was AFN 1,261 per person per month. This threshold, consistently

defined and valued at 2016-17 survey prices, increases to AFN 2,064 per person per month. Hence, the

affected people are living above the poverty line of Afghanistan.

Table 3.8: Income and Expenditure of AHs

Income Status of the AHs

Monthly Household Average Income(AFN) 32,013

Yearly Household Average Income(AFN) 384,160

Expenditure Status of the Surveyed AHs

Monthly Expenditure for food (AFN) 14,711

Monthly Expenditure for non-food items (AFN) 6,087

Average Monthly Total Expenditure (AFN) 20,797

Yearly Total Expenditure 249,568

Page 20: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

4. LEGAL AND POLICY FRAMEWORK AND ENTITLEMENTS

4.1 Policy and Legal Framework for Land Acquisition and Resettlement

43. The policy framework for the Project is based on Afghanistan Land Acquisition law, the ADB policy

on Involuntary Resettlement as embedded in the Safeguards Policy Statement (2009) and the

Operations Manuals F1 (2010), and the Land Management Law and the Land Acquisition Law of

Afghanistan. Where differences exist between local law and ADB practices, the resettlement policy will

be resolved in favour of the latter.

4.2 Land Acquisition and Resettlement Legislation in Afghanistan

44. The new Constitution of Afghanistan was ratified in early 2004. It has 3 articles that

closely relate to compensation and resettlement. There are 2 Laws and 1 regulation which are used in

Afghanistan which are relevant to Land Acquisition and Resettlement. They are the “Law on Land

Management” (LML) , “Land Acquisition Law” (LAL) and Regulation on Linear Proejcts Land

Acquisition Process.

4.3 Relevant Provisions from the Law on Land Management in Afghanistan

50. A comprehensive land policy was approved in 2017 by the President and Gazetted

on 15 April 2017. This “Law on Managing Land Affairs” (no. 1254) (LML) is aimed at:

• Management of land affairs in Afghanistan.

• Resolve the problem issue caused by the implementation of varying policy related to land management.

• Refund of all land which are distributed without any permission by law and Sharia.

• Establishment and facilitating legal access to government land for agriculture, Business, public services,

industrial activities and acquiring the national and international investment.

45. Furthermore, this Law aims also to proved standard system for land titling, land segregation and

registration; prevent illegal land acquisition and distribution; provide the people with access to land;

and provide conditions for appropriation of lands. The LML provides that:

46. Management of land ownership and related land management affairs and implementation of this law is

under the responsibility of Ministry of Urbana Development and Land MUDL (Article 4).

47. Ownership is verified by providing the legal and valuable documents (article 9), including power of

attorney, Decision of court, Tax paper, legal documents, deed, traditional deed and property dealer

document

48. Public project can be implemented in the public land by approval of the government.

49. Technical implementation and administration of land management affairs shall be

conducted under the Ministry of Urbana Development and Land MUDL and Ministry of Agriculture,

Irrigation and Livestock, Head of NWARA, Ministry of finance ,Department of geodesy and

Cartography and other related agencies have responsibilities for the implementation of this article

(Article 39).

50. If the land clearance is conducted for the implementation of government project, the right of owner who

are not present will be saved and when they claim and bring the required document, their right will be

given (article # 44).

4.4 Relevant Provisions from the Law on Land Acquisition in Afghanistan

51. For the purpose of public interest like the establishment/construction of public infrastructure and

facilitation for acquisition of land with cultural or scientific values, land of higher agricultural

productivity, large gardens, LAL provides that:

• The acquisition of a plot or a portion of plot, for public interest is decided by the Cabinet and will be

compensated at fair value based on the current market rates (section 2).

• The acquisition of a plot or part of it should not prevent the owner from using the rest of the property

or hamper its use. If this difficulty arises, the whole property will be acquired (section 4).

Page 21: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

• The right of the owner or land user will be terminated 3 months prior to start of civil works on the

project and after the proper reimbursement to the owner or person using the land has been made. The

termination of the right of the landlord or the person using the land would not affect their rights on

collecting their last harvest from the land, except when there is emergency evacuation (section 6).

• In case of land acquisition, the following factors shall be considered for compensation: value of land;

value of houses, buildings and the land; values of trees, orchards and other assets on land (section 8).

• The value of land depends on the category and its geographic location (section 11).

• A person whose residential land is subject to acquisition will receive a new plot of land of the same

value. He has the option to get residential land or a house on government property in exchange, under

proper procedures (section 13).

• It can be arranged with the owner if he wishes to exchange his property subject to acquisition with

government land. The difference on the values of land will be calculated (section 15).

• The values of orchards, vines and trees on land under acquisition shall be determined by the competent

officials of the municipality (section 16).

4.5 ADB’s Involuntary Resettlement Policy

52. The ADB Policy on Involuntary Resettlement is based on the following principles:

• Involuntary resettlement is to be avoided or at least minimized;

• Compensation must ensure the maintenance or improvement of the APs’ pre project living standards;

• APs should be fully informed and consulted on compensation options;

• APs’ socio-cultural institutions should be supported/used as much as possible;

• Compensation will be carried out with equal consideration of women and men;

• Lack of formal legal land title should not be a hindrance to assistance/rehabilitation;

• Particular attention should be paid to households headed by women and vulnerable groups, such as indigenous people and ethnic minorities, and appropriate assistance should be provided to help them improve their status;

• Land acquisition and resettlement should be conceived and executed as a part of the Project, and the full costs of compensation should be included in project costs;

• Compensation/rehabilitation assistance will be paid prior to ground levelling and demolition, and in any case, before an impact occurs.

The policy comprises three important elements:

I. Compensation to replace lost assets, livelihood, and income;

II. Assistance for relocation, including provision of relocation sites with appropriate facilities and services;

and

III. Assistance for rehabilitation to improve or achieve at least the same level of wellbeing with the project

as without it.

53. A project’s involuntary resettlement category is determined by the category of its most sensitive component in terms of involuntary resettlement impacts. The involuntary resettlement impacts of an

ADB-supported project are considered significant if 200 or more persons will experience major impacts,

which are defined as (i) being physically displaced from housing, or (ii) losing 10% or more of their

productive assets (income generating). The level of detail and comprehensiveness of the resettlement

plan are commensurate with the significance of the potential impacts and risks.

4.7 Principles and Policies for the Project

54. Given the assessment, some provisions in the Law on Land Acquisition have been waived to make it

consistent with the principles of ADB’s Policy on Involuntary Resettlement as embedded in the

Page 22: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

Safeguards Policy Statement (2009) and OM Section F1 (2010). Based on the above, the following

principles will be adopted for this LARP:

I. AP/AH impacts must be avoided or minimized as much as possible.

II. If impacts are unavoidable, the APs/AHs losing assets, livelihood or other resources will be fully

compensated and/or assisted so that they improve or at least restore their former economic and social

conditions.

