LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 2 / 27
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 3 / 27
Take Home Points
Phase II Rotate-able Collimators– Elevated to “Hard Deliverable Status” in eyes of our CERN colleagues – Schedule slippage of ~6 months
• Manpower issues
• Review committee issues (more complete design before can start)
– 400k$ returned to LARP general fund– Now on track & better staffed– Consensus that we need more effort to understand 1 MJ beam-abort
on jaw
Communication with CERN slower than ideal (see Nikolai’s comments later)– Should we ask Ralph to appoint a “Point of Contact”?
New Task 5 proposed: Crystal Collimation– To be examined by Gang of 5+1: (4 x L2 + VS) + S
• Impact on “baseline” secondary collimator
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 4 / 27
Task 2: Progress Since October 2005 Meeting
State of affairs Oct. 2005: Ion loss maps in RHIC agree with tracking results, protons do not.
Since then, no progress : analysis of proton loss data awaiting manpower– hope is that CERN student who set up Sixtrack with BNL lattice will
take BNL postdoc jobNew work on Collimator efficiency & set up
– Heavy Ions and protons very different– positioning procedure for p is slow and tedious and not reproducible– For protons, the effectiveness of the individual collimators changes
from store to store and between the IRsOther LARP (not collimation) activities:
– LBL luminosity monitor installed in RHIC IR10 between existing luminosity detectors for calibration later this year
– E-cloud studies with LHC style electron detectors installed in IR10
Electron Detector in RHIC
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 5 / 27
RHIC Tracking Results
-100 -50 0 50 100 150 200 250 3000
0.5
1
1.5
2
2.5
3
3.5
4
Lo
g o
f lo
ss
es
(a
rb. u
nit
s)
distance from PHENIX (m)
Comparison ICOSIM (black) with BLM data during gap cleaning
PH
EN
IX
PH
OB
OS
12 o
'clo
ck
BR
AH
MS
4 o
'clo
ck
S
TA
R
Ions Agree
With
“ICOSIM”
Protons Data does not agree
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 6 / 27
TERTIARY COLLIMATORS- October 2005 Status
Tertiary collimators (TCT) at 8.4 around IR1/5 protect SC triplets from tertiary halo coming from particles leaking from 7 secondary collimators, upstream beam-gas and inefficiency of MPS if unsynchronized beam abort. These must not induce peak energy deposition in the triplets above the quench limit nor induce detector backgrounds.
80 x 25 x 1000mm Cu jaws at .4s 145m from IP added to MARS15
Without TCTs With TCTs
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 7 / 27
Example of New MARS15 RESULTSafter upgrades to Mars code and updates to layout
• Outgoing beam: TCTs are pretty radioactive (especially if made of tungsten) and interfere with the TOTEM first station XRP1 at 146 m.
• Incoming beam: preliminary results for beam-gas are encouraging.
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 8 / 27
TERTIARY COLLIMATORS PROGRESS & PLANS
In October 2005, Nikolai wrote:
– File of Beam1 loss in TCT region calculated by CERN received 2005-09
• Need similar file for Beam2
• Need similar files for momentum cleaning insertion IR3
– Plan to begin updating results using these files beginning mid-October
Today Nikolai writes Need input from Ralph ASAP
- it’s not the first time – obviously a communication issue As soon as beam loss input files received ~2 mos to finish most work
on TCT If no surprises – task can be closed ~1/2 yr
6 months without requested information
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 9 / 27
Task #4: Irradiation Damage Assessment of LHC collimator materials
Scope: Irradiate 2-D weave carbon-carbon and exact graphite used in
Phase I jaws plus materials considered viable for Phase II jaws• BNL AGS/BLIP (117 & 200 MeV protons)
Measure material properties: thermal expansion, mechanical properties, thermal conductivity/diffusivity and thermal shock• BNL Hot Cell Sample Measurement Facility
Status October 2005:– Phase I Carbon-Carbon irradiation completed– Sample activation measurements completed– Thermal Expansion of specimens started
Specimens highly degraded under dose>> LHC collimator jaws will see.
