Landscape and Visual ImpactGas Import Jetty and Pipeline ProjectExpert Witness Statement: Visual Impact – Hayden Burge
Principal Landscape Architect and Visual Impact Consultant
Jacobs Group (Australia) Pty Limited
Level 11, 452 Flinders Street
Melbourne, Victoria 3000
Basis of my review
©Jacobs 20192
Review the EES Requirements relevant to Landscape and Visual Impact;
Reviewed available project information suitable to undertake a site visit;
Undertook a site visit on 29 July, 2020;
Reviewed the Ethos Urban LVIA and relevant report chapter;
Reviewed submissions relevant to my area of expertise;
Prepared my own photomontage;
Review the potential for views and visual impacts to form my views of the project and to consider key concerns raised in submissions (where possible);
Sought additional detail of the project;
Reviewed the mitigation measures proposed by the previous LVIA and make any further recommendations or changes; and
Reviewed evidence of other submitters.
Key Project Components
©Jacobs 20203
Key visual components:
Permanent mooring of a Floating Storage and Regasification Unit (FSRU) berthed at the existing Crib Point Jetty (FSRU);
New gas handling infrastructure on the existing jetty;
Gas Receiving Facility at Crib Point (CPRF);
~60km gas pipeline (Crib Point to Pakenham);
Mainline Valves (MLVs)
Delivery facility located at Pakenham East (PDF); and
End of line scraper station (EOLSS).
Submissions
Landscape and Visual Impact
©Jacobs 20204
Submissions Received
6000+ submissions comprising individual, template/proforma and agency submissions. Key themes:
Amenity and visual impact to recreation areas
Woolley’s and Jacks Beach
Foreshore areas and reserves
Warringine Park and Bittern Coastal Wetlands
trails;
Impacts to the landscape character of the locality due to further industrialisation
Increase in shipping and boat traffic within Western Port
Visual bulk of the FSRU
Night time lighting
Site Visit
29 July 2020
©Jacobs 20206
Locations Visited
EOLSS
General Pipeline Alignment
Alignment through Hastings
Western Edge of Warringine Park
Nearby Beach and Foreshore Areas
Stony Point Jetty
Locations Visited
EOLSS
Pakenham Delivery Facility
General Pipeline Alignment
Alignment through Hastings
Western Edge of Warringine Park
Nearby Beach and Foreshore locations
− Jacks Beach
− Woolleys Beach
− Woolleys Beach South
The Esplanade
Stoney Point Jetty
Review of Landscape and Visual Impact Assessment
Ethos Urban
©Jacobs 20209
Methodology Review: Ethos Urban
©Jacobs 201910
The assessment methodology adopted by Ethos Urban is based upon the Guidelines for Landscape and Visual Impact Assessment (the Guidelines) (LI & IEMA 2013).
UK Guidelines are often referred to as there is no formal or set guidance specific to Australia.
The methodology considers Landscape Impacts and Visual Impacts as separate metrics, and outlines the flowchart for each assessment methodology (Landscape Impact methodology) (Visual Impact Methodology)
Ethos Urban: Methodology
©Jacobs 201911
Viewshed / Study area was not clearly defined
Statutory/Planning review did not appear to fully inform landscape character
Landscape Character and sensitivity identified four LCA’s
− LU01 – Western Port Lowlands – Coastal Foreshore
− LU02 – Western Port Lowlands – Urban Settlement
− LU03 – Western Port Lowlands – Agricultural Plains
− LU04 – Dandenong Ranges – Southern Foothills
Views from Warringine Park, Locations along Woolley's Beach South and Stony Point Jetty
Photomontages
©Jacobs 202012
Photomontages
©Jacobs 202013
Technical Accuracy 3D Computer Generated Model Registered to existing background
Perceptual Accuracy Lens length 60º horizontal 15º +/- field of view Alignment to the view
Photomontage Locations
©Jacobs 201914
Urban Circus Photomontage Locations
Victorian Maritime Centre
Woolley’s Beach
Submarine Lookout
The Esplanade
The Pinnacles (French Island)
Ethos Urban
The Esplanade / Jacks Beach
MLV1 / 2
Photomontages
©Jacobs 201915
Urban Circus Photomontages
Prepared using client supplied models
Background imagery high smoke haze
Technically Accurate
Provide limited context of the view
Ethos Urban Montages
Limited technical basis
Some imagery overstate project impacts
Woolley’s Beach - Urban Circus
MLV 2 – Ethos Urban
Photomontage Review - Technical
©Jacobs 202016
Existing View
Photomontage
Wireframe
Photomontage Review - Perceptual
©Jacobs 202017
Photomontage - 60º
Additional Detail
©Jacobs 202018
Additional Detail
©Jacobs 201919
MLA Technical Drawings
Flaring and Lighting at the MLV
Existing Fencing at the CPRF Site
Vegetation Removal / Retention at the CPRF
Intention of MM-LV03 Materials and Finishes
Pipeline Alignment North of the Princes Freeway
Review of Landscape and Visual Impact Assessment
Ethos Urban
©Jacobs 202020
Planning considerations
©Jacobs 202021
Land Use: The FSRU is proposed to be permanently moored at the existing Crib Point Jetty. The Jetty has been in place and continually used as a commercial liquid fuels import facility since the 1960s. The proposed-on shore receiving facility is located within an area to the north of an existing fuel facility, which has also been part of an operational port since the 1960s.