III. Compensation will be provided at full replacement cost, free of depreciation, transfer costs or eventual

salvaged materials.

IV. Provincial Land Settlement Commission will facilitate changing of land use certifications of AF’s without fee charges.

V. Information on the preparation/implementation of a LARP will be disclosed to all APs and people’s participation will be ensured in LARP planning and implementation stages.

VI. Before taking possession of the acquired lands and commencing construction, compensation will be

paid in accordance with the provision described in this updated LARP. No land will be taken until the

legitimate user is compensated or rehabilitated as provided in this LARP.

VII. Lack of formal legal land title is not a bar to compensation or rehabilitation. A Grievance committee

including representatives of the APs will be established to resolve any conflicts which may arise during

the compensation process. Compensation measures will equally apply across gender lines and

vulnerable groups if any identified.

VIII. AP consultation will continue during the implementation of LARP.

IX. The full compensation of affected assets and the preparation of a compliance report by the Independent

Monitoring Agency will be a condition for initiating civil works.

4.8 Eligibility and Entitlements

55. The following categories of affected persons will be entitled to compensation and/or rehabilitation

benefits under the Project:

56. All owners of buildings,boundary walls, trees or other properties standing on the affected land.

4.9 Entitlement Matrix

72. The affected households are entitled for compensation of trees according the

Entitlement Matrix in the LARP. The compensation and rehabilitation entitlements for each affected

item established for the Project is detailed below in Table 4.1

Table 4.1: Entitlement Matrix

Loss Type Entitled Person Entitlements Responsibility

Agricultural/residential/ Commercial land loss

AP with title, formal/customary deed, or traditional land right as vouched by local Jirga, elders or Community Development Council

Cash compensation at replacement

cost either through replacement

plots or in cash based on full

replacement cost to be approved

by the council of ministers. All fees,

taxes, or other

charges, as applicable under

relevant laws are borne by the

project

CPMO

Buildings, Boundary

Walls/non-residential

Owners (with/without building/structure registration)

Cash compensation at negotiated

and according to replacement

CPMO

Page 23: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

structures (cattle shelters).

2cost, rates determined during the

census and impact assessment

surveys for affected

building/structures.

The right to salvage materials free

of cost.

Crop losses Owners of crops/Sharecroppers

Cash compensation equal to replacement cost of crop lost plus cost of replacement seeds for the next season.

CPMO

Trees

Owners of Trees

Compensation for trees at negotiated and according to

replacement cost, the value

determined during census and impact assessment surveys. The right to salvage materials free of cost.

CPMO

Business losses by shop owners and employees

Business / shop owners (including informal settlers), employees

Cash compensation for net income loss for the duration of business stoppage (maximum up to 3 months for temporary loss and an equivalent of 6 months income for permanent loss). The compensation for business loss will be calculated based on tax receipts or when these are not available based on fixed rates (Fixed rates will be determined on the basis of prevailing wage rate of Afghanistan) Employees: indemnity for lost wages equivalent to three months income

CPMO

Transitional Livelihood allowance

All affected households loosing Residential /Commercial Structures

Relocated owners/renters will

receive a transitional allowance for

3 months in case of livelihood

Transitional livelihood allowance

will be computed on the basis of

prevailing wage rate of Afghanistan

CPMO

Relocation allowance

All affected households loosing Residential /Commercial Structures

Relocated owners/renters

(including informal settlers) will

receive a relocation allowance for

3 months. Relocation cost will be

calculated on the basis of

prevailing market rate.

CPMO

.

Page 24: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

Loss of community, cultural, religious, or government sites

Community/ Affected Households in case of Temporary or permanent loss due to the Project activities

Conservation, protection and cash

compensation for replacement

(Schools, communal centers,

markets, health centers, shrines,

other religious or worship sites,

tombs). Cash compensation for

affected structures based on the

above structures entitlements

CPMO

Unanticipated

Impact.

Concerned

impacts.

10% provisions for unforeseen impacts have been made in the project Unanticipated impacts will be

documented and mitigated

based on the ADB Safeguard Policy Statement (SPS 2009)

CPMO

identifies and

mitigates

impacts as

required

Project related employment

Affected Persons(for Unskilled, Semi- skilled and Skilled)

Contractors should give priority to affected persons in project-related employment opportunities as drivers, carpenters, masons, clearing and digging work, and if possible as clerks or basic administration support staff.

CPMO

4.10 Assessment of Compensation

73. All the APs are entitled for compensation of trees as there is no any types of impacts except tree

removal in the ROW of canal.

74. Based on the community peoples’ agreement, it is considered that the whole area of affected lands is

owned by the Government. Compensation for the affected land therefore will not be applicable in this

case of obtaining the required land for physical implementation of Chardar irrigation scheme

improvement works. However, particular attention should be paid to the effective supervision of the

implementation activities in order to ensure that the improvement works are confined within the

construction limit.

75. Compensation provisions for APs suffering different types of losses are detailed below:

(i) Compensation for Trees: Affected trees will be compensated at the negotiated and replacement cost

value determined and recorded during CSS.

(ii) Compensation for Unforeseen Impacts:Unforeseen impacts will be documented and mitigated based

on the principles agreed in this LARP.

Page 25: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

5. PUBLIC CONSULTATION AND DISCLOSURE

5.1 Consultation

76. Public consultation meeting conducted in all 3 villages under the project by participation of affected

peoples, community development councils (CDCs), village head, water user, Water used association

and other stakeholders. All stakeholders were free to speak in such meetings, which is evidenced by the

in-depth information provided. A total of 4 consultation meetings (three with men and one with women)

were organized and atotal of 54 people participated in the meetings.

Table 5.1: List of public consultation meetings for Chardara canal

Dates Location of Meeting No. Participants and Origin Gender

15 June 2020 Chardara village (13) Head canal area Men

18 June 2020 Yar Baqal (10) Mid canal area Men

25 June 2020 Pul Kamar (14) Tail canal area Men

25 June 2020 Chardara (17) Tail canal area Women

1. Details of consultation meetings and results are included in Appendix 3.

2. As well as to extract information on the socio-economic situation in the sub-project area, the meetings

provided an opportunity for stakeholders to consider options and state their opinions. Concerns and

requests raised by stakeholders are included below.

