Date post: | 22-Jan-2018 |
Category: |
Documents |
Upload: | louis-poggenburg |
View: | 101 times |
Download: | 2 times |
Acme Machell
Lean Assessment
March 2011
2Lean – Six Sigma Project
Project DefinitionPROBLEM DESCRIPTION:
Acme Machell is past due on product affecting Nuevo Laredo, Shangai & Matamoros KA plants, Actually KA is expediting material having a Cost of Poor Quality of $____.
OBJECTIVE:
Reduce the Past due parts from 69.694 to 0, by April 2011 & give the Plant an assessment so they may create an Action Plan to improve & sustain their processes.
SCOPE: Acme Machell & its suppliers for KA products
Define/Measure/Analyze/Improve/Control
CORE TEAM:Alberto Martinez – K.A. Logistics Manager – LeaderTom Cox – A.M. PresidentLouis Poggenburg – A.M. Lean 6σ Engineer, QA Manager Glenn Litchford – A.M. VP- OperationsAlex Quezada – K.A. MBB/Lean 6σManager NA – Support
EXTENDED TEAM:Jim Reder – K.A. Purchasing Director NA – ChampionNicklas Berntsson – K.A. Purchase Director
3Lean – Six Sigma Project
Pareto of Part Numbers and Days to recover
Days to recover 2.226 0.1178.052 6.566 6.086 5.663 5.255 4.276 3.707 2.484Percent 5.0 0.318.1 14.8 13.7 12.7 11.8 9.6 8.3 5.6Cum % 99.7 100.018.1 32.9 46.6 59.3 71.2 80.8 89.1 94.7
Part NumberOth
er
'996T
-S10
30'
'092P
-S77
12'
'054J-
S173
2'
'073T
-S78
25'
'062T
-S77
54'
'076P
-S78
12'
'066P
-S28
07'
'006T
-S10
25'
'084P
-S78
11'
50
40
30
20
10
0
100
80
60
40
20
0
Day
s to
rec
over
Perc
ent
Pareto Char t of Par t Number
Define/Measure/Analyze/Improve/Control
4Lean – Six Sigma Project
Current VSM O84P-S7811Customer Demand:
27000 pieces per Month(Takt Time 67.2 seconds)
KONGSBERG
MIXING
Total C/T = 2 secondsDefect = 0%
1
INSPECTION
Total C/T = 12.2 secondsValue Add: 0 secondsNVA = 12.2 secondsDefect = 12%Distance Traveled: 12 ft.
1
Production Planning
Preferred Compund
Information
Information
Information
1008000 seconds
2 seconds
24864 seconds
11 seconds
16.6 seconds 65453 seconds 12.2 seconds Lead Time = 1098348 seconds
VA / T = 13 seconds
RM = 13.3 days
WIP = 24883 seconds
FG = 65465 seconds
15000 pcs
Information
MOLDING
Total C/T = 16.6 secondsValue Add: 11 secondsNVA = 5.6 secondsDefect = 4%C/O = 180 mins.Uptime = 75%Availability: 70%
1370 pcs
974 pcs
Define/Measure/Analyze/Improve/Control
Current State (data from 03-09-11)
Work Balancing
2 s. 24.7 s. 13.9 s.
MIXING
MOLDING
INSPECTION
Takt Time 67.2 s.
5Lean – Six Sigma Project
VSM O84P-S7811Define/Measure/Analyze/Improve/Control
Customer Demand:27000 pieces per Month
(Takt Time 67.2 seconds)
KONGSBERG
MIXING
Total C/T = 2 secondsDefect = 0%
1
INSPECTION
Total C/T = 12.2 secondsValue Add: 0 secondsNVA = 12.2 secondsDefect = 12%Distance Traveled: 12 ft.