Strategic Documents: Several policy and strategic documents determine the future use of Crib Point Jetty is to be retained for port uses.
These strategic port, transport and land-use studies contemplate and support an increase in port-related activities in the region and the recommendation for various landside upgrades to supporting road and rail infrastructure.
Several submissions have raised concerns relating to the visual impact of an increase in ship movements resulting from the approval of the Project at Crib Point.
It is apparent that the visual impact relating to increasing ship movements is not only commensurate with the nature of an active shipping lane and port, but this increase is also contemplated at various stages of planning and strategic reviews and by many departmental agencies.
FSRU and Jetty Works – Viewshed and Zones of Visual Influence
©Jacobs 202022
The tallest element associated with the FSRU is the 50 m high exhaust stack, projecting above the bridge and control centre.
CPRF – Viewshed and Zones of Visual Influence
©Jacobs 202023
The tallest element associated with the CPRF is the 20 m high liquid nitrogen storage tanks and vaporiser towers.
MLV’s – Viewshed and Zones of Visual Influence
©Jacobs 202024
The MLV’s will be enclosed within 3.0 m high perimeter fencing. The height of the fencing has been used to establish the viewshed for the MLVs.
MLV1
MLV2
PDF – Viewshed and Zones of Visual Influence
©Jacobs 202025
The largest component of the delivery facility would be the safety lighting at 10 m in height and vent outlets at 7 m high. The following calculations are based on a 10 m high vent stack.
Landscape Units
©Jacobs 202026
The LVIA undertaken by Ethos Urban for the project identified four landscape character units
− LU01 – Western Port Lowlands – Coastal Foreshore
− LU02 – Western Port Lowlands – Urban Settlement
− LU03 – Western Port Lowlands – Agricultural Plains
− LU04 – Dandenong Ranges – Southern Foothills
Additional Landscape Units :
− LU 05 - Rural Residential
− LU 06 - Industrial and Port Related Units
− LU 07 - Ramsar Wetlands
− LU 08 - Recreation and Open Space
Key Views and considerations
©Jacobs 202027
View Assessment – Publicly accessible locations
12 Viewpoints FSRU and CPRF4 Viewpoints Pakenham Delivery Facility / EOLSS
MLVs
VP 02 – Woolleys Beach Reserve
©Jacobs 202029
©Jacobs 202030
VP 02 – Woolleys Beach Reserve
©Jacobs 202031
Existing View
Photomontage
Wireframe
©Jacobs 202032
VP 12 – Warringine Park
©Jacobs 202033
HDD
HDD
Open Cut trenching
HDD
Open Cut trenching
VP 07 – The Pinnacles
©Jacobs 202034
The assessment of this view is based upon information included in the assessment undertaken by Ethos Urban within the EES and my observations from the broader area.
I have not visited this location due to the travel restrictions.
©Jacobs 202035
Crib Point Jetty/FSRU Long Island Point
The FSRU and the CPRF would be visible but not visually dominant features.
Boats are commensurate with the context of this view
The visual impact of the FSRU permanently moored alongside the existing Crib Point Jetty would be negligible to low.
The visual impact CPRF would be seen over the existing crib point jetty when boats are not moored at Berth 1.
When visible, the visual impact would be negligible to low.