• Don’t change canal alignment; • Provide a solution to offtake problems;

• Provide a solution to canal erosion;

• Provide a solution to intake/headworks problems;

• Provide a solution to land slides into the canal;

• Provide a solution to wash problems;

• Improve canal lining to reduce water losses;

• Provide a solution to the misalignment of land & water levels in some places;

• Don’t interrupt irrigation water supply during construction;

• Compensate farmers for any crop damage due to temporary construction roads;

• Hire unskilled laborers locally;

• Contractor should work according to design;

• Compensate for tree removal at construction sites;

• Construct foot/vehicle bridges;

• Women stated that canal water is an important domestic water source, and requested water access points

are constructed for domestic water collection, laundry, and livestock watering.

• Stakeholders added that, during the implementation of the project temporary canals will be required for

diverting the water from the structure site as well as to provide irrigation water for water users.

Therefore, they all agreed to give the land if needed for the temporary canal, but that after completion

of the work the land which is used for the temporary canal should be brought back to its original shape.

Page 26: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

• Stakeholders recommended that no compensation is made direct to APs for removal of trees, since trees

are on RoW and compensation may encourage false claims in the future. It was recommended that

compensation is instead made as a community contribution for building or enhancing community assets.

This could be used for construction of additional domestic or livestock access points, which are already

a task of the civil works contractor.

3. Details on the project, the impacts, entitlements and eligibility, and details of the GRM will be disclosed

to stakeholders via a short booklet local language.

4. Information on the project will continue to be disclosed to the public throughout the project duration,

e.g., via the ADB website, and via discussions between PIO staff and stakeholders.

5. The lead farmers, village leaders, mirabs and CDC chairmen agreed on the removal of those trees which

are planted in the RoW of the canal. They also agreed to assist in project implementation.

Page 27: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

6. GRIEVANCE REDRESS MECHANISM - GRM

6.1 GENERAL

77. Efforts will always be in place to prevent grievances through ensuring consultation, communication and

coordination with the affected families (AFs), the community and local level authorities in general.

Notwithstanding, complaints are sometimes unavoidable and a grievance mechanism needs to be in

place to allow the APs to append complaints to Grievance Redress Committee (GRC). GRCs will work

for any grievances involving resettlement benefits and issues, including ensuring proper presentation of

grievances, and impartial hearings and transparent decisions.

78. During the consultation meetings APs were informed of their rights to voice and resolve concerns. Also

After the Approval of this LARP again through public consultations and distribution of the public

information booklet, APs will be informed that they have a right to file complaints to GRC on any

aspects of resettlement, or on another related grievance

79. It should be pointed out that a GRC does not possess any legal mandate or authority to resolve LAR

issues, rather acts as an advisory body or facilitator to try to resolve issues relating to resettlement

benefits including value of compensation for affected properties. Any complaints of ownership or other

suits, to be resolved by the country’s judiciary system, will not be resolved in GRCs. Should the APs

want to pursue legal recourse, SST/CPMO will ensure that support to prepare a case, assisted by the

supervision consultants. However, every effort should be exerted to avoid this alternative because it would entail loss of time and expenses on the part of the APs.

6.2 GRIEVANCE REDRESS COMMITTEE

80. A Grievance Redress Committee (GRC) has been formed in order to receive and facilitate the resolution

of affected peoples’ concerns, complaints, and grievances about the project’s LAR performance. As

already mentioned GRC does not possess any legal mandate or authority to resolve LAR issues, rather

acts as an advisory body or facilitate to try to resolve issues, for example, relating to value of

compensation for affected properties.

81. GRC is established at the project area. During LARP implementation and project implementation in

case of the absence of any of the members during the decision-making process, an appropriate candidate

will be nominated by the original representative. However, at least five members should execute a

session for grievance resolution. GRC is composed of the following members:

Proposed Measures to Address Grievance

82. Grievances will be addressed through the following steps:

• Grievance registration: Any aggrieved AP will first produce his/her complain/grievance in writing to

the Convener of the GRC. If the Aps are illiterate, they can explain their complain orally or can write it

by another person maybe CDCs head. In the same time, contact details have been provided during the

consultation sessions. Upon receipt of complaint(s), the Convener will organize a GRC hearing session

in his/her office within 15 days for resolution of the grievance(s), and preserve all related records,

proceedings, decision and recommendations. The verdicts will be conveyed to the concerned AP

through the respective PIO office in the province.

• Grievance processing: Queries and complaints that are clarified and resolved at the intake point are

closed immediately. If grievances are not resolved at the local level GRC, then complaints can be lodged

at the District Committee at the district level. The District Committee under chairmanship of the

respective District Governor will resolve the case within 15 days and inform the APs.

Page 28: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

• Feedback provision: Receipt of grievances lodged in person or via phone will be acknowledged

immediately. Receipt of grievances received through a letter or e-mail or acknowledged through a letter

/ e-mail within 3 working days upon receipt by GRC coordinator at local level. In case the grievance is

not related to project activities or impacts generated due to the project implementation and cannot be

considered, the feedback will be provided to the complaining party specifying to which entity

(community or department as relevant) it has been forwarded.

• If the District Committee decision is unacceptable to the APs, they can register the complaint directly

to the PMO at Kabul within 1 month of receiving the response from the District Committee with

documents supporting their claim.

GRM: Central Level

• Following unsuccessful consideration of grievance by GRC at the district level complaint resolution

will be attempted at a central level through following steps.

• Grievance processing: If the District Committee decision is unacceptable to the APs, they can register

the complaint directly to the CPMO at Kabul within 1 month of receiving the response from the District

Committee with documents supporting their claim. The CPMO will then attempt to resolve the

grievance within 15 days and inform the APs.

• Feedback provision: If the grievance was resolved, the complaining party will be informed on the

outcome of grievance resolution. If grievance was not resolved by the GRC at central level, appropriate

information will be provided to the complaining party, including details why the case was not resolved.

• Should all the above three levels of grievance redress system fail to satisfy the AP, he/she may approach

the appropriate court of law for its resolution. The AP will be facilitated in this process by the SST.

Grievance Focal Points

Central Program Management Office (CPMO):

Mujeebullah Ahmadzai

Sr. Safeguard Manager

National Water Affair Regulation Authority (NWARA)

Mobile :( +93)766-388-242

Email: [email protected]

6.3 DISCLOSURE OF THE GRIEVANCE PROCESS

83. Grievance redress mechanism will continue to be disclosed to the public throughout the project

duration, e.g., via the ADB website, and via discussions between PIO staff and stakeholders except

details of individual grievances that will be protected confidentiality.

Page 29: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

7. INSTITUTIONAL FRAMEWORK

7.1 INSTITUTIONAL ARRANGEMENTS

84. The existing CPMO within the NWARA, headed by a Program Director (PD), will have overall

responsibility for implementation of the LARP. Social Safeguards Team (SST) within the CPMO,

staffed by a National Social Safeguards Manager (NSSM), Social safeguard officer at the headquarter

who is assisted at the field level by the social safeguards specialist in the Project Implementation Offices

(PIO) and contractor social safeguard officer. The CPMO SST will be directly responsible for

implementation of the LARP by contractor, including public consultation and information disclosures,

monitoring, reporting and documentation of the process, in coordination with local communities and

shura institutions.