1
Production Planning
Preferred Compund
Information
Information
Information
1008000 seconds
2 seconds
24864 seconds
11 seconds
16.6 seconds 65453 seconds 12.2 seconds Lead Time = 1098348 seconds
VA / T = 13 seconds
RM = 13.3 days
WIP = 24883 seconds
FG = 65465 seconds
15000 pcs
Information
MOLDING
Total C/T = 16.6 secondsValue Add: 11 secondsNVA = 5.6 secondsDefect = 4%C/O = 180 mins.Uptime = 75%Availability: 70%
1370 pcs
974 pcs
AnalyticalBatch Size
TPM
Set-up Reduction
CombineOperations
FIFO
5S
ReplenishmentPull System
VisualManagement
Visualizing the Future State
6Lean – Six Sigma Project
Customer Demand:27000 pieces per Month(Takt Time 72 seconds)
KONGSBERG
MIXING
Total C/T = 2 secondsDefect = 0%
1
Production Planning
Supplier
Information
Information
Information
8.89 days
2 seconds 11 seconds
15.2 seconds 7.11 days
11 seconds
Lead Time = 16 days
VA / T = 24 seconds
RM = 8.89 days
WIP = 576028 seconds
FG = 0 seconds
10000 pcs
Information
Supplier
8000 pcs
MOLDING & INSPECTING
Total C/T = 15.2 secondsValue Add: 11 secondsNVA = 4.2 secondsDefect = 4%C/O = 90 mins.Uptime = 75%
1
ASSEMBLY
Total C/T = 11 secondsDefect = 0%Uptime = 90%Distance Traveled: 12 ft.
1
Information
Information
Proposed State O84P-S7811
Define/Measure/Analyze/Improve/Control
Work Balancing
2 s. 15.8 s. 11 s.
MIXING
MOLDING & IN...
ASSEMBLY
Takt Time 58.9 s.
FIFO
7Lean – Six Sigma Project
Actions & Benefits in Process Improvements
Kaizens To Do:
• Kan ban racks and cards at Assembly to create a signal to produce according to
demand and Re-order material.
• SMED (Change Over reduction) to reduce from 180 mins to 25 mins by having a
heating plate to pre-heat the tool after installation.
• TPM have the operators know basic adjustments and maintenance of the
machine.
• Reduce scrap by using only new material.
• Reduce Scrap by having a Proper machine maintenance, oil is leaking and may
hurt operator.
• Work instruction properly showed at machine
• Combine Inspection with the same press operator, reduce one person
8Lean – Six Sigma Project
VSM 092P-S7712Define/Measure/Analyze/Improve/Control
Current State (data from 03-09-11)Customer Demand:
33000 pieces per Month(Takt Time 55 seconds)
KONGSBERG
MIXING
Total C/T = 2 secondsDefect = 0%
1
INSPECTION
Total C/T = 12.2 secondsValue Add: 0 secondsNVA = 12.2 secondsDefect = 12%Distance Traveled: 12 ft.
1
Production Planning
Preferred Compund
Information
Information
Information
824727 seconds
2 seconds
20343 seconds
11 seconds
15.2 seconds 53552 seconds 12.2 seconds Lead Time = 898652 seconds
VA / T = 13 seconds
RM = 10.9 days
WIP = 20360 seconds
FG = 53565 seconds
15000 pcs
Information
MOLDING
Total C/T = 15.2 secondsValue Add: 11 secondsNVA = 4.2 secondsDefect = 4%C/O = 180 mins.Uptime = 75%Availability: 70%
1370 pcs
974 pcs
Work Balancing
2 s. 22.6 s. 13.9 s.
MIX
ING
MO
LDIN
G
INSPEC
TIO
N
Takt Time 55 s.
9Lean – Six Sigma Project
Customer Demand:33000 pieces per Month(Takt Time 55 seconds)
KONGSBERG
MIXING
Total C/T = 2 secondsDefect = 0%
1
INSPECTION
Total C/T = 12.2 secondsValue Add: 0 secondsNVA = 12.2 secondsDefect = 12%Distance Traveled: 12 ft.
1
Production Planning
Preferred Compund
Information
Information
Information
824727 seconds
2 seconds
20343 seconds
11 seconds
15.2 seconds 53552 seconds 12.2 seconds Lead Time = 898652 seconds
VA / T = 13 seconds
RM = 10.9 days
WIP = 20360 seconds
FG = 53565 seconds
15000 pcs
Information
MOLDING
Total C/T = 15.2 secondsValue Add: 11 secondsNVA = 4.2 secondsDefect = 4%C/O = 180 mins.Uptime = 75%Availability: 70%
1370 pcs
974 pcs
AnalyticalBatch Size
TPM
Set-up Reduction
FIFO5S
ReplenishmentPull System
VisualManagement
VSM 092P-S7712Visualizing the Future State
Define/Measure/Analyze/Improve/Control
Work Balancing
2 s. 22.6 s. 13.9 s.
MIX
ING
MO
LDIN
G
INSPEC
TIO
N
Takt Time 55 s.
