Los Angeles County Metropolitan Transportation Authority Crenshaw/LAX Transit Corridor Open House July 19, 2011 Open House, Presentation on Screen 6:00 6:45 PM Narration with Presentation on Screen 6:45 – 7:00 PM Open House, Presentation on Screen 7:00 – 8:00 PM
Transcript

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 1/23

Los Angeles CountyMetropolitan Transportation Authority

Crenshaw/LAX Transit Corridor

Open House

July 19, 2011

Open House, Presentation on Screen 6:00 – 6:45 PM

Narration with Presentation on Screen 6:45 – 7:00 PMOpen House, Presentation on Screen 7:00 – 8:00 PM

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 2/23

Environmental Process

2

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 3/23

Project Milestones

Release Final EIS/EIR August 2011

Board Adopts Project and Certifies EIR September 22nd

File Notice of Determination End of September 2011

FTA Record of Decision &

Begin Project Implementation End of October 2011

Prepare for Design/ 

Build Procurements Now through mid 2012

3

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 4/23

Alternatives Screening Process

4

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 5/23

Base Project Definition

• Adopted Locally PreferredAlternative (LPA) – 8.5 mile Light Rail Transit Exposition

Blvd. to Metro Green Line

 – 6 Stations:› Exposition/Crenshaw› Crenshaw/Martin Luther King Jr.› Crenshaw/Slauson› Florence/West

› Florence/La Brea› Aviation/Century

• Recommended Changes to

LPA: – La Brea Avenue Grade Separation – Exposition Blvd. to 39th St. (below-

grade) – Partially Covered LAX Trench

 – Maintenance Facility near LAX

*

* Maintenance Facilit5

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 6/23

Exposition Connection

• At-grade connection to Exposition – challenging – Right-of-way (ROW) conflict with District

Square Development

 – Significant at-grade ROW impacts – Unmitigable Traffic Impacts – Difficult Safety Issues

Below-grade configuration withBelow-grade Crenshaw/ExpositionStation is being examined in the Final

EIS/EIR and Preliminary Engineering• Cost remains an issue

6

DistrictSquare

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 7/23

Florence/La Brea Station

• Earthquake Fault in the vicinity of station zone precludes: – Stations immediately west or east of La Brea

 – Aerial Stations

Station is recommended just east of Market Street alongFlorence Avenue

7

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 8/23

Partially Covered LAX Trench

8

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 9/23

Options

• Environmentally cleared,

NOT part of base projectdefinition

 –Crenshaw/Vernon station* –Centinela Grade Separation

 –Aviation/Manchester station

* To be included in construction biddocument as an option to be exercised if

base project and option can beconstructed within $1.715 billion

* Maintenance Facilit

*

9

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 10/23

Operating Plan

10

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 11/23

Vertical Profile of the Project Alignment

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 12/23

STATIONS

12

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 13/23

Crenshaw/Exposition Station

13

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 14/23

Crenshaw/King Station

14

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 15/23

Crenshaw/Slauson Station

15

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 16/23

Florence/West Station

16

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 17/23

Florence/La Brea Station

17

A i i /C S i

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 18/23

Aviation/Century Station

18

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 19/23

OPTIONAL STATIONS

19

C h /V O ti l St ti

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 20/23

Crenshaw/Vernon Optional Station

20

A i ti /M h t O ti l St ti

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 21/23

Aviation/Manchester Optional Station

21

Maintenance Facility: Arbor Vitae/Bellanca

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 22/23

Maintenance Facility: Arbor Vitae/Bellanca(City of Los Angeles)

22

Next Steps

8/6/2019 LAX Transit Project Update Open House - July 19, 2011

http://slidepdf.com/reader/full/lax-transit-project-update-open-house-july-19-2011 23/23

Next Steps

• Complete Final Environmental Impact Statement/ FinalEnvironmental Impact Report

• Board consideration – September 2011• Continue Preliminary Engineering/value engineering

• Board consideration Life-of-Project budget - Fall 2011

• Start Construction - 2012

23