85. The national and international Social Safeguards Specialists under the implementaiotn supervision

consultant (ISC) will provide support to CPMO .

Page 30: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

8. LARP BUDGET AND FINANCING

8.1 INSTITUTIONAL ARRANGEMENT

86. All funds required for compensating the affected HHs for loss of their properties or non-land asset including providing grants and allowances, will be allocated by the ADB.

8.2 BUDGET DESCRIPTION

87. Resettlement impact mitigation program under implementation of the Chardara will require a total

estimated amount of USD 19,727.37, out of which USD 17,933.37 is the direct compensation cost. USD

1,793.37 is kept as 10% contingency on the total direct cost to meet the cost of internal monitoring,

consultation and disclosure, administrative and other expenses.

88. Table 8.1 summarizes the estimated cost of LARP implementation for the Chardara. It should be

emphasized that this direct compensation cost estimate is derived from the inventory of survey.

89. The amount for compensation for tree removal will be included in the BOQ for the construction

contractor who will be tasked with paying this compensation before civil works can begin, fund for

compensation approved by ADB, annex 5.

Table 8.1: Summary of Cost Estimate and Budget

Compensation for Affected Assets & Compensation Number

of Trees

Unit Average

Rate (AFN)

Amount

AFN In USD

Compensation for Affected Assets

Compensation for Affected Sapling 176

(Number combined)

50 8,800 114.29

Compensation for Affected Medium trees 774

300 232,200 3,015.58

Compensation for Affected Mature Trees 346

3295 1,139,898 14,803.86

Total Direct Cost 1,380,898 17,933.73

Compensation for Vulnerabel

Aps. 0 0 0 0 0

Contingency 10% of the total direct cost

138,090 1,793.37

Total Estimated Resettlement Budget in US$ 1,518,987.35 19,727.11

Currency equivalent: AFN 77 = USD 1 as of January 2020.

Page 31: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

9. IMPLEMENTATION SCHEDULE AND PREPARATORY ACTIONS

9.1 LARP IMPLEMENTATION SCHEDULE

90. Figure 2 presents the Implementation Schedule of the LARP. The earliest time for

financial resources for resettlement aspects of the project are expected to be available in October 2020.

The actual implementation of the LARP, particularly delivery of

compensation therefore may begin by the footing of September 2020. However, sometimes

sequence may change due to circumstances beyond the control of the project.

Page 32: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

Figure 2: LARP Implementation Schedule

Task

2020

Jun Jul Aug Sep Oct Nov Dec

A. LARP Preparation

Preparation of LARP

Submission of Draft LARP for CPMO NWARA/ADB review

Submission of revised LARP addressing comments, if any

Acceptance of the LARP by CPMO/NWARA and ADB

Disclosure of the approved LARP

B. LARP Implementation

Allocation of LAR budget by Ministry of Finance

Preparation of vouchers

Compensation Payment

Preparation of Compliance Report by

Acceptance of CR by ADB

Public consultation and disclosure

Grievances Redress

Internal Monitoring

Commencement of Civil work

Page 33: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

9.2 Preparatory Actions

91. CPMO/NWARA will begin the implementation process of the LARP immediately after its acceptance by the

ADB.

92. The amount for compensation for tree removal will be included in the BOQ for the construction contractor

who will be tasked with paying this compensation before commencement of civil works.

93. Compensation payment will be made directly to the APs. Payment will be made as a cash payment to the AP

in the presence of the mirab, CDCs, PIO representative, contractor and RBA.

94. Grievances or objections (if any) will be redressed as per grievance redress procedure adopted in this LARP.

95. The steps for the delivery of compensation for all eligible AHs/APs will be the following:

• Preparation of invoices: Invoices for each of the eligible AHs/APs will be prepared by CPMO. This document

entitles each of the AHs/APs to receive the amount indicated in the invoice.

• Delivery of the money by construction contractor: Contractor will provide the money in Kunduz and will

be paid to AHs.

• Payment: Each AH/AP will creat a bank account or will receive a cash for the whole amount of compensation

from the contractor in the presense of PIO, CDCs/ Mirab and RBA. In case of cheque, it will be issued against

the household head name. The AH/AP shall sign a document acknowledging the receipt of the whole

compensation and a confirmation that he/she has no longer any pending claim over the affected property. A

photograph shall be taken with the AH/AP receiving the compensation as record of proof and as part of project

documentation. In case the AH/AP not having a bank account, they will be supported from project in opening

bank account.

• Identity of Person: At the time of receiving the compensation cash, as this is remote area and with no access

to the city and due to less amount the AHs may not be able to open bank account., therefore the AHs/APs will

present their National Identity Card (NIC) and will get their compensation as cash in the present of Social

safeguard specialist, PIO coordinator, CDCs head and water user association. Persons without NICs will

have to explain to the pertinent authorities the reasons why they are not in possession of the NIC.

Page 34: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

10. MONITORING, EVALUATION AND REPORTING

96. All planned tasks for implementation of the LARP will be subject to both internal and external monitoring to

assess the effectiveness and to provide feedback to CPMO/NWARA. Evaluation of the resettlement activities

will be resorted after implementation of the LARP to assess whether the resettlement objectives were

appropriate and whether they were met.

10.1. Internal Monitoring

97. Internal monitoring of all resettlement and consultation tasks and reporting to ADB will be conducted by the

SST within the CPMO. Also, the SST within the project consultants will conduct periodic review and

supervision mission during physical implementation stage. Internal monitoring report will then be integrated

by the CPMO with the overall Project Progress Report (PPR) for submission to ADB. However, the report will

include on progress in the activities envisaged in the implementation schedule with particular focus on public

consultations, accomplishment to-date, objectives attained and not attained during the period, problem

encountered, payment of compensation and level of satisfaction among APs, and record of grievances and

status of complaints.

10.3 Reporting

98. CPMO/PIO, supported by the social safeguards specialists of Implementation Supervision Consultant (ISC)

will supervise the implementation of the LARP and field level activities and prepare monthly reports on

resettlement activities and submit to the CPMO for review. Resettlement monitoring and compliance reports

will be sent to ADB along with regular submission of bi-annual social safeguard monitoring report SSMR for

review, clearance and disclosure through CPMO office.