MM-LV03 would further assist to reduce visual contrast of the CPRF
©Jacobs 202036
Crib Point Jetty
Long Island Point
Source light trends light pollution map
Long Island Point
Crib Point Jetty
Crib Point
Crib Point
Night Lighting
The Esplanade – Existing Lighting
Pinnacles – Existing Lighting
Night Lighting The Esplanade
©Jacobs 202037
The Esplanade – Existing Lighting Berth 1
The Esplanade – Existing Lighting
The Esplanade Project Impacts
FSRUBerth 1
Berth 1
Visual Impact Assessment Comparison
©Jacobs 202038
The overall visual impact is similar or the same for the landscape units identified within the Ethos Urban Assessment
The overall visual impact of the project in views from the additional landscape units would be low.
Mitigation Measures
©Jacobs 202039
POS – VS EPR
Mitigation Measures for the whole of project summarised at Chapter 25 of the EES
Six Mitigation measures were proposed to manage / mitigate the visual impacts of the project which applied to area around the CPRF and Pipeline components
The statutory approvals of the Gas Import Jetty works are subject to the Planning and Environment Act 1987. Proposed Mitigation Measures would form part of a planning permit and would be referenced in the Planning Scheme. It is preferable that Mitigation Measures are described as Environmental Performance Requirements (EPR’s).
Mitigation Measures Relevant to the Gas Import Jetty Works will be referred to MM/EPR’s.
The Pipeline component is subject to approvals under the Pipelines Act 2005. Planning permission is not required in respect to the Pipelines Act. Mitigation measures relevant to the Pipeline works are to form part of the Performance and Objectives Standards (POS). Mitigation Measures under the Pipelines Act are given effect as part of a CEMP. It is therefore preferable that these be more prescriptive.
Mitigation Measures Relevant to the Gas Import Jetty Works will be referred to MM/POS.
Gas Import Jetty Works - Environmental Performance Requirements – MM/EPR’s
©Jacobs 202040
Mitigation Measures are appropriate for the Gas Import Jetty Works
MM-LV01 relates primarily to the pipeline works. This is still relevant to the perimeter and site frontage
MM-LV02 – Vegetation will be retained where practicable and introduced to screen facilities within the viewshed of roads (such as The Esplanade) and where possible residences, if reasonably requested by affected landholders and with any necessary approvals granted.
It is noted that land based components of the Gas Import Jetty Works are to be designed to comply with Australian Standard AS 4282:2019 Control of the Obtrusive Effects of Outdoor Lighting.
Pipeline Works – Performance and Objectives – MM/POS
©Jacobs 202041
MM-LV01 Reinstate Ground Surface –MM/POS – LV01
CEMP R12 Habitat features removed during construction such as large hollow logs and large rocks will be returned to the ROW during rehabilitation if consistent with rehabilitation objectives at a particular location. Landholder requirements will be considered prior to returning habitat features to the ROW
CEMP R13 Rehabilitation by assisted natural regeneration will be undertaken on the ROW, except within four metres of the pipeline, in areas where there is an increased risk of habitat fragmentation (as identified in the Environmental Line List (Attachment G)).
CEMP R16 Following completion of reinstatement, written agreement will be sought from landowners (and occupiers, managers or government agencies as applicable) of the satisfaction of the reinstatement works.
Pipeline Works – Performance and Objectives – MM/POS
©Jacobs 202042
MM-LV02 Landscape Screening – MM/POS-LV02
CEMP Reference A2
CEMP Reference A5
CEMP Reference A6
CEMP Reference new A12 as per Technical note 24
Pipeline Works – Performance and Objectives – MM/POS
©Jacobs 202043
MM-LV03 Materials and finishes – MM/POS-LV03
CEMP Reference A13 Selection of materials and finishes will appropriately respond to the environment and be complimentary to the setting
Pipeline Works – Performance and Objectives – MM/POS
©Jacobs 202044
MM-LV05 Reflective Surfaces – MM/POS-LV05
CEMP Reference A14 Reflective surfaces on infrastructure will be minimised to reduce reflection of artificial light where practicable
Pipeline Works – Performance and Objectives – MM/POS
©Jacobs 202045
MM-LV06 Vegetation outside construction footprint – MM/POS-LV06
CEMP Reference B1 - All vegetation clearing works will be confined to the RoW. The boundary of the RoW will be clearly demarcated with survey pegs. If there is any loss of native vegetation outside of the RoW, it will be replaced.
