“Delivering Outstanding Services” 1 Lean Six Sigma Green Belt Project Building Safety Inspections – Zoning Cases Planning and Inspections Department Analyze Improve Control Define Measure Goal 3: Promote the Visual Image of El Paso 3.1 Provide business-friendly permitting and inspection processes 3.2 Improve the visual impression of the community Goal 6: Set the Standard for Sound Governance and Fiscal Management
Transcript

“Delivering Outstanding Services” 1

Lean Six SigmaGreen Belt Project

Building Safety Inspections – Zoning CasesPlanning and Inspections Department

Analyze Improve ControlDefine Measure

Goal 3: Promote the Visual Image of El Paso3.1 Provide business-friendly permitting and inspection processes

3.2 Improve the visual impression of the community

Goal 6: Set the Standard for Sound Governance and Fiscal Management

“Delivering Outstanding Services”

Project Team- Sonya Cahalan, Code Field Operations Supervisor

- Eduardo Ruvalcaba, Code Compliance Officer

- Rosendo Huerta, Code Compliance Officer

- Cesar Ortiz, Code Compliance Officer

- Nancy Spencer, Secretary

- Nellie Avalos, Building Safety Inspector

- Ron Roth, Chief Building Inspector

- Victor Morrison-Vega, Deputy Director

- Larry Nichols, Director (Project Sponsor)

- David A. Coronado, Project Manager

LSS ProjectBuilding Safety Inspections – Zoning Cases

Land Use Violation (ZN-LU)

2

“Delivering Outstanding Services” 3

LSS ProjectBuilding Safety Inspections – Zoning Cases- Goals

- Shorten number of days to conduct initial inspection (response times)

- Reduce amount of time to process and successfully complete building safety inspection cases

- Improve prompt compliance rates under 30 days

- Benefits

- Improve service to the public

- More time to conduct additional inspections and process more cases (improved capacity)

- Reduction in costs

Correction Notice

- Can be replicated to other 2 areas of the Building Safety Section- Support Strategic Goal #3 - Promote the Visual Image of El Paso

“Delivering Outstanding Services”

4.3

21.1

0

5

10

15

20

25

Before After

# of inspections conducted per day

5

LSS ProjectResults at a glance

How did we do?

‐ Reduced response times from an average of 4.97 days to 1.73 days

(65% reduction)

- Reduced case processing times from an average of 16.6 days to 14.3days (13.9% improvement)

- Increased compliance rates from 29.7% to 41.7%

- Improved case workload capacity 4.2 times!!

3.3

13.7

0

2

4

6

8

10

12

14

16

Before After

# of new cases created per day

“Delivering Outstanding Services” 6

LSS ProjectCost Savings

Estimated annual savings of

$394,214!!!

$148 reduction in

cost per case in staff time,

76% improvement

$194.70

$46.73

0

50

100

150

200

250

Before After

Cost Per Case

Improved workload capacity 4.2 times means…

Now we have the capacity to process 2,664 cases per year

up from 639 cases