Page 35: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

ANNEX 1: PARTICIPANT LIST OF CONSULTAITON MEETING

Date: June-July 2020

Date Location of meeting umber of participant Gender

District Village

15 June 2020 Chardara Chardara village 13) Head canal area Men

18 June 2020 Chardara Yar Baqal 10) Mid canal area Men

25 June 2020 Chardara Pul Kamar 14) Tail canal area Men

25 June 2020 Chardara Chardara (17) Tail canal area Women

Total 54

Page 36: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

ANNEX 2: ATTENDANCE LIST OF PUBLIC CONSULTAION MEETING, JUNE-JULY 2020

Page 37: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,
Page 38: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

MEN’S PUBLIC CONSULTATION MEETING AGENDA AND QUESTIONNAIRE

A. Introduction

B. Opening remarks

Dear Participants, we thank you very much for sparing your valuable time for participating in this important community consultation session, regarding the proposed project <name>. As the first step of our survey and design work, we are conducting field surveys and consultations with you people to obtain your collective views, interests and concerns regarding the design and construction of this project. Please, participate actively in this consultation session so that we clearly understand your views, interests and concerns, and possibly incorporate those in the design and construction of the project.

C. Discussion of project

1. Are you aware of the proposed project? Y/N

2. Do you approve of the construction of the project? Y/N

3. If not, why not? (give reason/s):

4. Do you think the construction this project is needed by you? Y/N

5. If yes, what specific difficulties do you face without this project? (for example, difficulties with: irrigation, agriculture water rotation, water losses, social conditions)

6. What specific benefits or positive Impacts do you expect from this project? (for example, improvements in irrigation, agriculture, water rotation, water losses, social conditions)

7. Approximately, how many villages and their total populations could benefit from this project?

Number of villages/towns: ___ estimated population: ___

8. Do you think the construction of this canal could cause any negative impacts? Y/N

9. If yes, what specific negative impacts or losses to local people do you foresee?

10. Do you think the construction of this canal could require land acquisition or resettlement?

11. If yes, what assets of local people could be affected and how severe would the negative impacts be?

Affected property/asset Severity of negative impacts (tick)

Productive land (crop, orchard, pasture) Severe □ Moderate □ Minor□

Land in built-up area (house, shop, etc.) Severe □ Moderate □ Minor□

Built-up structures (house, shop, etc.) Severe □ Moderate □ Minor□

Standing crops and wood/fruit trees Severe □ Moderate □ Minor□

Loss of income (business, employment) Severe □ Moderate □ Minor□

Other (specify) Severe □ Moderate □ Minor□

12. Do you think owners of affected assets may oppose construction of this project?

13. What might they demand in exchange for their cooperation with construction of this project?

14. What suggestions you can make to avoid or minimize land acquisition and resettlement impacts?

15. What specific suggestion you can make regarding design and construction of this project? (for example, changes in location or alignment of civil works)

Page 39: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

WOMEN’S PUBLIC CONSULTATION MEETING AGENDA AND QUESTIONNAIRE

1. Are you aware of the likely construction of the subproject?

2. What are your ideas about the construction of the subproject?

3. What are the major water-related problems for women’s activities, such as washing clothes?

4. What will be the positive impact for women of the subproject?

5. What modifications to the irrigation canals would be helpful (such as water collection, laundry, and animal watering points)?

6. Is the water you use for drinking clean and healthy or not? If not what are the problems and the reasons?

7. Where does your husband get water from? The irrigation canal or a tubewell? Do they get water from different places for different uses? (Drinking, washing, animals, watering the household garden)

8. Where do you wash your clothes? In the house? In the irrigation canal?

9. Are there times of the year when not enough water is available? If so, how do you manage?

10. What suggestions do you have regarding design and construction of this subproject?

11. What suggestions do you have to avoid or minimize the water problems you are facing?

Page 40: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

PUBLIC CONSULTATION WITH WOMEN

Questions

Village specifications

Focus groups answers in different villages

Chardara village (Chardara

Canal)

13 participants

Yar Baqal village

(Sharawan Canal)

10 Participant

Are you aware of the likely

construction of Sharawan-Takhar

Canal?

No Yes

What is your ideas for construction of

Sharawan-Takhar Canal?

We are happy to have for

water, we really need for water

in our village

We do not have proper access

for water, we would be happy

to have this canal

What are the major problems

regarding access to water

for washing the clothes and other

activities of women?

We do not have access for

water and we would be happy

to have for water through

canal repairing

We have problem for washing

clothes and other activities ,

some time there would not be

any water in canal

If Sharawan-Takhar canal improve the

construction what will be positives

impact for women?

The construction of this canal

will have many impacts , we

well have access for water and

well and we well not have

water shortage

definitely will have impact,

because we do not have

access for enough water for

drinking and irrigation

If the canal construction is here will

be modifications to the irrigation

canals that would be helpful (water

collection points, laundry points, and

animal water points)?

it would facilitate a lot we are

using canal water for

irrigation, for drinking, for

washing clothes etc

Yes, why not, it will help us

for having access for drinking

water, irrigation water and

animals

Page 41: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

is the water you use for drinking clean

and healthy or not? Of not what are

the problems. Reasons?

we are using for drinking for

washing clothes for animals

but it is not clean and safe in

any case we have to use this

water

yes we are using canal water

for drinking but it is not clean

Where does your husband get water

from? The irrigation canal or the tube

well? Or do they get water from

different places for different purposes

of drinking? Washing? Animals?

Watering the household gerden?

we are using from both canal

and wells

usually we are using canal

water, but some time using

from well

Where do you wash your clothes? In

the house? In the irrigation canal?

we are washing at home washing at home

Are there time of the year when there

is not enough water available? If so,

how do you manage?

from 12 month of the year, we

will have shortage of water in

the month of Saratan,Asad and

Mizan

from 12 months we will face

shortage of water in Jawza,

Saratan and Asad

What specific suggestions you can

make regarding design and

construction of this canal from

MoEW

We Suggest for ontime

construction of canal and

building stream from canal to

our house and which will

facilitate further access for

water and irrigation

we are suggesting for

construction of canal and

construction of stream for

overcoming of water issues

What suggestion you can make to

avoid or minimize water problems

which you are face along the time

from this canal

we need for wells we need of deep well

Page 42: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

MEETING MINUTES

1.4 MINUTES OF THE MEETING-CHARDARA CANAL UPSTREAM, MIDDLE STREAM, MEN

Meeting with Momen Abad Canal Middle stream( head area), men

Meeting date & time: 15 June 2020 1:00pm to 2:30pm

Place:

Chardara Village

Topics:

Explanation about the project proposed structures, discussion about

resettlement, environmental and social impacts, community feedback concern

and recommendations.