CEMP Reference B2 - Clearing of native vegetation will be offset in accordance with the Guidelines for the removal, destruction or lopping of native vegetation (DELWP 2017) prior to the clearing commencing.
CEMP Reference B3 - No native vegetation to be retained will be cleared. Environmental features to be retained within or directly adjacent to, the construction footprint, will be clearly demarcated and identified on site (Attachment G – Environmental Line List).
Conclusions
©Jacobs 202046
The change in views and visual impact brought about by the project will be noticeable but will not be unacceptable.
This change is commensurate with the types of views that would be expected within an active port’s precinct.
At over 10 km from the FSRU, views and visual impact from Phillip Island would be commensurate with the context of existing views.
The FSRU will be visible from French Island. Views towards the project and the FSRU are over open water and have historically included similar sized boats and landside infrastructure. In this context, the change to the view is the permanent presence of a boat, moored alongside at the existing jetty.
The CPRF will be visible from a short section of the Esplanade. Views will be confined due to road geometry and the surrounding vegetation. This vegetation will screen views from the surrounding recreational sites (including, Jacks Beach, the Bittern Boardwalk and extended coastal trails in the area)
In views from open water, the receiving facility will be visible, however, it would be in views that are over the existing jetty and against a backdrop that includes the Port of Hastings and remaining tanks along the eastern edge of the former BP Refinery Site.
Conclusions
©Jacobs 202047
Increased shipping traffic was a common concern for submitters. In the context site, these elements would not only be commensurate with the nature of an active shipping lane and port, but this increase is also contemplated at various stages of planning and strategic reviews and by many departmental agencies.
Policy and strategic reviews, confirm the desired future use of the existing Jetty and associated land is to be protected and retained for ports related uses while recognising the sensitivities of the surrounding areas. The proposed use is consistent with these objectives.
Impacts to nearby recreational areas was a common concern amongst submitters. The proposal will not impact on the current permissible access and circulation pattern of Woolley’s Beach Reserve, the foreshore areas and coastal trails to the south, the submarine trail and lookout, or Jack Beach Reserve further to the north.
The primary change in views from nearby recreational reserves would alter to include a boat permanently moored along side the existing Crib Point Jetty, rather than one that is infrequent. This visual change is consistent with the existing setting and use of this area.
Conclusions
©Jacobs 202048
The majority of the pipeline would be constructed using open-cut trenching, which is to be backfilled and rehabilitated to match the existing and surrounding area.
The remaining sections of the pipeline would be constructed using horizontal boring machines limiting impacts to sensitive vegetation and uses.
There are no landscape mitigation measures would be provided within Construction Environmental Management Plans (CEMP).
Construction impacts will be temporary and short in duration as evidenced by existing pipelines.
Landscape and Visual Impact�Gas Import Jetty and Pipeline Project�Expert Witness Statement: Visual Impact – Hayden BurgeBasis of my reviewKey Project ComponentsSubmissionsSubmissions ReceivedSite VisitLocations VisitedLocations VisitedReview of Landscape and Visual Impact AssessmentMethodology Review: Ethos UrbanEthos Urban: MethodologyPhotomontagesPhotomontagesPhotomontage LocationsPhotomontagesPhotomontage Review - TechnicalPhotomontage Review - PerceptualAdditional DetailAdditional DetailReview of Landscape and Visual Impact AssessmentPlanning considerationsFSRU and Jetty Works – Viewshed and Zones of Visual InfluenceCPRF – Viewshed and Zones of Visual InfluenceMLV’s – Viewshed and Zones of Visual InfluencePDF – Viewshed and Zones of Visual InfluenceLandscape UnitsKey Views and considerationsView Assessment – Publicly accessible locationsVP 02 – Woolleys Beach ReserveSlide Number 30VP 02 – Woolleys Beach ReserveSlide Number 32VP 12 – Warringine ParkVP 07 – The PinnaclesSlide Number 35Night LightingNight Lighting The EsplanadeVisual Impact Assessment ComparisonMitigation MeasuresGas Import Jetty Works - Environmental Performance Requirements – MM/EPR’sPipeline Works – Performance and Objectives – MM/POSPipeline Works – Performance and Objectives – MM/POSPipeline Works – Performance and Objectives – MM/POSPipeline Works – Performance and Objectives – MM/POSPipeline Works – Performance and Objectives – MM/POSConclusionsConclusionsConclusions