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 10 / 27
CTE Measurements of Irradiated C-C
Strong (fiber plane) direction
Irradiation Damage Self Anneals through thermal cycling in both strong and weak directions
7.50 mCi
Weak (┴fiber plane) direction
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 11 / 27
Materials for May 2006 BLIP Run are Ready
Primary Phase II Materials:
• Annealed Copper • Glidcop (0.15% Al –
balance Cu)
Other Potential Phase II Materials:
• Super Invar• Gum Metal
Other Materials to be (re)tested
• 2D Carbon-Carbon• 3D Carbon-Carbon
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 12 / 27
New Measurement Equipment
Mechanical Testing Equipment (Stress vs. Strain) to be
reintroduced to the Hot Lab
+
Thermal Conductivity Measurements Using the Laser Flash MethodLaser already in the Hot LabExperimental Safety Review is taking place at BNLGrad Student from SUNY/SB joined the team
Tests are planned for summer and fall FY06
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 13 / 27
Jaw Damage Studies(an increase in scope)
Simulations of Extreme Energy
Deposition (jaw damage case)
Using LS-DYNA
Measurements of laser induced
ablation of Cu and comparison with
LS-DYNA
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 14 / 27
Crystal Collimation Proposal
• Stages: – Stage 1: feasibility study itself– Stage 2: design of the LHC Phase II Collimation system
• Goal: deliver a report (of a mini-review?) by next LARP collaboration meeting (~ April 2007), be in position to decide whether to proceed to Stage 2
• Plan: – Prepare and perform bent crystal
experiments at Tevatron in Fall 2006 – Prepare and perform crystal characterization
experiment at SPS H8 line in Sep’06– Data processing and analysis – Theory work and code development for the LHC
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 15 / 27
Status of Phase II Rotating Collimator Project at 10-06-2005 Pheasant Run LARP Mtg.
SLAC and CERN agree on an initial set of specifications for the first mechanical prototype RC1– Put a new vacuum tank with cylinder jaws that fits LHC spatial constraints on a
CERN Phase I base and use CERN Phase I scheme for jaw alignment and cooling input
– Provide 12kW cooling to each 136mm x 95cm jaw through flexible tubing– Relax 25um flatness tolerance but provide flexible jaw support and a central
stop mechanism to ensure thermal bowing is AWAY from beam• 400 um sagitta for 1 hr beam lifetime engineering steady state• 1200 um sagitta for 12min beam lifetime 10 second transient
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 16 / 27
FY06 Goals of Phase II Rotating Collimator Project and Beyond
Work Plan outlined 10/6/20061. Single jaw thermal test: one jaw with internal helical cooling
channels to be thermally loaded for testing the cooling effectiveness and measuring thermal deformations.
2. Full RC1 prototype: a working prototype for bench top testing of the jaw positioning mechanism, supported to simulate operation in all necessary orientations, but not intended for mounting on actual beamline supports with actual beamline, cooling, control and instrumentation connections.
Deliverables listed 10/6/20051. Final version of RC1 CDR: Awaiting support/stopper design
2. External review of RC1 CDR: √
3. Construction & Performance report on RC1: Xmid FY07• Progress delayed ~6 months due to reviews & manpower issues
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 17 / 27
Jaw/Cooling Tube Joint Development
Purpose: determine appropriate joint configuration & fabrication methods
In process.. target completion date •Square hollow magnet conductor for first test ~ 9 mm x 9 mm
•Copper jaw and mandrel
•Cu-Au braze
•After first braze, machine coil o.d. for correct fit to jaw i.d.
•After second braze, section assy to inspect coverage
•Round tubing with grooved (?) mandrel is next
May 9th
Cooling Tube
Jaw Center Mandrel
~100 mm
~70 mmdia
~100 mm dia
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 18 / 27
Single Jaw Thermal Test setup
Reference bar, water cooled to maintain straightness (radiation shield ?)
Standoffs fix jaw distance to reference bar at center
Capacitive proximity sensors at ends
Flexible end mounts
2 x 5 kW heaters, coupled with thermal grease
Orientation: may be rotated 90o, or 180o or on end
Thermocouples measure temperature distribution
Water cooling
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 19 / 27
Single Jaw Test Thermocouple Locations
•Thermocouples recessed into Jaw slightly below the surface
•Spaced along Heater length and around Jaw circumference
•Should yield the Jaw heating profile predicted by the FE analysis
12 x Thermocouples
2 x 5kW Heaters
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 20 / 27
IR7 secondary collimators heat generation, deflection and effective length
Deflection and effective length based on ANSYS simulations for TCSM.A6L7. Power scaled from TCSM.A6L7 according to the distribution on secondary collimators provided by CERN. Note: first collimator in the series absorbs the
bulk of the energy.