Attending:

Proponents: TawoosWafa, National Environment Consultant, Muhabattullah,

Resettlement Specialist, Mohammad Shaiq, WUA executive members,

MirabBashi and landowners, Takhar, Province.

Stakeholders: per sign-in sheet below, 13 participants - Mirabs, landowners,

farmers, CDC representatives

Concerns raised by stakeholders

Explanation regarding the project in general, and the proposed structures

1. The meeting participants were provided with the necessary information

regarding the project intervention, implementation arrangement, implementation

nature, social and environmental impacts etc.

2. Stated that they are fully consulted in the selection of proposed structures, they

added that they were part of the preliminary survey and selection process, they

added that the selected structures are as per their desire and priority, they believed

that upon construction of the selected structures there will be tangible

improvement in irrigation infrastructure, in terms of availability of reliable water

for irrigation, increment of yield and enhancement of living standard of the local

communities.

Explanation of the potential social and environmental impacts resulting due to the implementation of the project. Beneficiaries cooperation and commitments for the smooth implementation of the project, access road etc.

3. The meeting participants were provided enough information regarding the

social and environmental impacts of the project especially the removal of some

non-fruit trees and small saplings.

4. Stated that, they are agreeing with the project and added that the value of the

project is big and important than the removal of some non-fruit trees.

5. Stated that, that they are fully committed to paving the way for smooth

implementation of the project like; giving access road if needed, and regarding

the overall project-related matters. They added, they will solve any potential

dispute if they occur, they also stated that they will allow the contractor for

making a temporary access road for the transportation of construction materials.

6. They added that they are eager for this important infrastructure project, and

they said that they will provide full support for the smooth implementation of the

mentioned project.

The meeting participants declared their full support and cooperation regarding

the project.

Suggestions and feedback of meeting participants, No interruption of irrigation water during construction

7. They requested that the contractor should maintain normal water flow in the

canal during construction and find an alternative solution for allowing water for

irrigation and other domestic usages.

Page 43: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

Compensate farmers for crop damage due to temporary access road, material storage

8. Stated that, farmers should be compensated for damage to their crops, in case

it happened, due to temporary access roads for construction materials to each of

the proposed construction sites. The team stated that they did not have the details

of the compensation policy for such a situation, but they would report it up to the

Project.

Hire unskilled laborers locally

5. Stated that unskilled laborers should be hired locally from the immediate

project area, because local people are mostly jobless, on the other hand, they are

familiar with the tradition and culture of the people in the area. The team stated

that this would be done.

Minutes of the meeting-Chardar Canal Middle, Men

Meeting Chardar Canal Middle Men

Meeting date & time: 18 June 2020- 10:00am to 12:00pm

Place:

Yar Baqal village

Topics:

Explanation about the project proposed structures, discussion about

resettlement, environmental and social impacts, community feedback concern

and recommendations.

Attending:

Proponents: TawoosWafa, National Environment Consultant, Muhabattullah,

Resettlement Specialist, Mohammad Shaiq,WUA executive members,

MirabBashi and landowners, Takhar, Province.

Stakeholders: per sign-in sheet below, 9 participants - Mirabs, landowners,

farmers, CDC representatives

Concerns raised by stakeholders

Explanation regarding the project in general, and the proposed structures

1. The meeting participants were provided with the necessary information

regarding the project intervention, implementation arrangement, implementation

nature, social and environmental impacts etc.

2. Stated that they are fully consulted in the selection of proposed structures, they

added that they were part of the preliminary survey and selection process, they

added that the selected structures are of their first and foremost priority and upon

construction of the selected structures there will be tangible improvement in

irrigation infrastructure, in terms of availability of reliable water for irrigation

and increment of yield and enhancement of living standard of the local

communities.

Explanation of the potential social and environmental impacts resulting due to the implementation of the project. Beneficiaries cooperation and commitments for the smooth implementation of the project, access road etc.

3. The meeting participants were provided enough information regarding the

social and environmental impacts of the project especially the removal of some

non-fruit trees and small saplings.

4. Stated that, they are agreeing with the project and added that the value of the

project is big and important than the removal of some non-fruit trees.

5. Stated that, that they are fully committed in terms of paving the way for smooth

implementation of the project like; giving access road, if needed, and regarding

the overall project-related matters. They added, they will solve any potential

dispute if any, they also stated that, they will allow the contractor for making a

temporary access road for the transportation of construction materials.

6. They added that they are eager for this crucial infrastructure project, and they

said that they will provide full support for the smooth implementation of the

Page 44: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

project.

The meeting participants declared their full support and cooperation regarding

the project.

Suggestions and feedback of meeting participants, No interruption of irrigation water during construction

3. They stated and requested that the contractor should maintain normal water

flow in the canal during construction and find an alternative solution for allowing

water for irrigation and other domestic usages. They also suggested for making

automatic gates for the intake of the Sharawan canal, because it is easy and

reliable to control the flow in case of any emergency.

Compensate farmers for crop damage due to temporary access road, material storage

4. Stated that, farmers should be compensated for damage to their crops, in case

it happened, due to temporary access roads for construction materials to each of

the proposed construction sites. The team stated that they did not have the details

of the compensation policy for this situation, but would report it up to the Project.

Hire unskilled laborers locally

5. Stated that unskilled laborers should be hired locally and from the immediate

project area, because local people are mostly jobless and they are familiar with

the tradition and culture of the people and area. Team stated that this would be

done.

Minutes of the Meeting: Chardara Canal Down Stream, Men

Meeting with Chardara Canal Downstream( head area), men

Meeting date & time: 25 June 2020 10-01:00 PM

Place:

Pul Kamar village in the Water User Association Office

Topics:

Explanation about the project proposed structures, discussion about

resettlement, environmental and social impacts, community feedback concern

and recommendations.

Attending:

Proponents: TawoosWafa, National Environment Consultant, Muhabattulah,

Resettlement Specialist, Mr. Shaiq Agriculture specialist, WUA executive

members, MirabBashi and landowners, Takhar, Province.

Stakeholders: per sign-in sheet below, 9 participants - Mirabs, landowners,

farmers, CDC representatives

Concerns raised by stakeholders

Explanation regarding the project in general, and the proposed structures

1. The meeting participants were provided with the necessary information

regarding the project intervention, implementation arrangement, implementation

nature, social and environmental impacts etc.

2. Stated that they are fully consulted in the selection of proposed structures, they

added that they were part of the preliminary survey and selection process, they

added that the selected structures are of their first and foremost priority and upon

construction of the selected structures there will be tangible improvement in

irrigation infrastructure, in terms of availability of reliable water for irrigation

and increment of yield and enhancement of living standard of the local

Page 45: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

communities.

Explanation of the potential social and environmental impacts resulting due to the implementation of the project. Beneficiaries cooperation and commitments for the smooth implementation of the project, access road etc.

