LCLS Photon Systems ETC and Methodology

Date post: 01-Jan-2016
Category:
Upload: jacob-carey
View: 21 times
Download: 2 times
Share this document with a friend
Description:
LCLS Photon Systems ETC and Methodology. John Arthur LCLS Photon Systems Manager. LCLS Photon Systems Schedule Overview Milestones ETC Risks. Photon Systems Areas. Front End Enclosure – Underground facility for X-ray diagnostics and mirrors. - PowerPoint PPT Presentation
16
John Arthur Photon Systems [email protected] .edu October 9, 2007 1 LCLS Photon Systems ETC and Methodology • LCLS Photon Systems • Schedule Overview • Milestones • ETC • Risks John Arthur LCLS Photon Systems Manager
Transcript
Page 1: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 1

LCLS Photon Systems ETC and Methodology

• LCLS Photon Systems• Schedule Overview• Milestones• ETC• Risks

John Arthur

LCLS Photon Systems Manager

Page 2: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 2

Far Experimental Hall – Cavern for 3 experimental hutches

Front End Enclosure – Underground facility for X-ray diagnostics and mirrors

Near Experimental Hall – Sub-basement facility for 3 experimental hutches

X-Ray Transport Tunnel – 200m tunnel to transport X-rays to FEH

Photon Systems Areas

Page 3: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 3

Photon Systems

WBS 1.05, 2.05 X-ray Transport, Optics, Diagnostics (XTOD)

Group located at LLNL, Donn McMahon, CAM

Transport the x-ray beam, in vacuum, to experimental stations

Condition the x-ray beam, with attenuators and apertures

Analyze the x-ray beam, with sophisticated diagnostics

Page 4: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 4

Photon Systems

WBS 1.06, 2.06X-ray Endstation Systems (XES)

Stefan Moeller, CAM

Provide basic infrastructure required for experimenters

Build instrument for Atomic Physics experiments

Advanced x-ray detector R&D

Page 5: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 5

Photon Systems

WBS 1.02.03, 1.06.04Injector laser and XES laser systems

Bill White, CAM

Coordinate laser design and acquisition throughout LCLS

Injector laser work nearly complete

Page 6: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 6

Photon Systems

WBS 1.05.02, 1.06.02X-ray Area Controls and Data Acquisition

Gunther Haller, CAM

Controls and DAQ hardware, cables, and software for the X-ray experimental area

Page 7: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 7

Photon Systems

WBS 2.01.01.05, 2.01.01.06X-ray Commissioning ManagementJohn Arthur, CAM

LOE manpower for 2 LCLS Physicists managing X-ray commissioning

WBS 2.06.03X-ray CommissioningHal Tompkins, CAM

LOE manpower for SLAC and LLNL personnel during X-ray commissioning process

Page 8: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 8

Design process, included in Project P3 scheduleInterface Control Documents specify which group has responsibility for each systemPhysics Requirements Documents are written by the LCLS Physics group specifying subsystem needsEngineering group holds Design Reviews, and writes Engineering Specification Documents to detail how each PRD is to be satisfied

Physicists and Engineers approve component assembly and testing prior to installation

System Design Management

Page 9: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 9

Delay work from FY08 to FY09

Page 10: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 10

LCLS Installation and Commissioning Time-Line

SS OO NN DD JJ FF MM AA MM JJ JJ AA SS OO NN DD JJ FF MM AA MM JJ JJ

Linac/BC2 Install

Linac/BC2 Commissioning

LTU/Und/Dump

Install

20072007 20082008

CF Early Occupancy

LTU/Und Commissioning

Flux milestone

AA SS OO NN DD

20092009 20102010PPS

X-ray tunnel/FEH Install

CD-4(7/30/10)

PPS

FEE/NEH Commissionin

g

Tunnel/FEH Commissioning

JJ FF MM AA MM

FEE/NEH Install

FEH X-rays

milestone

Page 11: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 11

Major Startup Activities

Commission FEE 6/09 - 8/09

FEE flux measurement 7/09

Commission NEH 8/09 - 9/09

Commission tunnel/FEH 11/09 - 2/10

X-rays in FEH 2/10

Page 12: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 12

Installation costsBased on experience in 2006 Injector installation

Hardware install estimate done top-down and bottom-up

Cable plant install estimated using R.S. MeansFabrication/procurement

Costs based on quotes and experience with similar types of prototypes at SLAC and LLNL

Engineering and CommissioningTimetable for completion well understood

Photon Systems Cost Estimation

Page 13: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 13

Photon Systems ETC

WBSActuals Thru

June 07Estimate to Complete

Budget at Complete

1.02 Injector System 3,867,088 100,926 3,968,0141.05 X-RAY Transport & Diagnostics 15,157,356 12,612,914 27,770,2701.06 X-RAY End Stations 2,247,103 14,911,831 17,158,935

TEC Total 21,271,548 27,625,671 48,897,2192.01 LCLS Project Mgmt, Planning and Admin 582,459 996,084 1,578,5432.02 Injector System 203,567 489,149 692,7152.05 X-RAY Transport & Diagnostics 943,788 2,573,529 3,517,3172.06 X-RAY End Stations 889,422 9,262,978 10,152,400

OPC Total 2,619,236 13,321,740 15,940,976TPC Total 23,890,784 40,947,411 64,838,194

43% doneCommissioning

still to come

Page 14: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 14

Risks

Late changes to design requirements

Atomic Physics design not finalized

Radiation Physics requirements not final

<$200k, <4mo impact

Mitigate through formal design process

AMO design will be finalized in 3 months

Page 15: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 15

Risks 2

Offset mirror system Mirrors are specialized long-lead procurements

Precision mirror controls still in development

<$300k, <6mo impact

Mitigate through generous schedule

Page 16: LCLS Photon Systems ETC and Methodology

John Arthur

Photon Systems [email protected]

October 9, 2007 16

Summary

XTOD is in procurement phase, XES still in design

XTOD and XES have suffered delays due to CR

New plan allows recovery with extended project,

phased completion

Risks to major project milestones are low


Recommended