CombineOperations
10Lean – Six Sigma Project
Customer Demand:33000 pieces per Month(Takt Time 55 seconds)
KONGSBERG
MIXING
Total C/T = 2 secondsDefect = 0%
1
Production Planning
Preferred Compund
Information
Information
Information
274909 seconds
2 seconds 5 seconds
15.2 seconds Lead Time = 274926 seconds
VA / T = 7 seconds
RM = 3.64 days
WIP = 17.2 seconds
FG = 0 seconds
5000 pcsMOLDING & INSPECTING
Total C/T = 15.2 secondsValue Add: 5 secondsNVA = 0 secondsDefect = 1%C/O = 60 mins.Uptime = 90%Availability: 90%
1
Proposed State 092P-S7712
Define/Measure/Analyze/Improve/Control
FIFO
Work Balancing
2 s. 17.1 s.
MIXING
MOLDING & IN
...
Takt Time 55 s.
11Lean – Six Sigma Project
Actions & Benefits in Process Improvements
Kaizens To Do:
• SMED (Change Over reduction) to reduce from 240 mins to 45 mins by having a
heating plate to pre-heat the tool after installation.
• TPM have the operators know basic adjustments and maintenance of the
machine
• Reduce scrap by using only new material and add FIFO.
• Reduce Scrap by having a Proper machine maintenance.
• Work instruction properly showed at machine
• Set up parameters optimized
• Combine Inspection with the same press operator, reduce one person
12Lean – Six Sigma Project
0
1
2
3
4
5
Level ScheduleContinuous Flow
Takt Time
Pull System
Abnormality Detection
Line Stop Call (Andon)
Problem Solving
Man/Machine Separation
Cell/Line LayoutPlant Design
Skill BuildingStandard Operations
5S
Visual Management
TPM
Inventory Management
Management Style
Change Readiness
Customer focusContinuous Improvement
9-Mar-11
Goal
Lean Assessment
Score 1.55
13Lean – Six Sigma Project
Lean Assessment CommentsProduction processes are isolated “islands” with considerable amounts of WIP between operations (i.e., departmentalized). Products move through the production line in batches resulting in long throughput times.
Production pace is not planned but assumed to be a fixed function of the current equipment. Line operates and adds/cuts hours or inventory to match customer demand.
Production flow is completely MRP based with no in-line control on operations or production Pace. Material enters & is pushed downstream on forecast only.
Some fail-safes and process monitors are present, but team members are still expected to prevent errors. Only a small group of people notice problems and understand the status of the shop floor.
Team members can notify supervisor/team leader of problems, but cannot consciously stop production. There is not an efficient process in place for team members to signal a problem.
Majority of problems are only noticed by team members and result in quick superficial “fixes” by maintenance technicians. Problems constantly reoccur and result in low process efficiency (productivity or OEE).
Basic work procedures exist, but are not strictly followed and are not easily accessible by team members.
14Lean – Six Sigma Project
Lean Assessment Comments
No workplace organization on the shop floor. All areas are generally disorganized and dirty. It is not clear what is needed and what is not needed.
Virtually no examples of visual management beyond basic forms, e.g., aisles marked.
PM plans in place for some select pieces of equipment, but majority of maintenance activity is for unplanned downtime. Only maintenance technicians work on machines. Little information available on downtime/OEE.
Only isolated areas practice FIFO. Designated areas for inventory may exist, but it is not clear because there are no labels and there is little discipline in place.
Problems are communicated to management, but response is slow and the status always unclear.
There are no improvement activities involving team members and there is no formal improvement organization.
15Lean – Six Sigma Project
0
1
2
3
4
5
SORT
SET
SHINESTANDARDIZE
SUSTAIN
9-Mar-11
Goal
5’s Assessment
Score 1.55
Generally cluttered. Quite a few unnecessary items either on benches, desks, shelves or cabinets. Some unneeded furniture and equipment. Items stored on floor.
Inadequate organization. Many key items have no designated location. Shelves and drawers are poorly labeled. Aisles or equipment markings are not clear or straight. Very few visual controls or instructions are evident. Safety equipment is not designated.
Area needs to be picked up. Items have not been cleaned in some time. Significant oil leakage. Floor is dirty and/or waste containers are full.
There is no evidence that a 5S. Checklist exists for the area. PM log is not up to date. Metrics and charts in the area are not current.
There is no system or commitment within the organization to sustaining 5S.
16Lean – Six Sigma Project
Areas
17Lean – Six Sigma Project
Next Steps:
Acme will develop an Action Plan to get out of backlog and improvements moving forward to maintain Quality & Delivery to KA – Tom Cox - TBD