3. The meeting participants were provided enough information regarding the

social and environmental impacts of the project especially the removal of some

non-fruit trees and small saplings.

4. Stated that, they are agreeing with the project and added that the value of the

project is big and important than the removal of some non-fruit trees.

5. Stated that, that they are fully committed in terms of paving the way for smooth

implementation of the project like; giving access road, if needed, and regarding

the overall project-related matters. They added, they will solve any potential

dispute if any, they also stated that, they will allow the contractor for making a

temporary access road for the transportation of construction materials.

6. They added that they are eager for this crucial infrastructure project, and they

said that they will provide full support for the smooth implementation of the

project.

The meeting participants declared their full support and cooperation regarding

the project.

Suggestions and feedback of meeting participants, No interruption of irrigation water during construction

3. They stated and requested that the contractor should maintain normal water

flow in the canal during construction and find an alternative solution for allowing

water for irrigation and other domestic usages. They also suggested making

automatic gates for the intake of the Sharawan canal, because it is easy and

reliable to control the flow in case of any emergency.

Compensate farmers for crop damage due to temporary access road, material storage

4. Stated that, farmers should be compensated for damage to their crops, in case

it happened, due to temporary access roads for construction materials to each of

the proposed construction sites. The team stated that they did not have the details

of the compensation policy for this situation but would report it up to the Project.

Hire unskilled laborers locally

5. Stated that unskilled laborers should be hired locally and from the immediate

project area, because local people are mostly jobless and they are familiar with

the tradition and culture of the people and area., Team stated that this would be

done.

Page 46: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

ANNEX 3: PHOTOGRAPHS OF PUBLIC CONSULTATION MEETINGS, JUNE-JULY 2020

Page 47: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

ANNEX 4: PUBLIC INFORMATION BOOKLET

ISLAMIC REPUBLIC OF AFGHANISTAN

NATIONAL WATER AFFAIR REGULATION AUTHORITY

PUBLIC INFORMATION BOOKLET

Resettlement and Compensation

Panj Amu River Basin Project (PARB-P)

July 2020

1. Introduction and Impact Summary

1. The Panj-Amu River Basin Project Sector Project (PARB), Afghanistan Project will support improved water allocation and availability, enhanced on-farm water management, and protection of watersheds in the Panj-Amu River basin, through construction of water conveyance and irrigation infrastructure at 21 priority subprojects (construction costs approximately $50 million); the establishment, strengthening, and support of subproject water user associations (WUAs) and irrigator associations (IAs); training on on-farm water management and improved agronomic techniques; implementation of watershed management plans at sites adjacent to the priority subprojects; and improved basin water resources planning and management.

2. Since 2004, the European Union (EU) has supported the Government of the Islamic Republic of Afghanistan (GoIRA) in its reconstruction efforts by funding integrated water management programmes in the Panj Amu River basin. The Qulbars-Shorab subprojects continues this EU support in partnership with ADB as co-financier and administrator. This approach aims to improve Government’s ownership of fund management and conform to EU policy in Afghanistan of moving funding on-budget or into co-financing arrangements, and to increase sustainability.

3. The importance of the PARB Project is in its impact on the well-being of rural communities in the basin, and in its support for Afghanistan’s sector investment plan, the $1.1 billion National Water and Natural Resources Development Program.

4. Census and Socioeconomic Survey data demonstrate that implementation of the Chardara canal will

cause involuntary resettlement impact on17 households (HHs) with a total of about 205 affected persons

across the whole project area.

5. However, project implementation will not cause any major impact. At the same time, the impact on the

income of the affected people will be less than 10% of the total income, i.e., no household will lose

more than 10% of his/her productive asset. A summary of impact is presented in Table 1.

Table 1: Summary of Impact under the Chardara canal

ype of Impact Magnitude of Impact

ected Households and Persons

Number of Affected Households ouseholds

Page 48: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

Number of Affected Persons (APs) 205 Persons

Affected Male APs 105 Persons

Affected Female APs 100 Persons

ected Assets

Number of Affected Trees (Grown on Govt. Land) 1081 Numbers

6. To address this resettlement impact, the Government has prepared this Land Acquisition and

Resettlement Plan (LARP), complying with the existing Law on Managing Land Affairs of Afghanistan

and the ADB’s safeguard requirements on involuntary resettlement under the Safeguard Policy

Statement (2009), adhering to the principles and procedures outlined in the Resettlement Framework

(RF) adopted by the Government for the Panjj Amu River Basin Project.

7. Chardara improvement works have been planned to be carried out within the available land owned by

the government along the existing canal alignments. However, in the course of CSS survey, it was found

that the people residing adjacent to the canal alignments are using this land over the years and benefiting

from the land commonly by planting trees.

2. Mention should be made that the amounts or the extent of land that will be obtained for Compensation

Eligibility and Entitlement

8. There are only trees which are affected due to project. The entitlement provisions for APs suffering

different types of losses and for rehabilitation allowances are:

• Compensation for Trees: compensation for trees removal has been calculated based on replacement

cost. The trees which are to be removed are non-fruit trees which are used for fuel wood, and the

compensation will be paid based on their dry wood.

• Compensation for Unforeseen Impacts:Unforeseen impacts will be documented and mitigated based

on the principles agreed in this LARP.

• Compensation for vulnerable people (Aps living under poverty line): compensation for Aps which

are determined as Aps who are living under poverty line.

3. Public Consultation and Disclosure

9. This LARP has been formulated through a process of active participation of the affected persons and

their community. The concerns and suggestions of the community people integrated through extensive

consultation during the CSS. The works of implementing the LARP will be carried out by the CPMO

within NWARA and the social safeguards specialist within the Implementing Supervision Consultant

(ISC). The LARP will be disclosed to the affected community after it is approved by NWARA and

ADB. This Information Booklet will be translated in local language and will be disclosed to APs. At

the time of its implementation, consultation will be carried out with the community to resolve any issue

that might crop up.

10. Chardara LARP cost estimate has included the compensation for the AHs for their affected trees. CPMO

SST and the SST within Implementing Supervision Consultant (ISC), will carry out this task in the

field.

4. GRIEVANCE REDRESS MECHANISM

11. Through public consultations and distribution of the Public Information Booklet, APs

will be informed that they have a right to file complaints to Grievance Redress Committee

(GRC) on any aspects of compensation or on any other related grievance. It should be

pointed out that this committee does not possess any legal mandate or authority to resolve

LAR issues, rather acts as an advisory body or facilitator to try to resolve issues between the

Page 49: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

affected household and the NWARA/CPMO. GRCs will review grievances involving in all

resettlement benefits. Any complaints of ownership or other suits, to be resolved by judicial

system, will not be resolved in GRCs.