No. name Power (kW)
Defl (um)
Eff. Lngth (cm)
Power (kW)
Defl (um)
Eff. Lngth (cm)
note
1 TCSM.A6L7 11.7 394 43 58.5 1216 24 simulated 2 TCSM.B5L7 2.7 137 75 13.5 422 46 scaled 3 TCSM.A5L7 .69 35 75 3.44 108 75 scaled 4 TCSM.D4L7 .18 9 75 .92 29 75 scaled 5 TCSM.B4L7 .20 10 75 1.01 31 75 scaled 6 TCSM.A4L7 .19 10 75 .96 30 75 scaled 7 TCSM.A4R7 .16 8 75 .81 25 75 scaled 8 TCSM.B5R7 .22 11 75 1.10 34 75 scaled 9 TCSM.D5R7 .19 9 75 .93 29 75 scaled 10 TCSM.E5R7 .13 6 75 .62 19 75 scaled 11 TCSM.6R7 .25 12 75 1.23 26 75 scaled
Steady State Transient
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 21 / 27
Unresolved Jaw Support Issues
Support needs to:
•hold ~100kg jaw to 5-10um accuracy
•not sag under gravity for vertical and skew orientations
•permit ~1200 um flex for 10 second bursts of 60kW energy deposition
•work with torque of Phase I stepping motors
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 22 / 27
Jaw Positioning Forces – Phase I => Phase II
Pull-in force
0
500
1000
1500
2000
2500
3000
3500
4000
0 20 40
x (mm)
F (
N) Fin
Fres
Jaw end springs will be sized as com-promise 1) bending-generated force applied to nut 2) static deflection due to jaw weight
Pull-in force
0
500
1000
1500
2000
2500
3000
3500
4000
0 20 40
x (mm)
F (
N) Fin
Fres
Pull-in headroom expressed as force at nut
Upper jaw - shown Lower jaw
Jaw deflection = 400 um for 1 hr beam lifetime case, 1200 um for 10 sec transient @12 minute lifetime power level
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 23 / 27
Unresolved Central Stop Issues
Interplay between alignment scheme
•independent motion of each end of each jaw
and stop
•must be on beam centerline
•this can vary ±5mm/ store
Reproducibility of alignment on successive stores
May use two stops to control tilt
Slot deep enough to avoid damage in accident
Stop far enough from beam to never be damaged & is out of way at injection
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 24 / 27
Unresolved Issues with Jaw Rotation
Torque required to rotate 360 understood and is substantial;Coil “creep” may alleviate.
Details of actuator not yet worked out
Interference with RF parts and gross jaw adjustment during injection not studied
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 25 / 27
NLC Jaw Indexing Mechanism
Reciprocating linear motion advances jaw by one or more ratchet pitches. LHC system will require opposing ratchet to hold jaw position against cooling tube deformation torque. Mechanism probably will be designed to actuate only when jaw fully retracted.
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 26 / 27
2.5 cm
Missteered beam (9E11 protons)on secondary Jaw
CopperJaw
Cross section at shower max.
Copper
Fracture temp. of copper is about 200 deg C
What is the damage area in a missteering accident?
FNAL Coll
with .5 MJ
~1MJ
LARP Collaboration Meeting. - 28 Apr. 2006 Collimator Task Summary - T. Markiewicz Slide n° 27 / 27
Phase II Task Summary
Project has slipped 6 months in 6 months due– Reality of hard deliverables as opposed to softer “design” milestones– Difficulty/cost of acquiring manpower– Understandable design requests by review committee
• Nothing we didn’t know about
Budget “slipped” 6 months as wellAfter taking this hit we believe we are on-track to deliver on new schedule
– Most nervous now about accident condition: begin to discuss beam tests
– Believe various steady state requirements are attack-able on an “as good as can be engineered” basis
Expect thermal tests and complete design by end of FY06 and mid-FY07, respectively
Need to get full Phase I mechanism from CERN vendor if we are to make RC2 deliver schedule. If SLAC can concentrate on jaws and have rest of infrastructure provided RC2 can meet LHC schedule.