12. GRC is proposed to be formed at the project area. In case of the absence of any of the members during

the decision-making process, an appropriate candidate will be nominated by the original representative.

However, at least five members should execute a session for grievance resolution.

Proposed Measures to Address Grievance

13. Grievances will be addressed through the following steps:

14. Grievance registration: Any aggrieved AP will first produce his/her complain/grievance in writing to

the Convener of the GRC. Upon receipt of complaint(s), the Convener will organize a GRC hearing

session in his/her office within 15 days for resolution of the grievance(s), and preserve all related

records, proceedings, decision and recommendations. The verdicts will be conveyed to the concerned

AP through the respective PIO office in the province.

15. Grievance processing: Queries and complaints that are clarified and resolved at the intake point are

closed immediately. If grievances are not resolved at the local level GRC, then complaints can be lodged

at the District Committee at the district level. The District Committee under chairmanship of the

respective District Governor will resolve the case within 15 days and inform the APs.

16. Feedback provision: Receipt of grievances lodged in person or via phone will be acknowledged

immediately. Receipt of grievances received through a letter or e-mail or acknowledged through a letter

/ e-mail within 3 working days upon receipt by GRC coordinator at local level. In case the grievance is

not related to project activities or impacts generated due to the project implementation and cannot be

considered, the feedback will be provided to the complaining party specifying to which entity

(community or department as relevant) it has been forwarded.

17. If the District Committee decision is unacceptable to the APs, they can register the complaint directly

to the CPMO at Kabul within 1 month of receiving the response from the District Committee with

documents supporting their claim.

GRM: Central Level

18. Following unsuccessful consideration of grievance by GRC at the district level complaint resolution

will be attempted at a central level through following steps.

19. Grievance processing: If the District Committee decision is unacceptable to the APs, they can register

the complaint directly to the CPMO at Kabul within 1 month of receiving the response from the District

Committee with documents supporting their claim. The CPMO will then attempt to resolve the

grievance within 15 days and inform the APs.

20. Feedback provision: If the grievance was resolved, the complaining party will be informed on the

outcome of grievance resolution. If grievance was not resolved by the GRC at central level, appropriate

information will be provided to the complaining party, including details why the case was not resolved.

21. Should all the above three levels of grievance redress system fail to satisfy the AP, he/she may approach

the appropriate court of law for its resolution. The AP will be facilitated in this process by SST.

5. Budget Description

22. Resettlement impact mitigation program under implementation of the Chardara will require a total

estimated amount of USD 17449.29, out of which USD 15862.3 is the direct compensation cost. USD

1586.30 is kept as 10% contingency on the total direct cost to meet the cost of internal monitoring,

Page 50: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

consultation and disclosure, administrative and other expenses. Table 8.1 summarizes the estimated cost

of LARP implementation for the Chardara subproject. It should be emphasized that this direct

compensation cost estimate is derived from the inventory of survey.

23. Contact Details for Inquiry

16. For further information about the project as a whole, and/or the LARP for the Chardara under the PARB-P,

please contact the CPMO/NWARA at the address given below.

Central Program Management Office (CPMO):

Mujeebullah Ahmadzai

Sr. Safeguard Manager

National Water Affair Regulation Authority (NWARA)

Mobile :( +93)766-388-242

Email: [email protected]

Page 51: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

ANNEX 5: LIST OF AHS AND COMPENSATION LIST OF AHS WITH RESTTLEMENT IMPACT AND COMPENSATION

No. Structure Name Village AP Name ID

Number

Type and Category of Trees

Total No of

Trees

under

structure

Platanus Willow Russian Olive Mulbery Poplas alba

Sa

pli

ng

Me

du

im

Ma

ture

Sa

pli

ng

Me

du

im

Ma

ture

Sa

pli

ng

Me

du

im

Ma

ture

Sa

pli

ng

Me

du

im

Ma

ture

Sa

pli

ng

Me

du

im

Ma

ture

1

Char Dara canal Head

Work to 1st 2nd 3rd & 4th

Spillway structure canal

lining

Qasim Ali 1st

2nd & 3rd

Lalah Midan

Sultan

Mohd. 9902048 13 150 50 65 20 20 40 110 100 568

2

Protection wall 100 m R/s

of canal(Lala maidan

village) Qasim Ali Abdul Kaliq 27133706 10 5 5 5 5 30

3 Protection wall 100m

Arbab

Husain, Abdul Nabi 12907985 5 5 5 5 5 5 5 5 5 5 50

4 Band Chilkhosh off-take

Maghoul ha

village

Agha Sha &

Naseir

Mohd. n/a 30 20 25 25 10 10 10 10 25 25 190

5

Madarasa Shakh off-take

& weir

Qasab

village, Char

sheed Attaullah 9902048 5 5 5 5 5 5 10 10 50

6 Mangel ha Bridge Mangal

Haji Sultan,

Ab. Halim,

M. Ismayel 4 5 14 4 5 6 38

7

Khoja Kaftar off-take

without weir Ahmad Zai

Aziz

Pahlawan 15 9 6 6 36

8

Jalpaq off-take & bank

protection Khalzai Baz Mir 7 4 6 17

Page 52: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

9 Palaw Kamar Canal lining Palaw Kamar

Dastgir,

Mohammad

Amin, Mirza

Ghafoor 13

2

1 9 12 4 6 4 69

10 Nawabad off-take & weir Palaw Kamar

Dastgir,

Mohammad

Amin, Mirza

Ghafoor 7 3 10

11 Jazaba off-take & wash Kunjak Farooq 4 4

12 Zadran Bridge Kunjak

Qari Nemat,

Samiullah 4 3 5 12

13

Zahir Khan Canal Bank

Protection Zadran Zahir Khan 4 3 7

14

Protection wall 100m

Protection wall 100m (Lala

maidan village) Qasim Ali Qasim Ali 27133706 0 10 10 10 10 10 10 10 10 20 100

15

Protection wall 250m (Lala

maidan village)

Qasim Ali

Malem

Mohd. Yosuf Gul Mohd. 25849910 10 5 5 10 10 10 10 60

16

Construction of new

spillway+100m P wall

Amir Mosa ,

Front of

School Attaullah 9902048 5 5 10 5 5 30

17 Band Qasim Ali Off-take Mer Shikh

Qari

Mahmod n/a 5 5 5 5 5 25

Total 17 41 254 99

5

2

15

3 49 30 68 38 37

10

9 10 16 190 150 1296

Page 53: Land Acquisition and Resettlement Plan (LARP) Compliance ... · Chardara canal length is 61 km and the structures are located in the existing alignment of canal which is 12-18 meters,

Recommended